Sei sulla pagina 1di 2

CONSULTANCY SERVICES FOR DESIGN OF ROADS, DRAINAGE AND

UTILITIES IN DUQM INDUSTRIAL LAND, DUQM PORT

Man-month Input (Hydraulic Design)

The man months required for hydraulic component are given in the table below:

Phase- l (Review of available Studies/ Data)

Sr. Man
Name Designation Grade
No Months
1. Kamran Ahmad Chief Hydraulics & Drainage Engineer 12 0.5
2. Mohsin Munir Senior Hydraulic Engineer 10 0.75
3. Shahneela Mukhtar Senior Hydraulic Engineer 9 0.75

Phase- ll (Preliminary Design Report)

Sr. Man
Name Designation Grade
No Months
1. Kamran Ahmad Chief Hydraulics & Drainage Engineer 12 1.5
2. Mohsin Munir Senior Hydraulic Engineer 10 1
3. Irfan Mehmood Senior Hydraulic Engineer 10 1
4. Shahneela Mukhtar Senior Hydraulic Engineer 9 2
5. TBN Draftsman 9 0.5

Phase- lll (Detailed Engineering Design)

Sr. Man
Name Designation Grade
No Months
Chief Hyd
1. Kamran Ahmad 12 2
raulics & Drainage Engineer
2. Mohsin Munir Senior Hydraulic Engineer 10 2.5
3. Irfan Mehmood Senior Hydraulic Engineer 10 2.5
4. Shahneela Mukhtar Senior Hydraulic Engineer 9 3
5. TBN Draftsman 9 2
6. TBN Costing Engineer 8a 1

Phase- lV (Design Team Input during Tender Documents)

Sr. Man
Name Designation Grade
No Months
1. Kamran Ahmad Chief Hydraulics & Drainage Engineer 12 1
2. Mohsin Munir Senior Hydraulic Engineer 10 1.5
3. Shahneela Mukhtar Senior Hydraulic Engineer 9 1.5

1
4. TBN Costing Engineer 8a 0.75

Phase- V (Design Team Input during Construction Phase)

Sr. Man
Name Designation Grade
No Months
1. Kamran Ahmad Chief Hydraulics & Drainage Engineer 12 3
2. Mohsin Munir Senior Hydraulic Engineer 10 5
3. TBN Draftsman 9 1

Direct Cost

Site visits, Stationery, Computer Time = As per actual cost involved