CCK Engineering & Construction Co.,ltd. SCHEDULE OF WORK REV.

00
Client ; Covestro (LEVEL I) DATE:15.05.62
PROJECT NAME :12" TOWER WATER PIPELINE WORK

ID Task Name Duration Start Finish Predecessors พ.ค. '62 มิ.ย. '62 ก.ค. '62 ส.ค. '62 ก.ย. '62 ต.ค. '62
13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21
1 Project Mile Stone 90 days จ 20/5/62 ศ 20/9/62
2 Engineering&Document 13 days จ 20/5/62 พ 5/6/62
3 Joint Running/pipe Cut length 3 days จ 20/5/62 พ 22/5/62
4 Materail Take off (Support Pipe/Steel Str.) 2 days จ 20/5/62 อ 21/5/62
5 WPS/PQR 3 days จ 20/5/62 พ 22/5/62
6 Lifting plan 7 days จ 20/5/62 อ 28/5/62
7 JSA 3 days จ 20/5/62 พ 22/5/62
8 ITP 3 days จ 20/5/62 พ 22/5/62
9 Package Test 10 days พ 23/5/62 พ 5/6/62 8
10 Procurement 7 days พ 22/5/62 พ 30/5/62
11 Material for support/Steel Str. 7 days พ 22/5/62 พ 30/5/62 4
12 Constrution 90 days จ 20/5/62 ศ 20/9/62
13 WQT 7 days พ 23/5/62 ศ 31/5/62 5,8
14 Scaffolding installation BY Covestro 30 days จ 20/5/62 ศ 28/6/62
15 Pipe sandblasting +2nd 6 days ศ 31/5/62 ศ 7/6/62 11
16 Pipe shop Fabrication (Elbow to pipe etc.) 800 DB. 12 days จ 10/6/62 อ 25/6/62 15,3
17 Pipe support fabrication 7 days ศ 31/5/62 จ 10/6/62 11
18 Steel Structure fabrication 10 days อ 11/6/62 จ 24/6/62 17
19 Pipe support/Steel str. Sandblasting+top 7 days อ 25/6/62 พ 3/7/62 18
20 Pipe support/Steel Str. Installation 14 days จ 1/7/62 พ 18/7/62 14,6
21 Pipe laying on rack 14 days จ 1/7/62 พ 18/7/62 14
22 Pipe fit-up & Weld filed Joint 35 days พ 10/7/62 อ 27/8/62 21FS-7 days,19
23 NDE 15 days พ 14/8/62 อ 3/9/62 22FF+5 days
24 Pressure test 3 days พ 4/9/62 ศ 6/9/62 23
25 Flushing 7 days จ 9/9/62 อ 17/9/62 24
26 Painting weld joint & touch up 7 days พ 4/9/62 พ 12/9/62 23
27 Pipe Tie-In / Modify 2 days พ 18/9/62 พ 19/9/62 25
28 Leakage Test 1 day ศ 20/9/62 ศ 20/9/62 27
29 Hand over Document 0 days พ 2/10/62 พ 2/10/62 28FS+7 days 2/10

Task Project Summary Manual Task Start-only Deadline Manual Progress

Project: sch01 Split Inactive Task Duration-only Finish-only Critical

Date: พ 15/5/62 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Progress