Sei sulla pagina 1di 1

SP SINGLA CONSTUCTIONS PVT LTD.

DAILY PROGRESS REPORT


Temp:Max:36°C , Min:26°C Weather: Sunny
(Source - Meteorological center, Patna)
Name of Work - Construction of Swap and grade separated U- turn based multi sectional interchange at Bailey road , Patna
DATE 04-May-19 TIME 8:00 AM
CRITICAL POINTS
1 Pending BBS from PICS:- R03-P3 Top Slab, Underpass R17 Raft Ch 1200-1174 (Revised)
2 Approval Required for R07 Road to start Drain & Approach Work for R01 Deck.
3 ROW for DRP required to start Drain & Road Work.
4 HighCourt Forest Clearance required to start Underpass C32 Work.
This Qty wise backlog status
This month Cumulative
S.N. Activity Name Unit Today month Remarks
Target Quantity Target Achieved Back log
achieved
A BPSC
R03-P2 RCC Box Wall
1 RCC Box Wall Reinforcement MT 20.00 0.00 0.00 20.00 0.00 -20.00
2 RCC Box Wall Concreting Cum 135.00 0.00 0.00 135.00 0.00 -135.00
R03-P2 Lower Pylon
1 Pylon Reinforcement MT 20.00 0.00 0.00 20.00 0.00 -20.00
2 Pylon Concreting Cum 62.00 0.00 0.00 62.00 0.00 -62.00

B LALIT BHAWAN
LA1 Approach RE Wall
1 Wall Concreting Cum 15.00 0.00 0.00 15.00 0.00 -15.00
2 Wall Reinforcement MT 1.00 0.00 0.00 1.00 0.00 -1.00
3 Crash Barrier Rmt 20.00 0.00 0.00 20.00 0.00 -20.00
RA2 Approach RE Wall
1 Raft Reinforcement MT 4.00 0.00 0.00 4.00 0.00 -4.00
2 Raft Concreting Cum 60.00 0.00 0.00 60.00 0.00 -60.00
3 Wall Reinforcement MT 4.00 0.00 0.00 4.00 0.00 -4.00
4 Wall Concreting Cum 40.00 0.00 0.00 40.00 0.00 -40.00
5 Crash Barrier Rmt 35.00 0.00 0.00 35.00 0.00 -35.00
R02 Deck Slab
1 Crash Barrier Rmt 100.00 0.00 0.00 100.00 0.00 -100.00

C DRP
R18-P2 Pile Cap
1 Pile Cap Reinforcement MT 60.00 0.00 0.00 60.00 0.00 -60.00
2 Pile Cap Concreting Cum 420.00 0.00 0.00 420.00 0.00 -420.00
R18-A2 Approach RE Wall
1 PCC MT 20.00 8.00 8.00 20.00 8.00 -12.00
2 Raft Reinforcement MT 3.00 0.00 0.00 3.00 0.00 -3.00
3 Raft Concreting Cum 50.00 0.00 0.00 50.00 0.00 -50.00
4 Wall Concreting Cum 50.00 0.00 0.00 50.00 0.00 -50.00
5 Wall Reinforcement MT 3.00 0.00 0.00 3.00 0.00 -3.00
Underpass [R17]
1 PCC Cum 50.00 0.00 0.00 50.00 0.00 -50.00
2 Pile Integrity Test Nos 30.00 0.00 0.00 30.00 0.00 -30.00
3 Raft Waterproofing Sqm 550.00 0.00 0.00 550.00 0.00 -550.00
4 Raft Reinforcement MT 50.00 0.00 0.00 50.00 0.00 -50.00
5 Raft Concreting Cum 333.50 0.00 0.00 333.50 0.00 -333.50
6 Wall Reinforcement MT 30.00 0.00 0.00 30.00 0.00 -30.00
7 Wall Concreting Cum 100.00 0.00 0.00 100.00 0.00 -100.00
8 Crash Barrier Rmt 60.00 0.00 0.00 60.00 0.00 -60.00

D ROAD WORKS
PQC
1 Earth Work Cum 1500.00 600.00 600.00 600.00 1500.00 600.00 -900.00
2 Sand Filling Cum 750.00 0.00 0.00 750.00 0.00 -750.00
3 GSB Cum 337.50 0.00 0.00 337.50 0.00 -337.50
4 R06 DLC Cum 225.00 0.00 0.00 225.00 0.00 -225.00
5 R06 PQC Cum 450.00 0.00 0.00 450.00 0.00 -450.00

E DRAIN WORKS
1 3 Cell Drain Casting Nos 144.00 0.00 0.00 144.00 0.00 -144.00
2 3 Cell Drain R/f Nos 144.00 0.00 0.00 144.00 0.00 -144.00
3 3 Cell Drain Slab Casting Nos 100.00 6.00 16.00 16.00 100.00 16.00 -84.00
4 3 Cell Drain Slab R/f Nos 100.00 6.00 16.00 16.00 100.00 16.00 -84.00
5 3 Cell Drain Erection Nos 144.00 0.00 0.00 144.00 0.00 -144.00
6 3 Cell Slab Erection Nos 50.00 0.00 0.00 50.00 0.00 -50.00
7 Load Bearing Drain R/f Cum 20.00 3.00 3.00 20.00 3.00 -17.00
8 Load Bearing Drain Concrete Cum 90.00 13.00 13.00 90.00 13.00 -77.00
9 3 Cell Load Bearing Slab-1200 W Nos 100.00 0.00 0.00 100.00 0.00 -100.00
10 3 Cell Load Bearing Slab-1700 W Nos 100.00 0.00 0.00 100.00 0.00 -100.00
11 3 Cell Load Bearing Slab-1100 W Nos 100.00 0.00 0.00 100.00 0.00 -100.00
12 R04/R06 Drain PCC Cum 30.00 0.00 0.00 30.00 0.00 -30.00
13 Road Widening Drain PCC Cum 30.00 0.00 0.00 30.00 0.00 -30.00