Sei sulla pagina 1di 235

REKAPITULASI RENCANA ANGGARAN BIAYA

NAME OF PROJE : East Park Apartmen Buaran Jatinegara, East Jakarta


PROJECT ACTIVI : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACT: PT.
NUMBER OF BLD : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

A SITE WORK & UTITILIY


B STRUCTURAL WORKS
C ARCHITECTURAL WORKS
D ARCHITECTURAL FINISHES
E CEILLING WORKS
F SANITARY
G PLUMBING WORK
H MECHANICAL & ELECTRICAL WORK INSTALLATION
I FIRE FIGHTING INSTALLATION
J FIRE ALARM INSTALLATION
K CCTV INSTALLATION
L MATV INSTALLATION
M SOUND SYSTEM INSTALLATION
N TELEPHONE INSTALLATION
O COMPUTER EQUIPMENT & CABLE INSTALLATION
P LIGHTNING GROUNDING CABLE INSTALLATION

TOTAL A s/d P
JUMLAH
DIBULATKAN

Terbilang : #REF!
BIAYA

JUMLAH HARGA (Rp.)

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-

Buaran, April, 23th, 2019


DEVELOPER,
PT. BANGUN SARANA GRAHA LESTARI

TEMMY MOZES TANNOS, SE


President Director
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

A SITE WORK & UTITILIY

A-1 SITE PRPARATIONS

1 Meassuring and Marking and Setting up Batten Board


2 Site Clearence
3 Temporary Fence

A-2 SITE DEVELOPMENT

1 Land Excavation
2 Soil Mobilisation
3 Hoarding Work
4 Site Dewatering Work

A-3 STRUCTURE

1 Meassuring and Marking and Setting up Batten Board


2 Electricity Room for Power Supply
3 Temporary Site Office Building
4 Temporary Material Warehouse
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

5 Security Guard house


6 Worker Barrack (Temporary Build. cap. 50 people c/w WC + Elec. Inst.)

A-4 UTILITIES

1 Electricity Generator Set


2 Telephone Connection by TELKOM
3 Water Installment Connection by PDAM
4 Generator Set Fuel Consumption
5 Water Consumption Charges
6 Telephone Charges
7 Direction, Area, Project Signage
8 Fire Extinguisher Equipment

A-5 INFRASTRUCTURE WORKS

1 Temporary Access Road


2 Retaining Wall (Basement 1 and 2 Wall)
3 Drop of Material Area and parking setting up
4 Drainage Under Ground Pipe
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

5 Drainage (Sewer) Work


6 Reinforce Concrete Tank Work Clean Water Tank Cap. 10 x 10 x 2 m3
7 Reinforce Concrete Tank Work Raw Water Tank Cap. 6.75 x 5 x 2 m3
8 Reinforce Concrete Tank Work Sump Pit (Waste Water) Cap. 6 x 5.5 x 2 m
9 Reinforce Concrete Cesspool Tank Work (Dirty Water) Cap. 6.5 x 6.5 x 2 m
10 Reinforce Concrete Grease Trap Tank (Waste Water) Cap. 3 x 2.5 x 2 m3

B STRUCTURAL WORKS
B - 1 GROUND ANCHOR WORKS
B.1.1 EARTH WORKS

1 Meassuring, Marking and Setting up Batten Board


2 Excavate for Pile Cap (P-01)
3 Excavate for Pile Cap (P-02)
4 Excavate for Pile Cap (P-03)
5 Excavate for Tie Beam (S-01)
6 Excavate for Tie Beam (S-02)
7 Excavate for Tie Beam (S-03)
8 Excavate for Tie Beam (S-04)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

9 Excavate for Tie Beam (S-05)


10 Excavate for Tie Beam (S-06)
11 Reinforce Concrete Pile Cap
12 Reinforce Concrete Tie Beam

B.1.2 TEST PILE WORKS

1 Test Pile Work

B.1.3 BORE PILE WORKS

1 Preparation

2 Pile Work (280 Pile, 4 Pile/Pile Cap Ø 0.3 m, 15 m height)


3 Pile Work (376 Pile, 4 Pile/Pile Cap Ø 0.35 m, 15 m height)
4 Pile Work (80 Pile, 4 Pile/Pile Cap Ø 0.4 m, 15 m height)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

5 Bore Work (P-1) 280 pile 15 m deep


6 Bore Work (P-2) 376 pile 15 m deep
7 Bore Work (P-3) 80 pile 15 m deep
8 Site Leveling
9 Material Testing

B-2 STRUCTURAL WORKS


B.2.1 Basement B2 :
1 Meassuring, Marking and Setting up Batten Board
2 Basement Entrance/Exit t. 15 cm
3 Tie Beam Work (S-01) dim. 25 x 45 cm
4 Tie Beam Work (S-02) dim. 25 x 50 cm
5 Tie Beam Work (S-03) dim. 30 x 60 cm
6 Tie Beam Work (S-04) dim. 30 x 65 cm
7 Tie Beam Work (S-05) dim. 35 x 65 cm
8 Tie Beam Work (S-06) dim. 40 x 75 cm
9 Ground Slab t. 15 cm
10 Suspended Slab t. 15 cm
11 Suspended Beam B-01
12 Suspended Beam B-02
13 Suspended Beam B-03
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

14 Suspended Beam B-04


15 Suspended Beam B-05
16 Suspended Beam B-06
17 Column Structure K-01 dim. 40 x 40 cm
18 Column Structure K-02 dim. 50 x 50 cm
19 Column Structure K-03 dim. 60 x 60 cm
20 Column Structure K-04 dim. 80 x 80 cm
21 Shear Wall (Elevator Wall) t. 15 cm
22 Stair
23 Pile Cap (PC-01) 135 x 135 x 70 cm
24 Pile Cap (PC-02) 160 x 160 x 75 cm
25 Pile Cap (PC-03) 200 x 200 x 80 cm

B.2.2 Basement B1
1 Meassuring, Marking and Setting up Batten Board
2 Basement Entrance/Exit t. 15 cm
3 Suspended Slab t. 15 cm
4 Suspended Beam B-01
5 Suspended Beam B-02
6 Suspended Beam B-03
7 Suspended Beam B-04
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

8 Suspended Beam B-05


9 Suspended Beam B-06
10 Column Structure K-01
11 Column Structure K-02
12 Column Structure K-03
13 Column Structure K-04
14 Shear Wall (Core Wall)
15 Stair

B.2.3 Ground Floor


1 Meassuring, Marking and Setting up Batten Board
2 Suspended Slab
3 Suspended Beam B-01 (25 x 45 cm)
4 Suspended Beam B-02 (25 x 50 cm)
5 Suspended Beam B-04 (30 x 65 cm)
6 Column Structure K-01
7 Column Structure K-02
8 Column Structure K-03
9 Column Structure K-04
10 Shear Wall (Core Wall)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

11 Stair

B.2.4 1st Floor to 6th Floor


1 Meassuring, Marking and Setting up Batten Board
2 Suspended Slab
3 Suspended Beam B-01
4 Suspended Beam B-02
5 Suspended Beam B-04
6 Column Structure K-01
7 Column Structure K-02
8 Column Structure K-03
9 Column Structure K-04
10 Shear Wall (Core Wall)
11 Stair
12 Balcony
13 Garden Balcony

B.2.5 7th to 18th Floor


1 Meassuring, Marking and Setting up Batten Board
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

2 Suspended Slab
3 Suspended Beam B-01
4 Suspended Beam B-02
5 Suspended Beam B-04
6 Column Structure K-01
7 Column Structure K-02
8 Column Structure K-03
9 Column Structure K-04
10 Shear Wall (Core Wall)
11 Stair
12 Balcony
13 Garden Balcony

B.2.6 Roof Top


1 Meassuring, Marking and Setting up Batten Board
2 Shear Wall (Core Wall)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

C ARCHITECTURAL WORKS

C-1 Basement B2
1 Wall Works
2 Plaster Work
3 Rendering Work
4 Floor hardener
5 Floor Epoxy Paint

C-2 Basement B1
1 Wall Works
2 Plaster Work
3 Rendering Work
4 Floor hardener
5 Floor Epoxy Paint

C-3 Ground Floor


1 Wall Works
2 Plaster Work
3 Rendering Work
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

4 Road Work
5 Side Road Work

C-4 1st Floor to 18th Floor


1 External Wall Works
2 Internal Wall Works
3 Plaster Work
4 Rendering Work

C-5 Roof Top


1 Wall Works
2 Plaster and Rendering Work
3 Floor Water Proffing Paint

D ARCHITECTURAL FINISHES
D - 1 Basement B2
1 Wall & Column Painting
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

2 Painting for Steel Door


3 Dust Proof Painting
4 Single Steel Door c/w Frame
5 Step Nosing for Stair

D-2 Basement B1
1 Wall & Column Painting
2 Painting for Wooden Door
3 Painting for Steel Door
4 Ceramic Tile 40 x 40 cm
5 Plinth Ceramic Tile 10 x 40 cm
6 Ceramic Tile 20 x 20 cm
7 Plinth Ceramic Tile 10 x 20 cm
8 Dust Proof Painting
9 Single PVC Door
10 Single Wooden Door (Mosque Door)
11 Single Wooden Door Frame 90 x 210 cm
12 Single Steel Door c/w Frame
13 Step Nosing for Stair

D - 3 Ground Floor
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

1 Painting for Wall


2 Painting for Wooden Door
3 Painting for Steel Door + Rolling Door
4 Ceramic Tile 60 x 60
5 Plinth Ceramic Tile 10 x 60
6 Ceramic Tile 40 x 40
7 Plinth Ceramic Tile 10 x 40
8 Ceramic Tile for Wall 15 x 25
9 Single HPL Door
10 Toilet Partition
11 Single Wooden Door Public Toilet
12 Single Wooden Door Janitor
13 Single Wooden Door Frame 90 x 220 cm
14 Single Wooden Door Frame 70 x 220 cm
15 Single Steel Door c/w Frame
16 Step Nosing for Stair
17 Main Lobby Alluminum Glass Door 2.00 x 2.20 m + 2 Window 0.6 x 2.20 m +
Upper Window h. 0.5 m c/w Alluminum Frame, Swing, Double Door
18 Service Lobby Alluminum Glass Door 1.80 x 2.20 m + 2 Window 0.6 x 2.20m
+ Upper Window h.0.5 m c/w Alluminum Frame, Swing, Double Door
19 Triple Window Alluminum + Glass 2.40 x 2.20 m + Upper Window
h.0.5m c/w Alluminum Frame
20 Single Alluminum Glass Door (Corridor Main Lobby) 1.00 x 2.20 m c/w Frame
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

21 Rolling Door dimension 2.5 m x 2.1 m

D-4 1st Floor to 18th Floor


1 Painting for External Wall
2 Painting for Internal Wall
3 Painting for Wooden Door
4 Painting for Steel Door
5 Ceramic Tile 40 x 40 cm
6 Plinth Ceramic Tile 10 x 40 cm
7 Ceramic Tile 20 x 20 cm
8 Plinth Ceramic Tile 10 x 20 cm
9 Ceramic Tile for Wall 15 x 25 cm
10 Single Wooden Door (Main Door Apartment)
11 Single Wooden Door Frame 6 x 15 x 210 cm
12 Single Wooden Door (Bed Room Door Apartment)
13 Single Wooden Door Frame 6 x 15 x 210 cm
14 Single Wooden Door (WC Door Apartment)
15 Single Wooden Door Frame 6 x 15 x 210 cm
16 Single Steel Door c/w Frame
17 Step Nosing for Stair
18 Single Window Frame Alluminum + Glass dimension 100 x 120 cm
19 Single Window Frame Alluminum + Glass dimension 60 x 120 cm
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

20 Double Window Frame Alluminum + Glass dimension 90 x 120 cm


21 Sliding Aluminum Door 1.20 x 2.10 m (Double)
22 Sliding Aluminum Door 0.90 x 2.10 m (Single)

D-5 Roof Top


1 Painting for External Wall
2 Painting for Internal Wall
3 Single Steel Door c/w Frame
4 Glass Block

E CEILLING WORKS
E-1 Ground Floor
1 Gypsum Board Installment
2 Water Resist Board (GRC Board) Installment
3 Ceilling Crown Moulding Installment
4 Painting for Gypsum Board Surface
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

E-2 1st Floor to 18th Floor


1 Gypsum Board Installment
2 Water Resist Board (GRC Board) Installment
3 Ceilling Crown Moulding Installment
4 Painting for Gypsum Board Surface

E-3 Roof Top


1
2
3

F SANITARY
F-1 Basement B1
1 WC
2 Standart Water Faucet
3 Floor Drain
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

F-2 Ground Floor


1 WC Seat type Flush Jet System White ex Toto
2 Jet Washer
3 Sink Water Valve
4 Liquid Soap Holder
5 Urinoir
6 Floor Drain
7 Wastafel / Basin
8 Mirror Glass
9 Toilet Paper Holder
10 Drainase
11 Drainase Cover

F-3 1st Floor to 18th Floor


1 WC
2 Jet Washer for Closet ex TOTO
3 Shower
4 Kitchen Sink + Kitchen Set c/w Electric Stove
5 Wastafel / Basin
6 Towel Hook
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

F-4 Roof Top


1
2
3

G PLUMBING WORK
G-1 MAIN EQUIPMENT
1 Water Pump to Roof Tank from clean water tank
2 Centrifugal End Suction Pump + Water Filter (Roof Tank)
3 Deep Well Pump Install Work
4 Water Filter Pump Install Work (Raw Water Tank to Clean Water Tank)
5 Submersible Pump for Sump Pit

G-2 MAIN DISTRIBUTION


1 Galvanis Pipe Transfer Roof Tank
2 Pipe Work Install Work (DW to RWT)
3 Pipe Work Deep Well Header
4 Water Level Controll Install Work (CWT Ground)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

5 Check Valve Install Work (DW to RWT)


6 Gate Valve Install Work (DW to RWT)
7 Floating Valve (DW to RWT)
8 Water Level Controll Install Work (DW)
9 Floating Valve (RWT to CWT)
10 Flexible Joint Install Work (CWT to RT)
11 Check Valve Install Work (CWT to RT)
12 Gate Valve Install Work (CWT to RT)
13 Strainer Install Work (CWT to RT)
14 Water Meter Install Work (CWT to RT)
15 Water Level Controll Install Work (CWT to RT)
16 Pipe Work Water Filter Header
17 Pipe Work (RWT to CWT)
18 Flexible Joint Install Work (RWT to CWT)
19 Check Valve Install Work (RWT to CWT)
20 Gate Valve Install Work (RWT to CWT)
21 Strainer Install Work (RWT to CWT)
22 Gate Valve Install Work (RWT to FF Hydrant)
23 Pipe Work (RWT to FF Hydrant)
24 Gate Valve Install Work (PDAM to CWT)
25 Pipe Work (PDAM to CWT)
26 Floating Valve (PDAM to CWT)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

27 Flow Meter for PDAM


28 Flexible Joint Install Work (SP Pump to Infiltration Well Reserve)
29 Check Valve Install Work (SP Pump to Infiltration Well Reserve)
30 Gate Valve Install Work (SP Pump to Infiltration Well Reserve)
31 Pipe Work (SP to Infiltration Well Reserve)
32 Water Level Controll Install Work (SP)
33 Floating Valve (SP)

G-3 STRUCTURE
1 Roof Water Tank for Clean Water
2 Deep Well Work
3 Deep Well Meter Controll Concrete Box
4 PDAM Meter Controll Concrete Box
5 Infiltration Well Rain Water Plan Ø 60 cm
6 Water Filter Treatment Plan
7 Water Filter Meter Controll Concrete Box
8 Grease Trap Work
9 Water Ground Tank for Raw Water
10 Water Ground Tank for Clean Water
11 Septic Tank Work
12 Sump Pit Work
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

13 Reinforce Concrete Tank Work Roof CW Tank Cap.6.5 x 10.5 x 3 m3

G-4 PIPE INSTALLATION


4.1 CLEAN WATER PIPE INSTALLATION
4.1.1 Basement B1
1 Pipe Work
2 Pipe Work
3 Check Valve Install Work
4 Gate Valve Install Work (Pressure Relief Valve/PRV)

4.1.2 Ground Floor


1 Pipe Work
2 Pipe Work
3 Pipe Work
4 Pipe Work
5 Check Valve Install Work
6 Globe Valve Install Work
7 Gate Valve Install Work
8 Water Meter Install Work (Store)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

4.1.3 1st Floor to 18th Floor


1 Pipe Work
2 Pipe Work
3 Pipe Work
4 Pipe Work
5 Check Valve Installation
6 Globe Valve Installation
7 Gate Valve Installation
8 Water Meter Installation

4.1.4 Roof Top


1 Pipe Work
2 Pipe Work
3 Pipe Work
4 Pipe Work
5 Pipe Work
6 Check Valve Installation
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

7 Gate Valve Installation

4.2 WASTE WATER & VENT PIPE INSTALLATION


4.2.1 Basement B2
1 Pipe Work
2 Pipe Work
3 Pipe Work

4.2.2 Basement B1
1 Pipe Work
2 Pipe Work
3 Pipe Work
4 Pipe Work
5 Clean Out
6 Clean Out
7 Clean Out

4.2.3 Ground Floor


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

1 Pipe Work
2 Pipe Work
3 Pipe Work
4 Pipe Work
5 Gate Valve
6 Controll Clean Out

4.2.4 1st Floor to 18th Floor


1 Pipe Work
2 Pipe Work
3 Pipe Work
4 Pipe Work
5 Pipe Work
6 Gate Valve
7 Ceilling Clean Out
8 Controll Clean Out

4.3 DIRTY WATER / CLOSET PIPE & VENT PIPE INSTALLATION


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

4.3.1 Basement B2
1 Pipe Work
2 Pipe Work
3 Pipe Work

4.3.2 Basement B1
1 Pipe Work
2 Pipe Work
3 Pipe Work
4

4.3.3 Ground Floor


1 Pipe Work
2 Pipe Work
3 Pipe Work
4 Pipe Work
5 Pipe Work
6 Gate Valve
7 Clean Out
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

4.3.4 1st Floor to 18th Floor


1 Pipe Work
2 Pipe Work
3 Pipe Work
4 Pipe Work
5 Pipe Work
6 Gate Valve
7 Ceilling Clean Out
8 Controll Clean Out
9 Vent Cap

H MECHANICAL & ELECTRICAL WORK INSTALLATION


H-1 MAIN EQUIPMENT
1 Passenger Elevator + Installation

2 Service Elevator + Installation


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

H-2 ELECTRIC DISTRIBUTION


1 Electric Connection to PLN (Electric Company)

2 Transformator Installment 1000 KVA ex Schneider Electric

3 Middle Voltage Main Distribution Panel (MVMDP Panel)

4 Generator Set
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

5 Low Voltage Main Distribution Panel (LVMDP Panel)


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

6 Capasitor Bank

H-3 ELECTRIC PANEL INSTALLATION


3.1 Basement BI and B2
1 Sub Distribution Panel for Sump Pit Pump (SDP Panel)

2 Power Panel for Hydrant


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

3 Lightning Panel Basement Level

4 Ventilation Power Panel for Basement Level

3.2 Ground Floor


1 Lightning Panel Outdoor
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

2 Lightning Panel Indoor

3 Air Conditioning Exhaust Van Power Panel

4 Box Switch Security


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

3.3 1st Floor to 18th Floor


1 Lightning Panel (LP)

2 Box Switch Electric Submeter Store and Apartment Unit

3 Air Conditioning Exhaust Van Power Panel


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

4 Box Switch Security

3.4 Roof Top


1 Lightning Panel Roof Top (LPR)

2 Sub Distribution Panel Roof Top


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

3 Air Conditioning Exhaust Van Power Panel

4 Pressurized Fan Power Panel

5 Lift Power Panel


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

H-4 CABLE FEEDER AND GROUNDING INSTALLATION


4.1 Basement BI and B2
4.1.1 Low Current Cable Feeder
1 Intallation Cable from SubMeter / KWH Meter to MVMDP
2 Intallation Cable from MVMDP to Transformator
3 Intallation Cable from Transformator to LVMDP
4 Intallation Cable for Genset to LVMDP
5 Intallation Cable from LVMDP to PP Hydrant
6 Intallation Cable from LVMDP to Pump SDP
7 Intallation Cable from SDP Pump to AB Pump Control Panel
8 Intallation Cable from SDP Pump to WTP Pump Control Panel
9 Intallation Cable from SDP Pump to Deep Well Control Panel
10 Intallation Cable from SDP Pump to STP Panel Control
11 Intallation Cable LVMDP to LP B
12 Intallation Cable LVMDP to PP VAC B
13 Intallation Cable LVMDP to LP OL
4.1.2 Grounding Cable Installation
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

1 Grounding Terminal (KWH Meter, Trafo, MVMDP)


2 Grounding Terminal to Hydrant PP
3 Grounding Terminal to Shaft
4 Grounding Terminal to Genset
5 Grounding Terminal to SDP Pump
6 SDP Pump to AB Pump Control Panel
7 SDP Pump to WTP Pump Control Panel
8 SDP Pump to Deep Well Control Panel
9 SDP Pump to STP Control Panel
10 LVMDP to LP B
11 LVMDP to PP VAC B
12 LVMDP to LP OL

4.2 Ground Floor


4.2.1 Low Current Cable Feeder
1 LVMDP to LP LB
2 LVMDP to LP VAC LB
3 LP OL to BS Submeter Store
4 LP OL to BS Security
4.2.2 Grounding Cable Installation
1 LVMDP to LP LB
2 LVMDP to LP VAC LB
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

4.3 1st Floor to 18th Floor


4.3.1 Low Current Cable Feeder
1 Intallation Cable for SubMeter / KWH Meter (LVMDP )
2 LVMDP to LP 1 to LP 18
3 LVMDP to LP VAC 1 to LP VAC 18
4 LP 1 to LP 18 to BS Apartment Unit
4.3.2 Grounding Cable Installation
1 Grounding Terminal (KWH Meter, LVMDP)
2 LVMDP to LP 1 to LP 18
3 LVMDP to LP VAC 1 to VAC 18

4.4 Roof Top


4.4.1 Low Current Cable Feeder
1 LVMDP to LP A
2 LVMDP to SDP Roof
3 SDP Roof to Booster Pump Panel Control
4 LVMDP to Lift PP
5 Lift PP to Lift A Control Panel
6 Lift PP to Lift B Control Panel
7 Lift PP to Lift Service Control Panel
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

8 LVMDP to Press Fan PP


4.4.2 Grounding Cable Installation
1 LVMDP to LP Roof
2 LVMDP to SDP Roof
3 SDP Roof to Booster Pump Panel Control
4 LVMDP to Lift PP
5 Lift PP to Lift A Control Panel
6 Lift PP to Lift B Control Panel
7 Lift PP to Lift Service Control Panel
8 LVMDP to Press Fan PP

H-5 CABLE TRAY INSTALLATION


5.1 Basement BI and B2
5.1.1 High Current
1 Cable Tray
2 Cable Tray
3 Cable Tray
4 In/Out side Rider (Tray)
5 Straight Reducer (Tray)
6 Straight Reducer (Tray)
7 Tee (Tray)
8 Tee (Tray)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

9 Elbow (Tray)
10 Elbow (Tray)
5.1.2 Low Current
1 Cable Tray
2 Cable Tray
3 In/Out side Rider (Tray)
4 Straight Reducer (Tray)
5 Tee (Tray)
6 Cross (Tray)
7 Supporting Material
8 Attaching Support

5.2 Ground Floor


5.2.1 High Current
1 Cable Tray
2 Cable Tray
3 Cable Tray
4 In/Out side Rider (Tray)
5 Straight Reducer (Tray)
6 Tee (Tray)
5.2.2 Low Current
1 Cable Tray
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

2 Cable Tray
3 In/Out side Rider (Tray)
4 Straight Reducer (Tray)
5 Tee (Tray)
6 Supporting Material
7 Attaching Support

5.3 1st Floor to 18th Floor


5.3.1 High Current
1 Cable Tray
2 Cable Tray
3 Cable Tray
4 In/Out side Rider (Tray)
5 Straight Reducer (Tray)
6 Tee (Tray)
5.3.2 Low Current
1 Cable Tray
2 Cable Tray
3 In/Out side Rider (Tray)
4 Straight Reducer (Tray)
5 Tee (Tray)
6 Supporting Material
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

7 Attaching Support

5.4 Roof Top


5.4.1 High Current
1 Cable Tray
2 Cable Tray
3 Cable Tray
4 In/Out side Rider (Tray)
5 Straight Reducer (Tray)
6 Tee (Tray)
5.4.2 Low Current
1 Cable Tray
2 Cable Tray
3 In/Out side Rider (Tray)
4 Straight Reducer (Tray)
5 Tee (Tray)
6 Supporting Material
7 Attaching Support

H - 6 ELECTRIC STOP CONTACT AND LIGHTNING INSTALLATION


6.1 Basement BI and B2
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

1 Lightning Installation
2 Downlight PLC 18W Cool Daylight
3 Downlight PLC 11W Cool Daylight
4 Baret TL Circular 22W
5 Baret TL Circular 22W
6 TLD Balk 18W Outbow
7 Bamboo TLD 36W
8 Bamboo TLD 36W c/w Nicad Battery
9 V Shape TLD 2 x 18W
10 V Shape TLD 2 x 36W
11 Exit Lamp 10W 1 side c/w Nicad Battery
12 Double Electric Switch
13 Single Electric Switch
14 Double Electric Switch
15 Grid Switch 9 Gangs
16 Stop Contact Installation 1 phase
17 Outlet Stop Contact Wall Maounted 200 w

6.2 Ground Floor


1 Lightning Installation
2 Downlight PLC 18W Cool Daylight
3 Downlight PLC 18W Warm White
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

4 Downlight PLC 18W Warm White c/w Nicad Battery


5 Downlight PLC 11W Cool Daylight
6 Downlight PLC 11W Cool Daylight c/w Nicad Battery
7 Downlight PLC 11W WarmWhite
8 Downlight PLC 11W WarmWhite c/w Nicad Battery
9 Downlight Halogen 50W
10 Baret TL Circular 22W
11 Baret TL Circular 22W c/w Nicad Battery
12 TLD Balk 18W Outbow
13 Bamboo TLD Lamp 36W
14 RM Lamp TLD 2 x 18W c/w Kapasitor
15 Exit Lamp 10W 1 side c/w Nicad Battery
16 Double Electric Switch
17 Single Electric Switch
18 Grid Switch 6 Gangs
19 Grid Switch 8 Gangs
20 Dimmer Stop Contact
21 Stop Contact Installation 1 phase
22 Outlet Stop Contact Wall Maounted 200 w
23 Outbow Stop Contact for Viewer 400 w
6.2.2 Outer Side Lightning Installation
1 Garden Lamp c/w PLC Lamp 18 W
2 Lobby Terrace Lamp PLC 18 W
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

3 Step Lamp
4 Wall Lamp
6.2.3 Security
1 Security Lightning Installation
2 Downlight PLC 18W Cool Daylight
3 Single Electric Switch
6.2.4 Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm
1 Stop Contact Installation 1 phase
2 Outlet Stop Contact Wall Maounted 200 w

6.3 1st Floor to 18th Floor


6.3.1 Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm
1 Lightning Installation
2 Downlight PLC 18W Cool Daylight
3 Downlight PLC 11W Cool Daylight
4 Downlight PLC 11W WarmWhite
5 Downlight PLC 11W WarmWhite c/w Nicad Battery
6 Baret TL Circular 22W
7 Baret TL Circular 22W c/w Nicad Battery
8 TLD Balk 18W Outbow
9 RM Lamp w/ Acrylic Cover TLD 2 x 18W c/w Kapasitor
10 Exit Lamp 10W 1 side c/w Nicad Battery
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

11 Double Electric Switch


12 Single Electric Switch
13 Grid Switch 4 Gangs
14 Grid Switch 10 Gangs
15 Outlet Stop Contact Wall Maounted 200 w
6.3.2 Apartmen Room
Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm
1 Lightning Installation
2 Downlight PLC 18W Cool Daylight
3 Downlight PLC 11W Cool Daylight
4 Wall Lamp PLC 11W WarmWhite
5 Double Electric Switch
6 Single Electric Switch
7 Outlet Stop Contact Wall Maounted 200 w

6.4 Roof Top


6.4.1 Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm
1 Lightning Installation
2 Downlight PLC 18W Cool Daylight
3 Downlight PLC 11W Cool Daylight
4 Downlight PLC 11W WarmWhite
5 Downlight PLC 11W WarmWhite c/w Nicad Battery
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

6 Downlight Halogen 50W 3,0 bh


7 RM Lamp Acrylic Cover TLD 2 x 18W c/w Kapasitor
8 Double Electric Switch
9 Single Electric Switch
10 Grid Switch 6 Gangs
11 Dimmer Stop Contact
6.4.2 Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm
1 Outlet Stop Contact Wall Maounted 200 w
2 Pump Engine Room
6.4.3 Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm
1 Lightning Installation
2 Bamboo TLD Lamp 16W
3 Double Electric Switch
4 Stop Contact Installation 1 phase
5 Outlet Stop Contact Wall Maounted 200 w

I FIRE FIGHTING INSTALLATION


I-1 MAIN EQUIPMENT
1.1 Basement BI and B2
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

1 BS SCH Pipe c/w Installation


2 BS SCH Pipe Installation
3 BS SCH Pipe Installation
4 BS SCH Pipe Installation
5 BS SCH Pipe Installation
6 BS SCH Pipe Installation
7 BS SCH Pipe Installation
8 BS SCH Pipe Installation
9 BS SCH Pipe Installation
10 Head Sprinkler
11 Branch Control Valve

12 Indoor Hydrant Box


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

13 Fire Extinguisher
14 Gate Valve

1.2 Main Equipment


1 Header
2 Header
3 Gate Valve
4 Butterfly Valve
5 Safety Valve
6 Safety Valve
7 Gate Valve
8 Gate Valve
9 Strainer
10 Strainer
11 Flexible Joint
12 Flexible Joint
13 Check Valve
14 Check Valve
15 Check Valve
16 Gate Valve
17 Pressure Switch
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

18 Pressure Gauge
19 Flow meter
20 Automatic Air Vent
21 Hydrant Diesel Pump

22 Electric Hydrant Pump

23 Jockey Pump

24 Main Control Valve

25 Pressure Reducing Valve


26 Fire Extinguisher

2.1 Ground Floor


1 BS SCH Pipe c/w Installation
2 BS SCH Pipe Installation
3 BS SCH Pipe Installation
4 BS SCH Pipe Installation
5 BS SCH Pipe Installation
6 BS SCH Pipe Installation
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

7 BS SCH Pipe Installation


8 BS SCH Pipe Installation
9 BS SCH Pipe Installation
10 Head Sprinkler
11 Branch Control Valve

12 Indoor Hydrant Box

13 Fire Extinguisher
14 Outdoor Hydrant Box c/w accessories
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

15 Pillar Hydrant
16 Seamese Conection
17 Gate Valve 4''
18 Check Valve 4''
19 Gate Valve dia. 2''

2.2 1st Floor to 18th Floor


1 BS SCH Pipe c/w Installation
2 BS SCH Pipe Installation
3 BS SCH Pipe Installation
4 BS SCH Pipe Installation
5 BS SCH Pipe Installation
6 BS SCH Pipe Installation
7 BS SCH Pipe Installation
8 BS SCH Pipe Installation
9 BS SCH Pipe Installation
10 Head Sprinkler
11 Head Sprinkler
12 Branch Control Valve
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

13 Indoor Hydrant Box

14 Fire Extinguisher
15 Gate Valve dia. 2''
16 Pressure Reducing Valve

2.3 Roof Top


1 BS SCH Pipe c/w Installation
2 BS SCH Pipe Installation
3 BS SCH Pipe Installation
4 BS SCH Pipe Installation
5 BS SCH Pipe Installation
6 BS SCH Pipe Installation
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

7 BS SCH Pipe Installation


8 Head Sprinkler
9 Branch Control Valve

10 Indoor Hydrant Box

11 Fire Extinguisher
12 Gate Valve dia. 2''
13 Fire Stop on Shaft
14 Automatic Air Vent
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

J FIRE ALARM INSTALLATION


Semi Addressable Fire Alarm Installation
J-1 Basement BI and B2
1.1 Cable NYA 2x1.5 mm² inside High Impact conduit Ø 20 mm
1 Fire Alarm Detector Installation
2 Heat Detector ROR c/w Alarm Response Lamp

3 Heat Detector Fixed c/w Alarm Response Lamp


4 Smoke Detector c/w Alarm Response Lamp
5 End of Line Resistor
6 Addressable Manual Call Point Installation
7 Addressable Manual Call Point

1.2 Cable FRC 2x1.5 mm² inside High Impact conduit Ø 20 mm


1 Indicator Lamp Installation
2 Alarm Bell Installation
3 Fireman's Intercom Jack Installation
4 Indicator Lamp
5 Alarm Bell
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

6 Fireman's Intercom Jack


7 Installation to Flow Switch
8 Installation toTamper Switch

1.3 Terminal Box


1 Fire Alarm Terminal Box Basement level (TBFA-B)

2 Cable Installation for Signal Address/Loop - TBFA-B to TBFA Lobby


3 Cable Installation for Electric Power - TBFA-B to MCPFA
4 Cable Installation for Electric Power - TBFA-B to TBFA Lobby
5 Cable Installation Grounding - (TBFA B to MCPFA)
6 Cable Installation Grounding - (TBFA B to TBFA Lobby)
7 Main Control Panel Fire Alarm (MCP-FA) Addressable 220 Address 1 Loop
8 Announciator
9 Line Surge Arrester 40 KA
10 Battery 4 Jam Nicad Type (Rechargeable)
11 Cable Installation MCP-FA to Pressurized Fan
12 Cable Installation MCP-FA to Sound System
13 Cable Installation MCP-FA to LVMDP
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

14 Cable Installation MCP-FA to PABX


15 Cable Installation MCP-FA to Lift Control
16 Cable Installation MCP-FA to Genset Monitoring
17 Cable Installation MCP-FA to Hydrant Pump Monitoring
18 Cable Installation for Signal Address/Loop - MCPFA to TBFA-B
19 Cable Installation for intercom - TBFA B to MCPFA
20 Cable Installation for Electric Power - MCP-FA to TBFA B
21 Cable Installation for Grounding MCPFA to Low Current Grounding Terminal
22 Alarm Installation Licensing

J-2 Ground Floor


2.1.1 Cable NYA 2x1.5 mm² inside High Impact conduit Ø 20 mm
1 Fire Alarm Detector Installation
2 Heat Detector ROR c/w Alarm Response Lamp
3 Heat Detector Fixed c/w Alarm Response Lamp
4 Smoke Detector c/w Alarm Response Lamp
5 End of Line Resistor
6 Addressable Manual Call Point Installation
7 Addressable Manual Call Point
2.1.2 Cable FRC 2x1.5 mm² inside High Impact conduit Ø 20 mm
1 Indicator Lamp Installation
2 Alarm Bell Installation
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

3 Fireman's Intercom Jack Installation


4 Indicator Lamp
5 Alarm Bell
6 Fireman's Intercom Jack
7 Installation to Flow Switch
8 Installation toTamper Switch

2.2 Terminal Box


1 Fire Alarm Terminal Box Ground level (TBFA-LB)

2 Cable Install for Signal Address/Loop - TBFA - Lobby to TBFA next Floor
3 Cable Installation for Electric Power - TBFA Lobby to TBFA Next Floor
4 Cable Installation Grounding - (TBFA Lobby to TBFA Next Floor)

J-3 1st Floor to 18th Floor


3.1 Cable NYA 2x1.5 mm² inside High Impact conduit Ø 20 mm
1 Fire Alarm Detector Installation
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

2 Heat Detector ROR c/w Alarm Response Lamp


3 Heat Detector Fixed c/w Alarm Response Lamp
4 Smoke Detector c/w Alarm Response Lamp
5 Remote Installation LED Indicator
6 Remote LED Indicator
7 End of Line Resistor
8 Addressable Manual Call Point Installation
9 Addressable Manual Call Point

3.2 Cable FRC 2x1.5 mm² inside High Impact conduit Ø 20 mm


1 Indicator Lamp Installation
2 Alarm Bell Installation
3 Fireman's Intercom Jack Installation
4 Indicator Lamp
5 Alarm Bell
6 Fireman's Intercom Jack
7 Installation to Flow Switch
8 Installation toTamper Switch

3.3 Terminal Box


1 Fire Alarm Terminal Box Ground level (TBFA-LB)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

2 Cable Install for Signal Address/Loop - TBFA - Lobby to TBFA next Floor
3 Cable Installation for Electric Power - TBFA Lobby to TBFA Next Floor
4 Cable Installation Grounding - (TBFA Lobby to TBFA Next Floor)

J-4 Roof Top


4.1 Cable NYA 2x1.5 mm² inside High Impact conduit Ø 20 mm
1 Fire Alarm Detector Installation
2 Heat Detector ROR c/w Alarm Response Lamp
3 Heat Detector Fixed c/w Alarm Response Lamp
4 Smoke Detector c/w Alarm Response Lamp
5 End of Line Resistor
6 Addressable Manual Call Point Installation
7 Addressable Manual Call Point

4.2 Cable FRC 2x1.5 mm² inside High Impact conduit Ø 20 mm


1 Indicator Lamp Installation
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

2 Alarm Bell Installation


3 Fireman's Intercom Jack Installation
4 Indicator Lamp
5 Alarm Bell
6 Fireman's Intercom Jack
7 Installation to Flow Switch
8 Installation toTamper Switch

4.3 Terminal Box


1 Fire Alarm Terminal Box Ground level (TBFA-LB)

2 Cable Install for Signal Address/Loop - TBFA - Lobby to TBFA next Floor
3 Cable Installation for Electric Power - TBFA Lobby to TBFA Next Floor
4 Cable Installation Grounding - (TBFA Lobby to TBFA Next Floor)

K CCTV INSTALLATION
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

CCTV Installation
K-1 Basement BI and B2
1.1 Coaxial Cable RG59 c/w Power Cable in High Impact Conduit Ø 20 mm
1 Fixed Camera CCTV Installation
2 Colour Fixed Camera Dome
3 Colour Fixed Camera c/w Housing Outdoor type + accessories

1.2 Main Equpment (Central CCTV)


1 DVR Card + Multiplexer cap. 16 Channel c/w hardisk 2 TB
2 Multi Screen Color Monitor 20 inch
3 Power Surge Arester 40 kA
4 UPS 1000 VA
5 Programming
6 Closed Rack

K-2 Ground Floor


Coaxial Cable RG59 c/w Power Cable in High Impact Conduit Ø 20 mm
1 Fixed Camera CCTV Installation
2 Colour Fixed Camera Dome
3 Colour Fixed Camera c/w Housing Outdoor type + accessories
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

K-3 1st Floor to 18th Floor


Coaxial Cable RG59 c/w Power Cable in High Impact Conduit Ø 20 mm
1 Fixed Camera CCTV Installation
2 Colour Fixed Camera Dome
3 Colour Fixed Camera c/w Housing Outdoor type + accessories

K-4 Roof Top


Coaxial Cable RG59 c/w Power Cable in High Impact Conduit Ø 20 mm
1 Fixed Camera CCTV Installation
2 Colour Fixed Camera Dome

L MATV INSTALLATION
MATV Installation
L-1 Main Equipment / Central MATV
1 Combiner 33 Channel
2 Active Splitter (First Media/Cable Vision/Indo Vision)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

3 Single Channel Amplifier 10 Channel


4 Outlet Socket
5 Masthead Amplifier
6 Line Surge Arrester 10kA
7 Power Surge Arrester 40kA
8 Coaxial Line Surge Arrester 10kA
9 UPS 1000 VA
10 Antenna UHF c/w Instalatiion
11 Antenna VHF c/w Instalation
12 Antenna Parabola Masive Type c/w Instalation
13 Modulator
14 Closed Rack
15 Supporting Material

L-2 Basement BI and B2


Coaxial Cable RG 6 & 11 c/w Power Cable in High Impact Conduit Ø 20 mm
1 Outlet TV Antenna Installation
2 Outlet TV Antenna

L-3 Ground Floor


1 Outlet TV Antenna Installation
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

2 Outlet TV Antenna
3 Splitter Installation
4 Indoor Splitter 4 ways

L-4 1st Floor to 18th Floor


1 Outlet TV Antenna Installation
2 Outlet TV Antenna
3 Splitter Installation
4 Indoor Splitter 4 ways
5 Taps Installation
6 Indoor Taps 4 ways

L-5 Roof Top


1 Outlet TV Antenna Installation
2 Outlet TV Antenna
3 Splitter Installation
4 Indoor Splitter 4 ways
5 Taps Installation
6 Indoor Taps 4 ways
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

M SOUND SYSTEM INSTALLATION


M - 1 MAIN EQUIPMENT
1.1 Sound System Equipment Installation
Cable NYMHY 2x1.5 mm² c/w Power Cable in High Impact Conduit Ø 20 mm
1 Speaker Selector
2 Main Distribution Frame Sound System (MDFSS)
3 Power Amplifier
4 Power Amplifier
5 Paging Microphone
6 Matrix System c/w System Manager & Surveillance

7 Paging Microphone in receptionist Installation


8 UPS 2000 VA
9 Power Surge Arrester 40kA
10 Cabinet Rack
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

1.2 Car Call Main Equipment


1 Speaker Selector
2 Main Distribution Frame Sound System (MDFSS)
3 Power Amplifier
4 Power Amplifier
5 Car Call Microphone
6 Microphone Car Call Installation in reception room
7 Chime Module
8 Microphone Pre Amplifire module

1.3 Emergency Main Equipment


1 Speaker Selector
2 Emergency Power Amplifier 120W
3 Relay
4 UPS 2000 VA
5 Power Surge Arrester 40kA
6 Microphone Emergency
7 Microphone Emergency direcptionis Installation
8 Grounding Installation

1.4 Terminal Box


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

1 Sound System Terminal Box


2 Cabinet Rack

M-2 Basement BI and B2


2.1 Cable NYMHY 2x1.5 mm² c/w Power Cable in High Impact Conduit Ø 20 mm
1 Ceilling Speaker Instalation
2 Ceiling Speaker 3W
3 Horn Speaker 15W
4 Volume Control & Instalation

2.2 Emergency Sound System


Cable FRC 2x1.5 mm² inside High Impact conduit Ø 20 mm
1 Emergency Speaker Installation
2 Wall Speaker 10 "

2.3 Terminal Box


1 Sound System Terminal Box - Basement Level (SSTB = B)
2 Cable NYMHY 3x1.5 mm² MDFSS to SSTB - B
3 Cable FRC 2x2.5 mm² MDFSS to SSTB - B)
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

M-3 Ground Floor


3.1 Cable NYMHY 2x1.5 mm² c/w Power Cable in High Impact Conduit Ø 20 mm
1 Ceilling Speaker Instalation
2 Ceiling Speaker 3W
3 Horn Speaker 15W
4 Volume Control & Instalation

3.2 Cable FRC 2x1.5 mm² inside High Impact conduit Ø 20 mm


1 Emergency Speaker Installation
2 Wall Speaker 10 "

M-4 1st Floor to 18th Floor


4.1 Cable NYMHY 2x1.5 mm² c/w Power Cable in High Impact Conduit Ø 20 mm
1 Ceilling Speaker Instalation
2 Ceiling Speaker 3W
3 Horn Speaker 15W
4 Volume Control & Instalation

4.2 Cable FRC 2x1.5 mm² inside High Impact conduit Ø 20 mm


CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

1 Emergency Speaker Installation


2 Wall Speaker 10 "

4.3 Terminal Box


1 Sound System Terminal Box - Basement Level (SSTB = B)
2 Cable NYMHY 3x1.5 mm² MDFSS to SSTB - B
3 Cable FRC 2x2.5 mm² MDFSS to SSTB - B)

M-5 Roof Top


5.1 Cable NYMHY 2x1.5 mm² c/w Power Cable in High Impact Conduit Ø 20 mm
1 Speaker Instalation
2 Ceiling Speaker 3W
3 Wall Speaker 10W
4 Volume Control & Instalation

5.2 Cable FRC 2x1.5 mm² inside High Impact conduit Ø 20 mm


1 Emergency Speaker Installation
2 Wall Speaker 10 "
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

5.3 Terminal Box


1 Sound System Terminal Box
2 Cable NYMHY 3x1.5 mm² MDFSS to SSTB - B
3 Cable FRC 2x2.5 mm² MDFSS to SSTB - B)

N TELEPHONE INSTALLATION
Telephone Installation c/w Accessories
N - 1 Main Equipment
1 Main Unit PABX cap. 240 co line 1.440 Extention :

2 MDF Box c/w frame & LSA 200 Ext.


3 Cable ITC 100x2x0.6mm² (MDF - PABX)
4 Operator Console + Operator Telephone Unit
5 Hand set digital key Telephone w/ display screen
6 Billing Sistem c/w Computer and report printer
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

7 Line Surge Arrester 40 KA


8 Power Surge Arrester 40 KA
9 Telephone Connection to PT TELKOM

N-2 Basement BI and B2


2.1 Cable ITC 20x2x0.6mm² in High Impact conduit Ø 20 mm
1 Telephone Installation
2 Single LineTelephone Hand Set
3 Wall Telephone Outlet 1 Pole

2.2 Terminal Box


1 Terminal Box Telephone Parallel to Ground Floor (TBTP - GF)
2 Cable ITC 20x2x0.6mm² TBTP - GF to MDF - TL

N-3 Ground Floor


3.1 Cable ITC 20x2x0.6mm² in High Impact conduit Ø 20 mm
1 Telephone Installation
2 Single LineTelephone Hand Set
3 Wall Telephone Outlet 1 Pole
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

3.2 Terminal Box


1 Terminal Box Telephone Parallel to Ground Floor (TBTP - GF)
2 Cable ITC 20x2x0.6mm² TBTP - GF to MDF - TL

N-4 1st Floor to 18th Floor


4.1 Cable ITC 20x2x0.6mm² in High Impact conduit Ø 20 mm
1 Telephone Installation
2 Single LineTelephone Hand Set
3 Wall Telephone Outlet 1 Pole

4.2 Terminal Box


1 Terminal Box Telephone Parallel to Ground Floor (TBTP - GF)
2 Cable ITC 20x2x0.6mm² TBTP - GF to MDF - TL

N - 5 Roof Top
Cable ITC 20x2x0.6mm² in High Impact conduit Ø 20 mm
1 Telephone Installation
2 Single LineTelephone Hand Set
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

3 Wall Telephone Outlet 1 Pole

O COMPUTER EQUIPMENT & CABLE INSTALLATION


Data Computer Cable Equipment & Installation Work, Distribution Switch
O - 1 Main Equipment
1 Computer Server

2 Air Conditioning Unit 2 PK


3 Installation & Programming Work
4 Closed Rack Wall Mounted

O - 2 Basement BI and B2
Cable UTP Cat 6 in High Impact conduit Ø 20mm
1 Computer Data Cable Installation
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

2 Data Computer Outlet Wall Mounted


3 Distribution Switch Hub Basement Level
4 Power Switch Hub Installation Ground Floor + Stop Contact
5 Switch Hub Installation Basement Level to Main Switch Hub

O-3 Ground Floor


3.1 Cable UTP Cat 6 in High Impact conduit Ø 20mm
1 Computer Data Cable Installation
2 Data Computer Outlet Wall Mounted
3 Distribution Switch Hub Ground Floor Level
4 Distribution Switch Hub Installation Ground Floor + Stop Contact
5 Distrb. Switch Hub Installation Ground Floor Level to Main Switch Hub

3.2 WIFI Hotspot


1 Wifi Data Cable Installation to Distribution Switch
2 Ceilling Antenna
3 Signal Splitter
4 Radio Access Point 150 Mbps + Installation
5 Closed Rack Wall Mounted
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

O-4 1st Floor to 18th Floor


4.1 Cable UTP Cat 6 in High Impact conduit Ø 20mm
1 Computer Data Cable Installation
2 Data Computer Outlet Wall Mounted
3 Distribution Switch Hub per Level
4 Distribution Switch Hub Installation per Floor + Stop Contact
5 Distrb. Switch Hub Installation per Floor Level to Main Switch Hub

4.2 WIFI Hotspot


1 Wifi Data Cable Installation to Distribution Switch
2 Ceilling Antenna
3 Signal Splitter
4 Radio Access Point 150 Mbps + Installation
5 Closed Rack Wall Mounted

O-5 Roof Top


5.1 Cable UTP Cat 6 in High Impact conduit Ø 20mm
1 Computer Data Cable Installation
2 Data Computer Outlet Wall Mounted
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION

5.2 WIFI Hotspot


1 Wifi Data Cable Installation to Distribution Switch
2 Ceilling Antenna
3 Signal Splitter
4 Radio Access Point 150 Mbps + Installation
5 Closed Rack Wall Mounted

P LIGHTNING GROUNDING CABLE INSTALLATION


Lightning Grounding Cable Equipment & Installation Work

1 Head Terminal w/ Protection Radius 50 meter


2 Down conductor NYY tegangan tinggi 70 mm²
3 Grounding Resistance Hole + Digging Work max 3 ohm
4 Supporting Post Lightning Receiver 1 meter c/w clamp
5 Supporting Material
6 Licensing
CONSTRUCTION COST ESTIMATION
NAME OF PROJECT : East Park Apartmen Buaran Jatinegara, East Jakarta
PROJECT ACTIVITY : Construction of 18th floor Apartmen
DEVELOPER : PT. BANGUN SARANA GRAHA LESTARI
MAIN CONTRACTOR : PT.
NUMBER OF BLDG : 2 (Two) Tower D and Tower E

No. JOB DESCRIPTION


CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Batten Board and Meassuring Equipment 340.00 M' A-02a


Removing Tree, Plants, Soil and Unused Material 7,000.00 M2
Zinc BJLS, Dolken Wood, h=2 m 340.00 M'

TOTAL A - 1

Excavator + Supporting Equipment 21,000.00 M3 B-02


Bulldozer, Excavator - M3
Level B1 Basement 21,000.00 M3
Water Pump + Supporting Equipment 1.00 Ls

TOTAL A - 2

Batten Board and Meassuring Equipment 157.00 M' A-02a


Foundation, Concrete Structure 4m x 6m x 3m + Finished 1.00 Ls
Container Office 1.00 Ls A-03b
Container Office 1.00 Ls A-03b
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Wood, Zinc Cover, Asbes Roof 1.5m x 2m x 2.5 m 3.00 M2 A-05


Wood board, Multiplex, Zinc cover, Asbestos Roof, 2 floor 100.00 M2 A-05

TOTAL A - 3

25 Kva, Silent c/w Installation ex Cummins 2.00 Unit 0


by Telkom 1.00 Ls 0
By PDAM 1.00 Ls 0
3000 lt/1 month, estimated consumption per year 36,000.00 Litre 0
Estimated Consumption per year 12.00 Ls 0
Estimated Consumption per year 12.00 Ls 0
Steel Plat, Steel pipe, Paint finished, Digital Printed 1.00 Ls 0
Portable 45 kg CO2 3.00 Unit 0

TOTAL A - 4

Lump Sum 1.00 Ls 0


Concrete Wall, 100 m x 70 m, t.15cm, h = 7 m 306.00 M3 D-05q
50 m x 60 m area 1.00 Ls 0
Reinforced Concrete Pipe dim, 8x5x1 m, t = 12 cm 160.00 M' 0
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

U-Ditch dim. 160.00 M' 0


Plaster Finished + Epoxy Waterproof Coating 2.00 Ls D-14a
Plaster Finished + Epoxy Waterproof Coating 2.00 Ls D-14b
Plaster Finished + Epoxy Waterproof Coating 2.00 Ls D-14c
Plaster Finished + Epoxy Waterproof Coating 2.00 Ls D-14d
Plaster Finished + Epoxy Waterproof Coating 2.00 Ls D-14g

TOTAL A - 5
TOTAL A

Batten Board and Meassuring Equipment 869.00 M' A-02a


Pile Cap 70 Nr dim. 1.35 x 1.35 x 0.7 m 102.90 1 M3 B-02
Pile Cap 94 Nr dim. 1.6 x 1.6 x 0.75 m 204.73 1 M3 B-02
Pile Cap 20 Nr dim. 2 x 2 x 0.8 m 68.00 1 M3 B-02
Tie Beam dim. 25 x 45 cm 105.15 1 M3 B-02
Tie Beam dim. 25 x 50 cm 37.62 1 M3 B-02
Tie Beam dim. 30 x 60 cm 70.98 1 M3 B-02
Tie Beam dim. 30 x 65 cm 129.18 1 M3 B-02
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Tie Beam dim. 35 x 65 cm 63.56 1 M3 B-02


Tie Beam dim. 40 x 75 cm 71.10 1 M3 B-02
In Civil Work
In Civil Work

TOTAL B.1.1

Mobilization of Plant and Equipment 1.00 Ls 0


Survey and setting out of the work
Pile Test Work
Site Leveling
Material Testing

TOTAL B.1.2

Mobilization of Plant and Equipment 1.00 Ls 0


Survey and setting out of the work - 0 0
120 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 280.00 M3 D-05e
120 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 376.00 M3 D-05e
120 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 80.00 M3 D-05e
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Drilling Soil 15 m + Pile Driver + Pile Hammer 4,200.00 M' C-05


Drilling Soil 15 m + Pile Driver + Pile Hammer 5,640.00 M' C-05
Drilling Soil 15 m + Pile Driver + Pile Hammer 1,200.00 M' C-05
1.00 Ls 0
1.00 Ls 0

TOTAL B.1.3

Batten Board and Meassuring Equipment 2,192.75 M' A-02a


120 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 12.47 M3 D-05h
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 78.86 M3 D-05g
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 28.50 M3 D-05g
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 56.16 M3 D-05g
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 102.81 M3 D-05g
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 51.64 M3 D-05g
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 59.25 M3 D-05g
120 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 1,415.97 M3 D-05h
120 kg Steel K-300 NFA/Fc'30 Mpa 1,415.97 M3 D-05i
150 kg Steel K-350 NFA/Fc'30 Mpa 78.86 M3 D-05k
150 kg Steel K-350 NFA/Fc'30 Mpa 28.50 M3 D-05k
150 kg Steel K-350 NFA/Fc'30 Mpa 56.16 M3 D-05k
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

150 kg Steel K-350 NFA/Fc'30 Mpa 102.81 M3 D-05k


150 kg Steel K-350 NFA/Fc'30 Mpa 51.64 M3 D-05k
150 kg Steel K-350 NFA/Fc'30 Mpa 59.25 M3 D-05k
230 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 32.48 M3 D-05m
230 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 29.75 M3 D-05m
230 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 133.56 M3 D-05m
230 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 58.24 M3 D-05m
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 25.58 M3 D-05q
5.5 m x 1.5 m w/ landing plate 1 m, h. 3.5 m, as drawing 3.49 M3 D-05g
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 89.30 M3 D-05f
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 180.48 M3 D-05f
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 64.00 M3 D-05f

TOTAL B.2.1

Batten Board and Meassuring Equipment 2,192.75 M' A-02b


120 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 12.47 M3 D-05k
120 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 1,415.97 M3 D-05i
150 kg Steel K-350 NFA/Fc'30 Mpa 78.86 M3 D-05k
150 kg Steel K-350 NFA/Fc'30 Mpa 28.50 M3 D-05k
150 kg Steel K-350 NFA/Fc'30 Mpa 56.16 M3 D-05k
150 kg Steel K-350 NFA/Fc'30 Mpa 102.81 M3 D-05k
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

150 kg Steel K-350 NFA/Fc'30 Mpa 51.64 M3 D-05k


150 kg Steel K-350 NFA/Fc'30 Mpa 59.25 M3 D-05k
200 kg Steel K-350 NFA/Fc'30 Mpa 32.48 M3 D-05n
200 kg Steel K-350 NFA/Fc'30 Mpa 29.75 M3 D-05n
200 kg Steel K-350 NFA/Fc'30 Mpa 133.56 M3 D-05n
200 kg Steel K-350 NFA/Fc'30 Mpa 58.24 M3 D-05n
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 25.58 M3 D-05q
5.5 m x 1.5 m w/ landing plate 1 m, h. 3.5 m, as drawing 3.49 M3 D-05g

TOTAL B.2.2

Batten Board and Meassuring Equipment 1,381.00 M' A-02b


120 kg Steel K-300 NFA/Fc'30 Mpa 364.20 M3 D-05i
150 kg Steel K-350 NFA/Fc'30 Mpa 45.00 M3 D-05k
150 kg Steel K-350 NFA/Fc'30 Mpa 35.88 M3 D-05k
150 kg Steel K-350 NFA/Fc'30 Mpa 135.33 M3 D-05k
200 kg Steel K-350 NFA/Fc'30 Mpa 38.08 M3 D-05n
200 kg Steel K-350 NFA/Fc'30 Mpa 38.50 M3 D-05n
200 kg Steel K-350 NFA/Fc'30 Mpa 37.80 M3 D-05n
200 kg Steel K-350 NFA/Fc'30 Mpa 58.24 M3 D-05n
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 33.68 M3 D-05q
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

5.5 m x 1.5 m w/ landing plate 1 m, h. 3.5 m, as drawing 3.49 M3 D-05g

TOTAL B.2.3

Batten Board and Meassuring Equipment 8,286.00 M' A-02b


120 kg Steel K-300 NFA/Fc'30 Mpa 2,185.20 M3 D-05i
150 kg Steel K-350 NFA/Fc'30 Mpa 270.00 M3 D-05k
150 kg Steel K-350 NFA/Fc'30 Mpa 215.25 M3 D-05k
150 kg Steel K-350 NFA/Fc'30 Mpa 811.98 M3 D-05k
200 kg Steel K-350 NFA/Fc'30 Mpa 228.48 M3 D-05n
200 kg Steel K-350 NFA/Fc'30 Mpa 231.00 M3 D-05n
200 kg Steel K-350 NFA/Fc'30 Mpa 226.80 M3 D-05n
200 kg Steel K-350 NFA/Fc'30 Mpa 349.44 M3 D-05n
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 202.10 M3 D-05q
5.5 m x 1.5 m w/ landing plate 1 m, h. 3.5 m, as drawing 20.95 M3 D-05g
120 kg Steel K-300 NFA/Fc'30 Mpa 250.80 M3 0
120 kg Steel K-300 NFA/Fc'30 Mpa 9.07 M3 0

TOTAL B.2.4
-
Batten Board and Meassuring Equipment 16,572.00 M' A-02b
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

120 kg Steel K-300 NFA/Fc'30 Mpa 4,370.40 M3 D-05j


130 kg Steel K-350 NFA/Fc'30 Mpa 540.00 M3 D-05l
130 kg Steel K-350 NFA/Fc'30 Mpa 430.50 M3 D-05l
130 kg Steel K-350 NFA/Fc'30 Mpa 1,623.96 M3 D-05l
150 kg Steel K-350 NFA/Fc'30 Mpa 456.96 M3 D-05p
150 kg Steel K-350 NFA/Fc'30 Mpa 462.00 M3 D-05p
150 kg Steel K-350 NFA/Fc'30 Mpa 453.60 M3 D-05p
150 kg Steel K-350 NFA/Fc'30 Mpa 698.88 M3 D-05p
150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 404.21 M3 D-05q
5.5 m x 1.5 m w/ landing plate 1 m, h. 3.5 m, as drawing 41.89 M3 D-05g
120 kg Steel K-300 NFA/Fc'30 Mpa 501.60 M3 0
120 kg Steel K-300 NFA/Fc'30 Mpa 18.13 M3 0

TOTAL B.2.5

Batten Board and Meassuring Equipment 25.79 M' A-02b


150 kg Steel K-350 NFA/Fc'30 Mpa w/ Puzdith 100 33.68 M3 D-05q

TOTAL B.2.6
TOTAL B
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Light Brick Concrete Block (Hebel) Masonry Wall Work dim. 60x20x7.5 172.60 M2 E-02b
Plaster Work 1 Pc : 3 Sn, t. 20 mm 345.20 M2 F-01c
MU Cement, Water, Sand Paper, Rubing Paper 2,782.62 M2 F-03b
Sika Chapdur (Red) + Trowel Finish 9,439.77 M2 F-04
- M2 N-10

TOTAL C - 1

Light Brick Concrete Block (Hebel) Masonry Wall Work dim. 60x20x7.5 303.13 M2 E-02b
Plaster Work 1 Pc : 3 Sn, t. 20 mm 606.26 M2 F-01c
MU Cement, Water, Sand Paper, Rubing Paper 3,027.48 M2 F-03b
Sika Chapdur (Red) + Trowel Finish 9,439.77 M2 F-04
Epoxy Paint Work (1kg/5 m2) 1000 micron - M2 N-10

TOTAL C - 2

Light Brick Concrete Block (Hebel) Masonry Wall Work dim. 60x20x7.5 1,992.00 M2 E-02b
Plaster Work 1 Pc : 4 Sn, t. 20 mm 5,492.96 M2 F-01b
MU Cement, Water, Sand Paper, Rubing Paper 6,602.64 M2 F-03b
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Paving Block Tile 6,579.83 M2 0


Canstine Block - 0 0

TOTAL C - 3

Wall Panel 100x600x3000 mm ex Quipanel, 120 kg 23,871.06 M2 E-02c


Light Brick Concrete Block (Hebel) Masonry Wall Work dim. 60x20x7.5 95,140.08 M2 E-02a
Plaster Work 1 Pc : 4 Sn, t. 20 mm 238,022.28 M2 F-01a
MU Cement, Water, Sand Paper, Rubing Paper 265,436.28 M2 F-03b

TOTAL C - 4

Light Brick Concrete Block (Hebel) Masonry Wall Work dim. 60x20x7.5 172.60 M2 E-02c
Plaster Work 1 Pc : 4 Sn, t. 20 mm 345.20 M2 F-01c
Epoxy Paint Work (1kg/5 m2) 1000 micron 3,035.00 M2 N-10

TOTAL C - 5
TOTAL C

Paint ex Pentalite ICI Interior 10 m2/ltr 3 layer 2,491.62 M2 N-06a


CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Ducco Metal Coat ex ICI/Dulux 3 x layer 2000 μm 16.80 M2 N-9c


Epoxy Paint ex ICI/Dulux 3 layer 1000 mikron 5 m2/kg 291.00 M2 N-10
Steel Door Fire proof 1010 x 2150 mm t.1.6 mm c/w frame t. 2mm 2.00 Item K-14
11.00 M 0

TOTAL D - 1

Paint ex Pentalite ICI Interior 10 m2/ltr 3 layer 3,027.48 M2 N-06a


Finished Varnish ex Ultran 5.16 M2 N-04
Ducco Metal Coat ex ICI/Dulux 3 x layer 2000 μm 16.80 M2 N-9c
Floor Tile ex Roman/Similar, PC, SN + Groutting Colour PC 52.50 M2 I-04e
Base Plate ex Roman/Similar, PC, SN + Groutting Colour PC 28.10 M' I-02b
Floor Tile ex Roman/Similar, PC, SN + Groutting Colour PC 18.00 M2 I-04b
Base Plate ex Roman/Similar, PC, SN + Groutting Colour PC 28.00 M I-02c
Epoxy Paint 3 layer 1000 mikron 5 m2/kg 291.00 M2 N-10
10.00 Item 0
Door Panel Wood Plank Kamper Medan w. 90 cm h. 210 cm 1.00 Nr J-04a
Wood Frame Profile Kamper Medan 6 x 15 cm 1.00 Nr J-03a
Steel Door Fire proof 1010 x 2150 mm t.1.6 mm c/w frame t. 2mm 2.00 Unit K-14
11.00 M 0

TOTAL D - 2
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Paint ex Pentalite ICI Exterior 3 layer 10 m2/ltr + Supporting Eqp 6,602.64 M2 N-06a
Finished Varnish ex Ultran 30.48 M2 N-04
Ducco Metal Coat ex ICI/Dulux 3 x layer 2000 μm 436.80 M2 N-9c
Granito Floor Tile ex Essenza/Similar, PC, SN + Groutting 170.50 M2 I-01a
Granito Base Plate ex Essenza/Similar, PC, SN + Groutting 87.60 M' I-02a
Floor Tile ex Roman/Similar, PC, SN + Groutting Colour PC 2,681.45 M2 I-04e
Base Plate ex Roman/Similar, PC, SN + Groutting Colour PC 595.30 M' I-02b
Wall Tile ex Roman/Similar, PC, SN + Groutting Colour PC 167.60 M2 E-09c
22.68 M2 J-05d
74.52 M2 J-05d
Door Panel Wood Plank Kamper Medan w. 90 cm h. 210 cm 4.00 Nr J-04a
Door Panel Wood Plank Kamper Medan w. 70 cm h. 210 cm 2.00 Nr J-04c
Wood Frame Profile Kamper Medan 6 x 15 cm 4.00 Nr J-03a
Wood Frame Profile Kamper Medan 6 x 15 cm 2.00 Nr J-03c
Steel Door Fire proof 1010 x 2150 mm t.1.6 mm c/w frame t. 2mm 4.00 Item K-14
11.00 M 0
Frame and Door Alumunium profile ex EDICO or similar, Hinge, 2.00 Unit K-15
Door handle, Temperded Glass ex ASAHI 5 mm, rubber seal - 0 0
Frame and Door Alumunium profile ex EDICO or similar, Hinge, 2.00 Unit K-16
Door handle, Temperded Glass ex ASAHI 5 mm, rubber seal - 0 0
Frame and Door Alumunium profile ex EDICO or similar, Hinge, 4.00 Unit K-18
Door handle, Temperded Glass ex ASAHI 5 mm, rubber seal - 0 0
Frame and Door Alumunium profile ex EDICO or similar, Hinge, 2.00 Unit K-17
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Frame and Door Alumunium profile ex EDICO or similar, Hinge, 430.50 M2 K-09k
Door handle, Temperded Glass ex ASAHI 5 mm, rubber seal
TOTAL D - 3

Paint ex Pentalite ICI Exterior 3 layer 10 m2/ltr + Supporting Eqp 47,720.52 M2 N-06a
Paint ex Pentalite ICI Exterior 3 layer 10 m2/ltr + Supporting Eqp 204,323.76 M2 N-06b
Finished Varnish ex Ultran 24,416.64 M2 N-04
Ducco Metal Coat ex ICI/Dulux 3 x layer 2000 μm 302.40 M2 N-9c
Floor Tile ex Roman/Similar, PC, SN + Groutting Colour PC 50,346.00 M2 I-04e
Base Plate ex Roman/Similar, PC, SN + Groutting Colour PC - M' I-02b
Floor Tile Setting Work ex Mulia dim. 20x20 cm Colour Patern 5,130.00 M2 I-03b
Base Plate ex Roman/Similar, PC, SN + Groutting Colour PC - M I-02c
Wall Tile Work 20 x 25 cm Plain ex Mulia 13,392.00 M2 E-07e
Door Panel Wood Plank Kamper Medan w. 90 cm h. 210 cm 1,440.00 Nr J-04a
Wood Frame Profile Kamper Medan 6 x 15 cm 1,440.00 Nr J-03a
Door Panel Wood Plank Kamper Medan w. 80 cm h. 210 cm 2,304.00 Nr J-04b
Wood Frame Profile Kamper Medan 6 x 15 cm 2,304.00 Nr J-03b
Door Panel Wood Plank Kamper Medan w. 70 cm h. 210 cm 1,440.00 Nr J-04c
Wood Frame Profile Kamper Medan 6 x 15 cm 1,440.00 Nr J-03c
Steel Door Fire proof 1010 x 2150 mm t.1.6 mm c/w handle + frame t. 72.00 Item K-14
198.00 M 0
72.00 Unit K-21
Frame and Door Alumunium profile ex EDICO or similar, Hinge,
360.00 Unit K-20
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

1,368.00 Unit K-19


Door handle, Temperded Glass ex ASAHI 5 mm, rubber seal
1,080.00 Unit K-22
360.00 Unit K-23

TOTAL D - 4

Paint ex Pentalite ICI Exterior 3 layer 10 m2/ltr + Supporting Eqp - M2 N-06a


Paint ex Pentalite ICI Exterior 3 layer 10 m2/ltr + Supporting Eqp - M2 N-06b
Ducco Metal Coat ex ICI/Dulux 3 x layer 2000 μm 2.00 Item K-14
- M2 0

TOTAL D - 5
TOTAL D

Hollow Steel 0.6, Gypsum Board 9 mm ex jayaboard + Support Eq 1,863.50 M2 H-05b


Hollow Steel 0.6, GRC Board 120 x 240 x 9 mm + Support Eq 207.77 M2 H-06b
Ceilling Moulding ex Jayaboard 1,569.42 M' H-07b
Paint ex ICI/Dulux 3 layer + Supporting Equipment 2,071.27 M2 N-7b

TOTAL E - 1
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Hollow Steel 0.6, Gypsum Board 9 mm ex jayaboard + Support Eq 51,264.00 M2 H-05b


Hollow Steel 0.6, GRC Board 120 x 240 x 9 mm + Support Eq 7,159.91 M2 H-06b
Ceilling Moulding ex Jayaboard 68,006.37 M' H-07b
Paint ex ICI/Dulux 3 layer + Supporting Equipment 68,624.86 M2 N-7b

TOTAL E - 2

- 0 0
- 0 0
- 0 0

TOTAL E - 3
TOTAL E

Toliet Squat ex TOTO Porcelain White 10.00 Item M-01


Wall Faucet ex Onda 1/2" 12.00 Item M-09
Floor Drain T5-A Outlet 50 mm Stainless Steel c/w Cover 4" 10.00 Item M-10a

TOTAL F - 1
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Toilet Seat type Flush Jet System ex TOTO White 20.00 Item M-15
Jet Washer for Closet ex TOTO 20.00 Item M-20
Water Sink Faucet Stainless Steel ex TOTO TX-129L 12.00 Item M-22
Sink Liquid Soap Holder ex Krisbow NGLE 4.00 Item M-23
Urinoir TOTO Colour Standard c/w Accessories 8.00 Item M-02a
Floor Drain T5-A Outlet 50 mm Stainless Steel c/w Cover 4" 20.00 Item M-10a
Sink Oval ex INA LW 230 c/w Mirror & Accessories White 12.00 Item M-03
Mirror Glass t. 5 mm ex ASAHIMAS 8.00 M2 M-24
Toilet Paper Holder TX-703AC ex TOTO 20.00 Item M-25
Precast dia. 50 cm / U - Gutter AW 0 0
Precast Cover dia. 50 cm AW 0 0

TOTAL F - 2

Toilet Seat type Flush Jet System ex TOTO White 1,440.00 Item M-15
Jet Washer for Closet ex TOTO 1,440.00 Item M-20
Shower wall mounted ex TOTO 1,440.00 Item M-21
Addition Work AW 0 0
Sink Oval ex INA LW 230 c/w Mirror & Accessories White 1,440.00 Item M-03
1,440.00 0 0

TOTAL F - 3
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

- 0 0
- 0 0
- 0 0

TOTAL F - 4
TOTAL F

Type AB-01 & 02, Cap. 2x 350 lpm / 80 M / 7.5 kW 2.00 Set M-27a
Cap. 400 lpm , 30 Meter, 1 kW + Supporting Equip. 4.00 Set M-27a
Submersible Pump 80 LPM, 40m, 2 kW + Supporting Equip. 2.00 Set M-27c
Centrifugal End Suction Cap. 400 lpm , 30 Meter, 1 kW 2.00 Set M-27a
Cap. 2 x 200 lpm , 20 m, 0.7 kw + Cover, reinforce concrete 2.00 Set M-27c

TOTAL G - 1

GIP Medium A Ø 50 mm or 2 " + Accessories - 0


GIP Medium A Ø 50 mm or 2 " + Accessories 75.60 M' M-17e
96.00 0
WLC w/ Nylon rope 2.00 Set M-28
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Y Check Valve 2" 2.00 Set M-29d


Gate Valve Thread 125psi 2" 4.00 Set M-31d
Ø 50 mm or 2" 2.00 Set M-33
WLC 2.00 Set M-34a
Ø 50 mm or 2" 2.00 Set M-33
Ø 75 mm or 3" 8.00 Set M-35a
Check Valve 3" 4.00 Set M-30a
Ø 75 mm or 3" 8.00 Set M-31d
Ø 75 mm or 3" 4.00 Set M-36a
Ø 50 mm or 2" 2.00 Set M-34c
WLC w/ Nylon rope 2.00 Set M-28
GIP Medium A Ø 75 mm or 3 " 3.00 M' M-17f
PVC AW Ø 65 mm or 2 1/2" + Accessories 24.00 M' M-07d
Ø 65 mm or 2 1/2" 4.00 Set M-35c
Check Valve 2 1/2" 4.00 Set M-30c
Gate Valve Thread 125psi 2 1/2" 4.00 Set M-31c
Ø 65 mm or 2 1/2" 4.00 Set M-36b
Ø 50 mm or 2" 6.00 Set M-31b
PVC AW Ø 50 mm or 2 " + Accessories 42.00 M' M-07d
Ø 50 mm or 2" 4.00 Set M-31b
PPR PN 10 Ø 50 mm or 2 " + Accessories 96.00 M' M-26d
Ø 50 mm or 2" 4.00 Set M-33
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Ø 50 mm or 2" 2.00 Set M-34c


Ø 50 mm or 2" 4.00 Set M-35b
Ø 50 mm or 2" 4.00 Set M-30b
Ø 50 mm or 2" 4.00 Set M-31b
PPR PN 10 Ø 50 mm or 2 " + Accessories 144.00 M' M-26d
WLC w/ Nylon rope 2.00 Set M-28
Ø 50 mm or 2" 2.00 Set M-33

TOTAL G - 2

FRP 4x3x3 m, water level 2,5 m, Cap. 30 m3 220.00 M3 M-37


30 m Bore Work, Piping Work 2.00 0
2.00 0
2.00 0
Excavt.3m, Ijuk layer,stone layer, Conc Pipe 2m, Conc cover 24.00 0
Sand+Carbon+MN Filter, Press Gauge, Safety Valve, Sight glass AW 0
2.00 0
by Civil 2.00 Ls
by Civil 2.00 Ls
by Civil 2.00 Ls
by Civil 2.00 Ls
by Civil 2.00 Ls
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Plaster Finished + Epoxy Waterproof Coating 2.00 Ls D-14e

TOTAL G - 3

PPR PN 10 Ø 15 mm or 1/2 " + Accessories 93.00 M' M-26a


PPR PN 10 Ø 40 mm or 2 " + Accessories 32.00 M' M-26d
Ø 50 mm or 2" 2.00 Set M-30b
Ø 50 mm or 2" 2.00 Set M-31b

TOTAL G - 4.1.1

PPR PN 10 Ø 15 mm or 1/2 " + Accessories 704.00 M' M-26a


PPR PN 10 Ø 25 mm or 1 " + Accessories 1,989.60 M' M-26b
PPR PN 10 Ø 40 mm or 1 1/2 " + Accessories 738.00 M' M-26c
PPR PN 10 Ø 50 mm or 2 " + Accessories 14.00 M' M-26d
Ø 50 mm or 2" 4.00 Set M-30b
Ø 50 mm or 2" 4.00 Set M-32
Ø 50 mm or 2" 80.00 Set M-31b
Ø 25 mm or 1" 80.00 Set M-34b
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL G - 4.1.2

PPR PN 10 Ø 15 mm or 1/2 " + Accessories 4,968.00 M' M-26a


PPR PN 10 Ø 25 mm or 1 " + Accessories 5,886.00 M' M-26b
PPR PN 10 Ø 40 mm or 1 1/2 " + Accessories 3,888.00 M' M-26c
PPR PN 10 Ø 50 mm or 2 " + Accessories 157.50 M' M-26d
Ø 50 mm or 2" 72.00 Set M-30b
Ø 50 mm or 2" 72.00 Set M-32
Ø 25 mm or 1" 1,440.00 Set M-31b
Ø 25 mm or 1" 1,440.00 Set M-34b

TOTAL G - 4.1.3

PPR PN 10 Ø 15 mm or 1/2 " + Accessories 176.00 M' M-26a


PPR PN 10 Ø 25 mm or 1 " + Accessories 28.00 M' M-26b
PPR PN 10 Ø 40 mm or 1 1/2 " + Accessories 34.00 M' M-26c
PPR PN 10 Ø 65 mm or 2 1/2 " + Accessories 36.00 M' M-26e
PPR PN 10 Ø 50 mm or 2 " + Accessories 18.00 M' M-26d
Check Valve 2" 6.00 Set M-30b
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

GIP Ø 75 mm or 3" 6.00 Set M-31d

TOTAL G - 4.1.4

PVC AW Ø 25 mm or 1 " + Accessories 84.40 M' M-07b


PVC AW Ø 50 mm or 2 " + Accessories 286.60 M' M-07d
PVC AW Ø 100 mm or 4 " + Accessories 116.00 M' M-07f

TOTAL G - 4.2.1

PVC AW Ø 25 mm or 1 " + Accessories 126.00 M' M-07b


PVC AW Ø 50 mm or 2 " + Accessories 240.00 M' M-07d
PVC AW Ø 50 mm or 3 " + Accessories 355.20 M' M-07e
PVC AW Ø 100 mm or 4 " + Accessories 748.50 M' M-07f
Ø 25 mm or 1 " 24.00 0 0
Ø 50 mm or 2 " 32.00 0 0
Ø 100 mm or 4 " 45.00 0 0

TOTAL G - 4.2.2
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

PVC AW Ø 25 mm or 1 " + Accessories 441.60 M' M-07b


PVC AW Ø 50 mm or 2 " + Accessories 588.60 M' M-07d
PVC AW Ø 75 mm or 3 " + Accessories 432.00 M' M-07e
PVC AW Ø 100 mm or 4 " + Accessories 43.75 M' M-07f
PVC AW Ø 50 mm or 3 " 24.00 Set M-31d
PVC AW Ø 50 mm or 4 " 9.00 Item M-10c

TOTAL G - 4.2.3

PVC AW Ø 20 mm or 3/4 " + Accessories 4,032.00 M' M-07a


PVC AW Ø 25 mm or 1 " + Accessories 7,948.80 M' M-07b
PVC AW Ø 50 mm or 2 " + Accessories 10,594.80 M' M-07d
PVC AW Ø 75 mm or 3 " + Accessories 7,776.00 M' M-07e
PVC AW Ø 100 mm or 4 " + Accessories 787.50 M' M-07f
PVC AW Ø 150 mm or 3 " 432.00 Set M-31d
PVC AW Ø 100 mm or 3 " 216.00 Item M-10c
PVC AW Ø 50 mm or 4 " 918 Item M-10c

TOTAL G - 4.2.4
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

PVC AW Ø 25 mm or 1 " + Accessories 92.84 M' M-07b


PVC AW Ø 50 mm or 2 " + Accessories 401.24 M' M-07d
PVC AW Ø 100 mm or 4 " + Accessories 208.80 M' M-07f

TOTAL G - 4.3.1

PVC AW Ø 25 mm or 1 " + Accessories 100.80 M' M-07b


PVC AW Ø 50 mm or 2 " + Accessories 96.00 M' M-07d
PVC AW Ø 100 mm or 4 " + Accessories 89.82 M' M-07e

TOTAL G - 4.3.2

PVC AW Ø 20 mm or 3/4 " + Accessories 80.64 M' M-07a


PVC AW Ø 25 mm or 1 " + Accessories 90.72 M' M-07b
PVC AW Ø 50 mm or 2 " + Accessories 235.44 M' M-07d
PVC AW Ø 75 mm or 3 " + Accessories 388.80 M' M-07e
PVC AW Ø 150 mm or 4 " + Accessories 52.50 M' M-07f
PVC AW Ø 150 mm or 4 " 8.00 Set M-31d
PVC AW Ø 50 mm or 2 " 24.00 Item M-10c
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL G - 4.3.3

PVC AW Ø 20 mm or 3/4 " + Accessories 1,451.52 M' M-07a


PVC AW Ø 25 mm or 1 " + Accessories 1,632.96 M' M-07b
PVC AW Ø 50 mm or 2 " + Accessories 4,237.92 M' M-07d
PVC AW Ø 75 mm or 3 " + Accessories 6,998.40 M' M-07e
PVC AW Ø 100 mm or 4 " + Accessories 945.00 M' M-07f
PVC AW Ø 150 mm or 4 " 144.00 Set M-31d
PVC AW Ø 150 mm or 4 " 432.00 Item M-10c
PVC AW Ø 50 mm or 2 " 360.00 Item M-10b

TOTAL G - 4.3.4
TOTAL G

Cap. 1.350 kg (20 prsn) speed 105 mpm, OP 15.9 kw, CO 4.00 0 0
Holstway 2.65 x 2.2 m, Pit 2.1 m, AC-VVVF - 0 0
2.00 0 0
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL H - 1

4 MVA 3 phase
Connection Charges 4,000.00 Kva Lump Sum
Deposit Charges 8,000.00 Kva Lump Sum
Certificate of Eligibility to operate and Administration charges 8,000.00 Kva Lump Sum
20 KV-400 V/231 V-Oil Immersed c/w Standart Protection 1.00 Ls
Cubicle TM Oil Control, Grounding, Support Material
(Factory Certified and Guarantee)
20 KV c/w Equipment, setting and Leveling 1.00 Unit
Incoming & Outgoing (LBS) 1 unit Cubicle c/w:
Switch Cubicle 20kV, Busbar and Heater
Operating Mechanism CIT (Manual)
Natural Interlock Earth-OFF-ON
Earthing Switch with SF6 gas Technology
Voltage Indicators and Transformer
Cap. 600 KVA Open Type, atenuator, battery, Silencer 2.00 Unit
standar accesories, test report, Certified & Guarantee
Insulation Work Genset House & Grounding System
Exhaust Fan Installation cap. 1.500 Cfm
Fuel System w/ Fuel Tank 2.000 lt + Fuel Pump
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Free Standing type 3 cell c/w Equipment and Installation 1.00 Unit
Panel Box dim. 240 x 200 x 80 cm (2mm thick)
MCCB 500-1250A/70kA/4P Motorized
MCCB 500-1250A/50kA/4P Motorized
MCCB 300A/36kA/3P
MCCB 160A/36kA/3P
MCCB 100A/36kA/3P
MCCB 75A/30kA/3P
MCCB 60A/30kA/3P
MCCB 40A/30kA/3P
Fuse 4A/3P
Indicator Lamp
Voltmeter
Amperemeter+CT
KWH meter
Frekwnsi Meter (Hz Meter)
Cos phi meter
Switch selector
Cu Busbar
ATS/AMF Module
Grounding Installation 2 x BC 50 mm + Local Material
Supporting Equipment + Local Material
Lightning Surge Arrester 400V Type 1 3P+N
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

MCB 10A/10kA/4P
300 Kfar Free Standing type c/w Box 180x70x80 cm 1 cell 2.00 Unit
MCCB 250-630A/50kA/3P
Push Button Switch, Fuse, Indicator lamp
MCB 50A/1P, Regulator 12 step, Cos phi meter
Magnetic contactor, Capasitor 25 Kfar, Relay MK 2P
Relay MK 3P, Exhaust Fan, Supporting Material

TOTAL H - 2

Box panel wall mounted (dim. 50x70x25cm) 1.00 Unit


- MCCB 125 A/18kA/3P
- MCCB 60A/18kA/3P
- MCB 16A/6kA/3P
- MCB 16A/6kA/1P
- Fuse 2 A, Indicator Lamp, Voltmeter, Amperemeter + CT
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
Box panel wall mounted (dim. 50x70x25cm) 1.00 Unit
- MCCB 250A/36kA/3P
- MCCB 200A/18kA/3P
- MCB 40A/10kA/3P
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

- MCB 16A/6kA/1P
- Fuse 2 A, Indicator Lamp, Voltmeter, Amperemeter + CT
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
Box panel wall mounted (dim. 40x50x25cm) 1.00 Unit
- MCCB 30A/18kA/3P
- MCB 16A/6kA/1P
- Fuse 2 A, Indicator Lamp On Off
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
Box panel wall mounted (dim. 40x50x25cm) 1.00 Unit
- MCCB 30A/18kA/3P
- MCB 16A/6kA/1P
- Direct online motor starter, Exhaust Fan On Off
- Fuse 2 A, Fan Indicator Lamp Switch Start, Stop, Fault
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material

TOTAL H - 3.1

Box panel wall mounted (dim. 40x50x25cm) 2.00 Unit


- MCCB 30A/18kA/3P
- MCB 16A/6kA/1P
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

- Magnetic Contactor 30 A/3P, Photocell


- Fuse 2 A, Indicator Lamp On Off
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
Box panel wall mounted (dim. 40x60x25cm) 2.00 Unit
- MCCB 30A/18kA/3P
- MCB 16A/6kA/1P
- Fuse 2 A, Indicator Lamp, Voltmeter, Amperemeter
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
Box panel wall mounted (dim. 40x60x25cm) 36.00 Unit
- MCCB 125A/18kA/3P
- MCB 40A/6kA/3P
- MCB 25A/6kA/3P
- MCCB 30A/18kA/3P
- MCB 16A/6kA/1P
- Direct online motor starter, AC On Off
- Fuse 2 A, Fan Indicator Lamp Switch Start, Stop, Fault
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
MCB Box Panel 2.00 Unit
- MCB 16A/6kA/1P
- MCB 10A/6kA/1P
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

- Magnetic Contactor 16A/1P, CU Busbar, Support Material

TOTAL H - 3.2

Box panel wall mounted (dim. 40x60x25cm) 36.00 Unit


- MCCB 20A/18kA/3P
- MCB 16A/6kA/1P
- Fuse 2 A, Indicator Lamp, Voltmeter, Amperemeter
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Installation Material & Equipment
Electric Submeter Box c/w Supporting Material 1,520.00 Unit
- MCB 16A/6kA/1P
- MCB 10A/6kA/1P
- Fuse 2 A, Indicator Lamp On Off
- Magnetic Contactor 16A/1P, CU Busbar, Grounding Installation
- Supporting Installation Material & Equipment
Box panel wall mounted (dim. 40x60x25cm) 36.00 Unit
- MCCB 125A/18kA/3P
- MCB 40A/6kA/3P
- MCB 25A/6kA/3P
- MCCB 30A/18kA/3P
- MCB 16A/6kA/1P
- Direct online (DOL) motor starter, AC On Off
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

- Fuse 2 A, Fan Indicator Lamp Switch Start, Stop, Fault


- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
MCB Box Panel 36.00 Unit
- MCB 16A/6kA/1P
- MCB 10A/6kA/1P
- Magnetic Contactor 16A/1P, CU Busbar, Support Material

TOTAL H - 3.3

Box panel wall mounted (dim. 30x40x25cm) 2.00 Unit


- MCCB 20A/18kA/3P
- MCB 16A/6kA/1P
- Fuse 2 A, Indicator Lamp, CU Busbar, Grounding Inst.
- Supporting Material
Box panel wall mounted (dim. 40x60x25cm) 2.00 Unit
- MCCB 125 A/18kA/3P
- MCCB 80A/18kA/3P
- MCCB 40A/18kA/3P
- MCB 20A/6kA/3P
- MCB 16A/6kA/1P
- Fuse 2 A, Indicator Lamp
- Selector Switch, CU Busbar, Grounding Installation
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

- Supporting Material
Box panel wall mounted (dim. 50x70x25cm) 1.00 Unit
- MCCB 125A/18kA/3P
- MCB 40A/6kA/3P
- MCB 25A/6kA/3P
- MCCB 30A/18kA/3P
- MCB 16A/6kA/1P
- Direct online motor starter, AC On Off
- Fuse 2 A, Fan Indicator Lamp Switch Start, Stop, Fault
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
Box panel wall mounted (dim. 40x50x25cm) 1.00 Unit
- MCCB 75A/18kA/3P
- MCB 50A/6kA/3P
- MCB 16A/6kA/1P
- Direct online motor starter, AC On Off
- Fuse 2 A, Fan Indicator Lamp Switch Start, Stop, Fault
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material
Box panel wall mounted (dim. 40x60x25cm) 2.00 Unit
- MCCB 75 A/18kA/3P
- MCCB 50A/18kA/3P
- MCCB 40A/18kA/3P
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

- MCB 16A/6kA/1P
- Fuse 2 A, Indicator Lamp
- Selector Switch, CU Busbar, Grounding Installation
- Supporting Material

TOTAL H - 3.4

Cable NA2XSEYFGBY 3x70 mm² 117.00 M


Cable N2XSY 3x1x70 mm² 37.50 M
Cable 3x NYY 4x1x185 mm² 128.00 M
Cable 3x NYY 4x1x185 mm² 63.00 M
Cable FRC 4x120 mm² 59.00 M
Cable NYY 4x50 mm² 63.00 M
Cable NYY 4x16 mm² 74.00 M
Cable NYY 4x16 mm² 95.00 M
Cable NYY 4x10 mm² 161.00 M
Cable NYY 4x16 mm² 183.00 M
Cable NYY 4x10 mm² 128.00 M
Cable NYY 4x10 mm² 172.00 M
Cable NYY 4x10 mm² 172.00 M
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Cable BC 50 mm² 104.50 M


Cable BCC 50 mm² 38.00 M
Cable BCC 50 mm² 58.50 M
Cable BCC 50 mm² 48.00 M
Cable BCC 35 mm² 45.00 M
Cable BCC 35 mm² 54.00 M
Cable BCC 10 mm² 25.00 M
Cable BCC 10 mm² 35.00 M
Cable BCC 10 mm² 72.00 M
Cable BCC 16 mm² 112.00 M
Cable BCC 16 mm² 112.00 M
Cable BCC 16 mm² 112.00 M

TOTAL H - 4.1

Cable NYY 4x10mm² 89.00 M


Cable NYY 4x50mm² 89.00 M
Cable NYM 3x2,5mm² 782.60 M
Cable NYY 3x4mm² 276.00 M

Cable BCC 16mm² 95.00 M


Cable BCC 35mm² 95.00 M
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL H - 4.2

Cable NA2XSEYFGBY 3x70 mm² 420.00 M


Cable NYY 4x10 mm² 1,960.00 M
Cable NYY 4x25 mm² 835.00 M
Cable NYM 3x2,5mm² 4,872.30 M

Cable BCC 16mm² 772.80 M


Cable BCC 16mm² 1,379.40 M
Cable BCC 16mm² 742.50 M

TOTAL H - 4.3

Cable NYY 4x10mm² 238.00 M


Cable NYY 4x50mm² 275.00 M
Cable NYY 4x10mm² 138.00 M
Cable FRC 4x35mm² 220.00 M
Cable NYY 4x16mm² 256.00 M
Cable NYY 4x16mm² 358.00 M
Cable NYY 4x16mm² 423.00 M
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Cable FRC 4x25mm² 68.00 M

Cable BCC 16mm² 238.00 M


Cable BCC 35mm² 245.00 M
Cable BCC 16mm² 236.00 M
Cable BCC 25mm² 278.00 M
Cable BCC 16mm² 256.00 M
Cable BCC 16mm² 358.00 M
Cable BCC 16mm² 423.00 M
Cable BCC 16mm² 185.00 M

TOTAL H - 4.4
STU Type c/w Hanging & Material Supporting

Dim. wide 600 mm x 50 mm 125.00 M


Dim. wide 400 mm x 50 mm 185.00 M
Dim. wide 300 mm x 50 mm 140.00 M
Dim. 600 mm 85.00 Item
Dim. 600-400 mm 63.00 Item
Dim. 400-300 mm 74.00 Item
Dim. 600 mm 40.00 Item
Dim. 400 mm 72.00 Item
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Dim. 600 mm 46.00 Item


Dim. 400 mm 85.00 Item

Dim. wide 400 mm x 50 mm 142.00 M


Dim. wide 300 mm x 50 mm 225.00 M
Dim. 400 mm 360.00 Item
Dim. 400-300 mm 65.00 Item
Dim. 400 mm 58.00 Item
Dim. 400 mm 49.00 Item
1.00 Ls
1.00 Ls

TOTAL H - 5.1

Dim. wide 600 mm x 50 mm 125.00 M


Dim. wide 400 mm x 50 mm 185.00 M
Dim. wide 300 mm x 50 mm 140.00 M
Dim. 600 mm 85.00 Item
Dim. 400-300 mm 63.00 Item
Dim. 400 mm 74.00 Item

Dim. wide 400 mm x 50 mm 142.00 M


CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Dim. wide 300 mm x 50 mm 225.00 M


Dim. 400 mm 360.00 Item
Dim. 400-300 mm 65.00 Item
Dim. 400 mm 58.00 Item
1.00 Ls
1.00 Ls

TOTAL H - 5.2

Dim. wide 600 mm x 50 mm 2,250.00 M


Dim. wide 400 mm x 50 mm 3,330.00 M
Dim. wide 300 mm x 50 mm 2,520.00 M
Dim. 600 mm 1,530.00 Item
Dim. 400-300 mm 1,134.00 Item
Dim. 400 mm 1,332.00 Item

Dim. wide 400 mm x 50 mm 2,556.00 M


Dim. wide 300 mm x 50 mm 4,050.00 M
Dim. 400 mm 6,480.00 Item
Dim. 400-300 mm 1,170.00 Item
Dim. 400 mm 1,044.00 Item
1.00 Ls
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

1.00 Ls

TOTAL H - 5.3

Dim. wide 600 mm x 50 mm 125.00 M


Dim. wide 400 mm x 50 mm 185.00 M
Dim. wide 300 mm x 50 mm 140.00 M
Dim. 600 mm 85.00 Item
Dim. 400-300 mm 63.00 Item
Dim. 400 mm 74.00 Item

Dim. wide 400 mm x 50 mm 142.00 M


Dim. wide 300 mm x 50 mm 225.00 M
Dim. 400 mm 360.00 Item
Dim. 400-300 mm 65.00 Item
Dim. 400 mm 58.00 Item
1.00 Ls
1.00 Ls

TOTAL H - 5.4
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm 1,120.00 M


Phillips Lamp Series+ Installation 72.00 Nr
Phillips Lamp Series+ Installation 108.00 Nr
Phillips Lamp Series+ Installation 24.00 Nr
Phillips Lamp Series+ Installation 24.00 Nr
Phillips Lamp Series+ Installation 24.00 Nr
Phillips Lamp Series+ Installation 24.00 Nr
Phillips Lamp Series+ Installation 24.00 Nr
Phillips Lamp Series+ Installation 36.00 Nr
Phillips Lamp Series+ Installation 24.00 Nr
Phillips Lamp Series+ Installation 36.00 Nr
Scneider Electric Classic 12.00 Nr
Scneider Electric Classic 24.00 Nr
Scneider Electric Classic 12.00 Nr
Scneider Electric Classic 8.00 Nr
Cable NYA 2x1,5mm² + High Impact Conduit Ø 20 mm 87.00 M
Scneider Electric Classic 8.00 Nr

TOTAL H - 6.1

Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm 1,344.00 M


Phillips Lamp Series+ Installation 72.00 Nr
Phillips Lamp Series+ Installation 108.00 Nr
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Phillips Lamp Series+ Installation 24.00 Nr


Phillips Lamp Series+ Installation 216.00 Nr
Phillips Lamp Series+ Installation 162.00 Nr
Phillips Lamp Series+ Installation 216.00 Nr
Phillips Lamp Series+ Installation 162.00 Nr
Phillips Lamp Series+ Installation 16.00 Nr
Phillips Lamp Series+ Installation 72.00 Nr
Phillips Lamp Series+ Installation 36.00 Nr
Phillips Lamp Series+ Installation 24.00 Nr
Phillips Lamp Series+ Installation 24.00 Nr
Phillips Lamp Series+ Installation 20.00 Nr
Phillips Lamp Series+ Installation 24.00 Nr
Scneider Electric Classic 189.00 Nr
Scneider Electric Classic 582.00 Nr
Scneider Electric Classic 56.00 Nr
Scneider Electric Classic 42.00 Nr
Scneider Electric Classic 16.00 Nr
Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm 1,344.00 Nr
Scneider Electric Classic 180.00 Nr
Scneider Electric Classic 8.00 Nr
Cable NYY 3x4mm² + Support Material 360.00 M
Phillips Lamp Series+ Installation 48.00 Nr
Phillips Lamp Series+ Installation 36.00 Nr
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Xeon Flat LED 5W 42.00 Nr


Xeon Strip3 LED 5W 16.00 Nr

Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm 280.00 M


Phillips Lamp Series+ Installation 24.00 Nr
Scneider Electric Classic 24.00 Nr

Cable NYA 2x1,5mm² + High Impact Conduit Ø 20 mm 72.00 M


Scneider Electric Classic 24.00 Nr

TOTAL H - 6.2

Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm 4,838.40 M


Phillips Lamp Series+ Installation 216.00 Nr
Phillips Lamp Series+ Installation 432.00 Nr
Phillips Lamp Series+ Installation 432.00 Nr
Phillips Lamp Series+ Installation 216.00 Nr
Phillips Lamp Series+ Installation 180.00 Nr
Phillips Lamp Series+ Installation 90.00 Nr
Phillips Lamp Series+ Installation 144.00 Nr
Phillips Lamp Series+ Installation 288.00 Nr
Phillips Lamp Series+ Installation 108.00 Nr
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Scneider Electric Classic 432.00 Nr


Scneider Electric Classic 351.00 Nr
Scneider Electric Classic 72.00 Nr
Scneider Electric Classic 54.00 Nr
Scneider Electric Classic 144.00 Nr

Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm 19,353.60 M


Phillips Lamp Series+ Installation 1,296.00 Nr
Phillips Lamp Series+ Installation 1,152.00 Nr
Phillips Lamp Series+ Installation 1,728.00 Nr
Scneider Electric Classic 1,224.00 Nr
Scneider Electric Classic 1,728.00 Nr
Scneider Electric Classic 8,640.00 Nr

TOTAL H - 6.3

Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm 360.00 M


Phillips Lamp Series+ Installation 12.00 Nr
Phillips Lamp Series+ Installation 12.00 Nr
Phillips Lamp Series+ Installation 12.00 Nr
Phillips Lamp Series+ Installation 8.00 Nr
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Phillips Lamp Series+ Installation 8.00 Nr


Phillips Lamp Series+ Installation 6.00 Nr
Scneider Electric Classic 24.00 Nr
Scneider Electric Classic 36.00 Nr
Scneider Electric Classic 3.00 Nr
Scneider Electric Classic 3.00 Nr

Scneider Electric Classic 8.00 Nr


Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm 350.00 M

Cable NYM 3x2,5mm² + High Impact Conduit Ø 20 mm 360.00 M


Phillips Lamp Series+ Installation 8.00 Nr
Scneider Electric Classic 4.00 Nr
Cable NYA 2x1,5mm² + High Impact Conduit Ø 20 mm 45.00 M
Scneider Electric Classic 4.00 Nr

TOTAL H - 6.4
TOTAL H
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Fitting, Supporting, Digging, Material Supporting


Ø 150 mm or 6 " 592.80 m'
Ø 100 mm or 4 " 122.40 m'
Ø 80 mm or 3 " 511.20 m'
Ø 65 mm or 2.5 " 259.20 m'
Ø 50 mm or 2 " 216.00 m'
Ø 40 mm or 1 1/2 " 108.00 m'
Ø 25 mm or 1 " 792.00 m'
Ø 20 mm or 3/4 " 1,097.60 m'
Up Right Type 294.00 pcs
c/w Material Support : 4.00 set
Control Valve 4" w/ indicating 4.00 pc
Temper Switch 4.00 pc
Flows Switch 4.00 pc
Pressure Gauge 4.00 pc
Inspector Valve 32 mm 8.00 pcs
Side Glass 32 mm 4.00 pc
Gate Valve 25 mm 4.00 pc
c/w Material Support : 8.00 unit
B Type Box 16.00 Item
Fire Hose 1,5 '' 30 meter c/w coupling machine 400.00 m'
Hose Rack 0,0 16.00 Item
Straight nozzle 0,0 16.00 Item
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Hydrant Valve 1,5'' & 2,5 ' 16.00 Item


Cap. 3 Kg class ABC Dry chemical powder type 18.00 unit
Ø 50 mm or 2 " 8.00 pcs

TOTAL I - 1.1.1

Header 12" 8.00 set


Header 6" 8.00 set
Ø 150 mm or 6 " 48.00 pcs
Ø 150 mm or 6 " 32.00 pcs
Ø 150 mm or 6 " 16.00 pcs
Ø 100 mm or 4 " 8.00 pcs
Ø 40 mm or 1 1/2 " 24.00 pcs
Ø 15 mm or 1 " 80.00 pcs
Strainer 6" 16.00 pcs
Strainer 1 1/2" 8.00 pcs
Flexible Joint 6" 32.00 pcs
Flexible Joint 2" 16.00 pcs
Check Valve 6" 16.00 pcs
Check Valve 1 1/2" 8.00 pcs
Check Valve 1/2" 40.00 pcs
Gate Valve 1 1/4" 8.00 pcs
24.00 unit
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

32.00 unit
Flow meter 6" 8.00 unit
8.00 unit
Cap. 750 USGPM, 95 meter, 75 kw c/w levelling 2.00 set
Control panel & Wiring, Exhaust manifolt & Support material
Cap. 750 USGPM 95 kW 3 Phase, 95 meter c/w 2.00 set
Control Panel, Wiring and accesories
Cap. 20 GPM 11 kW 3 phase, 95 meter c/w 2.00 set
Control Panel, Wiring and accesories
Ø 4'' c/w sprinkler alarm, valve, water pump motor & 1.00 set
alarm Sirine, pressure gauge
Reducing Valve dia 4'' 8.00 set
Cap. 25 Kg class ABC Dry chemical powder type 18.00 unit

TOTAL I - 1.1.2

Fitting, Supporting, Digging, Material Supporting


Ø 150 mm or 6 " 200.00 m'
Ø 100 mm or 4 " 176.00 m'
Ø 80 mm or 3 " 540.00 m'
Ø 65 mm or 2.5 " 312.00 m'
Ø 50 mm or 2 " 64.00 m'
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Ø 40 mm or 1 1/2 " 80.00 m'


Ø 25 mm or 1 " 232.00 m'
Ø 20 mm or 3/4 " 720.00 m'
Pendant Type 360.00 pcs
c/w Material Support : 4.00 set
Control Valve 4" w/ indicating 4.00 pc
Temper Switch 4.00 pc
Flows Switch 4.00 pc
Pressure Gauge 4.00 pc
Inspector Valve 32 mm 8.00 pcs
Side Glass 32 mm 4.00 pc
Gate Valve 25 mm 4.00 pc
c/w Material Support : 8.00 unit
B Type Box 16.00 unit
Fire Hose 1,5 '' 30 meter c/w coupling machine 400.00 m'
Hose Rack 0,0 16.00 unit
Straight nozzle 0,0 16.00 Item
Hydrant Valve 1,5'' & 2,5 ' 16.00 Item
Cap. 3 Kg class ABC Dry chemical powder type 40.00 unit
Hose Rack, Fire Hose 2,5'' 30 m, landing valve 4.00 unit
Bok tipe C 4.00 Item
Fire Hose 2,5 '' 30 meter c/w coupling machino 200.00 m'
Straight nozzle - Item
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

4.00 unit
4.00 unit
Ø 100 mm or 4 " 4.00 unit
Ø 100 mm or 4 " 4.00 unit
Ø 50 mm or 2 " 4.00 pcs

TOTAL I - 1.2.1

Fitting, Supporting, Digging, Material Supporting


Ø 150 mm or 6 " 720.00 m'
Ø 100 mm or 4 " 1,080.00 m'
Ø 80 mm or 3 " 3,024.00 m'
Ø 65 mm or 2.5 " 3,744.00 m'
Ø 50 mm or 2 " 3,384.00 m'
Ø 40 mm or 1 1/2 " 720.00 m'
Ø 25 mm or 1 " 1,296.00 m'
Ø 20 mm or 3/4 " 10,080.00 m'
Side Wall Type 720.00 pcs
Pendant Type 1,800.00 pcs
c/w Material Support : 72.00 set
Control Valve 4" w/ indicating 1.00 pc
Temper Switch 1.00 pc
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Flows Switch 1.00 pc


Pressure Gauge 1.00 pc
Inspector Valve 32 mm 2.00 pcs
Side Glass 32 mm 1.00 pc
Gate Valve 25 mm 1.00 pc
c/w Material Support : 72.00 unit
B Type Box - Item
Fire Hose 1,5 '' 30 meter c/w coupling machine 30.00 m'
Hose Rack 0,0 - Item
Straight nozzle 0,0 - Item
Hydrant Valve 1,5'' & 2,5 ' - Item
Cap. 3 Kg class ABC Dry chemical powder type 432.00 unit
Ø 50 mm or 2 " 144.00 pcs
Reducing Valve dia 4'' 144.00 set

TOTAL I - 1.2.2

Fitting, Supporting, Digging, Material Supporting


Ø 100 mm or 4 " 80.00 m'
Ø 80 mm or 3 " 184.00 m'
Ø 65 mm or 2.5 " 152.00 m'
Ø 50 mm or 2 " 152.00 m'
Ø 25 mm or 1 " 80.00 m'
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Ø 20 mm or 3/4 " 504.00 m'


Pendant Type 112.00 pcs
c/w Material Support : 8.00 set
Control Valve 4" w/ indicating 1.00 pc
Temper Switch 1.00 pc
Flows Switch 1.00 pc
Pressure Gauge 1.00 pc
Inspector Valve 32 mm 2.00 pcs
Side Glass 32 mm 1.00 pc
Gate Valve 25 mm 1.00 pc
c/w Material Support : 8.00 unit
B Type Box - Item
Fire Hose 1,5 '' 30 meter c/w coupling machine 30.00 m'
Hose Rack 0,0 - Item
Straight nozzle 0,0 - Item
Hydrant Valve 1,5'' & 2,5 ' - Item
Cap. 3 Kg class ABC Dry chemical powder type 24.00 unit
Ø 50 mm or 2 " 8.00 pcs
on specification 8.00 Ls
c/w valve & accessories 8.00 unit

TOTAL I - 1.2.3
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL I

c/w wiring, detector, Alarm Panel, accessories

by detail drawing specification 39.00 Nr


15V-30 VDC, 75 mA c/w Led Red lamp, temp change sensore 21.00 pcs
Dual Thermistor ROR, UL/ULC 21m, Amb 6⁰F/mnt, 135 to 200⁰F - 0
15V-30 VDC, 75 mA c/w Led Red lamp, temp change sensore 4.00 pcs
15V-30 VDC, 75 mA c/w Led Red lamp, temp change sensore 14.00 pcs
4.00 pcs
3.00 Nr
3.00 pcs

TOTAL J - 1.1.1

3.00 Nr
3.00 Nr
1.00 Nr
3.00 pcs
3.00 pcs
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

1.00 pcs
1.00 Nr
1.00 Nr

TOTAL J - 1.1.2

c/w Installation Equipment & Accessories 1.00 unit


Zone Address Module
Individual Address Module
Signal Zone Address Module
Control Zone Address Module
2 Pair AWG18 (Fire Rated Cable) - Twisted Shielded 15.00 m'
Cable FRC 3x2,5 mm² 30.00 m'
Cable FRC 3x2,5 mm² 15.00 m'
Cable NYA 16 mm² 30.00 m'
Cable NYA 16 mm² 15.00 m'
c/w Installation Equipment & Accessories 1.00 unit
2.00 unit
1.00 unit
1.00 unit
Cable FRC 2x1,5 mm² 230.00 m'
Cable FRC 2x1,5 mm² 55.00 m'
Cable FRC 2x1,5 mm² 55.00 m'
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Cable FRC 2x1,5 mm² 35.00 m'


Cable FRC 2x1,5 mm² 77.00 m'
Cable FRC 2x1,5 mm² 70.00 m'
Cable FRC 2x1,5 mm² 65.00 m'
2 Pair AWG18 (Fire Rated Cable) - Twisted Shielded 35.00 m'
2 Pair AWG18 (Fire Rated Cable) - Twisted Shielded 35.00 m'
Cable FRC 3x2,5 mm² 35.00 m'
Cable NYA 16 mm² 30.00 m'
1.00 Ls

TOTAL J - 1.1.3

31.00 Nr
11.00 pcs
2.00 pcs
18.00 pcs
3.00 pcs
2.00 pcs
2.00 pcs

2.00 Nr
2.00 Nr
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

1.00 Nr
2.00 pcs
2.00 pcs
1.00 pcs
1.00 Nr
1.00 Nr

TOTAL J - 2.2.1.1

c/w Installation Equipment & Accessories 1.00 unit


Zone Address Module
Individual Address Module
Signal Zone Address Module
Control Zone Address Module
2 Pair AWG18 (Fire Rated Cable) - Twisted Shielded 15.00 m'
Cable FRC 3x2,5 mm² 15.00 m'
Cable NYA 16 mm² 15.00 m'

TOTAL J - 2.2.2

450.00 Nr
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

198.00 pcs
54.00 pcs
198.00 pcs
180.00 Nr
180.00 pcs
54.00 pcs
36.00 Nr
36.00 pcs

TOTAL J - 3.1

36.00 Nr
36.00 Nr
18.00 Nr
36.00 pcs
36.00 pcs
18.00 pcs
18.00 Nr
18.00 Nr

TOTAL J - 3.2

c/w Installation Equipment & Accessories 18.00 unit


CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

Zone Address Module


Individual Address Module
Signal Zone Address Module
Control Zone Address Module
2 Pair AWG18 (Fire Rated Cable) - Twisted Shielded 270.00 m'
Cable FRC 3x2,5 mm² 270.00 m'
Cable NYA 16 mm² 270.00 m'

TOTAL J - 3.3

10.00 Nr
1.00 pcs
6.00 pcs
3.00 pcs
2.00 pcs
1.00 Nr
1.00 pcs

TOTAL J - 4.1

1.00 Nr
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

1.00 Nr
1.00 Nr
1.00 pcs
1.00 pcs
1.00 pcs
1.00 Nr
1.00 Nr

TOTAL J - 4.2

c/w Installation Equipment & Accessories 1.00 unit


Zone Address Module
Individual Address Module
Signal Zone Address Module
Control Zone Address Module
2 Pair AWG18 (Fire Rated Cable) - Twisted Shielded 90.00 m'
Cable FRC 3x2,5 mm² 90.00 m'
Cable NYA 16 mm² 90.00 m'

TOTAL J - 4.3
TOTAL J
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

c/w wiring, Camera, Cable Power, Bracket & accessories

3.00 Nr
1.00 pcs
2.00 pcs

TOTAL K - 1.1.1

2.00 unit
2.00 unit
1.00 unit
1.00 unit
1.00 Ls
1.00 Ls

TOTAL K - 1.1.2

4.00 Nr
3.00 pcs
1.00 pcs
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL K - 2

72.00 Nr
54.00 pcs
18.00 pcs

TOTAL K - 3

2.00 Nr
2.00 pcs

TOTAL K - 4
TOTAL K

c/w wiring, Outlet MATV & accessories, material planting

4.00 unit
2.00 unit
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

4.00 unit
2.00 unit
2.00 unit
2.00 unit
2.00 unit
4.00 unit
2.00 unit
4.00 unit
2.00 unit
2.00 unit
66.00 unit
1.00 Ls
1.00 Ls

TOTAL L - 1

Coaxial Cable RG 6 in Conduit Ø 20 mm 8.00 Nr


8.00 pcs

TOTAL L - 2

Coaxial Cable RG 6 in Conduit Ø 20 mm 2.00 Nr


CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

2.00 pcs
Coaxial Cable RG 11 in Conduit Ø 20 mm 2.00 Nr
2.00 pcs

TOTAL L - 3

Coaxial Cable RG 6 in Conduit Ø 20 mm 1,440.00 Nr


1,440.00 pcs
Coaxial Cable RG 11 in Conduit Ø 20 mm 480.00 Nr
480.00 pcs
Coaxial Cable RG 11 in Conduit Ø 20 mm 72.00 Nr
72.00 pcs

TOTAL L - 4

Coaxial Cable RG 6 in Conduit Ø 20 mm 4.00 Nr


4.00 pcs
Coaxial Cable RG 11 in Conduit Ø 20 mm 2.00 Nr
2.00 pcs
Coaxial Cable RG 11 in Conduit Ø 20 mm 2.00 Nr
2.00 pcs
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL L - 5
TOTAL L

c/w Wiring, Speaker, Power Panel, Planting Ins Work

10 zone 1.00 item


10 " 1.00 unit
120 W 1.00 item
60 W 1.00 item
1.00 item
1.00 unit
- Mixer 2.00 item
- Equalizer 1.00 item
- Paging Microphone 1.00 item
1.00 item
1.00 item
1.00 item
1.00 unit

TOTAL M - 1.1
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

4 zone 1.00 item


10 " 1.00 unit
120 W 1.00 item
30 W 1.00 item
1.00 item
1.00 item
1.00 item
1.00 unit

TOTAL M - 1.2

1.00 item
1.00 item
1.00 item
1.00 item
1.00 item
1.00 item
1.00 item
Cable NYA 10 mm in High Impact Conduit Ø 20 mm 50.00 m'

TOTAL M - 1.3
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

4.00 unit
4.00 unit

TOTAL M - 1.4

17.00 Nr
10.00 Item
7.00 Item
5.00 Item

TOTAL M - 2.1

6.00 Nr
6.00 Item

TOTAL M - 2.2

1.00 unit
45.00 m'
45.00 m'
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL M - 2.3

17.00 Nr
10.00 Item
7.00 Item
5.00 Item

TOTAL M - 3.1

6.00 Nr
6.00 Item

TOTAL M - 3.2

306.00 Nr
252.00 Item
54.00 Item
72.00 Item

TOTAL M - 4.1
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

90.00 Nr
90.00 Item

TOTAL M - 4.2

18.00 unit
810.00 m'
810.00 m'

TOTAL M - 4.3

11.00 Nr
7.00 Item
4.00 Item
1.00 Item

TOTAL - M.5.1

2.00 Nr
2.00 Item

TOTAL - M.5.2
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

1.00 unit
170.00 m'
170.00 m'

TOTAL - M.5.3
TOTAL M

c/w Wiring, Telephone Outlet, Panel, Planting Ins Work

- Main Unit PABX, 32 co line 192 extention c/w 7.00 Set


- Power supply, Memory card, Extension card, analog card
- Installing and Programming
- Battery back Up 1 hour c/w Battery
- Stabilizer
- Surge Arrester
- Testing & Licensing
7.00 Set
50.00 m'
1.00 Set
1.00 item
1.00 unit
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

2.00 unit
1.00 unit
1.00 Ls

TOTAL N - 1

17.00 Nr
17.00 Item
17.00 Item

TOTAL - N.2.1

1.00 0
30.00 0

TOTAL - N.2.2

64.00 Nr
64.00 Item
64.00 Item
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL - N.3.1

1.00 Unit
60.00 m'

TOTAL - N.3.2

- 0
1,460.00 Nr
1,460.00 Item
1,460.00 Item

TOTAL - N.4.1

72.00 0
2,160.00 0

TOTAL - N.4.2

2.00 Nr
2.00 Item
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

2.00 Item

TOTAL N - 5
TOTAL N

c/w Wiring, Outlet Computer, Hub Switch, Planting Work

CPU : Power supply, processor Intel Core I7 1.00 Set


Ram 4 Gb, VGA 2 Gb, DVD
Monitor : wide LCD 22 Inch, HDMI
OS windows 8 & server programming
Asseories Komputer : mouse, keyboard, desktop speaker
UPS 1000 VA + printer A3
c/w Installation 1.00 Unit
1.00 Ls
1.00 Unit

TOTAL O - 1

Unshielded Twisted Pair Cattegory 6 (UTP Cat 6)


c/w Connector, Accessories & Testing 5.00 Nr
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

5.00 Item
1.00 Item
1.00 Nr
1.00 Nr

TOTAL O - 2

Unshielded Twisted Pair Cattegory 6 (UTP Cat 6)


c/w Connector, Accessories & Testing 3.00 Nr
3.00 Item
Cap. 8 ports 1.00 Item
1.00 Nr
1.00 Nr

TOTAL O - 3.1

12.00 Nr
4.00 Item
4.00 Item
4.00 Item
1.00 Unit
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL O - 3.2

Unshielded Twisted Pair Cattegory 6 (UTP Cat 6)


c/w Connector, Accessories & Testing 18.00 Nr
18.00 Item
Cap. 8 ports 18.00 Item
18.00 Nr
18.00 Nr

TOTAL O - 4.1

216.00 Nr
72.00 Item
72.00 Item
72.00 Item
18.00 Unit

TOTAL O - 4.2

Unshielded Twisted Pair Cattegory 6 (UTP Cat 6)


c/w Connector, Accessories & Testing 1.00 Nr
1.00 Item
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL O - 5.1

2.00 Nr
2.00 Item
2.00 Item
2.00 Item
1.00 Unit

TOTAL O - 5.2
TOTAL O

c/w Down Conductor, Distrivution Head + Accessories


Grounding, Supporting Material and Planting Work
8.00 Unit
Cable NYY 70 mm² 750.00 m'
2.00 Ls
Lightning Needle Conductor 2.00 Unit
2.00 Ls
Lump Sum 1.00 Ls
CONSTRUCTION COST ESTIMATION

ESTIMATE COST
MATERIAL SPECIFICATION UNIT UNIT PRICE
QUANTITY ANALYSIS

TOTAL P

TOTAL A s/d P
JUMLAH TOTAL
DIBULATKAN

Buaran, April, 23th, 2019


TOTAL PRICE

-
-
-

-
-
-
-

-
-
-
-
TOTAL PRICE

-
-

-
-
-
-
-
-
-
-

-
-
-
-
TOTAL PRICE

-
-
-
-
-
-

-
Rp -

-
-
-
-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-

-
-
-
TOTAL PRICE

-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-

-
-
-
-
-
-
-
-
-
-
-
-
-

-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-

-
-

-
-
TOTAL PRICE

-
-
-
-
-

-
-
-
-
-

-
-
-
TOTAL PRICE

-
-
-
-

-
-
-

-
-

-
TOTAL PRICE

-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-

-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-
-

-
-
-
-

-
-

-
-
-
-

-
TOTAL PRICE

-
-
-
-

-
-
-

-
-

-
-
-

-
TOTAL PRICE

-
-
-
-
-
-
-
-
-

-
-
-

-
-

-
TOTAL PRICE

-
-
-

-
-

-
-
-
-
-

-
-
-
-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-
-

-
-
-
TOTAL PRICE

-
-
-
-

-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-

-
-
-
-
-
-
-
-

-
-
-
-
-
-
TOTAL PRICE

-
-
-

-
-
-
-
-
-
-

-
TOTAL PRICE

-
-
-
-
-
-

-
-
-
-
-
-
-
-

-
TOTAL PRICE

-
-
-
-

-
-
-
-

-
-
-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-
-
-

-
-
TOTAL PRICE

-
-
-
-

-
TOTAL PRICE

-
TOTAL PRICE

-
TOTAL PRICE

-
TOTAL PRICE

-
TOTAL PRICE

-
TOTAL PRICE

-
TOTAL PRICE

-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-

-
-
TOTAL PRICE

-
-
-
-

-
-
-

-
-
-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
TOTAL PRICE

-
-

-
-
-
-
-
-

-
-
-
-
-
-

-
TOTAL PRICE

-
-
-
-

-
-
-
-
-
-

-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-

-
-
-
-
-

-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-

-
-
-

-
-

-
-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-
-
-
-

-
-
-
-
-
-
-

-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-
-
-
-

-
-
-
-
-

-
-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-
-
-

-
-

-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
TOTAL PRICE

-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-

-
-
-

-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-

-
-
-
-

-
TOTAL PRICE

-
-

-
-
-
-
-

-
-
-
-
-
TOTAL PRICE

-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
TOTAL PRICE

-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-

-
-
TOTAL PRICE

-
-
-
-
-
-

-
-
-

-
TOTAL PRICE

-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-

-
TOTAL PRICE

-
-
-

-
-
-
-
-
-
-

-
TOTAL PRICE

-
-
-
-
-
-
-

-
-
-

-
-
TOTAL PRICE

-
-
-

-
-
-
-
-
-

-
-
-
TOTAL PRICE

-
-
-

-
-
-

-
-

-
-
TOTAL PRICE

-
-
-
-
-
-
-
-
-
-
-
-
-

-
-

-
TOTAL PRICE

-
-
-

-
-
-
-
-
-

-
-
-
-
-
-
TOTAL PRICE

-
-

-
-
-
-
-
-
-
-
-
-
-
-
-

-
TOTAL PRICE

-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-

-
TOTAL PRICE

-
-

-
-
-
-

-
-

-
-
-
TOTAL PRICE

-
-
-
-

-
-

-
-
-
-

-
TOTAL PRICE

-
-

-
-
-

-
-
-
-

-
-

-
TOTAL PRICE

-
-
-

-
-

-
-
-
-
-
TOTAL PRICE

-
-
-

-
-
-

-
-

-
-
-
TOTAL PRICE

-
-

-
-
-
-

-
-

-
-
TOTAL PRICE

-
-

-
-
-

-
TOTAL PRICE

-
-
-
-

-
-
-
-
-

-
-
-
-
-
TOTAL PRICE

-
-
-
-
-

-
-
-
-
-

-
-
TOTAL PRICE

-
-
-
-
-

-
-

-
-
-
-
-
-
TOTAL PRICE

-
-
-

ril, 23th, 2019

Potrebbero piacerti anche