Problem 2 Seepage
Based on the earthfill dam dimesion that you have designed in problem 1
1. Draw the river-side cross section of dam (A-A) with size to scale
1:1000
2. Determine the position of seepage line
3. Draw the flow net for the dam and the foundation in section A-A
4. Make calculation for the total flow discharge through the dam and
foundation for section A-A
5. Make calculation for the total water head, pressure head and elevation
head at point B, C, D as in the figure
6. Estimate the seepage strength of dam and foundation to check if it
exceeds the limit
Given:
The horizontal permeability Kh and the vertical permeability Kv of the dam
and the foundation is equal (i.e. isotropic) Kh=Kv
The permeability coefficient of the dam and the foundation is the same: K
dam = 7.10-8 m/s; K foundation=10-6m/s
NWL is given in Ex1
Tail water is to the ground (no tail water)
Assume the foundation depth T is evenly distributed in the river-side cross
section. T is the thickness of the foundation given in the Geological
longitudinal section in Ex1. Materials in the foundation is clay/sand
Based on the results of problem 1 (the dimension of the dam) and problem 2
(the flow net) determine the factor of safety, Fs, by using the method of
Fellenius/Bishop.
Given:
Dam Foundation
Moisture (wet) W=20% 20%