Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Report
Submitted to :-
The HRD
Submitted by:-
Vijayashree
(Trainee)
B-Tech 2rd Year
RTU Kota (Raj.)
PROCESS
VISCOSE PREPARATION:
DOMESTIC BUYERS:
The yarn and cord is packed in the boxes and fabric is packed in
the form of roll. The Anhydrous Sodium Sulphate is packed in the
bags with uniform weight of 50 Kg. The goods are dispatch as per
advised received from the Marketing through the nominated
transport.
FOREIGN BUYER:
The yarn, cord is packed in the form of Pallets and Fabric in the
form of Roll. The goods are normally dispatched in 20 and 40 Ft.
containers.
Viscose Department converts pulp sheets in to viscose. The whole
process for making viscose can be classified in to 6 steps. These steps are:
Steeping
Shredding
Ageing
Xanthation
Dissolving
Viscose Ripening
STEEPING:
No. of m/cs. = 5
Time = 50 ± 10 min.
Temp. = 29 ± 2°C
Capacity of motor = 50 HP
AGEING:
DISSOLVING:
When cut off pressure is >8 Kg then filter is cut off and put again
for dressing.
Vacuum is taken in ‘A’ Tank to the level of 600 mmHg and then
viscose batches are transferred one at a time from blender then
viscose filtered by ‘A’ Series filter press.
TRANSFER VISCOSE BATCH FROM ‘A’ TANK TO ‘C’
TANK:
When one ‘C’ Tank gets empty vacuum to the level of 650 mmHg
and then viscose from ‘A’ tank is pumped to ‘C’ Tank through ‘A’
Series filters. Air pro to the level of 2 Kg/Cm 2 is applied on ‘A’
Tank and ‘A’ Tank give positive pro in the suction of ‘A’ series
filter pumps. Then viscose is filtered by ‘C’ Series press.
H2SO4 = Depend on RI
ZnSO4 = 65.0 gpl
Spgr. = 1.258
Noigen G-200 = 200-250 ppm)
Na2SO4 = 200.0 gpl
Temp. = 63°C
H2S = <15 ppm
H2SO4 = 96.0
ZnSO4 = 610
Spgr. = 1.253
The return bath from the Spinning machines flows by gravity into Bath
addition tank. In this tank all the concentrated solution i.e. conc.
Sulphuric Acid, conc. Zn.Soln. Filtrate soln. are added for makeup of the
loss and consumption on the spinning machine. Apart from these spin
aids like Noigen G-200, Defoamer etc. are also added.
From addition tank return bath flows by gravity to 7 Nos. gravity sand
filters operating in parallel. Here all the suspended matters contaminated
on the spinning machines are filtered out by gravity through a bed of
sand. Filtered bath flows by gravity to filtered bath tank in basement.
From the filtered bath tank, bath is pumped through filtered bath pumps
to spinbath evaporator.
Three filtered bath transfer pumps each of 900 GPM capacity are in lower
basement near filtered bath tank.Out of the three pumps, two are running
at a time and one is standby.
From filtered bath transfer pumps, bath is partly pumped to the spinbath
evaporator and partly is bypassed to the spinbath head tanks and partly
goes to the degassifier. Part of the bath going to the degassifier is mixed
with air sucked in due to fall to remove the dissolved H2S gas. H2S is
vented out from the top of the tower along with air. From the bottom of
the tower bath flows to the transfer pump which pumps it back to
spinbath head tank No.4 or Evaporator Seal Tank.
From seal tank spinbath flows to spinbath supply head tanks (6 in Nos.).
These head tanks are always kept full to have constant gravity head for
feeding to spinning machines. From spinbath head tanks spinbath flows
by gravity through spinbath heaters to spinning machines. There are six
heaters operating in parallel. At a time normally four heaters are kept on
line and two will be in spare.
From the magma tank, magma is pumped to Rotary vacuum filter where
glauber salt crystals are removed and are dissolved back in the dissolving
trough into the circulation hot glauber salt soln. The glauber salt solution
is pumped to Anhydrous Sodium Sulphate Recovery Plant for further
processing. The glauber salt solution has the following composition:
The mother liquor filtered out from the rotary vacuum filter flows by
gravity through vacuum receiver to filtrate pit tank in the basement. A
vacuum of 5” of Hg. is maintained on rotary vacuum filer.
From filtrate pit tank the solution is pumped to filtrate head tank from
where filtrate solution is added back into spinbath through crystallizer
feed cooler at desired rate into bath addition tank.
HOT STRETCH SOLUTION
From hot stretch heater hot soft water is supplied to spinning machines at
a temperature of 87-88°C where it is heated further up to 92°C with steam
purged in the trough, is called hot stretch solution. Flow on spinning
machine is at the rate of 32 lts/min/machine. The heating of soft water is
carried out partly in hot stretch heat recovery system and partly in hot
stretch head tank and balance e.g. up to 88°C in hot stretch heater, all
installed at 1 floor. In heat recovery system, heat of dezincified water
(effluent after recovery of zinc from return hot stretch soln. in Zinc
Recovery Plant) is utilized to heat up the cold soft water up to about 54°C
with the help of plate heat exchangers. Hot soft water from heat recovery
system then flows to hot stretch head tank where it is further heated by
purging steam directly in to it up to temperature 70-75°C. Purging of
steam (50 psig) is distributed uniformally with the help of a multi arm
distributor pipe fitted in the center of the tank. Level in the head tank is
maintained constant with the help of an automatic pneumatic level
controller. Soft water supply piping arrangement is such that if needed,
heat recovery system can be bypassed and controller can directly feed the
head tank. Also cold soft water can directly be fed to the hot stretch
heater to carry out complete heating there. Hot soft water from hot stretch
head tank flows to spinning machines by gravity through the hot stretch
heater used for further heating up to 88°C. Heater is a shell & tube type
heat exchanger with automatic temperature controller fitted in steam
supply line (50 psig). Temperature sensing element is fitted in the header
going to spinning machines. Hot stretch from spinning machines retuns to
hot stretch pit tank in basement by gravity where from it is pumped by a
500 gpm. Capacity pump to the zinc Recovery plant for recovery of Zinc.
REGENERATION SOLUTION SYSTEM
Finish solutions from pit tank are then transferred to finish head tank at 1 st
floor with the help of finish transfer pump. During transfer, solutions are
filtered by in-line cloth wrapped wire mesh filters (2 Nos.) fitted in
transfer pump’s discharge lines near pit tank. Finish head tank is always
kept overflowing to maintain a constant head for uniform supply to
Spinning machines, overflow returns pit tank.
Finish solution carried away with the yarn (while having passed through
finish trough on spinning machines) is also recovered to some extent with
the help of vacuum strippers. Finish vacuum strippers are under the
vacuum of about 100 mmHg. Vacuum is developed by strippers vacuum
pumps (3 Nos., capacity 800 Cfm. At 280 mmHg) in basement and
passed on to vacuum strippers through vacuum receivers installed in the
basement. Vacuum receivers are cylindrical S.S. Tanks connected to
vacuum strippers through a 2” dia S.S. pipeline and to the suction header
of vacuum pump by a 3” dia sub header.
Finish solution thus accumulated in vacuum receiver is transferred to
finish pit tank with the help of a automatic drain pump called vacuum
receiver drain pump.
Conventional machines.
Parma (Tube spinning)
For ZENITH
Stretching
When yarn appears on the spinbath surface, it is wrapped on lower
godet and then taken to upper godet through hot stretch and in the
process, yarn is stretched.
Regeneration
The yarn is then taken to regeneration trough where the extra
chemicals dissolve in regeneration solution.
Washing
From regeneration yarn is washed with sodium carbonate solution
where the acid in yarn gets neutralize.
Finish Application
After washing the yarn is passed through finish oil. The finish oil is
lubricating oil which works as an antistatic agent. It helps to
eliminate the static charges produced in the further process in
textile.
Drying
After finish oil trough the yarn is winded on booster roller and then
to drier can. Drier can are maintained at 105°C where drying of
yarn takes place.
Winding
After drier can through guides and traveler yarn is winded on to an
aluminium bobbin. After getting required length of yarn, the
bobbin is changed and sent to Textile Department.
PIRNA MACHINES (TUBE SPINNING):
NATURE OF PACKAGE:
DOMESTIC BUYERS:
The yarn and cord is packed in the boxes and fabric is packed in
the form of roll.
FOREIGN BUYER:
The yarn, cord is packed in the form of Pallets and Fabric in the
form of Roll. The goods are normally dispatched in 20 and 40 Ft.
containers.
1. Manufacturing of rayon yarn, cord and fabric, both grey and dipped.
2. Conversion of nylon yarn in chafer fabric.
MANUFACTURING OF RAYON YARN, CORD AND FABRIC,
BOTH GREY AND DIPPED:
Elements of Weaving:
PRIMARY MOTIONS:
Shedding:
It is the name given to the motion which moves the heald frames up and
down in order to separate the warp sheet into two layers and create a
triangle in front of the reed (referred to as the shed) through which the
weft can be passed.
It is the means by which the weft is projected through the shed. This was
traditionally by shuttle, but more recently it is done by projectile, airjet or
water jet.
Beating up:
It is where the reed pushes the weft into the fell of he cloth to form fabric.
This requires considerable force. Hence the term, beating up.
SECONDARY MOTIONS:
There are three secondary motions in weaving : let off; take up
Let off motion - It ensures that the warp ends are controlled at the
optimum tension for the fabric that is being woven.
Take up motion - It withdraws cloth from the fell and stores it at the
front of the loom.
Ends per inch (or e.p.i.) are the number of warp threads per inch of
woven fabric. In general, the higher the ends per inch, the finer the fabric
is.
The number of ends per inch varies on the pattern to be woven and the
thickness of the thread.
Picks per inch (or p.p.i.) is the number of weft threads per inch of woven
fabric. A pick is a single weft thread, hence the term. In general, the
higher the picks per inch, the finer the fabric is.
Tex
Tex is a unit of measure for the linear mass density of fibers and is
defined as the mass in grams per 1000 meters. Tex is more likely to be
used in Canada and Continental Europe, while denier remains more
common in the United States and United Kingdom. The unit code is
"tex". The most commonly used unit is actually the decitex, abbreviated
dtex, which is the mass in grams per 10,000 meters.
Denier
Physical lab
The quality parameters are governed by in-house Physical Test Lab. The
following parameters are taken care of:
1840/1 Dtex Rayon tyre yarn :
Properties of CS2:
CS2 Furnace:
Insert loose brick in the opening of ash hole, seal it with earthen
mud.
Flush the sulphur separator with fresh sulphur.
Safety diaphragms are locked.
Sulphur feeding nozzles are poked and rubber tube connections
with the manometer is fixed.
Steam to sulphur doser and distributor is opened.
Current is maintained between 2100 – 2500 A. Current is
adjusted by charging the tapping of transformer.
Furnace pressure should not exceed 350 mm water.
Distance between electrodes = 2.45 M.
Consumption of Sulphur = 4.5 TPD.
Check parameters:
1. Furnace temperature.
2. Time
3. Electrical energy
4. Voltage, current, energy meter
5. Transformer oil temperature
6. Steam pressure.
Process:
Charcoal and molten sulphur are fed to the furnace. Gases are
taken out through pipe to separator where molten sulphur is stored.
Any Sulphur and Carbon particles present in CS2 gas are removed
there. Then the gas is passed through primary condenser. Here full
gas is not condensed, uncondensed gases contains H2S.
CS2 gas coming out from the furnace contains charcoal particles
and sulphur which are to be removed. To remove sulphur, the gases
are passed through sulphur separator which contains molten
sulphur. Sulphur present in the gas is condensed in the sulphur
separator. After separator, gas passes through primary condenser in
which water is flown in tubes. In secondary condenser, gas pass
through tubes with water around:
Chilled water inlet temperature (secondary) = 6 °C
Chilled water outlet temperature (secondary) = 12°C
Cooling water inlet temperature (primary) = 26°C
Cooling water outlet temperature (primary) = 29°C
Oil scrubbing system is used for separation CS2 is fed from bottom
to oil tower (4 Nos.) and oil from top through pumps. CS2 gets
absorbed in the oil and H2S does not H2S is taken to scrubber
where NaOH solution (NaOH H2O = 2.3) is sprayed to form Na2S.
Na2S system NaOH mixed with water in the ratio 20:80 is sprayed
to form Na2S in scrubber which is transferred to drier and after
drying, it is sold. There are 3 scrubbers out of which one is
working. Concentration of NaOH is kept 15% Na2S when
examined was found of concentration 150 – 170 gpl and free alkali
0 – 20 gpl.
There are two lime slurry tanks equipped with agitator for mixing
of lime. This slurry is continuously mixed with effluent water.
There are 5 lime dumping pit where dry lime is stored from where
it is discharged for slurry preparation. Apart from water from
Spinbath/Spinning/Textile/CS2/Power House, there is a line from
Water Treatment Plant also. This is partially mixed and rest is used
to make lime slurry.
Lime is added in the effluent. The zinc and acid reacts with lime to
form sludge. This water opens in the bottom of clarifier. The outlet
is sent to gate # 3 where its pH is checked and then is released.
Sludge which is settled and bottom of clarifier, is removed by
desludging pump.
POWER HOUSE
Turbine
Description
BOILER
Fire-tube boiler. Here, water partially fills a boiler barrel with a small
volume left above to accommodate the steam (steam space). This is the
type of boiler used in nearly all steam locomotives. The heat source is
inside a furnace or firebox that has to be kept permanently surrounded by
the water in order to maintain the temperature of the heating surface just
below boiling point. The furnace can be situated at one end of a fire-tube
which lengthens the path of the hot gases, thus augmenting the heating
surface which can be further increased by making the gases reverse
direction through a second parallel tube or a bundle of multiple tubes
(two-pass or return flue boiler); alternatively the gases may be taken
along the sides and then beneath the boiler through flues (3-pass boiler).
In the case of a locomotive-type boiler, a boiler barrel extends from the
firebox and the hot gases pass through a bundle of fire tubes inside the
barrel which greatly increase the heating surface compared to a single
tube and further improve heat transfer. Fire-tube boilers usually have a
comparatively low rate of steam production, but high steam storage
capacity. Fire-tube boilers mostly burn solid fuels, but are readily
adaptable to those of the liquid or gas variety.
Water-tube boiler. In this type,the water tubes are arranged inside a
furnace in a number of possible configurations: often the water
tubes connect large drums, the lower ones containing water and the
upper ones, steam and water; in other cases, such as a monotube
boiler, water is circulated by a pump through a succession of coils.
This type generally gives high steam production rates, but less
storage capacity than the above. Water tube boilers can be designed
to exploit any heat source and are generally preferred in high
pressure applications since the high pressure water/steam is
contained within small diameter pipes which can withstand the
pressure with a thinner wall.
WATER
COAL - Steam
AIR
Boiler 4 Specifications
Type AFBC
Make Thermax Limited
Capacity 30TPH
20%Musturd Husk
Primary SH 332 m2
Secondary SH 100 m2
Economizer 358 m2
Total 1662.9 m2
BOILER NO 1, 2 & 3
S NO PERAMETER UNIT SPECIFICATIONS
1 Type Travo Grate
Babcock and
2 Make Wilcox
3 design pressure psig 525
4 Capacity lb\ hr 65000
5 Steam temperature F 805
Feed water inlet o
C
6 temperature 104
7 heating surface Sq. feet 12243
8 Grate surface Sq. feet 195
9 Chimney height feet 112
BOILER
NO 4
1 Type AFBC
2 Make Thermax Limited
3 design pressure Kg/cm2 43
4 Capacity TPH 30
o
5 Steam temperature C 460
Feed water inlet o
C
6 temperature 104
7 heating surface M2 1662.9
8 Planum chamber area M3 19.762
9 Chimney height Meter 41
RUNNING DESIGN
S.NO. DESCRIPTION UNIT
PARAMETERS PARAMETERS
1 STEAM PRESSURE KG/CM2 40 43
0
2 STEAM TEMPERATURE C 440 460+ or - 5
3 STEAM FLOW TPH 30 30
4 WINBOX PR(1/2/3) MMWC 560 600/600
0
5 BED TEMP 1 COMP C 840/835 875/875
0
6 BED TEMP 2 COMP C 838/820 875/875
0
7 BED TEMP 3 COMP C 836/846 875/875
0
8 FURNACE TEMP C 720 850 - 895
9 FURNACE DRAUGHT MMWC -2.5 -5
0
10 F.W ECO I/L TEMP C 118 125
0
11 F.W ECO O/L TEMP C 157 175 - 195
0
12 D.SUP I/L TEMP C 360 406
0
13 D.SUP O/L TEMP C 353 330
14 F.D FLOW TPH 35.5 47.7
0
15 AIR TEMP AFTER APH C 125 150
0
16 FLUE GAS TEMP AT ECO I/L C 300 365
FLUE GAS TEMP AT ECO
0
17 0/L C 195 245
0
18 FLUE GAS TEMP AT ESP I/L C 128 155
%
19 UNBURNT IN BED ASH 0.5 0.3
%
20 UNBURNT IN BB ASH 15.13 6-7
%
21 UNBURNT IN APH ASH 26.06 8
%
22 UNBURNT IN ESP FLY ASH 23.8 10
%
23 BLOW DOWN 8 1 TO 3
24 PA PRESSURE MMWC 1200 1250
25 O2 % 5 4
RUNNING DESIGN
S.NO. DESCRIPTION UNIT
PARAMETERS PARAMETERS
1 Boiler feed water pressure Kg/Cm2 36 35
2 Boiler drum Pressure Kg/Cm2 35 35
3 SH outlet pressure Kg/Cm2 32.5 33
4 Main steam header Kg/Cm2 31.6 31.6
5 steam temperature °C 405 415
6 furnance temperature °C 700 Max 900
7 Water inlet temerature °C 104 104
8 Economiser water outlet °C 155
9 Feed water flow MT/hr 25 30
10 steam flow MT/hr 23 30
CM of
11 FD fan pressure H2O 6
CM of
12 Sec. air prussure H2O 46
CM of
13 Economiser water vac H2O 1
CM of
14 ID vac H2O -7.2
CM of
15 Furnance draft H2O -0.5 0.15
16 CO2 in gas outlet % 11 11.5
17 Flue gas inlet °C 287
18 Flue gas outlet °C 157 157
The water from drain condensate booster pump is fed through heat
exchanger where it gets heat from blow down water from Boiler. This
water is fed to settling tank (# 1) in which following chemicals are
added – Lime, Soda Ash, Calcium Magnesite, Steam (150 psig). The
water is then passed through filters (3 Nos.). Anthracite bed is there
as filter media. The water is stored in filtered water storage tank (# 1).
Through the booster pumps, the water is then passed through softener.
FROM softener, the water is passed to deaerator in which steam (150
psig), Phosphate and Hydrazine is added. Through the feed pumps the
water is passed through economizer and finally to Boiler Drum.
Blow down:
Since water is evaporating constantly, TDS (Total Dissolved
Solvents) in Boiler increases with time. To reduce this TDS, small
quantity of water is continuously taken out. This is called blow
down.
2p-m test:
Principle:
The basic objective of the ACVR Dept. Is to looks after the utility
i.e.
Air conditioning, ventilation & refrigeration, cooling water, plant
air, instrument air & Vacuum as per requirement to achieve the
quality product.
Key parameters
Chilled water
Cooling water
Vacuum
Air conditioning/refrigeration for process
Compressed Air ( Plant air and instrument air)
Fresh Air system
Ventilation system
REFRIGERATION
CAPACITY : 300 TR at 5 °c
Refrigerant : Water
Absorbent : Li.-Br Solution
AIR WASHER:
For supplying fresh air in Spinning, Textile, there are several air
washers. There are Seven Air washers for supplying Fresh air to
Spinning and Seven Air washers for supplying Fresh air. Generally,
two motors are required for each washer, one for fan and one for
pump. Capacity of fan motor is around 30 HP and that of pump
motor is 20 HP.
General details of air washer is like this.
Fresh air is sucked from the atmosphere and is first passed through
air filter. This air filter contains ferules in which fly ash or dust is
accumulated. The air then passed through a wet zone in which
water is sprayed from several nozzles. By passing through this, air
gets cooled. Then the air passes through eliminator which are
nothing but zigzag plates. Any water droplet present in air is
removed here. Then finally through a big fan the air is passed in
duct and is distributed to required area with the help of several
small ducts.
For maintaining RH water is sprayed through pump.
VENTILATION
Exhaust Fan
AIR WASHER
VACUUM SYSTEM