ID number Start Date Duration (days) Finish Date

Task 1 5/1/18 3 5/3/18


Task 2 5/3/18 2 5/4/18
Task 3 5/4/18 2 5/5/18
Task 4 5/5/18 2 5/7/18
Task 5 5/7/18 15 5/24/18
Task 6 5/1/18 3 5/3/18
Task 7 5/3/18 1 5/3/18
Task 8 5/4/18 1 5/4/18
Task 9 5/5/18 15 5/21/18
Task 10 5/1/18 7 5/9/18
Task 11 5/10/18 15 5/27/18
Task 12 5/27/18 7 6/3/18
Task 13 6/4/18 1 6/4/18
Task 14 6/4/18 7 6/12/18
Task 15 6/13/18 1 6/13/18
Task 16 6/14/18 1 6/14/18
Task 17 6/15/18 7 6/22/18
Task 18 6/23/18 1 6/23/18
Task 19 6/24/18 7 7/1/18
Task 20 7/2/18 10 7/12/18
Task 21 7/13/18 1 7/13/18
Task 22 7/13/18 7 7/21/18
Task 23 7/21/18 15 8/5/18
Task 24 7/30/18 7 8/8/18
Task 25 7/30/18 9 8/9/18
Task 26 7/26/18 8 8/3/18
Task 27 7/31/18 7 8/7/18

5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26


Task 1
Task 2
Task 3
Task 4
Task 5
Task 6
Task 7
Task 8
Task 9
Task 10
Task 11
Task 12
Task 13
Task 14
Task 15
Task 16
Task 17
Task 18
Task 19
Task 20
Task 21
Task 22
Task 23
Task 15
Task 16
Task 17
Task 18
Task 19
Task 20
Task 21
Task 22
Task 23
Task 24
Task 25
Task 26
Task 27
Task
Receive notice to proceed
Submit insurance and bond documents
Prepare project schedule
Obtain building perimts
Submit shop drawings
Site clearing and grading
Install underground utilities
Install temporary power service
Install exterior fire line
Establish building layouts
Excavation for footing
Preparing footing forms with steel
Reinforced concrete for footing
Curing
Strip forms
Pneumatic paint for footing
Steel works & coulmn forms for 1st floor
Reinforced concrete for 1st floor's columns
curing & Strip column forms
Steel works & forms for 1st floor beams and slabs
Reinforced concrete for 1st floor's beams and slabs
curing & Stripping beams and slabs forms
Masonary works
Plaster works
Ceramic works
Doors and windows
Internal and external painting

5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 8/7 8/14