INFORME DEL INSPECTOR N° 02

CORRESPONDIENTE AL MES: NOVIEMBRE DEL 2,015


I.- DATOS GENERALES

RESOLUCION DE APROBACION Nº 308 - 2015 - GM - MDE/LC 8/10/2015 Fecha de presentacion 12/5/2015


NOMBRE DEL PROYECTO
"INSTALACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL EN LA COMUNIDAD DE MEDIO IVOCHOTE - ZONAL IVOCHOTE, DISTRITO DE
ECHARATI - LA CONVENCION - CUSCO."

COORDINADOR DE SUPERVISION INGENIERO CIVIL: JULIO CARBAJAL COILA

INSPECTOR ING CIVIL: LUCIO BACA BÉJAR DE 9/9/2015 A A la fecha

RESIDENTE DE OBRA ING CIVIL: ALAIN MORA ESCALANTE DE 9/1/2015 A A la fecha

COMENTARIO

LA OBRA SE INICIO CON UN PIM ASIGNADO, LO QUE PERJUDICA EL BUEN AVANCE FISICO PARA EL PRESENTE AÑO, EL PLAZO DE EJECUCION ESTA PROYECTADO HASTA FIN DE AÑO, POR LO
QUE ESTO INDICA HACER UNA REPROGRAMACION DE PARTIDAS A EJECUTAR. PARA ESTE MES SE HA EFECTUADO UN INCREMENTO DE PRESUPUESTO PARA PAGO DE PLANILLAS AL
PERSONAL OBRERO CON LO QUE SE VIENE CUMPLIENDO SUS PAGOS OPORTUNOS,A SU VEZ SE TIENE UNA PARALIZACION TEMPORAL POR CIERRE DE AÑO FISCAL, ASI COMO TAMBIEN
POR LOS FENOMENOS NATURALES (PRECIPITACIONES PLUVIALES, DERRUMBES, DESLIZAMIENTOS, SATURACION DEL TERRENO LO QUE IMPIDE EFECTURA LOS TRABAJOS DE ACARREO
DE MATERIALES Y OTROS)

II.- GENERALIDADES

PLIEGO 2 Municipalidad Distrital de Echarati


UNIDAD EJECUTORA Concejo Distrital deEcharati - UNIDAD OPERATIVA IVOCHOTE
SECUENCIA FUNCIONAL 109 S.B.I. Medio Ivochote
FUNCION 18 Saneamiento
PROGRAMA 40 Saneamiento
SUB / PROGRAMA 89 Saneamiento Rural
Act. / Al- Obra 4000182 S.B.I. Medio Ivochote
COMPONENTE 2186143 S.B.I. Medio Ivochote
META 00001
FINALIDAD 127515 Construcción de un Sistema de Abastecimiento de Agua Potable
FUENTE DE FINANCIAMIENTO 18 CANON Y SOBRECANON

UBICACIÓN
Departamento Cusco
Provincia La Convencion
Distrito Echarati
Comunidad Medio Ivochote

III.- DESCRIPCION DEL PROYECTO.


3.1.- BREVE DESCRIPCION DEL PROYECTO

I. SISTEMA DE ABASTECIMIENTO DE AGUA


CAPTACIONES
• 02 Captaciones superficiales de riachuelo de C°A° de 2.0 m de ancho • 02 Sedimentadores • 02 Filtros Lentos • 04 Captaciones de ladera de C°A° de 2 salidas • 01 Captación de ladera Tipo I (L.C. 1 1/2") de
C°A° de 1 salida • 02 Captaciones de ladera Tipo I (L.C. 1") de C°A° de 1 salida • 06 Captaciones de ladera Tipo I (L.C. 3/4") de C°A° de 1 salida
LINEA DE CONDUCCION
• 13780.42 ml de Tubería PVC SAP Clase 10 ɸ 1 1/2”, 1” y ¾” en Línea de Conducción. • 02 Cámaras Distribuidora de Caudales (03 Salidas), de C°A° • 08 Cámaras Distribuidora de Caudales (02 Salidas), de
C°A° • 03 Válvulas de Control de 1” • 10 Válvulas de Control de 3/4” • 30 Cámaras Rompe Presiones Tipo 06, de C°A° • 01 Cámara de Reunión de Caudales, de CºAº • 01 Pase Aéreo Tubería F°G° 1” con
columnas y cables L=30.00 ml • 01 Pase Aéreo Tubería F°G° 3/4” con columnas y cables L=25.00 ml.
RESERVORIOS
• 06 Reservorios de C°A° de 1.00 m3 • 20 Reservorios de C°A° de 0.75 m3 • 04 Reservorios de C°A° de 0.50 m3
RED DE DISTRIBUCION
• 9450.23 ml de Tubería PVC SAP Clase 10 ¾”, ½ʺ en Red de Distribución • 05 Cámaras Rompe Presiones Tipo 07, de C°A° • 06 Válvulas de Control de 3/4” • 30 Válvulas de Purga • 01 Pase Aéreo Tubería
F°G° 3/4” con columnas y cables L=20.00 ml • 01 Pase Aéreo Tubería F°G° 1/2” con columnas y cables L=8.00 ml
CONEXIONES DOMICILIARIAS
• 62 Conexiones Domiciliarias agua • 62 Lavaderos de uso múltiples
II. TRANSPORTE
• Transporte de materiales con vehículo
• Acarreo interno de materiales en obra
III. SISTEMA DE ELIMINACION DE EXCRETAS Y TRATAMIENTO AGUAS SERVIDAS
• 63 Módulos de SS.HH. Domiciliarios, con su respectivo sistema de tratamiento (sistema de arrastre hidráulico a pozo percolador y pozo séptico).
IV. MITIGACIÓN DE IMPACTOS AMBIENTALES
PLAN DE MANEJO AMBIENTAL
• Programa de Manejo de residuos sólidos • Programa de Manejo de residuos líquidos • Programa de Educación e Información Ambiental • Programa de Reforestación • Programa de Control de Calidad
Ambiental
PLAN DE CIERRE O ABANDONO
• Programa de Rehabilitación • Programa de Depósito de Material Excedente
V. EDUCACIÓN SANITARIA Y GESTIÓN DE SERVICIOS
• Acciones de Promoción. • Acciones de Capacitación. • Educación Sanitaria

3.2.- PRESUPUESTO

DESCRIPCION MONTO APROBADO

Costo Directo : S/ ###


Gastos generales (12.96 %) : S/400,690.98
Gastos de Supervision (4.00 %) : S/145,424.14
Gastos de Liquidacion (0.94 %) : S/ 20,596.13
Gastos de Expediente Tecnico. (2.99 %) : S/ 61,905.61
Gastos de Suoervision de Estudios. (0.44%) : S/ 11,133.85
TOTAL PRESUPUESTO :S ###

EXPEDIENTE SOCIAL
EXPEDIENTE SOCIAL : S/ 66,146.06

PRESUPUESTO TOTAL DE PROYECTO :S ###

3.3.- CRONOLOGIA DE EJECUCION

FECHA DE ENTREGA DE TERRENO 12 DE OCTUBRE DEL 2015


FECHA DE INICIO DE OBRA 12 DE OCTUBRE DEL 2015
FECHA DE CONCLUSIÓN DE OBRA PROGRAMADO 26 DE JUNIO DEL 2016
FECHA DE PRIMERA PARALIZACION TEMPORAL DE OBRA
(NOTA: Por cierre de año fiscal y efectos climaticos, desastres 01 DE DICIEMBRE DEL 2015
naturales)
FECHA DE SEGUNDA PARALIZACION NINGUNO
FECHA DE PRIMER REINICIO DE OBRA NINGUNO
FECHA DE SEGUNDO REINICIO DE OBRA NINGUNO
3.4.- PLAZO DE EJECUCION

COMPONENTE INFRAESTRUCTURA 270 DIAS CALENDARIOS


COMPONENTE SOCIAL 390 DIAS CALENDARIOS
Ampliacion de Plazo de Infrestructura NO TIENE Res.Nº Fecha
Ampliacion NO TIENE Res.Nº Fecha
Plazo TOTAL APROBADO (dias utiles) NO TIENE

Plazo de Ejecucion Real (dias Utiles). NO TIENE

IV.- CONTROL DE LAS VALORIZACIONES

4.1.- RESUMEN DE VALORIZACIONES MENSUALES

COSTO DIRECTO TOTAL 2,530,798.01

VALORIZACIÓN PROGRAMADA* VALORIZACIÓN EJECUTADA


MES DEL MES ACUMULADO DEL MES ACUMULADO ESTADO DE LA OBRA
S/. % S/. % S/. % S/. %

AÑOS
ABRIL. 2015 0.00% 0.00 0.00% 0.00% 0.00 0.00%
MAYO. 2015 0.00% 0.00 0.00% 0.00% 0.00 0.00%
JUNIO. 2015 0.00% 0.00 0.00% 0.00% 0.00 0.00%
SETIEMBRE. 2015 0.00% 0.00 0.00% 0.00% 0.00 0.00%
OCTUBRE. 2015 291,485.80 11.52% 291,485.80 11.52% 16,721.86 0.66% 16,721.86 0.66%
NOVIEMBRE. 2015 321406.13 12.70% 612,891.92 24.22% 70,643.97 2.79% 87,365.83 3.45%
DICIEMBRE. 2015 240262.78 9.49% 853,154.70 33.71%
ENERO. 2016 238585.04 9.43% 1,091,739.74 43.14%
FEBRERO. 2016 298426.23 11.79% 1,390,165.97 54.93%
MARZO. 2016 365956.66 14.46% 1,756,122.63 69.39%
ABRIL. 2016 265755.30 10.50% 2,021,877.92 79.89%
MAYO. 2016 228926.76 9.05% 2,250,804.68 88.94%
JUNIO. 2016 279993.33 11.06% 2,530,798.01 100.00%
TOTAL 2,530,798.01 100.00% 2,530,798.01 100.00% 87,365.83 3.45% 87,365.83 3.45% 2,443,432.16 96.55%
###
COMENTARIO ###

En el presente cuadro se muestra el avance fisico de obra del mes, 2.79 % con respecto al costo directo, siendo en el presente mes la cantidad de S/. 70,643.97
En el presente cuadro se muestra el avance fisico de obra del mes acumulado, 3.45 % con respecto al costo directo, siendo en el presente mes la cantidad de S/. 87,365.83

PRESUPUESTO TOTAL 3,236,694.78

VALORIZACIÓN PROGRAMADA* VALORIZACIÓN EJECUTADA


MES DEL MES ACUMULADO DEL MES ACUMULADO ESTADO DE LA OBRA
S/. % S/. % S/. % S/. %

AÑOS
ABRIL. 2015 0.00% 0.00 0.00% 0.00% 0.00 0.00%
MAYO. 2015 0.00% 0.00 0.00% 0.00% 0.00 0.00%
JUNIO. 2015 0.00% 0.00 0.00% 0.00% 0.00 0.00%
SETIEMBRE. 2015 0.00% 0.00 0.00% 0.00% 0.00 0.00%
OCTUBRE. 2015 81,713.68 2.52% 81,713.68 2.52% 20,948.92 0.65% 20,948.92 0.65%
NOVIEMBRE. 2015 363,059.07 11.22% 444,772.75 13.74% 88,501.79 2.73% 109,450.71 3.38%
DICIEMBRE. 2015 399,435.84 12.34% 844,208.59 26.08%
ENERO. 2016 300,782.76 9.29% 1,144,991.35 35.38%
FEBRERO. 2016 298,742.98 9.23% 1,443,734.33 44.61%
MARZO. 2016 371,497.17 11.48% 1,815,231.49 56.08%
ABRIL. 2016 453,599.83 14.01% 2,268,831.32 70.10%
MAYO. 2016 331,776.24 10.25% 2,600,607.56 80.35%
JUNIO. 2016 287,000.56 8.87% 2,887,608.12 89.21%
JULIO. 2016 349,086.67 10.79% 3,236,694.78 100.00%
TOTAL 3,236,694.78 100.00% 3,236,694.78 100.00% 109,450.71 3.38% 109,450.71 3.38% 3,127,244.05 96.62%
###
COMENTARIO ###

En el presente cuadro se muestra el avance fisico de obra, 2.73 % con respecto al presupuesto total, siendo el acumulado para el presente mes de S/. 88,501.79
En el presente cuadro se muestra el avance fisico de obra del mes acumulado, 3.38 % con respecto al presupuesto total, siendo el acumulado para el presente mes de S/. 109,450.71

V.- CONTROL DEL AVANCE FINANCIERO


5.1.- AVANCE FINANCIERO DEL MES

CONTROL DE AVANCVE FINANCIERO DEL EXPEDIENTE TECNICO


DESCRIPCION PROYECTO ANTERIOR ACTUAL ACUMULADO %
COSTO DIRECTO 2,530,798.01 14,894.64 148,742.79 163,637.43 5.06
GASTOS GENERALES 400,690.98 34,471.99 23,724.98 58,196.97 1.80
GASTOS DE SUPERVISION 145,424.14 16,248.78 16,248.78 0.50
GASTOS DE ELAB, EXPED, TECN. 61,905.61 28,468.91 28,468.91 0.88
GASTOS DE SUPERV DE ESTUD, 11,133.85 0.00 0.00
GASTOS DE LIQUIDAC, DE OBRA, 20,596.13 0.00 0.00
EXPEDIENTE SOCIAL. 66,146.06 0.00 0.00
COSTO TOTAL 3,236,694.78 94,084.32 172,467.77 266,552.09 8.24

SALDO FINANCIERO
Monto programado Monto Ejecutado Saldo Porcentaje
3,236,694.78 266,552.09 2,970,142.69 8.24%

COMENTARIO

El avance financiero acumulado es de S/. 266,552.09 que representa el 8.24% con respecto al presupuesto total de obra.

CONTROL DE AVANCE FINANCIERO SEGUN PIM ASIGNADO 2015


FINANCIERO PROGRAMADO FINANCIERO EJECUTADO
Porcentaje % Porcentaje %
Monto Monto
Prog % Acum. Eject. Acum.
Inicio 2015 0.00 0.00 0.00 0.00
ABRIL. 2015 0.00 0.00 0.00 8,734.28 2.36 2.36
MAYO. 2015 0.00 0.00 0.00 800.00 0.22 2.57
JUNIO. 2015 0.00 0.00 0.00 18,934.63 5.11 7.68
SETIEMBRE. 2015 78,112.48 21.08 21.08 13,997.02 3.78 11.46
OCTUBRE. 2015 61,919.87 16.71 37.78 35,543.43 9.59 21.05
NOVIEMBRE. 2015 61,903.87 16.70 54.49 188,542.73 50.87 71.92
DICIEMBRE. 2015 168,688.78 45.51 100.00
ENERO. 2016 0.00 0.00 0.00
FEBRERO. 2016 0.00 0.00 0.00
MARZO. 2016 0.00 0.00 0.00
ABRIL. 2016 0.00 0.00 0.00
MAYO. 2016 0.00 0.00 0.00
JUNIO. 2016 0.00 0.00 0.00
TOTAL 370,625.00 100.00 100.00 266,552.09 71.92 71.92
SALDO FINANCIERO
Monto programado Monto Ejecutado Saldo Porcentaje
370,625.00 266,552.09 104,072.91 71.92%

COMENTARIO

El avance financiero acumulado es de S/. 266,552.09 que representa el 71.92% con respecto al presupuesto asignado del presente año 2015

VI.- CONTROL EN LA EJECUCIÓN OBRA


6.1 DEL EXPEDIENTE TECNICO

EL EXPEDIENTE TECNICO ESTA SUFRIENDO VARIACIONES MINIMAS EN CUANTO A LONGITUDES Y DIMENSIONES EN CAPTACIONES Y RESERVORIOS LO QUE EL RESIDENTE SUSTENTARA
OPORTUNAMENTE

6.2 DEL CUADERNO DE OBRA

EN EL MES DE NOVIEMBRE SE TIENE DESDE EL ASIENTO Nº 025, HASTA EL ASIENTO Nº 056 PERTENECIENTE AL SEGUNDO TOMO, DONDE SE HA ANOTADO TODAS LAS OCURRENCIAS Y
ANOTACIONES DEL RESIDENTE Y DEL INSPECTOR DE OBRA.

VII.- RECURSOS UTILIZADOS


7.1.- RECURSOS HUMANOS
7.2.- RESUMEN

CATEGORIA CANTIDAD
INSPECTOR DE OBRA 1
RESIDENTE DE OBRA 1
ASISTENTE TECNICO DE OBRA I 0
ASISTENTE TECNICO DE OBRA II 1
TECNICO ADMINISTRATIVO 0
TECNICO ADMINISTRATIVO II 0
AUXILIAR I 1
RESPONSABLE DE ALMACEN (OFICIAL) 1
OPERADOR DE MAQUINARIA LIVIANA 1
MAESTRO DE OBRA 1
TOPOGRAFO I 1
COCINERA 1
AYUDANTE DE COCINA 1
AFECTOS DE MUNICIPIO 2
OPERARIO I 4
OPERARIO II 1
OFICIAL 3
PEON 22
42
VIII.- RECURSOS DE MAQUINARIA Y EQUIPO.-

8.1.- MAQUINARIA PESADA


ESTADO
DESCRIPCION MARCA HM y/o DIA CAPACIDAD ACTIVIDAD CANTIDAD CONDICION
OPERATIVO
CAMION VOLQUETE 24 4M3 TRANSPORTE DEL PERSONAL Y OTROS OPERATIVO 1 ALQUILADO

COMENTARIO

A LA FECHA NO SE VIENE UTILIZANDO EQUIPO MECANICO PESADO

8.2.- MAQUINARIA LIVIANA

EQUIPO MARCA HM y7o DIA CANTIDAD CONDICION ESTADO

MOTOCICLETA LINEAL 200 CC YAMAHA 24 DIAS 1 APOYO COMUNAL OPERATIVO

MOTOSIERRA HUSQVARNA 13 DIAS 1 APOYO COMUNAL OPERATIVO

8.3.- EQUIPO DE INGENIERIA

TIPO MARCA MODELO SERIE CODIGO PATRIMO ESTADO OPERATIVO ALQUILADO

GPS GARMIN OPERATIVO PROPIEDAD DEL TOPOGRAFO

COMENTARIO
A LA FECHA SE VIENE ULTIZANDO EQUIPO DE INGENIERIA DE PROPIEDAD DEL TOPOGRAFO

IX.-OBSERVACIONES Y RECOMENDACIONES.
1.- OBSERVACIONES
PRESENCIA DE LLUVIAS, VIENE ATRAZANDO EN EL RENDIMIENTO DE PARTIDAS QUE EFECTUAN EL TRASLADO DE MATERIAL A PIE DE OBRA CON MAQUINARIA LIVIANA CORRIENDO PELIGRO
1.1
DE ACCIDENTARSE, ASI MISMO EL RENDIMIENTO DEL PERSONAL OBRERO ES BAJO ESTO DEBIDO AQUE EL TERRENO ES ARCILLOSO.
SE TIENE UN RETRAZO EN EL ABASTECIMIENTO DE MATERIALES POR PARTE DE LA ENTIDAD (AREA LOGISTICA) EN VISTA QUE SE HAN PROGRAMDO DIVERSAS ACTIVIDADES LAS CULAES
1.2 NO SE VIENEN CUMPLIENDO SATISFACTORIAMENTE POR LO QUE LA RESIDENCIA ESTA REALIZANDO SUS ANOTACIONES PARA CUALQUIER AMPLIACION DE PLAZO POR EL
DESABASTECIMIENTO DE LOS MATERIALES. EN MUCHOS CASOS AFECTANDO LA RUTA CRITICA DE LO PROGRAMADO.
2.0 RECOMENDACIÓN
2.1 EL PERSONAL OBRERO DEBE PORTAR SUS EPPs OBLIGATORIAMENTE PARA ASI EVITAR ACCIDENTES EN OBRA. ESTO DEBIDO A QUE EL PERSONAL NO ESTA ACOSTUBRADO ALLEVAR LOS IMPLEMENTOS
SE RECOMIENDA AL AREA DE LOGISTICA DE LA M.D.E. ATENDER LOS REQUERIMIENTOS A LA BREVEDAD POSIBLE, YA QUE DE ELLOS DEPENDEN LOS TRABAJOS PLANIFICADOS. Y
2.2
PROGRAMADOS
3.0 CONCLUSION

A LA FECHA DE REALIZACIÓN DEL PRESENTE INFORME MENSUAL CORRESPONDIENTE AL MES DE NOVIEMBRE 2015 DEL COMPONENTE DE INFRAESTRUCTURA, LA CUAL SE HA ALCANZADO
3.1 UN AVANCE FÍSICO ACUMULADO DE S/. 109,450.71 QUE REPRESENTA EL 3.38% QUEDANDO UN SALDO DE 96.62%.
EL AVANCE FINANCIERO ACUMULADO ES DE S/. 266,552.09 QUE REPRESENTA EL 8.24 % CON RESPECTO AL PRESUPUESTO TOTAL DE OBRA.

X.- ANEXOS
5.1.- COPIAS DEL CUADERNO DE OBRA (QUE SE ADJUNTA EN EL INFORME DEL RESIDENTE) SI
5.2.- VALORIZACION DE LAS METAS FISICAS (QUE SE ADJUNTA EN EL INFORME DEL RESIDENTE) SI
5.3.- MOVIMIENTO MENSUAL DE ALMACEN (QUE SE ADJUNTA EN EL INFORME DEL RESIDENTE) SI
5.4.- PLANILLA DE TAREO DEL PERSONAL (QUE SE ADJUNTA EN EL INFORME DEL RESIDENTE) SI
5.5.- REGISTRO FOTOGRAFICO (QUE SE ADJUNTA EN EL INFORME DEL RESIDENTE) SI