EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS

(Requiring EIS or EIS threshold EPRMP)

 1st 2nd 3rd ___ th Screening

Date Submitted for Screening: ________________________________________


Form of Submission: ___ Hard ___ Digital
Project Title: ___________________________________________________________________________________________
Project Location: _______________________________________________________________________________________
Project Proponent: ______________________________________________________________________________________
Authorized Representative: _______________________________________________________________________________
Address: _____________________________________________________________________________________________
Contact No: ____________________ Fax No: _________________Contact Person: _________________________________
EIS Consultant: ________________________________________________________________________________________
Address: ______________________________________________________________________________________________
Contact No:____________________ Fax No: __________________Contact Person: _________________________________
Project Category & Type (based on Annex A of MC 2014-005 Guildelines): (e.g. 1.3.2. Refineries-Category A)__________________________
Project Size (use parameter in Annex A of MC 2014-005 Guildelines): _______________________________________________________

Project Status (Please Check):


__New Project
__Existing Year of Establishment: _____

With Previous ECC? (Please check) __Yes __No

If with Previous ECC, Date/s of Issuance and Reference Code/s: (List in chronological order)

Date/s of Issuance: Reference Code/s:


_____________________________ _______________________________
_____________________________ _______________________________

Date of Technical Scoping:_________________________________________________________


Venue of Technical Scoping:________________________________________________________

Table 1. Checklist of Documentary Requirements


Boxes and blanks in the first column are to be filled-up during scoping and the rest, upon submission of EIS for screening
Acceptable?
Screening Officers’ Remarks
Yes No

Check required EIA Report1


 Environmental Impact Statement (EIS)
 Environmental Performance Report and
Management Plan (EPRMP)
(include photographs or plates of project site, impact/affected
areas and communities and land-use plan showing
compatibility of the proposed project)

Proof of Authority over the Project Site


 TCT  Lease Agreement
 Others: ___________________

Accountability Statements of Preparers & Proponent


(see Annexes 2-21 & 2-22 of Revised Procedural
Manual for DAO 2003-30)

Duly Accomplished Project Environmental Monitoring


& Audit Prioritization Scheme (PEMAPS)
Questionnaire (see Annex 2-7d of Revised Procedural
Manual for DAO 2003-30)

For EPRMP, Copy of previous ECC

For EPRMP, Proof of compliance in the submission of


monitoring reports

1
Please refer to attached checklist of EIS/EPRMP Contents

Page 1 of 21
EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

 1st 2nd 3rd ___ th Screening

ACTION TAKEN: (Please check to indicate corresponding action taken)


 Document accepted; please submit copies
 Document not accepted

NOTED BY:

___________________________ _________________________
Screening Officer Section/Division Chief
Division

EMB Office
Screening Office Date:

Page 2 of 21
EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

 1st 2nd 3rd ___ th Screening

Table 2. EIS/EPRMP Annotated Outline


Sections /
Content Page # Acceptable? REMARKS
Subsections

Executive Summary (maximum of 10 pages)

Project Fact Sheet Summary of Project Description


(For EPRMP, Include comparative matrix of the existing
project components vis-à-vis the proposed changes)

Process Documentation of the process undertaken in the conduct


Documentation of EIA (EIA Team, EIA Study Schedule & Area,
description of key EIA Methodologies including sampling
and measurement plan, Scoping and Public
Participation)

EIA Summary  Summary of alternatives considered in terms of siting,


technology selection/operation processes and design
 Concise integrated summary of the main impacts and
residual effects after applying mitigation
 Risks and uncertainties relating to the findings and
implications for decision making

1. Project Description
Include as an introduction, basic information about the project and project proponent

1.1 Project Location a) Map showing sitio, barangay, municipality, province,


and Area region boundaries, vicinity, proposed buffers
surrounding the area and Primary & secondary impact
For EPRMP, areas
discussions should
be in the context b) Geographic coordinates (shape file data) of project area
of the proposed (use WGS 84 datum - GPS setting)
modification/chang
es c. Describe the vicinity and the accessibility of the project
site/area

I.2.Project Rationale •Cite and focus on the need for the project based on
national and regional/local economic development in
For EPRMP, terms of contribution to sustainable development
discussions should agenda or current development thrusts.
be in the context • Describe the justification for the Project with particular
of the proposed reference made to the economic and social benefits,
modification/chang including employment and associate economic
es development, which the project may provide. The status
of the project should be discussed in a regional and
national context.

I.3. Project a) Cite criteria used in determining options for facility


Alternatives siting, development design, process/technology
selection, resource utilization and discuss how the
For EPRMP, decisions on preferred options were made.
discussions Siting: Alternative project locations including factors
should be in the significant to the selection such as severity of impacts,
context of the perception of affected communities with regards to
proposed
modification/ project, ancestral domain issues, land classification, etc.
changes Discuss other options on the siting of major components
of the project within the project area. Discuss alternative
location of haul roads/access roads.
Technology Selection/Operation Processes and design
Selection for storage: Alternative technologies, operation
processes, and measures to minimize wastes, prevent
adverse impacts such as air and water pollution,
groundwater and land contamination, and for the
prevention/control of emergency events (eg. fire,
explosion, leaks, spills) including factors significant to the

Page 3 of 21
EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

 1st 2nd 3rd ___ th Screening

Sections /
Content Page # Acceptable? REMARKS
Subsections

selection.
Resources: Alternative sources of power, water, raw
materials and other resources needed including factors
significant to the selection such as supply sustainability
and climate change projections

Likewise contextualize the determination of preliminary


options in terms of project site factors significant to the
selection such as supply sustainability and susceptibility
to:
• Liquefaction, Ground Shaking, Ground Rupture,
Earthquake induced Landslides Volcanic eruptions,
tsunami (PHIVOLCS )
• Rain-induced landslide and flooding (MGB)
• Storm surge, and flooding as well as extreme
climatologic conditions (PAGASA)

b.) Summarize and discuss the comparison of


environmental impacts of each alternative for facility
siting, development design, process/technology selection,
resource utilization

c) Discuss the consequences of not proceeding with the


project or no project option

1.4 Project a) General layout of facilities;


Components
b) Maps showing in particular, the location and
For EPRMP, boundaries of project area, location and footprint of main
discussions facilities, storage and support facilities, and proposed
should be in the buffers.
context of the
proposed c) Identification of major components including technical
modification/chan details such as specifications, capacity, number, etc.),
ges; boundaries including the cooling water system
of current project  Specify the operations and process
area should be
delineated from d) Identification and description of support facilities and
the proposed infrastructure requirements such as energy/power
expansion area, if generating facility (if any) or energy source, water supply/
any storage, storm water drainage, sewerage,
telecommunications, safety devices/emergency facilities,
accommodation and similar facilities

e)Identification and description of pollution control devices


and waste management system for the waste materials:
wastewater, air emissions, domestic wastes, toxic and
hazardous wastes, non toxic and non hazardous wastes,
etc.

I.5.Process/ a) Technology Description and Performance


Technology Specifications
o Include process flow-sheets for the operations and
For EPRMP, include the anticipated rates of inputs, wastes and recycle
discussion/comparis streams
on of existing and
proposed c) Description of the pollution control devices and waste
modifications or
management system
expansion
d) Description of the operations and maintenance of
facility

I.6.Project Size a) Total power generating capacity, filter plant capacity, ,


and port capacity and dimension

Page 4 of 21
EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

 1st 2nd 3rd ___ th Screening

Sections /
Content Page # Acceptable? REMARKS
Subsections

For EPRMP, include b)Total Project Area in sq.m. or hectares


discussion/compariso
n of existing and
proposed
modifications or
expansion

I.7.Development Plan, Phases to be described in terms identifying specific


Description of activities (w/ special attention on those with significant
Project Phases environmental impacts as well as climate change
and adaptation options relevant to the project and project
Corresponding activities) and corresponding projected implementation
Timeframes timeframes:
 Pre-construction (e.g. planning, acquisition of rights to
For EPRMP, use land, etc.)
discussions should  Construction (e.g. land/site clearing, temporary
be in the context housing, transport of materials, health and other
of the proposed services for the workforce, discussion of temporary
modification/chang facilities including the progress of works/milestones and
es the number workers required per milestones)
 Operation (projected period of
start-up/commissioning/full operation of various project
components) include discussion on the operation of
various components (as identified above) in terms of
raw materials, fuel requirements, waste management
and infrastructure requirements
 Decommissioning/Abandonment/Rehabilitation
- projected life of the project and alternatives for the
future use of the project area which should be
consistent with long term zoning and land use
development plan of the municipality;
- Abandonment Plan (general) to include management
plan for the projected cumulative/long term project
impacts such as remediation of contaminated soil and
water resources, land restoration, proper
dismantling/abandonment of facilities/ equipment and
other necessary activities

I.8. Manpower Tabulate the following per project phase (pre-construction,


construction, operation and maintenance):
• manpower requirements;
• expertise/skills needed;
• nature & estimated number of jobs available for men,
women, and indigenous peoples (if in IP ancestral
land);
• scheme for sourcing locally from host and neighboring
LGUs

I.9. Project Cost Indicative Project Investment Cost (Philippine Peso)

2. Assessment of Environmental Impacts

See Table 3 for the list of key environmental impacts which shall be subjected
to assessment. The assessment shall done using the prescribed
approach/method and in relation to the corresponding baseline characterization
in the primary and secondary impact areas (as determined using the Guidelines in
Annex 2-2 of the Revised Procedural Manual (RPM) for DAO 2003-30 or succeeding
issuances). The sampling and measurement plan used shall be discussed.
Likewise, the assessment should be done for the various phases of
development (i.e. pre-construction, construction and operation) and should
consider climate change projections and disaster risks based on existing
natural hazard information. For all maps, include overlays of project area
footprint, show sensitive/critical receptors and sampling points for baseline data
(indicate geographical coordinates). In conclusion, the residual and cumulative
impacts shall be assessed.

Page 5 of 21
EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

 1st 2nd 3rd ___ th Screening

Sections /
Content Page # Acceptable? REMARKS
Subsections

For EPRMP, the result of the proponent’s monitoring shall be used as baseline.
The assessment of environmental impacts of proposed modification shall be
discussed in relation to the actual impacts of existing project operations which
shall be presented from a summary of the results of compliance monitoring (in
matrix and graphical form) as described in 6.1.

3. Environmental Management Plan

Appropriate mitigation/management measures should be specified for each of


the identified key impacts (Table 3). Appropriate climate change adaptation and
disaster risk reduction measures/options shall likewise be thoroughly
discussed. The impact management plan should be summarized using at the
minimum, the format in Annex 2-17 of RPM for DAO 2003-30

For EPRMP, the proposed impact management plan to be discussed shall


consider review of performance of existing project based on the Environmental
Quality Performance Levels (EQPLs) set. Also include change in adaptation
measures / options and remediation of contaminated soil and water resources,
land restoration proper dismantling, if any.

4. Environmental Risk Assessment (ERA) & Emergency Response Policy and


Guidelines

The level of coverage and type of document required shall first be determined
based on Annex 2-7e of RPM for DAO 2003-30.

For EPRMP, discuss status of implementation of the safety policies/guidelines


and any proposed changes. Include last three (3) years of safety statistics. Also
include incidence such as spills, near spills and similar incidents such as
accidents and emergency. Discuss actions taken.

See Table 4 for details

5. Social Development Plan/Framework (SDP) and IEC Framework

For EPRMP, discussion should focus on the status of implementation of SDP and IEC commitments. Discuss adjustments that
should be undertaken.

5.1 Social Community development or livelihood programs/activities,


Development projected beneficiaries, partner institutions, timeframe of
Program (SDP) implementation as well as source and amount allotted per
activity/component (See Annex 2-18 of RPM for DAO
2003-30)

5.2.Information and Target sector, key messages, scheme/strategy/methods,


Education Information medium, timelines and frequency, cost (See
Campaign (IEC) Annex 2-19 of RPM for DAO 2003-30)

6. Environmental Compliance Monitoring

6.1 Environmental  Results of compliance monitoring in matrix and


Performance (for graphical form showing and explaining the trend in
EPRMP only) environmental conditions
 Analyze performance based on the Environmental
Quality Performance Levels (EQPLs) set
 Discuss compliance to ECC conditions and performance
against the originally approved Environmental
Management and Monitoring Plan, MMT
requirements/commitments, third party audits (if any)
 Discuss implementation of appropriate and effective
environmental impact remedial actions in case of
exceedances
 Discuss operationalization of complaints management

Page 6 of 21
EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

 1st 2nd 3rd ___ th Screening

Sections /
Content Page # Acceptable? REMARKS
Subsections

system

6.2.Self-Monitoring The monitoring plan shall be summarized using Annex 2-


Plan 20 of RPM for DAO 2003-30 or succeeding issuances as
template.

For EPRMP, the original and proposed additional/changes


in sampling sites/stations shall be discussed and shown in
map/s. Proposed reduction in or additional parameters
especially for air and water shall likewise be identified.
The proposed changes in parameters and/or sampling
stations which shall be based on the results of the impact
assessment reported in Chapter 2 shall be discussed in
this section.

6.3.Multi-Sectoral Discussion on the necessity of creating a Multi-Partite


Monitoring Monitoring Team (MMT). If deemed necessary, describe
Framework the proposed scope of MMT responsibilities and activities
and tabulate the list of proposed stakeholder-members of
the MMT, basis of selection and proposed role. (See
Annex 3-4 of the RPM for DAO 2003-30).

6.4 Environmental • Discussion on the necessity of putting up an EGF. If


Guarantee and deemed necessary, present a proposed amount of EGF
Monitoring Fund indicating the basis for the estimate (per guidelines in
Commitments annex 3-6 of RPM for DAO 2003-30)
• If MMT is deemed necessary, present a
proposed amount of EMF (based on a draft AWFP in
following the format in Annex 3-4 and consistent with
guidelines in Annex 3-5 of RPM for DAO 2003-30);

7.Decommissioning / Abandonment /Rehabilitation Policy

Statement on Proponent’s policies to implement the abandonment plan


described in Item 1.7 and to formulate and submit procedures for
Rehabilitation/ Decommissioning/Abandonment within a timeframe specified in
the ECC.

For EPRMP, present approved plan/program, if any, and proposed changes.

8. Institutional Plan for EMP Implementation

Present the organizational scheme of the proponent including line of command


and reporting procedures as well as manpower complement and relationships
with other operating departments.

For EPRMP, discuss status of implementation and any proposed changes in


the plan to cover modification/expansion if any.

Page 7 of 21
EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

Table 3. Key Environmental Impacts to be included in the Assessment and Formulation of Management and Monitoring Plan to be reflected in the EIS/EPRMP
During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Conditions Analysis Plan Plan
Remarks
Requirements Methodology/Approach

Page ✓ Page ✓ Page ✓ Page ✓

I. Land

1.1. Land Use and Classification

1.1.1 Impact in terms of compatibility with Description & Map showing the project Assessment of the compatibility of
existing land use area in relation to existing land use. the proposed project vis-a-vis actual
land use and the approved
1.1.2 Impact on compatibility with Identify ECA where the project is comprehensive land use plan/zoning
classification as an Environmentally located or near the project area. classification, ECA Classification
Critical Area (ECA) and/or the coastal resource
Identify areas vulnerable/susceptible to management plan of the LGU if any.
natural hazards where the project is
located or near the project area
(include map/s).

1.1.3 Impact in existing land tenure Determine if the project area is under Identify and assess impact in terms
issue/s CARP or with CADC / CADT / CALC/ of land tenure issues in relation to
CALT, with IFMA/CBFMA, within COC, project implementation
within MPSA or other tenurial
instruments and identify corresponding
existing tenure issues including
presence of informal settlers.  1st 2nd 3rd ___ th Screening
1.1.4 Impairment of visual aesthetics Visually significant landforms/ Identify and assess impact of the
landscape/structures project on these visually significant
landforms/landscape/structures

1.1.5 Devaluation of land value as a Existing solid waste management and Identify and assess impacts of the
result of improper solid waste related land management scheme in estimated generation of solid wastes
management and other related impacts the area and other related issues on the
existing management scheme

1.2 Geology/Geomorphology

1.2.1 Change in surface Slope and Elevation/Topographic Map; Identify and assess project impact in
landform/geomorphology/ topography/ terms of the changes in surface

Project Name: ___________________________________ Page 8 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Remarks
Requirements Methodology/Approach Conditions Analysis Plan Plan

Page ✓ Page ✓ Page ✓ Page ✓

terrain/slope landform/topography/terrain/slope
including existing hazard as maybe
aggravated by climate change as
projected by PAGASA

1.2.2 Change in sub-surface Regional/General Geological Map Identify and assess project impact in
geology/underground conditions terms of the changes in sub-surface
Natural Hazard Map (sub surface) geology and inducement of
subsidence, liquefaction, landslides,
1.2.3 Inducement of subsidence, Geological Map as needed.; hazard mud/debris flow to the environment
liquefaction, landslides, mud / maps (NAMRIA, NDRRMC, MGB, including the possibility of
debris flow, etc. PHIVOLCS, PAGASA) aggravating existing natural hazards

Discuss and assess the impacts of


geologic hazards and planned
earthworks on the project facilities
(e.g., landslides, mudflows,
subsidence, ground shaking from
earthquake, liquefaction, flooding,
etc.). Note in the discussion how
climate change can aggravate the
hazards and impacts. The geologic
hazards map must consider the  1st 2nd 3rd ___ th Screening
hazards/exposure/vulnerability/ risk
maps of Section 1.1.2.

1.3 Pedology

1.3.1 Soil erosion / Loss of  Summary of Soil Investigation Describe capability of the land to
topsoil/overburden Report on soil type and quality accommodate the proposed
 Soil map showing soil types, development with minimal or without
sampling stations, topography, soil erosion/loss of
streams, built-up areas, and topsoil/overburden
planned project features
 Water and wind erodibility potential Describe the physical properties and
 Sediment sources, and erodibility potential of the soil,

Project Name: ___________________________________ Page 9 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Remarks
Requirements Methodology/Approach Conditions Analysis Plan Plan

Page ✓ Page ✓ Page ✓ Page ✓

 Riverbank stability ongoing erosion processes and


assess the erosional impacts of the
project. The Universal Soil Loss
Equation (USLE) and its variants
may be used in the modeling.

1.3.2 Change in soil quality/fertility Laboratory results on soil sample Assess the impact of the project
analysis for N, P, K, pH, organic matter, activities including the possibility of
micronutrients and trace metals e. g. spills on soil quality and fertility
Pb, Hg, As, Cd, Cr hexavalent, etc.

1.4 Terrestrial Ecology

1.4.1 Vegetation removal and loss of • Map showing land cover; sampling To establish baseline,
habitat sites; location of observed important, - Use quadrat sampling for flora to
endangered, and keystone species; cover all land cover types
ecologically sensitive sites; planned - Use transect walk , mist nets,
land development works traps, for fauna
• Flora and fauna species inventory or - show survey locations in a map
survey report to cover species listing,
abundance, richness, dominance,
diversity, evenness, Identify and assess project impacts
ecological
status, and uses; in terms of the the following:  1st 2nd 3rd ___ th Screening
• Historical occurrences 1. Habitat loss or degradation – Land
of pest
clearing, river damming, etc. will
infestation, forest/grass fire and/or
similar incidences result in the loss of habitat. Some
activities may lead to the alteration of
1.4.2 Threat to existence and/or loss of Summary of endemicity / conservation habitat composition, structure or
important local species status function. Some habitats, e.g.,
wetlands, are critical to ecological
1.4.3Threat to abundance, frequency and • Summary of abundance, frequency processes or endangered species.
distribution of important species and distribution 2. Habitat fragmentation – This is the
• Economic importance and uses of break-up of the natural landscape
significant flora and fauna into small patches isolated from one
another. It affects the number of
1.4.4 Hindrance to wildlife access Survey map in relation to the project species present, movement of
species, and transfer of materials

Project Name: ___________________________________ Page 10 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Remarks
Requirements Methodology/Approach Conditions Analysis Plan Plan

Page ✓ Page ✓ Page ✓ Page ✓

site among habitats.


3. Loss of species – Of special
interest are the keystone,
endangered, and endemic species.
4. Pollution effects on species – The
stressors include dust,
noise,chemical/ petrochemical spills,
eroded sediment, increased
temperature, etc.

Relate discussions to estimated


GHG emissions and possible carbon
sequestration program/s

2. THE WATER

2.1 Hydrology/Hydrogeology

2.1.1 Change in drainage morphology / Drainage map (also showing local Identify and assess project impact on
inducement of flooding/ Reduction in drainage system/infrastructures); the change in drainage
stream volumetric flow Historical flooding/drought occurrences, morphology/local drainage system
stream flow measurements/estimates; and resulting effects of flooding
Delineation of watershed /sub- pattern in the project area and  1st 2nd 3rd ___ th Screening
watersheds/ floodplain; and surrounding. Include climate
identification of aquifers if any projections effects on flooding.

Relate discussions to item 3.1.1

2.1.2 Change in stream, lake water depth Regional hydrogeological map Identify and assess project impact in
terms of change in stream, lake
water depth

2.1.3 Depletion of water resources / Current / projected water use Identify and assess project impact on
competition in water use (groundwater/surface water) in the the existing water resources and the

Project Name: ___________________________________ Page 11 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Remarks
Requirements Methodology/Approach Conditions Analysis Plan Plan

Page ✓ Page ✓ Page ✓ Page ✓

area and adjacent areas resulting competition in the water use


using analysis/estimation of water
Inventory of water supply source availability. Include discussions
including springs and wells( indicate taking into consideration the
depth of water table) and show PAGASA medium to long term
location in a map of appropriate scale projections

2.2 Oceanography (applicable to projects with jetty/port and/or subsea structures that will change the bathymetry in the area)

2.2.1 Change/disruption in water  Bathymetric survey and map Identify and assess project impact on
circulation pattern, littoral  Measurement of water currents the degree of change/disruption of
current, coastal erosion and  Analysis of available proximate tides circulation pattern and the potential
deposition data for coastal erosion
 Hydrodynamic modeling
 Particle dispersion modeling and
map Build a hydrodynamic model based
 Storm surge hazard, exposure, on the measured bathymetry and
vulnerability, risk maps currents and tidal analysis and then
validate the model. A public domain
software like the United States
Environmental Protection Agency
Environmental Fluid Dynamics Code
(EFDC) may be used. Through the  1st 2nd 3rd ___ th Screening
validated hydrodynamic model,
assess the impacts of the project on
water circulation, littoral current, and
coastal erosion and deposition. Use
the modeling results of Sec. 1.3.1
and 2.1.1. Discuss how the impacts
may be affected by climate change
especially sea level rise.

2.2.2 Change in bathymetry Bathymetric map; USLE / similar modeling when


applicable

Project Name: ___________________________________ Page 12 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Remarks
Requirements Methodology/Approach Conditions Analysis Plan Plan

Page ✓ Page ✓ Page ✓ Page ✓

Use the hydrodynamic model to


assess the impacts of the
bathymetric changes. Discuss how
the impacts may be affected by
climate change. Compare projected
new bathymetry as a result of the
project with the existing

2.3 Water Quality

2.3.1 degradation of groundwater quality


Physico-Chemical characterization Identify and assess project impact in
of water: terms of degradation of groundwater,
 pH coastal surface water and
 BOD5 coastal/marine water quality. Use
DENR standard methods and
 COD procedures for sampling and
 DO analysis.
2.3.2 degradation of surface water  Oil and grease
quality  TSS Assess impact on siltation of surface
 Heavy Metals: Hg, Cd, As, and coastal/marine waters.
Cr, Pb Circulation / plume modeling for  1st 2nd 3rd ___ th Screening
 fecal / total coliform regular discharges, leaks/spills, worst
2.3.3 degradation of coastal/marine Others: case scenario of failure of WTF and
water quality ________________________ other emergency/ accident scenarios
R sampling site map for facilities with structures in water
bodies

Link discussion of spills with Section


1.3 especially if spills affect soil and
groundwater.

Aquifer (Groundwater) vulnerability


Assessment (i.e. discussions on
groundwater contamination due to

Project Name: ___________________________________ Page 13 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Remarks
Requirements Methodology/Approach Conditions Analysis Plan Plan

Page ✓ Page ✓ Page ✓ Page ✓

project operation).
Show in a map, sampling sites for
monitoring purposes based on the
above assessment.

2.4 Freshwater Ecology

2.4.1 Threat to existence and/or loss • Summary of endemicity / Identify and assess project impact in
species of important local and conservation status terms of threats to existence/and or
habitat • Abundance of ecologically and loss of species, abundance
economically important species frequency and distribution species
(fishes, benthos, planktons); and include discussions on overall
• Presence of pollution indicator impact to freshwater ecology.
2.4.2 Threat to abundance, frequency species;
and distribution of species • sampling site map Relate discussions to air and water

Show in a map, sampling sites for


monitoring purposes based on the
most significant threats identified.

2.5 Marine Ecology (applicable if project involves activities, discharges and structure in marine waters)

2.5.1 Threat to existence and/or loss of  Abundance/densities/distribution of Quadrat, transect, line intercept, spot  1st 2nd 3rd ___ th Screening
important local species and habitat ecologically and economically dive, manta tow, marine resource
important species (mangroves, characterization (e.g. municipal and
fishes, benthos, planktons, coral commercial fisheries data) for
reefs, algae, seaweeds, sea baseline gathering.
2.5.2 Threat to abundance, frequency grasses);
and distribution  Presence of pollution indicator Identify and assess project impact in
species; terms of threats to existence, loss of
 Historical occurrences of red-tide, fish important local species, threat to
kill or any related event abundance, frequency and
 marine resource map distribution and include discussions
 sampling site map on overall impact to marine ecology.
Relate discussions to air, water and
oceanography

Project Name: ___________________________________ Page 14 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Remarks
Requirements Methodology/Approach Conditions Analysis Plan Plan

Page ✓ Page ✓ Page ✓ Page ✓

Show in a map, sampling sites for


monitoring purposes based on the
most significant threats identified.

3.0 THE AIR

3.1 Meteorology/Climatology

3.1.1 Change in the local micro-climate Monthly average rainfall and Identify and assess project impact in
e.g. local temperature temperature of the area; Climatological terms of change in the local micro-
normals/extremes; Wind rose climate change. Also discuss effects
diagrams; Frequency of Tropical of climate change using PAGASA
cyclones medium to long term projections

3.1.2 Contribution in terms of Data on Greenhouse gasses (i.e. Estimate projected greenhouse
greenhouse gas emissions (or GHG carbon dioxide, nitrous oxide); gases (GHG) (i.e. carbon dioxide,
mitigation potential) nitrous oxide) using IPCC guidelines;
include mitigation and/or
Note: applicable only for projects with sequestration for both construction
significant GHG emissions and operation phases.

3.2 Air Quality (& Noise)


 1st 2nd 3rd ___ th Screening
3.2.1 Degradation of air quality Characterization of ambient air Use DENR standard methods and
quality: procedures for sampling and
 TSP analysis. Relate selection of
 PM10 sampling locations using data
collected in 3.1.1
 SO2
 NO2 Identification and assessment of
 Trace Metals: Hg, Pb, Cd, Cr, impact of the project to the identified
As parameters including VOCs and odor
others: through air dispersion modeling (as
________________________ may be applicable)
(for sampling methods refer to Clean Air
Act) Provide air dispersion modeling
R sampling site map (include worst case scenario of

Project Name: ___________________________________ Page 15 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Remarks
Requirements Methodology/Approach Conditions Analysis Plan Plan

Page ✓ Page ✓ Page ✓ Page ✓

failure of Air Pollution Control


Facility). Present conclusions of
modelling on extent of physical and
chemical dispersion/trajectory of
most relevant parameters and
resulting ground level concentrations
with increasing distance from the
source as basis for deriving buffer
zones and delineating the direct
impact area from the indirect impact
area. Superimpose on the
economically and ecologically critical
areas/resources and
population/significant socio-cultural
features

Show in a map, sampling sites for


monitoring purposes based on the
above assessment.

Compare changes in air quality over


time using statistical tools e.g. across  1st 2nd 3rd ___ th Screening
sampling sites over time, and test for
significant changes

3.2.2 Increase in ambient noise level Characterization of ambient noise level Use DENR standard methods and
procedures for sampling and
sampling site map measurement.

Identification and assessment of


impact to ambient noise level using
noise attenuation modeling and
comparing it with relevant standards.
(applicable if estimated total noise
level will exceed noise standard).

Project Name: ___________________________________ Page 16 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Remarks
Requirements Methodology/Approach Conditions Analysis Plan Plan

Page ✓ Page ✓ Page ✓ Page ✓

4.0 THE PEOPLE

4.1 Displacement of settler/s Demographic data of impact area: Identify and assess project impacts
- Number of households and on demography of affected
Displacement / disturbance of household size communities. Use assessment in the
properties - Land area, formulation of SDP/IEC

Change/conflict in land ownership


- Population, Assess availability of alternative
- Population density /growth public access and housing options
Change/conflict Right of way - gender and age profile, for displaced settlers
- literacy rate, profile of educational For project with displacement/
Impact on Public Access attainment disturbance of properties/settlers,
- settlements map change/conflict in land ownership
and change/conflict right of way,
Census of population / property that formulate resettlement framework
will be displaced / disturbed plan or RAP

4.2 In-migration Identify and assess project impact


Housing ownership profile / due to in-migration patterns
proliferation of informal settlers availability of housing/ number of including proliferation of informal
informal settlers settlers

4.3 Cultural/Lifestyle change (especially Demographic data on Indigenous Identity and assess project impact in  1st 2nd 3rd ___ th Screening
on Indigenous People, if any) People (if any) and existing terms of Culture/Lifestyle that may be
Culture/Lifestyle that may be affected and/or introduced
significantly affected

4.4 Impacts on physical cultural Inventory and description of physical Identify all potential project impacts
resources cultural resources and landscapes that in an integrated manner considering
have archaeologic, paleontologic, the type, significance, and
historical, religious, aesthetic, or value/importance of the physical
cultural significance: Movable or cultural resource/s
immovable objects, below ground or
under water, sites, structures, groups of Identify risks in terms of capacity and
structures, and natural features commitment in managing the impacts

Project Name: ___________________________________ Page 17 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Remarks
Requirements Methodology/Approach Conditions Analysis Plan Plan

Page ✓ Page ✓ Page ✓ Page ✓

Classify cultural interest value/ (protocols in handling chance finds


importance into local, provincial, shall be implemented)
national, or international level

Sources of information: UNESCO, National


Museum (NM), National Historical
Commission of the Philippines (NHCP),
National Commission for Culture and Arts
(NCAA) and the Local Government Units
(LGUs) in the project area and other UN or
National Publications

4.5 Threat to delivery of basic services Availability of public services in terms Identify and assess project impact in
/resource competition of: terms of threats to delivery of basic
• Water supply services including potential for
• Power supply resource competition in the area
• Communications including effects of in-migration
/transportation
• peace and order / crime
• education facilities
• recreational facilities / sports
facilities
 1st 2nd 3rd ___ th Screening
statistical data / information related to
public services:
• literacy rate, profile of
educational attainment
• Crime rate
• Food security

4.6 Threat to public health and safety Availability of public services in terms Identify and assess specific threats
of: health resources (Government and to public health and safety due to
Private) project impacts. Relate discussions
to land, air and water (Item 1 to 3)
Statistical data / information related to
public services: Analysis of the impact of project
• Morbidity and mortality rates implementation on existing disease

Project Name: ___________________________________ Page 18 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Unless otherwise specified as agreed during scoping, all items listed are required. Write specific instructions ( if any) on ✓ For completeness during procedural screening; page numbers
the blanks/spaces provided should be provided upon submission of the EIS/EPRMP

Baseline Data Parameter Required Assessment Baseline Impact Mgmt. Monitoring


List of Key Impacts Remarks
Requirements Methodology/Approach Conditions Analysis Plan Plan

Page ✓ Page ✓ Page ✓ Page ✓

(infants and adults - 5-year trend) profile including weather sensitive


• Common diseases in the area diseases and impact aggravation as
including endemic diseases; a result of climate change as
projected by PAGASA
Environmental Health and Sanitation
Profile

4.7 Generation of Local Benefits from the Socioeconomic data: Identify and assess local benefits of
project • Main sources of Income the project in terms of enhancement
• Employment rate/ profile of employment and livelihood
Enhancement of employment and • Poverty incidence opportunities, increased business
livelihood opportunities • sources of livelihood opportunities and associated
• commercial establishments and economic activities and increased
Increased business opportunities activities revenue of LGU
and associated economic activities • banking and financial institutions

Increased revenue of LGUs

4.8 Traffic congestion Road network/ systems Identify and assess project impact on
Existing Transportation/traffic situation the traffic situation in the area
including congestion based on
existing capacity of road system
 1st 2nd 3rd ___ th Screening

Table 4. Environmental Risk Assessment to be included in EIS/EPRMP

Project Name: ___________________________________ Page 19 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

During scoping: Check () required/applicable items; items with  are automatically required; write specific instructions (if any) on
Present? (✓)
the blanks/spaces provided.
Monitoring
Remarks/ ERA ERP
Level of Coverage & CONTENTS OF ERA AS PART OF EIS/EPRMP Plan
Specific Scoping REMARKS
Type of Risks For the identified safety risks in column 1
Instruction/s Page ✓ Page ✓ Page ✓

Level of Coverage: For EPRMP, include HAZOP or QRA for existing facilities and
Refer to Annex 2-7e of the RPM for
compare with that for the expansion. Also include discussions
DAO 2003-30 on safety incidents/records/history (in relation to environmental
o Level 2 (QRA Required) risks) classified into first aid, medical attention cases, days away
o Level1 (Emergency Plan from work cases, fatalities (including contractors), record of drills
based on hazard analysis) (fire, spills, explosion, among others) and any experience in
o Risk Screening Level implementing the ERP

For EIS, check type of report to be submitted prior to Operation:


o Quantitative Risk Assessment(QRA)
o Emergency Plan
o Risk Screening

Safety Risks Type: R Description of conditions, events and circumstances which


o Fire could be significant in bringing about identified safety risks
o Explosion R Description & assessment of the possible accident
o Release of toxic substances scenarios posing risk to the environment
R Description of the hazards, both immediate (acute effects)
and delayed (chronic effects) for man and the environment
posed by the release of toxic substance, as applicable
R The safety policy and emergency preparedness guidelines
consistent with the regulatory requirements. Emergency
Preparedness should also consider natural hazards to the  1st 2nd 3rd ___ th Screening
infrastructures and facilities.

For EPRMP, present actual Emergency Response Policy,record


of drills and recorded events.

o Physical Risks R Description of conditions, events and “trigger” which could


(Failure of Structure w/c could be significant in bringing about identified physical risks
endanger life, property and/or R Description & assessment of the possible accident
the environment) scenarios posing risk to the environment
R Description of the hazards both immediate (acute effects)
and delayed (chronic effects) for man and the environment
posed by the failure of structure, as applicable

Project Name: ___________________________________ Page 20 of 21


EIS/EPRMP SCOPING AND SCREENING FORM FOR THERMAL POWER PLANT PROJECTS
(Requiring EIS or EIS threshold EPRMP)

Noted By: Signature Signature

Review Committee Members EMB Representatives

1. 1.

2. 2.

3. 3.

4. Project Proponent:

5.

6. Project Preparer/Consultant:

Resource Person

1.

 1st 2nd 3rd ___ th Screening

Project Name: ___________________________________ Page 21 of 21