Sei sulla pagina 1di 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/323239289

The critical role of Anchor customer in microgrids

Preprint · February 2018

CITATIONS READS
0 132

3 authors:

Fabien Chidanand Robert Gyanendra Sisodia


Amrita Vishwa Vidyapeetham Ajman University, Fujairah
13 PUBLICATIONS   25 CITATIONS    24 PUBLICATIONS   49 CITATIONS   

SEE PROFILE SEE PROFILE

Sundararaman Gopalan
Amrita Vishwa Vidyapeetham, Amritapuri Campus, Kerala India
60 PUBLICATIONS   1,311 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Hf-Silicate for gate dielectric application View project

Low-Cost Large Scale Rural Heath Care Gadget View project

All content following this page was uploaded by Fabien Chidanand Robert on 17 February 2018.

The user has requested enhancement of the downloaded file.


THE CRITICAL ROLE OF ANCHOR CUSTOMERS IN RURAL
MICROGRIDS
IMPACT OF LOAD FACTOR ON ENERGY COST

Fabien Chidanand Robert Gyanendra Singh Sisodia Sundararaman Gopalan


Amrita Center for Wireless College of Business Department of Electronics and
Networks & Applications Administration, Communication Engineering
(AmritaWNA) Ajman University, Fujairah Amrita School of Engineering,
Amrita School of Engineering, Campus, UAE Amritapuri
Amritapuri Singh_gis@yahoo.co.in, Amrita Vishwa Vidyapeetham
Amrita Vishwa Vidyapeetham g.sisodia@ajman.ac.ae Amrita University,
Amrita University, India
India sundar@am.amrita.edu
chidanand@am.amrita.edu

Abstract—The development of the society was supported by cost effective and clean solution for the electrification of
an easy access to energy and in particular to electricity. remote areas with limited energy demand [4]. Microgrids
However, 1.2 billion people worldwide are yet to receive an powered through PV (Photo Voltaic) can generate power
electrical connection. Most of them live in rural areas and during the daytime, whereas the wind energy can be
many are far from the grid or in hilly terrains. Renewable
utilised to generate power when the wind blows
energy microgrids are a good alternative to grid extension in
many cases. However, the rural communities often consist of irrespective of day or night. During this time, the energy
households only, with an energy demand concentrated in the produced can be directly used without being stored, thus
morning and at night, in the early hours. This increases the reducing the need for costly storage, and avoiding energy
need for costly storage as renewable energy is either losses (~20%) during the storage process. However, in
available during the day for solar, or distributed throughout many newly electrified villages, the industrial,
the day for wind. Anchor customers are users such as commercial and public loads (schools and hospitals) are
schools, hospitals, small manufacturing units or GSM tower very limited since they had no access to electricity. This
that consume energy throughout the day. They contribute to leads to an overall load pattern that is very unbalanced
the local development and can be a source of steady income
with a small peak of consumption in the morning, a higher
for the microgrid owner. This paper illustrates that by
including such customers at the microgrid design stage, the peak at night (during early hours) and very little load at
average cost of electricity can be reduced. Through other times [5-7]. In addition, as the grid and generation
microgrid design simulations, it is shown that when anchor units have to be designed to cater to the peak load, there is
customers represent around 30% of the load (load factor of a poor utilisation ratio of assets. For both of these reasons,
0.4), the cost of electricity can be reduced by 22% for a the average cost of energy can be higher than anticipated
microgrid powered by wind and solar energy and by 48% in remote villages.
for a solar microgrid, compared to a village with less than Many successful microgrid entrepreneurs have
10% of anchor users (load factor 0.2). It is thus critical to reported that the support of anchor customers is a key
include anchor customers at the microgrid design stage in
order to provide affordable energy in rural areas.
factor of success for microgrid ventures [8-10]. Anchor
customers are users such as public loads (schools or rural
Keywords: microgrid; renewable energy; anchor hospitals), commercial loads or small manufacturing
customers; load factor; rural electrification. units. They have a regular energy demand and ensure that
the energy generated by the microgrid is not wasted.
I. INTRODUCTION Indeed many households may not be able to afford to pay
Energy has been a crucial parameter in the evolution for electricity on a regular basis which can lead to a
of the society. It has enabled humanity to gain tremendous microgrid business failure if revenues do not cover for the
time in its daily tasks, and allowed for the development of cost of maintenance and ensure the reliable operation of
more advanced technologies. 1.2 billion people the microgrid.
worldwide and 240 million in India are yet to be provided In this work, the economic impact of including anchor
with an electrical connection; 83% of those live in rural customers during the design phase of the microgrid is
areas [1]. Considering the extra costs involved in quantified. Two types of microgrids have been simulated
extending the grids to remote areas, and the cost of either powered by solar energy alone, or by wind and
operation and maintenance, the International Energy solar energy (hybrid). In each scenario, the design of the
Agency (IEA) estimates that 70% of future rural microgrid has been optimised for a total load of
electrification will be done via mini-grids and off-grid 225kWh/day for three different load patterns with load
systems [2]. factor of 0.2, 0.3 and 0.4. The results show that the load
With the decrease in cost in the solar and wind energy factor influences the cost of the energy significantly. The
technologies and the improvements in control overall cost of energy can be reduced by 22% and 48%
techniques [3], renewable energy microgrids represent a respectively in the hybrid case and in the solar case, when
anchor customers represent around 30% of the total load.
II. BACKGROUND III. LITERATURE REVIEW
The fixed cost related to the electrification such as Several practical studies have been published in the
engineering, planning, transportation of equipment and recent years on the optimisation of the microgrid design.
setting up for the distribution grid in the remote area can In [24], a comparative study presents the best
be high, thus the project is worth executing when there is microgrid design solution to power a village of 600
a minimum load demand. When the requirement is very households in South India. Four types of loads are
minimal such as for lighting, for a radio or for charging considered: domestic, commercial/industrial, agriculture
phones only, cheaper alternatives exist: solar home (irrigation) and a separate GSM tower load. The hybrid
systems, the gravity light, daylight or LEDs shining system with wind, solar, hydro and batteries is the optimal
through water bottles. choice and is more cost effective than grid extension.
The cost of grid extension may be justified when However, the load factor presented in the study is very
villages are close enough to a distribution grid but the close to 1, for domestic and industrial loads, which is not
energy losses in transmission and distribution in India are realistic, despite the fact that irrigation is considered as a
very high (30% overall) [11]. Power theft is also one of deferrable load. In addition, the project development and
the major concerns with work being done to detect it [12] installation costs do not seem to be included in this study
and improve real-time data collection on the distribution resulting in very optimistic results.
grid [13]. In [25], the economic feasibility of microgrid
There is thus a range of cases when microgrid electrification of a community that includes anchor
electrification is the appropriate solution. It is estimated in businesses is assessed. A broad study of microgrid cost
[14] that it can be the case for a village of 100 households effectiveness is performed by varying several parameters
situated beyond 20km from the grid in a hilly region. The such as the level of incentive, the technology (wind, solar
cost of the wind and solar energy has been reducing hydro, and biogas) and the availability of resource. The
consistently, is reaching grid parity in certain cases [15]. willingness to pay of villagers is studied depending for
Therefore, microgrids have emerged as well suited different levels of service. Anchor customers are included
solution for rural electrification. in the village, however their impact on the cost of energy
The cost of energy is an important factor for people for the community has not been studied.
living in the rural areas with limited revenue. An average It is shown in [26] that shifting loads towards midday
household spends less than 10% of its revenue for energy improves the reliability of supply, decreases energy
[16]. With 75% of the rural households of India having wastage and increases the life time of batteries, for a
their highest earner paid less than ₹5000 [16], most defined solar microgrid. Cost benefit and technical
households are expected to be able to spend in the order analysis of rural electrification alternatives is also
of 500Rs per month on electricity. For a household with a performed. However, the significance of the impact of the
low consumption of 1.5 kWh/day the maximum price load factor at the design stage of a microgrid is not
affordable per kWh is thus in the range of 11 ₹/kWh. studied.
The cost of electricity can be divided into fixed cost, Different designs of solar-wind-battery microgrid are
peak demand cost, and volumetric cost. Volumetric tested in [27], to power an island. Real load profile has
charges represent the major portion of the electricity bill been used. Many scenarios with different contribution of
for the small energy users. Thus, there is less incentive for wind and solar energy as well as different number of
households to reduce peak demand. In addition, the battery strings are tested to find the optimal design. A
demand in the evening may be relatively non-elastic. hybrid system is superior to a solar system for wind speed
However, it may be possible to encourage users to above 4 m/s and solar irradiation above 5 kWh/m2. It is
consume energy during low peak hours by offering noted that storage accounts for a significant portion of the
preferential tariffs. total cost (30%) and that 100% reliability requirement is
Anchor customers such as schools, clinics, GSM costly to achieve, with energy wastage above 50% in all
towers or other small enterprises consume energy cases.
throughout the day [17-23] and contribute to improving
the overall load factor of the community. The load factor Thus our work contributes to the literature by
is defined as the ratio between the average load and the determining the impact that the expected load factor (of a
peak load (1). village that has to be electrified), has on the design of a
microgrid, and further on the cost of energy. In the
present scope of the study, only generation costs are
considered and grid costs are excluded, this is justified as
they do not contribute significantly to the cost of energy
A constant load has a load factor of 1 and a very high (less than 10%) in microgrids [28]. This work aims at
power load that lasts for a very short period has a load promoting the inclusion of small industrial, commercial or
factor close to 0. Electrical infrastructure and in particular public loads at the planning stage, when designing a
the electrical grid is designed to cater to peak load microgrid for the rural electrification. It is demonstrated
requirement. As a consequence, it is less expensive to that such an approach is positive for the development of
supply loads with higher load factor. the concerned village and should be promoted by
governments, NGOs and microgrid investors.
IV. METHODOLOGY AND SIMULATION DESIGN industrial or public loads; the load factor is 0.3. The third
This study has used HOMER tool which is a case corresponds to a village of 90 households with an
microgrid simulation software designed by the National average consumption of 1.7 kWh/day and 30% of
Renewable Energy Laboratory (NREL) especially to commercial, industrial or public load; the load factor is
compare different microgrid generation designs. The 0.4.
software simulates different combinations of generation A newly electrified village is likely to have a load
units (wind or solar in this case) and storage, and designs factor between 0.2 and 0.4. Indeed a load factor less than
a microgrid that satisfies the energy demand at the least 0.2 would signify that there is very limited usage for
cost. Since lead acid batteries are used predominantly in electricity beyond lighting, which means that microgrid
India, storage using the same has been considered for the electrification might not be the best solution. A load
design. factor beyond 0.4 implies a significant commercial
The Levelised Cost of Energy (LCOE) corresponds to activity or a high level of public loads in the village which
the total cost spent for the total duration of the project is also unlikely for a village which has just been
divided by the total energy consumed by the users. As electrified.
there is no fuel cost involved, it is mostly affected by the The solar irradiance of Chennai is taken for reference
capital investment, the interest rate at which it has to be in this study. The average wind speed is 5m/s at 20 meter
reimbursed (cost of capital) and the inflation rate. It is the height, with the wind pattern from Madurai.
minimal price at which utility should sell the energy in The installation cost for solar is ₹1 70 000/kW, which
order to break even. In this study, government incentives corresponds to the cost indicated in [29] for small solar
are taken into consideration by choosing a cost of capital projects in India with a reduction to consider decrease in
equal to the inflation rate (5%). cost since 2014 (The current cost for famous MW projects
The software simulates all cases possible. Among the in India seem to be much lower than the average cost for
feasible cases that respect the constraints of reliability of MW projects indicated in this reference.). The cost for
supply for the microgrid, the first rank is attributed to the wind energy is taken from the same reference and is
design that has the least total cost for the project. ₹99 000/kW. Lead acid battery has an installed cost of
Providing electricity at high reliability level in isolated ₹7 700/kWh and a replacement cost of ₹6 700/kWh and a
microgrids powered by renewable energy is cost throughput of 800 kWh, which corresponds to the cost of
intensive. A percentage of electricity shortage of 4% is a battery from Luminous with 48 months guarantee.
allowed in this study which is acceptable for rural areas. Two sets of simulations are run for each load pattern,
A community load of 225 kWh/day is taken as a one using only solar energy and one using wind and solar
reference for this simulation. The same average energy energy (hybrid). In each case the software calculates the
demand is achieved through three different load patterns optimal design for powering the load. Only the load factor
corresponding to different levels of public, commercial is modified and the scaled average remains at
and industrial loads in the village (see Fig.1). 225 kWh/day in all simulations. It is thus possible to
isolate the impact that the load factor has on the cost of
energy through these simulations.
V. RESULTS AND ANALYSIS
The simulation results show that the optimal design is
influenced by the load factor. As illustrated in Fig. 2 and
Table 1, the number of generation units and especially the
number of batteries required is higher as the load factor
decreases. The variation is most pronounced for the solar
microgrid. It takes 80% more battery capacity and 15%
more generation capacity to power the 225 kWh load if
the load factor is 0.2 compared to 0.4. In the hybrid case,
it takes 50% more battery capacity and 10% more
generation capacity. In either case, as the load factor
decreases, the expense is significantly more.

Figure 1 Three possible load profiles for the same average load

The first case corresponds to a village of 130


households with an average consumption of 1.5 kWh/day
and 10% (~25 kWh/day) of commercial, industrial or
public loads, the load factor is 0.2. The second case
corresponds to a village of 110 households with an
average consumption of 1.6 kWh/day (The average
consumption of households can increase as there is more
development in the village.) and 20% of commercial, Figure 2 Impact of load factor on storage requirement
TABLE 1 OPTIMISED DESIGN FOR DIFFERENT LOAD FACTORS IN HYBRID AND SOLAR CASES

Wind LCOE Total cost Elec. Elec.


Load PV Battery
turbine Produced Consumed
factor (kW) (kWh)
(kW) (₹/kWh) (€/kWh) (Lakh ₹ ) (k€) (MWh/yr) (MWh/yr)
Hybrid 0.2 49 40 420 15.66 0.22 307 435 148
microgrids
0.3 51 30 331 13.59 0.19 267 379 134 78.8
0.4 51 30 278 12.63 0.18 248 352 134
Solar 0.2 98 797 23.74 0.34 466 661 157
microgrids
0.3 91 N.A. 433 17.52 0.25 344 488 145 78.8
0.4 84 445 16.26 0.23 319 452 134

The total cost of the project is calculated for a lifetime The combined effect of capital cost and total costs are
of 25 years. As seen in Fig. 3, the total cost is more summarised in the Levelised Cost Of Energy (LCOE).
affected than the capital cost. Indeed, the main difference The results show that the LCOE is affected significantly
in design comes from battery storage that is replaced by a change of load factor in both hybrid and solar
every 7 years. Thus impact on capital cost is less microgrids (see Fig. 5). In the solar microgrid, the LCOE
compared to when solar panels or wind turbines are is 48% higher when the load factor is at 0.2 compared to
added. 0.4. In the hybrid case, the LCOE is 22% higher.
The cost is shared between the PV system, the wind
turbine and the batteries. Due to the additional storage
requirement, for low load factors the cost of storage
represents close to 50% of the total cost when the load
factor is 0.2, compared to less than 40% when the load
factor is 0.4 (see Fig. 4).

Figure 5 Levelised Cost Of Energy for different load factor

Surplus energy occurs when renewable energy is available


in excess and the storage is full. It is necessary to accept a
certain percentage of energy wastage in order to maintain
a good reliability of the microgrid when renewable energy
is available in smaller amount. Energy is also wasted
during the storage process (~20%). This wasted energy is
a loss of revenue for the microgrid owner and should be
Figure 3 Impact of load factor on total cost and capital cost minimised. However, there are 25% more losses in the
hybrid case and 42% more in the solar case, when the
load factor is 0.2 compared to 0.4 (see Fig. 6).

Figure 4 Distribution of total cost depending on load factor


Figure 6 Impact of load factor on energy wastage
View publication stats

The results confirm that the design of a microgrid is [8] Global Network on Energy for Sustainable Development, K.
Sarangi, and P. Debajit, "Renewable energy-based rural
significantly affected by the expected load factor of the electrification: The mini-grid experience from India," Global
demand. A microgrid designed to power a community of Network on Energy for Sustainable Development, 2014.
households only, with low load factor, will be much more [9] United Nations Foundation, "Microgrids for rural electrification: A
expensive overall than a microgrid designed for critical review of best practices based on seven case studies),"
community that has anchor loads such as hospitals, United Nations Foundation, Feb. 2014.
schools, GSM towers or manufacturing units. [10] European Union Energy Initiative Partnership Dialogue Facility,
"Building energy access markets, A Value Chain Analysis of Key
Energy Market Systems," European Union Energy Initiative
VI. CONCLUSION Partnership Dialogue Facility (EUEI PDF), Eschborn, Feb. 2015.
The effect of the load factor on the microgrid design has [11] "Transmission & Distribution in India," in "Transmission and
been studied. When anchor customers such as small distribution in India A report A joint initiative of WEC-IMC and
power grid corporation of India limited," World Energy Council
businesses, schools, rural hospitals or GSM towers, India and Power Grid Corporation of India Limited, 2013.
represent around 30% of the load, the Levelised Cost Of [12] A. R. Devidas and M. V. Ramesh, "Power theft detection in
Energy (LCOE) can be reduced by 22% for a microgrid microgrids," in Smart Cities and Green ICT Systems
powered by solar and wind energy, and by 48% for a solar (SMARTGREENS), 2015 International Conference on, 2015.
microgrid. In absence of anchor customers, the investment [13] S. Nithin, P. Sivraj, K. Sasi K., and R. Lagerstom, "Development
in battery storage is almost half of all expenses and of a real time data collection unit for distribution network in a
smart grid environment," 2014 Power and Energy Systems:
energy wastage is almost as much as the useful energy, Towards Sustainable Energy, IEEE, 2014.
which points out that microgrid electrification is a valid [14] M. R. Nouni, S. C. Mullick, and T. C. Kandpal, "Providing
solution when there are anchors customers who consume electricity access to remote areas in India: Niche areas for
energy throughout the day. decentralized electricity supply," in Renewable Energy, Elsevier
This emphasises the need for microgrid developers to BV, 2009, vol. 34, no. 2, pp. 430–434.
identify key consumers who will improve the load factor [15] V. Shah and J. Booream-Phelps, "Deutsche Bank Markets
Research, Solar industry," 2015.
of the microgrid, at the design stage. This approach leads
[16] Selected Socio‐Economic Statistics (2011) India: Government of
to important savings on energy cost for the whole India, Ministry of Statistics and Programme Implementation.
community and improves the chances of long term [17] Powering health (2016) Available at:
success of the microgrid. Anchors customers can generate http://tools.poweringhealth.org (Accessed: 14 December 2016).
local revenue, offer job opportunities and are key [18] Jimenez, A.C. and Olson, K. (1998) Renewable Energy for Rural
contributors for the sustainable development of rural Health Clinics. NREL.
areas. Suitable energy tariffs may be developed to attract [19] Jimenez, A.C. and Lawand, T. (2000) Renewable Energy for Rural
such entrepreneurs [30]. Schools. NREL.
These results can be used as inputs by policy makers [20] Green power for mobile, bi-annual report (2014) GSMA.
and microgrid entrepreneurs to encourage the creation of [21] Green power for mobile: Energy outsourcing: Sunlabob Myanmar
(2014) GSMA.
small enterprises whenever villages are electrified using
[22] Bastakoti, B.P. (2003) ‘Rural electrification and efforts to create
microgrids. This is how rural India can come forward. enterprises for the effective use of power’, Applied Energy, 76(1-
3), pp. 145–155. doi: 10.1016/s0306-2619(03)00055-2.
ACKNOWLEDGEMENTS [23] Presentation by Rohit Kansal, Ministry of New and Renewable
Energy, New Delhi n.d. Available at: http://www.eria.org/events/3.
The authors would like to thank Amrita University for %20Mr.Rohit%20Kansal%20-20Lessons%20Learnt%20from%20
India's%20Micro-grid%20Development.pdf
supporting our research and providing the funds for the
software licence. [24] W. Amutha and V. Rajini, "Cost benefit and technical analysis of
rural electrification alternatives in southern India using HOMER",
Renewable and Sustainable Energy Reviews, vol. 62, pp. 236-246,
REFERENCES 2016.
[25] N. Ramchandran, R. Pai and A. Parihar, "Feasibility assessment of
[1] REN21, Renewables 2016 Global Status Report (2016) Paris: Anchor-Business-Community model for off-grid rural
REN21 Secretariat. ISBN 978-3-9818107-0-7 electrification in India", Renewable Energy, vol. 97, pp. 197-209,
[2] IEA. (2011). World Energy Outlook. OECD/IEA. 2016.
[3] P. Kanakasabapathy and V. V. Rao, "Control strategy for inverter [26] S. Fezai and J. Belhadj, "Load profile impact on a stand-alone
based micro-grid," in 2014 Power and Energy Systems: Towards Photovoltaic system," in 2016 7th International Renewable Energy
Sustainable Energy, Institute of Electrical and Electronics Congress (IREC), Institute of Electrical and Electronics Engineers
Engineers (IEEE), 2014. (IEEE), 2016.
[4] F. Urban, R. M. J. Benders, and H. C. Moll, "Energy for rural [27] T. Ma, H. Yang and L. Lu, "A feasibility study of a stand-alone
India," Applied Energy, vol. 86, pp. S47–S57, Nov. 2009 hybrid solar–wind–battery system for a remote island", Applied
Energy, vol. 121, pp. 149-158, 2014.
[5] European Commission, "Promotion of microgrids and renewable
energy sources for electrification in developing countries," 2008. [28] South Asia Energy Unit Sustainable Development Department The
World Bank, "Empowering Rural India: Expanding Electricity
[6] N. Fall, L. Giles, B. Marchionini, E. G. Skolnik, and Energetics, Access by Mobilizing Local Resources," 2010.
Inc., "Remote Area Power Supply (RAPS) Load and Resource
Profiles," Sandia National Laboratories, Jul. 2007. [29] IRENA, "Renewable Power Generation Costs in 2014," 2014.
[7] N. Martensen, R. Kuwahata, T. Ackermann, M. Ram, R. Kumar, [30] Sisodia, G. S., Soares, I., Banerji, S., & Van den Poel, D. (2015,
and S. Teske, "‘e[r] cluster’ for a smart energy access," in "Bihar November). The status of energy price Modelling and its relevance
smart energy access," Greenpeace India Society, May 2012. to marketing in emerging economies.
doi:10.1016/j.egypro.2015.11.5

Potrebbero piacerti anche