Sei sulla pagina 1di 103

POLYPROPYLENE

UNIT
About Instructor …

 Current job position:

 Working experiences:
EMERGENCY EVACUATION INSTRUCTION
Whenever you hear the building alarm or are informed of a
general building emergency:
 Leave the building immediately, in an orderly fashion;
 Do not use elevators;
 Follow quickest evacuation route from where you are;
 If the designated assembly point/area is unsafe or blocked due to
the emergency, proceed to the alternate assembly point;
 Report to your Work Area Rep at the assembly point to be checked
off as having evacuated safely;
 Specific safety requirements for TODAY.

Today: NO testing of fire alarm systems


COURSE OBJECTIVES

When you complete this module you will be able:

 To understand the feed and products characteristics; PP process

description;

 To assess the influence of operating parameters on a unit

performance through an analysis of operation case study.

 To learn about potential deficiencies and troubleshooting.

 To acquire the best practices for unit start-up, normal operation


COURSE OUTLINE

 Total duration: 2 days;

 Lecture: 2 days;

 Practice on dynamic simulator: 2 days;


COURSE ASSESSMENT

Lecture:
 The multiple-choice (knowledge based questions) section of the test
is scored based on the number of questions you answered correctly;
 Multi-choice test : 40 questions
 Passing grade: 36/ 40;
 No additional points are subtracted for questions answered
incorrectly;
 Even if you are uncertain about the answer to a question, it is better
to guess than not to respond at all.

Dynamic simulator:
 Passing grade: Implement an extract operation procedure for 10
minutes and troubleshoot successfully 2 scenarios in simulator;
OUTLINE

1. Feed Characteristics
2. Process Description
3. Start-up Preparation
4. Operation Cases Study
1. FEED CHARACTERISTICS

 Polypropylene: (PP), is a thermoplastic polymer used in a wide

variety of applications including packaging and labeling, textiles

(e.g., ropes, thermal underwear and carpets), stationery, plastic

parts and reusable containers of various types;

 An addition polymer made from the monomer propylene, it is

rugged and unusually resistant to many chemical solvents, bases

and acids
1. FEED CHARACTERISTICS

Polypropylene:

 Chemical and physical properties

 Most commercial polypropylene is isotactic and has an

intermediate level of crystallinity between that of low-density

polyethylene (LDPE) and high-density polyethylene (HDPE).

 Polypropylene is normally tough and flexible, especially when

copolymerized with ethylene. This allows polypropylene to be used

as an engineering plastic, competing with materials such as ABS.


1. FEED CHARACTERISTICS

Polypropylene:

 Polypropylene is reasonably economical, and can be made

translucent when uncolored but is not as readily made transparent

as polystyrene, acrylic, or certain other plastics.

 It is often opaque or colored using pigments. Polypropylene

has good resistance to fatigue.


1. FEED CHARACTERISTICS

Polypropylene:

 The melting point of polypropylene occurs at a range, so a

melting point is determined by finding the highest temperature of

a differential scanning calorimetry chart.

 Perfectly isotactic PP has a melting point of 171°C (340°F).


1. FEED CHARACTERISTICS

Polypropylene:

 Chemical and physical properties

 Commercial isotactic PP has a melting point that ranges from 160

to 166°C (320 to 331°F), depending on atactic material and

crystallinity.

 Syndiotactic PP with a crystallinity of 30% has a melting point of

130°C (266°F).
1. FEED CHARACTERISTICS

Polypropylene:

 The melt flow rate (MFR) or melt flow index (MFI) is a measure

of molecular weight of polypropylene.

 The measure helps to determine how easily the molten raw

material will flow during processing.


1. FEED CHARACTERISTICS

Polypropylene:

 Polypropylene with higher MFR will fill the plastic mold more

easily during the injection or blow-molding production process.

 As the melt flow increases, however, some physical properties,

like impact strength, will decrease.

 There are three general types of polypropylene: homopolymer,

random copolymer, and block copolymer.

 The comonomer is typically used with ethylene.


1. FEED CHARACTERISTICS

Polypropylene:

 Ethylene-propylene rubber or EPDM added to polypropylene

homopolymer increases its low temperature impact strength.

 Randomly polymerized ethylene monomer added to polypropylene

homopolymer decreases the polymer crystallinity and makes

the polymer more transparent


1. FEED CHARACTERISTICS

Polypropylene:
Degradation
 Polypropylene is liable to chain degradation from exposure to heat
and UV radiation such as that present in sunlight.
 Oxidation usually occurs at the tertiary carbon atom present in
every repeat unit.
 A free radical is formed here, and then reacts further with oxygen,
followed by chain scission to yield aldehydes and carboxylic acids.
 In external applications, it shows up as a network of fine cracks
and crazes that become deeper and more severe with time of
exposure.
1. FEED CHARACTERISTICS

Polypropylene:

 For external applications, UV-absorbing additives must be used.

Carbon black also provides some protection from UV attack.

 The polymer can also be oxidized at high temperatures, a

common problem during molding operations.

 Anti-oxidants are normally added to prevent polymer degradation.

 Microbial communities isolated from soil samples mixed with starch

have been shown to be capable of degrading polypropylene


1. FEED CHARACTERISTICS
Polypropylene:
Synthesis
An important concept in understanding the link between the structure of
polypropylene and its properties is tacticity. The relative orientation of each
methyl group (CH3 in the figure) relative to the methyl groups in neighboring
monomer units has a strong effect on the polymer's ability to form crystals

Isotactic
Tacticity

Syndiotactic
Tacticity

Atactic
Tacticity
1. FEED CHARACTERISTICS

Polypropylene:
Synthesis
 A Ziegler-Natta catalyst is able to restrict linking of monomer
molecules to a specific regular orientation, either isotactic, when all
methyl groups are positioned at the same side with respect to the
backbone of the polymer chain, or syndiotactic, when the
positions of the methyl groups alternate.
1. FEED CHARACTERISTICS

Polypropylene:
Synthesis
 Commercially available isotactic polypropylene is made with
two types of Ziegler-Natta catalysts.
 The first group of the catalysts encompasses solid (mostly
supported) catalysts and certain types of soluble metallocene
catalysts.
 Such isotactic macromolecules coil into a helical shape; these
helices then line up next to one another to form the crystals that
give commercial isotactic polypropylene many of its desirable
properties
1. FEED CHARACTERISTICS
Polypropylene:
Synthesis
 Modern supported Ziegler-Natta catalysts developed for the
polymerization of propylene and other 1-alkenes to isotactic
polymers usually use TiCl4 as an active ingredient and MgCl2
as a support.
 The catalysts also contain organic modifiers, either aromatic acid
esters and diesters or ethers.
 These catalysts are activated with special cocatalysts containing
an organoaluminum compound such as Al(C2H5)3 and the
second type of a modifier.
1. FEED CHARACTERISTICS
Polypropylene:

 The catalysts are differentiated depending on the procedure used

for fashioning catalyst particles from MgCl2and depending on

the type of organic modifiers employed during catalyst

preparation and use in polymerization reactions.


1. FEED CHARACTERISTICS
Polypropylene:

 Two most important technological characteristics of all the

supported catalysts are high productivity and a high fraction of the

crystalline isotactic polymer they produce at 70–80°C under

standard polymerization conditions.

 Commercial synthesis of isotactic polypropylene is usually

carried out either in the medium of liquid propylene or in gas-

phase reactors
1. FEED CHARACTERISTICS
Polypropylene:

Synthesis

 Commercial synthesis of syndiotactic polypropylene is carried

out with the use of a special class of metallocene catalysts.

 They employ bridged bis-metallocene complexes of the type

bridge-(Cp1)(Cp2)ZrCl2 where the first Cp ligand is the

cyclopentadienyl group, the second Cp ligand is the fluorenyl

group, and the bridge between the two Cp ligands is -CH2-CH2-,

>SiMe2, or >SiPh2.
1. FEED CHARACTERISTICS
Polypropylene:

Synthesis

 These complexes are converted to polymerization catalysts by

activating them with a special organoaluminum cocatalyst,

methylaluminoxane (MAO)
1. FEED CHARACTERISTICS

Feed characteristics in Dung Quat Polypropylene Plant:

 PP plant uses two raw materials, propylene and hydrogen which

are supplied from the Refinery.


1. FEED CHARACTERISTICS

Feed characteristics in Dung Quat Polypropylene Plant:

 Propylene and hydrogen from the refinery will be treated in

propylene drying/COS removal system and hydrogen purification

system to meet the following properties

No. Item Specifications


1 Hydrogen Content 95 mol% (min)
2 Methane 5 mol% max.
3 Oxygen 5 mol ppm max.
4 Water 5 mol ppm max.
5 Carbon Monoxide 5 mol ppm max.
6 Carbon Dioxide 5 mol ppm max.
7 Hydrogen Sulfide 5 mol ppm max.
1. FEED CHARACTERISTICS
Feed characteristics in Dung Quat Polypropylene Plant
No. Item Specifications
1 Propylene Content 99.5 mol% (min)
2 Methane 100 mol ppm max.
3 Ethane 200 mol ppm max.
4 Ethylene 100 mol ppm max.
5 Propane 0.5 mol% max.
6 Butane & Butenes 10 mol ppm max.
7 Acetylene 5 mol ppm max.
8 Methylacetylene 5 mol ppm max.
9 Propadiene 5 mol ppm max.
10 1,3-Butadiene 5 mol ppm max.
1. FEED CHARACTERISTICS
Feed characteristics in Dung Quat Polypropylene Plant
No. Item Specifications
11 Total of 7, 8, 9, 10 10 mol ppm max.
12 Oxygen 5 mol ppm max.
13 Hydrogen 5 mol ppm max.
14 Carbon Monoxide 0.1 mol ppm max.
15 Carbon Dioxide 4 mol ppm max.
16 Carbonyl Sulfide 0.05 mol ppm max.
17 Total Sulfur 1 wt ppm max.
18 Water 2 mol ppm max.
19 Oxygenated organic compounds 5 mol ppm max.
(methanol)
20 Arsine 0.03 wt ppm max.
2. PROCESS DESCRIPTION
The Mitsui “Hypol” polypropylene process has tended to make more specialty
resins, including TPO’s and very high impact copolymers. With multiple
reactors in series, the unit costs are typically higher than the larger capacity
single reactors
2. PROCESS DESCRIPTION

Feedstock and Raw Materials Preparation


 Co-catalyst (concentrated TEAL, 100% approx.) and donor-
stereomodifier are supplied in vendor containers (drums, etc.)
to feed drums with further metering to catalyst activation
section.
 Solid Ti-Mg catalyst HY-HS of the 4-generation is supplied in
drums from the chemicals store to catalyst preparation and
metering section.
 Solid Ti-Mg catalyst shall be dispersed in the blend of mineral oil
and grease (thickener) and further metered to the catalyst
activation section.
2. PROCESS DESCRIPTION

Feedstock and Raw Materials Preparation

 Mineral oil shall be discharged from the drums to oil feed

drum.

 From this drum mineral oil shall be used for TEAL piping

washing and degassing and for jacketed vessel with agitator

filling.

 Mineral oil from this jacketed vessel with agitator is supplied to

the catalyst preparation and metering section.


2. PROCESS DESCRIPTION

Feedstock and Raw Materials Preparation


 Grease from the drums is also discharged to jacketed vessel with
agitator with further supply to the catalyst preparation and metering
section.
 Additive for catalyst de-activation and washing oil degassing is
to be discharged to two feed drums.
 From the first drum it shall be supplied to low pressure
propylene washing tower and rich oil receiver, and from the second
drum it shall be supplied to the jacketed pipe provided for discharge
of polypropylene slurry in propylene from the reactor to high
pressure separator
2. PROCESS DESCRIPTION

Feedstock and Raw Materials Preparation


 Grease from the drums is also discharged to jacketed vessel with
agitator with further supply to the catalyst preparation and metering
section.
 Additive for catalyst de-activation and washing oil degassing is
to be discharged to two feed drums.
 From the first drum it shall be supplied to low pressure
propylene washing tower and rich oil receiver, and from the second
drum it shall be supplied to the jacketed pipe provided for discharge
of polypropylene slurry in propylene from the reactor to high
pressure separator
2. PROCESS DESCRIPTION

Bulk Polymerization

 In the catalyst activation section, the catalyst suspended in oil and

grease is mixed with co-catalyst and donor and is further mixed

with small portion of liquid propylene for pre-polymerization in small

loop reactor.

 Polymerization is performed in liquid phase intwo loop reactors in

series.
2. PROCESS DESCRIPTION

Bulk Polymerization

 Reactors are of the same volume and operated under the same

conditions, as follows:

 Pressure – 4.5 MPa, approx.

 Temperature – 80oC

 Total residence time – 1.5 hours, approx.


2. PROCESS DESCRIPTION

Bulk Polymerization
 Axial pumps are installed at the bottom section of the reactor.
 Reaction blend circulation by these pumps provides a proportional
temperature profile over the whole length of the reactors.
 Heat removal in the reactors is provided via demineralized
water circulation in the reactor jackets.
 Hydrogen containing gas from the battery limits is fed to the
hydrogen recovery (up to 99.5% vol.) and compression section
with its further supply to propylene feed line upstream the
reactors.
2. PROCESS DESCRIPTION

Bulk Polymerization

 Liquid propylene from the propylene feed drum and hydrogen as

well are supplied to the both reactors.

 Some portion of propylene shall be evaporated upstream the

reactor for pressure control in the surge drum.

 This drum is provided to fill the reactors completely and to

avoid pressure swing in the reactors.


2. PROCESS DESCRIPTION

Bulk Polymerization

 Blend from the catalyst activation section is injected to the

propylene stream that is fed to the first reactor only.

 Polymer slurry from the first loop reactor feeds directly to the

second loop reactor to finalize polymerization.

 Polypropylene slurry from the second reactor is discharged via

jacketed pipe to the high-pressure separator for polymer

separation from the recycle propylene.


2. PROCESS DESCRIPTION

Polymer Degassing and Propylene Recovery

 High-pressure separator is provided to separate polymer from the

recycle propylene.

 Polymer resin from the separator is discharged to the filter for

polymer degassing.

 The resin is further supplied to the steaming section for

polymer steam-out.
2. PROCESS DESCRIPTION

Polymer Degassing and Propylene Recovery

 Stabilization additives shall be injected into the polymer resin prior

to steam-out.

 Filter overhead gas is fed to washing scrubber where oil washing is

provided for fines removal in recycle gas.

 Specific additive shall be added to the oil for TEAL traces

removal.
2. PROCESS DESCRIPTION

Polymer Degassing and Propylene Recovery

 Upon saturation with polymer rich washing oil shall be replaced

with fresh one. Rich oil is pumped out to recovery.

 Scrubber off-gas is compressed, mixed with high-pressure

separator off-gas and supplied to the propylene recovery tower.

 Tower overhead vapors are condensed and recycled to the

tower as a reflux.
2. PROCESS DESCRIPTION

Polymer Degassing and Propylene Recovery

 Balanced recovered propylene is collected in the receiver

where fresh purified propylene is to be fed.

 Propylene from the receiver is fed to the polymerization reactors.

 Propylene recovery tower bottoms are supplied to the polymer filter

inlet via jacketed pipe.


2. PROCESS DESCRIPTION

Polymer Steaming and Drying

 Downstream the filter polymer resin by gravity flow is supplied

to the polymer steaming section where catalyst reminder is

deactivated and entrained hydrocarbons are steamed out by

direct steam.

 Vapor and gas mixture from the steaming section is supplied to

water scrubber for steaming and water washing.

 Water condensate and steamed hydrocarbonsare fed to the

separator from scrubber draw-off tray.


2. PROCESS DESCRIPTION

Polymer Steaming and Drying

 Liquid from the separator is recycled to the scrubber and vapor

and gas phase is to be combined with scrubber overhead

monomers and to be supplied to water cycle compressor.

 Cooled downstream water cycle compressor vapor and gas

phase shall be either routed to the flare system or recycled to

the process after drying.


2. PROCESS DESCRIPTION

Polymer Steaming and Drying

 Organic liquid separated in the water cycle compressor (oligomers)

shall be discharged into drums after separation.

 Wet polymer from the steaming section is conveyed to dryingby

circulating nitrogen.

 Dried polymer is supplied by closed nitrogen transportation system

to the surge silo.


2. PROCESS DESCRIPTION

Polymer Steaming and Drying

 Wet nitrogen from the polymer drying section shall bewashed

and cooled in the scrubber.

 Then it is recycled to the drying section by blower via preheater.

 Water is supplied to the scrubber for nitrogen washing.

 Water condensate with polymer traces is discharged from the

scrubber bottom to the waste water sump.


2. PROCESS DESCRIPTION

Emergency Discharge System

 Emergency discharge from the reactor safety valves is routed to

steam jacketed high pressure emergency blow-down drum.

 Discharges from the reactors shall be routed to low-pressure drum

when shutdown is required.

 Polymer powder collected in the high-pressure drum is transferred

to the low pressure drum by steam and nitrogen mixture.


2. PROCESS DESCRIPTION

Emergency Discharge System

 After polymer powder de-activation by circulating steam and

nitrogen mixture, the powder shall be discharged to containers.

 Gas vents from both drums are discharged to the Refinery flare

system via cyclone.


2. PROCESS DESCRIPTION

Refrigeration Unit

 Chilled water (diethyleneglycol solution indemineralized water)

is prepared at the package supplied refrigeration unit where

propylene is used as a cooling agent.

 Then chilled water is collected in the receiver under nitrogen

blanket (to prevent corrosion) and pumped out to consumers.


2. PROCESS DESCRIPTION

Condensate Return

 All steam condensate from the PP Plant is collected incondensate

receiver and further pumped out to the battery limits.

 Some portion of condensate is cooled and supplied for expansion

vapors condensing.
2. PROCESS DESCRIPTION

Washing Oil Recovery

 This section is under intermittent operation.

 Mineral oil contaminated with TEAL is collected in the recovery

vessel, liquid additive for TEAL neutralization is supplied to this

vessel as well.

 Recovered oil is routed to incineration.


2. PROCESS DESCRIPTION

Feedstock Preparation

 Polymer grade propylene (99.6% wt.) is pumped from the

intermediate storage to the feed preparation section.

 In this section propylene is dried at molecular sieves for water

removal and treated by catalyst for COS traces removal.

 These treatments are required, as polymerization catalyst is very

sensitive to certain impurities in the feedstock.


2. PROCESS DESCRIPTION

Silos, Extrusion, Pelletizing, Homogenization and Storage

 Polymer from the surge silo is metered to blender. Solid and liquid

additives are also metered to the blender continuously.

 Polypropylene with additives from the blender is fed to the

extruder.

 Fusible additives can be added to the extruder as well, if required.

 In the extruder polymer and additives are homogenized, gelled and

filtrated.
2. PROCESS DESCRIPTION

Silos, Extrusion, Pelletizing, Homogenization and Storage

 Pelletizing is performed in subaqueous pelletizer.

 Pellets are supplied by circulating water (demin water) to

separator and further to air dryer.

 Dry pellets are fed by gravity to the classifier.


2. PROCESS DESCRIPTION

Silos, Extrusion, Pelletizing, Homogenization and Storage

 On-spec polymer pellets are supplied to the feed drum with

further air

 conveying to the homogenization and storage silos.

 Off-spec pellets are collected in the container.

 Water separated from the polymeris collected in the drum with

further recycle to the pelletizer via cooler.


2. PROCESS DESCRIPTION

Silos, Extrusion, Pelletizing, Homogenization and Storage

 Polymer homogenization and storage silos are provided to get

homogeneous polymer batches.

 They serve as a buffer between production sections and bagging

lines. Storage capacity enables to store the product within 5 days

maximum.
2. PROCESS DESCRIPTION

Bagging and Palletization Section

 Commercial polypropylene is bagged automatically into 25 kg PE

bags.

 The bags are automatically palletized and wrapped by PE

shrink film and transported to the warehouse by a forklift.

 The PP Plant comprises facilities for PE bags and shrink film

production.
2. PROCESS DESCRIPTION

Local Effluent Treatment

 Condensate and industrial and rainwater effluents, as well as floor

washing effluents are collected in the waste water sump.

 Water from the sump after oil and polymer powder removal is

to be pumped out to the Refinery treatment facilities.


2. PROCESS DESCRIPTION
Effluents Disposal

 Effluents disposal section covered by the PP Plant is provided

for effluents incineration.

 Spent oil from the PP Plant and non-diluted laboratory wastes

(acetone, xylene, etc.) are to be combusted in the incinerator

on intermittent base.

 Effluents are to be delivered to the incinerator in bottles by trucks.

 Flue gas filtration at the bag filter is provided for environmental

protection purpose prior to flue gas discharge to incinerator

stack.
3. START-UP PREPARATION

Outlines
 Each equipment at the plant is run for trial prior to the start-up of the
plant.
 When the construction of the plant progresses to such a stage that
various pieces of equipment can undergo trial run, it is necessary to
first introduce utilities into the plant so as to facilitate the
preparations for this trial run.
 The trial run is the best opportunity for plant operators to become
familiar with pieces of equipment and their operation
procedures.
 For this reason, it is desirable that the operators make
preparations in person for plant start-up.
3. START-UP PREPARATION

Outlines

The following are the precautions required for the preparations:

 Inspections to be made at the time of completion of plant

construction.

 The above inspections should be carried out in line with P &

ID and construction drawings before conducting the cleaning and

airtight test of pieces of equipment.


3. START-UP PREPARATION

Outlines

 These inspections are to ascertain whether or not:

a) The pipings are installed exactly as specified in P & ID

b) There is any problem as to the operability of equipment

c) The materials and parts of pipings are proper

d) The heat insulation of pieces of equipment, etc. has been properly

provided

e) Measuring instruments have been installed exactly as specified in

P & ID.
3. START-UP PREPARATION

Cleaning
 The following are the items to which attention should be paid during
cleaning:
a) Pieces of equipment and pipings are cleaned in such a manner
that scrapings and the like can be collected in drums. For
this reason, inspect the drum interiors after the cleaning to see
whether or not there are any scrapings or the like left there.
b) In cleaning the seal oil line, skip the mechanical seals of
pieces of rotary equipment which use seal oil.
c) In order to prevent control valves from being fouled with
dirt during the cleaning, temporarily remove these valves or
insert a blind plate into their flanges.
3. START-UP PREPARATION

Cleaning
The following are the items to which attention should be paid during
cleaning:
d) Do not use water for cleaning catalyst-measuring instruments,
pieces of equipment and lines from which it is difficult to completely
remove water. If water should be used for cleaning any equipment
or line, completely remove the water from it.
e) Thoroughly clean the Catalyst Preparation Section and any
section where product polymer is handled.
f) In cleaning the heat exchangers, pay attention to the smudges on
both shell and tube sides.
3. START-UP PREPARATION

Cleaning
g) It is necessary to surely clean the lines mentioned here.
i) Seal oil lines
ii) Propylene flushing lines
iii) Connection lines for process gas chromatographs and moisture
analyzers
iv) Connection lines for pieces of equipment which handle AT-CAT
v) Suction lines for pumps and blowers
3. START-UP PREPARATION

Airtight test

The following are the items which demand attention particularly at the

time an airtight test.

a) Confirmation of the design pressures of equipment and piping

prior to an airtight test

b) Sure insertion of a blind plate at a portion where two lines of

different design pressures join


3. START-UP PREPARATION

Airtight test

Never carry out an airtight test with equipment isolated with valves

only. Also, open the vent and drain valves of lower-pressure

equipment connected to the portion which is to be subjected to an

airtight test.

This is because if the compressed air for airtight test should leak into

any lower-pressure equipment, such air can be released into the

atmosphere to prevent the equipment from being over-pressurized.


3. START-UP PREPARATION
Airtight test

c) When an airtight test is conducted on any rotary equipment, the

seal oil system should be put in service when possible, and the

test be implemented after seal oil is supplied to the rotary

equipment, with a view to preventing its mechanical seal from

being damaged.

d) How to raise pressure

The pressures of equipment and piping should be raised by stages.

e) First, raise the pressure to the 50% level of the pressure designed

for airtight test to see whether or not there is any leakage.


3. START-UP PREPARATION

Airtight test

f) When there is no leakage, raise the pressure by stages by 10% of

the air tight test pressure at a time.

g) Every time the pressure is raised to a given level, apply soapy

water or the like to the equipment and piping to see whether or not

they have any leakage, and then raise the pressure to their

specified target pressure to confirm that they have no leakage.


3. START-UP PREPARATION

Confirmation of performance of rotary equipment


The performance of rotary equipment should be confirmed prior to
plant startup. The following are the items which require attention at
the time of this confirmation.
a) Confirm that all pieces of rotary equipment have been
installed precisely in line with the instructions given by their
respective vendors.
b) Install temporary strainers to remove weld scraps, foreign matters
and the like from rotary equipment for the purpose of damage
prevention.
3. START-UP PREPARATION

Confirmation of performance of rotary equipment

c) Confirm beforehand the differences in shaft horsepower,

pressure rise and temperature rise which stem from the difference

in physical property of fluid.

d) In order to accurately grasp the performance of pumps,

compressors and blowers, obtain the necessary information

and guidance from the respective vendors beforehand.


3. START-UP PREPARATION
Instrumentation and electricity

 Regarding the instrumental and electrical installations, put

necessary sequence control systems in service, and confirm

their performance during the simulation of normal operation.

 Prior to starting an airtight test and also to performance

confirmation test of rotary equipment, put both measuring and

controlling instruments in service, and test use these instruments

to ascertain whether or not they function properly.


3. START-UP PREPARATION
Instrumentation and electricity

 Put alarms and interlock systems in service to closely ascertain

whether or not they function properly at their respectively

specified set points.


3. START-UP PREPARATION
Safety system

a) Prior to their installation, ascertain by the use of a testing device

whether or not safety valves function properly.

b) Confirm that all XVs open and close normally.

c) Conduct a test on alarms to see whether or not they function

normally.

d) Conduct a test on flammable gas detectors and fire-fighting

facilities to see whether or not these detectors and facilities

function normally.
3. START-UP PREPARATION
Safety system

e) Prepare documents which graphically show the following

information to communicate such information to those who

concern for the sake of the safety at the plant. Meanwhile, it is

desirable to train operators and personnel concerned in plant

safety when possible.


3. START-UP PREPARATION

Safety system

f) Block diagram of Emergency Shut Down (ESD) procedures

g) The locations of fire extinguishers, fire hydrants and ESD valves

h) Locations of emergency lights

i) Comprehensive table of safety valves and rupture disks

j) Distribution diagram of power supply

k) Lists of measuring instruments and alarms

l) Distribution diagrams of instrumental- and back-up power supplies

m) Diagram of waste-water system


3. START-UP PREPARATION

Introduction of utilities

The utilities referred to here include:

a) Fire-fighting water

b) Cooling Water (CW)

c) Steam

d) Demineralized Water (DW)

e) Nitrogen

f) Instrument Air (IA)

g) Electricity
3. START-UP PREPARATION
Plan for plant start-up preparations
The following should be taken into consideration in planning
plant start-up preparations.

a) Introduction of utilities should be begun with IA, CW, nitrogen and


steam in this order.

b) When utilities are introduced in the course of plant


construction, safety measures inclusive of the following should be
taken.

i) Make necessary isolation with blind plates.


ii) Never close nor open any valve.
3. START-UP PREPARATION
Plan for plant start-up preparations
The following should be taken into consideration in planning
plant start-up preparations.

c) Cleaning of the CWS, CWR and DW lines should be


conducted before the trial run of rotary equipment.

d) Since seal oil is required for the trial run of rotary equipment, it is
desirable to operate the seal oil system if possible before such
equipment is put to test.
3. START-UP PREPARATION

Nitrogen purge

Precautions required for nitrogen purge

a) In order to properly conduct nitrogen purge, it is important to

decide from where nitrogen should be introduced, where nitrogen

purge be conducted and whether relevant valves be closed or

opened, in accordance with the shape of equipment.

b) Nitrogen purge procedures vary with the analytical value of

oxygen concentration at the place where this purge is intended.


3. START-UP PREPARATION

Nitrogen purge

c) Supply of refrigerated water to equipment which is being purged with

nitrogen causes the equipment to be dewed internally, thus possibly

hindering nitrogen purge. Hence, refrigerated water should be

supplied after completion of nitrogen purge.

d) Nitrogen purge should be conducted in such a manner that oxygen,

water or the like will not be left in the pocketed areas of equipment

and drain valves on its associated lines.


3. START-UP PREPARATION

Nitrogen purge

e) While conducting nitrogen purge, drain and vent valves should be

closed or opened so that equipment, lines, valves, etc. will not

be left unpurged with nitrogen.


3. START-UP PREPARATION

Nitrogen purge
Completion of nitrogen purge
a) Nitrogen purge is deemed completed when as a result of oxygen
concentration analysis, this concentration in equipment is
ascertained to have become lower than the lower explosive limit,
by making reference to the material relative to the explosive
ranges of multiple-component systems
b) Measure oxygen concentrations and dew points at given locations.
When the values so measured meet the respective specified
values, close the valves at the places where nitrogen purge has
been performed. Thus the nitrogen purge is concluded.
3. START-UP PREPARATION

Nitrogen purge
Completion of nitrogen purge
c) The following are the criteria by which to judge the
completion of nitrogen purge.
Item Criterion
Dew point in equipment -40°C or lower
Oxygen conc. in equipment 0.2 vol% or lower
Note: Unless otherwise mentioned.
For gas analysis, take sample gas at three or more spots of the place
where nitrogen purge has been conducted.
3. START-UP PREPARATION

Nitrogen purge
d) Measures to be taken after completion of nitrogen purge. When
nitrogen purge is completed, blanket pieces of equipment with
nitrogen with their pressures kept at 0.2 to 1 Kg/cm2g so that
oxygen, water, etc. will not enter them.
Note: Nitrogen purge procedures and a rough diagram for nitrogen
purge are shown as an example in the ensuing page; however,
these diagram and procedures should be established by taking into
consideration the actual plant at the time of its completion.
3. START-UP PREPARATION
Introduction of utilities

 Blowdown and Flare system

 When a safety device is actuated due to abnormality occurring to

any equipment at the time during the start-up, normal operation or

shutdown of the plant, the blowdown and flare system serve to

release the flammable gases discharged from the safety devices.


3. START-UP PREPARATION
Introduction of utilities

 Therefore, the aforesaid system is first put in service prior to

introducing flammable gases into B/L. When the airtight test and

nitrogen purge of the blowdown and flare lines are completed and

the flare system commissioned and ready for use, connect the flare

line to the outside-B/L flare line and immediately start to use these

lines
3. START-UP PREPARATION

Introduction of utilities

 Cooling water (CWS and CWR)

 Cooling water is used for removing the heat of polymerization

reaction and for cooling pieces of equipment. CWS is introduced

from outside B/L and CWR is discharged back to B/L.

 After an airtight test is conducted on CWS and CWR lines

and CWS supply valve for each CWS user is closed, the CWS

receipt B/L valve is opened to introduce CWS into B/L.


3. START-UP PREPARATION

Introduction of utilities

 After the gas in the CWS header line is discharged, the B/L valve

for CWR is opened to discharge CWR. CWS is supplied to each

CWS user to discharge gas in its CWS line. The specified set

points of PT-0121A LL, PT-0121B LL and FQI-0121 L are set on

them respectively.
3. START-UP PREPARATION

Introduction of utilities

 Demineralized water (DW)

 After mechanical completion and cleaning of DW line, the DW

supply valve for each DW user is closed. Then, the B/L valve for

DW is opened to introduce DW into B/L.

 DW so introduced is supplied to its users in order one by one to

discharge the gas in their DW lines. The leak test is performed by

DW when DW is introduced inside B/L.


3. START-UP PREPARATION

Introduction of utilities

 Low pressure steam (SL)

 Low pressure steam (SL) is supplied from outside B/L. Steam

condensate (CL) of SL generated by SL users are collected into

the steam condensate drum (D-606) and transferred to the CL

users inside B/L and/or outside B/L.

a) Preparations for SL introduction

b) Introduction of SL

c) Put steam condensate system in service


3. START-UP PREPARATION

Introduction of utilities

Nitrogen (HN, MN and LN)

Nitrogen is produced inside B/L also to meet the requirement and

back-up. HN is also produced with nitrogen generation PKG.

a) Preparations and confirmation

b) Nitrogen Purge
3. START-UP PREPARATION

Introduction of utilities

c) Open and close the nitrogen supply valves of each equipment

to which a nitrogen supply line is connected to conduct nitrogen

purge on this nitrogen supply line.

d) Completion of nitrogen purge


3. START-UP PREPARATION

Introduction of utilities

 Instrument air (IA)

 IA is supplied from outside B/L and used for various

instruments.

 After the airtight test of the IA line is completed, IA is introduced into

B/L as occasion demands


3. START-UP PREPARATION

Introduction of utilities

 Plant air (PA)

 PA is supplied from outside B/L as Instrument air (IA) and

used for various equipments.

 After the airtight test of the PA line is completed, PA is introduced

into B/L as occasion demands


3. START-UP PREPARATION

Propylene circulation operation

 Start-up sequence of the units with propylene

 Upon completion of the preliminary operations, the plant units shall

be arranged for the start-up. The units shall be started-up in the

following sequence.
a) Blowdown
b) Reactor feed
c) Degassing and monomer recovery
d) Reactors
e) Steaming and drying
f) Catalyst and cocatalyst storage and metering
3. START-UP PREPARATION

Propylene circulation operation


 Propylene circulation operation is performed in preparation for start-
up.
 This mode is also used during the time of temporary catalyst
outages and for a short period before plant shutdown.
 Fresh and recycle propylene is supplied to the loop reactors
from the propylene feed drum (D-302) and circulated with the
loop reactor pumps (P-201/P-202).
 The pressure of loop reactors is maintained with the reactors
surge drum (D-202). The loop reactors are operated liquid full at all
times
3. START-UP PREPARATION

Propylene circulation operation

 The propylene from the loop reactors is sent to the transfer line

dryer (E-307). Here the liquid propylene is heated and vaporized

before it enters the flash drum (D-301).

 A small portion of vapor is directly to the recycle gas filter (F-301),

while the main flow goes overhead from D-301 to the recycle

propylene scrubber (T-301) for recovery.

 Vapor propylene exits the top of F-301 and enters the low pressure

propylene scrubber (T-302).


3. START-UP PREPARATION

Propylene circulation operation

 The propylene gas from the top of T-302 is compressed with the

recycle gas compressor (PK-301) and transferred to the T-301.

 Liquid propylene for scrubbing of T-301 comes from the boot

of the propylene condenser (E-301) and enter the top of T-301.

 Liquid propylene from the bottom of T-301 is discharged to F-301

passing through double tube vaporizers.

 Vapor propylene leaves the top of T-301, is condensed and

pumped back to D-302 for recycle back through the system.


4. OPERATION CASES STUDY

Propylene circulation operation

The following refers to some troubleshooting cases in Dung Quat

Polypropylene Plant sections

1. AT-CAT Storage and Feeding

2. OF-CAT Storage and Feeding

3. Catalyst Dispersion Preparation and Metering

4. Prepolymerization and Polymerization


4. OPERATION CASES STUDY

Propylene circulation operation

The following refers to some troubleshooting cases in Dung Quat

Polypropylene Plant sections

5. Degassing and Monomer Recovery

6. Low Pressure Flash and Monomer Compression

7. Reactor Feed System

8. Polymer finishing
THANK YOU

www.pvmtc.com.vn

Potrebbero piacerti anche