Sei sulla pagina 1di 13

https://www.whatispiping.

com/piping-design-considerations-for-vertical-columns

Piping Design Considerations for Vertical


Columns – What is Piping
want2learn

Columns are used in the process units for fractionation and stripping. They are cylindrical in
shape and their axis is vertical to the grade.

Fractionation:

Fractionation is the process of separating a mixture of different miscible liquids by vaporizing


the mix and condensing the constituents at their individual boiling points. The process of
distillation has evolved during the century from Batch shell still process to Continuous shell still
process to the present Fractional distillation process.

Principle of operation of fractionating tower:

Fractionation is the process of separating a mixture of different miscible liquids by vaporizing


the mix and condensing the constituents at their individual boiling points. Higher boiling point
liquids will condense first, followed by lower boiling point products. This is achieved in the
fractionating tower by creating zones of different temperatures along the length of the tower, the
lowest at the top and the highest at the bottom. As the vapors rise along the column, they loose
heat and condense at their respective boiling points. Column internal trays / packed beds,
accumulators and draw-offs help in this function.

Trays:

These are stamped plates of steel with unidirectional valves attached to them. They allow the
passage of vapor in the upward direction only. They are placed all along the length of the tower.
The valve lifts when the vapor force on the bottom on the valve exceeds the liquid force on top
of it. As the vapors push the valves and pass thru the liquid, vapors with higher condensation
point loose heat and condense. The excess liquid on the tray flows down to the lower tray via a
down comer. Lighter boiling fractions in this liquid are vaporized on the lower tray by the heat of
the upward traveling vapors. Vaporization and condensation takes places all along the length of
the tower. Draw-offs at appropriate locations allow the removal of desired products from the
column.

Packed Beds:

These are beds of metal rings, packed along the length of the column. They function similar to
trays. Rising vapor passing thru the metal rings comes in contact with liquid flowing down the
column. Down flowing liquid is heated by the upward flowing vapor similar to trayed columns.
Design considerations for Columns:

Locating the column

The piping designer should economize piping interconnections between the column and its
adjacent equipments (pumps, condensers, heaters, reboilers etc.) when locating the column. The
following documents are needed to locate the column on the plot plan.

 P&ID
 Process Vessel Sketch
 Plot plan
 Piping & Plant Layout Specification

The column is located on the plot plan as per the process sequence dictated by the P&ID. Small
columns can be placed on stand-alone structures. Large columns need a civil foundation of their
own. In plants where the related equipments are housed, they are placed adjacent to the building
or structure. Columns are best located on either side of the pipe rack, serviced by auxiliary roads
for maintenance access. Vessel transportation, erection and other constructability issues should
also be looked into while finalizing the location of the vessel. Adequate space must be provided
around the column for operator movement and maintenance access. Locating close to an access
road to reduce maintenance efforts. Inter-distances between adjacent equipments are fixed as per
Table 5 of Piping & Plant Layout Specification. The Bottom Tan Line elevation is fixed by the
P&ID. The same may be increased to facilitate piping and equipment layout in consultation with
the Process group.

After the column has been located on the plot plan, the following jobs are carried out.

 Column elevation review and support selection


 Tray orientation
 Nozzle orientation
 Platform and access requirement
 Support cleat location detailing
 Lifting lugs and earthling lugs location planning
 Finalizing Vessel Name Plate location

Column elevation review and support selection

The Bottom Tan Line elevation fixed by the P&ID is the minimum elevation required for NPSH
of the bottoms pumps. This may be increased in consultation with Process Group for the
following.

 Operator Access – Proper headroom clearance should be available for safe operator
access to the column.
 Maintenance Access- Proper maintenance access clearance should be available for safe
movement of maintenance equipment around the column.
 Minimum clearance as per piping layout
 Bottom nozzle size – The bottom nozzles are connected to the bottom head with a
straight pipe piece and a 90(elbow. This lowers the clearance available below the bottom
of the elbow
 Bottom head details (elliptical, hemispherical etc.) Hemispherical head has a depth twice
as compared to elliptical (2:1) This will change the center line elevation of the bottom
nozzle and consequently the clearance under the elbow.
 Vertical thermosyphon reboiler connections -Reboiler bonnet removal area dictates the
minimum tan line elevation of the column, when reboiler is attached to the column.

Column supporting arrangement

Columns are generally supported by the following methods

 Skirt Supported with foundation on grade – most preferred. Skirts are straight for short
columns and flared for tall ones.
 Ring girder supported – On table top (when bottom nozzle needs to be accessed)
 Skirt supported – On tabletop
 The choice of support may fix the column elevation for some layouts.
Fig. 1: Image of a Typical Vertical Column

Tray orientation:

The following documents are required for orienting the trays.


 Vessel Process sketch & Tray data (No. Of pass, down comer area, tray spacing etc)
 P&ID
 Plot plan
 Plant Layout Specification

Tray nomenclature:

 Odd and Even trays – Trays are numbered from the top of the column to the bottom.
Trays with odd numbers 1,3,5, are the odd trays and those with even numbers 2,4,6, are
the even trays.
 Number of Passes – Trays can be one pass, two pass, three pass or Four pass depending
on column diameter.
 Active Area (Bubbling area) – Area of the tray, which allows vapor to pass thru it
 Down comer area – Area that allows excess liquid on one tray to flow down to the tray
below it.
 Tray spacing – Inter-distance between adjacent trays.
 Chimney tray – It is a solid plate with a central chimney section and is provided at the
draw off sections of the column.

Tray orientation considerations:

The main items influencing tray orientation are

 Feed nozzle orientation


 Reboiler location
 Access Manholes

Feed nozzles are large in diameter and their orientation is fixed by the piping layout. The feed
nozzle may have one or multiple external connections with different internal configurations for
the following:

 One nozzle with two orientations


 Two nozzles with two orientations
 One nozzle with multiple orientations

It is of utmost importance that the feed nozzle is parallel to the tray down comer. Reboiler
location is fixed on the plot plan .Now, as reboiler draw off nozzle is mostly located on the same
side as the reboiler to minimize piping run, the draw off orientation is established. Reboiler
returns nozzle is to be parallel to the tray down comer. For bottom draw-off nozzle arrangement,
tray orientation remains unaffected. Access Manholes on the cylindrical section are best located
towards areas of direct maintenance access and opposite pipe racks. Thus their location may
dictate the orientation of the trays.

Nozzle orientation:

The following documents are required for orienting the nozzles.


 Process vessel sketch
 Level co-ordination diagram
 P&ID
 Plant layout specification
 Nozzle summary
 Insulation requirements
 Plot plan

General considerations for locating nozzles:

Generally, the following nozzles are present on all columns.

 Feed Inlet
 Bottoms Outlet
 Drain
 Vapor Outlet
 Vent
 Reboiler Draw off
 Reboiler Return
 Product Draw off
 Reflux
 Instrument Nozzles
 Steams Out Nozzle
 Access Manholes

Orienting the nozzles:

While orienting these nozzles the following points are to be considered.

 Feed inlet to be placed parallel to the down comer tray as discussed in tray orientation.
Orientation of feed inlet is in the sector towards the pipe rack from which the feed piping
is coming. Proper support and flexibility should be available to route the piping.
 Bottoms Outlet will be on the bottom head, best located on the center of the head. This is
of gooseneck type for vessels with skirt type support and the nozzle flange has to be
brought outside the skirt. A separate drain nozzle at the bottom head but a tapped nozzle
on bottoms outlet is most preferred. Orientation is generally chosen to minimize piping to
the bottoms pump keeping the line flexible enough from stress point of view.
 Vapor outlet, PSV connections and Vent will be on the top head of the column. Vapor
outlet is best located on the center of the head, though it may have to be shifted based on
some layout considerations as explained. A large diameter makes location of the vapor
nozzle critical. The nozzle may have to be offset from the center of the column so that,
after two elbows, the piping travels down the column at a practically supportable distance
from the column.
 Reboiler draw off nozzle is mostly located on the same side as the reboiler to minimize
piping run, thus the draw off orientation is established. For bottom draw-off nozzle
arrangement, the best-suited orientation as per piping layout may be chosen.
 Reboiler return nozzle is to be parallel to the tray down comer as discussed in tray
orientation.
 Reflux nozzles are to be oriented for proper and even flow of refluxed liquid on the
bubbling area. This can be achieved by internal distributor piping.
 Level Instrument nozzles should be oriented as close to any inlet nozzle to avoid effects
of turbulence. When baffles are provided this consideration is relaxed.
 Pressure tapping for vapor pressure should be oriented in the bubbling area of the tray
above it.
 Temperature tapping for liquid temperature measurement should be oriented in the down
comer area. They are best-oriented perpendicular to the tray down comer. When multiple
temperature elements are required, they are best placed at the same orientation but
different elevations. Care must be taken to ensure that the internal projection of
temperature element does not hit the down comer. The nozzle should be made hillside if
the probe length cannot be accommodated in radial direction.
 Inaccessible Instrument nozzles to be oriented near ladders (location of ladder and
Instrument nozzles to be decided concurrently)
 Steam out connection should preferably be hillside type on the cylindrical shell so that
swirling action is generated inside the vessel. This will ensure faster steam out of the
column. These should be placed as close to the bottom tan line as possible.
o Access manhole can be located at the following places, depending on the type of
access required into the column.
o On the top of the column. (In this case the vent can be located on the blind flange
of the access manhole.)
o On the cylindrical portion of the column (radially or hill side) this is the most
preferred location. The orientation of manhole should be such that the manhole
faces the maintenance access area. This is to be in conjunction with tray
orientation. Manhole entry should be directly on a bubbling area and never in the
down comer area. Internal piping should not block the access area of a manhole.

It should be verified that the davit swing area of the manhole cover does not obstruct the
movement of maintenance personnel and does not hit any instruments or instrument nozzle
connections. The centerline of the manhole should be between 600mm to 1000mm (ideally
760mm) from the top of service elevation of the vessel.

 Goose neck nozzle for Vapor outlet should be considered when piping layout is fixed and
requires an elbow immediately at the nozzle. This can be flanged type, thus acting as a
manhole also for big nozzle diameters. Flange type nozzles have the added advantage that
their orientation can be changed even after the delivery of the vessel at site.
 Skirt access manholes are to be oriented for easy access.
 Skirt vents are to be oriented in such a manner so that they do not come at the same
location as the access ladder.

Nozzle standouts:

Nozzles on the top of the column should have their flange a minimum of 180mm and a
maximum of 1000mm from the TOG of the access platform. Nozzle standouts on the shell are
calculated on the clearance requirement for maintenance access to nuts on the back of the flange.
Due consideration is to be given to vessel insulation when calculating the standout. This standout
will be confirmed by mechanical so that the nozzle passes the mechanical requirements.

Preparing the Nozzle Orientation Document:

This document should show the plan, and if required, the elevation of the vessel with the location
of nozzles on the same. Nozzle orientation is to be from plant north and taken clockwise.
Dimensioning should show the radial distance of the vessel flange from the vessel center. A
nozzle summary table indicating the Nozzle number, service, size, rating, flange face, elevation
from bottom tan line, and standout from vessel center is to be included in the drawing. For
nozzles on the vessel heads, the F/F standout from the bottom or top tan line should be given. . In
lieu of elevation from bottom tan line.

Miscellaneous Data to be included in Nozzle Orientation Document:

Lifting Lugs

Generally columns can be lifted with two lugs welded below the top tan line. A tailing lug is to
be provided near the bottom of the skirt for tailing operation .The preferred locations should be
marked on the nozzle orientation drawing.

Earthling Lugs

Two earthling lugs, ideally 180°apart should be provided on the lower portion of the skirt. The
same should be marked on the nozzle orientation drawing.

Name Plate

Nameplate should be located at a prominent location and marked on the nozzle orientation
drawing. Care should be taken that the nameplate projects outside the vessel insulation.

Vessel Insulation Clips

Indicate that insulation clips/rods are required for holding the vessel insulating bands.

Platforms and Access Ladders

Platforms are required for the following purposes

 Operational access to valves and instruments etc.


 Maintenance access to manholes.
 Mid landings (when elevation difference between two platforms exceeds 9m)

Calculating the TOG elevation


Platform on the top head of the column

TOG elevation from top of column head = Insulation thickness + 50mm clearance + Platform
member depth (assume 200mm minimum) + 30mm grating. Round off to the next higher
multiple of 10.

Platforms on the cylindrical portion of the column

 Nozzles – Platform to be 500mm (minimum) below the bottom of flange of nozzle.


 Instruments (LT/LG) and their standpipes – Platform to be 200mm below the lowest
process drain on any of these items.
 Access manholes – Platform is to be ideally760mm below the centerline of the manhole.
Acceptable range is 600mm to 1500mm below the centerline of the manhole.
 Mid landing platforms-These are to be provided when the elevation difference between
two platforms levels exceeds 9m. The mid landing to be ideally evenly placed between
the two platforms.
 Two platforms being serviced by a single ladder should ideally have an elevation
difference of 600mm between them.
 The platform elevations (TOG) should be rounded off to the nearest multiple of 10.

Platform sizing

Platform on the top head of the column

This platform should be rectangular .It should cover all the nozzles, instruments davits etc. that
need access for operations and maintenance. Ideally a space of 750mm should be provided
around 3 sides of a nozzle. This may be lowered at the discretion of the piping lead. Side entry
access to the platform should be the first preference when deciding the exact shape of the
platform. Orienting the platform axis along the ladder orientation and providing an extended
landing point may achieve this.

Platforms on the cylindrical portion of the column

Determining the Orientation angles

 This platform should be circular .Its orientation extent should cover all the nozzles,
instruments davits etc. that need access for operations and maintenance. Platform should
extend beyond the centerline of manhole by a minimum of 1 manhole diameter.
 A free landing space of 750mm is to be provided for access ladders.
 Ideally a space of 750mm should be provided around the sides of a nozzle. This may
however be lowered to 600mm on the discretion of the piping lead.

Determining the width

 The inner radius of the platform should clear the column insulation by 50mm.
 Platform width is dictated by operator access requirements. The following considerations
are to be taken care of when deciding the width.
 Minimum platform width is to be 750mm(free of all obstructions).
 Width of manhole platform is to be minimum 900mm.
 Platforms may be locally extended width wise at regions where vertical pipes pierce the
platform, maintaining 750mm clear space from insulation of piping to handrail of
platform.
 When controls are located on the platform, the width of the platform is to be 900mm plus
the width of the controls.

Platform bracket orientation

Platform support brackets are to be oriented so that they clear the vertical piping traveling down
the column, thru the platform. Support bracings for platforms at all elevations should be
maintained the same as far as possible.

Access ladder

 Access ladders are to be vertical. They should have a clear climbing space of 680mm.Toe
clearance from the centerline of ladder rung to any obstruction to be 230mm.Special care
is to be taken for vessel stiffeners.
 Cage is to be provided for all ladders at elevation of 2300mm and above. Side entry
ladders are the first preference.
 The ladder is to be oriented so that it can also be utilized for access to instrument
connections that are inaccessible from working level.
 Inclined ladders are permissible on inclined portions of the skirt and column. The angle is
limited to 15°from vertical.

Preparing the Platform Input Document

Platform and Access ladder input is transmitted to Civil via a platform input drawing.

Platform on the top head of the column

This should clearly indicate the TOG elevation from bottom T/L, dimensions of platform, and its
location w.r.t. The vessel centerlines. Grating cutout requirements (indicating size, shape and
location), required swing direction of self-closing gate, and davit location need to be marked on
the same drawing. Any pipe supports intended to be taken from the platform should be marked.

Platforms on the cylindrical portion of the column

This should clearly indicate the TOG elevation from bottom T/L; dimensions of platform
(orientation angles and width), and its outer radius form the vessel axis. Grating cutout
requirements (indicating size, shape and orientation), required swing direction of self-closing
gate. Any pipe supports intended to be taken from the platform should be marked. Orientations
of access ladders should be marked on the respective platform elevation plans.
Orienting piping on the face of the column

It is imperative that the orientations, arrangement and standouts of various piping traveling down
the face of the column are calculated keeping in mind the following points.

Large diameter columns

 Piping has to be arranged in the order of the elevation and orientation of the nozzles.
 The piping of these columns can travel down the column radially, with independent
supports.
 Clear minimum space between pipe and shell is to be 300mm excluding any insulation.
 The pipe with insulation should clear the stiffening ring and its insulation.
 Minimum orientation angle between two adjacent pipes should be calculated to clear the
support bracket of one pipe hitting the insulation cladding of the adjacent pipe.
 Support points of adjacent piping should be offset to save space between them. as the
support brackets will have to be oriented so that there is no clash between the cleats of
the supports, or between the support members and bracings.

Small diameter columns

 Piping has to be arranged in the order of the elevation and orientation of the nozzles.
 Small diameter columns have an inherent problem of supporting and guiding each line
independently due to the small circumference available for the piping. After the first rest
support near the nozzle , the pipes should be oriented as though the are traveling down a
vertical pipe rack .
 Clear minimum space between back of pipe or shoe and shell is to be 600mm. On the
vertical run, minimum spacing requirements have to be followed.

Supporting Piping from Columns

Piping should be supported form the vessel or its platform when it is difficult to construct a civil
support from grade or adjacent structure at the required location. Vessel support may also be
taken to take advantage of lower differential thermal growth between vessel and piping , as
compared to piping and civil support. Judicious selection of support location can eliminate the
requirement of springs.

Thumb rules for supporting piping from columns

 Small loads can be transferred directly to the platform members. These include rest , one
way stop , two way stop or hold down supports and the piping layout should be done
accordingly.

 Large loads should be transferred to the vessel shell and the piping layout should be done
such that the platform members do not interfere with these independent supports.
 First piping support is a rest support and it should be as close to the equipment nozzle as
possible. Second and subsequent supports are guides and they are to be located as per the
allowable piping spans available in the tables. For tall columns , another rest support may
be needed. This is done by providing a spring support which will take care of the
differential expansion of vessel and piping.

 Piping support should not cause any hindrance to movement of personnel.

 Vessel growth should be considered to check clash of a piping support with any adjacent
piping or structure.

Types of supports

Supports welded to piping

Horizontal trunnions welded to pipe take the vertical load of the pipe. They are generally used in
pairs , set apart at 180°. Their axis is perpendicular to line drawn from center of column to center
of pipe at the location of support. Trunnion lengths should be adequate enough so that their ends
project 50mm from outer edge of support bracket member Shoes are provided for guiding
purpose and to prevent insulation cladding hitting the support bracket member. Adequate shoe
length is to be taken for differential movement of pipe and vessel.

Supports welded to vessel

Support brackets( non braced and braced ) and Guide brackets( non braced and braced ) are the
most common support arrangements for vertical piping.

Calculating the minimum dimensions of support members

Load bearing supports

Trunnions or springs transfer load to these supports. Minimum clear inside dimensions are
calculated so that the insulation cladding is 50mm away from the inside of structural member or
support plate of spring.

Guide supports

Bare pipe is guided directly by the guide bracket. Shoes are provided in pairs ,180° apart, for
lines with insulation. These can be single pair or double pair depending upon the type of guiding
required at that particular location. The guide gap required by stress is to be added to the end to
end-to-end dimensions of bare pipe or pipe with shoes.

Preparing the Civil Pipe Support (CPS) Input Document

CPS input is transmitted to Civil and Mechanical via a CPS input drawing. A sketch clearly
indicating the TOS, dimensions , and the CPS location w.r.t. the vessel centeline needs to be
drawn. Any requirement of additional support plates for springs or trunnions are to be indicated.
A summary table indicating the CPS number, TOS, stress file number, corresponding node
number from the Nozzle cleat load information chart needs to be created. The Nozzle cleat load
information chart indicates the various loads acting at the support location under various
conditions. It is to be attached along with the CPS input document.

Potrebbero piacerti anche