Sei sulla pagina 1di 3

MECHANICAL – DUCTWORKS

PROJECT:

CHECKLIST FOR: MECHANICAL – DUCTWORKS

Location of Inspection: Date:

Installation Basis :
1. Post Award :

a. Shop Drawings: b. Submittals (Samples):

c. Mock Up: d. Location of Mock Up:

2. Fabrication Inspection (where applicable):

a. Fabrication (Fill in where applicable):

Item Acceptance Criteria Findings A/N*


Sheet Metal
Gauge
Reinforcement
Duct Joint
Sealant & Tapes

* A = Approve; N = Non Compliance (Corrective Action Required)

b. Test (where applicable):

Type of Test Acceptance Criteria Findings** A/N*

* A = Approve; N = Non Compliance (Corrective Action Required)


** Attach Test Report where applicable

c. Delivery:

Delivery Order
(Specify Delivery
Handling / Storage Findings
Equipment/Material Date
Delivered)
Duct

1/4
MECHANICAL – DUCTWORKS

3. Installation:

As per approved shop


a. Work Statement: b. Date Submitted:
drawing

** Fill in Where Applicable

Items Acceptance Criteria** Findings** A/N*


Seals
Penetrations
Joints
Metal ductworks
Labeling
Bracket and Support

* A = Approve; N = Non Compliance (Corrective Action Required)

2/4
MECHANICAL – DUCTWORKS

4. Post Installation:

Item Acceptance Criteria** Findings** A/N*


Leveling
Visual
Ends/ openings

* A = Approve; N = Non Compliance (Corrective Action Required)

5. General:

Item Site Observations General Comments AR / Date

Inspected By:

______________________ ______________________ ______________________


Name Signature Date