Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
TOTAL A s/d P
JUMLAH
DIBULATKAN
Terbilang : #REF!
BIAYA
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1 Land Excavation
2 Soil Mobilisation
3 Hoarding Work
4 Site Dewatering Work
A-3 STRUCTURE
A-4 UTILITIES
B STRUCTURAL WORKS
B - 1 GROUND ANCHOR WORKS
B.1.1 EARTH WORKS
1 Preparation
B.2.2 Basement B1
1 Meassuring, Marking and Setting up Batten Board
2 Basement Entrance/Exit t. 15 cm
3 Suspended Slab t. 15 cm
4 Suspended Beam B-01
5 Suspended Beam B-02
6 Suspended Beam B-03
7 Suspended Beam B-04
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
11 Stair
2 Suspended Slab
3 Suspended Beam B-01
4 Suspended Beam B-02
5 Suspended Beam B-04
6 Column Structure K-01
7 Column Structure K-02
8 Column Structure K-03
9 Column Structure K-04
10 Shear Wall (Core Wall)
11 Stair
12 Balcony
13 Garden Balcony
C ARCHITECTURAL WORKS
C-1 Basement B2
1 Wall Works
2 Plaster Work
3 Rendering Work
4 Floor hardener
5 Floor Epoxy Paint
C-2 Basement B1
1 Wall Works
2 Plaster Work
3 Rendering Work
4 Floor hardener
5 Floor Epoxy Paint
4 Road Work
5 Side Road Work
D ARCHITECTURAL FINISHES
D - 1 Basement B2
1 Wall & Column Painting
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
D-2 Basement B1
1 Wall & Column Painting
2 Painting for Wooden Door
3 Painting for Steel Door
4 Ceramic Tile 40 x 40 cm
5 Plinth Ceramic Tile 10 x 40 cm
6 Ceramic Tile 20 x 20 cm
7 Plinth Ceramic Tile 10 x 20 cm
8 Dust Proof Painting
9 Single PVC Door
10 Single Wooden Door (Mosque Door)
11 Single Wooden Door Frame 90 x 210 cm
12 Single Steel Door c/w Frame
13 Step Nosing for Stair
D - 3 Ground Floor
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
E CEILLING WORKS
E-1 Ground Floor
1 Gypsum Board Installment
2 Water Resist Board (GRC Board) Installment
3 Ceilling Crown Moulding Installment
4 Painting for Gypsum Board Surface
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
F SANITARY
F-1 Basement B1
1 WC
2 Standart Water Faucet
3 Floor Drain
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
G PLUMBING WORK
G-1 MAIN EQUIPMENT
1 Water Pump to Roof Tank from clean water tank
2 Centrifugal End Suction Pump + Water Filter (Roof Tank)
3 Deep Well Pump Install Work
4 Water Filter Pump Install Work (Raw Water Tank to Clean Water Tank)
5 Submersible Pump for Sump Pit
G-3 STRUCTURE
1 Roof Water Tank for Clean Water
2 Deep Well Work
3 Deep Well Meter Controll Concrete Box
4 PDAM Meter Controll Concrete Box
5 Infiltration Well Rain Water Plan Ø 60 cm
6 Water Filter Treatment Plan
7 Water Filter Meter Controll Concrete Box
8 Grease Trap Work
9 Water Ground Tank for Raw Water
10 Water Ground Tank for Clean Water
11 Septic Tank Work
12 Sump Pit Work
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
4.2.2 Basement B1
1 Pipe Work
2 Pipe Work
3 Pipe Work
4 Pipe Work
5 Clean Out
6 Clean Out
7 Clean Out
1 Pipe Work
2 Pipe Work
3 Pipe Work
4 Pipe Work
5 Gate Valve
6 Controll Clean Out
4.3.1 Basement B2
1 Pipe Work
2 Pipe Work
3 Pipe Work
4.3.2 Basement B1
1 Pipe Work
2 Pipe Work
3 Pipe Work
4
4 Generator Set
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
6 Capasitor Bank
9 Elbow (Tray)
10 Elbow (Tray)
5.1.2 Low Current
1 Cable Tray
2 Cable Tray
3 In/Out side Rider (Tray)
4 Straight Reducer (Tray)
5 Tee (Tray)
6 Cross (Tray)
7 Supporting Material
8 Attaching Support
2 Cable Tray
3 In/Out side Rider (Tray)
4 Straight Reducer (Tray)
5 Tee (Tray)
6 Supporting Material
7 Attaching Support
7 Attaching Support
1 Lightning Installation
2 Downlight PLC 18W Cool Daylight
3 Downlight PLC 11W Cool Daylight
4 Baret TL Circular 22W
5 Baret TL Circular 22W
6 TLD Balk 18W Outbow
7 Bamboo TLD 36W
8 Bamboo TLD 36W c/w Nicad Battery
9 V Shape TLD 2 x 18W
10 V Shape TLD 2 x 36W
11 Exit Lamp 10W 1 side c/w Nicad Battery
12 Double Electric Switch
13 Single Electric Switch
14 Double Electric Switch
15 Grid Switch 9 Gangs
16 Stop Contact Installation 1 phase
17 Outlet Stop Contact Wall Maounted 200 w
3 Step Lamp
4 Wall Lamp
6.2.3 Security
1 Security Lightning Installation
2 Downlight PLC 18W Cool Daylight
3 Single Electric Switch
6.2.4 Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm
1 Stop Contact Installation 1 phase
2 Outlet Stop Contact Wall Maounted 200 w
13 Fire Extinguisher
14 Gate Valve
18 Pressure Gauge
19 Flow meter
20 Automatic Air Vent
21 Hydrant Diesel Pump
23 Jockey Pump
13 Fire Extinguisher
14 Outdoor Hydrant Box c/w accessories
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
15 Pillar Hydrant
16 Seamese Conection
17 Gate Valve 4''
18 Check Valve 4''
19 Gate Valve dia. 2''
14 Fire Extinguisher
15 Gate Valve dia. 2''
16 Pressure Reducing Valve
11 Fire Extinguisher
12 Gate Valve dia. 2''
13 Fire Stop on Shaft
14 Automatic Air Vent
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
2 Cable Install for Signal Address/Loop - TBFA - Lobby to TBFA next Floor
3 Cable Installation for Electric Power - TBFA Lobby to TBFA Next Floor
4 Cable Installation Grounding - (TBFA Lobby to TBFA Next Floor)
2 Cable Install for Signal Address/Loop - TBFA - Lobby to TBFA next Floor
3 Cable Installation for Electric Power - TBFA Lobby to TBFA Next Floor
4 Cable Installation Grounding - (TBFA Lobby to TBFA Next Floor)
2 Cable Install for Signal Address/Loop - TBFA - Lobby to TBFA next Floor
3 Cable Installation for Electric Power - TBFA Lobby to TBFA Next Floor
4 Cable Installation Grounding - (TBFA Lobby to TBFA Next Floor)
K CCTV INSTALLATION
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
CCTV Installation
K-1 Basement BI and B2
1.1 Coaxial Cable RG59 c/w Power Cable in High Impact Conduit Ø 20 mm
1 Fixed Camera CCTV Installation
2 Colour Fixed Camera Dome
3 Colour Fixed Camera c/w Housing Outdoor type + accessories
L MATV INSTALLATION
MATV Installation
L-1 Main Equipment / Central MATV
1 Combiner 33 Channel
2 Active Splitter (First Media/Cable Vision/Indo Vision)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
2 Outlet TV Antenna
3 Splitter Installation
4 Indoor Splitter 4 ways
N TELEPHONE INSTALLATION
Telephone Installation c/w Accessories
N - 1 Main Equipment
1 Main Unit PABX cap. 240 co line 1.440 Extention :
N - 5 Roof Top
Cable ITC 20x2x0.6mm² in High Impact conduit Ø 20 mm
1 Telephone Installation
2 Single LineTelephone Hand Set
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
O - 2 Basement BI and B2
Cable UTP Cat 6 in High Impact conduit Ø 20mm
1 Computer Data Cable Installation
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL A - 1
TOTAL A - 2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL A - 3
TOTAL A - 4
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL A - 5
TOTAL A
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL B.1.1
TOTAL B.1.2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL B.1.3
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL B.2.1
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL B.2.2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL B.2.3
TOTAL B.2.4
-
Batten Board and Meassuring Equipment 16,572.00 M' A-02b
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL B.2.5
TOTAL B.2.6
TOTAL B
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
Light Brick Concrete Block (Hebel) Masonry Wall Work dim. 60x20x7.5 172.60 M2 E-02b
Plaster Work 1 Pc : 3 Sn, t. 20 mm 345.20 M2 F-01c
MU Cement, Water, Sand Paper, Rubing Paper 2,782.62 M2 F-03b
Sika Chapdur (Red) + Trowel Finish 9,439.77 M2 F-04
- M2 N-10
TOTAL C - 1
Light Brick Concrete Block (Hebel) Masonry Wall Work dim. 60x20x7.5 303.13 M2 E-02b
Plaster Work 1 Pc : 3 Sn, t. 20 mm 606.26 M2 F-01c
MU Cement, Water, Sand Paper, Rubing Paper 3,027.48 M2 F-03b
Sika Chapdur (Red) + Trowel Finish 9,439.77 M2 F-04
Epoxy Paint Work (1kg/5 m2) 1000 micron - M2 N-10
TOTAL C - 2
Light Brick Concrete Block (Hebel) Masonry Wall Work dim. 60x20x7.5 1,992.00 M2 E-02b
Plaster Work 1 Pc : 4 Sn, t. 20 mm 5,492.96 M2 F-01b
MU Cement, Water, Sand Paper, Rubing Paper 6,602.64 M2 F-03b
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL C - 3
TOTAL C - 4
Light Brick Concrete Block (Hebel) Masonry Wall Work dim. 60x20x7.5 172.60 M2 E-02c
Plaster Work 1 Pc : 4 Sn, t. 20 mm 345.20 M2 F-01c
Epoxy Paint Work (1kg/5 m2) 1000 micron 3,035.00 M2 N-10
TOTAL C - 5
TOTAL C
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL D - 1
TOTAL D - 2
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
Paint ex Pentalite ICI Exterior 3 layer 10 m2/ltr + Supporting Eqp 6,602.64 M2 N-06a
Finished Varnish ex Ultran 30.48 M2 N-04
Ducco Metal Coat ex ICI/Dulux 3 x layer 2000 μm 436.80 M2 N-9c
Granito Floor Tile ex Essenza/Similar, PC, SN + Groutting 170.50 M2 I-01a
Granito Base Plate ex Essenza/Similar, PC, SN + Groutting 87.60 M' I-02a
Floor Tile ex Roman/Similar, PC, SN + Groutting Colour PC 2,681.45 M2 I-04e
Base Plate ex Roman/Similar, PC, SN + Groutting Colour PC 595.30 M' I-02b
Wall Tile ex Roman/Similar, PC, SN + Groutting Colour PC 167.60 M2 E-09c
22.68 M2 J-05d
74.52 M2 J-05d
Door Panel Wood Plank Kamper Medan w. 90 cm h. 210 cm 4.00 Nr J-04a
Door Panel Wood Plank Kamper Medan w. 70 cm h. 210 cm 2.00 Nr J-04c
Wood Frame Profile Kamper Medan 6 x 15 cm 4.00 Nr J-03a
Wood Frame Profile Kamper Medan 6 x 15 cm 2.00 Nr J-03c
Steel Door Fire proof 1010 x 2150 mm t.1.6 mm c/w frame t. 2mm 4.00 Item K-14
11.00 M 0
Frame and Door Alumunium profile ex EDICO or similar, Hinge, 2.00 Unit K-15
Door handle, Temperded Glass ex ASAHI 5 mm, rubber seal - 0 0
Frame and Door Alumunium profile ex EDICO or similar, Hinge, 2.00 Unit K-16
Door handle, Temperded Glass ex ASAHI 5 mm, rubber seal - 0 0
Frame and Door Alumunium profile ex EDICO or similar, Hinge, 4.00 Unit K-18
Door handle, Temperded Glass ex ASAHI 5 mm, rubber seal - 0 0
Frame and Door Alumunium profile ex EDICO or similar, Hinge, 2.00 Unit K-17
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
Frame and Door Alumunium profile ex EDICO or similar, Hinge, 430.50 M2 K-09k
Door handle, Temperded Glass ex ASAHI 5 mm, rubber seal
TOTAL D - 3
Paint ex Pentalite ICI Exterior 3 layer 10 m2/ltr + Supporting Eqp 47,720.52 M2 N-06a
Paint ex Pentalite ICI Exterior 3 layer 10 m2/ltr + Supporting Eqp 204,323.76 M2 N-06b
Finished Varnish ex Ultran 24,416.64 M2 N-04
Ducco Metal Coat ex ICI/Dulux 3 x layer 2000 μm 302.40 M2 N-9c
Floor Tile ex Roman/Similar, PC, SN + Groutting Colour PC 50,346.00 M2 I-04e
Base Plate ex Roman/Similar, PC, SN + Groutting Colour PC - M' I-02b
Floor Tile Setting Work ex Mulia dim. 20x20 cm Colour Patern 5,130.00 M2 I-03b
Base Plate ex Roman/Similar, PC, SN + Groutting Colour PC - M I-02c
Wall Tile Work 20 x 25 cm Plain ex Mulia 13,392.00 M2 E-07e
Door Panel Wood Plank Kamper Medan w. 90 cm h. 210 cm 1,440.00 Nr J-04a
Wood Frame Profile Kamper Medan 6 x 15 cm 1,440.00 Nr J-03a
Door Panel Wood Plank Kamper Medan w. 80 cm h. 210 cm 2,304.00 Nr J-04b
Wood Frame Profile Kamper Medan 6 x 15 cm 2,304.00 Nr J-03b
Door Panel Wood Plank Kamper Medan w. 70 cm h. 210 cm 1,440.00 Nr J-04c
Wood Frame Profile Kamper Medan 6 x 15 cm 1,440.00 Nr J-03c
Steel Door Fire proof 1010 x 2150 mm t.1.6 mm c/w handle + frame t. 72.00 Item K-14
198.00 M 0
72.00 Unit K-21
Frame and Door Alumunium profile ex EDICO or similar, Hinge,
360.00 Unit K-20
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL D - 4
TOTAL D - 5
TOTAL D
TOTAL E - 1
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL E - 2
- 0 0
- 0 0
- 0 0
TOTAL E - 3
TOTAL E
TOTAL F - 1
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
Toilet Seat type Flush Jet System ex TOTO White 20.00 Item M-15
Jet Washer for Closet ex TOTO 20.00 Item M-20
Water Sink Faucet Stainless Steel ex TOTO TX-129L 12.00 Item M-22
Sink Liquid Soap Holder ex Krisbow NGLE 4.00 Item M-23
Urinoir TOTO Colour Standard c/w Accessories 8.00 Item M-02a
Floor Drain T5-A Outlet 50 mm Stainless Steel c/w Cover 4" 20.00 Item M-10a
Sink Oval ex INA LW 230 c/w Mirror & Accessories White 12.00 Item M-03
Mirror Glass t. 5 mm ex ASAHIMAS 8.00 M2 M-24
Toilet Paper Holder TX-703AC ex TOTO 20.00 Item M-25
Precast dia. 50 cm / U - Gutter AW 0 0
Precast Cover dia. 50 cm AW 0 0
TOTAL F - 2
Toilet Seat type Flush Jet System ex TOTO White 1,440.00 Item M-15
Jet Washer for Closet ex TOTO 1,440.00 Item M-20
Shower wall mounted ex TOTO 1,440.00 Item M-21
Addition Work AW 0 0
Sink Oval ex INA LW 230 c/w Mirror & Accessories White 1,440.00 Item M-03
1,440.00 0 0
TOTAL F - 3
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
- 0 0
- 0 0
- 0 0
TOTAL F - 4
TOTAL F
Type AB-01 & 02, Cap. 2x 350 lpm / 80 M / 7.5 kW 2.00 Set M-27a
Cap. 400 lpm , 30 Meter, 1 kW + Supporting Equip. 4.00 Set M-27a
Submersible Pump 80 LPM, 40m, 2 kW + Supporting Equip. 2.00 Set M-27c
Centrifugal End Suction Cap. 400 lpm , 30 Meter, 1 kW 2.00 Set M-27a
Cap. 2 x 200 lpm , 20 m, 0.7 kw + Cover, reinforce concrete 2.00 Set M-27c
TOTAL G - 1
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL G - 2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL G - 3
TOTAL G - 4.1.1
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL G - 4.1.2
TOTAL G - 4.1.3
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL G - 4.1.4
TOTAL G - 4.2.1
TOTAL G - 4.2.2
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL G - 4.2.3
TOTAL G - 4.2.4
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL G - 4.3.1
TOTAL G - 4.3.2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL G - 4.3.3
TOTAL G - 4.3.4
TOTAL G
Cap. 1.350 kg (20 prsn) speed 105 mpm, OP 15.9 kw, CO 4.00 0 0
Holstway 2.65 x 2.2 m, Pit 2.1 m, AC-VVVF - 0 0
2.00 0 0
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 1
4 MVA 3 phase
Connection Charges 4,000.00 Kva Lump Sum
Deposit Charges 8,000.00 Kva Lump Sum
Certificate of Eligibility to operate and Administration charges 8,000.00 Kva Lump Sum
20 KV-400 V/231 V-Oil Immersed c/w Standart Protection 1.00 Ls
Cubicle TM Oil Control, Grounding, Support Material
(Factory Certified and Guarantee)
20 KV c/w Equipment, setting and Leveling 1.00 Unit
Incoming & Outgoing (LBS) 1 unit Cubicle c/w:
Switch Cubicle 20kV, Busbar and Heater
Operating Mechanism CIT (Manual)
Natural Interlock Earth-OFF-ON
Earthing Switch with SF6 gas Technology
Voltage Indicators and Transformer
Cap. 600 KVA Open Type, atenuator, battery, Silencer 2.00 Unit
standar accesories, test report, Certified & Guarantee
Insulation Work Genset House & Grounding System
Exhaust Fan Installation cap. 1.500 Cfm
Fuel System w/ Fuel Tank 2.000 lt + Fuel Pump
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
Free Standing type 3 cell c/w Equipment and Installation 1.00 Unit
Panel Box dim. 240 x 200 x 80 cm (2mm thick)
MCCB 500-1250A/70kA/4P Motorized
MCCB 500-1250A/50kA/4P Motorized
MCCB 300A/36kA/3P
MCCB 160A/36kA/3P
MCCB 100A/36kA/3P
MCCB 75A/30kA/3P
MCCB 60A/30kA/3P
MCCB 40A/30kA/3P
Fuse 4A/3P
Indicator Lamp
Voltmeter
Amperemeter+CT
KWH meter
Frekwnsi Meter (Hz Meter)
Cos phi meter
Switch selector
Cu Busbar
ATS/AMF Module
Grounding Installation 2 x BC 50 mm + Local Material
Supporting Equipment + Local Material
Lightning Surge Arrester 400V Type 1 3P+N
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
MCB 10A/10kA/4P
300 Kfar Free Standing type c/w Box 180x70x80 cm 1 cell 2.00 Unit
MCCB 250-630A/50kA/3P
Push Button Switch, Fuse, Indicator lamp
MCB 50A/1P, Regulator 12 step, Cos phi meter
Magnetic contactor, Capasitor 25 Kfar, Relay MK 2P
Relay MK 3P, Exhaust Fan, Supporting Material
TOTAL H - 2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
- MCB 16A/6kA/1P
- Fuse 2 A, Indicator Lamp, Voltmeter, Amperemeter + CT
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
Box panel wall mounted (dim. 40x50x25cm) 1.00 Unit
- MCCB 30A/18kA/3P
- MCB 16A/6kA/1P
- Fuse 2 A, Indicator Lamp On Off
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
Box panel wall mounted (dim. 40x50x25cm) 1.00 Unit
- MCCB 30A/18kA/3P
- MCB 16A/6kA/1P
- Direct online motor starter, Exhaust Fan On Off
- Fuse 2 A, Fan Indicator Lamp Switch Start, Stop, Fault
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
TOTAL H - 3.1
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 3.2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 3.3
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
- Supporting Material
Box panel wall mounted (dim. 50x70x25cm) 1.00 Unit
- MCCB 125A/18kA/3P
- MCB 40A/6kA/3P
- MCB 25A/6kA/3P
- MCCB 30A/18kA/3P
- MCB 16A/6kA/1P
- Direct online motor starter, AC On Off
- Fuse 2 A, Fan Indicator Lamp Switch Start, Stop, Fault
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
Box panel wall mounted (dim. 40x50x25cm) 1.00 Unit
- MCCB 75A/18kA/3P
- MCB 50A/6kA/3P
- MCB 16A/6kA/1P
- Direct online motor starter, AC On Off
- Fuse 2 A, Fan Indicator Lamp Switch Start, Stop, Fault
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
Box panel wall mounted (dim. 40x60x25cm) 2.00 Unit
- MCCB 75 A/18kA/3P
- MCCB 50A/18kA/3P
- MCCB 40A/18kA/3P
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
- MCB 16A/6kA/1P
- Fuse 2 A, Indicator Lamp
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
TOTAL H - 3.4
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 4.1
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 4.2
TOTAL H - 4.3
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 4.4
STU Type c/w Hanging & Material Supporting
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 5.1
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 5.2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
1.00 Ls
TOTAL H - 5.3
TOTAL H - 5.4
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 6.1
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 6.2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 6.3
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL H - 6.4
TOTAL H
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL I - 1.1.1
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
32.00 unit
Flow meter 6" 8.00 unit
8.00 unit
Cap. 750 USGPM, 95 meter, 75 kw c/w levelling 2.00 set
Control panel & Wiring, Exhaust manifolt & Support material
Cap. 750 USGPM 95 kW 3 Phase, 95 meter c/w 2.00 set
Control Panel, Wiring and accesories
Cap. 20 GPM 11 kW 3 phase, 95 meter c/w 2.00 set
Control Panel, Wiring and accesories
Ø 4'' c/w sprinkler alarm, valve, water pump motor & 1.00 set
alarm Sirine, pressure gauge
Reducing Valve dia 4'' 8.00 set
Cap. 25 Kg class ABC Dry chemical powder type 18.00 unit
TOTAL I - 1.1.2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
4.00 unit
4.00 unit
Ø 100 mm or 4 " 4.00 unit
Ø 100 mm or 4 " 4.00 unit
Ø 50 mm or 2 " 4.00 pcs
TOTAL I - 1.2.1
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL I - 1.2.2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL I - 1.2.3
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL I
TOTAL J - 1.1.1
3.00 Nr
3.00 Nr
1.00 Nr
3.00 pcs
3.00 pcs
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
1.00 pcs
1.00 Nr
1.00 Nr
TOTAL J - 1.1.2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL J - 1.1.3
31.00 Nr
11.00 pcs
2.00 pcs
18.00 pcs
3.00 pcs
2.00 pcs
2.00 pcs
2.00 Nr
2.00 Nr
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
1.00 Nr
2.00 pcs
2.00 pcs
1.00 pcs
1.00 Nr
1.00 Nr
TOTAL J - 2.2.1.1
TOTAL J - 2.2.2
450.00 Nr
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
198.00 pcs
54.00 pcs
198.00 pcs
180.00 Nr
180.00 pcs
54.00 pcs
36.00 Nr
36.00 pcs
TOTAL J - 3.1
36.00 Nr
36.00 Nr
18.00 Nr
36.00 pcs
36.00 pcs
18.00 pcs
18.00 Nr
18.00 Nr
TOTAL J - 3.2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL J - 3.3
10.00 Nr
1.00 pcs
6.00 pcs
3.00 pcs
2.00 pcs
1.00 Nr
1.00 pcs
TOTAL J - 4.1
1.00 Nr
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
1.00 Nr
1.00 Nr
1.00 pcs
1.00 pcs
1.00 pcs
1.00 Nr
1.00 Nr
TOTAL J - 4.2
TOTAL J - 4.3
TOTAL J
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
3.00 Nr
1.00 pcs
2.00 pcs
TOTAL K - 1.1.1
2.00 unit
2.00 unit
1.00 unit
1.00 unit
1.00 Ls
1.00 Ls
TOTAL K - 1.1.2
4.00 Nr
3.00 pcs
1.00 pcs
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL K - 2
72.00 Nr
54.00 pcs
18.00 pcs
TOTAL K - 3
2.00 Nr
2.00 pcs
TOTAL K - 4
TOTAL K
4.00 unit
2.00 unit
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
4.00 unit
2.00 unit
2.00 unit
2.00 unit
2.00 unit
4.00 unit
2.00 unit
4.00 unit
2.00 unit
2.00 unit
66.00 unit
1.00 Ls
1.00 Ls
TOTAL L - 1
TOTAL L - 2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
2.00 pcs
Coaxial Cable RG 11 in Conduit Ø 20 mm 2.00 Nr
2.00 pcs
TOTAL L - 3
TOTAL L - 4
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL L - 5
TOTAL L
TOTAL M - 1.1
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL M - 1.2
1.00 item
1.00 item
1.00 item
1.00 item
1.00 item
1.00 item
1.00 item
Cable NYA 10 mm in High Impact Conduit Ø 20 mm 50.00 m'
TOTAL M - 1.3
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
4.00 unit
4.00 unit
TOTAL M - 1.4
17.00 Nr
10.00 Item
7.00 Item
5.00 Item
TOTAL M - 2.1
6.00 Nr
6.00 Item
TOTAL M - 2.2
1.00 unit
45.00 m'
45.00 m'
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL M - 2.3
17.00 Nr
10.00 Item
7.00 Item
5.00 Item
TOTAL M - 3.1
6.00 Nr
6.00 Item
TOTAL M - 3.2
306.00 Nr
252.00 Item
54.00 Item
72.00 Item
TOTAL M - 4.1
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
90.00 Nr
90.00 Item
TOTAL M - 4.2
18.00 unit
810.00 m'
810.00 m'
TOTAL M - 4.3
11.00 Nr
7.00 Item
4.00 Item
1.00 Item
TOTAL - M.5.1
2.00 Nr
2.00 Item
TOTAL - M.5.2
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
1.00 unit
170.00 m'
170.00 m'
TOTAL - M.5.3
TOTAL M
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
2.00 unit
1.00 unit
1.00 Ls
TOTAL N - 1
17.00 Nr
17.00 Item
17.00 Item
TOTAL - N.2.1
1.00 0
30.00 0
TOTAL - N.2.2
64.00 Nr
64.00 Item
64.00 Item
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL - N.3.1
1.00 Unit
60.00 m'
TOTAL - N.3.2
- 0
1,460.00 Nr
1,460.00 Item
1,460.00 Item
TOTAL - N.4.1
72.00 0
2,160.00 0
TOTAL - N.4.2
2.00 Nr
2.00 Item
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
2.00 Item
TOTAL N - 5
TOTAL N
TOTAL O - 1
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
5.00 Item
1.00 Item
1.00 Nr
1.00 Nr
TOTAL O - 2
TOTAL O - 3.1
12.00 Nr
4.00 Item
4.00 Item
4.00 Item
1.00 Unit
CONSTRUCTION COST ESTIMATION
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL O - 3.2
TOTAL O - 4.1
216.00 Nr
72.00 Item
72.00 Item
72.00 Item
18.00 Unit
TOTAL O - 4.2
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL O - 5.1
2.00 Nr
2.00 Item
2.00 Item
2.00 Item
1.00 Unit
TOTAL O - 5.2
TOTAL O
ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS
TOTAL P
TOTAL A s/d P
JUMLAH TOTAL
DIBULATKAN
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
Rp -
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
TOTAL PRICE
-
TOTAL PRICE
-
TOTAL PRICE
-
TOTAL PRICE
-
TOTAL PRICE
-
TOTAL PRICE
-
TOTAL PRICE
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE
-
-
-