Sei sulla pagina 1di 31

G.R. No.

187521 March 14, 2012 The terms of the Subcontract Agreement with the representative of the DPWH and
F.F. CRUZ & CO., INC., Petitioner, v. HR should prevail. the consultants. Indubitably, FFCCI, being
CONSTRUCTION CORP., Respondent In resolving the dispute as to the proper the main contractor of DPWH, has the
valuation of the works accomplished by responsibility to request the representative
ISSUES: In sum, the crucial issues for this HRCC, the primordial consideration of DPWH to conduct the said joint
Courts resolution are: first, what is the effect should be the terms of the Subcontract measurement.
of FFCCIs non-compliance with the Agreement. It is basic that if the terms of a
stipulation in the Subcontract Agreement contract are clear and leave no doubt upon The CIAC held that FFCCI, on account of its
requiring a joint quantification of the works the intention of the contracting parties, the failure to demand the joint measurement of
completed by HRCC on the payment of the literal meaning of its stipulations shall HRCCs completed works, had effectively
progress billings submitted by the latter; and control. waived its right to ask for the conduct of the
second, whether there was a valid same as a condition sine qua non to HRCCs
rescission of the Subcontract Agreement by In Abad v. Goldloop Properties, Inc.,[31] we submission of its monthly progress billings.
HRCC stressed that:
The Supreme Court agree.
RULING: The petition is not meritorious. A courts purpose in examining a contract is
to interpret the intent of the contracting In People of the Philippines v. Donato,
First Substantive Issue: Effect of Non- parties, as objectively manifested by them. this Court explained the doctrine of waiver in
compliance with the Joint Quantification The process of interpreting a contract this wise:
Requirement on the Progress Billings of requires the court to make a preliminary
HRCC inquiry as to whether the contract before it is Waiver is defined as "a voluntary and
ambiguous. A contract provision is intentional relinquishment or
Basically, the instant issue calls for a ambiguous if it is susceptible of two abandonment of a known existing legal
determination as to which of the parties reasonable alternative interpretations. right, advantage, benefit, claim or
respective valuation of accomplished works Where the written terms of the contract are privilege, which except for such waiver
should be given credence. FFCCI claims not ambiguous and can only be read one the party would have enjoyed; the
that its valuation should be upheld since the way, the court will interpret the contract as a voluntary abandonment or surrender, by a
same was the result of a measurement of matter of law. If the contract is determined capable person, of a right known by him to
the completed works conducted by it and to be ambiguous, then the interpretation of exist, with the intent that such right shall be
the DPWH. On the other hand, HRCC the contract is left to the court, to resolve the surrendered and such person forever
maintains that its valuation should be upheld ambiguity in the light of the intrinsic deprived of its benefit; or such conduct as
on account of FFCCIs failure to observe the evidence. warrants an inference of the relinquishment
joint measurement requirement in of such right; or the intentional doing of an
ascertaining the extent of its completed It bears stressing that the joint act inconsistent with claiming it."
works. measurement contemplated under the
Subcontract Agreement should be As to what rights and privileges may be
conducted by the parties herein together waived, the authority is settled:

Case Digests for Cases under Articles 1189-1198 Page | 1


x x x the doctrine of waiver extends to rights We rule in the affirmative. progress billings. Further, the CIAC stated
and privileges of any character, and, since that FFCCI could no longer assail the work
the word waiver covers every conceivable As intimated earlier, the joint measurement stoppage of HRCC as it failed to file any
right, it is the general rule that a person may requirement is a mechanism essentially counterclaim against HRCC pursuant to the
waive any matter which affects his granting FFCCI the opportunity to verify terms of the Subcontract Agreement.
property, and any alienable right or and, if necessary, contest HRCCs valuation
privilege of which he is the owner or of its completed works prior to the For its part, FFCCI asserted that the work
which belongs to him or to which he is submission of the latter’s monthly progress stoppage of HRCC was not justified and, in
legally entitled, whether secured by billings. any case, its failure to raise a counterclaim
contract, conferred with statute, or against HRCC for liquidated damages
guaranteed by constitution, provided such In the final analysis, the joint measurement before the CIAC does not amount to a
rights and privileges rest in the individual, requirement seeks to limit the dispute ratification of the latter’s work stoppage.
are intended for his sole benefit, do not between the parties with regard to the
infringe on the rights of others, and further valuation of HRCCs completed works. The determination of the validity of HRCCs
provided the waiver of the right or privilege Accordingly, any issue which FFCCI may work stoppage depends on a determination
is not forbidden by law, and does not have with regard to HRCCs valuation of the of the following: first, whether HRCC has
contravene public policy; and the principle is works it had completed should be raised the right to extrajudicially rescind the
recognized that everyone has a right to and resolved during the said joint Subcontract Agreement; and second,
waive, and agree to waive, the advantage of measurement instead of raising the same whether FFCCI is already barred from
a law or rule made solely for the benefit and after HRCC had submitted its monthly disputing the work stoppage of HRCC.
protection of the individual in his private progress billings. Thus, having relinquished
capacity, if it can be dispensed with and its right to ask for a joint measurement of HRCC had waived its right to rescind the
relinquished without infringing on any public HRCCs completed works, FFCCI had Subcontract Agreement.
right, and without detriment to the necessarily waived its right to dispute
community at large. HRCCs valuation of the works it had The right of rescission is statutorily
accomplished. recognized in reciprocal obligations.
Here, it is undisputed that the joint Article 1191 of the Civil Code pertinently
measurement of HRCCs completed works Second Substantive Issue: reads:
contemplated by the parties in the
Subcontract Agreement never materialized. Validity of HRCCs Rescission of the Art. 1191. The power to rescind obligations
Subcontract Agreement. is implied in reciprocal ones, in case one of
Essentially, the question that should be the obligors should not comply with what is
resolved is this: In view of FFCCIs waiver of Both the CA and the CIAC held that the work incumbent upon him.
its right to demand a joint measurement of stoppage of HRCC was justified as the
HRCCs completed works, is FFCCI now same is but an exercise of its right to rescind The injured party may choose between the
barred from disputing the claim of HRCC in the Subcontract Agreement in view of fulfillment and the rescission of the
its monthly progress billings? FFCCIs failure to pay the formers monthly obligation, with the payment of damages in

Case Digests for Cases under Articles 1189-1198 Page | 2


either case. He may also seek rescission, Notwithstanding any dispute, controversy, The power to rescind obligations is implied
even after he has chosen fulfillment, if the differences or arbitration proceedings in reciprocal ones, in case one of the
latter should become impossible. relating directly or indirectly to this obligors should not comply with what is
SUBCONTRACT Agreement and without incumbent upon him.
The court shall decree the rescission prejudice to the eventual outcome thereof,
claimed, unless there be just cause [HRCC] shall at all times proceed with the The injured party may choose between the
authorizing the fixing of a period. prompt performance of the Works in fulfillment and the rescission of the
accordance with the directives of FFCCI and obligation, with the payment of damages in
This is understood to be without prejudice to this SUBCONTRACT Agreement. either case. He may also seek rescission,
the rights of third persons who have even after he had chosen fulfillment, if the
acquired the thing, in accordance with Hence, in spite of the existence of dispute latter should become impossible.
Articles 1385 and 1388 and the Mortgage or controversy between the parties during
Law. the course of the Subcontract Agreement, xxx xxx xxx
HRCC had agreed to continue the
The rescission referred to in this article, performance of its obligations pursuant From the foregoing, the right of rescission
more appropriately referred to as resolution to the Subcontract Agreement. In view of is implied in every reciprocal obligation
is on the breach of faith by the defendant the provision of the Subcontract Agreement where one party fails to perform what is
which is violative of the reciprocity between quoted above, HRCC is deemed to have incumbent upon him while the other is
the parties. The right to rescind, however, effectively waived its right to effect willing and ready to comply.
may be waived, expressly or impliedly. extrajudicial rescission of its contract
with FFCCI. Accordingly, HRCC, in the Certainly, petitioner's failure to deliver the
While the right to rescind reciprocal guise of rescinding the Subcontract units on the commencement date of the
obligations is implied, that is, that such Agreement, was not justified in lease on October 1, 1997 gave respondent
right need not be expressly provided in implementing a work stoppage. the right to rescind the contract after the
the contract, nevertheless the contracting latter had already paid the contract price in
parties may waive the same. full.
G.R. No. 168522 December 19, 2007
Contrary to the respective dispositions of UNIWIDE HOLDINGS, INC., Petitioner, vs. Furthermore, respondent's right to
the CIAC and the CA, we find that HRCC JANDECS TRANSPORTATION CO., INC., rescind the contract cannot be prevented
had no right to rescind the Subcontract Respondent by the fact that petitioner had the option
Agreement in the guise of a work to substitute the stalls.
stoppage, the latter having waived such RULING:
right. Apropos is Article 11.2 of the Even if petitioner had that option, it did not,
Subcontract Agreement, which reads: Right of Rescission When Available however, mean that it could insist on the
continuance of the contract by forcing
11.2 Effects of Disputes and Continuing Article 1191 of the Civil Code provides: respondent to accept the substitution.
Obligations Neither did it mean that its previous default

Case Digests for Cases under Articles 1189-1198 Page | 3


had been obliterated completely by the BENITEZ, and ROLANDO SUAREZ, different acts of the parties involved. The
exercise of that option. Respondents issue of receivership does not arise from the
parties’ obligations under the Memorandum
However, so as not to run counter to or RULING: The Petition is bereft of merit. We of Agreement, but rather from specific acts
depart from the well-established doctrines in uphold the Decision of the CA affirming that attributed to petitioners as members of the
BF Homes, Inc. and PAL, and considering of the RTC. Board of Directors of the Bank.
further the SEC's appointment of a
receivership committee, we will defer the Petitioners, without conceding the propriety Clearly, the rescission of the
entry of judgment in this case even after this of the judgment of rescission, also argue Memorandum of Agreement is a cause of
resolution attains finality. In effect, the that the subject Memorandum of Agreement action within the jurisdiction of the trial
execution of the RTC decision (which the could not just be ordered rescinded without courts, notwithstanding the fact that the
CA and this Court have affirmed) is the corresponding order for the restitution of parties involved are all directors of the same
suspended until further advice from us. the parties’ total contributions and/or corporation.
investments in the Rural Bank.
One final note. Petitioner's extreme bad Still, the petitioners insist that the trial court
faith in dealing with respondent was too On the other hand, respondents declare that had no jurisdiction over the complaint
glaring for the Court to ignore. immediately after the signing of the because the issues involved are intra-
Petitioner’s lack of good and honest Memorandum of Agreement, they complied corporate in nature.
intentions, as well as the evasive manner by with their obligation and transferred control
which it was able to frustrate respondent's of the Rural Bank to petitioner Unlad This argument miserably fails to persuade.
claim for a decade, should not go Resources and its nominees, but that, The law in force at the time of the filing of
unsanctioned. Parties in a contract cannot despite repeated demands, petitioners have the case was Presidential Decree (P.D.)
be allowed to engage in double-dealing failed and refused to comply with their 902-A, Section 5(b) of which vested the
schemes to dupe those who transact with concomitant obligations under the Securities and Exchange Commission with
them in good faith. Agreement. original and exclusive jurisdiction to hear
and decide cases involving controversies
The main issue in this case is the arising out of intra-corporate relations.
G.R. No. 149338 July 28, 2008 rescission of the Memorandum of Interpreting this statutorily conferred
UNLAD RESOURCES DEVELOPMENT Agreement. jurisdiction on the SEC, this Court had
CORPORATION, UNLAD RURAL BANK occasion to state:
OF NOVELETA, INC., UNLAD This is to be distinguished from
COMMODITIES, INC., HELENA Z. respondent’s allegation of the alleged Nowhere in said decree do we find even so
BENITEZ, and CONRADO L. BENITEZ II, mismanagement and dissipation of much as an [intimation] that absolute
Petitioners, vs. RENATO P. DRAGON, corporate assets by the petitioners which is jurisdiction and control is vested in the
TARCISIUS R. RODRIGUEZ, VICENTE D. based on the prayer for receivership over Securities and Exchange Commission in all
CASAS, ROMULO M. VIRATA, FLAVIANO the bank. The two issues, albeit related, are matters affecting corporations. To uphold
PERDITO, TEOTIMO BENITEZ, ELENA obviously separate, as they pertain to the respondents’ arguments would remove

Case Digests for Cases under Articles 1189-1198 Page | 4


without legal imprimatur from the regular It is to be noted, however, that determination In a previous case, this Court has held that
courts all conflicts over matters involving or of the contractual undertaking of the parties Article 1389:
affecting corporations, regardless of the under a contract lies with the Regional Trial
nature of the transactions which give rise to Courts and not with this Commission. applies to rescissible contracts, as
such disputes. The courts would then be enumerated and defined in Articles 1380
divested of jurisdiction not by reason of the Be that as it may, this point has been and 1381.
nature of the dispute submitted to them for rendered moot by Republic Act (R.A.) No.
adjudication, but solely for the reason that 8799, also known as the Securities We must stress however, that the
the dispute involves a corporation. This Regulation Code. This law, which took effect rescission in Article 1381 is not akin to
cannot be done. in 2000, has transferred jurisdiction over the term rescission in Article 1191 and
such disputes to the RTC. Article 1592.
It is well to remember that the respondents
had actually filed with the SEC a case Consequently, whether the cause of action In Articles 1191 and 1592, the rescission
against the petitioners which, however, was stems from a contractual dispute or one that is a principal action which seeks the
dismissed for lack of jurisdiction due to the involves intra-corporate matters, the RTC resolution or cancellation of the contract
pendency of the case before the RTC. The already has jurisdiction over this case. In while in Article 1381, the action is a
SECs Order dismissing the respondents this light, the question of whether the subsidiary one limited to cases of rescission
complaint is instructive: doctrine of estoppel by laches applies, as for lesion as enumerated in said article.
enunciated by this Court in Tijam v.
From the foregoing allegations, it is Sibonghanoy, no longer finds relevance. The prescriptive period applicable to
apparent that the present action involves rescission under Articles 1191 and 1592,
two separate causes of action which are Second, the issue of prescription. is found in Article 1144, which provides
interrelated, and the resolution of which Petitioners further contend that the that the action upon a written contract
hinges on the very document sought to be action for rescission has prescribed should be brought within ten years from the
rescinded. The assertion that the under Article 1398 of the Civil Code, time the right of action accrues.
defendants failed to comply with their which provides:
contractual undertaking and the claim for Article 1381 sets out what are rescissible
rescission of the contract by the plaintiffs Article 1389. The action to claim rescission contracts, to wit:
has, in effect, put in issue the very status of must be commenced within four years x x x.
the herein defendants as stockholders of the Article 1381. The following contracts are
Rural Bank. The issue as to whether or not This is an erroneous proposition. rescissible:
the defendants are stockholders of the Rural
Bank is a pivotal issue to be determined on Article 1389 specifically refers to (1) Those which are entered into by
the basis of the Memorandum of rescissible contracts as, clearly, this guardians whenever the wards whom they
Agreement. It is a prejudicial question provision is under the chapter entitled represent suffer lesion by more than one-
and a logical antecedent to confer Rescissible Contracts. fourth of the value of the things which are
jurisdiction to this Commission. the object thereof;

Case Digests for Cases under Articles 1189-1198 Page | 5


(2) Those agreed upon in representation of is counted from the time the right of contemplated by Article 1191 of the Civil
absentees, if the latter suffer the lesion action accrues. The right of action Code, which reads:
stated in the preceding number; accrues from the moment the breach of
right or duty occurs. Thus, the original Article 1191. The power to rescind
(3) Those undertaken in fraud of creditors Complaint was filed well within the reciprocal obligations is implied in reciprocal
when the latter cannot in any other manner prescriptive period. ones, in case one of the obligors should not
collect the claims due them; comply with what is incumbent upon him.
We now proceed to determine if the trial
(4) Those which refer to things under court, as affirmed by the CA, correctly The injured party may choose between
litigation if they have been entered into by ruled for the rescission of the subject the fulfillment and the rescission of the
the defendant without the knowledge and Agreement. obligation, with the payment of damages in
approval of the litigants or of competent either case. He may also seek rescission,
judicial authority; Petitioners contend that they have fully even after he has chosen fulfillment, if the
complied with their obligation under the latter should become impossible.
(5) All other contracts specially declared by Memorandum of Agreement. They allege
law to be subject to rescission. that due to respondents’ failure to increase The court shall decree the rescission
the capital stock of the corporation to an claimed, unless there be just cause
The Memorandum of Agreement subject amount that will accommodate their authorizing the fixing of a period.
of this controversy does not fall under undertaking, it had become impossible for
the above enumeration. Accordingly, the them to perform their end of the Agreement. This is understood to be without prejudice to
prescriptive period that should apply to the rights of third persons who have
this case is that provided for in Article Again, petitioners’ contention is untenable. acquired the thing, in accordance with
1144, to wit: There is no question that petitioners herein Articles 1385 and 1388 and the Mortgage
failed to fulfill their obligation under the Law.
Article 1144. The following actions must be Memorandum of Agreement. Even they
brought within ten years from the time the admit the same, albeit laying the blame on Thus, petitioners should have exacted
right of action accrues: respondents. fulfillment from the respondents or asked for
the rescission of the contract instead of
(1) Upon a written contract; It is true that respondents increased the simply not performing their part of the
Rural Banks authorized capital stock to only Agreement. But in the course of things, it
xxxx P5 million, which was not enough to was the respondents who availed of the
accommodate the P4.8 million worth of remedy under Article 1191, opting for the
Based on the records of this case, the action stocks that petitioners were to subscribe to rescission of the Agreement in order to
was commenced on July 3, 1987, while the and pay for. However, respondents’ failure regain control of the Rural Bank.
Memorandum of Agreement was entered to fulfill their undertaking in the agreement
into on December 29, 1981. Article 1144 would have given rise to the scenario Having determined that the rescission of the
specifically provides that the 10-year period subject Memorandum of Agreement was in

Case Digests for Cases under Articles 1189-1198 Page | 6


order, the trial court ordered petitioner Unlad [S]ince Article 1385 of the Civil Code rescission has the effect of abrogating the
Resources to return to respondents the expressly and clearly states that rescission contract in all parts.
management and control of the Rural Bank creates the obligation to return the things
and for the latter to return the sum of which were the object of the contract, Clearly, the petitioners failed to fulfill their
P1,003,070.00 to petitioners. together with their fruits, and the price with end of the agreement, and thus, there was
its interest, the Court finds no justification just cause for rescission. With the
Mutual restitution is required in cases to sustain petitioners’ position that said contract thus rescinded, the parties must be
involving rescission under Article 1191. Article 1385 does not apply to rescission restored to the status quo ante, that is,
under Article 1191. before they entered into the Memorandum
This means bringing the parties back to of Agreement.
their original status prior to the inception of Rescission has the effect of unmaking a
the contract. Article 1385 of the Civil Code contract, or its undoing from the beginning,
provides, thus: and not merely its termination. G.R. No. 130913. June 21, 2005
OLIVERIO LAPERAL and FILIPINAS
ART. 1385. Rescission creates the Hence, rescission creates the obligation GOLF & COUNTRY CLUB INC.,
obligation to return the things which to return the object of the contract. petitioners, vs. SOLID HOMES, INC.,
were the object of the contract, together respondent. SOUTHRIDGE VILLAGE
with their fruits, and the price with its It can be carried out only when the one HOMEOWNERS ASSOCIATION,
interest; consequently, it can be carried out who demands rescission can return intervenor
only when he who demands rescission whatever he may be obliged to restore.
can return whatever he may be obligated RULING: The Court finds merit in the
to restore. To rescind is to declare a contract void at its petition.
inception and to put an end to it as though it
Neither shall rescission take place when never was. While this Court does not agree with
the things which are the object of the petitioners that the right to rescind under
contract are legally in the possession of It is not merely to terminate it and release Article 1191 of the Civil Code does not carry
third persons who did not act in bad faith. the parties from further obligations to each with it the corresponding obligation for
other, but to abrogate it from the beginning restitution, we do not subscribe to the Court
In this case, indemnity for damages may and restore the parties to their relative of Appeals conclusion that: (1) the
be demanded from the person causing positions as if no contract has been made. forfeiture/penalty clause under paragraphs
the loss. Nos. 2 and 3 of the Addendum to the
Accordingly, when a decree for rescission is Revised Development and Management
This Court has consistently ruled that this handed down, it is the duty of the court to Agreements is, under the factual milieu of
provision applies to rescission under require both parties to surrender that this case, unreasonable and
Article 1191: which they have respectively received unconscionable and, therefore, void for
and to place each other as far as being contrary to morals and good
practicable in his original situation. The customs[15]; and (2) petitioners must

Case Digests for Cases under Articles 1189-1198 Page | 7


reimburse respondent the actual cost of respondents, lest the latter unjustly enrich The court shall decree the rescission
development and completed improvements themselves at the expense of the former. claimed, unless there be just cause
on the project in the total amount of authorizing the fixing of the period.
P5,200,833.27.[16] Rescission creates the obligation to
return the object of the contract. This is understood without prejudice to the
It is petitioners’ thesis that inasmuch as the rights of third persons who have acquired
rescission of the Revised Agreements and It can be carried out only when the one the thing, in accordance with articles 1385
its Addendum was made pursuant to Article who demands rescission can return and 1388 and the Mortgage Law. (1124)
1191 of the Civil Code, the provision of whatever he may be obliged to restore
Article 1385[17] of the same Code, which (citing Co v. Court of Appeals, 312 SCRA Despite the fact that Article 1124 of the old
requires mutual restitution should not apply 528, August 17, 1999; and Vitug, Civil Code from whence Article 1191 was
because Article 1385 applies only if the Compendium of Civil Law and taken, used the term resolution, the
rescission is made under the instances Jurisprudence, 1993 revised ed., p. 556). amendment thereto (presently, Article 1191)
enumerated in Article 1381[18] of the Code. explicitly and clearly used the term
To rescind is to declare a contract void at its rescission. Unless Article 1191 is
We do not agree. inception and to put an end to it as though it subsequently amended to revert back to the
never was. It is not merely to terminate it term resolution, this Court has no alternative
Mutual restitution is required in cases and release the parties from further but to apply the law, as it is written.
involving rescission under Article 1191. obligations to each other, but to abrogate it
from the beginning and restore the parties Again, since Article 1385 of the Civil Code
In Velarde vs. Court of Appeals, this Court, to their relative positions as if no contract expressly and clearly states that
in no uncertain terms, squarely ruled on this has been made (citing Ocampo v. Court of rescission creates the obligation to
matter: Appeals, 233 SCRA 551, June 30, 1994). return the things which were the object of
the contract, together with their fruits, and
Considering that the rescission of the Article 1191 of the Civil Code provides: the price with its interest, the Court finds
contract is based on Article 1191 of the Civil no justification to sustain petitioners’
Code, mutual restitution is required to Art. 1191. The power to rescind obligations position that said Article 1385 does not
bring back the parties to their original is implied in reciprocal ones, in case one of apply to rescission under Article 1191.
situation prior to the inception of the the obligors should not comply with what is
contract. incumbent upon him. In Palay, Inc. vs. Clave, this Court applied
Article 1385 in a case involving resolution
Accordingly, the initial payment of P800,000 The injured party may choose between under Article 1191, thus:
and the corresponding mortgage payments the fulfillment and the rescission of the
in the amounts of P27,225, P23,000 and obligation, with the payment of damages in Regarding the second issue on refund of the
P23,925 (totaling P874,150.00) advanced either case. He may also seek rescission, installment payments made by private
by petitioners should be returned by private even after he has chosen fulfillment, if the respondent. Article 1385 of the Civil Code
latter should become impossible. provides:

Case Digests for Cases under Articles 1189-1198 Page | 8


ART. 1385. Rescission creates the Applying the clear language of the law and DEVELOPER deliberately abandoned or
obligation to return the things which were the consistent jurisprudence on the matter, discontinued the work on the project, said
the object of the contract, together with their therefore, the Court rules that rescission party shall lose any entitlement, if any, to
fruits, and the price with its interest; under Article 1191 in the present case, any refund and/or advances it may have
consequently, it can be carried out only carries with it the corresponding incurred in connection with or relative to
when he who demands rescission can obligation of restitution. previous development works in the
return whatever he may be obliged to subdivision; likewise, all improvements of
restore. This notwithstanding, the Court does not whatever nature and kind introduced by the
agree with the Court of Appeals that, as a DEVELOPER on the property, existing as of
Neither shall rescission take place when consequence of the obligation of mutual the date of default or violation, shall
the things which are the object of the restitution in this case, petitioners should automatically belong to the OWNER without
contract are legally in the possession of return the amount of P5,200,833.27 to obligation on his part to pay for the costs
third persons who did not act in bad respondent. thereof.
faith.
Article 1191 states that the injured party 2. Similarly with the same condition of
In this case, indemnity for damages may may choose between fulfillment and default or violation obtaining, as stated in
be demanded from the person causing rescission of the obligation, with the paragraph 10 of said agreement, all
the loss. payment of damages in either case. In other advances made and remittances of
words, while petitioners are indeed obliged proceeds from reservations and sales given
As a consequence of the resolution by to return the said amount to respondent by the DEVELOPER to the OWNER as
petitioners, rights to the lot should be under Article 1385, assuming said figure is provided for in this agreement shall be
restored to private respondent or the same correct, respondent is at the same time deemed absolutely forfeited in favor of the
should be replaced by another acceptable liable to petitioners in the same amount as OWNER, resulting to waiver of
lot. However, considering that the liquidated damages by virtue of the DEVELOPERs rights, if any, with respect to
property had already been sold to a third forfeiture/penalty clause as freely stipulated said amount(s).
person and there is no evidence on upon by the parties in the Addendum,
record that other lots are still available, paragraphs 1 and 2 of which respectively If this Court recognized the right of the
private respondent is entitled to the read: parties to stipulate on an extrajudicial
refund of installments paid plus interest rescission under Article 1191, there is no
at the legal rate of 12% computed from WHEREAS, included as part of said reason why this Court will not allow the
the date of the institution of the action. It agreement are the following: parties to stipulate on the matter of
would be most inequitable if petitioners were damages in case of such rescission under
to be allowed to retain private respondent's 1. Further to the stipulations on paragraph Book IV, Title VIII, Chapter 3, Section 2 of
payments and at the same time appropriate 10, upon default of performances, violations the Civil Code governing liquidated
the proceeds of the second sale to another. and/or non-compliance with the terms and damages.
conditions herein agreed upon by the
DEVELOPER wherein it appears that the

Case Digests for Cases under Articles 1189-1198 Page | 9


G.R. No. 157480. May 6, 2005 Likewise, it is settled that if the terms of the corresponding to the remaining term of the
PRYCE CORPORATION (formerly contract clearly express the intention of the lease as well as for any and all damages,
PRYCE PROPERTIES CORPORATION), contracting parties, the literal meaning of the actual or consequential resulting from such
petitioner, vs. PHILIPPINE AMUSEMENT stipulations would be controlling. default and termination of this contract.
AND GAMING CORPORATION,
respondent In this case, Article XX of the parties d) x x x x x x x x x. (Italics supplied)
Contract of Lease provides in part as
RULING: The Petition is partly meritorious. follows: The above provisions leave no doubt that
the parties have covenanted 1) to give PPC
Collection of Remaining Rentals XX. BREACH OR DEFAULT the right to terminate and cancel the
Contract in the event of a default or breach
PPC anchors its right to collect future rentals a) The LESSEE agrees that all the terms, by the lessee; and 2) to make PAGCOR fully
upon the provisions of the Contract. conditions and/or covenants herein liable for rentals for the remaining term of
Likewise, it argues that termination, as contained shall be deemed essential the lease, despite the exercise of such right
defined under the Contract, is different from conditions of this contract, and in the event to terminate. Plainly, the parties have
the remedy of rescission prescribed under of default or breach of any of such terms, voluntarily bound themselves to require
Article 1659 of the Civil Code. On the other conditions and/or covenants, or should the strict compliance with the provisions of the
hand, PAGCOR contends, as the CA ruled, LESSEE become bankrupt, or insolvent, or Contract by stipulating that a default or
that Article 1659 of the Civil Code governs; compounds with his creditors, the LESSOR breach, among others, shall give the lessee
hence, PPC is allegedly no longer entitled to shall have the right to terminate and cancel the termination option, coupled with the
future rentals, because it chose to rescind this contract by giving them fifteen (15 days) lessors’ liability for rentals for the remaining
the Contract. prior notice delivered at the leased premises term of the lease.
or posted on the main door thereof. Upon
Contract Provisions Clear and Binding such termination or cancellation, the For sure, these stipulations are valid and are
LESSOR may forthwith lock the premises not contrary to law, morals, good customs,
Article 1159 of the Civil Code provides that and exclude the LESSEE therefrom, public order or public policy. Neither is there
obligations arising from contracts have forcefully or otherwise, without incurring any anything objectionable about the inclusion in
the force of law between the contracting civil or criminal liability. During the fifteen the Contract of mandatory provisions
parties and should be complied with in (15) days notice, the LESSEE may prevent concerning the rights and obligations of the
good faith. the termination of lease by curing the events parties. Being the primary law between the
or causes of termination or cancellation of parties, it governs the adjudication of their
In deference to the rights of the parties, the the lease. rights and obligations. A court has no
law allows them to enter into stipulations, alternative but to enforce the contractual
clauses, terms and conditions they may b) x x x x x x x x x stipulations in the manner they have been
deem convenient; that is, as long as these agreed upon and written. It is well to recall
are not contrary to law, morals, good c) Moreover, the LESSEE shall be fully that courts, be they trial or appellate, have
customs, public order or public policy. liable to the LESSOR for the rentals no power to make or modify contracts.

Case Digests for Cases under Articles 1189-1198 Page | 10


Neither can they save parties from In his Concurring Opinion in Universal Food Article 1191 (and, conformably, also Article
disadvantageous provisions. Corporation v. CA, Justice J. B. L. Reyes 1659).
differentiated rescission under Article
Termination or Rescission? 1191 from that under Article 1381 et seq. Now, as to the distinction between
as follows: termination (or cancellation) and
Well-taken is petitioner’s insistence that it rescission (more properly, resolution),
had the right to ask for termination plus the x x x. The rescission on account of breach Huibonhoa v. CA held that, where the
full payment of future rentals under the of stipulations is not predicated on injury to action prayed for the payment of rental
provisions of the Contract, rather than just economic interests of the party plaintiff but arrearages, the aggrieved party actually
rescission under Article 1659 of the Civil on the breach of faith by the defendant, that sought the partial enforcement of a lease
Code. violates the reciprocity between the parties. contract. Thus, the remedy was not
It is not a subsidiary action, and Article 1191 rescission, but termination or cancellation,
This Court is not unmindful of the fact that may be scanned without disclosing of the contract. The Court explained:
termination and rescission are terms that anywhere that the action for rescission
have been used loosely and thereunder is subordinated to anything other x x x. By the allegations of the complaint, the
interchangeably in the past. than the culpable breach of his obligations Gojoccos aim was to cancel or terminate the
to the defendant. This rescission is a contract because they sought its partial
But distinctions ought to be made, principal action retaliatory in character, it enforcement in praying for rental
especially in this controversy, in which being unjust that a party be held bound to arrearages. There is a distinction in law
the terms mean differently and lead to fulfill his promises when the other violates between cancellation of a contract and its
equally different consequences. his. As expressed in the old Latin aphorism: rescission. To rescind is to declare a
Non servanti fidem, non est fides servanda. contract void in its inception and to put an
The term rescission is found in: Hence, the reparation of damages for the end to it as though it never were. It is not
breach is purely secondary. merely to terminate it and release parties
1) Article 1191 of the Civil Code, the general from further obligations to each other but
provision on rescission of reciprocal On the contrary, in rescission by reason of to abrogate it from the beginning and restore
obligations; lesion or economic prejudice, the cause of the parties to relative positions which they
action is subordinated to the existence of would have occupied had no contract ever
2) Article 1659, which authorizes rescission that prejudice, because it is the raison detre been made.
as an alternative remedy, insofar as the as well as the measure of the right to
rights and obligations of the lessor and the rescind. x x x.[18] x x x. The termination or cancellation of a
lessee in contracts of lease are concerned; contract would necessarily entail
and; Relevantly, it has been pointed out that enforcement of its terms prior to the
resolution was originally used in Article 1124 declaration of its cancellation in the same
3) Article 1380 with regard to the rescission of the old Civil Code, and that the term way that before a lessee is ejected under
of contracts. became the basis for rescission under a lease contract, he has to fulfill his
obligations thereunder that had accrued

Case Digests for Cases under Articles 1189-1198 Page | 11


prior to his ejectment. However, get back the rentals it paid the former for the ISSUES:
termination of a contract need not undergo use of the hotel space.
judicial intervention. x x x. Tan argues that the CA erred in affirming the
In contrast, the parties in a case of RTCs ruling to cancel the lis pendens
Rescission has likewise been defined as termination are not restored to their annotation on TCT No. 27335. Due to the
the unmaking of a contract, or its undoing original situation; neither is the contract unauthorized novation of the agreement,
from the beginning, and not merely its treated as if it never existed. Tan presented before the trial court two
termination. alternative remedies in his complaint either
Prior to its termination, the parties are the rescission of the contract and the return
Rescission may be effected by both obliged to comply with their contractual of the down payment, or the reformation of
parties by mutual agreement; or obligations. Only after the contract has the contract to adjust the payment period, so
unilaterally by one of them declaring a been cancelled will they be released from that Tan will pay the remaining balance of
rescission of contract without the their obligations. the purchase price only after the lapse of the
consent of the other, if a legally sufficient required two-year encumbrance on the title.
ground exists or if a decree of rescission is In this case, the actions and pleadings of Tan posits that the CA erroneously
applied for before the courts. petitioner show that it never intended to disregarded the alternative remedy of
rescind the Lease Contract from the reformation of contract when it affirmed the
On the other hand, termination refers to beginning. This fact was evident when it removal of the lis pendens annotation on the
an end in time or existence; a close, first sought to collect the accrued rentals title.
cessation or conclusion. With respect to a from September to November 1993
lease or contract, it means an ending, because, as previously stated, it actually Tan further contends that the CA erred
usually before the end of the anticipated demanded the enforcement of the Lease when it recognized the validity of the
term of such lease or contract, that may Contract prior to termination. Any intent to forfeiture of the down payment in favor of the
be effected by mutual agreement or by one rescind was not shown, even when it vendors. While admitting that the Deed of
party exercising one of its remedies as a abrogated the Contract on November 25, Conditional Sale contained a forfeiture
consequence of the default of the other. 1993, because such abrogation was not the clause, he insists that this clause applies
rescission provided for under Article 1659. only if the failure to pay the balance of the
Thus, mutual restitution is required in a purchase price was through his own fault or
rescission (or resolution), in order to negligence. In the present case, Tan claims
bring back the parties to their original G.R. No. 153820 October 16, 2009 that he was justified in refusing to pay the
situation prior to the inception of the DELFIN TAN, Petitioner, vs. ERLINDA C. balance price since the vendors would not
contract. BENOLIRAO, ANDREW C. BENOLIRAO, have been able to comply with their
ROMANO C. BENOLIRAO, DION C. obligation to deliver a clean title covering the
Applying this principle to this case, it means BENOLIRAO, SPS. REYNALDO property.
that PPC would re-acquire possession of TANINGCO and NORMA D. BENOLIRAO,
the leased premises, and PAGCOR would EVELYN T. MONREAL, and ANN KARINA Lastly, Tan maintains that the CA erred in
TANINGCO, Respondents ordering him to pay the respondents

Case Digests for Cases under Articles 1189-1198 Page | 12


P30,000.00, plus P1,000.00 per court The very essence of a contract of sale is xxx
appearance as attorneys fees, since he filed the transfer of ownership in exchange for
the foregoing action in good faith, believing a price paid or promised. Jurisprudence has established that where
that he is in the right. the seller promises to execute a deed of
In contrast, a contract to sell is defined absolute sale upon the completion by the
The respondents, on the other hand, assert as a bilateral contract whereby the buyer of the payment of the price, the
that the petition should be dismissed for prospective seller, while expressly contract is only a contract to sell.[12] Thus,
raising pure questions of fact, in reserving the ownership of the property while the contract is denominated as a Deed
contravention of the provisions of Rule 45 of despite delivery thereof to the prospective of Conditional Sale, the presence of the
the Rules which provides that only buyer, binds himself to sell the property above-quoted provision identifies the
questions of law can be raised in petitions exclusively to the prospective buyer contract as being a mere contract to sell.
for review on certiorari. upon fulfillment of the condition agreed,
i.e., full payment of the purchase price. A Section 4, Rule 74 annotation is an
RULING: The petition is granted. encumbrance on the property
A contract to sell may not even be
Tans complaint prayed for either the considered as a conditional contract of sale While Tan admits that he refused to pay the
rescission or the reformation of the Deed of where the seller may likewise reserve title to balance of the purchase price, he claims
Conditional Sale. the property subject of the sale until the that he had valid reason to do so the sudden
fulfillment of a suspensive condition, appearance of an annotation on the title
Contract is a mere contract to sell because in a conditional contract of sale, the pursuant to Section 4, Rule 74 of the Rules,
first element of consent is present, although which Tan considered an encumbrance on
A contract is what the law defines it to be, it is conditioned upon the happening of a the property.
taking into consideration its essential contingent event which may or may not
elements, and not what the contracting occur. We find Tans argument meritorious.
parties call it. Article 1485 of the Civil Code
defines a contract of sale as follows: In the present case, the true nature of the The annotation placed on TCT No. 27335,
contract is revealed by paragraph D thereof, the new title issued to reflect the
Art. 1458. By the contract of sale one of the which states: extrajudicial partition of Lamberto
contracting parties obligates himself to Benoliraos estate among his heirs, states:
transfer the ownership and to deliver a xxx
determinate thing, and the other to pay x x x any liability to creditors (sic), excluded
therefor a price certain in money or its d) That in case, BUYER has complied with heirs and other persons having right to the
equivalent. the terms and conditions of this contract, property, for a period of two (2) years, with
then the SELLERS shall execute and deliver respect only to the share of Erlinda, Andrew,
A contract of sale may be absolute or to the BUYER the appropriate Deed of Romano and Dion, all surnamed Benolirao.
conditional. Absolute Sale;

Case Digests for Cases under Articles 1189-1198 Page | 13


This annotation was placed on the title Senator Vicente Francisco discusses this administrator and does not disturb the
pursuant to Section 4, Rule 74 of the Rules, provision in his book The Revised Rules of possession enjoyed by the distributees.
which reads: Court in the Philippines, where he states:
An annotation is placed on new certificates
Sec. 4. Liability of distributees and estate. - The provision of Section 4, Rule 74 of title issued pursuant to the distribution
If it shall appear at any time within two (2) prescribes the procedure to be followed if and partition of a decedents real properties
years after the settlement and distribution of within two years after an extrajudicial to warn third persons on the possible
an estate in accordance with the provisions partition or summary distribution is made, an interests of excluded heirs or unpaid
of either of the first two sections of this rule, heir or other person appears to have been creditors in these properties. The
that an heir or other person has been unduly deprived of his lawful participation in the annotation, therefore, creates a legal
deprived of his lawful participation in the estate, or some outstanding debts which encumbrance or lien on the real property in
estate, such heir or such other person may have not been paid are discovered. When favor of the excluded heirs or creditors.
compel the settlement of the estate in the the lawful participation of the heir is not Where a buyer purchases the real property
courts in the manner hereinafter provided payable in money, because, for instance, he despite the annotation, he must be ready for
for the purpose of satisfying such lawful is entitled to a part of the real property that the possibility that the title could be subject
participation. And if within the same time of has been partitioned, there can be no other to the rights of excluded parties. The
two (2) years, it shall appear that there are procedure than to cancel the partition so cancellation of the sale would be the logical
debts outstanding against the estate which made and make a new division, unless, of consequence where: (a) the annotation
have not been paid, or that an heir or other course, the heir agrees to be paid the value clearly appears on the title, warning all
person has been unduly deprived of his of his participation with interest. But in case would-be buyers; (b) the sale unlawfully
lawful participation payable in money, the the lawful participation of the heir consists in interferes with the rights of heirs; and (c) the
court having jurisdiction of the estate may, his share in personal property of money left rightful heirs bring an action to question the
by order for that purpose, after hearing, by the decedent, or in case unpaid debts are transfer within the two-year period provided
settle the amount of such debts or lawful discovered within the said period of two by law.
participation and order how much and in years, the procedure is not to cancel the
what manner each distributee shall partition, nor to appoint an administrator to As we held in Vda. de Francisco v. Carreon:
contribute in the payment thereof, and may re-assemble the assets, as was allowed
issue execution, if circumstances require, under the old Code, but the court, after And Section 4, Rule 74 xxx expressly
against the bond provided in the preceding hearing, shall fix the amount of such debts authorizes the court to give to every heir his
section or against the real estate belonging or lawful participation in proportion to or to lawful participation in the real estate
to the deceased, or both. Such bond and the extent of the assets they have notwithstanding any transfers of such real
such real estate shall remain charged with a respectively received and, if circumstances estate and to issue execution thereon. All
liability to creditors, heirs, or other persons require, it may issue execution against the this implies that, when within the
for the full period of two (2) years after such real estate belonging to the decedent, or amendatory period the realty has been
distribution, notwithstanding any transfers of both. The present procedure is more alienated, the court in re-dividing it among
real estate that may have been made. expedient and less expensive in that it the heirs has the authority to direct
dispenses with the appointment of an cancellation of such alienation in the same

Case Digests for Cases under Articles 1189-1198 Page | 14


estate proceedings, whenever it becomes attached until the expiration of the two-year remains the owner for as long as the vendee
necessary to do so. To require the institution period. Clearly, at this time, the vendors has not complied fully with the condition of
of a separate action for such annulment could no longer compel Tan to pay the paying the purchase price. If the vendor
would run counter to the letter of the above balance of the purchase since considering should eject the vendee for failure to meet
rule and the spirit of these summary they themselves could not fulfill their the condition precedent, he is enforcing the
settlements. obligation to transfer a clean title over the contract and not rescinding it. x x x Article
property to Tan. 1592 speaks of non-payment of the
Similarly, in Sps. Domingo v. Roces, we purchase price as a resolutory condition. It
said: Contract to sell is not rescinded but does not apply to a contract to sell. As to
terminated Article 1191, it is subordinated to the
The foregoing rule clearly covers transfers provisions of Article 1592 when applied to
of real property to any person, as long as the What then happens to the contract? sales of immovable property. Neither
deprived heir or creditor vindicates his rights provision is applicable [to a contract to sell].
within two years from the date of the We have held in numerous cases that the
settlement and distribution of estate. remedy of rescission under Article 1191 We, therefore, hold that the contract to
Contrary to petitioners’ contention, the cannot apply to mere contracts to sell. sell was terminated when the vendors
effects of this provision are not limited to the We explained the reason for this in Santos could no longer legally compel Tan to
heirs or original distributees of the estate v. Court of Appeals, where we said: pay the balance of the purchase price as
properties, but shall affect any transferee of a result of the legal encumbrance which
the properties. [Emphasis supplied.] [I]n a contract to sell, title remains with the attached to the title of the property. Since
vendor and does not pass on to the vendee Tans refusal to pay was due to the
Indeed, in David v. Malay, although the title until the purchase price is paid in full. Thus, supervening event of a legal encumbrance
of the property had already been registered in a contract to sell, the payment of the on the property and not through his own fault
in the name of the third party buyers, we purchase price is a positive suspensive or negligence, we find and so hold that the
cancelled the sale and ordered the condition. Failure to pay the price agreed forfeiture of Tans down payment was clearly
reconveyance of the property to the estate upon is not a mere breach, casual or unwarranted.
of the deceased for proper disposal among serious, but a situation that prevents the
his rightful heirs. obligation of the vendor to convey title from
acquiring an obligatory force. This is entirely G.R. No. 173441 December 3, 2009
By the time Tans obligation to pay the different from the situation in a contract of HEIRS OF SOFIA QUIRONG,
balance of the purchase price arose on May sale, where non-payment of the price is a Represented by ROMEO P. QUIRONG,
21, 1993 (on account of the extensions negative resolutory condition. The effects in Petitioners, vs. DEVELOPMENT BANK
granted by the respondents), a new law are not identical. In a contract of sale, OF THE PHILIPPINES, Respondents
certificate of title covering the property had the vendor has lost ownership of the thing
already been issued on March 26, 1993, sold and cannot recover it, unless the RULINGS:
which contained the encumbrance on the contract of sale is rescinded and set aside.
property; the encumbrance would remain so In a contract to sell, however, the vendor

Case Digests for Cases under Articles 1189-1198 Page | 15


The CA held that the Quirong heir’s action from January 28, 1993, the date of such such as what contracts are about, the option
for rescission of the sale between DBP and finality. to choose between fulfillment and
their predecessor, Sofia Quirong, is barred rescission.
by prescription reckoned from the date of The next question that needs to be resolved
finality of the December 16, 1992 RTC is the applicable period of prescription. The Arturo M. Tolentino, a well-known authority
decision in Civil Case D-7159 and applying DBP claims that it should be four years as in civil law, is quick to note, however, that
the prescriptive period of four years set by provided under Article 1389 of the Civil the equivalent of Article 1191 in the old
Article 1389 of the Civil Code. Code. Article 1389 provides that the action code actually uses the term resolution
to claim rescission must be commenced rather than the present rescission. The
Unfortunately, the CA did not state in its within four years. The Quirong heirs, on the calibrated meanings of these terms are
decision the date when the RTC decision in other hand, claim that it should be 10 years distinct.
Civil Case D-7159 became final and as provided under Article 1144 which states
executory, which decision resulted in the that actions upon a written contract must be Rescission is a subsidiary action based on
Quirong heir’s loss of 80% of the lot that the brought within 10 years from the date the injury to the plaintiff’s economic
DBP sold to Sofia Quirong. Petitioner heirs right of action accrues. interests as described in Articles 1380 and
claim that the prescriptive period should be 1381.
reckoned from January 17, 1995, the date Now, was the action of the Quirong heirs
this Courts resolution in G.R. 116575 for rescission or upon a written Resolution, the action referred to in
became final and executory. contract? Article 1191, on the other hand, is based
on the defendant’s breach of faith, a
But the incident before this Court in G.R. There is no question that their action was violation of the reciprocity between the
116575 did not deal with the merit of the for rescission, since their complaint in Civil parties. As an action based on the binding
RTC decision in Civil Case D-7159. That Case CV-98-02399-D asked for the force of a written contract, therefore,
decision became final and executory on rescission of the contract of sale between rescission (resolution) under Article
January 28, 1993 when the DBP failed to Sofia Quirong, their predecessor, and the 1191 prescribes in 10 years. Ten years is
appeal from it within the time set for such DBP and the reimbursement of the price of the period of prescription of actions based
appeal. The incident before this Court in P78,000.00 that Sofia Quirong paid the on a written contract under Article 1144.
G.R. 116575 involved the issuance of the bank plus damages. The prescriptive
writ of execution in that case. The DBP period for rescission is four years. The distinction makes sense.
contested such issuance supposedly
because the dispositive portion of the But it is not that simple. The remedy of Article 1191 gives the injured party an
decision failed to specify details that were rescission is not confined to the option to choose between, first,
needed for its implementation. Since this rescissible contracts enumerated under fulfillment of the contract and, second,
incident did not affect the finality of the Article 1381. its rescission. An action to enforce a
decision in Civil Case D-7159, the written contract (fulfillment) is definitely an
prescriptive period remained to be reckoned Article 1191 of the Civil Code gives the action upon a written contract, which
injured party in reciprocal obligations, prescribes in 10 years (Article 1144). It will

Case Digests for Cases under Articles 1189-1198 Page | 16


not be logical to make the remedy of of property or thing. Article 1548 of the Civil decision in Civil Case D-7159 became final
fulfillment prescribe in 10 years while the Code provides: and executory and ousted the heirs from a
alternative remedy of rescission (or substantial portion of the lot, the latter had
resolution) is made to prescribe after only Article 1548. Eviction shall take place only until January 28, 1997 within which to
four years as provided in Article 1389 when whenever by a final judgment based on a file their action for rescission. Given that
the injury from which the two kinds of actions right prior to the sale or an act imputable to they filed their action on June 10, 1998, they
derive is the same. the vendor, the vendee is deprived of the did so beyond the four-year period.
whole or of a part of thing purchased.
Here, the Quirong heirs alleged in their With the conclusion that the Court has
complaint that they were entitled to the xxxx reached respecting the first issue presented
rescission of the contract of sale of the lot in this case, it would serve no useful
between the DBP and Sofia Quirong With the loss of 80% of the subject lot to the purpose for it to further consider the issue of
because the decision in Civil Case D-7159 Dalopes by reason of the judgment of the whether or not the heirs of Quirong would
deprived her heirs of nearly the whole of that RTC in Civil Case D-7159, the Quirong heirs have been entitled to the rescission of the
lot. had the right to file an action for rescission DBPs sale of the subject lot to Sofia Quirong
against the DBP pursuant to the provision of as a consequence of her heirs having been
But what was the status of that contract Article 1556 of the Civil Code which evicted from it. As the Court has ruled
at the time of the filing of the action for provides: above, their action was barred by
rescission? prescription. The CA acted correctly in
Article 1556. Should the vendee lose, by reversing the RTC decision and dismissing
Apparently, that contract of sale had reason of the eviction, a part of the thing their action.
already been fully performed when Sofia sold of such importance, in relation to the
Quirong paid the full price for the lot and whole, that he would not have bought it Parenthetically, the Quirong heirs were
when, in exchange, the DBP executed without said part, he may demand the allowed by the RTC to intervene in the
the deed of absolute sale in her favor. rescission of the contract; but with the original action for annulment of sale in Civil
There was a turnover of control of the obligation to return the thing without other Case D-7159 that the Dalopes filed against
property from DBP to Sofia Quirong since encumbrances than those which it had the DBP and the Funcions. Not only did the
she assumed under their contract, the when he acquired it. x x x heirs intervene in defense of the sale, they
ejectment of squatters and/or occupants on likewise filed a cross claim against the DBP.
the lot, at her own expense. And that action for rescission, which is And they were apparently heard on their
based on a subsequent economic loss defense and cross claim but the RTC did not
Actually, the cause of action of the Quirong suffered by the buyer, was precisely the adjudicate their claim for the reason that
heirs stems from them having been ousted action that the Quirong heirs took against they failed to make a formal offer of their
by final judgment from the ownership of the the DBP. Consequently, it prescribed as documentary exhibits. Yet, they did not
lot that the DBP sold to Sofia Quirong, their Article 1389 provides in four years from appeal from this omission or from the
predecessor, in violation of the warranty the time the action accrued. Since it judgment of the RTC, annulling the DBPs
against eviction that comes with every sale accrued on January 28, 1993 when the sale of the subject lot to Sofia Quirong. This

Case Digests for Cases under Articles 1189-1198 Page | 17


point is of course entirely academic but it
shows that the Quirong heirs have The court shall decree the rescission (3) When demand would be useless,
themselves to blame for the loss of claimed, unless there be just cause as when the obligor has rendered it beyond
whatever right they may have in the case. authorizing the fixing of a period. his power to perform.

This is understood to be without prejudice to In reciprocal obligations, neither party


G.R. No. 176868 July 26, 2010 the rights of third persons who have incurs in delay if the other does not
SOLAR HARVEST, INC., Petitioner, vs. acquired the thing, in accordance with comply or is not ready to comply in a
DAVAO CORRUGATED CARTON Articles 1385 and 1388 and the Mortgage proper manner with what is incumbent
CORPORATION, Respondent Law. upon him. From the moment one of the
parties fulfills his obligation, delay by the
ISSUE: In this petition, petitioner insists that The right to rescind a contract arises other begins.
respondent did not completely manufacture once the other party defaults in the
the boxes and that it was respondent which performance of his obligation. In reciprocal obligations, as in a contract of
was obliged to deliver the boxes to sale, the general rule is that the fulfillment
TADECO. In determining when default occurs, Art. of the parties’ respective obligations
1191 should be taken in conjunction with should be simultaneous.
RULING: We find no reversible error in the Art. 1169 of the same law, which provides:
assailed Decision that would justify the grant Hence, no demand is generally necessary
of this petition. Art. 1169. Those obliged to deliver or to do because, once a party fulfills his obligation
something incur in delay from the time the and the other party does not fulfill his, the
Petitioners claim for reimbursement is obligee judicially or extrajudicially demands latter automatically incurs in delay.
actually one for rescission (or resolution) from them the fulfillment of their obligation.
of contract under Article 1191 of the Civil But when different dates for performance
Code, which reads: However, the demand by the creditor shall of the obligations are fixed, the default
not be necessary in order that delay may for each obligation must be determined
Art. 1191. The power to rescind obligations exist: by the rules given in the first paragraph
is implied in reciprocal ones, in case one of of the present article, that is, the other
the obligors should not comply with what is (1) When the obligation or the law party would incur in delay only from the
incumbent upon him. expressly so declares; or moment the other party demands fulfillment
of the formers obligation.
The injured party may choose between the (2) When from the nature and the
fulfillment and the rescission of the circumstances of the obligation it appears Thus, even in reciprocal obligations, if the
obligation, with the payment of damages in that the designation of the time when the period for the fulfillment of the obligation is
either case. He may also seek rescission, thing is to be delivered or the service is to be fixed, demand upon the obligee is still
even after he has chosen fulfillment, if the rendered was a controlling motive for the necessary before the obligor can be
latter should become impossible. establishment of the contract; or

Case Digests for Cases under Articles 1189-1198 Page | 18


considered in default and before a cause of of facts, and findings of fact made by the trial petitioner be ordered to remove the boxes
action for rescission will accrue. court, especially when reiterated by the CA, from its factory site, which could only mean
must be given great respect if not that the boxes are, up to the present, still in
Evident from the records and even from considered as final. In dealing with this respondent’s premises.
the allegations in the complaint was the petition, we will not veer away from this
lack of demand by petitioner upon doctrine and will thus sustain the factual We also believe that the agreement
respondent to fulfill its obligation to findings of the CA, which we find to be between the parties was for petitioner to
manufacture and deliver the boxes. The adequately supported by the evidence on pick up the boxes from respondent’s
Complaint only alleged that petitioner made record. warehouse, contrary to petitioner’s
a follow-up upon respondent, which, allegation. Thus, it was due to petitioner’s
however, would not qualify as a demand for As correctly observed by the CA, aside from fault that the boxes were not delivered to
the fulfillment of the obligation. Petitioners the pictures of the finished boxes and the TADECO.
witness also testified that they made a production report thereof, there is ample
follow-up of the boxes, but not a demand. showing that the boxes had already been Petitioner had the burden to prove that the
Note is taken of the fact that, with respect to manufactured by respondent. There is the agreement was, in fact, for respondent to
their claim for reimbursement, the testimony of Estanislao who accompanied deliver the boxes within 30 days from
Complaint alleged and the witness testified Que to the factory, attesting that, during payment, as alleged in the Complaint. Its
that a demand letter was sent to their first visit to the company, they saw the sole witness, Que, was not even competent
respondent. Without a previous demand for pile of petitioner’s boxes and Que took to testify on the terms of the agreement and,
the fulfillment of the obligation, petitioner samples thereof. Que, petitioners witness, therefore, we cannot give much credence to
would not have a cause of action for himself confirmed this incident. He testified his testimony. It appeared from the
rescission against respondent as the latter that Tan pointed the boxes to him and that testimony of Que that he did not personally
would not yet be considered in breach of its he got a sample and saw that it was blank. place the order with Tan.
contractual obligation. Ques absolute assertion that the boxes
were not manufactured is, therefore,
Even assuming that a demand had been implausible and suspicious. G.R. No. 171076 August 1, 2012
previously made before filing the present GOLDLOOP PROPERTIES INC.,
case, petitioners claim for reimbursement In fact, we note that respondent’s counsel Petitioner, vs. GOVERNMENT SERVICE
would still fail, as the circumstances would manifested in court, during trial, that his INSURANCE SYSTEM, Respondent
show that respondent was not guilty of client was willing to shoulder expenses for a
breach of contract. representative of the court to visit the plant ISSUE: Goldloop faults the CA in rescinding
and see the boxes. Had it been true that the the MOA and the Addendum, in
The existence of a breach of contract is a boxes were not yet completed, respondent extinguishing the obligations of the parties
factual matter not usually reviewed in a would not have been so bold as to challenge relative thereto, in declaring that each party
petition for review under Rule 45. The Court, the court to conduct an ocular inspection of should bear its own damage and, in
in petitions for review, limits its inquiry only their warehouse. Even in its Comment to discarding the findings of facts and
to questions of law. After all, it is not a trier this petition, respondent prays that conclusions of the RTC.

Case Digests for Cases under Articles 1189-1198 Page | 19


RULING: The Court upholds the rescission Twenty-four Months 15% Section 1.2 That after the project has been
but for a reason different from that upon 21,133,500.00 completed and sold but not later than six (6)
which the CA based its conclusion. Thirty Months 15% 21,133,500.00 months after the 48-month period, in
Thirty-Six Months 10% reference to the schedule of payment in
Reciprocal obligations of the parties under 14,089,000.00 Item 1 above, a calculation of the gross
the MOA. Forty-Two Months 10% sales net of the 8% marketing fee will be
14,089,000.00 made. The GSIS will be entitled (in addition
"Reciprocal obligations are those which Forty-Eight Months 10% to the guaranteed amount in excess of
arise from the same cause, and which 14,089,000.00 P140.89 Million) to 9.86% of the amount in
each party is a debtor and a creditor of 100% ₱ 140,890,000.00 excess of the P1,428.28 Million (the
the other, such that the obligation of one guaranteed revenue for sharing) while
is dependent upon the obligation of the Without prejudice to the right of GSIS to GOLDLOOP will be entitled to the balance
other." Here, the parties’ reciprocal collect the interest provided for in Section of 90.14% in case the gross sales net of the
obligations are embodied in Article I of the 1.3 hereof, the aforesaid periods may be 8% marketing fee does not exceed
MOA, viz: extended in the event that GOLDLOOP P1,428.28 Million, the GSIS will not be
PROPERTIES INC. fails to obtain all the entitled to any additional amount.
ARTICLE I necessary permits and licenses for causes
ABSOLUTE SALE beyond the control of GOLDLOOP or by GSIS has the right to full information as to
reason of force majeure. all matter’s requisite in the determination of
Section 1.1 That GOLDLOOP the gross sales relative to this project that
PROPERTIES INC. will pay the GSIS a It is expressly agreed that extension of time may be in its possession and a full
guaranteed amount of ONE HUNDRED [/] period provided for herein may not be disclosure of any information that it may
FORTY MILLION EIGHT HUNDRED claimed unless GOLDLOOP has, prior to deem material and relevant for the purpose.
NINETY THOUSAND PESOS (₱ the expiration of the contract time and within
140,890,000.00) as payment for the 1,195 fifteen (15) calendar days after the Section 1.3 Payment to GSIS of the
sq. m. portion of the lot on which the second circumstances leading to such claim have amounts provided for in the preceding
tower will stand in accordance with the arisen, delivered an appropriate written paragraphs shall be remitted by
following schedule: notice to the GSIS to enable the latter to GOLDLOOP within the periods stated
have [the] reason for extension investigated. therein without need of prior notice or
Period from signing of the Agreement The GSIS shall, on the basis of the facts and demand; and failure to so pay within said
Percentage of Total Amount circumstances and of the merits or lack of periods shall entitle the GSIS to an interest
Amount to be Remitted merit of the request, grant or deny the of 18% per annum, compounded monthly,
Six Months 10% ₱ 14,089,000.00 request for extension, as it may deem without prejudice to the other rights and
Twelve Months 15% 21,133,500.00 proper. The decision of the GSIS on this remedies of the GSIS under the Agreement
Eighteen Months 15% matter shall be final and binding. Failure to and under applicable laws.
21,133,500.00 provide such notice constitutes a waiver by
x x x GOLDLOOP of any claim for extension.

Case Digests for Cases under Articles 1189-1198 Page | 20


Section 1.4 GSIS warrants that it has title installments, the first installment of which second installment. However, we note that
over the subject property and subject to the would fall due on December 16, 1995 and the Addendum was executed on June 18,
obligation of GOLDLOOP to undertake the the subsequent payments every six months 1996 or two days after the second
conversion of the same to a condominium thereafter until June 16, 1999. The dates of installment payment was supposed to be
property and the identification of the 1,195 payment may be extended if Goldloop fails remitted (June 16, 1996). Hence, by that
sq. m. of vacant lot as a unit thereof capable to obtain all the necessary permits and time, Goldloop’s duty to complete the
of being legally sold by GSIS to licenses for causes beyond its control or by payment for the second installment had
GOLDLOOP, that same is transferable, free reason of force majeure. However, such already arisen. However, the records fail to
from all liens and encumbrances request for extension must be in writing and show that Goldloop, from that time on,
whatsoever. made prior to the expiration of the contract endeavored to at least complete such
and within 15 calendar days after the second installment. Worse, it totally failed to
Section 1.5 After full compliance by circumstances leading to such claim for remit the other subsequent installments.
GOLDLOOP of its obligations under the extension have arisen.
preceding Section, GSIS shall execute [in] The RTC ratiocinated that Goldloop’s failure
its favor, or in favor of its nominee a Deed of Sec. 1.3, on the other hand, provides for the to comply with the said obligation was due
Absolute Sale for the 1,195 sq. m. portion of remittance to GSIS of such payments to the non-issuance of permits. According to
the subject property.47 (Emphasis without need of demand as well as for the it, Goldloop experienced financial difficulty
supplied.) consequence of nonpayment. when the construction did not push thru
since it had to return the deposits, some with
Clearly, Goldloop’s obligation is to pay Admittedly, Goldloop failed to pay the first interest, of would-be buyers and had
for the portion of the property on which installment on time; hence, the parties already paid the commission of brokers and
the second tower shall stand and to stipulated in the Addendum that Goldloop agents of the condominium units, and these
construct and develop thereon a shall advance the payment for expense amounted to millions of pesos. Hence, its
condominium building. On the other items which were for GSIS’s account. The failure to pay was justified.
hand, GSIS is obliged to deliver to money advanced shall then be credited as
Goldloop the property free from all liens full payment of the first installment and the While the Court is inclined to agree with the
and encumbrances and to execute a excess therefrom, as partial payment of the RTC that the non-issuance of permits
deed of absolute sale in Goldloop’s second. By way of said expense items, indeed affected Goldloop’s ability to pay, it
favor. Goldloop claimed to have already advanced cannot, however, ignore the fact that
in favor of GSIS the sum of ₱ Goldloop itself failed to avail of the
Goldloop failed to complete its payment of 24,824,683.00.48 protection granted to it by the MOA in case
the guaranteed amount in the manner of failure to obtain the necessary permits
prescribed in the contract. Assuming said figure is correct for purposes and licenses. Under the circumstances,
of this discussion, the same only covers the Goldloop could have applied for an
Under Sec. 1.1 of the MOA, Goldloop full payment of the first installment which is extension within which to pay the
undertook to pay GSIS the guaranteed P14,089,000.00 and the excess therefrom, installments of the guaranteed amount as
amount of P140,890,000.00, in eight the partial payment for the P21,133,500.00 clearly provided for under the second and

Case Digests for Cases under Articles 1189-1198 Page | 21


third paragraphs of said Sec. 1.1. Yet again, parties much leeway and considers their rescind the MOA in the earlier quoted Sec.
the records are bereft of any showing that it agreement to be the law between them. This 2.4 and hereinafter reproduced:
ever availed of such extension. is because ‘courts cannot follow one every
step of his life and extricate him from bad Section 2.4. Should GOLDLOOP fail to start
From the above, it is clear that said section bargains x x x relieve him from one-sided the construction works within the thirty (30)
did not extend the four-year period within contracts, or annul the effects of foolish working days from date all relevant permits
which to pay the guaranteed amount. In fact, acts.’ The courts are obliged to give and licenses from concerned agencies are
no mention was made regarding this. What effect to the agreement and enforce the obtained, or within six (6) months from the
was extended was the period within which contract to the letter. date of the execution of this Agreement,
Goldloop should have started the whichever is earlier, or at any given time
construction, which was changed from six Here, as the parties voluntarily and freely abandon the same or otherwise commit any
months from the date of the execution of the executed the MOA and the Addendum, the breach of their obligations and commitments
MOA to six months from the date of terms contained therein are the law between under this Agreement, this agreement shall
execution of the Addendum. This is very them. Hence, Goldloop should have be deemed terminated and cancelled
plain from the said provision. completed its payment of the guaranteed without need of judicial action by giving thirty
amount in the manner prescribed by the (30) days written notice to that effect to
Be that as it may, it would be too late in the contract. When it could not do so as a GOLDLOOP who hereby agrees to abide by
day for Goldloop to request for an extension. consequence of the non-issuance of the decision of the GSIS. x x x
As may be recalled, such request must be permits, it should have asked for an
made not only prior to the expiration of the extension within which to pay the same. Under the above-quoted provision, one
contract but also within 15 calendar days of the grounds under which GSIS may
after the event leading to such claim for However, since Goldloop neither validly rescind the MOA is if at any given
extension has arisen. And since the problem completed the payment nor sought for time, Goldloop abandons the
with the non-issuance of permits had long an extension, it is considered to have construction or otherwise commit any
arisen during that time, Goldloop cannot breached its commitment and obligation breach of its obligations and
anymore avail of the extension even if by under Sec. 1.1 of the MOA. commitments thereunder.
then the contract has not yet expired.
GSIS rescinded the contract pursuant to The February 23, 2000 notice clearly
At this point, it bears to stress that: its right to rescind under the relevant specified that GSIS is rescinding the
provisions of the MOA. contract for failure of Goldloop to pay the
It is basic that a contract is the law guaranteed amount of P140,890,000.00
between the parties, and the stipulations Concededly, parties may validly stipulate under Sec. 1.1 of the MOA.
therein – provided that they are not the unilateral rescission of a contract."
contrary to law, morals, good customs, This falls under the said ground, it being a
public order or public policy – shall be Such is the case here since the parties breach of an obligation and commitment
binding as between the parties. In conferred upon GSIS the right to unilaterally under the said agreement. Because of said
contractual relations, the law allows the breach, Sec. 1.3 of the MOA which provides

Case Digests for Cases under Articles 1189-1198 Page | 22


for the consequence of the nonpayment What is plain is that the property was by then Goldloop, the latter had already committed
thereof should be read in relation to Sec. not free from burden since real estate taxes a breach of its own obligation.
2.4. were imposed upon it and these taxes As to when GSIS actually committed its
remained unpaid. There was, therefore, on breach of failing to deliver the property free
Under Sec. 1.3, Goldloop’s failure to pay the part of GSIS, a failure to comply with from any burden, the same is a different
the guaranteed amount within the its obligation to deliver the property free matter which will be discussed later.
periods provided for in Sec. 1.1 of the from burden.
MOA shall entitle GSIS to interest, without In view of the rescission, mutual
prejudice to its other rights and remedies This is not to say, however, that Goldloop’s restitution is required.
under the agreement and applicable laws. obligation to pay the guaranteed amount, as
This right referred to is the right of rescission discussed above, did not arise considering As correctly observed by the RTC, the
under Sec. 2.4 authorizing GSIS to exercise that GSIS could not comply with its rescissory action taken by GSIS is pursuant
the same upon Goldloop’s breach of any of concurrent obligation to deliver the property to Article 119157 of the Civil Code. In cases
its obligations and commitments. Clearly free from burden. It is well to note that even involving rescission under the said
therefore, when GSIS rescinded the MOA before Goldloop became aware of GSIS’s provision, mutual restitution is required.
and the Addendum, it merely exercised its supposed tax liability with the City of
right to rescind under Sec. 2.4 in relation to Pasig through the latter’s October 8, 1997 The parties should be brought back to their
Sec. 1.3 of the MOA. letter, Goldloop was already in default in original position prior to the inception of the
its payment of the guaranteed amount. contract. "Accordingly, when a decree of
However, GSIS is not entirely faultless rescission is handed down, it is the duty of
since it likewise failed in its obligation to As can be recalled and again under the the court to require both parties to surrender
deliver the property free from burden. assumption that Goldloop advanced that which they have respectively received
P24,824,683.00 on behalf of GSIS which and to place each other as far as practicable
GSIS is, however, not entirely faultless. It amount was credited as full and partial in [their] original situation."60 Pursuant to
also failed to comply with its obligation, payment of the first and second this, Goldloop should return to GSIS the
although it cannot be conclusively installments, the remaining balance for the possession and control of the property
determined when it actually begun as the second installment should have been paid subject of their agreements while GSIS
same only became apparent to Goldloop as early as June 16, 1996. No such payment should reimburse Goldloop whatever
after the execution of the MOA and the was, however, made. The same thing is true amount it had received from the latter by
Addendum. This was when the City of Pasig with respect to the third and fourth reason of the MOA and the Addendum.
formally notified GSIS that it was holding in installments which respectively became due
abeyance any action on the latter’s on December 16, 1996 and June 16, 1997. Here, out of the total amount of expenses
application for building permits due to its Clearly, Goldloop had already defaulted in which Goldloop claims to have incurred for
outstanding real estate taxes in the amount its payments even before it became aware the project, it appears that the only sum it
of P54 million. The fact that GSIS disputes of GSIS’s tax issues. In short, even before paid to GSIS was that amount it expended
such tax liability because of its firm stand such failure of GSIS became apparent to by way of change order of expense items
that it was tax exempt is beside the point. supposed to be for GSIS’s account and,

Case Digests for Cases under Articles 1189-1198 Page | 23


which under the Addendum was to be found in the premises of the subject thereto, the parties’ respective claims for
credited as full payment and partial payment property. damages are thus deemed extinguished
of the first and second installments of the and each of them shall bear its own
guaranteed amount, respectively. The Damages damage.
figure, however, remains disputed. Goldloop
alleges that the same amounts to As discussed, both parties failed to comply
P24,824,683.00. Yet, there is nothing in the with their respective obligations under their G.R. No. 201167 February 27, 2013
records to support the same. Said amount agreements. Hence, relevant is the GOTESCO PROPERTIES, INC., JOSE C.
was not clearly specified in Goldloop’s provision of Article 1192 of the Civil GO, EVELYN GO, LOURDES G. ORTIGA,
Consolidated Financial Statements for Code which reads: GEORGE GO, and VICENTE GO,
years 1995 to 2000 and Auditor’s Report. Petitioners, vs. SPOUSES EUGENIO and
What is in the records is a mere self-serving Art. 1192. In case both parties have ANGELINA FAJARDO, Respondents
list of expenses that it submitted and which committed a breach of the obligation, the
indicates the said figure as liability of the first infractor shall be RULING: The petition is partly meritorious.
"Expenses/Charges on Change Orders". equitably tempered by the courts. If it
GSIS, on the other hand, asserts that the cannot be determined which of the parties A. Spouses Fajardo’s right to rescind
expense items for its account, per Annex "C" first violated the contract, the same shall be
of the Addendum, is only ₱ 21,225,521.08 deemed extinguished, and each shall bear It is settled that in a contract to sell, the
and provided that the works for which the his own damages. seller's obligation to deliver the
items were supposed to be used, that is, the corresponding certificates of title is
relocation of the powerhouse and cistern In this case, it cannot be determined with simultaneous and reciprocal to the
tank, were indeed completed. Unfortunately, certainty which between the parties is the buyer's full payment of the purchase price.
said Annex "C" is likewise not part of the first infractor. It could be GSIS because of
records of this case and GSIS merely the high probability that even before the In this relation, Section 25 of PD 957, which
quoted the relevant portion of the same in its execution of the agreements, real property regulates the subject transaction, imposes
Answer. Be that as it may, Zapanta testified taxes were already imposed and unpaid on the subdivision owner or developer the
that the installation of the cistern tank was such that when GSIS applied for building obligation to cause the transfer of the
already 100% complete,63 although there permits, the tax liability was already in the corresponding certificate of title to the buyer
was no mention regarding the status of the substantial amount of P54 million. It was just upon full payment, to wit:
powerhouse. In view of this, the Court can that GSIS could not have been mindful of
only consider the sum spent with respect to the same because of its stand that it is tax Sec. 25. Issuance of Title. The owner or
the completed installation of the cistern tank exempt. But as this cannot be developer shall deliver the title of the lot or
which the GSIS admitted in its Answer as conclusively presumed, there exists an unit to the buyer upon full payment of the lot
amounting to ₱ 4,122,133.19.64 Aside from uncertainty as to which between the or unit. No fee, except those required for the
the said amount, GSIS must also return to failure to comply on the part of each registration of the deed of sale in the
Goldloop all equipment, machineries and party came first; hence, the last portion Registry of Deeds, shall be collected for the
other properties of the latter which may be of Article 1192 finds application. Pursuant issuance of such title. In the event a

Case Digests for Cases under Articles 1189-1198 Page | 24


mortgage over the lot or unit is outstanding Exchange executed between it and Andres Moreover, despite petitioners’ allegation
at the time of the issuance of the title to the Pacheco (Andres), the former registered that the claim of BSP had been settled, there
buyer, the owner or developer shall redeem owner of the property. GPI was issued TCT appears to be no cancellation of the
the mortgage or the corresponding portion No. 244220 on March 16, 1992 but the same annotations in GPI’s favor. Clearly, the long
thereof within six months from such did not bear any technical description. delay in the performance of GPI's obligation
issuance in order that the title over any fully However, no plausible explanation was from date of demand on September 16,
paid lot or unit may be secured and advanced by the petitioners as to why the 2002 was unreasonable and unjustified. It
delivered to the buyer in accordance petition for inscription (docketed as LRC cannot therefore be denied that GPI
herewith. Case No. 4211) dated January 6, 2000,25 substantially breached its contract to
was filed only after almost eight (8) years sell with Spouses Fajardo which thereby
In the present case, Sps. Fajardo claim from the acquisition of the subject property. accords the latter the right to rescind the
that GPI breached the contract due to its same pursuant to Article 1191 of the
failure to execute the deed of sale and to Neither did petitioners sufficiently explain Code, viz:
deliver the title and possession over the why GPI took no positive action to cause the
subject lot, notwithstanding the full immediate filing of a new petition for ART. 1191. The power to rescind
payment of the purchase price made by inscription within a reasonable time from obligations is implied in reciprocal ones, in
Sps. Fajardo on January 17, 2000 as well notice of the July 15, 2003 CA Decision case one of the obligors should not comply
as the latter’s demand for GPI to comply which dismissed GPI’s earlier petition based with what is incumbent upon him.
with the aforementioned obligations per the on technical defects, this notwithstanding
letter dated September 16, 2002. For its Sps. Fajardo's full payment of the The injured party may choose between the
part, petitioners proffer that GPI could purchase price and prior demand for fulfillment and the rescission of the
not have committed any breach of delivery of title. GPI filed the petition before obligation, with the payment of damages in
contract considering that its purported the RTC-Caloocan, Branch 122 (docketed either case. He may also seek rescission,
non-compliance was largely impelled by as LRC Case No. C-5026) only on even after he has chosen fulfillment, if the
circumstances beyond its control i.e., the November 23, 2006 following receipt of the latter should become impossible.
legal proceedings concerning the letter dated February 10, 2006 and the filing
subdivision of the property into individual of the complaint on May 3, 2006, The court shall decree the rescission
lots. Hence, absent any substantial breach, alternatively seeking refund of payments. claimed, unless there be just cause
Sps. Fajardo had no right to rescind the While the court a quo decided the latter authorizing the fixing of a period.
contract. petition for inscription in its favor, there is no
showing that the same had attained finality This is understood to be without prejudice to
The Court does not find merit in petitioners’ or that the approved technical description the rights of third persons who have
contention. had in fact been annotated on TCT No. acquired the thing, in accordance with
244220, or even that the subdivision plan articles 1385 and 1388 and the Mortgage
A perusal of the records shows that GPI had already been approved. Law.
acquired the subject property on March 10,
1992 through a Deed of Partition and B. Effects of rescission

Case Digests for Cases under Articles 1189-1198 Page | 25


At this juncture, it is noteworthy to point out are legally in the possession of third persons Indeed, there would be unjust enrichment if
that rescission does not merely terminate who did not act in bad faith. respondents Solid Homes, Inc. & Purita
the contract and release the parties from Soliven are made to pay only the purchase
further obligations to each other, but In this case, indemnity for damages may be price plus interest. It is definite that the value
abrogates the contract from its inception demanded from the person causing the of the subject property already escalated
and restores the parties to their original loss. after almost two decades from the time the
positions as if no contract has been petitioner paid for it. Equity and justice
made. Consequently, mutual restitution, This Court has consistently ruled that this dictate that the injured party should be paid
which entails the return of the benefits that provision applies to rescission under Article the market value of the lot, otherwise,
each party may have received as a result of 1191: respondents Solid Homes, Inc. & Purita
the contract, is thus required. To be sure, it Soliven would enrich themselves at the
has been settled that the effects of Since Article 1385 of the Civil Code expense of herein lot owners when they sell
rescission as provided for in Article 1385 of expressly and clearly states that "rescission the same lot at the present market value.
the Code are equally applicable to cases creates the obligation to return the things Surely, such a situation should not be
under Article 1191, to wit: which were the object of the contract, countenanced for to do so would be contrary
together with their fruits, and the price with to reason and therefore, unconscionable.
xxxx its interest," the Court finds no justification to Over time, courts have recognized with
sustain petitioners’ position that said Article almost pedantic adherence that what is
Mutual restitution is required in cases 1385 does not apply to rescission under inconvenient or contrary to reason is not
involving rescission under Article 1191. This Article 1191. x x x allowed in law.
means bringing the parties back to their
original status prior to the inception of the In this light, it cannot be denied that only GPI On this score, it is apt to mention that it is
contract. Article 1385 of the Civil Code benefited from the contract, having received the intent of PD 957 to protect the buyer
provides, thus: full payment of the contract price plus against unscrupulous developers, operators
interests as early as January 17, 2000, and/or sellers who reneged on their
ART. 1385. Rescission creates the while Spouses Fajardo remained obligations. Thus, in order to achieve this
obligation to return the things which were prejudiced by the persisting non-delivery purpose, equity and justice dictate that the
the object of the contract, together with their of the subject lot despite full payment. As injured party should be afforded full
fruits, and the price with its interest; a necessary consequence, considering the recompense and as such, be allowed to
consequently, it can be carried out only propriety of the rescission as earlier recover the prevailing market value of the
when he who demands rescission can discussed, Sps. Fajardo must be able to undelivered lot which had been fully paid for.
return whatever he may be obligated to recover the price of the property pegged at
restore. its prevailing market value consistent with
the Court’s pronouncement in Solid Homes, G.R. No. 81158 May 22, 1992
Neither shall rescission take place when the viz: OSCAR A. JACINTO and LIBRADA
things which are the object of the contract FRANCO-JACINTO, petitioners, vs.
ROGELIO KAPARAZ, RAUL KAPARAZ

Case Digests for Cases under Articles 1189-1198 Page | 26


and ROSE MARIET KAPARAZ, . . . The upshot of all these stipulations is at the time agreed upon the rescission of the
respondents that in seeking the ouster of Maritime for contract shall of right take place, the vendee
failure to pay the price as agreed upon, may pay, even after the expiration of the
RULING: The petition is impressed with Myers was not rescinding (or more properly, period, as long as no demand for rescission
merit. resolving) the contract, but precisely of the contract has been made upon him
enforcing it according to its express terms. either judicially or by a notarial act. After the
Vital to the resolution of the controversy is In its suit Myers was not seeking restitution demand, the court may not grant him a new
the determination of the true nature of the to it of the ownership of the thing sold (since term.
questioned agreement. Is it a contract of it was never disposed of), such restoration
sale or a contract to sell? being the logical consequence of the This Article applies to instances where
fulfillment of a resolutory condition, no stipulation for automatic rescission is
The two are not, of course, the same. express or implied (Article 1190); neither made because it says "even though".
was it seeking a declaration that its
In the latter case, ownership is retained by obligation to sell was extinguished. What it The agreement in the instant case has all
the seller and is not to pass until full sought was a judicial declaration that the earmarks of a contract of sale. The
payment of the price. Such payment is a because the suspensive condition (full and possession of the portion sold was
positive suspensive condition the failure punctual payment) had not been fulfilled, its immediately delivered to the petitioners.
of which is not a breach, casual or serious, obligation to sell to Maritime never arose or They were granted the right to enjoy all the
but simply an event that prevents the never became effective and, therefore, it improvements therein effective from the
obligation of the vendor to convey title (Myers) was entitled to repossess the date of the execution of the agreement.
from acquiring binding force. property object of the contract, Private respondents unqualifiedly bound
possession being a mere incident to its themselves to execute the final deed of sale
In such a situation, to argue that there was right of ownership. "as soon as the settlement or partition of the
only a casual breach is to proceed from the estate of the deceased Narcisa R. Kaparaz
assumption that the contract is one of On the other hand, since in a contract of shall have been consummated and effected,
absolute sale, where non-payment is a sale, the non-payment of the price is a but not later than March 31, 1967" and only
resolutory question. Otherwise stated, as resolutory condition, the remedy of the upon full payment of the unpaid portion of
capsulized in Luzon Brokerage Co., Inc. vs. seller under Article 1191 of the Civil Code the purchase price. The private
Maritime Building Co., Inc., "there can be is to exact fulfillment or to rescind the respondents did not reserve unto
no rescission or resolution of an contract. In respect, however, to the sale of themselves the ownership of the
obligation as yet non-existent, because immovable property, this Article must be property until full payment of the unpaid
the suspensive condition did not read together with Article 1592 of the same balance of P1,000.00. Finally, there is no
happen." Expanding on this point, this Code: stipulation giving the private
Court, in said case, made the following respondents the right to unilaterally
disquisitions: Art. 1592. In the sale of immovable rescind the contract the moment the
property, even though it may have been vendee fails to pay within a fixed period.
stipulated that upon failure to pay the price

Case Digests for Cases under Articles 1189-1198 Page | 27


In reality, the agreement was an absolute notarial act before the filing of the complaint purchase price to be made to the DBP
sale which allowed the petitioners to pay in Civil Case No. 586. It is only in their should be applied exclusively to the
the remaining balance of the purchase Answer that they belatedly raised the agricultural loan indicated in the exordium of
price in installment. We agree with the defense of resolution of the contract the agreement. The loan was mentioned
submission of petitioners that Dignos vs. pursuant to Article 1191 by reason of only to lay the basis for private respondents'
Court of Appeals applies in this case. In said petitioners' breach of their obligation. need for the downpayment. In the second
case, this Court stated: place, to allow private respondents to reject
Even if the general law on resolution, Article the payment of P400.00, plus the excess of
Thus, it has been held that a deed of sale 1191 of the Civil Code, is to be applied, Our P100.00 after they benefited therefrom,
is absolute in nature although decision would still be for the petitioners. would be unjust.
denominated as a "Deed of Conditional The third paragraph of this Article reads:
Sale" where nowhere in the contract in xxx xxx xxx Then too, at no time before the filing of their
question is a proviso or stipulation to the Answer did private respondents declare
effect that title to the property sold is The Court shall decree the rescission their intention to rescind the agreement, or if
reserved in the vendor until full payment claimed, unless there be just cause they did, communicate such intention to the
of the purchase price, nor is there a authorizing the fixing of a period. petitioners. It was necessary for private
stipulation giving the vendor the right to respondents to have done so. As this Court
unilaterally rescind the contract the moment It is not denied that petitioners made two (2) held in University of the Philippines vs. De
the vendee fails to pay within a fixed period payments in the sums of P200.00 and los Angeles:
(Taguba v. Vda. de Leon, 132 SCRA 722; P300.00 at a time when what remained
Luzon Brokerage Co., Inc. v. Maritime unsettled under the agreement was only Of course, it must be understood that the act
Building Co., Inc., 86 SCRA 305). P400.00. There was then an excess of a party in treating a contract as cancelled
payment of P100.00. These payments were or resolved on account of infractions by the
As stated earlier, in a contract of sale, the made to the DBP which applied them to an other contracting party must be made
remedy of an unpaid seller is either outstanding account of the private known to the other and is always
specific performance or rescission. The respondents. Private respondents neither provisional, being ever subject to scrutiny
latter, with respect to the sale of complained of the delay in these payments and review by the proper court. If the other
immovables, is specifically governed by nor rejected their application to their party denies that rescission is justified, it is
Article 1592 of the Civil Code. account. They were, undoubtedly, benefited free to resort to judicial action in its own
by the application because it either satisfied behalf, and bring the matter to court. Then,
In the case at bar, there was non- their account or correspondingly reduced it. should the court, after due hearing, decide
compliance with the requirements The claim that the account to which it was that the resolution of the contract was not
prescribed in these provisions. It is not applied was not the account stipulated in the warranted, the responsible party will be
controverted that private respondents had agreement is without merit. In the first place, sentenced to damages; in the contrary case,
neither filed an action for specific the agreement fails to disclose an express the resolution will be affirmed, and the
performance nor demanded the rescission agreement that the monthly amortizations consequent indemnity awarded to the party
of the agreement either judicially or by a on the P1,000.00 unpaid balance of the prejudiced.

Case Digests for Cases under Articles 1189-1198 Page | 28


In other words, the party who deems the definite time, is not absolute but admits of MATURITY; TO BE DETERMINED BY THE
contract violated may consider it resolved or qualifications and exceptions. "The general PROPER COURT; FORECLOSURE AND
rescinded, and act accordingly, without rule is that an agreement to extend the time SALE OF SECURITY, PREMATURE. —
previous court action, but it proceeds at its of payment, in order to be valid, must be for Even the pledge which modified the fixed
own risk. For it is only the final judgment of a definite time, although it seems that no period in the original promissory note, did
the corresponding court that will precise date be fixed, it being sufficient that not provide for dates of payment of
conclusively and finally settle whether the the time can be readily determined." (8 C.J. installments, nor of any fixed date of
action taken was or was not correct in law. 425). In case the period of extension is not maturity of the whole amount of
But the law definitely does not require that precise, the provisions of Article 1197 of the indebtedness. Accordingly, the date of
the contracting party who believes itself Civil Code should apply. maturity of the indebtedness should be as
injured must first file suit and wait for a may be determined by the proper court
judgment before taking extrajudicial steps to 2. ID.; AGREEMENT TO EXTEND under Art. 1197 of the Civil Code. Hence,
protect its interest. Otherwise, the party PERIOD OF PAYMENT; CONDITIONS the disputed foreclosure and the
injured by the others' breach will have to AND ARRANGEMENTS CHANGING subsequent sale were premature. The Court
passively sit and watch its damages TERMS OF PAYMENT MAY BE of Appeals noted that no demand for
accumulate during the pendency of the suit INTRODUCED. — There was an agreement payment of the P50,000.00 was made right
until the final judgment of rescission is to extend the payment of the loan, including after it allegedly fell due. It was only on
rendered when the law itself requires that he the first installment thereon which was due March 4, 1958 or 13 days after the execution
should exercise due diligence to minimize on or before July 1957. The pledge of the pledge instrument on February 19,
its own damages (Civil Code, Article 2203). executed as collateral security on February 1958 that PBC presented its demand for
9, 1958 no longer contained the provision on payment to Insular Farms.
an installment of P50,000.00 due on or
G.R. No. L-45656. May 5, 1989 before July 1957. This can mean no other 6. ID.; RIGHT TO REIMBURSEMENT
PACIFIC BANKING CORPORATION and thing than that the time of payment of the FROM THE EMPLOYEE FOR WHAT IS
CHESTER G. BABST, Petitioners, v. THE said installment of P50,000.00 was PAID FOR DAMAGES ATTRIBUTABLE TO
COURT OF APPEALS, JOSEPH C. HART extended. It is settled that bills and notes HIM, NOT MANDATORY. — Article 2181
and ELEANOR HART, Respondents may be varied by subsequent agreement. does not make recovery from the employee
Thus, conditions may be introduced and a mandatory requirement. A right to relief
SYLLABUS: arrangements made changing the terms of shall be recognized only when the party
payment (10 CJS 758). The agreement for concerned asserts it through a proper
1. OBLIGATIONS AND CONTRACTS; extension of the parties is clearly indicated pleading filed in court. In this case, the
RULE THAT AN ORAL AGREEMENT TO and may be inferred from the acts and employer, Pacific Banking Corporation did
EXTEND TIME OF PAYMENT MUST BE declarations of the parties, as testified to in not manifest any claim against Babst by
FOR A DEFINITE TIME TO BE VALID, NOT court. filing a cross-claim before the trial court;
ABSOLUTE. — The rule which states that thus, it cannot make its right automatically
there can be no valid extension of time by 5. OBLIGATIONS AND CONTRACTS; enforceable. Babst was made a party to the
oral agreement unless the extension is for a PLEDGE WITHOUT FIXED DATE OF case upon the complaint of the private

Case Digests for Cases under Articles 1189-1198 Page | 29


respondents in his official capacity as the first installment thereon which was due the extension, considering that this pledge
Executive Vice President of the bank. In the on or before July 1957. As the Court of was the additional collateral required by
absence of a cross-claim against Babst, the Appeals stated: Pacific Banking in addition to the continuing
court has no basis for enforcing a right guarantee of Clarkin.
against him to which his co-defendant may ". . . — and here, this court is rather well
be entitled. convinced that Hart had been given the The presumption of good faith of possession
assurance by the conduct of Babst, provided in Article 527, is only a
RULING: We find for the respondents on Executive Vice President of Pacific Bank, presumption juris tantum. Said presumption
the following grounds. that payment would not as yet be pressed, cannot stand in the light of the evidence to
and under 1197 New Civil Code, the the contrary in the record.
In the case at bar, the parties to the meaning must be that there having been
purported agreement, Hart and Babst, were intended a period to pay — modifying the It was established that there was an
still alive, and both testified in the trial court fixed period in original promissory note, agreement to extend indefinitely the
regarding the purported extension. Their really, the cause of action of Pacific Bank payment of the installment of P50,000.00
testimonies are in fact, quoted in the would have been to ask the Courts for in July 1957 as provided in the promissory
decision of the respondent Court of the fixing of the term;" note. Consequently, Pacific Banking
Appeals. Corporation was precluded from enforcing
The pledge executed as collateral security the payment of the said installment of July
We also note, that the rule which states that on February 9, 1958 no longer contained the 1957, before the expiration of the indefinite
there can be no valid extension of time by provision on an installment of P50,000.00 period of extension, which period had to be
oral agreement unless the extension is for a due on or before July 1957. This can mean fixed by the court as provided in Art. 1197 of
definite time, is not absolute but admits of no other thing than that the time of the Civil Code (10 CJS p. 7611, citing Drake
qualifications and exceptions. payment of the said installment of v. Pueblo Nat. Bank, 96 P. 999, 44 Colo.
P50,000.00 was extended. 49).
"The general rule is that an agreement to
extend the time of payment, in order to be It is settled that bills and notes may be Even the pledge which modified the fixed
valid, must be for a definite time, although varied by subsequent agreement. Thus, period in the original promissory note,
it seems that no precise date be fixed, it conditions may be introduced and did not provide for dates of payment of
being sufficient that the time can be readily arrangements made changing the terms of installments, nor of any fixed date of
determined." payment. The agreement for extension of maturity of the whole amount of
the parties is clearly indicated and may be indebtedness.
In case the period of extension is not inferred from the acts and declarations of
precise, the provisions of Article 1197 of the parties, as testified to in court. Accordingly, the date of maturity of the
the Civil Code should apply. indebtedness should be as may be
The pledge constituted on February 19, determined by the proper court under Art.
In this case, there was an agreement to 1958 on the shares of stocks of Insular 1197 of the Civil Code. Hence, the
extend the payment of the loan, including Farms, Inc. was sufficient consideration for

Case Digests for Cases under Articles 1189-1198 Page | 30


disputed foreclosure and the subsequent Babst also identified an auditor’s report by
sale were premature. Sycip, Gorres and Velayo dated March 17,
1958. The first paragraph of the report
The whole indebtedness was guaranteed by states that the auditors went to inspect
the continuing guaranty of Clarkin, who had Insular Farms pursuant to a request of
a corresponding deposit with Pacific Babst dated March 5, 1958 that is, as found
Banking which guaranty and deposit, Babst by the Court of Appeals just one day after
and Charles Chua, president of Pacific Babst had through his letter of March 4,
Banking, had actual knowledge of. 1958, threatened Insular Farms, Clarkin and
Hart, with the remedies available to Pacific
The Court of Appeals noted that no demand Bank if the whole loan was not paid within
for payment of the P50,000.00 was made 48 hours. This can also mean that the
right after it allegedly fell due. It was only on investigation by the auditing firm was a well
March 4, 1958 or 13 days after the execution conceived subterfuge, when all the while,
of the pledge instrument on February 19, foreclosure was already intended against
1958 that PBC presented its demand for private respondents.
payment to Insular Farms.
On account of the foregoing, the Court of
As found by the Court of Appeals, there was Appeals concluded that the foreclosure was
really no investigation of Insular Farms’ an act of bad faith:
ability to pay the loan after the pledge was
executed but before the demand for "5th — Foregoing cannot but convince this
payment, considering that the latter was Court that the foreclosure was not an act of
made barely two weeks after the execution good faith on the part of the Pacific Banking,
of the pledge. — for it must be bound by the acts or
representations, active or tacit of its agent or
The inconsistency of the petitioner’s its Executive Vice-President Babst, . . . ."
position vis-a-vis the evidence on record
is apparent.

According to Babst, the investigation was


made by Mr. Joseph Tupaz, who rendered
his report (TSN, IX: 6-9, C Babst). The
report, however, as found by the Court of
Appeals, was dated August 28, 1957 way
before the pledge was executed on
February 19, 1958.

Case Digests for Cases under Articles 1189-1198 Page | 31

Potrebbero piacerti anche