4 PCC
No of
Type L W H Voloumn
Footing
F1 4 1.8 1.6 0.1 1.15
F2 4 2.3 2.1 0.1 1.93
F3 2 2.7 2.6 0.1 1.40
F4 2 3.2 2.9 0.1 1.86
F5 1 3.4 3.1 0.1 1.05
F6 1 3.5 3 0.1 1.05
F7 2 3.2 2.9 0.1 1.86
F8 1 1.2 1.2 0.1 0.14
10.45
5 RCC
No of
Type L W H Voloumn
Footing
F1 4 1.6 1.4 0.3 2.69
F2 4 2.1 1.9 0.5 7.98
F3 2 2.5 2.4 0.6 7.20
F4 2 3 2.7 0.6 9.72
F5 1 3.2 2.9 0.6 5.57
F6 1 3.3 2.8 0.4 3.70
F7 2 3 2.7 0.4 6.48
F8 1 1 1 0.3 0.30
43.63
6 Neck Column
No of
Type L W H Voloumn
Footing
C1 6 0.4 0.2 1.95 0.94
C2 6 0.6 0.2 1.75 1.26
C3 3 1.2 0.2 1.85 1.33
C4 2 0.07 1.95 0.27
3.80
7 Backfilling
Volumn
Villa 403.44 57.88 345.56
BOQ
Activities Unit Qty Rate Amount
Excavation m3 403.44 20 8,068.80
Disposal m3 403.44 25 10,086.00
Compaction m2 268.96 10 2,689.60
Road Base m3 67.24 150 10,086.00
PCC m3 10.45 250 2,612.00
RCC m3 43.63 1200 52,358.40
Neckcolumn m3 3.80 1200 4,561.20
Backfilling m3 345.56 25 8,639.00
Direct Cost 99,101.00
1.Steel Mess calculation for villa
Total Total
No of No of Total No One steel Length
Type of Weight
Steel in y Steel in X Length Steel of Steel
F1
F2
F3
F4
F5
F6
F7
F8