Sei sulla pagina 1di 4

Optimizing the

Design-to-Cost Cycle
By intensifying cooperation between process designers and cost engineers in the conceptual
stage of plant projects, better-informed decisions can be made on the economic viability of
plant projects

T
Stefan Bakker he global eco-
Cost Engineering nomic envi- 1 2
Consultancy ronment is
competitive, de- Ability to impact
manding and fast-paced, 1 cost and functional
In Brief
Effort/effect

capabilities
and becoming more so.
PRocess Design and The world has become 2 Cost of design
changes
cost more integrated through
the expansion of trade,
Fostering
communication
investment and com-
munications, leading to
Evaluating more international com- Time
alternative scenarios petitive pressure [1]. This
Object-oriented effect also leads to a continuous shortening Figure 1. The cost of design changes rise as plant projects
estimating of project lifecycles; decreasing profit mar- progress [2]
gins make it imperative that new plants move
Focus on Cost
quickly into operational mode. This trend re- factors such as reliability, available space
analysis
quires a change in how to approach the cost and safety concerns. Of course, capital cost
Become a learning engineering for new potential projects. will certainly be considered, but it is not their
organization To succeed in these challenging times, main concern. Cost engineers, on the other
Multidisciplinary chemical process industries (CPI) companies, hand, are less involved in the actual design
approach among others, need to be able to identify eco- of the process, but rather with how much it
nomically viable projects as early in the design is going to cost. Their findings can be com-
Concluding remarks
process as possible, thereby minimizing time pared to the business case drawn up by the
and money spent on potentially non-profitable project’s owner to assess the viability of that
endeavors. In order to remain competitive particular project design.
and maximize business performance, optimal In order to assess a design for its costs,
process designs must therefore be identified process engineers and cost engineers should
quickly with the minimum risk of rework, be- work closely together during the economic
cause design changes further in the project- analysis of the different solutions.
development cycle come at the expense of During conceptual and front-end engineer-
higher cost and more effort (Figure 1). ing and design (FEED) project stages, pro-
cess engineers should aim to accomplish
Process design and cost the following objectives:
The challenge of quickly identifying optimum • Informed decision-making. Analyze and
process designs reflects on two very differ- evaluate the different process alternatives
ent disciplines involved in a project. On one early in the project lifecycle in order to make
side, there are the process designers, re- a substantiated decision to “do the right
sponsible for process optimization, in terms project,” in terms of its economic viability
of throughput rate, process yield and prod- • Engineering time and cost savings. Allow-
uct purity. They must also take into account ing engineers to quickly and easily deter-
34 Chemical Engineering www.chemengonline.com december 2015
mine the cost implications of their process
design choices will reduce the number of
man-hours spent on evaluating expensive
process configurations and validating data
to support decision trade-offs.
• Re-use of (cost) engineering knowledge.
When process engineers are more involved
in the cost aspects of projects, it will
become much easier to re-use information
about cost objects (equipment groups)
when preparing the process design, result-
ing in more cost-effective solutions.
To achieve this, the process engineer and
cost engineer need to intensify their coop-
eration during the conceptual phase. This
article explores how this cooperation can
be organized to allow for informed decision-
making during the conceptual design and
FEED phases. becoming a complex and especially time- Figure 2. Modeling with
consuming task. process flow diagrams allows
the use of equipment groups
Fostering communication called “cost objects”
In many companies, the engineering disci- Evaluating alternative scenarios
plines that are involved in realizing a project In order to determine the required information
(such as process-, mechanical-, piping- and that should be transferred between the pro-
cost engineering) are segregated. This is often cess design and cost engineering groups, it
done to increase effectiveness within each dis- is important to understand the cost estimat-
cipline, but usually leads to reduced interde- ing methodology that is commonly applied
partmental cooperation, since the exchange during the conceptual and FEED phases of
of information tends to follow an “over-the- a project.
wall” principle, where personnel from different Traditionally, equipment-factored method-
disciplines are not fully aware of each other’s ologies, or simply “factor estimating,” is ap-
concerns and priorities. plied during the conceptual and FEED phases
It is important to have a robust and open of a project. This method uses the correlation
communication platform between these dis- between the total equipment costs and the
ciplines, because they are closely related to costs of related disciplines (piping, civil, elec-
each other. For example, the placement of trical and instrumentation and so on) to esti-
the equipment items determines to a large mate the total installed cost (TIC). For each
extent the costs of the main pipelines. The type of process equipment, different factors
complex task to come to an optimal plot are used to reflect the differences in the costs
plan requires close interaction between the of piping, foundations, cables, instrumenta-
different disciplines. tion and so on. Although this is a commonly
In order to evaluate the cost implications accepted estimating methodology during
and economic viability of a project, the cost early phases of project development, the ac-
engineer should assess the different design curacy of the TIC estimate strongly depends
alternatives. This requires an optimal flow of on obtaining the correct cost values for all
information between process engineers and equipment. This, in turn, requires precise and
cost engineers. correct information about equipment param-
Fortunately, the automation and digitaliza- eters, such as sizing, metallurgy and capac-
tion of most activities within these disciplines ity. Cost estimating software can use these
enables us to share and access useful in- equipment parameters as an input to para-
formation, although both process engineers metric equipment models (based on cost-
and cost engineers have their own (software) estimating relationships) to come up with an
tools to respectively design and estimate the accurate estimate for the equipment.
project. This arrangement, by the way, is a To quickly screen and compare different
good thing — specializations like these truly project designs on costs and economic vi-
need dedicated tools, specifically designed ability, a cost engineer needs to get the
for their purpose. But the potential gain of equipment parameters as an input from the
enabling easy exchange of information is evi- process engineer to make a factor estimate.
dent; it can prevent the evaluation of the cost This is where the integration between pro-
implications of each design alternative from cess-design tools and cost-estimating tools

Chemical Engineering www.chemengonline.com december 2015 35


2 and 3). A cost object can be, for example,
a pump with associated foundation, piping,
instrumentation and electrical work. The
cost objects are driven by the quantities of
the characteristic values. These quantities
(the generic equivalent of material take off
(MTO) quantities) can be priced using his-
torical data, to derive the total project cost.
One of the main advantages of focusing on
quantities, rather than costs, is that quanti-
ties are better understood by the engineers
and designers. This approach, thus, can im-
prove communication.
Objects
It is clear that object-oriented estimating
Objects requires more time, effort and (historical)
knowledge than factor estimating. However,
Figure 3. Recent software de- can deliver its value. When it becomes pos- since projects often have multiple go/no-go
velopments allow integration sible to feed the process data directly from stages, it can be a suitable supplement if, of
between process design and
cost engineering
the former to the latter, these data can be course, the required data are available. The
automatically mapped with cost models to method increases accuracy not only by ac-
produce a cost estimation for the simulated counting for a larger number of variables,
project scope. This way, the cost of process but also through the possibility of fine-tuning
designs can be estimated in less time, allow- specific components (for example, the pipe
ing for the estimation and consistent com- length associated with a storage tank). A
parison of multiple design alternatives. Ex- factor-estimating approach succeeded by
amples of the combination of two software object-oriented estimating thus further en-
solutions offering this functionality are now hances the evaluation process of the differ-
available, and together, the two can cover ent design alternatives.
the entire project lifecycle, from preliminary
process design to project execution. Focus on cost analysis
As a result, only the (most) profitable de- When, after careful consideration, a project
signs will be developed further, reducing the advances to the detailed engineering phase,
amount of (re-)engineering effort. the added details of the plant design as cre-
ated by the process-engineering team will
Object-oriented estimating eventually result in a (bulk) MTO.
Of course, such a high-level factor estimate Until not so long ago, it was common prac-
of a process design might get you through tice to manually translate such an MTO into
the first “go/no-go” decision gate, but it is in a cost estimate. Thanks to modern technol-
no way sufficient to actually build the plant. ogy however, it is now possible to speed up
The next step is the more advanced estimat- that process through an automatic analysis
ing methodology: object-oriented estimating. of the MTO based on commonly used terms;
Based on data from previously executed a cross-reference with historical data, possi-
projects, it is possible to identify characteris- bly supplemented by publicly available mar-
tic values from those projects. Characteristic ket data or preliminary quotes, can result in a
values are metrics used for object-oriented fairly accurate estimate.
estimating in order to determine the expected This method further supports the objective
project quantities, without having to involve a of identifying the most cost-effective design,
full design team to determine these quantities. since it simplifies making slight design altera-
Some examples of characteristic values are: tions while seeing the impact on costs in al-
• An average of 150 m pipe per equipment most realtime.
• An average size of 4.5-in. pipe
• An average of 0.9–1.2 control valves per Become a learning organization
equipment By no means does an approved project es-
• An average of 5.5 field instruments per timate represent the end of a project — it
equipment is at the execution phase that the estimate
is challenged by reality. Some might argue
These characteristic values can be used that, at this point in time, the project is out
to create “cost objects” — combinations of the hands of the cost engineer, but this is
of characteristic values for each discipline, actually a perfect opportunity to learn. Cost
representing the associated scope (Figures engineers should be sure to stay involved
36 Chemical Engineering www.chemengonline.com december 2015
throughout the project until the very end.
Every finished project can have a learning ef-
fect, through reusing the data of executed
projects in early type estimates for a future
project during conceptual design, creating a
continuous improvement cycle.

Multidisciplinary approach
Getting good insight into the cost implica-
tions of process designs is not the only ad-
vantage of the link between process- and
cost-engineering tools. Because process en-
gineers can almost directly see the cost im-
pact of changes in the process design, their
cost awareness will improve. From a techni- and cost engineers will significantly reduce Figure 4 . Cost objects con-
cal perspective, it could be a perfect solution the time required to estimate the different sist of the equipment item
to double the size of a heat exchanger, but and its associated disciplines.
process alternatives, while at the same time, Together the cost objects form
perhaps it will be more cost-effective to have
the number of re-engineering hours will be the complete project
two separate items to achieve the same re-
reduced, because unprofitable process
sult. Eventually, the process engineer will be
able to recognize those designs that are op- designs are identified early on in the project
timally cost-effective before effort and time development stage.
are actually expended to develop less effec- Enhanced flexibility. Process engineers will
tive designs. have the ability to quickly explore the cost
The reverse benefit is also realized by link- impacts of design changes, allowing more
ing process and cost engineering — the cost flexibility to explore “out-of-the-box” solutions
engineer will get a better understanding of that normally would not be considered.
the process engineer’s thoughts. This will im- Transparency. Through the use of the
prove the communication between the two object-oriented estimating method, based
disciplines. Keep in mind that it is not rec- on the input of high-level process equip-
ommended to make the process engineer ment information, the cost estimate can be
responsible for the cost estimate, or vice given a hierarchical structure, from detailed
versa. But in the end, by combining each information, up to the object level. This
other’s knowledge, the synergistic effect will provides a transparent view on the build-up
result in an optimal technical and economical of the cost estimate.
solution for the project. Communication. The integration of other-
wise isolated process- and cost-engineering
Concluding remarks tools will help to remove communication
CPI companies should strive to make better barriers between the two disciplines. n
decisions earlier in the project development
stage. To achieve this, good, early insight Edited by Scott Jenkins
into the technical, as well as the economic, Reference
viability of a project during the conceptual 1. Dahlmann, C., Technology, globalization and international competitiveness:
Challenges for developing countries. United Nations publications. Accessed
and FEED phases is required. Recent soft- from: http://www.un.org/esa/sustdev/publications/industrial_develop-
ment/1_2.pdf.
ware developments allow for a tight inte-
2. Chadron, R., Graph of design changes versus cost, Cost Engineering Consul-
gration between process design and cost tancy, 2015.
engineering software, making it possible to
compare design alternatives and choose the Author
most profitable solution (Figure 4). This will Stefan Bakker is a certified cost engineer at
result in the following: Cost Engineering Consultancy (IJsselmeeer
32e, 3332 EX Zwijndrecht, the Netherlands;
Informed decision-making. By having a Phone: +31 78 620 09 10; Email: SBakker@
clear understanding of the cost implica- costengineering.eu; www.costengineering.eu),
an independent cost-engineering services and
tions of process-design alternatives, better software provider established in 1996. Along
informed decisions can be made. Even with the company, Bakker has helped owners
during the conceptual phase, engineers will and EPC contractors worldwide in their cost
engineering activities on numerous industrial
be better able to choose the “right” project, projects. Cost Engineering Consultancy’s main areas of expertise
based not only on technical factors, but are: cost engineering services (cost estimating, cost control, risk
management); cost data development; cost engineering academy;
also economic ones. and total cost management software (Cleopatra Enterprise, a cost-
Engineering cost and time savings. The management solution that can now be linked to Honeywell UniSim
Design software (Honeywell Corp.) in order to get the required process
collaboration between process designers data to provide engineers with a cost estimation of the project.
Chemical Engineering www.chemengonline.com december 2015 37

Potrebbero piacerti anche