Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
I hope that this Newsletter will contribute to communicate technical ideas, solutions and
experiences gained by TCAA to whomever in the VSL Group, who is trying to chase
respectively carry out similar type of work.
Max Meyer
Manager Technical Centre Asia/Australia
1
CONTENT TCAA
ABOUT TCAA 3
TCAA – The Organisation 3
TCAA – The People 3
ONGOING PROJECTS 5
Hong Kong 5
India 7
Indonesia 8
Malaysia 9
Singapore 9
Vietnam 10
Australia 10
USA 11
South America 11
JOB REPORT 12
Telok Blangah Semi-Expressway 12
SPECIALIST EQUIPMENT 18
VSL Modular Formtraveller 18
VSL Thailand Overhead Gantry 21
Newsletter published by VSL Singapore Pte Ltd – Technical Centre Asia/Australia, 25 Senoko Way,
Woodlands East Industrial Estate, Singapore 758047 z Layout and Editing by MLU, FEF, LYM z
Technical Articles MLU (Telok Blangah), GTH (Formtraveller), NCC (VSLTH Gantry) z Photos TCAA, Site
Teams and PCs z Cover Photo Metro Line 4, Santiago de Chile by Site Team z Copyright VSL
Singapore Pte Ltd – Technical Centre Asia/Australia, May 2004 – All rights reserved
2
TCAA – THE TEAM TCAA
TCAA – THE ORGANISATION
TCAA
3
TCAA – THE TEAM TCAA
Surya KUSUMA (SUR) William CHUNG (CHL)
Engineer Senior Draftsman
1 / 4 years *) 9 / 9 years *)
Concrete design
4
ONGOING PROJECTS TCAA
ASIA
HONG KONG
Deep Bay Link
Span-by-span precast segmental bridge, span length
34.1– 42.3 m, span weight 910 tonnes.
TCAA Involvement:
Tender:
• Modular formtraveller and lifting frame for bridge
CPR1 North
• Assessment of recycling Humin gantry and Penny’s
Bay gantry for span-by-span erection
Team: AHR, CHL, EDF, FEF, LMC, LYM, MLU, NCC,
NSB
Execution:
• Gantry AB: Modification of Type 2 overhead gantry
(ex Penny’s Bay)
• Gantry C: Design of new span-by-span overhead
gantry
Team: AHR, AHS, CHH, CHL, GTH, LMC, LHY, LTC,
THA, YMN, YYL
5
ONGOING PROJECTS TCAA
Penny’s Bay
Span-by-span pre-cast segmental bridge, span length
36m, span weight 760 tonnes.
TCAA Involvement:
Tender:
• Erection scheme proposal (overhead gantry)
Team: MLU
Execution:
• Modification of Type 2 underslung gantry into
overhead gantry (ex East Rail)
Team: AHR, AHS, CHL, EDF, GTH, LTC, MLU, NCC,
NSB, YMN
6
ONGOING PROJECTS TCAA
INDIA
Bandra Worli Sea Link
Span-by-span pre-cast segmental bridge, span length
50m, span weight 1800 tonnes.
TCAA Involvement:
Tender:
• Erection concept using span-by-span overhead
gantry
• Casting cell and yard layout concept
• Loading installation for lifting of segments onto deck
and erection of gantry
Team: CHH, GTH, LMC, LYM
Execution:
• Detailing of bridge deck
• Segment shop drawings
• Geometry control and precamber calculation
• Design of span-by-span overhead gantry
• Supply of gantry launching equipment
• Loading installation for lifting of segments onto deck
and erection of gantry
• Supervision of heavy lifting of gantry during erection
• Design of cleaning platform
• Casting yard layout and foundation design
• Design of casting cells
• Design of rebar jig
• On site secondment of Technical Manager
Team: AHR, AHS, CHH, CHL, EDF, GTH, LMC, LYM, MZU, NSB, SCD, YMN, YYL
7
ONGOING PROJECTS TCAA
INDONESIA
Pasupati Viaduct
FCM pre-cast segmental bridge, span length 44.5m,
max segment weight 143 tonnes.
TCAA Involvement:
Tender:
• Costing for package works (segment production and
erection)
• Erection concept using overhead gantry
• Casting cell concept
• Alternative design for viaduct
Team: FEF, LYM, MLU
Execution:
• Design of temporary post-tensioning
• Conceptual design of temporary fixity
• Stage-by-stage analysis
• Detailing of bridge deck
• Segment shop drawings
• Geometry control and precamber calculation
Team: CHL, NSB, MLU, SUR
8
ONGOING PROJECTS TCAA
MALAYSIA
Bayan Baru Viaduct
FCM pre-cast segmental bridge, typical span length
47m, segment weight 100 tonnes.
TCAA Involvement:
Tender:
• Alternative design for main viaduct/ramp to optimize
concrete / PT quantity
• Temporary tower for unbalanced moment
Team: FEF, MZU
Execution:
• Modification overhead gantry (ex Pakse)
• Geometry control and precamber calculation
• Nailing concept
Team: AHR AHS, CHH, CHL, GTH, LTC, LYM, MLU, NCC, NSB
SINGAPORE
BKE Widening and Strengthening
Widening and strengthening of existing Highway
bridges under traffic.
TCAA Involvement:
Tender:
• Design of two schemes
• Package costing
Team: FEF, EDF, CHH, LYM, NSB, MLU, YMN
Execution:
• Design and detailing of widening and strengthening
works
• Design of bracket for bearing replacement
Team: AHR, LYM, MLU, NSB, PG, SUR
9
ONGOING PROJECTS TCAA
VIETNAM
Bai Chai Stay Cable Bridge
Stay cable bridge, main span length 435m.
TCAA Involvement:
Tender:
• Various formtraveller proposal (underslung,
overhead, modular)
• Deck steel struts: fixation, aligning and setting
method
• Erection of guide pipe with steel frame
• Assistance for package costing
Team: FEF, GTH, LMC, LYM, MLU
Execution:
• Independent design check
Team: CHH, LYM, NSB, SUR
AUSTRALIA
WestLink M7 – Sydney
FCM and span-by-span pre-cast segmental bridges.
TCAA Involvement:
Execution:
• Modification of Type 2 underslung gantry (ex
Eastrail)
• Geometry control and precamber calculation
• Provision of Technical Manager (2 months)
Team: AHR, AHS, CHL, LMC, MLU, MZU, PG, SUR
10
ONGOING PROJECTS TCAA
USA
US Grant
Stay cable bridge, main span length 251.5m.
TCAA Involvement:
Execution:
• Stay cable fabrication and installation method
Team: AHR, CHH, FEF, LMC, LYM
US Greenville
Stay cable bridge, main span length 420m.
TCAA Involvement:
Execution:
• Stay cable fabrication and installation method
Team: AHR, CHH, FEF, LMC, LYM
SOUTH AMERICA
Metro Line 4 – Santiago de Chile
Span-by-span pre-cast segmental viaduct
TCAA Involvement:
Tender:
• Erection concept using span-by-span overhead
gantry
Team: NCC
Execution:
• Design of span-by-span overhead gantry
• Supply of ULRS
• Supervision of gantry commissioning
• On-site review of operation
Team: AHS, EDF, GTH, LTC, NCC, NSB, SCD, YYL
11
JOB REPORT TCAA
Telok Blangah Semi Expressway, Singapore
Project Description
Telok Blangah Road is located at
the southern tip of Singapore. The
road is used by heavy trucks
ferrying containers between the
port facilities at Keppel Road /
Pulau Brani and Jurong.
A portion of Telok Blangah Road
is upgraded with an elevated
semi-expressway, primarily to
relieve the on-grade road from the
port traffic. The total project of
around 5km length is divided into
two phases. The works described
in this article concern the first
phase.
The first phase compromises a
2.4km long twin box-girder
structure above the existing Telok
Fig 1 – Telok Blangah Gantry
Blangah Road. Each box girder
has a width of 12.8m and is 2.2m pier shaft are connected tonnes) were used to lift the beam
deep and spans over a length of monolithically. onto the pier. At that stage the
35 to 45m. The structure is tendons, providing the strength for
designed as a structural frame Crosshead Construction the simply supported mode during
with the box girders connected transport, were distressed byoxy-
Out of the 59 piers, 49 are
monolithically to a common cutting. The precast beam was
standard piers, crosshead on a
crossbeam, which is supported on placed onto the custom designed
single pier, and 10 piers have
a single pier. The chosen steel support installed on the pier.
larger crossheads on double
construction method is the free- The steel structure, designed by
piers. The tender documents
balanced cantilever method using TCAA, came in several parts to
called for casting of the standard
precast segments. The 59 spans ease installation. Two small steel
crosshead parallel to the existing
per bound consist of 12 to 16 section, stressed to the pier, were
road with a subsequent rotation of
segments each, totaling to 1448 installed first and provided the
the entire crosshead. A faster and
segments. Besides the main support for the actual support and
more economical solution was
bridge, four ramps were alignment frame. The heavy loads
needed. TCAA proposed to
constructed with a total length of were introduced through recesses
partially precast the crosshead off-
1.6km. The ramps are cast in-situ. into the pier. The support and
site, erect the precast crosshead
The main challenges of the project by crane and complete it with
were the construction of an minimal in-situ work. TCAA was Project Facts:
elevated structure, while the involved in the conceptual design Location Singapore
complete capacity of the road Owner Land Transport Authority
of the crosshead and produced Singapore
below had to be maintained the shop drawings.
throughout most of the day. Partial Permanent Structure
The precast section is 3.8m high, Structural frame, expansion joint in ¼
road closures were allowed only 2.2m wide and 28m long, points every 7 spans (260m).
during the night hours. A station of weighing between 140 and 160 Main Bridge Length 2x 2.4 km
the Singapore MRT (subway) was tonnes. Casting took place in pre- Deck Area 73’600m
2
12
JOB REPORT TCAA
casting of the in-situ section.
Casting of the in-situ section was
done in a 2-week cycle as well.
Two sets of platforms allowed to
work on two crossheads, hence
one crosshead was completed
every week. Tendons installed in
the in-situ section were stressed
remaining duct, castings and anti-
Fig 4 – Stitching Beams
in several stages as the load onto
the crosshead increased. by the hanger beams. Once lifted
to correct level, the segment was
A part of the viaduct features a
suspended in four stressbars,
ramp between the two decks. The
which allowed the accurate
two decks move further apart to
leveling of the segment. The
allow space for the ramp, creating
stressbars were anchored in
large odd shaped crosshead
sledges, which could be moved
supported on two piers. The size
byhydraulic jacks for the
and odd shape of these 10
horizontal alignment of the
crossheads made them not
segment. All four first segments of
suitable for the partially precast
Fig 2 – Temporary Support for Crosshead the cantilevers were delivered and
method, hence they were cast
alignment frame allowed the lifted during one night. Stressing
entirely in-situ. These crossheads
movement of the crosshead in all platform and wet-joint formwork
were built in 2 months cycles.
three dimensions (translation and were lifted together with the
rotation). Laser survey equipment segment. Relocation of the steel
was used to align the crosshead Erection of the 1st work, segment lifting, placing of
in the same night as the erection. Segment Pair the reinforcement and joining of
Casting of the monolithic Deck and crosshead are the ducts, casting of the wet-joint
connection followed the next day, connected monolithically, hence a and stressing of the tendons was
after which the steel wet-joint of nominal 0.25m length again achieved in a one week
support could be removed. This was required between precast cycle.
construction method allowed to segment and crosshead. Being on The authorities required that
undercut the planned 1 week the critical path, TCAA proposed segments hanging over traffic,
lifting cycle by as much as 4 days. to separate the operation form the without stressed permanent
Light access platforms were then segment erection by gantry. For tendons, are to be provided by a
installed along the crosshead to this purpose a set of so-called so-called “Triple Safety” system,
facilitate the installation of the hanger beams was designed by requiring three independent
bursting reinforcement were all TCAA. Segments were lifted with suspension systems. Hence,
placed within the precast section, a SLU-70. The SLU was mounted segments were not only
and the reinforcement of the in- in a truss, recycled from a gantry suspended by the four stressbars
situ section. Only simple side used on an earlier project in used for alignment, a second set
forms were required for the Singapore, which was supported of four stressbars was installed
and the SLU-70 stayed connected
to the segment at all times.
Accordingly, the steel structure
had to be designed for the same
requirement, making it far bigger
than required for a single
suspension system.
At a later stage a second set of
hanger beams was
commissioned. This set was not
equipped with SLUs instead a
mobile crane was used to lift the
segments. The triple safety
requirement was relaxed to a
double safety requirement for the
second the set.
13
JOB REPORT TCAA
VSL Scope
VSL Singapore’s scope
compromised the erection of the
precast crossheads and bridge
segments and the supply and
installation of the post-tensioning
steel for the whole bridge
including ramps. TCAA was
responsible for the design of the
temporary
14
ERECTION GANTRIES – REUSED I: 2nd Link Gantry TCAA
2ND LINK GANTRY
2nd Link Malaysia – Singapore 1995 –
1997
FCM pre-cast segmental viaduct
New gantry design
Max segment weight 134tonnes
Span Length 70m
840 Segments placed
PAKSE GANTRY
Mekong Bridge Pakse, Laos 1997 –
1999
FCM pre-cast segmental viaduct
New rear portal and main leg, modified front
support and roller frames, additional truss element,
stay cable system and stressing platforms added
Max segment weight 107tonnes
Span Length 102 / 143m
384 Segments placed
15
ERECTION GANTRIES – REUSED II: Type 2 West Rail TCAA
West Rail, Hong Kong 1999 – 2001
Span-by-span pre-cast segmental viaduct
New gantry design (7 No.)
Max span weight 400tonnes
Span Length 25 – 40.5m
9400 Segments placed
16
ERECTION GANTRIES – REUSED II: Type 2 West Rail TCAA
Penny’s Bay, Hong Kong 2003 – 2004
Span-by-span pre-cast segmental viaduct
Modification into overhead gantry
Max span weight 760 tonnes
Span Length 36 m
70 Segments placed
17
SPECIALIST EQUIPMENT I TCAA
The VSL Modular Formtraveller - A Success Story for
the VSL Group
Introduction
VSL Modular Formtraveller
System (MFT) has been specially
developed for construction of cast-
in situ viaduct / bridge utilizing
Free-balanced Cantilever Method
(FCM). This well established
construction scheme has become
very popular worldwide due to its
proven competitiveness. This is
especially suitable for bridges with
either long span or crossing over
deep valley or water where normal
logistics would not be feasible.
• One time investment that leads Fig 1 – Formtraveller installed on pier table, casting of first segment
to long-term benefits and Design specification for VSL MFT erected simultaneously. This is
returns. are summarized as follows: made possible due to the fact that
• Competitive quote for future the two main frames and rails of
Bridge Alignment
projects and short lead time to the travelers could be partially
site mobilisation. Vertical Curve/ Gradient overlapped. This would offer great
maximum ±5% reduction in terms of initial
• Elements are exchangeable
between various profit centres. Horizontal Curve in Plan program and cost incurred for pier
minimum radius in plan of 500m table false work.
TCAA first started working on the
MFT concept as early as in 1997. Crossfall / Superelevation
The scheme was subsequently maximum ±5%
received strong support in Asia for Segment Geometry
R&D program in late 1999. Budget
Segment Length
was hence granted from VSL
maximum 5m
Management and Asia in 2000 for
TCAA to proceed with final Segment Weight
design/detailing works. Final maximum 180 tonnes
drawings and documents were (With two main frames)
fully produced by early 2001. First Number of Cells / Boxes
Fig 2 – Endspan Closure
prototype pair was built and used Can handle single or multi-cell /
on Taiwan High Speed Rail box segments Closure Pour
Contract 215 by late 2001 (2 pairs Web inclination Mid span closure can be done
required). VSL Taiwan then Can handle vertical and inclined with the traveler provided the main
secured Contract 260 in the same webs components of inner form can be
year and another pair was removed prior to casting the last
Pier TableMinimum length of 7.2m
fabricated. cantilever segment. Some form
is required to erect the travelers
one after another. First traveler is panels that can be easily
General Characteristics to be installed on top of pier table, dismantled and removed through
Being a modular system, VSL the first segment is cast and the some manholes provided in this
MFT is intended to be used and traveler is launched to the tip of vicinity shall replace them.
adjusted with ease for various first segment before the second The main frame is designed
projects with different geometrical traveler could be erected. without considering the provision
variances or requirements. Minimum length of 8.2m is for vertical alignment of the two
required if both travelers are to be adjacent cantilevers prior to
closure. It can however be
18
SPECIALIST EQUIPMENT I TCAA
calculated to check its remaining Cycle Non-modular elements are those,
capacity of doing this vertical which always need to be modified,
Concrete curing is the most critical
alignment on a case-by-case replaced or even added to suit the
path for MFT operation. A certain
basis if necessary. new arrangement for new
minimum strength of the concrete
geometry requirements.
End Span must be achieved prior to form
End spans are normally built on stripping and cantilever PT
application. MFT could then be Formwork Description
false works prior to the
construction of the adjacent launched to the top of the newly All components of formwork have
cantilever by MFT. cast segment for next cycle. not been considered as
In order to minimize curing permanent part of the modular
It is however possible to build the
requirement and to gain flexibility system. They generally require
end span also utilizing the MFT if
speeding up construction, high replacement after certain usage
temporary propping is feasible
early strength concrete mix or and need to be tailor made for
below the adjacent cantilever. The
steam curing is generally new projects to suit new profiles.
MFT could then continue casting
the end span with the out of recommended. They can be designed based on
balance load resisted by such Typical cycle time is hence highly plywood skin and timer runners.
temporary propping. dependent on the curing time Alternatively the incorporation of
required from job to job. An proprietary system form by
optimum cycle of 4 days is specialist such as DOKA or
achievable based on 12 hours of ALUMA can also be implemented.
steam curing time over night. This approach however will need
Otherwise at least one full day very close and proper
shall be added for curing and coordination to ensure all parts fit
would bring the typical cycle to 5 eventually on site.
or even 6 days.
Work by TCAA
Element Description Project Leader
Fig 3 – Front View of Traveller Gan Teng Hwai
Elements of VSL MFT can be
generally divided into two main Design Engineer
Casting Sequence and categories, modular and non- Suchada Padermkul
Cycle modular. As their names suggest, Drafting
Sequence modular elements are those, Aspiah Huri
which can be used from job to job
Asymmetric construction with only difference in number
sequence is generally required and combination.
recommended, as this would
reduce the out of balance moment
introduced to pier significantly.
First segment to be cast shall
have half the length of the usual
segment. Second (on the opposite
cantilever) and subsequent
segments would be cast
alternatively to the two cantilevers
with the normal length.
Alternate MFT advancing
sequence shall always be
adopted. This method involves
staggering of the activities for the
pair of MFT for approximately half
the intended cycle. This would
hence allow operating both MFT
economically by avoiding
undertaking same activities at the
same time, thus optimizing
utilization of personnel.
19
RECENTLY COMPLETED PROJECTS TCAA
TPE – Sengkang Interchange /
Flyover, Singapore
Incrementally Launched Bridge
Incrementally launched bridges
Max span length during launching 32m
• Detailing of superstructure including shop
drawings
• Design of temporary works (launching nose,
temporary bearings and guides, formwork,
temporary tower, launching equipment)
20
SPECIALIST EQUIPMENT II TCAA
VSL Thailand Overhead Launching Gantry – Modular
Gantry for I-Girder Erection
This article shows the use of modular erection gantry, which was originally designed for
30m span launching and 70tonnes precast beam erection. It was fabricated in Thailand in
1994. The gantry had been modified and reused for 7 projects and erected almost 2,000
precast beams over 8 years. Recently the gantry was modified and upgraded to meet the
latest challenge of 42m. span with 78tonnes precast beam in the Philippines.
21
SPECIALIST EQUIPMENT II TCAA
Reused with Ramindra – section was added to parts with
Atnarong and Bang high shear loading. The diagonal
was shifted to its section’s center
Pakong Project [1995] of gravity and welded to gusset
Due to popularity of I-girder bridge plate. This detailing helped to get
deck system in Thailand, the rid of local eccentricity of member,
gantry was reused again for which was present due to bolted
Ramindra – Atnarong Expressway connections. Existing steel was
Project – Lot 7 in Bangkok, efficiently reused to minimize
Thailand. The project was carried modification costs [See Fig.4] .
out in 1995. Typical span was 30- Other gantry components were
m with heaviest girder weight 65T. also upgraded slightly. UCB had
Approximately 1,200 precast minor modification and repair to
girders were erected with the LG. good condition. FSL was
After completed the expressway equipped with trolley frame and
project, the gantry was again movable along MT. Rear Support
needed for Bridge over Bang Leg (RSL), similar to FSL, was
Pakong River Project, Thailand. Fig. – 3 Cross Section of MT after
added to the gantry and replaced
The LG successfully completed strengthened for Talingchan-
Buddhamonthon II ProjectAtnarong
the use of RB. RSL made the LG
erection of 40 girders. The 66-m symmetrical and allowed
long MT was used with slight Project. The second gantry was
VSLTH modular gantry used for launching in both directions.
modification for span 35-m in
Bang Pakong. Special sequences Section 2. The precast beam was delivered
were implemented for launching Typical span of this project was from ground underneath the span
and LCB was used as a counter 35m and had one span of of erection. LCB was placed on
weight when MT was reaching out maximum length 38.2m. Heaviest wide half-joint crosshead. Special
to next span with its center of I-girder weighed 70tonnes. kinematics involving LCB shifting
gravity beyond LCB support. on crosshead was done to launch
The bridge was built over one of over maximum span length
With minimal technical support, the busiest 8 lanes highway in 38.2m. The erection was carried
the gantry can be operated by Bangkok. The erection was done out during late 1996 to 1997.
local team with small engineering during the nighttime with one side Section 2 and 3 erection was
cost. It proved to be user friendly of the road closed for erection. finished ahead of the schedule.
and economically designed for The existing MT elements were VSL gantry again successfully
various applications. Though the not long enough to be launched completed 800 beams erection.
gantry had been used to erect over the 35m span. A new
over a thousand of beams, the The gantry was used for other two
element of 10m long was projects in Thailand. A bridge
structure was still fit to serve fabricated in 1996 to increase the
more. project crossing a river in
total length of MT to 76m. Top and Ubonratchathani and bridge over
bottom chords of MT were Tapi river in Suratthani, southern
Talingchan – strengthened to take the part of Thailand. The Tapi project
Buddhamonthon II increased loading. Side plates has haunched precast crosshead
Elevated Highway Project were added to top chord. Wing with maximum span between
plates were added to top and
[1996] bottom flange of bottom chord
center of crosshead 50m. Twin
decks were erected at the same
The project was located in member [See Fig.3]. time. The gantry was launched on
southern part of Bangkok. It was
Diagonal members were also crosshead with help of temporary
one of His Majesty King
strengthened. Bolted connection supports underneath and specific
Bhumiphol’s contemplate to
was changed to welding. Existing LCB relocation steps.
resolve traffic problem. The
small channel was doubled up to Total 63 girders were erected
project was divided into 3
one member. Stronger channel
sections. Erection of I-girder for
Section 1 was done by mobile
crane. Section 2 and 3, which had
some spans crossing over existing
flyover, were erected using 2
gantries. The first gantry belonged
to main contractor, Italian – Thai
Development Pub. Co. Ltd, but it
was designed by VSL TCAA since
Ramindra –
Fig. 4 – General Arrangement for Talingchan-Buddhamonthon II Elevated Highway Project
[1996-1997]
22
SPECIALIST EQUIPMENT II TCAA
Chain drive units were used for
safe launching operation at 5%
gradient. UCB was equipped with
chain drive for safe operation at
steep gradient. VSL strand lifting
unit was still in service for the
lifting of precast beam. ULRS was
upgraded to have 8 wheels per
unit to take the remarkable load
increment. PU10 was still in use
for transverse sliding of MT. LCB
Fig. 5 – General Arrangement for Bridge over Tapi River, Thailand. [1999] and its support from CEBU project
were slightly strengthened.
using VSLTH gantry in Tapi was strengthened at critical Additional LCB support legs were
project. Engineering work and region. Connection bars were placed at critical position on
kinematics were carried out by increased from 4 CT Stressbar certain pier of 42m span.
local team including casting yard Ø38 to 8 CT Stressbar Ø38.
FSL and RSL were modified to
set up behind the erection gantry Existing member was still
have more working stroke. Outer
[See FIG.5]. sufficient for the new loading.
housing was extended with
Some single channel diagonal
outrigger to accommodate
Cebu Coastal Road members were braced to reduce
Project, Philippines [2000]
After long service in Thailand, the
gantry was transferred to The
Philippines for Cebu Coastal Road
Project. The viaduct ran across
the open sea for about 1.4-km.
Precast beam was delivered by
barge from underneath span of
erection. LCB support was
modified to suit the new
crosshead configuration. Minor
touch-up was done on LG to make
it running properly. Maximum
span length in this project was
36.75m with heaviest beam
60tonnes. The gantry completed
320 precast beam erection around Fig. 6 – Cross section of MT with Intermediate Transverse Bracing: C5 Project, Philippines
late 2002. [2003]
buckling length and improve shear shimming. The shim will allow
Latest Challenge – C5 capacity of MT. Special feature FSL/RSL to reset its inner housing
Ortigas Interchange, introduced for 42m span when the stroke is not sufficient.
Philippines [2003] launching was intermediate The gantry was assembled to 76-
transverse bracing between MT. m length and used to erect first
Latest assignment for the gantry
was C5 Ortigas Interchange Four intermediate bracing were part of 30m spans by normal
needed during 42m span procedure. Three front MT
located in busy district of Manila. nd
The viaduct was built over an launching in order to reduce 2 elements were added only before
existing flyover. Bridge length is order effect from large reaching 42m spans. Those
695m with 22 spans. Three center deformation and to gain lateral elements were taken out after the
spans over existing bridge are stability of MT itself. [See FIG.6]
42m long. The maximum weigh of
beam is 78tonnes. The maximum
span length becomes 1.4 times
longer than its original design.
Two sections of 8m long MT
elements were added to increase
the MT total length to 92m. The
new and strongest elements were
placed at the maximum loading
location. Existing top chord splice Fig. 7 – General Arrangement of Gantry for 42-m Span: C5 Ortigas Interchange Project,
Philippines [2003]
23
SPECIALIST EQUIPMENT II TCAA
special spans were done. The gantry was modified late 2002 gantry at 42m span in C5 Ortigas
The structure was analyzed using and assembled on site in Project.
modern sophisticate engineering December. 21 spans with 176
software and equipped with new precast beams were erected by
gears for better performance. the gantry in 2003. Figure 7
shows general arrangement of
Up to end of 2002, the gantry had erected approximately 2,400 precast beams over 8 years. It still continues the service for more and
more challenging task. The structure had efficiently designed and proved to be economical and very versatile for many projects.
Combining with dedicated effort and thoughtful consideration from operation team, the gantry will be able to deal with any challenging
task in the future.
24
SELECTED REFERENCE PROJECTS TCAA
Formtraveller
2001 Contract 260, Taiwan: modular formtraveller
2000 Modular Formtraveller
1997 Ma Wan, Hong Kong
1996 2nd Link Malaysia – Singapore
1996 Ilan Bridge, Taiwan
1994 Barelang Bridge 2, Indonesia
25
SELECTED REFERENCE PROJECTS TCAA
Heavy Lifting
2004 NUS, Singapore: transfer beam lifting
2004 DHDS Reactor Lifting, India: reactor lifting
2003 Bandra Worli, India: loading installation, gantry lifting
2001 New Bangkok International Airport, Thailand: tender design
1999 Telok Blangah Semi-Expressway, Singapore: crosshead fixity, hanger
beams
1999 Telok Blangah Semi-Expressway, Singapore: crosshead fixity, hanger
beams
1994 KLCC Skybridge, Malaysia
1994 Peruri Water Tower, Indonesia
1992 Brunei Hanger, Brunei
1991 Mobile Badger, Singapore
26
SELECTED REFERENCE PROJECTS TCAA
Circular Structures
2002 Changi Water Reclamation Plant, Singapore: design and shop drawings
2002 NEWater Service Reservoir, Singapore: design and shop drawings
2001 Kim Chuan Egg-Shaped Digesters, Singapore: design and shop drawings
1996 Ulu Pandan Egg-Shaped Digesters, Singapore
1996 Seletar Egg-Shaped Digesters, Singapore
1995 Kranji Egg-Shaped Digesters, Singapore
Repair / Strengthening
2003 BKE Widening and Strengthening, Singapore: strengthening of existing deck
2000 Blue Circle, Singapore: strengthening of cement silo
2000 Contract 324, 324, Taiwan: realignment of bridge deck modules moved during
earthquake
27
SELECTED REFERENCE PROJECTS TCAA
28
CREATING SOLUTIONS TOGETHER TCAA
GEMANY
SWITZERLAND
VSL (Switzerland) Ltd.
JAKARTA
Phone: +62 - 21 570 07 86
Australia
VSL Systems GmbH SUBINGEN Fax: +62 - 21 573 12 17 VSLPrestressing(Aust.)Pty.Ltd.
BERLIN Phone: +41 - 32 613 30 30 SYDNEY
JAPAN
Middle East Phone: +49 - 30 53 01 35 32
Fax: +49 – 30 53 01 35 34
Fax: +41 - 32 613 30 15
VSL Japan Corporation Phone: +61 - 2 9 484 59 44
VSL (Suisse) SA TOKYO Fax: +61 - 2 9 875 38 94
UNITED ARAB EMIRATES GREAT BRITAIN Phone: +81 - 3 3346 8913
VOUVRY BRISBANE
VSL Middle East Office VSL Systems (UK) Ltd. Fax: +81 - 3 3345 9153
Phone: +41 - 24 481 57 71 Phone: +61 - 7 3 265 64 00
DUBAI CAMBRIDGESHIRE Fax: +41 - 24 481 57 72 KOREA Fax: +61 - 7 3 265 75 34
Phone: +971 - 4 282 08 03 Phone: +44 - 1480 404 401
Fax: +971 - 4 282 94 41 Fax: +44 - 1480 404 402 VSL Korea Co. Ltd.
SEOUL MELBOURNE and SOUTHERN
GREECE Phone: +82 - 2 553 8200 Phone: +61 - 3 979 503 66
VSL Systems A/E Fax: +82 - 2 553 8255 Fax: +61 - 3 979 505 47
ATHENS
MAINLAND CHINA
Africa Phone: +30 - 2 1 0363 84 53
Fax: +44 - 2 1 0360 95 43 VSL Engineering Corp., Ltd.
HEIFEI
SOUTH AFRICA NETHERLANDS Phone: +86 - 551 557 6008 Technical Centres
VSL Systems (South Africa) Pty. Ltd. VSL Benelux B.V. Fax: +86 - 551 557 6018
Tsala-VSL Construction Systems AT LEIDEN Technical Centre Asia/Australia
(Pty) Ltd. Phone: +31 - 71 576 89 00 VSL Engineering Corp., Ltd. SINGAPORE
Kya Sand, RANDBURG Fax: +31 - 71 572 08 86 Shanghai Branch Co. Phone: +65 - 6559 12 22
Phone: +27 - 11 708 21 00 SHANGHAI Fax: +65 - 6257 70 11
Fax: +27 - 11 708 21 20 NORWAY Phone: +86 - 21 6475 4206
VSL Norge A/S Technical Centre Europe
Fax: +86 - 21 6475 4255 SUBINGEN
STAVANGER
Phone: +47 - 51 52 50 20 MALAYSIA Phone: +41 - 32 613 30 30
Fax: +47 - 51 56 27 21 VSL Engineers (M) Sdn. Bhd. Fax: +41 - 32 613 30 15
KUALA LUMPUR
POLAND Phone: +60 - 3 7981 47 42
VSL Polska Sp. z o.o Fax: +60 - 3 7981 84 22
WARSAW
Phone: +48 - 22 817 84 22 PHILIPPINES
Fax: +48 - 22 817 83 59 VSL Philippines Inc.
PASIG CITY
Phone: +63 - 2 672 17 03
Fax: +63 - 2 672 13 95
SINGAPORE
VSL Singapore Pte. Ltd.
SINGAPORE
Phone: +65 - 6559 12 22
Fax: +65 - 6257 77 51
29