CONSTRUCTION Including Column Stub Upto GL # Activity Activity ID Duration Precedence Relationship ( days ) 1 Site Clearance A 2 ------- 2 Marking at GL for B 1 A Excavation 3 Excavation of Footing Pit C 2 B 4 Shoring D 2 B 5 Dewatering E 1 C or D or both C & D 6 Sand Bed Filling F 1 E 7 PCC Bed Pouring G 2 F 8 Marking over PCC Bed H 1 G 9 Rebar Fabrication J 6 -------- 10 Rebar Transportation K 1 --------- 11 Rebar Fixing INSIDE THE L 2 K, H PITS and Supporting them 12 Setting Up of Formworks M 2 L 13 Pouring of Concrete N 2 M 14 Curing P 7 N 15 Deshuttering Q 1 N 16 Backfilling & Soil R 2 Q Compaction TOTAL 35 DURATION days BAR CHART / GANTT CHART for 10 Nos. of RCC ISOLATED FOOTING CONSTRUCTION Including Column Stub Upto GL Day 1 2 3 4 5 6 7 8 9 1 0 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 0 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 # Activity ID D Predece * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * ssor 1 Site Clear A 2 ------- 2 GL Markin B 1 a 3 Excavate C 2 b 4 Shoring D 2 b 5 Dewater E 1 c/d or cd * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * 6 Sand Bed F 1 e 7 PCC Bed G 2 f 8 Marking H 1 g 9 Rebar J 6 -------- Fabricate 1 Rebar K 1 j 0 Shift 1 Rebar L 2 k, h 1 Fixing 1 Setting M 2 L 2 Formwork 1 Concreting N 2 m 3 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * 1 Curing P 7 n 4 1 Deshutter Q 1 n 5 1 Backfilling R 3 q 6 Compact
Total Project Duration = 25 days or 22 days or ??????????