Sei sulla pagina 1di 3

A Driven Pile Advantage:

Batter Piles
By Edward Kavazanjian, Jr., Ph.D., P.E., Associate Professor and Interim Chair,
Department of Civil and Environmental Engineering, Arizona State University

Introduction Until the 1990s, batter piles were Historical Overview


The ability to install driven piles on a common means for carrying lateral Sources of lateral loads on deep
an angle, or batter, gives them a distinct loads, particularly when the lateral loads foundations include not only seismic
advantage with respect to their ability were large, there was a large unsupported loads but also winds, blasts and other
to carry lateral loads. Batter piles carry length, or there were weak soils at the impacts, waves and currents, and lat-
lateral loads primarily in axial compres- ground surface. Examples of such situa- eral earth pressures and displacements.
sion and/or tension while vertical deep tions include seismic design of bridges Throughout most of the 20th century,
foundations carry lateral loads in shear and design of marginal wharfs and other batter piles were employed routinely
and bending. When subjected to lat- port and harbor structures. In the 1990s, to carry lateral loads. Retaining walls
eral loading, batter piles will therefore following the poor performance of bat- founded upon soft soils, anchored bulk-
generally have a greater capacity and ter piles in a series of earthquakes, some heads, pile supported decks, breasting
be subject to smaller deformations than engineers began advising against the use dolphins, and bridge piers regularly em-
vertical piles of the same dimensions of batter piles. However, once the reason ployed batter piles. In fact, batter piles
and material. Large shear and moment for the poor performance of batter piles were the preferred methods for deep
loads induced at the pile head have was understood, engineers developed de- foundations subject to lateral loads
been a source of performance problems sign strategies to address these problems. until well into the second half of the
with batter piles in some cases. However, Using these strategies, batter piles have 20th century. Reasons for this include
these problems can be mitigated by ap- once again become an important weap- the extremely poor moment (bending)
propriate design and detailing of the on in the engineer’s arsenal for designing capacity of some of the more common
pile-structure connection. foundations subject to lateral loads. deep foundation types employed in

• Q4 • 2006 21
Graphics Courtesy of Mukhopadhyay, G., 2001, Geotechnical Challenges and Solutions for a
Fast-Track Container Terminal Project at a Contaminated and Seismically Active Site at Pier A
At the Port of Long Beach. Proceedings of Ports 2001 Conference in Norfolk, Virginia, April 29
– May 3, 2001.

STRUCTURAL FUSE SCHEME

the first half of the 20th century, e.g. 14-in. H-Piles) to support the main was due in large part to the develop-
timber piles, FrankiTM piles, Raymond piers, including several rows of batter ment of reliable procedures for their
Step TaperTM piles, and the difficulties piles to carry the lateral loads. In the design and construction, including
in analyzing vertical piles subject to 1970s and 1980s, more and more bridg- the development of p-y analyses for
lateral loads. es employed large diameter drilled design of piles and drilled piers subject
Through the 1960s, major bridges piers as foundation elements. The in- to lateral loads. However, batter piles
routinely employed a large number creased popularity of large diameter still remained a popular means of car-
of relatively small driven piles (e.g. drilled piers for bridge foundations rying the large lateral loads associated

• Q4 • 2006 23
with pile-supported decks and for lim- pile-structure connection to allow it to
iting the displacement of foundations rotate without a loss of capacity. With
subjected to lateral loads. this understanding of the source of the
Towards the end of the 20th cen- observed poor performance and how it
tury, poor performance of batter piles could be mitigated, in the past few years
in a series of earthquakes cast batter batter piles have re-assumed their tradi-
piles in a poor light. The performance tional role in withstanding large lateral
of prestressed concrete batter piles loads applied to deep foundations. The
supporting container cranes at the piers for the new San Francisco Bay
Port of Oakland 7th Street Terminal Bridge East Span Replacement struc-
in the 1989 Loma Prieta earthquake ture are perhaps the best example of this
was the first of several such incidents. renewed acceptance of batter piles for
Liquefaction-induced lateral displace- lateral loads. Each pier is supported by
ment of a rock fill dike through which six 8-ft diameter steel pipe piles driven
the batter piles were driven resulted in on a batter through the underlying bay
shearing of the pile heads. The pier was mud to firm bearing.
retrofitted using large diameter verti-
cal drilled piers to replace the batter Batter Pile Design Philosophy
piles at this location. Similar damage Several different approaches to
was observed in prestressed concrete the design of batter piles are now used
batter piles in the Port of Los Angeles in practice. One approach, present-
in the 1994 Northridge earthquake ed in Chapter 7, Foundation Design
and in the 1996 Manzanillo, Mexico Requirements, of the 2000 National
earthquake. As a result of these inci- Earthquake Hazard Reduction Program
dents, some engineers began advising design guidance for buildings, states
Wharf Construction - Structural fuse
against the use of batter piles. For in- that “The connection between batter
can be seen in foreground.
stance, a 1998 monograph on Seismic piles and grade beams or pile caps shall
Photo Courtesy of Mukhopadhyay, G., 2001, Geotechnical
Design of Port and Harbor Facilities be designed to resist the full strength of Challenges and Solutions for a Fast-Track Container Terminal
published by the American Society the pile acting as a short column. Batter Project at a Contaminated and Seismically Active Site at
Pier A At the Port of Long Beach. Proceedings of Ports 2001
of Civil Engineers Technical Council piles shall be capable of resisting forces Conference in Norfolk, Virginia, April 29 – May 3, 2001.

on Lifeline Earthquake Engineering and moments from the load combina- pile length or in weak soils where there is
advised that “The use of batter piles tions ...”. An alternative to this “brute little lateral support, as vertical founda-
at ports is typically not encour- force” method of batter pile design is tion elements typically carry lateral loads
aged because of their poor seismic the use of a structural “fuse” to limit the by bending over their top 10 diameters
performance during past earthquakes.” forces at the pile head. One manifesta- of length below the pile cap. Over the
As the cost of not employing batter tion of this approach is the proposed range of batters typically employed in
piles for many seismic design problems AASHTO guidelines for seismic design practice the bending capacity of a batter
became apparent, many engineers began of bridges, which allow for “capacity pile is essentially the same as that of a
to question the conclusion that batter protected” pile caps in which the col- vertical pile, thus lateral load carried as
piles were unsuitable for seismic load- umns above the pile caps are designed axial load by the batter pile is essentially
ing. Forensic analysis of the observed to yield without forming a collapse entirely “additional” lateral capacity for
failures suggested that the poor perfor- mechanism before the elastic limit of the pile Batter piles are not suitable in
mance of batter piles in seismic events the batter piles and pile cap connec- all situations. Batter piles are particu-
was due to the fact design analyses typi- tions are exceeded. Another example of larly problematic when the soil through
cally assumed the head of the pile was this approach is the innovative design which the pile is driven may settle, as
“pinned”, i.e. free to rotate, and thus was of the Port of Long Beach Pier A pile the settlement will impose lateral loads
not designed to sustain any moment supported deck, where the prestressed and bending moments along the entire
loading. However, due to the design de- concrete piles are connected to a steel length of the pile. Furthermore, careful
tails, the heads of the prestressed con- beam below the deck that is designed to attention is required to the design of the
crete piles could not rotate freely and yield and rotate after the piles undergo pile / structure connection to provide ei-
thus were subjected to large shear and 1 inch of elastic compression. ther sufficient strength to resist applied
moment loads, resulting in failure at moment and shear loads or sufficient ro-
the pile head. This suggested that the Conclusion tational ductility to limit loads at the pile
observed deficiency in the performance Batter piles can provide driven pile head to the pile capacity. However, with
of batter piles could be remedied by a foundations a significant advantage over proper attention to these details, batter
combination of strengthening the pile drilled piers and other vertical elements piles remain the most economical way
head so that it could resist the applied for deep foundations subject to lateral to carry lateral loads in many common
moment and shear loads and providing loads. Batter piles are particularly advan- situations, providing a true driven pile
sufficient ductility to the pile head or tageous when there is a large unsupported advantage. ▼

• Q4 • 2006 25

Potrebbero piacerti anche