Q1:What are the difference between free float, total float and what is different between Float and

Slack?

This is very common question in a primavera interview, Float and slack are the two different words for the same meaning.

Top 10 Primavera Interview questions and Model Answers

Free Float : amount of time , an activity can be delayed without delaying the successor activity

Total Float : amount of time , an activity can be delayed without delaying the project finish date.

Q2:What is a constraint in primavera?

Constrains in primavera is to fix the early or late start or finish date of an activity as per following options:

1) Project Must Finish by

2) Mandatory Start / Mandatory Finish

3) Start / Finish On or After

4) Start / Finish On or Before

5) Start / Finish On

6) Expected Finish

Q3:How can you define the Critical Path in primavera?


The sequence of activities which describe the longest path from the data date to the end of the project. In a schedule
without any constraints, this will be all activities with zero total float.

(if you have constrains which force negative float, simply filtering on total float equal to or less than zero can bring up
activities which are not on the critical path)

Q4:What is WBS?

WBS means Work Breakdown Structure. it represents a hierarchical breakdown of a Project into elements and
deliverables.

Q5:What is an open end activity in primavera?

The open end activity is the activity that does not have any successor. Normally open end activity is not accepted in
schedule because the total float will be calculate from the end of the project and these entire activities late dates gather at
the end of the project and can not be prepare a logical late start plan.

Q6:What is the difference between Retained Logic & Override Logic in progress update?

If a project is generally running according to plan and activities are not progressed out of sequence then there will be
virtually no difference between the two methods. BIG differences come when activities are progressed out of sequence.
I believe in retained logic. Invariably that will produce the longest critical path but if activities have been progressed out
of sequence, there could be some resulting illogical dependencies remaining, in particular resulting from dependencies
with durations.
Progress override invariably produces a shorter critical path and again there could be some illogical lack of dependencies
resulting from activities having been progressed out of sequence.

Q7:How do u measure & compare the progress using primavera?

This is one of the Hard primavera Interview Questions, try to explain without confusion.

Progress is measured primarily against the baseline. If the baseline has been loaded with cost and/or resources, earned
value management can be used for this purpose. If not, progress is measured as variance to baseline dates.
Budget at Completion (BAC)
Planned Value (PV) = budget at Completion (BAC) x Planned % Complete
Earned Value (EV) = budget at Completion (BAC) x Actual% Complete
Actual Cost (AC) = No formula What you’ve actually spent on the project
Schedule Performance Index (SPl) =Earned Value (EV) / Planned Value (PV)
Schedule Variance (SV) =Earned Value (EV) – Planned Value (PV)
Cost Performance Index (CPI) =Earned Value (EV) / Actual Cost (AC)
To Complete Performance Index (TCPI) =(Budget at Completion (BAC) – Earned Value (EV) ) / (Budget at Completion
(BAC) -Actual Cost (AC) )
Cost Variance (CV) = Earned Value (EV) -Actual Cost (AC)
For more information see this article: EVM earned value management
Q8:What is resource allocation and resource leveling?

Resource allocation is assigning resources to activities,determine the amount of labor, equipment and money required for
any activity.
Resource leveling is Resource requirements of all scheduled activities are compared to the maximum quantity available at
the time of leveling.An activity is delayed if too few resources are available at any time during the activity’s duration.The
maximum quantity for a resource is determined through the Max units/time for a particular resource in the Resources Tab.

Q9:What is an S – Curve and how to create S Curve in primavera?

An S-curve is a graph showing cumulative cost or value (measured in terms of money or manhours) against time. On a
typical project, these graphs follow an “S” shape, hence the name. Typical data to be plotted on an S-Curve includes:

Actual Cost (ACWP)

Planned Value (BCWS) –Early dates

Planned Value (BCWS) –Late dates

Earned Value (BCWP)

Forecast Value –Early dates

Forecast value –Late dates

Forecast Cost –Early dates

Forecast cost –Late dates

Q10:What are the difference between flag and milestone activity in primavera?

This is one of the tricky Primavera Interview questions.

Mile stone & flags both are events rather then activities. Some client likes to use flags rather than mile stone due the
following differences.
1- With the use of flags the logic of main event can be easily tracked as these can not be created without predecessor as
stand alone allocating the constraint.Where as mile stone can.
2- Flags can not update manually as Primavera automatically update the status where as milestone can be update
manually.
3- Flags can not be constraint only driven by predecessor where as milestone can