PLANT ROUND OBSERVATIONS Dated 19-03-2019

Concerned
Picture Observation
Responsible

Chemical Store in
refrigerator ,SS container
Dirty Found/Rust type or
Production
yellowish accumulation

Dirty wall near Line No.02 Production


PLANT ROUND OBSERVATIONS Dated 19-03-2019

Dust accumulation at the


Production (Hand
flappers of the exhaust
Washing Station)
fan.

Dirty wall and IPA not


Production
available at the identified
place in Locker Room (Locker Room)
PLANT ROUND OBSERVATIONS Dated 19-03-2019

Dirty Wall in locker room Production

Roof broken in Hand


Production
washing station
PLANT ROUND OBSERVATIONS Dated 19-03-2019

Water Stagnant at the


Production
floor near blancher Line 02

Rusted Window near drum


Production
drier No, Line No.01
PLANT ROUND OBSERVATIONS Dated 19-03-2019

Temporary fixing at
equipment (Geyser ) at Production
Line No.01

Dust accumulation at the


Production
surface of electrical panels
PLANT ROUND OBSERVATIONS Dated 19-03-2019

Paint and cleaning


required on air curtain at Production
entry of bunkers

Rusted equipments at
production to blending the Production
additives
PLANT ROUND OBSERVATIONS Dated 19-03-2019

Coving broken at the


Production
production.

Wall not painted at empty


Packaging Area
bag inspection station
PLANT ROUND OBSERVATIONS Dated 19-03-2019

Wall pillar damage at Flakes Packaging


packaging area Area

Locker is not locked


properly while additives Ready Mix
and ink are placed in changing area
changing room
PLANT ROUND OBSERVATIONS Dated 19-03-2019

Wall not painted in ready Ready mix


mix packaging area packaging area