PROJECT - CONSTRUCTION, COMPLETION MAINTENANCE OF SHEIK TALAL VILLA (REV.

-2)

CLIENT - MR. SHEIK TALAL AL MAMARI

CONSULTANT - ARAB ENGINEERING BUREAU

CONTRACTOR - AL ARKAN CONSTRUCTION LLC

Activity ID Activity Name Original BL Project BL Project Actual Start Actual Finish Activity2018
% 2019
Duration Start Finish Complete Q3 Q4 Q1 Q2 Q3 Q4
CONSTRUCTION, COMPLETION & MAINTENANCE OF SHEIK TALAL VILLA (REV.-2) 316 06-Jun-18 19-Jun-19 06-Jun-18 09-Jun-19, CONSTRUCTION, COMPLETION
MOBILIZATION 14 06-Jun-18 21-Jun-18 06-Jun-18 21-Jun-18 21-Jun-18 A, MOBILIZATION
MOB1000 MOBILIZATION & REMOVAL OF MATERIAL 14 06-Jun-18 21-Jun-18 06-Jun-18 21-Jun-18 100%21-Jun-18 A
DISMANTLING & PROTECTION 38 03-Jul-18 15-Aug-18 03-Jul-18 15-Aug-18 15-Aug-18 A, DISMANTLING & PROTECTION
A1000 DISMANTLING OF INSIDE FLOOR TILES & SHIFT TO BALDIYA STOCK YARD 24 19-Jul-18 15-Aug-18 19-Jul-18 15-Aug-18 100% 15-Aug-18 A
A1010 PROTECTION OF INSIDE DECORATIVE PAINTING 10 10-Jul-18 21-Jul-18 10-Jul-18 21-Jul-18 100% 21-Jul-18 A
A1020 REMOVING OF EXISTING CAR PARKING SHADE & TRANSPORT THE MATERIAL AS PER CONSULTANT
15 10-Jul-18
INSTRUCTION
26-Jul-18 10-Jul-18 26-Jul-18 100% 26-Jul-18 A
A1030 TREE REMOVAL/CAR NEAR LIFT & MAID ROOM 15 24-Jul-18 09-Aug-18 24-Jul-18 09-Aug-18 100% 09-Aug-18 A
A1040 AC UNITS REMOVAL & DISPOSAL OF TOSHIBA BRAND 15 03-Jul-18 19-Jul-18 03-Jul-18 19-Jul-18 100% 19-Jul-18 A
PENT HOUSE 271 10-Jul-18 15-Jun-19 10-Jul-18 21-May-19, PENT HOUSE
A1050 DISMANTLING OF EXISTING COLUMNS 10 10-Jul-18 21-Jul-18 10-Jul-18 21-Jul-18 100% 21-Jul-18 A
A1060 COLUMN STEEL, SHUTTERING & CONCRETE 10 18-Sep-18 29-Sep-18 18-Sep-18 29-Sep-18 18-Sep-18
100% A 29-Sep-18 A
A1070 BEAM, SLAB SHUTTERING , STEEL & CONCRETE 20 06-Sep-18 29-Sep-18 06-Sep-18 29-Sep-18 06-Sep-18
100% A 29-Sep-18 A
A1080 DESHUTTERING OF SLAB 18 27-Sep-18 17-Oct-18 27-Sep-18 17-Oct-18 27-Sep-18 A
100% 17-Oct-18 A
A1420 BLOCK WORK 15 08-Nov-18 25-Nov-18 20-Oct-18 30-Nov-18 100% 20-Oct-18 A 30-Nov-18 A
A1430 MEP FIRST FIX 10 24-Nov-18 04-Dec-18 0% 30-Oct-18 10-Nov-18
A1440 INTERNAL PLASTER 18 05-Dec-18 25-Dec-18 0% 11-Nov-18 01-Dec-18
A1450 EXTERNAL PLASTER 30 13-Dec-18 16-Jan-19 0% 19-Nov-18 23-Dec-18
A1460 INTERNAL PRIMER & PUTTY 15 25-Dec-18 10-Jan-19 0% 01-Dec-18 17-Dec-18
A1470 MEP SECOND FIX 15 09-Jan-19 26-Jan-19 0% 16-Dec-18 01-Jan-19
A1480 HVAC WORK 15 09-Jan-19 26-Jan-19 0% 16-Dec-18 01-Jan-19
A1490 FALSE CEILING WORK 15 27-Jan-19 12-Feb-19 0% 02-Jan-19 19-Jan-19
A1500 WET AREA WATER PROOFING 10 27-Jan-19 06-Feb-19 0% 02-Jan-19 13-Jan-19
A1510 TILING- WALLS & FLOOR 40 07-Feb-19 25-Mar-19 0% 14-Jan-19 28-Feb-19
A1520 FIRST COAT PAINTING 8 20-Mar-19 28-Mar-19 0% 24-Feb-19 04-Mar-19
A2540 WOODEN DOORS 30 26-Mar-19 29-Apr-19 0% 02-Mar-19 04-Apr-19
A2560 MEP SWITCH & SOCKET FIXING 30 26-Mar-19 29-Apr-19 0% 02-Mar-19 04-Apr-19
A2570 HVAC FINAL FIX 30 26-Mar-19 29-Apr-19 0% 02-Mar-19 04-Apr-19
A2580 LIGHT INSTALLATION 30 26-Mar-19 29-Apr-19 0% 02-Mar-19 04-Apr-19
A2590 SANITARY INSTALLATION 30 26-Mar-19 29-Apr-19 0% 02-Mar-19 04-Apr-19
A2600 INTERNAL SECOND COAT PAINTING 20 23-May-19 15-Jun-19 0% 29-Apr-19 21-May-19
FIRST FLOOR 182 01-Nov-18 15-Jun-19 23-Oct-18 30-May-19, FIRST FLOOR
A1349 MEP FIRST FIX, CHIESELING & RE-ROUTING THE CONDUITS AS PER ISSUED IFC 15 01-Nov-18 18-Nov-18 23-Oct-18 28-Nov-18 100% 23-Oct-18 A 28-Nov-18 A
A1350 REMOVAL OF EXISTING PAINT & PLASTER REPAIRING WORKS 15 01-Nov-18 18-Nov-18 25-Nov-18 30%
A1360 INTERNAL PRIMER & PUTTY 15 22-Nov-18 09-Dec-18 0% 14-Nov-18 02-Dec-18
A1370 MEP SECOND FIX 15 04-Dec-18 20-Dec-18 0% 26-Nov-18 13-Dec-18
A1380 HVAC WORKS 15 12-Dec-18 29-Dec-18 0% 26-Nov-18 13-Dec-18
A1390 FALSE CEILING WORK 15 30-Dec-18 15-Jan-19 0% 13-Dec-18 31-Dec-18
A1400 WET AREA WATER PROOFING 10 30-Dec-18 09-Jan-19 0% 13-Dec-18 25-Dec-18
A1410 TILE - WALLS & FLOOR 40 09-Jan-19 24-Feb-19 0% 24-Dec-18 09-Feb-19
A1411 FIRST COAT OF PAINT 8 18-Mar-19 26-Mar-19 0% 02-Mar-19 11-Mar-19

Remaining Level of Effort Critical Remaining Work


DATE REVISION PREPARED BY CHECKED BY STATUS
Actual Level of Effort Milestone Page 1 of 6 16.6.2018 0 KETAN KUMAR S. GAWALI NA
Actual Work Summary CONSTRUCTION, COMPLETION & MAINTENANCE OF
Remaining Work
12.11.2018 1 KETAN KUMAR S. GAWALI AWC
OMANTEL CEO VILLA
19.11.2018 2 KETAN KUMAR S. GAWALI APPROVED
PROJECT - CONSTRUCTION, COMPLETION MAINTENANCE OF SHEIK TALAL VILLA (REV.-2)

CLIENT - MR. SHEIK TALAL AL MAMARI

CONSULTANT - ARAB ENGINEERING BUREAU

CONTRACTOR - AL ARKAN CONSTRUCTION LLC

Activity ID Activity Name Original BL Project BL Project Actual Start Actual Finish Activity2018
% 2019
Duration Start Finish Complete Q3 Q4 Q1 Q2 Q3 Q4
A2650 WOODEN DOORS 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2670 MEP SWITCH & SOCKET FIXING 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2680 HVAC FINAL FIX 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2690 LIGHT INSTALLATION 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2700 SANITARY INSTALLATION 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2710 INTERNAL SECOND COAT PAINTING 20 23-May-19 15-Jun-19 0% 07-May-19 30-May-19
GROUND FLOOR 208 01-Oct-18 15-Jun-19 01-Oct-18 30-May-19, GROUND FLOOR
A1260 MEP FIRST FIX, CHIESELING & RE-ROUTING THE CONDUITS AS PER ISSUED IFC 15 01-Oct-18 17-Oct-18 01-Oct-18 20-Nov-18 100%01-Oct-18 A 20-Nov-18 A
A1270 REMOVAL OF EXISTING PAINT & PLASTER REPAIRING WORK 15 06-Nov-18 22-Nov-18 15-Oct-18 95% 15-Oct-18 A 06-Nov-18
A1280 INTERNAL PRIMER & PUTTY-2 COATS 15 20-Nov-18 06-Dec-18 0% 03-Nov-18 20-Nov-18
A1290 MEP SECOND FIX ABOVE FALSE CEILING 15 24-Nov-18 10-Dec-18 0% 06-Nov-18 24-Nov-18
A1300 HVAC WORK 15 25-Nov-18 11-Dec-18 0% 07-Nov-18 25-Nov-18
A1310 FALSE CEILING WORKS 25 12-Dec-18 09-Jan-19 0% 25-Nov-18 24-Dec-18
A1320 WET AREA WATER PROOFING WORKS 10 12-Dec-18 23-Dec-18 0% 25-Nov-18 06-Dec-18
A1330 TILING - WALL & FLOOR 32 10-Jan-19 16-Feb-19 0% 24-Dec-18 30-Jan-19
A1340 FIRST COAT OF PAINTING 8 17-Feb-19 25-Feb-19 0% 30-Jan-19 09-Feb-19
A2720 WOODEN DOORS 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2740 MEP SWITCH & SOCKET FIXING 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2750 HVAC FINAL FIX 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2760 LIGHT INSTALLATION 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2770 SANITARY INSTALLATION 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2780 INTERNAL SECOND COAT PAINTING 20 23-May-19 15-Jun-19 0% 07-May-19 30-May-19
LIFT 207 26-Jul-18 20-Mar-19 05-Sep-18 24-Mar-19, LIFT
A1090 EXCAVATION FOR LIFT PIT & PCC 5 30-Jul-18 04-Aug-18 05-Sep-18 15-Nov-18 05-Sep-18 A
100% 15-Nov-18 A
A1100 LIFT RAFT SHUTTERING/STEEL/CONCRETE 10 26-Jul-18 06-Aug-18 23-Sep-18 26-Sep-18 23-Sep-18 A
100% 26-Sep-18 A
A1110 LIFT WALL CONCRETE FROM GF TO FF 9 15-Sep-18 24-Sep-18 06-Oct-18 06-Oct-18 100%06-Oct-18 A 06-Oct-18 A
A1120 BITUMEN PAINT 8 29-Sep-18 07-Oct-18 09-Oct-18 09-Oct-18 100% 09-Oct-18 A 09-Oct-18 A
A1130 LIFT WALL CONCRETE FROM FF TO PH 7 02-Oct-18 09-Oct-18 11-Oct-18 11-Oct-18 100% 11-Oct-18 A 11-Oct-18 A
A1140 LIFT HEAD ROOM SLAB CONCRETE 6 20-Oct-18 25-Oct-18 15-Oct-18 15-Oct-18 100% 15-Oct-18 A 15-Oct-18 A
A2170 VENDOR FINALIZATION 10 15-Oct-18 25-Oct-18 31-Oct-18 31-Oct-18 100% 31-Oct-18 A 31-Oct-18 A
A2180 SHOP DRAWING PREPARATION & APPROVAL 20 25-Oct-18 17-Nov-18 08-Nov-18 5% 08-Nov-18 A 20-Nov-18
A2190 MANUFACTURING 35 15-Nov-18 25-Dec-18 0% 19-Nov-18 29-Dec-18
A2200 SHIPMENT 27 26-Dec-18 26-Jan-19 0% 30-Dec-18 29-Jan-19
A2210 SITE READY 2 11-Feb-19 12-Feb-19 0% 14-Feb-19 16-Feb-19
A2220 TRANSIT & DELIVERY 8 13-Feb-19 21-Feb-19 0% 17-Feb-19 25-Feb-19
A2230 INSTALLATION 23 23-Feb-19 20-Mar-19 0% 26-Feb-19 24-Mar-19
KITCHEN 160 20-Oct-18 23-Apr-19 08-May-19, KITCHEN
A2380 VENDOR FINALIZATION 15 20-Oct-18 05-Nov-18 0% 04-Nov-18 20-Nov-18
A2390 SHOP DRAWING PREPARATION & APPROVAL 20 14-Nov-18 06-Dec-18 0% 29-Nov-18 22-Dec-18
A2400 MANUFACTURING 36 09-Dec-18 19-Jan-19 0% 24-Dec-18 03-Feb-19
A2410 SHIPMENT 44 19-Jan-19 10-Mar-19 0% 03-Feb-19 25-Mar-19

Remaining Level of Effort Critical Remaining Work


DATE REVISION PREPARED BY CHECKED BY STATUS
Actual Level of Effort Milestone Page 2 of 6 16.6.2018 0 KETAN KUMAR S. GAWALI NA
Actual Work Summary CONSTRUCTION, COMPLETION & MAINTENANCE OF
Remaining Work
12.11.2018 1 KETAN KUMAR S. GAWALI AWC
OMANTEL CEO VILLA
19.11.2018 2 KETAN KUMAR S. GAWALI APPROVED
PROJECT - CONSTRUCTION, COMPLETION MAINTENANCE OF SHEIK TALAL VILLA (REV.-2)

CLIENT - MR. SHEIK TALAL AL MAMARI

CONSULTANT - ARAB ENGINEERING BUREAU

CONTRACTOR - AL ARKAN CONSTRUCTION LLC

Activity ID Activity Name Original BL Project BL Project Actual Start Actual Finish Activity2018
% 2019
Duration Start Finish Complete Q3 Q4 Q1 Q2 Q3 Q4
A2420 SITE READY 2 11-Mar-19 12-Mar-19 0% 26-Mar-19 27-Mar-19
A2430 TRANSIT & DELIVERY 15 13-Mar-19 30-Mar-19 0% 28-Mar-19 14-Apr-19
A2440 INSTALLATION 15 07-Apr-19 23-Apr-19 0% 22-Apr-19 08-May-19
ROOF FLOOR 122 01-Nov-18 13-Apr-19 20-Oct-18 20-Mar-19, ROOF FLOOR
A1530 PARAPET BLOCK WORK 20 01-Nov-18 24-Nov-18 20-Oct-18 31-Oct-18 100% 20-Oct-18 A 31-Oct-18 A
A1540 MEP FIRST FIX 12 22-Nov-18 05-Dec-18 0% 30-Oct-18 12-Nov-18
A1550 INTERNAL PARAPET PLASTER 8 13-Jan-19 21-Jan-19 0% 20-Dec-18 29-Dec-18
A1560 SCREEDING 5 22-Jan-19 27-Jan-19 0% 30-Dec-18 03-Jan-19
A1570 WATER PROOFING 15 06-Feb-19 23-Feb-19 0% 14-Jan-19 30-Jan-19
A1580 HEAT INSULATION 8 21-Feb-19 02-Mar-19 0% 29-Jan-19 06-Feb-19
A1590 ROOF FLOOR TILES WORKS 27 03-Mar-19 02-Apr-19 0% 07-Feb-19 10-Mar-19
A1600 FOUNDATION FOR WATER TANK & AC UNITS 9 03-Apr-19 13-Apr-19 0% 11-Mar-19 20-Mar-19
MAID ROOM 265 09-Jul-18 28-May-19 09-Jul-18 13-May-19, MAID ROOM
A1150 FOOTING EXCAVATION 11 09-Jul-18 21-Jul-18 09-Jul-18 21-Jul-18 100% 21-Jul-18 A
A1160 FOOTING STEEL/SHUTTERING/CONCRETE 8 20-Aug-18 28-Aug-18 20-Aug-18 28-Aug-18 20-Aug-18
100% A 28-Aug-18 A
A1161 GRADE SLAB 8 27-Sep-18 06-Oct-18 27-Sep-18 06-Oct-18 27-Sep-18
100% A 06-Oct-18 A
A1162 BLOCK WORK 13 07-Oct-18 21-Oct-18 06-Oct-18 20-Oct-18 100%06-Oct-18 A 20-Oct-18 A
A1180 SLAB STEEL/SHUTTERING/CONCRETE 15 22-Oct-18 07-Nov-18 20-Oct-18 31-Oct-18 100% 20-Oct-18 A 31-Oct-18 A
A1190 DESHUTTERING OF SLAB 14 07-Nov-18 22-Nov-18 01-Nov-18 14-Nov-18 100% 01-Nov-18 A 14-Nov-18 A
A1620 MEP FIRST FIX 5 03-Dec-18 08-Dec-18 15-Nov-18 18-Nov-18 100% 15-Nov-18 A 18-Nov-18 A
A1630 INTERNAL PLASTER 10 11-Dec-18 22-Dec-18 22-Nov-18 10%
A1640 EXTERNAL PLASTER 8 23-Dec-18 31-Dec-18 22-Nov-18 10%
A1650 INTERNAL PRIMER & PUTTY 8 02-Jan-19 10-Jan-19 0% 21-Nov-18 01-Dec-18
A1660 MEP SECOND FIX 5 20-Jan-19 24-Jan-19 0% 09-Dec-18 15-Dec-18
A1670 HVAC WORK 4 29-Jan-19 02-Feb-19 0% 18-Dec-18 23-Dec-18
A1690 WET AREA WATER PROOFING 5 05-Feb-19 10-Feb-19 0% 25-Dec-18 31-Dec-18
A1700 TILING- WALLS & FLOOR 8 18-Feb-19 26-Feb-19 0% 07-Jan-19 16-Jan-19
A1710 FIRST COAT PAINTING 5 27-Feb-19 04-Mar-19 0% 16-Jan-19 22-Jan-19
A2790 WOODEN DOORS 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2800 WINDOWS 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2810 MEP SWITCH & SOCKET FIXING 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2820 HVAC FINAL FIX 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2830 LIGHT INSTALLATION 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2840 SANITARY INSTALLATION 30 26-Mar-19 29-Apr-19 0% 10-Mar-19 14-Apr-19
A2850 INTERNAL SECOND COAT PAINTING 30 24-Apr-19 28-May-19 0% 08-Apr-19 13-May-19
A2860 ROOF WATER PROOFING 8 05-Mar-19 13-Mar-19 0% 22-Jan-19 31-Jan-19
A2870 ROOF TILING 8 14-Mar-19 23-Mar-19 0% 31-Jan-19 10-Feb-19
PARKING RCC SLAB 194 15-Jul-18 07-Mar-19 15-Jul-18 25-Feb-19, PARKING RCC SLAB
A1200 FOOTING EXCAVATION 10 15-Jul-18 25-Jul-18 15-Jul-18 25-Jul-18 100% 25-Jul-18 A
A1210 FOOTING STEEL/SHUTTERING/CONCRETE 8 20-Aug-18 28-Aug-18 20-Aug-18 28-Aug-18 20-Aug-18
100% A 28-Aug-18 A
A1220 COLUMNS STEEL/SHUTTERING/CONCRETE 8 26-Aug-18 03-Sep-18 26-Aug-18 03-Sep-18 26-Aug-18
100% A 03-Sep-18 A

Remaining Level of Effort Critical Remaining Work


DATE REVISION PREPARED BY CHECKED BY STATUS
Actual Level of Effort Milestone Page 3 of 6 16.6.2018 0 KETAN KUMAR S. GAWALI NA
Actual Work Summary CONSTRUCTION, COMPLETION & MAINTENANCE OF
Remaining Work
12.11.2018 1 KETAN KUMAR S. GAWALI AWC
OMANTEL CEO VILLA
19.11.2018 2 KETAN KUMAR S. GAWALI APPROVED
PROJECT - CONSTRUCTION, COMPLETION MAINTENANCE OF SHEIK TALAL VILLA (REV.-2)

CLIENT - MR. SHEIK TALAL AL MAMARI

CONSULTANT - ARAB ENGINEERING BUREAU

CONTRACTOR - AL ARKAN CONSTRUCTION LLC

Activity ID Activity Name Original BL Project BL Project Actual Start Actual Finish Activity2018
% 2019
Duration Start Finish Complete Q3 Q4 Q1 Q2 Q3 Q4
A1221 GRADE SLAB 15 19-Sep-18 06-Oct-18 19-Sep-18 06-Oct-18 19-Sep-18 A
100% 06-Oct-18 A
A1230 SLAB STEEL/SHUTTERING/CONCRETE 16 07-Oct-18 24-Oct-18 07-Oct-18 24-Oct-18 100% 07-Oct-18 A 24-Oct-18 A
A1240 DESHUTTERING OF SLAB 14 24-Oct-18 08-Nov-18 25-Oct-18 10-Nov-18 100% 25-Oct-18 A 10-Nov-18 A
A2880 BLOCK WORK 8 12-Nov-18 20-Nov-18 0% 01-Nov-18 10-Nov-18
A2890 MEP FIRST FIX 4 27-Nov-18 01-Dec-18 0% 17-Nov-18 20-Nov-18
A2900 INTERNAL PLASTER 10 02-Dec-18 12-Dec-18 0% 21-Nov-18 02-Dec-18
A2910 PRIMER & PUTTY 10 13-Dec-18 24-Dec-18 0% 03-Dec-18 13-Dec-18
A2920 CLAUSTRA BLOCKS 5 26-Dec-18 31-Dec-18 0% 16-Dec-18 20-Dec-18
A2930 CAR PARK FLOORING 10 02-Jan-19 13-Jan-19 0% 23-Dec-18 02-Jan-19
A2940 ROOF WATER PROOFING 15 14-Jan-19 30-Jan-19 0% 03-Jan-19 20-Jan-19
A2950 ROOF TILING 15 31-Jan-19 17-Feb-19 0% 21-Jan-19 06-Feb-19
A2960 FIRST COAT PAINTING 8 18-Feb-19 26-Feb-19 0% 07-Feb-19 16-Feb-19
A2970 MEP SECOND FIX 8 27-Feb-19 07-Mar-19 0% 17-Feb-19 25-Feb-19
EXTERNAL DEVELOPMENT WORKS 181 15-Oct-18 08-Jun-19 28-May-19, EXTERNAL DEVELOPMENT WORK
CAR PARKING SHADE IN FABRICATION - CLIENT SCOPE 97 10-Jan-19 02-May-19 22-Apr-19, CAR PARKING SHADE IN FABRICATION -
A1890 EXCAVATION 8 10-Jan-19 19-Jan-19 0% 31-Dec-18 08-Jan-19
A1900 PCC 2 20-Jan-19 21-Jan-19 0% 09-Jan-19 10-Jan-19
A1910 FOUNDATION WITH BOLTS 8 22-Jan-19 30-Jan-19 0% 12-Jan-19 20-Jan-19
A1920 STRUCTURAL FABRICATED MEMBER ERECTION 9 31-Jan-19 10-Feb-19 0% 21-Jan-19 30-Jan-19
A1930 ROOF SHED ERECTION 5 28-Apr-19 02-May-19 0% 17-Apr-19 22-Apr-19
ROLLING SHUTTER FOR CAR PARKING 100 10-Jan-19 06-May-19 25-Apr-19, ROLLING SHUTTER FOR CAR PARKING
A2470 VENDOR FINALIZATION 15 10-Jan-19 27-Jan-19 0% 31-Dec-18 16-Jan-19
A2480 SHOP DRAWING PREPARATION & APPROVAL 30 28-Jan-19 03-Mar-19 0% 17-Jan-19 20-Feb-19
A2490 MANUFACTURING 50 03-Mar-19 29-Apr-19 0% 20-Feb-19 18-Apr-19
A2500 INSTALLATION 10 25-Apr-19 06-May-19 0% 15-Apr-19 25-Apr-19
SWIMMIMG POOL- CLIENT SCOPE 136 01-Jan-19 08-Jun-19 28-May-19, SWIMMIMG POOL- CLIENT SCOP
A1720 EXCAVATION 8 01-Jan-19 09-Jan-19 0% 22-Dec-18 30-Dec-18
A1730 PCC 1 10-Jan-19 10-Jan-19 0% 31-Dec-18 31-Dec-18
A1740 RAFT STEEL/ SHUTTERING/ CONCRETE 15 12-Jan-19 28-Jan-19 0% 01-Jan-19 17-Jan-19
A1750 WALL STEEL/ SHUTTERING/ CONCRETE 15 27-Jan-19 12-Feb-19 0% 16-Jan-19 02-Feb-19
A1760 GUTTER STEEL/ SHUTTERING/ CONCRETE 7 12-Feb-19 19-Feb-19 0% 02-Feb-19 09-Feb-19
A1770 MEP FIRST FIX 8 20-Feb-19 28-Feb-19 0% 10-Feb-19 18-Feb-19
A1780 INTERNAL WATER PROOFING 10 20-Feb-19 03-Mar-19 0% 10-Feb-19 20-Feb-19
A1790 EXTERNAL WATER PROOFING 10 20-Feb-19 03-Mar-19 0% 10-Feb-19 20-Feb-19
A1800 WALL & FLOOR TILES 15 03-Mar-19 19-Mar-19 0% 20-Feb-19 09-Mar-19
A1810 PUMP & BALANCING TANK 10 19-Mar-19 30-Mar-19 0% 09-Mar-19 19-Mar-19
A1820 MEP SECOND FIX, LIKE PUMP INSTALLATION & PIPING 10 19-Mar-19 30-Mar-19 0% 09-Mar-19 19-Mar-19
A1830 TESTING & COMMISSIONING 10 28-May-19 08-Jun-19 0% 18-May-19 28-May-19
STEPS 115 10-Jan-19 23-May-19 13-May-19, STEPS
A1840 EXCAVATION 8 10-Jan-19 19-Jan-19 0% 31-Dec-18 08-Jan-19
A1850 PCC 2 20-Jan-19 21-Jan-19 0% 09-Jan-19 10-Jan-19

Remaining Level of Effort Critical Remaining Work


DATE REVISION PREPARED BY CHECKED BY STATUS
Actual Level of Effort Milestone Page 4 of 6 16.6.2018 0 KETAN KUMAR S. GAWALI NA
Actual Work Summary CONSTRUCTION, COMPLETION & MAINTENANCE OF
Remaining Work
12.11.2018 1 KETAN KUMAR S. GAWALI AWC
OMANTEL CEO VILLA
19.11.2018 2 KETAN KUMAR S. GAWALI APPROVED
PROJECT - CONSTRUCTION, COMPLETION MAINTENANCE OF SHEIK TALAL VILLA (REV.-2)

CLIENT - MR. SHEIK TALAL AL MAMARI

CONSULTANT - ARAB ENGINEERING BUREAU

CONTRACTOR - AL ARKAN CONSTRUCTION LLC

Activity ID Activity Name Original BL Project BL Project Actual Start Actual Finish Activity2018
% 2019
Duration Start Finish Complete Q3 Q4 Q1 Q2 Q3 Q4
A1860 FOUNDATION CONCRETE 8 22-Jan-19 30-Jan-19 0% 12-Jan-19 20-Jan-19
A1870 SOLID BLOCK WORKS 9 31-Jan-19 10-Feb-19 0% 21-Jan-19 30-Jan-19
A1880 STEPS RISER/TREAD TILE FIXING 10 13-May-19 23-May-19 0% 02-May-19 13-May-19
EXTERNAL PAVING WITH CURB STONE & DEVELOPMENT 68 10-Feb-19 29-Apr-19 18-Apr-19, EXTERNAL PAVING WITH CURB STONE &
A1940 EXCAVATION 10 10-Feb-19 20-Feb-19 0% 30-Jan-19 10-Feb-19
A1950 COMPACTION & PROCTOR DENSITY TEST 2 21-Feb-19 23-Feb-19 0% 11-Feb-19 12-Feb-19
A1960 PROPOSED MANHOLE COVER RE-ROUTING 8 24-Feb-19 04-Mar-19 0% 13-Feb-19 21-Feb-19
A1970 EXTERNAL AREA LIGHT CONDUITING 12 05-Mar-19 18-Mar-19 0% 23-Feb-19 07-Mar-19
A1980 EXTERNAL AREA ELECTRICAL CONDUITING 10 19-Mar-19 30-Mar-19 0% 09-Mar-19 19-Mar-19
A1990 PLANTER BLOCK WORK 21 19-Mar-19 11-Apr-19 0% 09-Mar-19 01-Apr-19
A2000 PLANTER ASHLER TILES 10 10-Apr-19 21-Apr-19 0% 31-Mar-19 10-Apr-19
A2240 INTERLOCK FIXING/GRANITE FLOOR FIXING 40 14-Mar-19 29-Apr-19 0% 04-Mar-19 18-Apr-19
BOUNDARY WALL 101 05-Dec-18 01-Apr-19 21-Mar-19, BOUNDARY WALL
A2010 EXISTING BOUNDARY WALL DEMOLITION 8 05-Dec-18 13-Dec-18 0% 25-Nov-18 03-Dec-18
A2020 EXCAVATION FOR FOUNDATION 8 13-Dec-18 22-Dec-18 0% 03-Dec-18 11-Dec-18
A2030 PCC 1 23-Dec-18 23-Dec-18 0% 12-Dec-18 12-Dec-18
A2040 FOUNDATION STEEL/SHUTTERING/CONCRETE 8 24-Dec-18 01-Jan-19 0% 13-Dec-18 22-Dec-18
A2050 COLUMNS CONCRETE SOLID BLOCK WORKS 15 02-Jan-19 19-Jan-19 0% 23-Dec-18 08-Jan-19
A2060 MEP CHIESELING & CONDUITING FOR LIGHTS 2 20-Jan-19 21-Jan-19 0% 09-Jan-19 10-Jan-19
A2070 PLASTER 10 22-Jan-19 02-Feb-19 0% 12-Jan-19 22-Jan-19
A2080 PRIMER & TWO COAT PAINTING 8 09-Feb-19 17-Feb-19 0% 29-Jan-19 06-Feb-19
A2090 GATE FOOTING CONCRETE 20 18-Feb-19 12-Mar-19 0% 07-Feb-19 02-Mar-19
A2100 GATE ERECTION 20 10-Mar-19 01-Apr-19 0% 27-Feb-19 21-Mar-19
LANDSCAPE WORKS 42 16-Apr-19 03-Jun-19 23-May-19, LANDSCAPE WORKS
A2110 EXCAVATION 10 16-Apr-19 27-Apr-19 0% 06-Apr-19 16-Apr-19
A2120 IRRIGATION LINE LAYING 10 28-Apr-19 08-May-19 0% 17-Apr-19 28-Apr-19
A2130 SOIL FILLING 8 09-May-19 18-May-19 0% 29-Apr-19 07-May-19
A2140 PUMP INSTALLATION 8 19-May-19 27-May-19 0% 08-May-19 16-May-19
A2150 TESTING & COMMISSSIONING 4 28-May-19 01-Jun-19 0% 18-May-19 21-May-19
A2160 PLANTATION 14 19-May-19 03-Jun-19 0% 08-May-19 23-May-19
ELEVATION WORK & COMMON WORK 146 15-Oct-18 30-Apr-19 17-Apr-19, ELEVATION WORK & COMMON WORK
A2505 WINDOWS 30 25-Mar-19 28-Apr-19 0% 14-Mar-19 17-Apr-19
A2510 EXTERNAL PAINTING (INCLUDING SCAFFOLDING REMOVAL) 35 19-Mar-19 28-Apr-19 0% 09-Mar-19 17-Apr-19
A2520 TESTING & COMMISSIONING FOR MEP WORKS (HVAC/LIFT/LIGHT FITTINGS/SANTRY FITTING
15/BOOSTER
18-Mar-19PUMP/WATER
03-Apr-19 PUMP etc.) 0% 07-Mar-19 24-Mar-19
A2530 HAND RAILING AS PER APPROVED BOQ & DRAWING 15 09-Mar-19 25-Mar-19 0% 26-Feb-19 14-Mar-19
A2610 CARPET FLOOR & GYM FLOOR MATERIAL SELECTION 7 06-Apr-19 13-Apr-19 0% 12-Mar-19 19-Mar-19
A2620 CARPET FLOOR & GYM FLOOR MATERIAL INSTALLATION 15 14-Apr-19 30-Apr-19 0% 20-Mar-19 06-Apr-19
A2630 HOME AUTOMATION & SECURITY SYSTEM CONTRACTOR ON BOARD 7 15-Oct-18 22-Oct-18 0% 30-Oct-18 06-Nov-18
A2640 SATELLITE TV SYSTEM CONTRACTOR ON BOARD 7 15-Oct-18 22-Oct-18 0% 30-Oct-18 06-Nov-18
TESTING & COMMISSIONING, APPROVAL FORM GOVT. AUTHORITIES 43 01-May-19 19-Jun-19 09-Jun-19, TESTING & COMMISSIONING, AP
A2280 SNAGGING & DESNAGGING 34 12-May-19 19-Jun-19 0% 27-Apr-19 04-Jun-19

Remaining Level of Effort Critical Remaining Work


DATE REVISION PREPARED BY CHECKED BY STATUS
Actual Level of Effort Milestone Page 5 of 6 16.6.2018 0 KETAN KUMAR S. GAWALI NA
Actual Work Summary CONSTRUCTION, COMPLETION & MAINTENANCE OF
Remaining Work
12.11.2018 1 KETAN KUMAR S. GAWALI AWC
OMANTEL CEO VILLA
19.11.2018 2 KETAN KUMAR S. GAWALI APPROVED
PROJECT - CONSTRUCTION, COMPLETION MAINTENANCE OF SHEIK TALAL VILLA (REV.-2)

CLIENT - MR. SHEIK TALAL AL MAMARI

CONSULTANT - ARAB ENGINEERING BUREAU

CONTRACTOR - AL ARKAN CONSTRUCTION LLC

Activity ID Activity Name Original BL Project BL Project Actual Start Actual Finish Activity2018
% 2019
Duration Start Finish Complete Q3 Q4 Q1 Q2 Q3 Q4
A2300 SUBSTAINTIAL COMPLETION CERTIFICATE 1 01-May-19 01-May-19 0% 21-Apr-19 21-Apr-19
A2310 ROP INSPECTION 2 02-May-19 04-May-19 0% 22-Apr-19 23-Apr-19
A2320 MUNCIPALITY INSPECTION 5 04-May-19 08-May-19 0% 23-Apr-19 28-Apr-19
A2330 WATER CONNECTION 10 20-May-19 30-May-19 0% 09-May-19 20-May-19
A2340 ELECTRICITY CONNECTION 10 20-May-19 30-May-19 0% 09-May-19 20-May-19
A2345 FINAL TESTING & COMMISSIONING 16 02-Jun-19 19-Jun-19 0% 22-May-19 09-Jun-19
HANDING OVER 38 12-May-19 19-Jun-19 09-Jun-19, HANDING OVER
A2350 SUBMISSION OF AS BUILT DRAWINGS & WARRANTY CERTIFICATE 34 12-May-19 19-Jun-19 0% 27-Apr-19 04-Jun-19
A2360 FINAL HANDING OVER 0 19-Jun-19 0% FINAL HANDING OVER

Remaining Level of Effort Critical Remaining Work


DATE REVISION PREPARED BY CHECKED BY STATUS
Actual Level of Effort Milestone Page 6 of 6 16.6.2018 0 KETAN KUMAR S. GAWALI NA
Actual Work Summary CONSTRUCTION, COMPLETION & MAINTENANCE OF
Remaining Work
12.11.2018 1 KETAN KUMAR S. GAWALI AWC
OMANTEL CEO VILLA
19.11.2018 2 KETAN KUMAR S. GAWALI APPROVED