Sei sulla pagina 1di 7

Downloaded from http://iranpaper.

ir
http://www.itrans24.com/landing1.html

252
2012 Conference on Smart Electric Grids Technology (SEGT2012)
December 18-19, 2012, Tehran, Iran

Allocation and Sizing of a DG Unit Considering ZIP Load Model

M.Sadeghi*, M.Kalantar**
*Iran University of Science and Technology. Mahmood.sadeghi@gmail.com
** Iran University of Science and Technology, kalantar@iust.ac.ir

Index Terms—Distributed Generation, Dispersed Generation, DG, Allocation, Load Model, ZIP

Abstract— This paper proposes an algorithm to calculate systems. In addition they considered different load
the optimal size and to locate the corresponding optimum models with voltage dependency. Ref [5], maximized
place for minimizing power loss of the power system with the integration of DG and energy export minimizing
considering load models for each bus. The method is tested
losses and short circuit level with time varying load
on 30 bus test system. The results is analyzed and compared
with that of comprehensive load flows and an approximate model. The generator modeled with wind generation
loss formula based method. Results show that the proposed and the optimization method is based on multi
approach to determine the load model and the suggested objective optimization with NSGA. In[6], Soroudi and
algorithm lead to the best placement of the DG unit for loss Ehsan minimized the cost of active losses, investment
reduction. The DG that is considered in this paper is a and operation cost of DG and emission cost. The load
constant PQ generator unit, the “ZIP” load model is used in
is modeled with a multi load level and the generator is
this paper as well. The method by which the load models are
determined in this paper is least squares method. modeled as negative PQ load with variable power
factor. The optimization solution is particle swarm
A. Introduction optimization method. Ref [7], has worked on sitting
Distributed Generation (DG), which consists of and sizing of DG for optimal microgrid architecture
distributed resources, can be defined as electric power with simulated annealing optimization method. Ref [8],
generation within distribution networks or on the describes a successive elimination algorithm to place
customer side of the network [1]. Distributed and size the DGs. Ref [9], describes a new heuristic
Generation (DG) is related with the use of small approach based on cost benefit analysis to optimally
generating units installed in strategic points of the determine the capacity and location of the DG from the
electric power system close to load centers [2]. The prospect of a distribution company. Ref [10], is about
technologies used in DG comprise as: micro turbines, optimal load flow with second order algorithm method.
fuel cells, wind turbines, photovoltaic cells, gas Ref [11], is about genetic algorithm and herford ranch
turbines, biomass fuelled gas turbines, etc. In order to algorithm which can find optimums.
minimize line losses, improve the voltage profile and As seen above, the problem of the placement
all other positive effects, it is crucially important to of the DG unit is considered in many papers and
determine the size and location of local generation to studies but in approximately all the studies the load in
be placed. So, in recent years, several studies have each bus is considered as constant load or it is
considered techniques for locating DG units on considered as special loads, such as increasingly loads,
distribution systems. Methods of different procedures uniformly distributed loads, centrally distributed loads
are summarized as below: or etc[17]. The placement of DG unit with considering
Ref [4], worked on optimal sitting and sizing of load models or nonlinear loads is not studied nearly
of Distributed Generations in radial and networked in the papers. Ref [12] is one of the papers that studies
about the allocation and sizing of the DG unit with

978-1-4799-3040-1/13/$31.00 ©2013 IEEE


Downloaded from http://iranpaper.ir
http://www.itrans24.com/landing1.html

253

considering of nonlinear load models. This paper This paper ignored from the frequency
analyzes the issue of the sizing and sitting of the DG variations, so the discussed model is in equations (3),
unit with residential, commercial, constant, industrial (4) [14]:
and mixed load models. Another paper is written by
this author about the sizing and sitting of the DG unit ⎡ V V ⎤
with GA algorithm. This paper assumes load models P = P0 ⎢ Z p ( ) 2 + I p ( ) + Pp ⎥ (3)
for each bus in a power system and after this ⎣ V0 V0 ⎦
assumption the placing and sizing of the DG is
analyzed.
One of the important issues about simulating a ⎡ V V ⎤
power system with load models for each bus is that the
Q = Q 0 ⎢ Z q ( ) 2 + I q ( ) + Pq ⎥ (4)
⎣ V0 V0 ⎦
load models should be simulated in a way that they can
show the specifications of the loads well, but in these
papers the load models of the buses is not calculated
and are assumed.
Z p + I p + P p = 1 (5)
The aim of this paper is to compare the
behavior of the power system with and without load
models, so at the fist step the algorithm of finding the Z q + I q + Pq = 1 (6)
load models for each bus in a power system is shown.
At the second step the algorithm of finding the best
size and the best place for the DG unit in a power Z p : % Resistance
system with an approximate function is shown. At last
the best places for the DG unit in a power system are Z q : % Reactance
analyzed and a priority list of the best places is
provided. After finding the priority list for placement
I p : % Active Current
of the DG unit the loads replaced with the load models I q : % Reactive Current
for each bus and then the priority list for placement of
the DG unit is determined. Finally the results of the Pp : % Active Power
proposed method and the power loss formula based
methodology [16] will be compared and the superiority Pq : % Reactive Power
of the proposed algorithm will be clarified. P0 , Q0 ,V0 : Nominal Values
V : Voltage of the Buses
B. ZIP Load Model
The constant active & reactive power loads is
used in the general load flow programs, but it should be C. Calculation of Parameters
considered that current, voltage and impedance of the As mentioned before, ZIP load model consists
load in all the times are not constant and varied of three parameters, constant impedance (Z), constant
dependent on the load, so the results of constant power current (I) and constant power (P), so in this section
consumption based calculations can not be correct. these parameters must be calculated. ZIP parameters
The load model that is considered in this paper can be determined by some methods. The optimization
is “ZIP” load model [13]. This load model consists of method that is used in this paper is Least Squares
three parts: Constant impedance (Z), constant current solution.
(I) and constant power (P). The constant current, The objective function that should be
constant power and constant impedance model that is minimized is as equation (7):
known as “ZIP” model is one of the most important
and appropriate models. n
⎛V ⎞
2
⎛V ⎞ ⎛P ⎞
This model is formulated in different shapes λ = ∑ ( Z P ⎜⎜ i ⎟⎟ + I P ⎜⎜ i ⎟⎟ + PP − ⎜⎜ i ⎟⎟ ) 2 (7)
that are shown in equations (1), (2) [13]: i =1 ⎝ V0 ⎠ ⎝ V0 ⎠ ⎝ P0 ⎠

The Vi and Pi are the input values. These are


⎡ V V ⎤ (1) the voltage and the power consumption at the
P = P0 ⎢ Z p ( ) 2 + I p ( ) + Pp (1 + K p f ) ⎥
V0 V0 correspond voltage of a bus. To simplify the above
⎣ ⎦
relation, we assume that the Vi and Pi values are in pu
base. So the above equation (7) is simplified to the
P ⎡ V 2 V ⎤
= ⎢ P1 ( ) + P2 ( ) + P3 ⎥ (1 + L DP Δ f ) (2) equation (8):
P0 ⎣ V 0 V0 ⎦
n

∑ (Z )2
These models are other derivations of the λ = P .V i 2 + I P .V i + PP − Pi (8)
general model in the fifth and seventh equations. i =1
Downloaded from http://iranpaper.ir
http://www.itrans24.com/landing1.html

254

The procedure of solving the problem is to


rij (12)
β ij = sin( δ i − δ j )
derive from the above equation to each parameters (Zp , ViV j
Ip , Pp ). After derivation, each equation should be
equal to zero. At last there will be 3 equations in 3
variables that should be solved. Pi = PGi − PDi , Qi = QGi − QDi (13)
To simplify and to solve the problem in order
to achieve the ZIP parameters, the equations are written
in matrix format. The matrix equation (9) is resulted. PGi & QGi are injection powers of generators to the
So the matrix of variables is calculated from
the reverse of the matrix (3*3) multiplied in the matrix bus.
(3*1). Equation (10) shows the ZIP parameters that are PDi & Q Di are the loads.
achieved in matrix format. So there should be some
Pi & Qi are the active and reactive power of the
points for each node that is calculated from dispatching
of the power system. These points can be achieved buses.
from the measurement devices that are placed in each
node in some hours in a day or in some hours in a week E. Proposed Algorithm
too. After five measurements (for example) with the
The purpose of this paper is to compare the
measurement devices or dispatching the power system
result of allocation of DG unit in a power system with
for each bus, there are five points for each node to
the same power system when the loads in each bus are
calculate the ZIP parameters. Now a ZIP load model is
simulated with a “ZIP” load model. So, at the first step,
calculated for each bus.
the optimum size of the DG unit for each bus in order
to minimize the power loss of the system is calculated.
⎡n 4 n n
⎤ ⎡n 2⎤
⎢∑2Vi ∑2V ∑2V ⎢∑2Pi .Vi ⎥
3 2 The algorithm used in this section is based on the
i i⎥ complete enumeration. At the end of this section all of
⎢ i=1 i=1 i=1
⎥ ⎡ZP ⎤ ⎢ i=1 ⎥ (9)
⎢n 3 n n
⎥ ⎢ ⎥ ⎢n ⎥ the buses are ranked in a priority list (the minimum
⎢∑2Vi ∑2V i
2
∑ 2Vi ⎥ × ⎢I P ⎥ = ⎢∑2Pi .Vi ⎥ power loss to the maximum one). At the second step,
⎢ i=1 i=1 i=1 ⎥ ⎢P ⎥ ⎢ i=1 ⎥ we assume that the active and reactive generation of
⎢n 2 n
⎥ ⎣ P⎦ ⎢ n ⎥
⎢∑2Vi ∑2V ⎢∑2Pi ⎥
2n ⎥ the DG unit for each bus is given (the values that are
i
⎣ i=1 i=1 ⎦ ⎣ i=1 ⎦ calculated in the last step for each bus). The loads of
each bus are modeled with “ZIP” load model. The DG
units place in the buses and the power loss of the
−1 system with the help of equation (11) is computed for
⎡n 4 n n
⎤ ⎡n ⎤
⎢∑2Vi ∑2Vi3 ∑ 2Vi 2 ⎥ ⎢∑2Pi .Vi 2 ⎥ each placement of the DG unit. At the end of this step,
a priority list from minimum power loss to the
⎡ZP ⎤ ⎢ n ⎥ ⎢ i=1 ⎥
i =1 i =1 i =1

⎢I ⎥ = ⎢ 2V 3 ⎥ ⎢n ⎥ maximum one is formed. Now, the priority lists of the


n n

⎢ P ⎥ ⎢∑ ∑2V ∑ 2Vi ⎥ × ⎢∑2Pi .Vi ⎥ (10)


2
i i buses in the two steps, is compared.
⎢⎣PP ⎥⎦ ⎢ i=n1 i =1 i =1 ⎥ ⎢ i=1 ⎥ The algorithm of the computational procedure is
⎢ n ⎥ ⎢n ⎥
⎢∑2Vi ∑2V ⎥ ⎢∑2Pi ⎥
2
i 2n summarized as below. There are 3 steps in this
⎣ i=1 i =1 ⎦ ⎣ i=1 ⎦ algorithm, at the first step the optimum DG size for
each bus is computed and at the second step the
D. Loss equation priority list of the buses with the loads in each bus is
The purpose of this paper is to find the best found. At the last step the priority lists of the last 2
place for the DG unit to decrease the real power loss of steps will be compared.
the power system. Real power loss in a system is given 1. Sitting and sizing of the DG unit in the power
by (11) [16]. This equation is essential in finding the system.
best size and place of the DG unit, but it can not 1.1. Run the base case load flow.
receive the exact power loss of the power system. 1.2. Consider the active power limits of a DG
unit.
N N 1.3. Change active power from the minimum
PL = ∑∑[αij (Pi Pj +QiQj ) + βij (Qi Pj − PiQj )] (11) value to the maximum value with small steps.
i=1 j =1 1.4. In each of the real power steps, change the
reactive power from zero to eighty percent of
rij the real power on that step and then calculate
α ij = cos( δ i − δ j ) (12)
V iV j the loss from equation (11).
1.5. Store the reactive power that gives the
minimum loss for the related active power.
Downloaded from http://iranpaper.ir
http://www.itrans24.com/landing1.html

255

1.6. Choose the real power with its reactive power The active power loss computed with load
that gives the minimum loss for that bus. flow program is 4.932 MW, and when the loads are
1.7. Repeat these steps for all of the buses and replaced with the load models the power loss will be
find the best size (active and reactive power) 5.101 MW. As seen on the table, there are some
of the DG units for each bus. differences in the calculated loss in three methods.
1.8. Compare the losses of each state and find the A computer program has been written in
minimum loss in the distribution system. MATLAB7 to calculate the load model of each bus,
1.9. Store the bus that gives the minimum loss placement and sizing of the DG unit for the power
with its DG sizes. system. The PSAT software has been used for the
1.10. Run the base case load flow with DG. calculations related to load models in the power system
1.11. Rank the buses in a priority list from the and load flows.
minimum power loss to the maximum one. Fig.2 shows the optimum DG values obtained
2. Sitting of the DG unit in presence of the load models. for each bus.
2.1. Run the base case load flow.
2.2. Place the DG unit with the given value in
each bus.
2.3. Calculate the power loss of the system with
the help of load flow program in each
placement of the DG unit.
2.4. Rank the buses in a priority list from the
minimum power loss to the maximum one.
3. Compare the priority lists of the 2 steps.

F. Simulations
The proposed algorithm is tested on 30 bus
test system [16]. There are some changes in the test Fig.1.Single Line Diagram of a 30 Bus Test System
system that is used in this paper with the test system in
the ref [16]. The original 30 bus test system [16] has 1
generator, 32 lines and 27 constant PQ loads, but in Table 2 shows the load models computed for
this paper an admittance is considered for some buses each bus.
as a constant impedance load, on the other hand the Table 3 shows the real power loss of the
loads of buses is modified in order to calculate an power system in 3 methods with optimum size of the
appropriate ZIP load model for each bus. Fig.1 shows DG unit obtained in fig.2. The power loss in the first
the modified 30 bus test system. column that is based on the loss formula method [16],
Table 1 shows the real power loss of the is computed with equation (11). The third column
power system in 3 methods in presence of the optimum shows the losses are calculated with load flow program
size of the DG unit that is obtained in fig.2. The power that is the real power loss of the power system. The
loss of the base system without the DG unit is shown in fifth column shows the power loss of the test system is
table 1. The power loss calculated with equation (11) is computed with the proposed method.
4.821 MW.

Fig.2 The Active & Reactive Generation of the DG Unit for each Bus
Downloaded from http://iranpaper.ir
http://www.itrans24.com/landing1.html

256

As seen on the second and the fourth columns of table Table2. The Load Models Calculated for Each Bus.
3, the calculated power loss with the proposed method
is nearer to the real value calculated with load flow
program (calculated in the second column) for example Bus P(Active Power) Q(Reactive Power)
when the DG unit with size of 1.5 MW, 1.2 MVAr is No. Z% I% P% Z% I% P%
placed in bus 11, the power loss with the loss formula
based method [16] will be 4.666 MW, but the real 2 89.69 0 10.31 96.62 0 3.38
value of the active power loss is 4.087 MW, so there is 3 100 0 0 100 0 0
14.16% difference with the real value, but the proposed
method shows 4.121 MW active power loss that has 4 81.3 0 18.7 93.46 0 6.54
0.83% difference with the real value. In all of the 10.6
5 56.12 0 43.88 89.37 0
values the proposed method has the minimum 3
difference with the real value that is achieved with the 6 0 0 0 0 0 0
load flow program.
The reason of these differences is because of the 7 0 0 0 0 0 0
method of calculation. The values of the first column 8 76.98 0 23.02 96.49 0 3.51
are computed with equation (11) that is not an exact
formula and it gives an approximation of the real 9 0 0 100 0 0 100
power loss. With the help of this equation, consisting 10 0 0 0 0 0 0
of the priority list of DG allocation and finding the
optimum DG size, as seen in fig.2, can be possible, but 11 0 0 100 96.62 0 3.38
in order to calculate the exact power loss for checking 28.5
12 0 0 100 71.43 0
the accuracy of the priority list of the DG allocation 7
and analyzing the real power loss with load models 33.3
13 0 0 100 66.67 0
instead of the loads, the load flow program is run and 3
15.4
the results are shown. As seen on the table, the results 14 40.08 0 59.92 84.60 0
0
of the 3rd and the 5th columns have a little difference
that can be neglected. When the loads replaced with the 15 91.58 0 8.42 0 0 100
load models in the buses, and after that the DG unit is 16 72.99 0 27.01 97.01 0 2.99
placed in each bus, there will be a new topology from
19.7
software point of view, so there will be a little 17 17.45 0 82.55 80.21 0
9
difference in the results of these load flows that can be
18 0 0 100 0 0 100
neglected.
Table 4 shows the priority list of placement of 19 0 0 100 0 0 100
the DG unit is obtained from load flow program.
According to this table the buses 10, 11, 12, 24, 25, 26, 20 0 0 100 0 0 100
27 are the best buses for placement of the DG unit. 36.9
21 35.83 0 64.17 63.02 0
Table 5 shows the priority list of the DG 8
allocation that is obtained from loss formula based 22 0 0 100 0 0 100
method [16], equation (11) and table1. The buses are 62.6
ranked from minimum power loss to the maximum 23 31.88 0 68.12 37.36 0
4
one. According to the table4, buses 23, 24, 25, 26, are 24 89.69 0 10.31 0 0 100
the best locations for placement of the DG unit,
28.8
Because of the minimum power loss after placement of 25 37.49 0 62.51 71.12 0
8
the DG unit in the power systm. 45.7
26 13.57 0 86.43 54.26 0
4
Table1. The power loss of the base system 27 0 0 100 0 0 100

28 0 0 100 0 0 100
17.9
Load Flow 29 33.48 0 66.52 82.03 0
7
Eq.(11) With With Load 30 0 0 100 90.91 0 9.09
Loads Model
4.821 MW 4.932 MW 5.101 MW
Downloaded from http://iranpaper.ir
http://www.itrans24.com/landing1.html

257

Table 3. Power loss of the test system after DG allocation

%Increment of power loss %Increment of power loss Power Loss


Bus Power Loss Power Loss
with Eq.(11) to the power with load model to the with Load
No. with Eq.(11) with Load Flow
loss with load flow power loss with load flow Model
6 4.809 2.56 4.689 2.60 4.811
7 4.752 7.95 4.402 1.72 4.478
8 4.696 14.1 4.116 1.02 4.158
9 4.687 14.12 4.107 0.92 4.145
10 4.677 14.13 4.098 0.88 4.134
11 4.666 14.16 4.087 0.83 4.121
12 4.687 14.46 4.095 0.81 4.128
15 4.813 0.90 4.770 2.83 4.905
16 4.803 2.78 4.673 2.59 4.794
17 4.787 5.26 4.548 2.07 4.642
18 4.766 6.76 4.464 1.66 4.538
19 4.739 8.10 4.384 1.28 4.440
20 4.715 9.75 4.296 0.91 4.811
21 4.692 9.65 4.279 0.75 4.478
22 4.667 11.07 4.202 0.43 4.158
23 4.643 12.89 4.113 0.19 4.145
24 4.618 14.48 4.034 0.02 4.134
25 4.631 14.51 4.044 0.27 4.121
26 4.646 14.26 4.066 0.22 4.128
27 4.662 14.49 4.072 0.56 4.905
28 4.753 7.15 4.403 1.7 4.794
29 4.753 8.00 4.401 1.7 4.642
30 4.753 8.05 4.399 1.7 4.538

Table 4. priority list of placement of the DG unit with load flow results

Rank Losses between Bus No.


1 4.0 MW – 4.1 MW 10, 11, 12, 24 , 25 , 26 , 27
2 4.1 MW – 4.2 MW 8 , 9, 23
3 4.2 MW – 4.3 MW 20, 21, 22
4 4.3 MW – 4.4 MW 7, 19, 28, 29, 30
5 4.4 MW – 4.5 MW 18
6 4.5 MW – 4.6 MW 1718
7 4.6 MW – 4.7 MW 6,16
8 4.7 MW – 4.8 MW 15

Table5. Priority list of placement of the DG unit with loss formula based

Rank Losses between Bus No.


1 4.6 MW- 4.65 MW 23 , 24 , 25 , 26
2 4.65 MW- 4.70 MW 8 , 9 , 10 , 11 , 12 , 21 , 22 , 27
3 4.70 MW – 4.75 MW 19 , 20
4 4.75 MW- 4.80 MW 6 , 7 , 16 , 17 , 18 , 28 , 29 , 30
5 4.80 MW – 4.85 MW 15

Table 6 is the priority of the placement of the Table 7 summarizes these results. As seen on
DG unit achieved from the proposed methodology. The the table, the results of the proposed method are
buses 24, 25, 26, 27 are the best places for placement approximately the same as the real results.
the DG units.
Downloaded from http://iranpaper.ir
http://www.itrans24.com/landing1.html

258

Table6. Priority list of placement of the DG unit with load model results

Rank Losses between Bus No.


1 4.0 MW – 4.1 MW 24 , 25 , 26 , 27
2 4.1 MW – 4.2 MW 8 , 9 , 10 , 11 , 12 , 23
3 4.2 MW – 4.3 MW 22
4 4.3 MW – 4.4 MW 20 , 21
5 4.4 MW – 4.5 MW 7 , 19 , 28 , 29 , 30
6 4.5 MW – 4.6 MW 18
7 4.6 MW – 4.7 MW 17
8 4.7 MW – 4.8 MW 16
9 4.8 MW – 4.9 MW 6
10 4.9 MW – 5.0 MW 15
Table7. Comparison of the results of different approaches

Power Loss (MW)


Optimum Locations
With Load Flow With Eq.(11) With Load Model
24 4.034 4.618 4.035
25 4.044 4.631 4.055
26 4.066 4.646 4.075
27 4.072 4.662
Ochoa,L.F., Padiha-Feltrin, et 4.095
al.,”Time Series Based Maximization
of Distributed Wind Generation Integration”, IEEE Trans.
G. CONCLUSION Energy Conversion, vol.3, no.3, pp.968-974.
Soroudi A,”Multi Objective Distributed Generation Planning in
This paper modeled the loads of a power Liberalized Electricity Market”, in Proc. 2008, pp.1-7.
system with ZIP load model with least squares Maaikarjuna R.Vallem, Joydeep Mitra,”Sitting and Sizing of
optimization method and analyzes the effect of load Distributed Generation for Optimal Microgrid Architecture”,
Power Symposium, 2005. Proceedings of the 37th Annual
models on placement of DG unit and compare it with North American, pp. 611-616.
the state that there are loads on the buses instead of the R.E.Brown,” Sitting Distributed Generation to Defer T&D
load models (there is only the loads connected to the Expansion”, IEEE/PES Transmission and Distribution
Conference and Exposition, 2001, vol.2, pp.622-627.
buses). The results show that the load model can W.El-khattam, K.Bhattacharya, Y.Hegazy, M.M.A.Salma, “Optimal
simplify the placement of the DG unit and gives the Investment Planning for Distributed Generation in a
correct location for placement of the DG unit. Competetive Electricity Market”, IEEE Trans. On Power
Systems, vol.19, no.3, aug 2004.
The most important specification of this paper S.Rau and Y.H.Wan,”Optimum Location of Resources in Distributed
is to simulate the loads of a power system with a load Planning”, IEEE Trans. Power System, vol.9, no.7, 1994,
model that can show the behavior of the power system pp.2014-2020.
K.H.Kim, Y.J.Lee, S.B.Rhee, S.K.Lee, S.Ok.You, “Dispersed
well. After modeling the loads with ZIP load model Generator Placement Using FUZZY-GA in Distribution
allocation of the DG unit is done. The results in Systems”, IEEE Summer Meeting, vol.3,july 2002, pp.1148-
compare with the state that there are only the loads (the 1153.
Devender Singh, R.K.Misra, Deependra Singh,” Effect of Load
loads are not modeled) showed that this load model can
Models in Distributed Generation Planning”, IEEE Trans.
apply to the system and will show the specification of Power Systems, vol.22, no.4, Nov.2007,pp.2204-2212.
the power system well. This method is applied on a 30 IEEE Task Force,”Standard Load Models for Power Flow and
bus test system and the results of the simulation show Dynamic Performance Simulations”, IEEE Trans. Power
Systems, vol.10,no.3,aug 1999.
the applicability of the method. M.Haghifam, K.E.Jome, B.Khaki, “Analyzing the Effect of Different
Load Models on Load Flow of the Distribution Power
H. References Systems”, the Ninth Students Electrical and Electronic Eng.
T.Ackermann, G.Anderson, L.Soder, “Distributed Generation: A Conference 1385, Tehran, Iran.
Definition”, Electric Power System Research 57, 2001, pp.195- Ines Romero Navarro, “Dynamic Load Models for Power Systems,”
204. Licentiate Thesis, Lund University, Department of Industrial
Carmen L.T.Borges, Djalma M.Falcao,”Optimal Distributed Electrical Engineering and Automation, 2002.
Generation Allocation for Reliability, Losses and Voltage Naresh Acharya, Pukar Mahat, N.Mithulananthan, “An Analytical
Profile Improvement”, Electric Power and Energy Systems, Approach for DG Allocation in Primary Distribution Network”,
28(2006), pp.413-420. Electrical Power and Energy Systems 28, Science Direct,
S.W/Illerhaus, J.S.Versteg,”Optimal Operation of Industrial CHP pp.559-678, 2006.
Based Power Systems in Liberalized Energy Markets”, IEEE Caisheng Wang , M.Hashem Nehrir , "Analytical Approaches for
Industry Applications Conference, 2000, vol..2, pp.901-908. Optimal of Distributed Generation Sources in Power Systems "
R.K.Singh,S.K.Goswamj,”Optimal Sitting and Sizing of Distributed , IEEE Trans. On Power Systems, Vol. 19, No.4, November
Generations in Radial and Networked Systems Considering 2004
Different Voltage Dependent Static Load Models”, 2nd IEEE Amany M.El-Zonkoly, "Optimal Placement of Multi DG Units
International Conference on Power and Energy (PECON), Including Different Load Models Using PSO", Scientific
December 1-3, 2008, Johor Baharu, Malaysia, pp.1535-1540. Research, Smart Grid Renewable Energy,2010,1,160-171

Potrebbero piacerti anche