Sei sulla pagina 1di 4

RETENTION PONDS S I T E

GREATER DUBLIN STRATEGIC DRAINAGE STUDY -


CONTROL

PRIMARY CONSIDERATIONS BENEFITS

Construction Cost HIGH þWater Quality Control YES


þWater Quantity Control YES
Maintenance Requirements LOW
þAmenity Value YES
Land Take HIGH þHabitat Creation Value YES
þBiological Treatment YES

City West Retention Pond


DESCRIPTION DESIGN

R
etention ponds are permanent SThe original design volume of the pond
General Design Criteria / Features should take into account gradual
water bodies which hold water for SDesign to have a minimum permanent
a couple of weeks allowing sediment accumulation.
pool of 4 x Vt (Wallingford Procedure). SThe average depth of water in the
particles to settle and biological SDesign to hold water for 14 - 21 days.
treatment. Retention ponds are permanent pool should be between 1m
STypically ponds are comprised of a and 2m, with a limit of 2.5m to prevent
regional controls which serve large sediment forebay, a permanent pool of
scale developments, such as industrial anaerobic conditions. This should also
open water and an outlet structure. be deep enough to minimise algal
estates and major housing SWetland and aquatic vegetation are
developments. They are one of the blooms and re-suspension of previously
planted mainly around a shallow settled materials.
most effective storm water management benched edge. SSome flood storage is also available

ENVIRONMENTAL MANAGEMENT POLICY


installations for removing storm water SA minimum contributing area of 5 ha is
pollutants. Sedimentation of solids above the permanent pool which is
desirable. limited to 2m above the normal water
occurs in the open water and wetland SThe inlet should be designed to
bench. Nutrients are removed in the level to prevent inundation of the
minimise the velocity of flow entering vegetation.
open water by photosynthesis and by the system. The inlet and outlet should
bacteria attached to wetland plants. SWet ponds need a sufficient drainage
be remote from each other. The inlet area to maintain the permanent pool.
Since retention ponds have the should not be fully submerged at normal
capability of removing soluble SDuring large flood events it may be
pool elevation. necessary to divert runoff round the
pollutants, they are suitable for sites SPre-treatment is achieved in the
where nutrient loadings are expected to pond.
sediment forebay: a small pool (typically SThe water should be retained in the
be high. These systems also provide about 10% of the volume of the
flood control, when designed to allow pond for 14 to 21 days during the
permanent pool). Coarse particles wettest months to allow for biological
fluctuations in water level above the should be trapped in the forebay.
permanent pool of water. treatment and allow settlement of fine
SOpen water in retention ponds should solids.
occupy 50-75% of the permanent pool SA liner may be required to retain a
surface area. The remaining area permanent pool where soils are
should be used to create a shallow permeable.
bench about 3m wide (CIRIA, 2000). SIn pollution hotspots, such as industrial
SThis shallow bench should be planted estates, ponds should be lined to
with appropriate native aquatic prevent groundwater contamination. A
vegetation which will: liner should also be used where
- enhance the removal of soluble groundwater levels are high or require
nutrients and sediment trapping, protection, to prevent interaction with
- p revent sediment re-suspension, the polluted run-off.
-provide a wildlife habitat, SThe design should incorporate
-act as a safety bench to prevent features to lengthen the flow path
children reaching deeper water, through the pond, such as underwater
-help to conceal any litter or debris berms.
which may accumulate SLength to width ratio should be 5:1
-help stabilise the soil at the edge of preferably, with a minimum of 3:1
the pond, preventing erosion, (Horner et al, 1994).
-enhance the aesthetic value of the SThe use of multiple ponds in sequence
facility, helping to make an asset improves treatment.
to the community. SFencing of ponds is generally not
SSide slopes should be limited to 1 in 4. desirable but may be required in some
SFlatter slopes also help to prevent situations.
erosion of banks, make routine bank SSigns may be posted during cold
Roadside Retention Pond, Scotland maintenance tasks easier and provide periods, to warn of the dangers of ice.
for public safety.
MORE OVERLEAF - 1 of 4
RETENTION PONDS S I T E
CONTROL
DESIGN DESIGN
Habitat Enhancement Volumetric Design Criteria 5) Rainfall Characteristics of the Area:
SIreland has been analysed for
SLocate ponds near (but not directly The volume required is defined by a
hydrological characteristics. These have
connected to) other wetland areas e.g. matrix of parameters which are
been processed to enable appropriate
(natural ponds, lakes, floodplains) to summarised as:
design storm events to be produced for
allow plants & animals to colonise. 1) Depth / Area Storage Relationship:
any location, duration
SCreate habitat mosaics with sub-basins SThis is largely dictated by topography
and return period. This is based on the
of permanent, temporary and semi- and outfall levels. Volumetric
Flood Studies Report undertaken in the
permanent ponds, varied in size (from allowances for vegetation of up to
1970’s.
1ha down to 1m2) and depth (1m down 25% should be provided.
to 5cm). 6)Level of Service:
2) Head / Discharge Relationship:
SMaximise the area of shallow and SDesign should be for a range of return
SThe pond/basin should be designed to
seasonally inundated ground periods (1 to 100 years). It is unlikely
a maximum discharge rate, achieved
dominated by emergent plants which that one structure will serve the needs of
when the structure is full but
are generally more tolerant of pollutants the various criteria. Temporary flooding
consideration must be given to outfall
than submerged aquatic plants. of car parks and public space areas are
conditions, e.g. receiving water levels.
SCreate undulating 'hummocky likely to be acceptable on
3) Throttle Rate:
margins' in shallow water, which mimic occasions. The hydraulic implications
SThrottle sizes are generally a minimum
the natural physical diversity of semi- for loss of volume due to sediment or
of 150mm. For smaller developments,
natural habitats. Avoid smooth finished vegetation should also be considered.
the volumetric requirement is likely to be
surfaces, as they provide less physical 7) Safety:
achieved by other drainage components
diversity for plants & animals. SThis should be considered for all stages
such as lined or unlined permeable
SEncourage development of open, of construction, operation, maintenance
pavement car parks or soak-aways.
lightly shaded and densely shaded areas and decommissioning.
4) Effective Contributing Area:
or pools. SIn the case of extreme events an
SThis is the paved and pervious
SEncourage a mosaic of marginal plants appropriate design criteria should be
catchment surfaces which contribute
(rather than single species stands). applied to protect against overtopping.
runoff after various losses.
SUse native water plants, trees, shrubs SLarge storage areas may have to
The relationship between contributing
or grass species. consider not only the freeboard and
area and throttle rate will define the
reinforced spillway but the fetch for wave
critical duration of the design rainfall
development.
events. Events will be longer for tighter
SVery large storage reservoirs would
throttle rates and storage volumes
have have regard to dams regulations
Embankment
and risk of failure should be examined in
Submerged all cases.
Earth Berm Aquatic Bench
SBlockage of the pass forward structure
must be catered for and an alternative
method of drawing down the storage
Weir Wall system must be provided.
Outlet
Inflow Structure
Forebay
Permanent Pool
Outfall

Maintenance Embankment
Access Road Safety Bench
PLAN VIEW Embankment
Hooded
Low Flow
Orifice Weir Wall
Extreme Flood Control
Outlet
Overbank Flood Control Structure
Channel Protection
Water Quality Stable Outfall
Inflow

Wet Pool
Ground
Water Table
Forebay Retention Pond, Scotland
PROFILE
FROM PREVIOUS & CONTINUES - 2 of 4
S I T E
RETENTION PONDS

GREATER DUBLIN STRATEGIC DRAINAGE STUDY -


CONTROL
POLLUTANT REMOVAL ZRegular mowing can be carried out INTERNATIONAL EXPERIENCE
The effectiveness of wet ponds has been around the margins. However, this
estimated through a wide range of adds to the maintenance costs, reduces In Scotland, monitoring of retention
research, producing variable results. the habitat potential and is not always ponds has highlighted the importance
However, it is believed that proper required. of bank stabilisation at an early stage.
design and maintenance may help to ZMaintenance costs may be higher in Erosion, due to wave action has been a
improve performance. Research the first few years after construction, problem in systems which are not
reported by Schueler suggests the until the vegetation becomes adequately sheltered from the
following typical removal rates (USEPA established. prevailing westerly wind. In
Factsheets): ZTypically sediment may have to be Dunfermline, retention ponds have
removed from the forebay once every provided an added amenity to the local
Pollutant Removal (%) 10 years or after 50% of total forebay area. Recently, educational initiatives
capacity has been lost. have been set up to encourage school
ZAdequate maintenance access should children to make supervised visits to the
Total Suspended Solids 67 be provided. ponds and assist with planting.
ZSediment should be removed from Competitions have been held in the
the pond, as required, when the pool local press for local children to invent
Total Phosphorous 48 volume has become reduced names for the ponds. Display boards
significantly or the pond becomes are to be positioned around the ponds
eutrophic. US EPA factsheets suggest to explain their purpose.
Total Nitrogen 31 this is required once every 20 years.
Retention ponds have also been used to

ENVIRONMENTAL MANAGEMENT POLICY


COST CONSIDERATIONS control runoff from a motorway service
Nitrate 24
station on the M40 in Oxford, England.
SPonds are long-life facilities (typically
The drainage of the site is based on the
longer than 20 years).
treatment train concept. Permeable
Metals 24-73 SThe construction costs associated with
paving and filter drains have been used
these facilities vary considerably.
as source control measures. Regional
SIn addition to the water resource
facilities consist of retention ponds and
Bacteria 65 protection benefits of wet ponds,
a stormwater wetland.
Details of other studies are available evidence suggests they may provide an
from the (US) National Stormwater Best economic benefit by increasing property
Management Practices Database. values, where they add to the overall
(www.database.org) amenity. This is supported by experience
in the USA and Australia.

OTHER CONSIDERATIONS
SExisting wetlands or natural ponds
should not be used as SuDS facilities.

Retention Pond, Scotland


A Retention Pond in Scotland
MAINTENANCE CONSIDERATIONS
ZReadily visible facilities tend to receive
more and better maintenance than
Barrier Planting in a Retention Pond in Scotland
those less visible, more remote
locations. Aquatic Zone: Reed Zone:
ZInlets and outlets should be inspected Includes floating The reeds,which grow
plants and totally densely, act as a barrier
quarterly or after large storms for submerged plants while supporting wildlife

evidence of clogging or accumulation of


debris.
ZOther potential problems that should
be checked include subsidence,
nuisance plants, erosion and litter Gentle slope promotes safety
accumulation. and help wildlife

CONTINUES - 3 of 4
RETENTION PONDS S I T E
CONTROL
INTERNATIONAL EXPERIENCE ADVANTAGES LIMITATIONS
U.K. ýSafety concerns.
A suite of SuDS options has also been þCapable of removing solid and
used at the Hopwood motorway service soluble pollutants.
ýRequires relatively large land area
station on the M42. SuDS measures therefore may not be suitable for high
þProvides biological treatment of run-
include permeable paving and retention density urban areas.
off.
ponds.
þSuitable for sites where nutrient ýRequires contributing area greater
loadings are expected to be high. than 5 hectares, typically.

þCan be used in residential, ýLiners may be required when soil


commercial and industrial sites. conditions are permeable or where
groundwater levels are high.
þCan provide flood control.

þHabitat creation.

þProvision of an amenity to local


residents.
M42 Motorway Services
þEducational opportunity.

þCan increase property values when


planned and sited properly.

Construction Stage...

Operational Stage

Retention Ponds, Construction Stage, M74, Scotland

Retention Ponds, Operation Stage, M74, Scotland

FROM PREVIOUS - 4 of 4

Potrebbero piacerti anche