Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1.0 Introduction
6.0 Levels
8.0 Materials
15.0 ANNEXURES:
1.0 Introduction
Indian Oil LNG Private Ltd. (IOLPL) is planned to set up LNG import, storage and regasification terminal
including LNG road tanker loading facility along with all the associated facilities and off-sites at Ennore
IOLPL has awarded the contract to M/s L&T Construction for carrying out the design and construction of
Marine facilities and nominated M/s Amec Foster Wheeler Iberia S.L.U as a consultant for this project.
The Marine facilities include a jetty within the port along with associated facilities like Mooring Dolphins,
This document describes the analysis and design of Mooring Dolphins (MD) for the LNG Terminal.
Mooring Dolphins
The jetty consists of a unloading platform flanked by four number berthing and six number mooring dolphins.
MD-1 MD-2
MD-3
MD-4
MD-5 MD-6
The unloading platform and dolphins are inter connected by walkways. The unloading platform is connected
to the shore by an approach trestle. Mooring dolphins consist of a concrete slab supported by steel piles.
Six mooring dolphins,each of size 12 x 12 m, three at each side of the unloading platform are provided for
the installation of the triple quick release hooks (QRH) of 3x150 tonnes for both the bow and stern ends.
Additionally, these structures shall support other equipment (a safety ladder, handrails, rope guards,
lighting, etc.) and utilities (electricity and lighting services) required for terminal operation.
A hand railing shall be provided along the periphery of the dolphin deck at positions not conflicting with
the mooring lines. The dolphin edge shall be provided with a rope guard to prevent chafing of the mooring
line. Access from water to end dolphins is possible by means of vertical steel ladders.
Each mooring dophin is supported by 9 number of steel piles (1H:3V rake). These piles are designed by
X56 grade steel with 1066mm dia. and different thickness depending on the zone (air, splash, submerged
and buried). The length of piles ranges from (-)29.00 m CD to (-)34.00 m CD, depending on the axial force
transmitted to ground.
1) Design Basis Report for Marine Civil works, Document No: 19200-0103-8310-SP-0003
The design and construction of equipment and structures shall be carried out considering totally with the
Indian Standards
● IS 875-1987: Code of Practice for Design Loads for Buildings and Structures.
● IS 1786-2008: Specification for high strength deformed steel bars and wires for concrete reinforcement.
● IS 1893 (Part 1)-2002: Criteria for Earthquake Resistant Design of Structures - General Provisions
and Buildings.
● IS 1893 (Part 4)-2005: Criteria for Earthquake Resistant Design of Structures - Industrial Structures
● IS: 2911 (Part 1)-2010: COP for Design and Construction of Pile Foundations - Concrete Piles.
● IS: 2911 (Part 4)-2013: COP for Design and Construction of Pile Foundations - Load Test on Piles.
● IS 4651 (Part 1)-1974: COP for Planning and Design of Ports and Harbours - Site Investigation.
● IS 4651 (Part 2)-1989: COP for Planning and Design of Ports and Harbours - Earth Pressures.
● IS 4651 (Part 3)-1974: COP for Planning and Design of Ports and Harbours - Loading.
Considerations.
● IS 4651 (Part 5)-1980: COP for Planning and Design of Ports and Harbours - Layout and Functional
Requirements.
British Standards
● BS 6349 (Part-2) - Maritime Structures - Design of Quay Walls, Jetties, and Dolphins.
● BS 6349 (Part-4) - Maritime Structures - Code of Practice for Design of Fendering & Mooring systems.
6.0 Levels
A detailed soil investigation is planned at the proposed site of LNG Terminal. This document covers the
Mooring Dolphins i.e, MD2, MD3, MD4 & MD5, which are located near to shore line. The bore holes at
this location are MBH-2 and MBH-6. Presently the investigations are not started at this location. The
completed bore hole MBH-14 were used which is nearly 200m away from the present dolphins location.
The following design soil profile has been considered for arriving the pile capacities based on the field
investigation data. This profile will be rechecked and updated as per the exact bore log data.
Levels Layer
SPT
Layer No. Thickness Soil Strata
"N"
From To (m)
8.0 Materials
Concrete
Reinforcement Steel
Cover to Reinforcement
The clear cover to main reinforcement shall be 50mm in all concrete elements.
Apart from the modelled members, the self weight of non-modelled items are considered as follows:
(-) (+)
45o
75o
25o
The vertical, Horizontal angles and subsequent forces considered for the design of Mooring Dolphins
Mooring Loads
The basic wind speeds considered for the structural design are as follows:
Furthermore, the following wind coefficients are used (IS 875 - Part 3):
Operating Condition:
Extreme Condition:
Walkway - WL (+)X
Walkway - WL (-)X
Walkway - WL (+)Z
Walkway - WL (-)Z
The proposed jetty shall be well protected by the existing breakwaters within the port basin. However the
W
Factor
0.5 1.0 3.57
W
Factor
0.5 1 1.60
The seismic forces are calculated as per the Cl: 6.4.2 of IS: 1893 (Part 1)-2002 and as per the Cl: 8.3.2
The seismic force shall be calculated for 50 % of the design live load.
The highest temperature is recorded in May and June with a mean maximum temperature of about 36.5ºC.
The lowest temperature is recorded in January with a mean minimum temperature of about 20.7ºC.
The design air temperature conditions are: Max 37ºC and Min 20ºC.
annual variation in temperature. The average maximum annual variation in temperature for this purpose
shall be taken as the difference between the mean of daily minimum ambient temperature during the
coldest month of the year and mean of daily maximum ambient temperature during the hottest month
of the year. The structure shall be designed to withstand the stresses due to 50% of the total
temperature variation.
Temperature rise and fall including shrinkage is considered as two primary load cases.
(Shrinkage loads along with Temperature Rise is ignored since both are in opposite directions.)
The primary load cases and load combinations considered in the analysis are tabulated below.
PRIMARY LOADS
5 Dead Load DL
10 Mooring Load with 25ᵒ Vertical & +45ᵒ Horizontal Angle ML4(25V/+45H)
11 Mooring Load with 25ᵒ Vertical & +75ᵒ Horizontal Angle ML5(25V/+75H)
12 Mooring Load with 25ᵒ Vertical & 90ᵒ Horizontal Angle ML6(25V/90H)
15 Mooring Load with 25ᵒ Vertical & -45ᵒ Horizontal Angle ML9(25V/-45H)
16 Mooring Load with 25ᵒ Vertical & -75ᵒ Horizontal Angle ML10(25V/-75H)
31 Temperature Rise TR
LOAD COMBINATIONS
1001 - 1001 DL + LL
1401 - 1404 DL + LL + EQ
1501 - 1501 DL + LL
3001 - 3120 1.5DL + 1.5LL + 1.5MOORING LOAD + 1.0WIND OPR + 1.2WAVE OPR
The Six Mooring Dolphins are categorised into two types based on the bed level infront of the dolphins
i.e. MD1 & MD6 as one category and MD2, MD3, MD4 & MD5 as second category. This document
deals with the analysis and design of Mooring Dolphins MD2, MD3, MD4 & MD5.
The typical Mooring Dolphin is idealised as a 3D space frame. In 3D model, piles are modelled as beam
elements and deck slab as plate elements. The piles are interconnected at top by deck slab.
The analysis is done by using the Fixity Depth Method with Structural Analysis and Design Software
"STAAD.Pro V8i (Select Series 4)". Structural Analysis has been carried out by considering different
In Fixity depth method piles were modeled upto a fixed depth where the bending moments are maximum.
The fixity depth considered for the present case is seven times the diameter of the pile from the bed level.
The approximate bed level at the Mooring Dolphins front and back are (-)6.00m CD and (-)3.00m CD.
The virtual ground surface (VGS) is considered as (-)4.50m CD based on the bed levels.
Berthing Dolphin
Mooring Dolphin
The structural geometry, materials, loads and load combinations defined in STAAD Pro are presented
in the Annexure-B.
All steel piles are designed by working stress design method as per API RP 2A - WSD. Deck slab is
designed by Ultimate Limit State Design method (ULS) and checked for Serviceability Limit State (SLS)
as per IS: 456. The design of different structural components will be based on the design forces obtained
from the analysis. All components are designed to sustain safely the effect of various load combinations
with safety/load factors for ULS/SLS conditions that can possibly co-exist.