Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Alfonso Fuggetta
Politecnico di Milano and UCI
Planning
Tracking
(control)
Corrective
actions
Details
ID Task Name
1 Initial ISO 9000 Process Work
2 Seek ISO 9000 Documents Work
3 Order Documents Work
4 Determine which standard is applicable Work
5 Hold Management Meeting - Gain Management Support Work
6 Project Leader Work
7 Define Project Leader's Role Work
8 Appoint Project Leader Work
Determine Project
Leader’s Role
NE = c1 × KDSI c2
• Note: this is
%Budget just an
Mil. $
example:
40 100%
Actual
cost Planned – The project is
cost
30
late and more
20 50% expensive
Earned
value
than planned.
10
Today Time
Delay
Overcost
ISO9000
I
Name BCWS BCWP ACWP SV CV EAC BAC VAC
D
1 Initial ISO 9000 Process $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00
2 Seek ISO 9000 Documents $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00
3 Order Documents $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00
4 Determine which standard is applicable $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00
5 Hold Management Meeting - Gain Management Support $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00 $0,00
• The Cost field shows the scheduled timephased cost for a resource
assignment, based on costs already incurred for work performed by the
resource on the task, in addition to the costs planned for the remaining
work for the assignment. This can also be referred to as estimate at
completion (EAC). This timephased field shows the cost for the
assignment as distributed over time.
• When an assignment is first made, cost is the same as remaining cost,
which is the remaining work value multiplied by the resource cost. As
actual work is reported on the assignment, Microsoft Project calculates
the cost by adding the actual cost to the remaining cost. This figure is
distributed across the scheduled duration of the assignment.
– Cost = Actual Cost + Remaining Cost
%Budget
Mil. $
40 100%
Actual
cost Planned
cost
30
20 50%
Earned
10 value
Today Time
%Budget
Mil. $
40 100%
Actual
cost Planned
cost
30
20 50%
Earned
10 value
Today Time
%Budget
Mil. $
40 100%
Actual
cost Planned
cost
30
20 50%
Earned
10 value
Today Time
%Budget
Mil. $
40 100%
Actual
cost Planned
cost
30
20 50%
Earned
10 value
Today Time
%Budget
Mil. $
40 100%
Actual
cost Planned
cost
30
20 50%
Earned
10 value
Today Time