Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Temperature 30 35 40 45 50 55 60 65
Temperature Factor 1 0.94 0.87 0.79 0.71 0.61 0.5 0.35
No. of Cable 1 2 3 4 5 7 10
Grouping Factor 1 0.94 0.87 0.79 0.7 0.61 0.5
1
Naming of Cable:
Multi Core Cable:
(3*185+1*95) - 4 core cable of which 3 cores is 185 mm2 and 1 core of 95 mm
4 x (1*10) – 4 single core cables with cross sectional are 10 mm2.
Note:
In case of industrial application that used power electronics it’s preferred to
make the neutral C.S.A equal to phase C.S.A
Also, full neutral is used in case of fluorescent lamps used because the 3rd
harmonic value is very high.
Load Calculation:
Demand Factor:
The demand factor is concerned by the loads of the same type at the same panel for
example: Load of lighting at the same panel, Loads of socket at the same panel
Demand Factor = The maximum demand of a certain load type / The total
connected load of the same load type
The diversity Factor: It is the probability of operating different types load in the
same time.
Example: Room Loads: Sockets + Lighting + Air-conditioning load
Illumination Calculation:
Room Index (K) = L x W /HNet (L+W)
Fault Current:
1. Fault current is used to set the relay over current and earth fault setting as per
lowest fault current at tail end so that relay can respond even at the lowest fault
current.
2. Fault current is also used to select the breaker and other equipment as per
highest at that point.
3. Short circuit current = Driving voltage / Total Impedance
Lighting:
1. Lumen or Zonal cavity method
2. Point by point method
Φ= Eav A/ µ.d
Eav = Average illumination Level
µ = Utilization Factor
d = maintenance Factor
To insert fig 3 from cell phone for number fluorescent lamp
Fenestration Percentage = (Window area/ Floor Area) x 100
Here nomogram to insert
4.4.3.3 Method of use
The following steps shall be followed for the use of nomogram:
a) Step 1. Decide the desired illumination level depending upon the task illumination
requirement in the proposed room and read
the value of watt per m2 on the curve corresponding to the required illumination
level.
b) Step 2. Fix the vertical line corresponding to the given separation to height ratio of
opposite buildings on the abscissa. From the point of intersection of this vertical line
and the above curve move along horizontal and read the value of fenestration percent
on the left-hand ordinate.
c) Step 3. If the floor area is greater than 50 m2 or if it is less than 30 m2, the value of
watt per m2 as well as fenestration percent may be easily determined for adequate
daylighting and supplemental artificial lighting for design
NOTE: Diversity may be considered, if multiple units of water heater are there in an
individual house -hold installation, including individual dwelling of a block
1) For the purpose of the table, an instantaneous water heater is deemed to be a water
heater of any loading which heats water only while the tap is turned on a therefore
uses electricity intermittently.
2) It is important to ensure that the distribution boards are of enough rating to take
the total load connected to them without the application of any diversity.
After calculating the electrical load on the above basis, an overall load factor of 70 to 90
percent is to be applied to arrive at the minimum capacity of substation. A future
load may also be considered for substation sizing (see 3.3). The area required for
substation and transformer room for different capacities is given in Annex C for general
guidance. For reliability, it is recommended to split the load into more than one
transformer and also provide for standby transformer as well as multiple sources, bus-
section, etc.
The selection of the maximum size (capacity) of the transformer is guided by the short-
circuit making and breaking capacity of the switchgear used in the medium voltage
distribution system. Maximum size limitation is important from the aspect of feed to a
downstream fault.
In case of two transformers (dry type or transformers with oil quantity less than
2000 litre) located next to each other without intermittent wall, the distance between
the two shall be minimum 1500 mm for 11 kV, minimum 2000 mm for 22 kV and
minimum 2500 mm for 33 kV. Beyond 33 kV, two transformers shall be separated by
baffle wall of 4 h fire rating.
As a general rule, the kVAr rating of the capacitor should not exceed the no-load
magnetizing kVA of the motor.
In many cases there may be no choice available to the consumer, as most of the
licensees have formulated their policy of correlating the supply voltage with the
connected load or the contract demand. Generally, the supply is at 240 V single phase up
to 5 kVA,415/240 V 3-phase from 5 kVA to 100 kVA, 11 kV (or 22 kV) for loads up to 5
MVA and 33 kV or 66 kV for consumers of connected load or contract demand more
than 5 MVA.
240 V - Up to 5 KVA
415 V - 5 KVA to 100 KVA
11 KV (or 22 KV) - Up to 5 MVA
33 KV or 66 KV - more than 5 MVA
System fault level at a point in distribution systems is predominantly dependent on the
transformer size and its reactance. Parallel operation of transformers increases the
fault level.
Harmonics may lead to almost as much current in the neutral as in the phases. This
current is almost third, fifth, seventh and ninth harmonic.
To limit the harmonics, phase rectification devices may be considered at the planning
stage itself for the limits of harmonic voltage distortion. With the wide spread use of
thyristor and rectifier-based loads, there is a necessity of providing a full size neutral;
but this requirement is generally limited to the 3-phase 4-wire distribution generally in
the 415/240 V.
In final circuits where cable size of 16 mm2 and below are used, these shall be 4 core
cables only to avoid the possibility of neutral overload, (except for equipment such as
motors, heaters which offer balanced 3 phase load and do not require a neutral
connection. As a result, it is not desirable to use half-size neutral conductor as
possibility of neutral conductor overload due to harmonics is likely. Larger feeders (size
greater than 16 mm2) may revert to use 3½ core cables.
The colour of cores of non-flexible cables shall be in accordance with the following:
Note:
1. As alternative to the use of red, yellow or blue colour may be used, if desired in
large installations, up to the final distribution board.
The colour of cores of flexible cables and flexible cords shall be in accordance with the
following:
5.7.2 The current ratings of switches for domestic and similar purposes are 6 A, 16 A, 20
A and 25 A.
5.7.3 The current ratings of isolators and normal duty switches and composite units of
switches and fuses shall be selected from one of the following values:
16, 25, 32, 63, 100, 160, 200, 320, 400, 500, 630, 800, 1 000 and 1 250 A.
5.7.5 The current ratings of miniature circuit-breakers shall be chosen from the values
given below:
6, 10, 16, 20, 25, 32, 40, 50, 63, 80, 100 and 125 A.
5.7.6 The current ratings of moulded case circuit breakers shall be chosen from the
values given below:
100, 125, 160, 200, 250, 315, 400, 630, 800, 1 000, 1 250 and 1 600A.
5.7.7 The current ratings of air circuit-breakers shall be chosen from the values given
below:
630, 800, 1 000, 1 250, 1 600, 2000, 2500, 3200, 4000A and 6300 A.
5.7.8 The current ratings of the distribution fuse board shall be selected from one of the
following values:
6, 16, 25, 32, 63 and 100 A.
Lighting Demand:
Lighting demand for buildings should be considered as per type of building. Where
nothing is specified, for lighting demand of any type of building a maximum of
13 W/m2 of all built-up areas including balconies. Covered parking areas may be
considered at 3.23 W/m2 including balconies, service areas, corridors, etc, may be
considered with very basic diversity of 80 percent to 100 percent. Power
requirements shall be considered at least 55 W/m2 with an overall diversity not
exceeding 50 percent. These shall be excluding defined loads such as lifts, plumbing
system, fire-fighting systems, ventilation requirement, etc.
While incandescent lamps (GLS or halogen) does not require any control gear, other
light sources such as tubular fluorescent lamps, compact fluorescent lamps,
mercury vapour lamps, sodium vapour lamps, metal halide lamps and light emitting
diode (LED) lamps have non-linear characteristics and require specifically made
control gear for each type of lamp for their proper operation. space for such control
gear. There will be heat emission, introduction of harmonics etc, and they also consume
some energy.
Page
193
Page
196
table
2
Earthing
Substation
Testing of installation
Switchboard Testing:
1. Dielectric Testing, earthing continuity, Operation of protective device, Operation
of breaker, indicating lamp test, interlock test, closing and opening timing in case
of ATS., contact resistance of main and isolator contacts, specific gravity and
voltage of control battery.
Transformer Testing:
1. For any class of insulation, Polarization index should be greater than 1.5
2. Insulation Resistance and other as per good practice.
Cables Testing:
1. Insulation resistance before and after the tests.
2. The insulation resistance between each conductor and against earth shall be
measured. The insulation resistance varies with the type of insulation used and
with the length of cable. The following empirical rule gives reasonable guidance:
Insulation Resistance = (10 x Voltage, in KV) / Length, in km
3. Continuity Test
Motor and other equipment test:
the frame and between the windings shall be measured. Megger of 500 V or 1 000 V
rating shall be used. Star points should be disconnected. Minimum acceptable value of
the insulation resistance varies with the rated power and the rated voltage of the motor.
The following relation may serve as a reasonable guide:
R1 = 20 X En / 1000 + 2p
where
RI = insulation resistance in mega-ohms at 25°C.
En = rated phase to phase voltage.
P = rated power, in kW.
Aviation obstacle Light
S = Ki X Kc X L / Km
Insulation Resistance: