USER'S DATA
------------------------------------------------------------
------------------------------------------------------------
For single Track Loading in 2-Lane
------------------------------------------------------------
------------------------------------------------------------
For Double Track Loading in 4-Lane
------------------------------------------------------------
------------------------------------------------------------
DESIGN CALCULATIONS
------------------------------------------------------------
------------------------------------------------------------
STEP 1.0 : LOAD CALCULATION
------------------------------------------------------------
------------------------------------------------------------
1.1 LOAD ON TOP SLAB
------------------------------------------------------------
------------------------------------------------------------
Permanent Loads
------------------------------------------------------------
------------------------------------------------------------
Live Load
------------------------------------------------------------
------------------------------------------------------------
For One Track Load Covering 2-Lane
------------------------------------------------------------
------------------------------------------------------------
For Two Track Load Covering 4-Lane
------------------------------------------------------------
------------------------------------------------------------
STEP 1.2 : LOAD ON BOTTOM SLAB
------------------------------------------------------------
------------------------------------------------------------
Permanent Load
------------------------------------------------------------
Total Load = p5
= 4.800 + 8.308
= 13.11 kN/sq.m
------------------------------------------------------------
Live Load
------------------------------------------------------------
------------------------------------------------------------
STEP 1.3 : LOAD ON SIDE WALLS
------------------------------------------------------------
------------------------------------------------------------
STEP 1.4 : BASE PRESSURE
------------------------------------------------------------
------------------------------------------------------------
Permanent Load
------------------------------------------------------------
------------------------------------------------------------
Live Load
------------------------------------------------------------
Base Pressure = 17.908 + 35.011 = 52.919 kN/sq.m < 150.000 (sbc) OK.
------------------------------------------------------------
STEP 2.0 : BENDING MOMENT CALCULATION
------------------------------------------------------------
------------------------------------------------------------
STEP 2.1 : TOP SLAB
------------------------------------------------------------
------------------------------------------------------------
STEP 2.2 : BOTTOM SLAB
------------------------------------------------------------
------------------------------------------------------------
SIDE WALL
------------------------------------------------------------
------------------------------------------------------------
Case 1 : BOX Empty + Live Load Surcharge
------------------------------------------------------------
= 1.474 kN-m
= 2.60 kN-m
= 2.211 kN-m
= 2.60 kN-m
= 2.764 kN-m
= 3.902 kN-m
------------------------------------------------------------
Case 2 : BOX Full with Water + Live Load Surcharge
------------------------------------------------------------
= 0.655 kN-m
= 2.601 kN-m
= 0.983 kN-m
= 2.60 kN-m
= 1.228 kN-m
= 3.902 kN-m
------------------------------------------------------------
Case 3 : BOX Full with Water + No Live Load Surcharge
------------------------------------------------------------
= 0.655 kN-m
= 0.983 kN-m
= 1.228 kN-m
Let us denote the Four corner of Box Culvert as A,B,C and D clockwise,
Starting from Left Top Corner, then next Right Top Corner,
next Right Bottom Corner and finally Left Bottom Corner
A B
-------------------------------
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
-------------------------------
D C
Box Culvert
------------------------------------------------------------
Calculation Details
------------------------------------------------------------
Cal 1 : K_ab = (4 * E * I) / L
= (4 * E * d1^3) / ((b + d3) * 12)
= (4 * 2.500E+004 * 0.2^3) / ((1.5 + 0.225) * 12)
= 3.865E+001
Cal 3 : K_ad = (4 * E * I) / L
= (4 * E * d3^3) / ((d + d1 / 2 + d2 / 2) * 12)
= (4 * 2.500E+004 * 0.225^3) / ((1.5 + 0.2 / 2 + 0.2 / 2) * 12)
= 5.584E+001
Cal 7 : K_cd = (4 * E * I) / L
= (4 * E * d2^3) / ((b + d3) * 12)
= (4 * 2.500E+004 * 0.2^3) / ((1.5 + 0.225) * 12)
= 3.865E+001
------------------------------------------------------------
Corner/Joint Associated 4EI/L DF
Sides
------------------------------------------------------------
A AB K_ab DF_ab = 0.4090
(Cal 1) (Cal 9)
AD K_ad DF_ad = 0.5910
(Cal 3) (Cal 11)
------------------------------------------------------------
STEP 4 : MOMENT DISTRIBUTION
------------------------------------------------------------
------------------------------------------------------------
FIXED END MOMENT for Permanent Load ( Case 1)
------------------------------------------------------------
Mab = m1 = 1.156
Mba = m1 = 1.156
Mdc = m7 = 3.157
Mcd = m7 = 3.157
Mad = m11 = 1.474
Mbc = m11 = 1.474
Mda = m14 = 2.211
Mcb = m14 = 2.211
------------------------------------------------------------
FIXED END MOMENT for Live Load ( Case 1)
------------------------------------------------------------
Mab = m2 = 8.432
Mba = m2 = 8.432
Mdc = m2 = 8.432
Mcd = m2 = 8.432
Mad = m12 = 2.601
Mbc = m12 = 2.601
Mda = m12 = 2.601
Mcb = m12 = 2.601
------------------------------------------------------------
FIXED END MOMENT for Total Load ( Case 1)
------------------------------------------------------------
----------------------------------------
AB BC CD DA
AB BA BC CB CD DC DA AD
- + - + - + - +
----------------------------------------
------------------------------------------------------------
FIXED END MOMENT for Permanent Load ( Case 2)
------------------------------------------------------------
Mab = m1 = 1.156
Mba = m1 = 1.156
Mdc = m7 = 3.157
Mcd = m7 = 3.157
Mad = m19 = 0.655
Mbc = m19 = 0.655
Mda = m21 = 0.983
Mcb = m21 = 0.983
------------------------------------------------------------
FIXED END MOMENT for Live Load ( Case 2)
------------------------------------------------------------
Mab = m2 = 8.432
Mba = m2 = 8.432
Mdc = m2 = 8.432
Mcd = m2 = 8.432
Mad = m12 = 2.601
Mbc = m12 = 2.601
Mda = m12 = 2.601
Mcb = m12 = 2.601
------------------------------------------------------------
FIXED END MOMENT for Total Load ( Case 2)
------------------------------------------------------------
------------------------------------------------------------
FIXED END MOMENT for Permanent Load ( Case 3)
------------------------------------------------------------
Mab = m1 = 1.156
Mba = m1 = 1.156
Mdc = m7 = 3.157
Mcd = m7 = 3.157
Mad = m19 = 0.655
Mbc = m19 = 0.655
Mda = m21 = 0.983
Mcb = m21 = 0.983
------------------------------------------------------------
FIXED END MOMENT for Live Load ( Case 3)
------------------------------------------------------------
Mab = m2 = 8.432
Mba = m2 = 8.432
Mdc = m2 = 8.432
Mcd = m2 = 8.432
Mad = m26 = 0.000
Mbc = m26 = 0.000
Mda = m28 = 0.000
Mcb = m28 = 0.000
------------------------------------------------------------
FIXED END MOMENT for Total Load ( Case 3)
------------------------------------------------------------
Table-1 MOMENT DISTRIBUTION for TOTAL LOAD ON TOP, BOTTOM & SIDES for CASE I
-----------------------------------------------------------------------------
-------------------------------------------------------------------------------
--
DISTRIB DF_ab= DF_ad= DF_ba= DF_bc= DF_cb= DF_cd= DF_dc= DF_da=
FACTORS 0.409 0.591 0.409 0.591 0.591 0.409 0.409 0.591
-------------------------------------------------------------------------------
--
FEM Mab1 = Mad1 = Mba1 = Mbc1 = Mcb1 = Mcd1 = Mdc1 = Mda1 =
-9.59 4.07 9.59 -4.07 4.81 -11.59 11.59 -4.81
DIST D1 = D2 = D3 = D4 = D5 = D6 = D7 = D8 =
2.25 3.26 -2.25 -3.26 4.01 2.77 -2.77 -4.01
(Cal 1) (Cal 2) (Cal 3) (Cal 4) (Cal 5) (Cal 6) (Cal 7) (Cal 8)
CO C1 = C2 = C3 = C4 = C5 = C6 = C7 = C8 =
-0.92 -2.37 0.92 2.37 -1.93 -1.13 1.13 1.93
(Cal 9) (Cal 10) (Cal 11) (Cal 12) (Cal 13) (Cal 14) (Cal 15) (Cal
16)
------------------------------------------------------------
Calculation Details
------------------------------------------------------------
Table-2 MOMENT DISTRIBUTION for TOTAL LOAD ON TOP, BOTTOM & SIDES for CASE II
-----------------------------------------------------------------------------
-------------------------------------------------------------------------------
--
DISTRIB DF_ab= DF_ad= DF_ba= DF_bc= DF_cb= DF_cd= DF_dc= DF_da=
FACTORS 0.409 0.591 0.409 0.591 0.591 0.409 0.409 0.591
-------------------------------------------------------------------------------
--
FEM Mab2 = Mad2 = Mba2 = Mbc2 = Mcb2 = Mcd2 = Mdc2 = Mda2 =
-9.59 3.26 9.59 -3.26 3.58 -11.59 11.59 -3.58
DIST D1 = D2 = D3 = D4 = D5 = D6 = D7 = D8 =
2.59 3.74 -2.59 -3.74 4.73 3.27 -3.27 -4.73
(Cal 1) (Cal 2) (Cal 3) (Cal 4) (Cal 5) (Cal 6) (Cal 7) (Cal 8)
CO C1 = C2 = C3 = C4 = C5 = C6 = C7 = C8 =
-1.06 -2.80 1.06 2.80 -2.21 -1.34 1.34 2.21
(Cal 9) (Cal 10) (Cal 11) (Cal 12) (Cal 13) (Cal 14) (Cal 15) (Cal
16)
------------------------------------------------------------
Calculation Details
------------------------------------------------------------
Table-3 MOMENT DISTRIBUTION for TOTAL LOAD ON TOP, BOTTOM & SIDES for CASE III
-----------------------------------------------------------------------------
-------------------------------------------------------------------------------
--
DISTRIB DF_ab= DF_ad= DF_ba= DF_bc= DF_cb= DF_cd= DF_dc= DF_da=
FACTORS 0.409 0.591 0.409 0.591 0.591 0.409 0.409 0.591
-------------------------------------------------------------------------------
--
FEM Mab3 = Mad3 = Mba3 = Mbc3 = Mcb3 = Mcd3 = Mdc3 = Mda3 =
-9.59 0.66 9.59 -0.66 0.98 -11.59 11.59 -0.98
DIST D1 = D2 = D3 = D4 = D5 = D6 = D7 = D8 =
3.65 5.28 -3.65 -5.28 6.27 4.34 -4.34 -6.27
(Cal 1) (Cal 2) (Cal 3) (Cal 4) (Cal 5) (Cal 6) (Cal 7) (Cal 8)
CO C1 = C2 = C3 = C4 = C5 = C6 = C7 = C8 =
-1.49 -3.70 1.49 3.70 -3.12 -1.77 1.77 3.12
(Cal 9) (Cal 10) (Cal 11) (Cal 12) (Cal 13) (Cal 14) (Cal 15) (Cal
16)
------------------------------------------------------------
Calculation Details
------------------------------------------------------------
A B
-------------------------------
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
-------------------------------
D C
Box Culvert
-------------------------------------------------------------------------------
-----
CASES Mab Mdc Mad Mda
-------------------------------------------------------------------------------
-----
CASE 1 SMab1 = 6.685 SMdc1 = 8.427 SMad1 = 6.685 SMda1 =
8.427
CASE 2 SMab2 = 6.261 SMdc2 = 7.921 SMad2 = 6.261 SMda2 =
7.921
CASE 3 SMab3 = 4.938 SMdc3 = 6.596 SMad3 = 4.938 SMda3 =
6.596
-------------------------------------------------------------------------------
-----
MAXIMUM SMabx = 6.685 SMdcx = 8.427 SMadx = 6.685 SMdax =
8.427
-------------------------------------------------------------------------------
-----
Top Bottom Top/Side Bottom/Side
-------------------------------------------------------------------------------
-----
-------------------------------------------------------------------------------
-----
CASE 1 CASE 2 CASE 3
-------------------------------------------------------------------------------
-----
Mab m6 - SMab1 m6 - SMab2 m6 - SMab3
= 14.38 - 6.68 = 14.38 - 6.26 = 14.38 - 4.94
= 7.70 (Top) = 8.12 (Top) = 9.44 (Top)
-------------------------------------------------------------------------------
-----
Mdc m10 - SMdc1 m10 - SMdc2 m10 - SMdc3
= 17.38 - 8.43 = 17.38 - 7.92 = 17.38 - 6.60
= 8.96 (Bottom) = 9.46 (Bottom) = 10.79 (Bottom)
-------------------------------------------------------------------------------
-----
Mad m18-(SMad1+SMda1)/2 m24-(SMad2+SMda2)/2 m29-
(SMad3+SMda3)/2
= 6.67-(6.68+8.43)/2 = 5.13-(6.26+7.92)/2 = 1.23-(4.94+6.60)/2
= 0.89 (Side) = 1.96 (Side) = 4.54 (Side)
-------------------------------------------------------------------------------
-----
-------------------------------------------------------------------------------
-----
------------------------------------------------------------
STEP 5 : DESIGN OF TOP SLAB
------------------------------------------------------------
= 600 mm
------------------------------------------------------------
DESIGN OF SHEAR REINFORCEMENT
------------------------------------------------------------
percent = Ast*100/(1000*deff)
= 185.62*100/(1000*144.00)
= 13%
p4*[b-(x+cover)*(2/1000)]/2 = 27.360
x = -((((shear_capacity * 2) / p4) - b) * (1000 / 2) + cover)
------------------------------------------------------------
STEP 6 : DESIGN OF BOTTOM SLAB
------------------------------------------------------------
= 530 mm
As the required spacing per metre width is more than 200,
Provided T12 bars @200 mm c/c, Provided Ast = 565.487 sq.mm
------------------------------------------------------------
DESIGN OF SHEAR REINFORCEMENT
------------------------------------------------------------
= p6*[b-(deff+cover)*2/1000] / 2
= 48.119*[1.50-(144.00+50.00)*2/1000] / 2
= 26.75 kN
percent = Ast*100/(1000*deff)
= 212.01*100/(1000*144.00)
= 39%
p6*[b-(x+cover)*(2/1000)]/2 = 39.600
x = -((((shear_capacity * 2) / p6) - b) * (1000 / 2) + cover)
------------------------------------------------------------
STEP 7 : DESIGN OF SIDE WALLS
------------------------------------------------------------
Maximum moments at joints with top slab and bottom slab are save as
taken for Design of Slabs. So provide same Reinforments.
= 680 mm
------------------------------------------------------------
DESIGN OF SHEAR REINFORCEMENT
------------------------------------------------------------
percent = Ast*100/(1000*deff)
= 165.62*100/(1000*144.00)
= 39%
p12*[b-(x+cover)*(2/1000)]/2 = 39.600
x = -((((shear_capacity * 2) / p12) - b) * (1000 / 2) + cover)
------------------------------------------------------------
TABLE 1 : PERMISSIBLE SHEAR STRESS
------------------------------------------------------------
---------------------------------------------------------------------------
--------------------- END OF REPORT --------------------------
---------------------------------------------------------------------------
---------------------------------------------------------------------------