EVALUATION AND PREPARATION OF CLAIM


IN CONSTRUCTION PROJECTS
ABSTRACT
Claim management is an essential skill required by the Contract and Project
Management Professionals, especially due to the increase in both number and
value of claims in construction projects. A claim must be presented in a
professional manner with sufficient details including the basis, calculations
and evidences in order to save time, cost and effort of the Claimant and
Defendant.

This Technical Paper describes the importance and meaning of claims,


method of evaluation, and preparation of a successful claim presentation. The
relationship between the contract base lines, i.e., Contract Price, Scope,
Schedule and Conditions are established here along with the head of claim
due to change in conditions, delay and disruption. Methodology for the
calculation of Head Office Overhead and Profit is also discussed with their
relative importance and interrelations. This Paper further discusses about
some of the common terms in claim. As the final output of the evaluation
process is the claim presentation, this paper describes the structure and
requisites of it.

1. INTRODUCTION
Claim is a request for a benefit for which the Claimant believes or contends he
is entitled, but agreement has not been reached. The construction industry is
witnessing an increased numbers of claims in both domestic and international
sectors and the claim presentation is important in claim related issues in
Project Management. The Project Management and Contract Management
Professional should have basic knowledge about the meaning, evaluation and
preparation of claim.

Claim leads to wastage of money, time and efforts, especially due to


unprofessional presentation of it. A survey conducted with 24 construction
projects in Western Canada, demonstrated that the total amount of claims
contributed to a 40% increase in project cost and total delays to 48%. The
study also revealed that more than half of the claims led to a cost increase of
at least 30% of the original contract value.

The unfortunate reality is that construction claims are often resolved by


people who were not directly involved in the construction project. In the
courtroom, it is settled by lawyers and judges; or in conference room often by
corporate, vice presidents, or financial officers with little construction
experience. Hence, it is critical to provide a simplified, graphically driven
presentation of claim issues. Too much information and not enough
information are two main pitfalls of claim presentation, and should be
avoided in claim presentation.

A well prepared claim presentation helps all the involved in settling the issues
in an early stages, before going to arbitration and litigation, which are
expensive and time consuming. A claim must be presented in a professional
manner with sufficient details including the basis, calculations and causations.
If the claim presentation is transparent and reasonable, it is easy for both
parties to reach in agreement in an early stage itself and this requires a
professional claim presentation, which is the rationale of this Paper.

2. MEANING OF ‘CLAIM’
A claim is a demand, request or application for a benefit for which the
Claimant believes or contends he is entitled, but agreement has not been
reached. In other words, claim may be defined as a failure to fulfill obligations
under the contract or law by either of the parties. Change order claims can be
defined as, written authorization provided to a Contractor that approves a
change from the original plans, specifications, or other contract documents, as
well as a change in the cost. A claim may be for money, for time, or both;
however it should be noted that a successful claim for time extension does
not automatically honor a valid claim for money, and vice versa.

When the liability of the discovered change is easily attributable and the
consequences of the change can be ascertained (cause and effect) by
evaluation; then a formalized variation orders will be the result. Sometimes
the liability of the change cannot be easily attributed or for which liability is
disputed, then it will lead to claims. Claim is usually caused by defects;
conflicts or ambiguities in the Scope or Schedule; Exclusion clauses; or
Endeavour to avoid un-quantified risk. In order to successfully justify such
claims, it is usually necessary to carefully analyze the scope and the schedule,
particularly the contract documents and the provisions of the law.

Claims under Contract and Law


A contractual claim is an entitlement under the contract itself where specific
provisions or implied conditions of the contract can be invoked to support the
entitlement. A Claim under law, sometimes referred to as an ‘extra-
contractual’ claim is where the entitlement accrues from the provisions of the
law.
Notice of Breach or Claim
The injured party (Claimant) shall give notice of breach to the defending party
(Defendant), immediately upon discovering the breach; and such notice
should specify the nature of the breach in most of the jurisdictions. Most of
the Construction Contracts contain a requirement of notice to submit a claim
both for time extension and for money. The purpose of the notice is to enable
the other party to be aware of and to mitigate the effects of the breach
causing the claim. Failure to give prescribed notice is a breach of the contract
conditions and while such breach may not deprive the Contractor of his rights
under law, such breach may lead to a defense by the Employer that lack of
knowledge about the breach had prevented actions to mitigate the effects of
the breach and had also prevented proper evaluation of the effects of the
breach.

Evaluation
Evaluation is the process of assessing the quantum in money value and for the
extension of time. As Burden of Proof is on the claimant, the claimant must
show that there is a direct link (causal link) between the breach (cause) and
the loss (effect) thereby sustained. When there is more than one competing
causes, then it is necessary to ascertain and define such competing causes
and responsibility, the timing and effect, and losses actually and properly
sustained. Generally a claim can only comprehend the losses actually incurred,
possibly with the addition of an agreed or ascertained element for overheads
and profit.

3. ‘CONTRACT BASE LINES’: THE BASIS OF CLAIM


EVALUATION
Firm Fixed Price (FFP) or lumpsum contracts are most common and are more
vulnerable to claim due to its inherent natures. While lumpsum contracting
provides the lowest possible financial risk for the Employer, it provides the
highest risk for the Contractor, because any variance in scope, schedule, or
conditions affects the Contractor’s costs. When the work is changed, the
Contractor is expected to perform the work as a result of which he may
sustain additional costs. Obviously, the Contractor will attempt to seek
additional compensation based upon each such change, and often extensions
of time, within which will lead to claims and disputes. All changes in the
scope, schedule or conditions under which the Contractor’s work will be
performed, which result in delay or time-related claims, should be considered
in terms of their deviation from the ‘baseline’. As illustrated in the Figure
below, the contract defined scope, schedule, and conditions constitute the
‘baseline’.

Scope Schedule

Contract

Price

Conditions

Figure: The Contract Base Lines

Schedule is the most easily affected element of the lumpsum contract


baseline, because any delay, acceleration, disruption, or distortion of
performance constitutes a change which may entitle the Contractor and
obligate the Employer to pay additional compensation. ‘Time is money’, is a
factual reality, and the failure by either or both the Employer and the
Contractor to recognize this relationship can lead to substantial delay and
subsequent time-related damage claims.

The Contractor’s right to obtain time related compensation must be proven


against the contract’s ‘baseline’, which should be accurate and verifiable with
the contract scope, schedule, and condition. The Employer, on the other hand,
must ensure that he has a clear idea of the effect of its actions upon these
three ‘baseline’ elements.
A claim consisting of a request by the Contractor for money or time, due to a
change in any of the three basic elements of the contractual baseline, given
that each change is beyond the control of the Contractor, may affect his cost
and thus decrease his profit unless an appropriate adjustment is made to the
contract.

4. EVALUATION PROCESS
Evaluation is the process of quantifying the amount or extent of the additional
costs sustained due to the breach, and establishing that the subject losses
were actually and properly sustained as a result of the breach. As the Contract
Price of the lumpsum contract is equated to the elements of ‘baseline’, each
of the three basic elements should be priced to aggregate to the ‘Contract
Price’.

The basis of the pricing is usually referred to as the ‘Price Analysis’, given that
the Contract Price usually aggregated from the total of a Bill of Quantity, the
rates which in turn are broken down or analyzed into the primary cost
elements of :

Labor

Material

Equipment

Subcontractors

Overheads & Profit

The more detailed the price analysis the more accurately and quickly any
variance from the original contract price can be ascertained. Budget of a
project, which can be used as a benchmark for measuring any variation in
respective cost element coupled with proper cost monitoring and control
mechanism will enable to evaluate the claim adequately and effectively.
Records
While it is important to have an accurate and detailed make up of the contract
price it is equally important to keep accurate contemporary records of the
usage of key resources of labor, equipment and material. A brief list of the
more important records that should be properly and regularly updated for the
purpose of efficient project management, and particularly to claim
management, is as follows:

Tender and contract documentation

Works records sheets

Daily record of labor and plant staff etc.

Materials received and issued

Drawings register

Materials approval register

Request for information register

Site Instructions register

Correspondence and minutes files

Site diaries

Site instructions

Variation orders

Additional works register

Contract program
Updates of contract program

As-built program

Photographs and video

Agreed measurements of ‘covered’ works

Delay notifications

Claim notifications

Materials orders and invoices

Any other project documents related to schedule, cost, risk or quality


including correspondence between various stakeholders can be used as
Detailed and Extensive Records in the evaluation and preparation of claim.

5. HEADS OF CLAIM
Most of the construction projects are unique by their very nature and have
varying characteristics; however certain heads of claim that occurs frequently,
can be grouped into three main categories as follows:

New or changed conditions or circumstances


Any change in conditions or environment, where the contract is operating has
a corresponding change in other factors and may be measured in money
terms, i.e., cost. This change can be adjusted with a different factor or factors
without changing the cost. The following are the main constituent of changed
conditions:

Ground conditions, obstructions etc.

Occurred Risks not mentioned, not quantified or excessive

New or changed laws, regulations, duties, taxes etc.


Unforeseen problems of supply and/or delivery of resources

Loss due to carrying out work at a time of the year involving special factors

Particular climatic conditions

Prolongation costs due to delay


It may be identified that the act of postponement is the ‘cause’, and hindrance
is the ‘effect’ of delay. Primarily construction activities may be delayed but not
disrupted i.e., duration of activities may be postponed in commencement,
hindered or slowed down in achieving regular progress, and hence prolonged
in completion. The following are some of the expenses due to delay:

Remuneration of site staff and incidental traveling expenses

Plant and scaffolding retained on site

Temporary power distribution and lighting

Temporary office and storage accommodation

Utility accounts for the delay period

Telephone account for the delay period including rental and calls

Additional insurance and Bond premiums

Attendances on sub-Contractors over a longer period

Increased costs due to inflation of labor, plant and material

Profit and overheads on increased costs reimbursed during the extended


period

Watching, lighting and protection


Safety and welfare measures

Site clearance and maintenance of temporary roads

Time-related temporary works

Lost opportunity due to overdraft facility

Extended equipment warranties

Increased maintenance period risk

Head office overheads

Finance charges

Loss of profit.

Disruption or Loss of Productivity


Delays and prolongation are time related, but disruption is resource related.
Construction activities may be disrupted in regular progress or logical
sequence but the experience of disruption of progress may not result in a
delayed completion of activities. It is often that more resources are committed
to the activity to achieve completion in time. The following are some of the
examples of disruption:

Fragmented working: lack of utilization of resources

Reduced production for planned resources

Planned production from increased resources

Often delay equates to prolongation which invariably requires an Award of


Extension of Time for completion of the contract in due time. The Employer’s
award of Extension of Time by keeping alive the Penalty or Liquidated
Damages clause will not automatically entitle the Contractor for additional
money.

Another term for disruption is ‘fragmented working’, in which the claimant


contends that the actions of the other party have prevented or hindered the
claimant from executing the affected works, reduced output level and/or
enforced the same output for an increased level of resources. Due to the
burden of proof, and the requirement to show causal link substantiating
claims for disruption can be very tedious and difficult.

Costs of Disruption
In order to make claim for the costs of disruption, it must be evident that
some planned or orderly sequence of work had been affected by an act of the
Employer, of the Engineer, and/or by a variation or variations. It is often the
case that individual sections of work may be affected in a way, which does not
cause prolongation by themselves. Idle time of plant, tools and equipment;
and Loss of Productivity are the two main heads of costs of disruption.

Finance Charges and Interest


Certain breaches of the contract conditions would normally entitle the
Contractor to obtain interest. The cost of finance should be calculated on the
basis of charges by the Contractor’s bank i.e., using the same rates and
compounding accrued interest at the same intervals. Where the Contractor is
self-financed or financed from within its corporate group the appropriate rate
of interest is that earned by the Contractor (or its group) on monies it has
placed on deposit.

6. OVERHEADS AND PROFIT


Site Overheads
Site overheads cover all of those site costs that are not directly related to
particular items of work, which may include:
Salaries and wages of all indirect staff

Office facilities cost

Security

Provision of stores, workshops, latrines, etc.

Construction, maintenance and removal of site access roads

Transportation of plant to and from site

Contract insurances, performance bond, guarantees etc.

Provision and maintenance of small tools

Subsistence and traveling costs and allowances

The majority of the above items are of a time-related nature, but there are a
few with lumpsum nature. The latter must be excluded when calculating the
weekly site on cost, which may be calculated separately.

Head-Office Overheads
Head Office Overheads are the costs incurred by the Contractor in
maintaining his head office establishment, and include the cost such as, head
office staff, rent of head office premises, Contractor’s all risk insurance,
tendering for new projects etc., together with all other global costs. From
historical data a Contractor can identify the cost of Head Office Overheads,
and his gross turnover (revenue) for the same period. Head Office Overheads
can be allocated at the same percentage of historical data in estimation.

Profit
The percentage included for profit in a tender is entirely a management policy
decision of a Contractor only. The profit is a function of revenue, where Head
Office Overheads is a function of time. ‘Lost opportunity’ is the philosophy
behind claims for profit because the Contractor has been denied the
opportunity to generate further revenue and profit from other projects by
utilizing the resources for the additional time. To claim for this item, the
Contractor will show that he would have probably undertaken other contracts
by utilizing these resources.

Head-Office Overheads and Profit


Because of the similarities of Head Office Overheads and Profit, as they are
both related to the value recovered by the Contractor over a particular period
of time, they may be considered together. There are two main methods of
calculating Head Office Overheads and Profit (HOOHP), i.e.; by using details of
actual additional costs, and by using formulae. Since the true basis of the
value of a claim is on ‘actual costs’, then actual method is preferable. But it is
not practical for Contractor to record and allocate their head office costs in
sufficient details and accuracy to specific project and task.

Different Formulae for calculating the Head Office Overheads and Profit, as
follows:

The Hudson formula

The Emden formula

The Eichleay formula.

Ernstrom Formula

Manshul Formula

Carteret Formula

Allegheny Formula
The Hudson Formula
The Hudson formula states that the loss suffered by the Contractor as a
consequence of additional time spent on Site is equivalent to:

Claim Value for HOOHP = P * CV * PD / (100 * CP)

Where, P – Planned HOOH

CV – Contract Value

CP – Contract Period in weeks

PD – Period of excusable delay in weeks

Emden’s Formula
Emden’s Formula is similar to the Hudson formula except that instead of using
the percentage included in the Contract for Head Office Overheads and Profit
the percentage used is for the company identified from audited accounts,
generally the average of the percentage for overheads and profit for the
previous 2 – 3 years is used.

Eichleay’s Formula
The Eichleay Formula, although once again following a similar concept to both
the Hudson formula and Emden’s formula, is a more sophisticated formula
and amount claimed are calculated on the basis of a number of calculations.

HOOHP allocated in Original Contract, OAC = VCP * TOC / TO

Where, VCP – Value of work invoiced during the contract period

LawTeacher
TO – Turnover of the company during the contract

TOC – Total overheads of the company during the contract period


Claim Value for HOOHP = OAC * PD / CP

Where, OAC – HOOH allocated in Original Contract

CP – Contract Period in weeks

PD – Period of excusable delay in weeks

7. GLOBAL CLAIMS
The correct way of presenting a claim to the Engineer or before a Court or
Arbitrator is by using causation, i.e., rational and logical linking of the effect
with the cause. If the Engineer is 14 days late in issuing the drawings for the
foundations and as a result the completion of the work is delayed by 14 days,
will illustrate cause and effect linkage.

Nowadays, the Contractors and Subcontractors are practicing a method


known as the global or ‘Rolled up’ claim by giving less importance to the
classical cause and effect linking. All causes of loss and/or delay under the
global claim method are compiled together and one overall delay given as a
consequence. In this global claim method, the classical method of linking each
effect with its cause ignores the synergic effect of additional cost and/or
delay.

While such rolled up claims may be acceptable in respect of financial claims,


cause and effect will still have to be linked in respect of delay claims, as a
matter of evidence. While it is impractical to assign individual cause to a
particular effect, the principles of global claim method can be used
successfully. If a rolled up claim is appropriate, the events on which it was
evolved should be described in sufficient detail to indicate how they might be
causative of the entitlement claimed and why the other party was responsible
for them.

To avoid a great deal of argument over a global claim, Contractors and


Subcontractors are advised to establish the linkage between cause and effect
of every event, which may lead to a claim, at the time of occurrence itself. As
well as producing the cause and effect matrix, it will be appropriate to
highlight major delaying events in the text of the claim by making reference
to progress of works and effect on other trades. Particulars about the implied
link between cause and effect also shall be given with sufficient details such
as:

The unwritten assumptions on which such a claim is often based

The reasonableness of the original tender price, program and resources

The absence of other explanations for the delay and disruption suffered.

A rolled up claim is unlikely to succeed unless detailed factual evidence is


available to explain the disruptive nature of the events on which it is based,
and the Engineer or Tribunal is satisfied that there are no other explanations,
such as over optimistic programming, unrealistic pricing, and a Contractor’s
inefficiency for the resulting delays, disruption and loss, etc.

Total cost method of claim


‘Total cost method of claim’ is an extreme form of a Global claim, consisting
of evidence offered by the Contractor, often from internal sources, as to the
total cost of executing the contract, and then claiming the difference between
that total cost and the contract price. This is very frequently used in support of
perfectly ordinary breaches of contract or variations, where disruption is
alleged.

A claim so presented dispenses with the requirement of identifying precisely


the breaches or causes of action relied on, or of connecting the amount
claimed, as a matter of causation, to the individual causes of action. A total
cost claim may be advanced in relation to the performance of the contract as
a whole, or used as the basic underlying principle, subject to adjustment, of
the computation of the damages for a particular individual part of the
contract. As a matter of first principle, the obvious objections to the use of the
total cost computation are as follows:

Standing by itself, an over-run of cost is evidence of nothing, and certainly not


of a change or breach of contract by the owner

Coupled with convincing evidence of a breach or change, it is still not


evidence that any damage or additional cost has been caused by that breach
or change

Coupled with evidence of a change or breach, and evidence that at least some
damage or expenditure must have been incurred as a result of the change or
breach, it is not evidence as to what that damage is, since there are so many
other possible explanations of the cost over-run

If there is more than one cause of action involved, or one cause of


expenditure for which the owner cannot be responsible, the owner’s advisers,
and any tribunal, have no material for valuing or examining the case on those
parts of the claim which they are disposed to accept or concede

A function of such claim is to impose an absolute upper limit on any claim or


group of claims which a Contractor may wish to bring, since a total loss claim
represents the maximum theoretical damage or additional expenditure
attributable to all proven changes or breaches affecting the performance of a
contract.

8. PREPARATION AND SUBMISSION OF CLAIM


Usually, the Contractor or the Subcontractor will produce a claim document to
the Engineer, Employer or Main Contractor. A claim presented in a tidy and
professional manner will often result in a better settlement than an
unprofessional one. It shall be structured logically into sections, and each one
can be divided into subsections having sufficient details. The following are the
most common sections in a general sense:
Introduction

Contractual basis of the claim

The details of the claim

The evaluation of the claim

Appendices

Introduction
As the person, who is responsible for the final assessment may not be totally
familiar with the contract, it is important to give background details in order
to make the document a complete entity in itself. The minimum required
details should be as follows:

Names of the parties to the contract and the consultants

Details of the conditions of contract governing the contract

The tender date

The original contract sum

Dates for possession and completion

Details of extensions of time claimed

Details and amounts of money claimed

Details of extensions of time awarded

Details of amounts certified

Basis of the claim


It is important to state precisely about contractual basis of the claim. The
claim will fall under one or both of the following categories:

A claim for loss and expense or extra costs or expense flowing from a remedy
contained within the conditions themselves

A claim for damages resultant upon a breach of the express or implied terms
of the contract or the law

It is essential to state clearly the event or events pertaining to the claim. It is


also good practice in this section of the claim to make reference to
notifications which have been made during the contract.

Details of the claim


This section of the claim should provide the complete details as much as
possible of all delays with reasons, responsibility and effect on progress as a
whole. Assistance can be gained to prove this cause and effect by the use of
critical path method (CPM) or any other graphical method.

Evaluation of the claim


In most cases the evaluation will fall into two sections, i.e., costs associated
with prolongation and costs associated with disruption. Methodology of
heads of claim has been described earlier in this Paper.

Appendices
A well prepared claim usually has a large volume of backup documentation to
substantiate the case such as correspondence, records, photographs, video
and programs. Inclusion of all the details in the main body will make the
presentation bulky and distract the reader. Hence it is advisable to attach as
appendices.

Cite This Essay


To export a reference to this article please select a referencing style below:

OSCOLA APA MLA MLA-7 Harvard Vancouver

Wikipedia

All Answers ltd, 'EVALUATION AND PREPARATION OF CLAIM IN


CONSTRUCTION PROJECTS' (Lawteacher.net, January 2019)
<https://www.lawteacher.net/free-law-essays/contract-law/evaluation-
and-preparation-of-claim-in-construction-projects-contract-law-
essay.php?vref=1> accessed 8 January 2019

COPY TO CLIPBOARD

Need help with your work?


Find out more about our essay writing service:

ESSAY WRITING SERVICE


Dissertation Writing Service

Our Dissertation Writing service can help with everything from


full dissertations to individual chapters.

Marking Service

Our Marking Service will help you pick out the areas of your
work that need improvement.
All Writing Services

Fully referenced, delivered on time. Get the extra support you


require now.

FREE OSCOLA Referencing

FREE Case Summaries

FREE Act Summaries

FREE Lecture Notes

FREE Problem Question Examples

Request Removal
If you are the original writer of this essay and no longer wish to have the
essay published on the Law Teacher website then please click on the link
below to request removal:

Request the removal of this essay

More from Law Teacher


Law Essays
Examples of Our Work

We Write Bespoke Law Essays!

Find Out More

SERVICES

Law Essay Writing Service

Law Dissertation Writing Service

Law Assignment Writing Service

All Law Services

USEFUL RESOURCES

Law Essays

Case Summaries

Act Summaries

Problem Questions

OSCOLA Referencing Tool

LLM Resources
Law Help

Study Modules

COMPANY

About

Fair Use Policy

Complaints

Help Centre

Become a Researcher

Part of All Answers Ltd

Copyright © 2003 - 2019 - LawTeacher is a trading name of All Answers Ltd, a company
registered in England and Wales. Company Registration No: 4964706. VAT Registration No:
842417633. Registered Data Controller No: Z1821391. Registered office: Venture House, Cross
Street, Arnold, Nottingham, Nottinghamshire, NG5 7PJ.

Privacy Policy

Terms & Conditions

Cookies

Potrebbero piacerti anche