TECNOLOGY UNIVERSITY OF PANAMA

FACULTY OF CIVIL ENGINEERING


BACHELOR'S DEGREE IN CIVIL ENGINEERING

PLANNING AND CONTROLLING CONSTRUCTION PROJECTS


HOMEWORK 1

TEACHER:
MARIA LOURDES PERALTA FRIAS

STUDENT:
ELOY SOTO
9-733-1153

GROUP:
1IC251

DATE:
24-8-2017
Problem 1
You have been given the information of construction for a small residential building.
Estimate the critical Path. Complete the Table.
i j Activity ES EF LS LF TF FF
2 4 4
2 6 8
2 8 7
4 6 d1 0
4 14 6
6 12 5
8 10 6
10 12 d2 0
10 16 5
12 18 4
14 18 4
16 18 7

Results

i j Activity ES EF LS LF TF FF
2 4 4 0 4 5 9 5
2 6 8 0 8 1 9 1
2 8 7 0 7 0 7 0
4 6 d1 0 4 4 9 9 5
4 14 6 4 10 8 14 4
6 12 5 4 9 9 14 5
8 10 6 7 13 7 13 0
10 12 d2 0 13 13 14 14 1
10 16 5 13 18 13 18 0
12 18 4 13 17 14 18 1
14 18 4 10 14 14 18 4
16 18 7 18 25 18 25 0

Critical path:
2 – 8 – 10 – 16 - 18
Problem 2

In the expansion of a telephone service the following Activities are


1. Receive circuit request from traffic department involved
2. CNT check facilities.
3. Transmission engineering check facilities.
4. Issue truck work order.
5. Issue circuit work order.
6. Obtain plu-in Equipment.
7. Office wiring.
8. Test circuit.
9. Turn up for service.
10. Install equipment in local office.
11. Adjust records.

Activities 2 and 3 follow 1


Activities 4 to 6 follow 2 and 3
Activity 7 follows 5 and precedes 8
Activity 8 precedes 9
Activity 6 precedes 10
11 follows 10
9 and 11 are terminal Activities
4 precedes 8

Draw the CPM network


CPM Network

1 d1
2 4 10
4 d2

3 5 8 9
8 12 16 20 22
7

6
14 11
18
10