Sei sulla pagina 1di 26

LNG IMPORT, STORAGE AND

REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 1 of 26
CONTENTS:

1.0 Introduction

2.0 Key Plan

3.0 Description of Mooring Dolphins

4.0 Reference Drawings/Documents

5.0 Codes and Standards

6.0 Levels

7.0 Design Soil Parameters

8.0 Materials

9.0 Design Loads

9.1 Dead Load

9.2 Live Load

9.3 Mooring Load

9.4 Wind Load

9.5 Wave Load

9.6 Seismic Load

9.7 Temperature Load

10.0 Load Combinations

11.0 Structural Idealization and Analysis

11.1 Structural Model

11.2 Staad Input

12.0 Analysis Results

13.0 Method of Design

14.0 Design Summary

15.0 ANNEXURES:

Annexure - A Load Combinations

Annexure - B Staad Input

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 2 of 26
Annexure - C Analysis Results

Annexure - D Pile Design

Annexure - E Deck Slab Design

Annexure - F Geotechnical Capacity of Piles and Founding Levels

16.0 List of Figures:

Figure 1: Mooring Dolphins Location in Plan

Figure 2: Mooring Dolphins Plan View

Figure 3: Mooring Dolphins Elevation and Side View

Figure 4: Walkway Load Application Points

Figure 5: Mooring Load Horizontal and Vertical Angles

Figure 6: Wind Loads on the Mooring Dolphin

Figure 7: Wave Force on Piles

Figure 8: Mooring Dolphin 3D Model

Figure 9: Mooring Dolphin Side View

Figure 10: Mooring Dolphin Top View

Figure 11: Mooring Dolphin Piles ID and Slab ID

Figure 12: Mooring Dolphin Fixity Depth

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 3 of 26

1.0 Introduction

Indian Oil LNG Private Ltd. (IOLPL) is planned to set up LNG import, storage and regasification terminal

including LNG road tanker loading facility along with all the associated facilities and off-sites at Ennore

Kamarajar Port in Tamil Nadu, India.

The broad scope of the project facilities can be summarised as follows:

● LNG Storage Tanks and Associated Facilities

● Regasification Facilities including Offsites and Utility Blocks

● Marine Facilities including Jetty

IOLPL has awarded the contract to M/s L&T Construction for carrying out the design and construction of

Marine facilities and nominated M/s Amec Foster Wheeler Iberia S.L.U as a consultant for this project.

The Marine facilities include a jetty within the port along with associated facilities like Mooring Dolphins,

Berthing Dolphins, Unloading Platform, Approach Trestle etc.

This document describes the analysis and design of Mooring Dolphins (MD) for the LNG Terminal.

2.0 Key Plan

The below figure shows the location of Mooring Dolphins.

Mooring Dolphins

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 4 of 26

Figure 1: Mooring Dolphins Location in Plan

3.0 Description of Mooring Dolphins

The jetty consists of a unloading platform flanked by four number berthing and six number mooring dolphins.

MD-1 MD-2

MD-3
MD-4

MD-5 MD-6

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 5 of 26

Figure 2: Mooring Dolphins Plan View

Figure 3: Mooring Dolphins Elevation and Side View

The unloading platform and dolphins are inter connected by walkways. The unloading platform is connected

to the shore by an approach trestle. Mooring dolphins consist of a concrete slab supported by steel piles.

Six mooring dolphins,each of size 12 x 12 m, three at each side of the unloading platform are provided for

the installation of the triple quick release hooks (QRH) of 3x150 tonnes for both the bow and stern ends.

Additionally, these structures shall support other equipment (a safety ladder, handrails, rope guards,

lighting, etc.) and utilities (electricity and lighting services) required for terminal operation.

A hand railing shall be provided along the periphery of the dolphin deck at positions not conflicting with

the mooring lines. The dolphin edge shall be provided with a rope guard to prevent chafing of the mooring

line. Access from water to end dolphins is possible by means of vertical steel ladders.

Each mooring dophin is supported by 9 number of steel piles (1H:3V rake). These piles are designed by

X56 grade steel with 1066mm dia. and different thickness depending on the zone (air, splash, submerged

and buried). The length of piles ranges from (-)29.00 m CD to (-)34.00 m CD, depending on the axial force

transmitted to ground.

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 6 of 26
The superstructure consists of M40 concrete slab where the quick release hooks are anchored. Elevation

for this slab is (+)7.50 m CD.

4.0 Reference Drawings/Documents

This document is prepared based on the following references:

1) Design Basis Report for Marine Civil works, Document No: 19200-0103-8310-SP-0003

2) Mooring Dolphin - General Arrangement Plan, Drawing No: 19200-0103-8310-46-0010

3) Mooring Dolphin - General Arrangement Sectin Detail, Drawing No: 19200-0103-8310-46-0011

5.0 Codes and Standards

The design and construction of equipment and structures shall be carried out considering totally with the

latest revision of the following Codes and Standards referenced herein.

Indian Standards

● IS 456-2000: Code of Practice for Plain and Reinforced Concrete.

● IS 800-1984: Code of Practice for General Construction of Steel.

● IS 875-1987: Code of Practice for Design Loads for Buildings and Structures.

● IS 1786-2008: Specification for high strength deformed steel bars and wires for concrete reinforcement.

● IS 1893 (Part 1)-2002: Criteria for Earthquake Resistant Design of Structures - General Provisions

and Buildings.

● IS 1893 (Part 4)-2005: Criteria for Earthquake Resistant Design of Structures - Industrial Structures

including Stack-Like Structures.

● IS: 2911 (Part 1)-2010: COP for Design and Construction of Pile Foundations - Concrete Piles.

● IS: 2911 (Part 4)-2013: COP for Design and Construction of Pile Foundations - Load Test on Piles.

● IS 4651 (Part 1)-1974: COP for Planning and Design of Ports and Harbours - Site Investigation.

● IS 4651 (Part 2)-1989: COP for Planning and Design of Ports and Harbours - Earth Pressures.

● IS 4651 (Part 3)-1974: COP for Planning and Design of Ports and Harbours - Loading.

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 7 of 26
● IS 4651 (Part 4)-2014: COP for Planning and Design of Ports and Harbours - General Design

Considerations.

● IS 4651 (Part 5)-1980: COP for Planning and Design of Ports and Harbours - Layout and Functional

Requirements.

● SP 16-1980: Design aids for Reinforced Concrete to IS: 456

● SP 34-1987: Handbook on Concrete Reinforcement and Detailing

British Standards

● BS 6349 (Part-1) - Maritime Structures - Code of Practice for General Criteria.

● BS 6349 (Part-2) - Maritime Structures - Design of Quay Walls, Jetties, and Dolphins.

● BS 6349 (Part-4) - Maritime Structures - Code of Practice for Design of Fendering & Mooring systems.

Other International Codes and References

● API-RP-2A-(WSD) 2000-12 (Twenty – First Edition) American petroleum Institute-Recommended

practice for planning, design and constructing fixed off-shore structure.

● Shore Protection Manual Vol I, II and III.

● Coastal Engineering Manual.

● OCIMF Mooring Equipment Guidelines (3rd ed. 2008).

6.0 Levels

● Highest High Water (HHW) - (+) 1.50 m CD

● Mean High Water Springs (MHWS) - (+) 1.10 m CD

● Mean High Water Neaps (MHWN) - (+) 0.80 m CD

● Mean Sea Level (MSL) - (+) 0.65 m CD

● Mean Low Water Neap (MLWN) - (+) 0.40 m CD

● Mean Low Water Spring (MLWS) - (+) 0.10 m CD

● Lowest Low Water (LLW) - (-) 0.10 m CD

● Deck Top Level - (+) 7.50 m CD

● Pile Cut-off Level - (+) 5.50 m CD

● Sea Bed Level @ Mooring Dolphin - (-) 4.50 m CD

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 8 of 26
7.0 Design Soil Profile

A detailed soil investigation is planned at the proposed site of LNG Terminal. This document covers the

Mooring Dolphins i.e, MD2, MD3, MD4 & MD5, which are located near to shore line. The bore holes at

this location are MBH-2 and MBH-6. Presently the investigations are not started at this location. The

completed bore hole MBH-14 were used which is nearly 200m away from the present dolphins location.

The following design soil profile has been considered for arriving the pile capacities based on the field

investigation data. This profile will be rechecked and updated as per the exact bore log data.

Design soil profile (MBH-14)

Levels Layer
SPT
Layer No. Thickness Soil Strata
"N"
From To (m)

1 3.00 -1.00 4.0 Loose Sand 6


Medium
2 -1.00 -7.00 6.0 19
Dense Sand
3 -7.00 -9.00 2.0 Dense Sand 31
Medium
4 -9.00 -11.00 2.0 19
Dense Sand
5 -11.00 -13.00 2.0 Loose Sand 10
Medium
6 -13.00 -20.00 7.0 17
Dense Sand
7 -20.00 -24.00 4.0 Dense Sand 33
Medium
8 -24.00 -26.00 2.0 Dense 23
Sand`
9 -26.00 -29.00 3.0 Dense Sand 45
Very Dense
10 -29.00 -47.00 18.0 56
Sand

8.0 Materials

Concrete

Grade of Concrete = M40

Reinforcement Steel

Grade of Steel = Fe 500

Structural Steel for Piles

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 9 of 26
Minimum yield stress = 386 N/mm2

API X56 grade, conforming to API spec. 2B

Cover to Reinforcement

The clear cover to main reinforcement shall be 50mm in all concrete elements.

9.0 Design Loads

9.1 Dead Load

Unit weight of Reinforced Concrete = 25 kN/m3

Unit weight of Steel = 78.5 kN/m3

Apart from the modelled members, the self weight of non-modelled items are considered as follows:

Hand Rail Load = 0.2 kN/m

Quick Release Mooring Hook (QRH) Load = 40 kN

Marine Growth Load = ∏/4*(1.266^2-1.066^2)*13 = 4.76 kN/m

Walkway Maximum Load = (17.78+17.5)/2 = 17.64 say 18 kN = 18 kN

Walkway Dead Load

Horizontal Vertical Horizontal Moment


Node L/C
Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm

1 5 DL 0.06 17.78 -0.63 0 0 0

12 5 DL -0.06 17.50 0.63 0 0 0

69 5 DL 0.00 17.75 -0.63 0 0 0

70 5 DL 0.00 17.50 0.63 0 0 0

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 10 of 26

Figure 4: Walkway Load Application Points

9.2 Live Load

Live load on deck = 5 kN/m2

Live load due to walkway = (48.05+45.02)/2 = 46.54 say 47 kN = 47 kN

Walkway Live Load

Horizontal Vertical Horizontal Moment


Node L/C
Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm

1 6 LL 0.79 48.05 -1.61 0 0 0

12 6 LL -0.79 45.02 1.66 0 0 0

69 6 LL 0.00 47.79 -1.68 0 0 0

70 6 LL 0.00 45.03 1.63 0 0 0

9.3 Mooring Load

Mooring Load = 3x1500 = 4500 kN

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 11 of 26

(-) (+)
45o
75o

25o

Figure 5: Mooring Load Horizontal and Vertical Angles

The vertical, Horizontal angles and subsequent forces considered for the design of Mooring Dolphins

are detailed in the below table.

Mooring Loads

Vertical Angle = 0o Vertical Angle = 25o


Force

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 12 of 26
Force
45o H 75o H 90o H 45o H 75o H 90o H

Fy 0.00 0.00 0.00 1901.78 1901.78 1901.78

Fx 3181.98 1164.69 0.00 2883.85 1055.56 0.00

Fz 3181.98 4346.67 4500.00 2883.85 3939.42 4078.39

Mx 4772.97 6520.00 6750.00 4325.78 5909.13 6117.58

Mz 4772.97 1747.03 0.00 4325.78 1583.35 0.00

9.4 Wind Load

The basic wind speeds considered for the structural design are as follows:

Operating Condition (Tanker Moored Condition) = 16.5 m/s

Extreme Condition (Without Tanker Moored) = 50 m/s

Furthermore, the following wind coefficients are used (IS 875 - Part 3):

Risk Coefficient, k1 = 1.0

Terrain, Height and Structure Size Factor, k2 = 1.1

Topography Factor, k3 = 1.0

Operating Condition:

Design wind speed, Vzo = Vb*k1*k2*k3 = 16.5*1.0*1.1*1.0 = 18.15 m/s

Design wind pressure, Pzo = 0.6*(Vzo)^2 = 0.6*18.15*18.15/1000 = 0.20 kN/m2

Extreme Condition:

Design wind speed, Vze = Vb*k1*k2*k3 = 50*1.0*1.1*1.0 = 55 m/s

Design wind pressure, Pze = 0.6*(Vze)^2 = 0.6*55*55/1000 = 1.82 kN/m2

Force Coefficient on Piles, Cf = 0.9

Force Coefficient on Slab, Cf = 2.0

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 13 of 26
Wind Loads (WL)

Operating (OPR) Extreme (EXT)


Load
Member Fx Fz Fx Fz
Direction
(kN) (kN) (kN) (kN)

(+) X 0.19 0.00 1.75 0.00

(-) X 0.19 0.00 1.75 0.00


Piles
(+) Z 0.00 0.19 0.00 1.75

(-) Z 0.00 0.19 0.00 1.75

(+) X 0.80 0.00 7.28 0.00

(-) X 0.80 0.00 7.28 0.00


Slab
(+) Z 0.00 0.80 0.00 7.28

(-) Z 0.00 0.80 0.00 7.28

Wind Load due to Walkways

Walkway - WL (+)X

Horizontal Vertical Horizontal Moment


Node L/C
Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm

1 7 WL +X -13.43 -0.69 -0.58 0 0 0

12 7 WL +X -13.42 -0.69 0.58 0 0 0

69 7 WL +X 0.00 0.69 -0.03 0 0 0

70 7 WL +X 0.00 0.69 0.03 0 0 0

Walkway - WL (-)X

Horizontal Vertical Horizontal Moment


Node L/C
Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 14 of 26
1 8 WL -X 13.43 0.69 0.58 0 0 0

12 8 WL -X 13.42 0.69 -0.58 0 0 0

69 8 WL -X 0.00 -0.69 0.03 0 0 0

70 8 WL -X 0.00 -0.69 -0.03 0 0 0

Walkway - WL (+)Z

Horizontal Vertical Horizontal Moment


Node L/C
Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm

1 9 WL +Z -121.42 -28.37 -17.31 0 0 0

12 9 WL +Z 121.42 28.37 -17.72 0 0 0

69 9 WL +Z 0.00 -21.72 -10.47 0 0 0

70 9 WL +Z 0.00 21.72 -10.61 0 0 0

Walkway - WL (-)Z

Horizontal Vertical Horizontal Moment


Node L/C
Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm

1 10 WL -Z 121.42 28.37 17.30 0 0 0

12 10 WL -Z -121.42 -28.37 17.72 0 0 0

69 10 WL -Z 0.00 21.72 10.47 0 0 0

70 10 WL -Z 0.00 -21.72 10.61 0 0 0

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 15 of 26

Figure 6: Wind Loads on the Mooring Dolphin

9.5 Wave load

The proposed jetty shall be well protected by the existing breakwaters within the port basin. However the

significant wave heights considered for design are as follows:

Operating Condition = 0.76 m

Extreme Condition = 1.70 m

Wave forces are calculated as per Shore Protection Manual.

Wave Operating Condition:

Wave Height H = 0.76 m

Wave period T = 8 sec

Bed Level = -4.5 m CD

Still Water Level SWL = 1.5 m CD

Density of seawater γ = 10.25 KN/m3

Diameter of Pile including marine growth D = 1.266 m

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 16 of 26
Deep Water Wave Length L0 = gT2/2π = 99.92 m

Depth of Still Water d = 6m

Dimensioless Water Depth d/gT2 = 0.01

From Fig 7-68, Ratio LA/Lo = 0.58

Airy approximation of Wave Length LA = 57.96 m

Maximum Horizontal Water Velocity umax = (πH/T)*(Lo/LA) = 0.51 m/s

Viscocity v = 9.29E-07 m2/s

Reynold's Number (Equ. 7-45) Re = Umax D/v = 701234.825

From Fig 7-85, Drag Coefficient CD = 0.7

Since 2.5 x 10^5 < Re > 5 x 10^5 Then CM = 1.5

As per equation, 7.41 W = (CM*D/CD*H) = 3.57

Dimensionless Wave Steepness H/gT2 = 0.0012

Dimensionless d/gT2 = 0.0096

Refer to Fig.7.76 to 7.83

W
Factor
0.5 1.0 3.57

Φm 0.18 0.26 0.67

αm 0.11 0.16 0.42

Max. Force on Pile Fm = Φm*CD*w*H2*D = 3.52 KN

Max. Moment on Pile Mm = αm*CD*w*H2*D*d = 13.22 KNm

CG of this force from bed level = 3.76 m

Wave Extreme Condition:

Wave Height H = 1.7 m

Wave period T = 12 sec

Bed Level = -4.5 m CD

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 17 of 26
Still Water Level SWL = 1.5 m CD

Density of seawater γ = 10.25 KN/m3

Diameter of Pile including marine growth D = 1.266 m

Deep Water Wave Length L0 = gT2/2π = 224.83 m

Depth of Still Water d = 6m

Dimensioless Water Depth d/gT2 = 0.004

From Fig 7-68, Ratio LA/Lo = 0.4

Airy approximation of Wave Length LA = 89.93 m

Maximum Horizontal Water Velocity umax = (πH/T)*(Lo/LA) 1.11 m/s

Viscocity v = 9.29E-07 m2/s

Reynold's Number (Equ. 7-45) Re = Umax D/v = 1516266.53

From Fig 7-85, Drag Coefficient CD = 0.7

Since 2.5 x 10^5 < Re > 5 x 10^5 Then CM = 1.5

As per equation, 7.41 W = (CM*D/CD*H) = 1.60

Dimensionless Wave Steepness H/gT2 = 0.0012

Dimensionless d/gT2 = 0.0042

Refer to Fig.7.76 to 7.83

W
Factor
0.5 1 1.60

Φm 0.29 0.37 0.47

αm 0.18 0.22 0.27

Max. Force on Pile Fm = Φm*CD*w*H2*D = 12.34 KN

Max. Moment on Pile Mm = αm*CD*w*H2*D*d = 42.53 KNm

CG of this force from bed level = 3.45 m

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 18 of 26

Figure 7: Wave Force on Piles

9.6 Seismic Load

The seismic forces are calculated as per the Cl: 6.4.2 of IS: 1893 (Part 1)-2002 and as per the Cl: 8.3.2

of IS: 1893 (Part 4) - 2005.

The design horizontal seismic coefficient, Ah = Z/2*I/R*Sa/g

Z = Zone Factor (Table 2 of IS: 1893-2002, Part-1), Zone-III = 0.16

I = Importance Factor (Table 2 of IS: 1893-2005, Part-4) = 1.75

R = Response Reduction Factor (Table 3 of IS: 1893-2005, Part-4) = 3.0

Sa/g = Ave. Response Acceleration Coefficient (Fig. 2 of IS: 1893-2002, Part-1)

The seismic force shall be calculated for 50 % of the design live load.

9.7 Temperature Load

The highest temperature is recorded in May and June with a mean maximum temperature of about 36.5ºC.

The lowest temperature is recorded in January with a mean minimum temperature of about 20.7ºC.

The design air temperature conditions are: Max 37ºC and Min 20ºC.

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 19 of 26
For Temperature loading, the total temperature variation shall be considered as the average maximum

annual variation in temperature. The average maximum annual variation in temperature for this purpose

shall be taken as the difference between the mean of daily minimum ambient temperature during the

coldest month of the year and mean of daily maximum ambient temperature during the hottest month

of the year. The structure shall be designed to withstand the stresses due to 50% of the total

temperature variation.

Design total temperature = 0.5*(37-20) = ± 8.5 o C

Temperature rise and fall including shrinkage is considered as two primary load cases.

As per Cl. 6.2.4.1, Shrinkage strain considered for design = 0.0003

Equivalent temp. due to shrinkage = 0.0003/11.7*10 -6 = 25.65 o C

Temperature Rise, TR = 8.5 o C

(Shrinkage loads along with Temperature Rise is ignored since both are in opposite directions.)

Temperature Fall along with Shrinkage, TF = 34.15 o C

10.0 Load Combinations

The primary load cases and load combinations considered in the analysis are tabulated below.

PRIMARY LOADS

Load No. Description of Load Abbrevation

1 Earthquake Load in (+)X Direction EQ (+)X

2 Earthquake Load in (-)X Direction EQ (-)X

3 Earthquake Load in (+)Z Direction EQ (+)Z

4 Earthquake Load in (-)Z Direction EQ (-)Z

5 Dead Load DL

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 20 of 26
6 Live Load LL

7 Mooring Load with 0ᵒ Vertical & +45ᵒ Horizontal Angle ML1(0V/+45H)

8 Mooring Load with 0ᵒ Vertical & +75ᵒ Horizontal Angle ML2(0V/+75H)

9 Mooring Load with 0ᵒ Vertical & 90ᵒ Horizontal Angle ML3(0V/90H)

10 Mooring Load with 25ᵒ Vertical & +45ᵒ Horizontal Angle ML4(25V/+45H)

11 Mooring Load with 25ᵒ Vertical & +75ᵒ Horizontal Angle ML5(25V/+75H)

12 Mooring Load with 25ᵒ Vertical & 90ᵒ Horizontal Angle ML6(25V/90H)

13 Mooring Load with 0ᵒ Vertical & -45ᵒ Horizontal Angle ML7(0V/-45H)

14 Mooring Load with 0ᵒ Vertical & -75ᵒ Horizontal Angle ML8(0V/-75H)

15 Mooring Load with 25ᵒ Vertical & -45ᵒ Horizontal Angle ML9(25V/-45H)

16 Mooring Load with 25ᵒ Vertical & -75ᵒ Horizontal Angle ML10(25V/-75H)

17 Wind Load Operation in (+)X Direction WL OPR(+)X

18 Wind Load Operation in (-)X Direction WL OPR(-)X

19 Wind Load Operation in (+)Z Direction WL OPR(+)Z

20 Wind Load Operation in (-)Z Direction WL OPR(-)Z

21 Wind Load Extreme in (+)X Direction WL EXT(+)X

22 Wind Load Extreme in (-)X Direction WL EXT(-)X

23 Wind Load Extreme in (+)Z Direction WL EXT(+)Z

24 Wind Load Extreme in (-)Z Direction WL EXT(-)Z

25 Wave Force Operation in (+)X Direciton WAVE OPR(+)X

26 Wave Force Operation in (-)X Direciton WAVE OPR(-)X

27 Wave Force Operation in (-)Z Direciton WAVE OPR(-)Z

28 Wave Force Extreme in (+)X Direciton WAVE EXT(+)X

29 Wave Force Extreme in (-)X Direciton WAVE EXT(-)X

30 Wave Force Extreme in (-)Z Direciton WAVE EXT(-)Z

31 Temperature Rise TR

32 Temperature Fall including Shrinkage TF

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 21 of 26

LOAD COMBINATIONS

Limit State of Serviceability (Steel) - Normal Condition

1001 - 1001 DL + LL

1002 - 1003 DL + LL + TEMP

1004 - 1007 DL + LL + WIND OPR

1008 - 1019 DL + LL + WIND OPR + WAVE OPR

1020 - 1049 DL + MOORING LOAD + WAVE OPR

1050 - 1079 DL + LL + MOORING LOAD + WAVE OPR

1080 - 1199 DL + MOORING LOAD + WIND OPR + WAVE OPR

1200 - 1319 DL + LL + MOORING LOAD + WIND OPR + WAVE OPR

Limit State of Serviceability (Steel) - Extreme Condition

1401 - 1404 DL + LL + EQ

1405 - 1416 DL + WAVE OPR + EQ

1417 - 1428 DL + LL + WAVE OPR + EQ

1429 - 1440 DL + LL + WAVE EXT + EQ

1441 - 1452 DL + LL + WIND EXT + WAVE EXT

Limit State of Serviceability (Steel) - Deflection

1501 - 1501 DL + LL

1502 - 1503 DL + LL + TEMP

1504 - 1507 DL + LL + WIND OPR

1508 - 1519 DL + LL + WIND OPR + WAVE OPR

1520 - 1549 DL + 0.55MOORING LOAD + WAVE OPR

1550 - 1579 DL + LL + 0.55MOORING LOAD + WAVE OPR

1580 - 1699 DL + 0.55MOORING LOAD + WIND OPR + WAVE OPR

1700 - 1819 DL + LL + 0.55MOORING LOAD + WIND OPR + WAVE OPR

Limit State of Serviceability (Concrete) - Crack Width

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 22 of 26
2001 - 2240 DL + LL + MOORING LOAD + WIND OPR + WAVE OPR + TEMP

Limit State of Serviceability (Concrete) - Deflection

2301 - 2324 DL + LL + WAVE OPR + TEMP + EQ

Limit State of Serviceability (Concrete) - Long Term

2401 - 2402 DL + 0.50LL + TEMP

Limit State of Collapse (Concrete) - Normal Condition

3001 - 3120 1.5DL + 1.5LL + 1.5MOORING LOAD + 1.0WIND OPR + 1.2WAVE OPR

Limit State of Collapse (Concrete) - Extreme Condition

3201 - 3212 1.2DL + 1.2LL + 1.2WIND EXT + 1.0WAVE EXT

3213 - 3224 1.2DL + 1.2LL + 1.0WAVE EXT + 1.2EQ

The detailed load combinations are given in the Annexure-A.

11.0 Structural Idealization and Analysis

11.1 Structural Model

The Six Mooring Dolphins are categorised into two types based on the bed level infront of the dolphins

i.e. MD1 & MD6 as one category and MD2, MD3, MD4 & MD5 as second category. This document

deals with the analysis and design of Mooring Dolphins MD2, MD3, MD4 & MD5.

The typical Mooring Dolphin is idealised as a 3D space frame. In 3D model, piles are modelled as beam

elements and deck slab as plate elements. The piles are interconnected at top by deck slab.

The analysis is done by using the Fixity Depth Method with Structural Analysis and Design Software

"STAAD.Pro V8i (Select Series 4)". Structural Analysis has been carried out by considering different

load combinations over the structure as detailed in Annexure-A.

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 23 of 26

Figure 8: Mooring Dolphin 3D Model

Figure 9: Mooring Dolphin Side View

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 24 of 26

Figure 10: Mooring Dolphin Top View

Figure 11: Mooring Dolphin Piles ID and Slab ID

In Fixity depth method piles were modeled upto a fixed depth where the bending moments are maximum.

The fixity depth considered for the present case is seven times the diameter of the pile from the bed level.

The approximate bed level at the Mooring Dolphins front and back are (-)6.00m CD and (-)3.00m CD.

The virtual ground surface (VGS) is considered as (-)4.50m CD based on the bed levels.

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 25 of 26

Berthing Dolphin

Mooring Dolphin

Figure 12: Mooring Dolphin Fixity Depth

11.2 Staad Input

The structural geometry, materials, loads and load combinations defined in STAAD Pro are presented

in the Annexure-B.

12.0 Analysis Results

Results obtained from the analysis are presented in the Annexure-C.

13.0 Method of Design

All steel piles are designed by working stress design method as per API RP 2A - WSD. Deck slab is

designed by Ultimate Limit State Design method (ULS) and checked for Serviceability Limit State (SLS)

as per IS: 456. The design of different structural components will be based on the design forces obtained

from the analysis. All components are designed to sustain safely the effect of various load combinations

with safety/load factors for ULS/SLS conditions that can possibly co-exist.

14.0 Design Summary

The structural design of pile is presented in the Annexure-D.

The deck slab design is presented in the Annexure-E.

# Sensitivity: LNT Construction Internal Use


LNG IMPORT, STORAGE AND
REGASIFICATION TERMINAL PROJECT

O15006-MR-BH-CN-DC-065 DESIGN CALCULATION FOR MOORING DOLPHINS 19200-0103-8310-CA-0012, Rev-O1


Rev-A (MD2, MD3, MD4 & MD5) DSN: xxxx Page: 26 of 26
Geotechnical capacity of piles and founding levels are presented in Annexure-F.

# Sensitivity: LNT Construction Internal Use

Potrebbero piacerti anche