WORK BREAKDOWN STRUCTURE for 10 Nos.

of RCC ISOLATED FOOTING


CONSTRUCTION Including Column Stub Upto GL
# Activity Activity ID Duration Precedence Relationship
( days )
1 Site Clearance A 2 -------
2 Marking at GL for B 1 A
Excavation
3 Excavation of Footing Pit C 2 B
4 Shoring D 2 B
5 Dewatering E 1 C or D or both C & D
6 Sand Bed Filling F 1 E
7 PCC Bed Pouring G 2 F
8 Marking over PCC Bed H 1 G
9 Rebar Fabrication J 6 --------
10 Rebar Transportation K 1 ---------
11 Rebar Fixing INSIDE THE L 2 K, H
PITS and Supporting them
12 Setting Up of Formworks M 2 L
13 Pouring of Concrete N 2 M
14 Curing P 7 N
15 Deshuttering Q 1 N
16 Backfilling & Soil R 2 Q
Compaction
TOTAL 35
DURATION days
BAR CHART / GANTT CHART for 10 Nos. of RCC ISOLATED FOOTING CONSTRUCTION Including Column Stub Upto GL
Day 1 2 3 4 5 6 7 8 9 1 0 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3
0 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5
# Activity ID D Predece * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
ssor
1 Site Clear A 2 -------
2 GL Markin B 1 a
3 Excavate C 2 b
4 Shoring D 2 b
5 Dewater E 1 c/d
or cd
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
6 Sand Bed F 1 e
7 PCC Bed G 2 f
8 Marking H 1 g
9 Rebar J 6 --------
Fabricate
1 Rebar K 1 j
0 Shift
1 Rebar L 2 k, h
1 Fixing
1 Setting M 2 L
2 Formwork
1 Concreting N 2 m
3
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
1 Curing P 7 n
4
1 Deshutter Q 1 n
5
1 Backfilling R 3 q
6 Compact

Total Project Duration = 25 days or 22 days or ??????????