NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH

I. PEKERJAAN PERSIAPAN
1 Pembersihan Perataan Tanah Lokasi 323.25 M2 18,062.00 5,838,541.50
2 Pengukuran/Pemasangan bouwplank 36.00 M1 99,830.80 3,593,908.80
3 Bangsal Kerja, Gudang, & Ruang Direksi 32.00 M2 1,518,667.15 48,597,348.80
4 Papan Nama Proyek 1.00 Ls 500,000.00 500,000.00
5 Mobilisasi/Demobilisasi 1.00 Ls 750,000.00 750,000.00
6 Dokumentasi dan Pelaporan 1.00 Ls 1,000,000.00 1,000,000.00
7 Pembersihan Akhir 1.00 Ls 500,000.00 500,000.00
60,779,799.10
II. PEKERJAAN TANAH
1 Galian tanah 211.48 M3 51,761.60 10,946,481.05
2 Mengurug kembali bekas galian 1/4 x 52.87 M3 24,819.96 1,312,223.84
3 Urugan Pasir dibawah pondasi 3.04 M3 473,300.40 1,437,886.62
4 Timbunan Tanah dibawah lantai dipadatkan 137.73 M3 64,702.00 8,911,082.95
5 Urugan Pasir dibawah lantai 31.18 M2 473,300.40 14,755,139.97
37,362,814.43
III. PEKERJAAN PASANGAN / BETON
Pas. Batu Kosong 4.46 M3 632,198.16 2,822,132.59
1 Pas. pondasi Batu Kali 1 : 4 15.28 M3 1,168,095.40 17,843,825.33
5 Pas. Dinding batu bata Trasraam 1 : 2 10.90 M3 199,006.86 2,169,672.29
1 Pas. dinding batu bata 1 : 5 251.87 M3 183,846.10 46,305,318.21
2 Plesteran Pondasi Dan Tangga 1:3 81.90 M2 70,043.54 5,736,566.25
2 Plesteran + Acian dinding Batu bata 1 : 4 503.74 M2 67,969.96 34,239,187.65
3 Plesteran + Acian dinding transram 1 : 2 21.81 M2 73,107.66 1,594,112.44
3 Plesteran Beton + Acian 1 : 3 18.34 M2 70,043.54 1,284,598.60
4 Pek.beton bertulang 1 : 2 : 3 :
- Sloof 25/30 ### 90.00 Kg 5.64 M3 5,645,634.60 31,841,379.14
- Kolom 10x10 ### 390.00 Kg 0.67 M3 11,786,955.90 7,838,325.67
- Kolom 35x35 170.00 Kg 2.02 M3 9,328,485.74 18,855,201.80
- Kolom 40x50 130.00 Kg 11.00 M3 9,037,849.74 99,416,347.14
- Balok Atap 15/20 ### 160.00 Kg 1.82 M3 11,470,311.56 20,818,615.48
- Balok Atap 20/25 ### 210.00 Kg 2.10 M3 12,110,835.56 25,432,754.68
- Balok Lantai 20/30 190.00 Kg 7.44 M3 11,696,625.80 87,022,895.95
- Plat Lantai 12 CM 170.00 Kg 18.29 M3 8,314,283.62 152,032,911.70
- Plat Atap 10 CM 180.00 Kg 1.32 M3 7,254,883.62 9,576,446.38
- Lisplank Beton Untuk Talang 10.00 Kg - M3 7,566,146.12 -
- Pondasi Telapak 130 X 130 170.00 Kg 8.79 M3 5,405,066.50 47,499,724.40
792,285,553.27
IV. PEKERJAAN KAYU DAN PENUTUP ATAP
1 Kosen pintu, Jendelah dan Ventilasi 4.82 M3 10,572,452.00 51,000,493.49
2 Daun Pintu Panel Papan Kls I 41.73 M2 745,262.00 31,099,783.26
3 Daun Pintu tripleks 0,30 mm Lapis Seng Plat 0.03 5.60 M2 603,927.80 3,381,995.68
4 Daun Jendela Kaca 5 mm Bingkai Kayu Kls I 45.00 M2 599,415.60 26,973,702.00
5 Pekerjaan Kaca 3 mm 31.31 M2 309,636.03 9,693,960.97
4 Kuda-kuda dan Konsol Kayu Kls I - M2 9,451,708.00 -
6 Gording 5/10 Kayu Kls II A - M2 6,407,928.00 -
6 Skor Angin Kayu 5/10 Kls II - M2 6,407,928.00 -
7 Kasau dan Ring Genteng - M2 109,496.10 -
8 Lysplank Kayu 1/30 Kls I - M2 299,111.20 -
9 Atap Genteng Metal Roof - M2 106,569.44 -
10 Bubungan Genteng Metal Roof 37.25 M1 411,208.10 15,317,501.73
11 Plafond Tripleks 5 mm + Rangka Kayu Kls II 456.75 M2 148,188.80 67,685,234.40
12 Lis Plafond Profil 2/5 Cm 189.60 M1 54,571.84 10,346,820.86
13 Mur Baut - Bh 31,536.01 -
14 Angker Baut - Bh 31,536.01 -
15 Beugel - Bh 31,536.01 -
215,499,492.39
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH

V. PEKERJAAN LANTAI
1 Lantai Rabat Beton Tebal 5 cm camp. 1 : 3 : 6 311.75 M2 55,391.20 17,268,206.60
4 Plesteran dan acian Lantai 311.75 M2 23,106.28 7,203,384.04
6 Pek. Lantai Keramik 40x40 486.00 M2 383,325.16 186,296,029.70
7 Pekerjaan Lantai Keramik WC/KM 20x20 2.40 M2 265,515.16 637,236.39
8 Pekerjaan Dinding WC/KM 20x20 67.20 M2 483,632.64 32,500,113.41
12 Pekerjaan Dinding Keramik 40x40 (63.52) M2 383,325.16 (24,348,814.42)
219,556,155.73
VI. PEKERJAAN CAT
1 Cat dinding dgn Matex 2x termasuk 1x Plamir (Baru) 667.50 M2 43,820.08 29,249,902.45
2 Cat Plafond dgn Matex 2x termasuk 1x Plamir (Baru) 456.75 M2 43,820.08 20,014,820.89
3 Cat Pintu, Jendela, Kosen, Ventilasi dan Lysplank 120.60 M2 27,088.75 3,266,838.24
4 3x dgn Glotex/Platone (Baru)
5 Cat Atap Seng - M2 35,812.15 -
52,531,561.57
VII. PEKERJAAN KUNCI
1 - Kunci Pintu 2 Slaag 32.00 Bh 241,614.12 7,731,651.84
2 Kunci Pintu KM/WC 1 Slaag Merk Ancor 4.00 Bh 214,462.60 857,850.40
2 Engsel Pintu Kuningan Kwalitas Baik 144.00 Bh 77,206.03 11,117,668.32
3 Engsel Jendela Dan Ventilasi Kuningan Kwalitas Baik 150.00 Bh 57,594.02 8,639,103.00
4 Kait Angin Kwalitas Baik 150.00 Bh 79,548.04 11,932,206.00
5 Grendel Pintu 96.00 Bh 79,548.04 7,636,611.84
6 Grendel Jendela 150.00 Bh 79,548.04 11,932,206.00
59,847,297.40
VIII. PEKERJAAN INSTALASI LISTRIK

1 Titik Lampu + Instalasi - Bh 220,000.00 -


2 Lampu Jari-jari 25 Watt - Bh 60,500.00 -

3 Lampu Pijar 25 Watt - Bh 4,070.00 -


4 Saklar Ganda - Bh 12,760.00 -

6 Stop Kontak - Bh 51,370.00 -


9 MCB - Bh 80,000.00 -
-

IX PEKERJAAN SANITASI
2 Kloset Duduk INA / TOTO ( Lengkap ) - Bh 1,974,514.30 -

3 Kran Air Bersih Kualitas Standard - Bh 60,087.70 -


4 Saringan Pemb, Air Kotor/Avour Alumunium - Bh 46,525.20 -

5 Bak Tampungan Air BersIh - Bh 5,288,992.72 -


6 Pipa Paralon PVC dia. 3" - M1
119,651.66 -

7 Pipa Paralon PVC dia. 1/2" - M1 26,604.07 -


8 Septic Tank dan Peresapan Lengkap - Bh 5,500,000.00 -
-
REKAPITULASI RENCANA ANGGARAN BIAYA

PROYEK : PENINGKATAN SARANA DAN PRASARANA PERIKANAN


P E K E R J AA N : PEMBANGUNAN GEDUNG KOMERSIAL
LOKASI : DUFA-DUFA KEC. TERNATE UTARA
TAHUN ANGGARAN : 2007

NO. URAIAN PEKERJAAN JUMLAH HARGA

I. PEKERJAAN PERSIAPAN Rp. 60,779,799.10

II. PEKERJAAN TANAH Rp. 37,362,814.43

III. PEKERJAAN PASANGAN / BETON Rp. 792,285,553.27

II PEKERJAAN KAYU Rp. 215,499,492.39

III PEKERJAAN LANTAI Rp. 219,556,155.73

IV PEKERJAAN CAT Rp. 52,531,561.57

V PEKERJAAN KUNCI Rp. 59,847,297.40

VIII. PEKERJAAN INSTALASI LISTRIK Rp. -

IX PEKERJAAN SANITASI Rp. -

J U M LAH = Rp. 1,437,862,673.89

PPN 10 % = Rp. 143,786,267.39


IMB = Rp. 3,937,500.00
JUMLAH TOTAL = Rp. 1,585,586,441.28

PEMBULATAN = Rp. 1,585,586,000.00

TERBILANG : ENAM RATUS SEMBILAN PULUH EMPAT JUTA DELAPAN RATUS DELAPAN BELAS RIBU RUPIAH

TERNATE, FEBRUARI 2006

MENYETTUUI
PEMBANTU REKTOR
BIDANG ADMINISTRASI DAN KEUANGAN

………………………………………………………
NIP………………………………..
REKAPITULASI U M U M
PROYEK :
P E K E R J AA N : REHABILITASI PUSKESMA PEMBANTU TOLIWANG
LOKASI : DESA TOLIWANG
TAHUN ANGGARAN : 2005

NO. URAIAN PEKERJAAN JUMLAH HARGA

1 Biaya Konstruksi Fisik Rp. 1,585,586,000.00

2 Biaya Perencanaan Konstruksi (5%) Rp. 79,279,300.00

3 Biaya Pengawasan Konstruksi (4%) Rp. 63,423,440.00

4 Biaya Pengolaan Proyek (1%) Rp. 15,855,860.00

Jumlah Rp. 1,744,144,600.00

Dibulatkan 1,744,144,000.00

TERBILANG : ENAM PULUH EMPAT JUTA DELAPAN RATUS LIMA PULUH TUJUH RIBU RUPIAH

TERNATE, FEBRUARI 2006


MENYETTUUI
PEMBANTU REKTOR
BIDANG ADMINISTRASI DAN KEUANGAN

………………………………………………………
NIP………………………………..
ANGKA MAX. 11 DIGIT ANGKA #VALUE! TERBILANG : EMPAT RATUS

MILYAR #VALUE! #VALUE! #VALUE! 0


#VALUE! #VALUE! #VALUE! 100
JUTA #VALUE! #VALUE! #VALUE! 200
#VALUE! #VALUE! #VALUE! 300
RIBU #VALUE! #VALUE! #VALUE! 400
#VALUE! #VALUE! #VALUE! 500
RUPIAH #VALUE! #VALUE! #VALUE! 600
700
800
900
4 5 6 7
MILYAR EMPAT RATUS TIGA PULUH SEMBILAN JUTA SERATUS
#VALUE! #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
0
SERATUS 1 SATU
DUA RATUS 2 DUA
TIGA RATUS 3 TIGA
EMPAT RATUS 4 EMPAT
LIMA RATUS 5 LIMA
ENAM RATUS 6 ENAM
TUJUH RATUS 7 TUJUH
DELAPAN RATUS 8 DELAPAN
SEMBILAN RATU 9 SEMBILAN
10 SEPULUH
11 SEBELAS
12 DUA BELAS
13 TIGA BELAS
14 EMPAT BELAS
15 LIMA BELAS
16 ENAM BELAS
17 TUJUH BELAS
18 DELAPAN BELAS
19 SEMBILAN BELAS
20 DUA PULUH
21 DUA PULUH SATU
22 DUA PULUH DUA
23 DUA PULUH TIGA
24 DUA PULUH EMPAT
25 DUA PULUH LIMA
26 DUA PULUH ENAM
27 DUA PULUH TUJUH
28 DUA PULUH DELAPAN
29 DUA PULUH SEMBILAN
30 TIGA PULUH
31 TIGA PULUH SATU
32 TIGA PULUH DUA
33 TIGA PULUH TIGA
34 TIGA PULUH EMPAT
35 TIGA PULUH LIMA
36 TIGA PULUH ENAM
37 TIGA PULUH TUJUH
38 TIGA PULUH DELAPAN
39 TIGA PULUH SEMBILAN
40 EMPAT PULUH
41 EMPAT PULUH SATU
42 EMPAT PULUH DUA
43 EMPAT PULUH TIGA
44 EMPAT PULUH EMPAT
45 EMPAT PULUH LIMA
46 EMPAT PULUH ENAM
47 EMPAT PULUH TUJUH
48 EMPAT PULUH DELAPAN
49 EMPAT PULUH SEMBILAN
50 LIMA PULUH
51 LIMA PULUH SATU
52 LIMA PULUH DUA
53 LIMA PULUH TIGA
54 LIMA PULUH EMPAT
55 LIMA PULUH LIMA
56 LIMA PULUH ENAM
57 LIMA PULUH TUJUH
58 LIMA PULUH DELAPAN
59 LIMA PULUH SEMBILAN
60 ENAM PULUH
61 ENAM PULUH SATU
62 ENAM PULUH DUA
63 ENAM PULUH TIGA
64 ENAM PULUH EMPAT
65 ENAM PULUH LIMA
66 ENAM PULUH ENAM
67 ENAM PULUH TUJUH
68 ENAM PULUH DELAPAN
69 ENAM PULUH SEMBILAN
70 TUJUH PULUH
71 TUJUH PULUH SATU
72 TUJUH PULUH DUA
73 TUJUH PULUH TIGA
74 TUJUH PULUH EMPAT
75 TUJUH PULUH LIMA
76 TUJUH PULUH ENAM
77 TUJUH PULUH TUJUH
78 TUJUH PULUH DELAPAN
79 TUJUH PULUH SEMBILAN
80 DELAPAN PULUH
81 DELAPAN PULUH SATU
82 DELAPAN PULUH DUA
83 DELAPAN PULUH TIGA
84 DELAPAN PULUH EMPAT
85 DELAPAN PULUH LIMA
86 DELAPAN PULUH ENAM
87 DELAPAN PULUH TUJUH
88 DELAPAN PULUH DELAPAN
89 DELAPAN PULUH SEMBILAN
90 SEMBILAN PULUH
91 SEMBILAN PULUH SATU
92 SEMBILAN PULUH DUA
93 SEMBILAN PULUH TIGA
94 SEMBILAN PULUH EMPAT
95 SEMBILAN PULUH LIMA
96 SEMBILAN PULUH ENAM
97 SEMBILAN PULUH TUJUH
98 SEMBILAN PULUH DELAPAN
99 SEMBILAN PULUH SEMBILAN

8 9 10
#VALUE! #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
GOBLOK BANGET SIH, TAU BEKING RAB KA' NYANDA
BUSYETTT !!!!! LEBIH BAIK BUAT BELI KOREK KUPING, KALO KURANG LOE TAM
GILE BENER !!! BUAT APAAN TUH DUIT SEGITU, NGAK ONGKOS BUAT BAPIKIR
LEBIH BAGUS TIDUR JOO !!! KALO MO URISIN DUIT CUMA SEGITU !!!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
G, KALO KURANG LOE TAMBAH NECH !!!
K ONGKOS BUAT BAPIKIR
CUMA SEGITU !!!
RENCANA ANGGARAN BIAYA ( RAB )

PROGRAM : PENINGKATAN SARANA DAN PRASARANA BADAN SAR NASIONAL


P E K E R JAAN : PENGEMBANGAN GEDUNG SERBAGUNA LANTAI 02
LOKASI : TERNATE
TAHUN ANGGARAN : 2017

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH


A. PEKERJAAN PERSIAPAN
1 Persiapan Existing 1.00 Ls 1,500,000.00 1,500,000.00
2 Bangsal Kerja, Gudang dan Direksi Ket 9.00 M2 1,518,667.15 13,668,004.35
3 Mobilisasi/ Demobilisasi Bahan & Peralatan 1.00 Ls 3,500,000.00 3,500,000.00
4 Papan Nama Proyek 1.00 Ls 500,000.00 500,000.00
5 Air, Listrik Kerja dan Penerangan Proyek 1.00 Ls 5,500,000.00 5,500,000.00
6 Asbuild Drawing dan Pelaporan 1.00 Ls 4,000,000.00 4,000,000.00
7 Pembersihan Akhir 1.00 Ls 2,750,000.00 2,750,000.00
31,418,004.35
B. PEKERJAAN LANTAI I
I PEKERJAAN TALUD DAN PERBAIKAN SALURAN
1 Pek. Pengukuran dan Pas. Bouplank 29.25 M1 99,830.80 2,920,050.90
2 Urugan Tanah Kembali 14.33 M2 24,819.96 355,732.08
3 Pas. Batu Kali ad. 1: 5 18.37 M3 1,214,893.40 22,323,210.64
4 Pipa PVC AW uk 2" 6.00 M' 66,636.11 399,816.65
5 Plesteran Pondasi ad.1: 3+Acian 31.19 M2 70,043.54 2,184,307.92
6 Pek. Profil Talud ad.1: 3 + Acian 29.25 M1 23,106.28 675,858.81
28,858,976.99
II PEKERJAAN KOLOM BANTU
1 Lantai kerjaCor ad. 1:2:3 0.52 M3 1,479,435.40 766,939.31
2 Pembukaan Keramik + Galian Renc. Kolom Bantu 3.00 Ttk 2,000,000.00 6,000,000.00
3 Pek. Tapak Kolom Bantu Beton 100/100 (170 Kg/M3) 1.20 M3 5,405,066.50 6,486,079.80
4 Pek. Kolom Bantu Beton Kb 35/50 (170 Kg/M3) 3.28 M3 9,328,485.74 30,609,093.83
43,862,112.95
III. PEKERJAAN PINTU, PARTISI DAN PLAFOND
1 Pek. Kusend Alumunium 48.90 M1 201,788.10 9,867,438.29
2 Daun Jendela kaca 5 mm Rangka Alumunium 5.73 M2 1,216,660.04 6,971,462.03
3 Pek. Kusend Kayu Kls. I 0.17 M3 10,572,452.00 1,745,723.27
4 Daun Pintu Panel kaca 5 mm 3.52 M2 745,262.00 2,623,322.24
5 Pas Kaca Mati 5 mm 1.52 M2 309,636.03 470,027.49
6 Pas. Partisi Gipsum 60.20 M2 413,500.48 24,892,728.60
7 Engsel Jendela 6.00 Bh 57,594.02 345,564.12
8 Engsel Pintu 10.00 Bh 77,206.03 772,060.30
9 Grendel Jendela 3.00 Bh 79,548.04 238,644.12
10 Pek. Rangka Plafond besi hollow 248.49 M2 135,547.28 33,682,651.91
11 Pek. Plafond Gipsum 248.49 M2 91,916.25 22,840,613.65
12 Pek. Pas Lis profil Gipsum 214.86 M1 54,571.84 11,725,305.54
116,175,541.56
IV. PEKERJAAN LANTAI DAN PASANGAN
1 Pek. Saluran Keliling 76.00 M1 281,776.00 21,414,975.62
2 Pek. Rabat beton Kotak 30/30 (Rabat Keliling) 60.80 M2 193,008.24 11,734,900.99
3 Pek. Lapis ACP Pintu Utama 7.00 M2 1,124,819.20 7,873,734.40
4 Pas. Keramik Tektur 60/60 Tangga teras 9.66 M2 383,325.16 3,702,921.08
5 Beton Plat Konsul keliling jendela 12 x 20 cm 1.36 M3 6,615,843.62 8,997,547.32
6 Pek. Plester + Acian Konsul keliling jendela 12x40 63.00 M2 70,043.54 4,412,743.27
7 Pek. Plester + Acian Kolom bantu 25.50 M2 70,043.54 1,786,110.37
8 Pas. Batu Alam Kolom Teras LT. I 7.00 M2 483,632.64 3,385,428.48
9 Pas. Batu Alam Dinding Lt.I dan LT. II 16.80 M2 483,632.64 8,125,028.35
10 Pek. Revisi Trap anak Tangga 1.00 Ls 2,750,000.00 2,750,000.00
11 Pek. Relling Tangga (Pagar Besi) 10.00 M' 938,658.02 9,386,580.24
12 Pek. Lantai Keramik Tangga Granit 30x60 19.68 M2 643,365.16 12,661,426.43
13 Pas. Lantai Keramik areal Kolom bantu Granit 60x60 9.72 M2 643,365.16 6,253,509.39
102,484,905.96
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH

V. PEKERJAAN CAT
1 Perbaikan Cat Profil Beton luar ( Kupas Plamiran) 183.60 M2 13,620.60 2,500,742.16
2 Cat dinding lama Luar 2x Lapis 535.60 M2 28,342.42 15,180,198.62
3 Cat dinding lama Dalam 2 x Lapis 144.50 M2 22,877.62 3,305,815.68
4 Cat kolom bantu 25.50 M2 43,820.08 1,117,412.00
5 Cat Bidang Plafond 248.49 M2 27,088.75 6,731,385.07
28,835,553.53
VI. PEKERJAAN INSTALASI LISTRIK
1 Titik Lampu + Instalasi 55.00 Titik 220,000.00 12,100,000.00
2 Lampu Philips 20 Watt 15.00 Bh 79,750.00 1,196,250.00
3 Lampu Philips 13 Watt 16.00 Bh 60,500.00 968,000.00
4 Lampu Philips 8 Watt 9.00 Bh 49,500.00 445,500.00
5 Pemasangan Kabel Listrik NYM 2.5 x 3 250.00 M1 19,475.00 4,868,750.00
6 Saklar Ganda 10.00 Bh 51,370.00 513,700.00
7 Saklar AC 7.00 Bh 110,000.00 770,000.00
8 Saklar Tunggal 4.00 Bh 51,370.00 205,480.00
9 Stop Kontak 8.00 Bh 51,370.00 410,960.00
21,478,640.00
Sub Total ( A) 373,113,735.33

C. PEKERJAAN LANTAI II
I. PEKERJAAN PASANGAN
1 Pas. dinding 1/2 bata Pres Pabrikasi 8x25x50 (ringan) 167.34 M2 218,082.00 36,494,190.81
2 Pas. 1 Bata Pres Pabrikasi 8x25x50 ( Panggung) 5.90 M2 436,164.00 2,573,367.60
3 Urugan Batu Apung ( Panggung) 12.90 M3 412,500.00 5,321,250.00
4 Ornamen Profil sudut 7x7 cm 14.40 M1 23,106.28 332,730.49
5 Plester+ Acian Profil dinding 20x10 cm 25.00 M2 70,043.54 1,751,088.60
6 Plester+ Acian Profil dinding 10x10 cm 25.20 M2 70,043.54 1,765,097.31
7 Plesteran Dek Atap 1 : 3 (Level Kemiringan 2%) 94.50 M2 70,043.54 6,619,114.91
8 Plesteran + Acian dinding Batu bata 1 : 4 334.68 M2 67,969.96 22,748,403.72
9 Plesteran Beton dan Profil 1 :3 + Acian 52.50 M2 70,043.54 3,677,286.06
10 Papan Nama (GEDUNG SERBAGUNA) 1.00 Ls 10,000,000.00 10,000,000.00
91,282,529.49
II. PEKERJAAN STRUKTUR
1 Kolom Beton K-275
- Kolom Utama K2 35/35 150.00 Kg 7.45 M3 9,037,849.74 67,313,904.86
- Kolom Praktis 12/10 150.00 Kg 0.25 M3 9,037,849.74 2,277,538.13
2 Balok Beton Elevasi +8.80 K-275
- Balok RB1 25/80 170.00 Kg 6.00 M3 9,611,989.80 57,671,938.80
- Balok RB2 25/40 170.00 Kg 6.80 M3 9,611,989.80 65,361,530.64
- Balok Anak BE 15/25 150.00 Kg 1.65 M3 8,970,369.80 14,801,110.17
- Ring Balok Atap 12/20 150.00 Kg 1.73 M3 8,970,369.80 15,500,799.01
3 Plat Beton Atap Tbl. 10 cm Elevasi +8.80 K-275
- Plat Lantai Beton Atap 120.00 Kg 5.75 M3 7,254,883.62 41,715,580.82
- Plat Konsul Jendela dan Atap Lbr. 40cm 2.30 M3 6,615,843.62 15,242,903.70
279,885,306.14
III. PEKERJAAN KUSEN JENDELA DAN ALAT PENGGANTUNG
1 Pek, Kosen pintu dan Jendela alumunium (putih) 206.60 M1 201,788.10 41,689,422.29
2 Daun Jendela kaca 5 mm Rangka Alumunium 24.18 M2 1,216,660.04 29,414,459.79
3 Pemasangan Kaca Mati 5 mm jendela 46.48 M2 309,636.03 14,392,501.95
4 Engsel Jendela 56.00 Bh 57,594.02 3,225,265.12
5 Grendel Jendela 28.00 Bh 79,548.04 2,227,345.12
90,948,994.26
IV. PEKERJAAN PLAFOND
1 Pek. Rangka Plafond besi hollow 243.00 M2 135,547.28 32,937,989.04
2 Pek. Plafond Gipsum 243.00 M2 91,916.25 22,335,648.75
3 Pek. Pas Lis profil Gipsum 68.20 M1 54,571.84 3,721,799.49
58,995,437.28
V. PEKERJAAN LANTAI
1 Pek. Pagar Besi (Pengaman Void) 7.75 M' 938,658.02 7,274,599.69
2 Pek. Lantai Keramik Granit 60x60 213.38 M2 643,365.16 137,278,041.87
144,552,641.55
VI. PEKERJAAN ATAP
1 Pek. Rangka Atap Baja Ringan 236.96 M2 313,471.35 74,279,079.58
2 Pek. Atap Spandek 236.96 M2 109,290.81 25,897,170.43
3 Pek Lisplank GRC 6mm lbr.20 cm 86.30 M1 145,960.08 12,596,354.90
112,772,604.91
VII. PEKERJAAN CAT
1 Cat dinding Luar 270.04 M2 51,865.48 14,005,836.82
2 Cat dinding Dalam 167.34 M2 43,820.08 7,332,922.06
3 Cat Bidang Plafond 243.00 M2 27,088.75 6,582,566.25
27,921,325.13
VIII. PEKERJAAN INSTALASI LISTRIK
1 Titik Lampu + Instalasi 37.00 Titik 220,000.00 8,140,000.00
2 Lampu Philips 20 Watt 15.00 Bh 79,750.00 1,196,250.00
3 Lampu Philips 13 Watt 7.00 Bh 60,500.00 423,500.00
4 Lampu Philips 8 Watt 6.00 Bh 49,500.00 297,000.00
5 Pemasangan Kabel Listrik NYM 2.5 x 3 300.00 M1 19,475.00 5,842,500.00
6 Saklar Ganda 8.00 Bh 51,370.00 410,960.00
7 Saklar AC 8.00 Bh 110,000.00 880,000.00
8 Stop Kontak 7.00 Bh 51,370.00 359,590.00
9 Panel Box Sekring 30/40 1.00 Bh 979,000.00 979,000.00
10 Ranning Tes dan SLO 1.00 Ls 2,000,000.00 2,000,000.00
20,528,800.00
Sub Total ( B) 826,887,638.77

Ternate, 20 Maret 2017


Dibuat Oleh :
CV. KONTEKS DESAIN

SUTINI M.NUR, ST
Direktris
REKAPITULASI RENCANA ANGGARAN BIAYA

PROGRAM : PENINGKATAN SARANA DAN PRASARANA BADAN SAR NASIONAL


P E K E R J AA N : PENGEMBANGAN GEDUNG SERBAGUNA LANTAI 02
LO KASI : TERNATE
TAHUN ANGGARAN : 2017

NO. URAIAN PEKERJAAN JUMLAH HARGA

A PEKERJAAN PERSIAPAN Rp. 31,418,004.35


B PEKERJAAN LANTAI I
I. PEKERJAAN TALUD DAN PERBAIKAN SALURAN Rp. 28,858,976.99
II. PEKERJAAN KOLOM BANTU Rp. 43,862,112.95
III. PEKERJAAN PINTU, PARTISI DAN PLAFOND Rp. 116,175,541.56
IV. PEKERJAAN LANTAI DAN PASANGAN Rp. 102,484,905.96
V PEKERJAAN CAT Rp. 28,835,553.53
VI PEKERJAAN INSTALASI LISTRIK Rp. 21,478,640.00
Sub Total B Rp. 341,695,730.98
C PEKERJAAN LANTAI II
I. PEKERJAAN PASANGAN Rp. 91,282,529.49
II. PEKERJAAN STRUKTUR Rp. 279,885,306.14
III. PEKERJAAN KUSEN JENDELA DAN ALAT PENGGANTUNG Rp. 90,948,994.26
IV. PEKERJAAN PLAFOND Rp. 58,995,437.28
V PEKERJAAN LANTAI Rp. 144,552,641.55
VI PEKERJAAN ATAP Rp. 112,772,604.91
VII PEKERJAAN CAT Rp. 27,921,325.13
VIII PEKERJAAN INSTALASI LISTRIK Rp. 20,528,800.00

Sub Total C Rp. 826,887,638.77

J U M LAH = Rp. 1,200,001,374


PPN 10 % = Rp. 120,000,137
JUMLAH TOTAL = Rp. 1,320,001,512

PEMBULATAN = Rp. 1,320,000,000.00

TERBILANG : SATU MILYAR TIGA RATUS DUA PULUH JUTA RUPIAH

Ternate, 20 Maret 2017


Dibuat Oleh :
CV. KONTEKS DESAIN

SUTINI M.NUR, ST
Direktris
ESTIMATE ENGINEERING (EE)

PROYEK : PENINGKATAN SARANA DAN PRASARANA PERIKANAN


P E K E R J AA N : PEMBANGUNAN GEDUNG KOMERSIAL
LO KAS I : DUFA-DUFA KEC. TERNATE UTARA
TAHUN ANGGARAN : 2007

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH

I. PEKERJAAN PERSIAPAN
1 Pembersihan Perataan Tanah Lokasi 323.25 M2 18,062.00 5,838,541.50
2 Pengukuran/Pemasangan bouwplank 36.00 M1 99,830.80 3,593,908.80
3 Bangsal Kerja, Gudang, & Ruang Direksi 32.00 M2 1,518,667.15 48,597,348.80
4 Papan Nama Proyek 1.00 Ls 500,000.00 500,000.00
5 Mobilisasi/Demobilisasi 1.00 Ls 750,000.00 750,000.00
6 Dokumentasi dan Pelaporan 1.00 Ls 1,000,000.00 1,000,000.00
7 Pembersihan Akhir 1.00 Ls 500,000.00 500,000.00
60,779,799.10
II. PEKERJAAN TANAH
1 Galian tanah 211.48 M3 51,761.60 10,946,481.05
2 Mengurug kembali bekas galian 1/4 x 52.87 M3 24,819.96 1,312,223.84
3 Urugan Pasir dibawah pondasi 3.04 M3 473,300.40 1,437,886.62
4 Timbunan Tanah dibawah lantai dipadatkan 137.73 M3 64,702.00 8,911,082.95
5 Urugan Pasir dibawah lantai 31.18 M2 473,300.40 14,755,139.97
37,362,814.43
III. PEKERJAAN PASANGAN / BETON

Pas. Batu Kosong 4.46 M3 632,198.16 2,822,132.59


1 Pas. pondasi Batu Kali 1 : 4 15.28 M3 1,168,095.40 17,843,825.33
5 Pas. Dinding batu bata Trasraam 1 : 2 10.90 M3 199,006.86 2,169,672.29
1 Pas. dinding batu bata 1 : 5 251.87 M3 183,846.10 46,305,318.21
2 Plesteran Pondasi Dan Tangga 1:3 81.90 M2 70,043.54 5,736,566.25
2 Plesteran + Acian dinding Batu bata 1 : 4 503.74 M2 67,969.96 34,239,187.65
3 Plesteran + Acian dinding transram 1 : 2 21.81 M2 73,107.66 1,594,112.44
3 Plesteran Beton + Acian 1 : 3 18.34 M2 70,043.54 1,284,598.60
4 Pek.beton bertulang 1 : 2 : 3 :
- Sloof 25/30 ### 90.00 Kg 5.64 M3 5,645,634.60 31,841,379.14
- Kolom 10x10 ### 390.00 Kg 0.67 M3 11,786,955.90 7,838,325.67
- Kolom 35x35 170.00 Kg 2.02 M3 9,328,485.74 18,855,201.80
- Kolom 40x50 130.00 Kg 11.00 M3 9,037,849.74 99,416,347.14
- Balok Atap 15/20 ### 160.00 Kg 1.82 M3 11,470,311.56 20,818,615.48
- Balok Atap 20/25 ### 210.00 Kg 2.10 M3 12,110,835.56 25,432,754.68
- Balok Lantai 20/30 190.00 Kg 7.44 M3 11,696,625.80 87,022,895.95
- Plat Lantai 12 CM 170.00 Kg 18.29 M3 8,314,283.62 152,032,911.70
- Plat Atap 10 CM 180.00 Kg 1.32 M3 7,254,883.62 9,576,446.38
- Lisplank Beton Untuk Talang 10.00 Kg - M3 7,566,146.12 -
- Pondasi Telapak 130 X 130 170.00 Kg 8.79 M3 5,405,066.50 47,499,724.40
792,285,553.27
IV. PEKERJAAN KAYU DAN PENUTUP ATAP
1 Kosen pintu, Jendelah dan Ventilasi 4.82 M3 10,572,452.00 51,000,493.49
2 Daun Pintu Panel Papan Kls I 41.73 M2 745,262.00 31,099,783.26
3 Daun Pintu tripleks 0,30 mm Lapis Seng Plat 0.03 5.60 M2 603,927.80 3,381,995.68
4 Daun Jendela Kaca 5 mm Bingkai Kayu Kls I 45.00 M2 599,415.60 26,973,702.00
5 Pekerjaan Kaca 3 mm 31.31 M2 309,636.03 9,693,960.97
4 Kuda-kuda dan Konsol Kayu Kls I - M2 9,451,708.00 -
6 Gording 5/10 Kayu Kls II A - M2 6,407,928.00 -
6 Skor Angin Kayu 5/10 Kls II - M2 6,407,928.00 -
7 Kasau dan Ring Genteng - M2 109,496.10 -
8 Lysplank Kayu 1/30 Kls I - M2 299,111.20 -
9 Atap Genteng Metal Roof - M2 106,569.44 -
10 Bubungan Genteng Metal Roof 37.25 M1 411,208.10 15,317,501.73
11 Plafond Tripleks 5 mm + Rangka Kayu Kls II 456.75 M2 148,188.80 67,685,234.40
12 Lis Plafond Profil 2/5 Cm 189.60 M1 54,571.84 10,346,820.86
13 Mur Baut - Bh 31,536.01 -
14 Angker Baut - Bh 31,536.01 -
15 Beugel - Bh 31,536.01 -
215,499,492.39
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH

V. PEKERJAAN LANTAI
1 Lantai Rabat Beton Tebal 5 cm camp. 1 : 3 : 6 311.75 M2 55,391.20 17,268,206.60
4 Plesteran dan acian Lantai 311.75 M2 23,106.28 7,203,384.04
6 Pek. Lantai Keramik 40x40 486.00 M2 383,325.16 186,296,029.70
7 Pekerjaan Lantai Keramik WC/KM 20x20 2.40 M2 265,515.16 637,236.39
8 Pekerjaan Dinding WC/KM 20x20 67.20 M2 483,632.64 32,500,113.41
12 Pekerjaan Dinding Keramik 40x40 (63.52) M2 383,325.16 (24,348,814.42)

219,556,155.73
VI. PEKERJAAN CAT
1 Cat dinding dgn Matex 2x termasuk 1x Plamir (Baru) 667.50 M2 43,820.08 29,249,902.45
2 Cat Plafond dgn Matex 2x termasuk 1x Plamir (Baru) 456.75 M2 43,820.08 20,014,820.89
3 Cat Pintu, Jendela, Kosen, Ventilasi dan Lysplank 120.60 M2 27,088.75 3,266,838.24
4 3x dgn Glotex/Platone (Baru)
5 Cat Atap Seng - M2 35,812.15 -

52,531,561.57
VII. PEKERJAAN KUNCI
1 - Kunci Pintu 2 Slaag 32.00 Bh 241,614.12 7,731,651.84
2 Kunci Pintu KM/WC 1 Slaag Merk Ancor 4.00 Bh 214,462.60 857,850.40
2 Engsel Pintu Kuningan Kwalitas Baik 144.00 Bh 77,206.03 11,117,668.32
3 Engsel Jendela Dan Ventilasi Kuningan Kwalitas Baik 150.00 Bh 57,594.02 8,639,103.00
4 Kait Angin Kwalitas Baik 150.00 Bh 79,548.04 11,932,206.00
5 Grendel Pintu 96.00 Bh 79,548.04 7,636,611.84
6 Grendel Jendela 150.00 Bh 79,548.04 11,932,206.00
59,847,297.40

VIII. PEKERJAAN INSTALASI LISTRIK

1 Titik Lampu + Instalasi - Bh 220,000.00 -

2 Lampu Jari-jari 25 Watt - Bh 60,500.00 -

3 Lampu Pijar 25 Watt - Bh 4,070.00 -

4 Saklar Ganda - Bh 12,760.00 -

6 Stop Kontak - Bh 51,370.00 -

9 MCB - Bh 80,000.00 -

IX PEKERJAAN SANITASI

2 Kloset Duduk INA / TOTO ( Lengkap ) - Bh 1,974,514.30 -

3 Kran Air Bersih Kualitas Standard - Bh 60,087.70 -

4 Saringan Pemb, Air Kotor/Avour Alumunium - Bh 46,525.20 -

5 Bak Tampungan Air BersIh - Bh 5,288,992.72 -

6 Pipa Paralon PVC dia. 3" - M 1


119,651.66 -

7 Pipa Paralon PVC dia. 1/2" - M1 26,604.07 -

8 Septic Tank dan Peresapan Lengkap - Bh 5,500,000.00 -

-
REKAPITULASI RENCANA ANGGARAN BIAYA

PROYEK : PENINGKATAN SARANA DAN PRASARANA PERIKANAN


P E K E R J AA N : PEMBANGUNAN GEDUNG KOMERSIAL
LO KAS I : DUFA-DUFA KEC. TERNATE UTARA
TAHUN ANGGARAN : 2007

NO. URAIAN PEKERJAAN JUMLAH HARGA

I. PEKERJAAN PERSIAPAN Rp. 60,779,799.10

II. PEKERJAAN TANAH Rp. 37,362,814.43

III. PEKERJAAN PASANGAN / BETON Rp. 792,285,553.27

II PEKERJAAN KAYU Rp. 215,499,492.39

III PEKERJAAN LANTAI Rp. 219,556,155.73

IV PEKERJAAN CAT Rp. 52,531,561.57

V PEKERJAAN KUNCI Rp. 59,847,297.40

VIII. PEKERJAAN INSTALASI LISTRIK Rp. -

IX PEKERJAAN SANITASI Rp. -

J U M LAH = Rp. 1,437,862,673.89

PPN 10 % = Rp. 143,786,267.39


IMB = Rp. 3,937,500.00
JUMLAH TOTAL = Rp. 1,585,586,441.28

PEMBULATAN = Rp. 1,585,586,000.00

TERBILANG : ENAM RATUS SEMBILAN PULUH EMPAT JUTA DELAPAN RATUS DELAPAN BELAS RIBU RUPIAH

TERNATE, FEBRUARI 2006

MENYETTUUI
PEMBANTU REKTOR
BIDANG ADMINISTRASI DAN KEUANGAN

………………………………………………………
NIP………………………………..
DAFTAR PERHITUNGAN VOLUME

PROYEK : PENINGKATAN SARANA DAN PRASARANA PERIKANAN


PEKERJAAN : PEMBANGUNAN GEDUNG KOMERSIAL
LOKASI : DUFA-DUFA KEC. TERNATE UTARA
TAHUN ANGGARAN : 2007

PEKERJAAN TANAH
1. GALIAN TANAH PONDASI
GALIAN PONDASI JALUR 1
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG VOLUME
0.70 M1 0.70 M1 0.63 M1 0.441 M2 86.80 M1 38.28 M3
GALIAN PONDASI JALUR 1
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG VOLUME
0.00 M1 0.00 M1 0.00 M1 0.00 M2 0.00 M1 0.00 M3
GALIAN PONDASI TELAPK 1
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG JUMLAH VOLUME
1.30 M1 1.30 M1 5.00 M1 6.50 M2 1.30 M1 20.00 Bh 169.00 M3
GALIAN PONDASI TELAPAK 2
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG JUMLAH VOLUME
0.00 M1 0.00 M1 0.00 M1 0.00 M2 0.00 M1 0.00 Bh 0.00 M3
GALIAN PONDASI RABAT
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG VOLUME
0.15 M1 0.15 M1 0.40 M1 0.06 M2 70.00 M1 4.20 M3
GALIAN SALURAN
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG VOLUME
0.00 M1 0.00 M1 0.00 M1 0.00 M2 0.00 M1 0.00 M3
211.48 M3
2. URUGAN PASIR
URUGAN PASIR DIBAWAH PONDASI 1
LEBAR TEBAL LUAS PANJANG VOLUME
0.70 M1 0.05 M1 0.04 M2 86.80 M1 3.04 M3
URUGAN PASIR DIBAWAH PONDASI 2
LEBAR TEBAL LUAS PANJANG VOLUME
0.00 M1 0.05 M1 0.00 M2 0.00 M1 0.00 M3
3.04 M3
URUGAN PASIR DIBAWAH LANTAI 1
LEBAR TEBAL LUAS PANJANG VOLUME
10.00 M1 0.10 M1 1.00 M2 20.00 M1 20.00 M3
URUGAN PASIR DIBAWAH LANTAI 2
LEBAR TEBAL LUAS PANJANG VOLUME
3.50 M1 0.10 M1 0.35 M2 6.00 M1 2.10 M3
URUGAN PASIR DIBAWAH LANTAI TERAS
LEBAR TEBAL LUAS PANJANG VOLUME
1.50 M1 0.10 M1 0.15 M2 60.50 M1 9.08 M3
31.18 M3
2. URUGAN TANAH
URUGAN Tanah DIBAWAH LANTAI 1
LEBAR TEBAL 1 TEBAL 2 LUAS PANJANG VOLUME
10.00 M1 0.50 M1 0.50 M1 5.00 M2 20.00 M1 100.00 M3
URUGAN Tanah DIBAWAH LANTAI 2
LEBAR TEBAL 1 TEBAL 2 LUAS PANJANG VOLUME
3.50 M1 0.50 M1 0.50 M1 1.75 M2 6.00 M1 10.50 M3
URUGAN Tanah DIBAWAH LANTAI TERAS
LEBAR TEBAL 1 TEBAL 2 LUAS PANJANG VOLUME
1.50 M1 0.30 M1 0.30 M1 0.45 M2 60.50 M1 27.23 M3
137.73 M3
PEKERJAAN BETON
1. PASANGAN BATU KOSONG
PAS. BATU KOSONG 1
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG VOLUME
0.60 M1 0.60 M1 0.15 M1 0.09 M2 49.60 M1 4.464 M3
PAS. BATU KOSONG 2
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG VOLUME
0.00 M1 0.00 M1 0.15 M1 0 M2 0.00 M1 0 M3
4.46 M3
2. PASANGAN BATU KALI
PAS. BATU KALI 1
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG VOLUME
0.30 M1 0.60 M1 0.55 M1 0.2475 M2 49.60 M1 12.276 M3
PAS. BATU KALI 2
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG VOLUME
0.15 M1 0.15 M1 0.40 M1 0.06 M2 50.00 M1 3 M3
15.276 M3
PAS. BATU KALI UNTUK RABAT KELILING
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG VOLUME
0.00 M1 0.00 M1 0.55 M1 0 M2 0.00 M1 0 M3
PAS. BATU KALI UNTUK SALURAN
LBR ATAS LBR BAWAH TINGGI LUAS PANJANG VOLUME
0.00 M1 0.00 M1 0.00 M1 0 M2 0.00 M1 0 M3
15.28 M3

2. PASANGAN DINDING BATU-BATA DAN PLESTERAN


PAS. BATU BATA CAMP. 1:2 TRASRAM
TINGGI PANJANG LUAS KOTOR LUBANG LUAS BERSIH TEBAL VOLUME
0.35 M1 94.80 M1 33.18 M2 2.03 M2 31 M2 0.12 M1 10.9025 M3
PAS. BATU BATA CAMP. 1:5
TINGGI PANJANG LUAS KOTOR LUBANG LUAS BERSIH TEBAL VOLUME
4.00 M1 94.80 M1 379.20 M2 127.33 M2 251.87 M2 0.12 M1 251.87 M3
PLESTERAN PONDASI
TING. RATA-2 PANJANG VOLUME
1.58 M1 52 M1 81.9 M2
PLESTERAN BETON
L. KLM 10x10 L. KLM 15x15 L. KLM 12x20 L. KLM 20x20 VOLUME
13.30 M2 5.04 M2 0.00 M2 0.00 M2 18.34 M2

2. SLOOF
- Sloof 12/15
LEBAR TINGGI LUAS PANJANG VOLUME
0.12 M1 0.15 M1 0.02 M2 - M1 0.00 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 06 Jml Besi 12 Pjg Besi 12 Kg Besi 12 KG BESI / M3 DIBULATKAN
55.56 277.78 0.44 134.44 29.85 5.00 277.78 249.44 279.29 KG 270.00 KG
- Sloof 15/20
LEBAR TINGGI LUAS PANJANG VOLUME
0.15 M1 0.20 M1 0.03 M2 38.85 M1 1.17 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 06 Jml Besi 12 Pjg Besi 12 Kg Besi 12 KG BESI / M3 DIBULATKAN
33.33 166.67 0.6 110.00 24.42 4.00 133.33 119.73 144.15 KG 140.00 KG

- Sloof 25/30
LEBAR TINGGI LUAS PANJANG VOLUME
0.20 M1 0.30 M1 0.06 M2 94.00 M1 5.64 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 06 Jml Besi 12 Pjg Besi 12 Kg Besi 12 KG BESI / M3 DIBULATKAN
16.67 83.33 0.9 82.50 18.32 5.00 83.33 74.83 93.15 KG 90.00 KG
2. KOLOM
- Kolom 10x10
LEBAR PANJANG LUAS TINGGI JUMLAH VOLUME
0.10 M1 0.10 M1 0.01 M2 3.50 M1 19.00 Bh 0.67 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 06 Jml Besi 12 Pjg Besi 12 Kg Besi 12 KG BESI / M3 DIBULATKAN
100.00 500.00 0.3 165.00 36.63 4.00 400.00 359.20 395.83 KG 390.00 KG
- Kolom 15x15
LEBAR PANJANG LUAS TINGGI JUMLAH VOLUME
0.15 M1 0.15 M1 0.02 M2 1.00 M1 14.00 Bh 0.32 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 06 Jml Besi 12 Pjg Besi 12 Kg Besi 12 KG BESI / M3 DIBULATKAN
44.44 222.22 0.5 122.22 27.13 4.00 177.78 159.64 186.78 KG 180.00 KG
- Kolom 12x20
LEBAR PANJANG LUAS TINGGI JUMLAH VOLUME
0.12 M1 0.20 M1 0.02 M2 0.00 M1 0.00 Bh 0.00 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 06 Jml Besi 12 Pjg Besi 12 Kg Besi 12 KG BESI / M3 DIBULATKAN
41.67 208.33 0.54 123.75 27.47 4.00 166.67 149.67 177.14 KG 170.00 KG
- Kolom Bulat 30x30
LEBAR PANJANG LUAS TINGGI JUMLAH VOLUME
0.27 M1 0.27 M1 0.07 M2 0.00 M1 0.00 Bh 0.00 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 06 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
14.24 71.20 0.96 75.19 16.69 0.00 0.00 0.00 8.00 113.92 179.88 196.57 170.00 KG
- Kolom 30x30
LEBAR PANJANG LUAS TINGGI JUMLAH VOLUME
0.30 M1 0.30 M1 0.09 M2 5.00 M1 14.00 Bh 6.30 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
11.11 55.56 1.1 67.22 26.55 0.00 0.00 0.00 8.00 88.89 140.36 166.91 160.00 KG
- Kolom 35x35
LEBAR PANJANG LUAS TINGGI JUMLAH VOLUME
0.35 M1 0.35 M1 0.12 M2 5.50 M1 3.00 Bh 2.02 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
8.16 40.82 1.3 58.37 23.06 0.00 0.00 0.00 12.00 97.96 154.68 177.73 170.00 KG
- Kolom 40x50
LEBAR PANJANG LUAS TINGGI JUMLAH VOLUME
0.40 M1 0.50 M1 0.20 M2 5.50 M1 10.00 Bh 11.00 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 19 Pjg Besi 19 Kg Besi 19 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
5.00 33.33 1.7 62.33 24.62 0.00 0.00 0.00 14.00 70.00 110.53 135.15 130.00 KG

2. BALOK
- Balok Latei 8/15
LEBAR TINGGI LUAS PANJANG VOLUME
0.08 M1 0.15 M1 0.01 M2 77.90 M1 0.93 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 06 Jml Besi 12 Pjg Besi 12 Kg Besi 12 KG BESI / M3 DIBULATKAN
83.33 416.67 0.36 165.00 36.63 4.00 333.33 299.33 335.96 KG 330.00 KG
- Balok Atap 15/20
LEBAR TINGGI LUAS PANJANG VOLUME
0.15 M1 0.20 M1 0.03 M2 60.50 M1 1.82 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 06 Jml Besi 12 Pjg Besi 12 Kg Besi 12 KG BESI / M3 DIBULATKAN
33.33 333.33 0.6 220.00 48.84 4.00 133.33 119.73 168.57 KG 160.00 KG
- Balok Atap 10/20
LEBAR TINGGI LUAS PANJANG VOLUME
0.10 M1 0.20 M1 0.02 M2 36.00 M1 0.72 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 06 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
50.00 500.00 0.5 275.00 61.05 4.00 200.00 179.60 - 0.00 0.00 240.65 240.00 KG
- Balok Atap 20/25
LEBAR TINGGI LUAS PANJANG VOLUME
0.20 M1 0.25 M1 0.05 M2 42.00 M1 2.10 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 06 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
20.00 133.33 0.8 117.33 26.05 0.00 0.00 0.00 6.00 120.00 189.48 215.53 210.00 KG
- Balok Lantai 20/30
LEBAR TINGGI LUAS PANJANG VOLUME
0.20 M1 0.30 M1 0.06 M2 124.00 M1 7.44 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
16.67 83.33 0.9 82.50 32.59 2.00 33.33 29.93 5.00 83.33 131.58 194.10 190.00 KG
- Balok Lantai 25/40
LEBAR TINGGI LUAS PANJANG VOLUME
0.25 M1 0.40 M1 0.10 M2 86.50 M1 8.65 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
10.00 66.67 1.2 88.00 34.76 2.00 20.00 17.96 5.00 50.00 78.95 131.67 130.00 KG
- Balok Lantai 35/70
LEBAR TINGGI LUAS PANJANG VOLUME
0.35 M1 0.70 M1 0.25 M2 18.10 M1 4.43 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
4.08 27.21 2 59.86 23.65 4.00 16.33 14.66 9.00 36.73 58.00 96.31 90.00 KG
- Balok Lantai 30/65
LEBAR TINGGI LUAS PANJANG VOLUME
0.30 M1 0.65 M1 0.20 M2 20.00 M1 3.90 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 19 Pjg Besi 19 Kg Besi 19 KG/M3 DIBULATKAN
5.13 34.19 1.8 67.69 26.74 4.00 20.51 18.42 10.00 51.28 114.15 159.31 150.00 KG
- Balok Luifel Lantai
LEBAR TINGGI LUAS PANJANG VOLUME
0.00 M1 0.00 M1 0.00 M2 0.00 M1 0.00 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
#DIV/0! #DIV/0! -0.1 #DIV/0! #DIV/0! 0.00 #DIV/0! #DIV/0! 5.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0! KG
- Balok Atap 11/15
LEBAR TINGGI LUAS PANJANG VOLUME
0.00 M1 0.00 M1 0.00 M2 0.00 M1 0.00 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
#DIV/0! #DIV/0! -0.1 #DIV/0! #DIV/0! 0.00 #DIV/0! #DIV/0! - #DIV/0! #DIV/0! #DIV/0! #DIV/0! KG
- Balok Atap 20/30
LEBAR TINGGI LUAS PANJANG VOLUME
0.00 M1 0.00 M1 0.00 M2 0.00 M1 0.00 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
#DIV/0! #DIV/0! -0.1 #DIV/0! #DIV/0! 0.00 #DIV/0! #DIV/0! - #DIV/0! #DIV/0! #DIV/0! #DIV/0! KG
- Balok Atap 20/40
LEBAR TINGGI LUAS PANJANG VOLUME
0.00 M1 0.00 M1 0.00 M2 0.00 M1 0.00 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
#DIV/0! #DIV/0! -0.1 #DIV/0! #DIV/0! 0.00 #DIV/0! #DIV/0! - #DIV/0! #DIV/0! #DIV/0! #DIV/0! KG
- Balok Atap 30/40
LEBAR TINGGI LUAS PANJANG VOLUME
0.30 M1 0.40 M1 0.12 M2 18.40 M1 2.21 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
8.33 55.56 1.3 79.44 31.38 4.00 33.33 29.93 8.00 66.67 105.27 166.58 160.00 KG
- Balok Atap 30/50
LEBAR TINGGI LUAS PANJANG VOLUME
0.00 M1 0.00 M1 0.00 M2 0.00 M1 0.00 M3
Pjg/KG (M1) Jml Bgl (Bh) Pjg Bgl/Bh Pjg Bgl Ttl Kg Bgl 08 Jml Besi 12 Pjg Besi 12 Kg Besi 12 Jml Besi 16 Pjg Besi 16 Kg Besi 16 KG/M3 DIBULATKAN
#DIV/0! #DIV/0! -0.1 #DIV/0! #DIV/0! 0.00 #DIV/0! #DIV/0! - #DIV/0! #DIV/0! #DIV/0! #DIV/0! KG
2. PLAT LANTAI
- Plat Lantai 12 CM
LEBAR SATUAN TINGGI LUAS PANJANG LEBAR VOLUME
1.00 M1 0.11 M1 0.11 M2 1.00 M1 174.15 M1 18.29 M3
Pjg/KG (M1) JML B H PJG B H ST KG B H KG B.H/M3 JML B V PJG B V ST KG B V KG B.V/M3 KG/M3 DIBULATKAN
9.52 141 140.78 0.62 86.84 16 150.16 0.62 92.6258632 179.47 170.00 KG
- Plat Atap 10 CM
LEBAR SATUAN TINGGI LUAS PANJANG LEBAR VOLUME
1.00 M1 0.10 M1 0.10 M2 1.00 M1 13.20 M1 1.32 M3
Pjg/KG (M1) JML B H PJG B H ST KG B H KG B.H/M3 JML B V PJG B V ST KG B V KG B.V/M3 KG/M3 DIBULATKAN
10.00 148 147.77 0.62 91.15 16 157.67 0.62 97.26 188.41 180.00 KG
2. LISPLANK
- Lisplank Beton Untuk Talang
LEBAR SATUAN lebar LUAS PANJANG LEBAR VOLUME
1.00 M1 1.00 M1 1.00 M2 0.00 M1 1.00 M1 0.00 M3
Pjg/KG (M1) JML B H PJG B H ST KG B H KG B.H/M3 JML B V PJG B V ST KG B V KG B.V/M3 KG/M3 DIBULATKAN
1.00 16 16 0.395 6.22 16 15.77 0.395 6.22 12.45 10.00 KG
- Lisplank Beton
LEBAR SATUAN lebar LUAS PANJANG LEBAR VOLUME
1.00 M1 0.60 M1 0.60 M2 62.50 M1 0.07 M1 2.63 M3
Pjg/KG (M1) JML B H PJG B H ST KG B H KG B.H/M3 JML B V PJG B V ST KG B V KG B.V/M3 KG/M3 DIBULATKAN
1.67 26 26 62.500 1596.53 16 26.28 0.395 10.37 1606.90 1600.00 KG

2. PONDASI TELPAK
- Pondasi Telapak 130 X 130
LEBAR SATUAN Tinggi LUAS PANJANG LEBAR JUMLAH VOLUME
1.00 M1 0.40 M1 0.40 M2 1.30 M1 1.30 M1 13.00 8.79 M3
Pjg/KG (M1) JML B H PJG B H ST KG B H KG B.H/M3 JML B V PJG B V ST KG B V KG B.V/M3 KG/M3 DIBULATKAN
2.50 56 56 1.579 88.59 23 57.75 1.579 91.20 179.79 170.00 KG

- Pondasi Telapak 100 X 100


LEBAR SATUAN Tinggi LUAS PANJANG LEBAR JUMLAH VOLUME
1.00 M1 0.40 M1 0.40 M2 1.00 M1 1.00 M1 4.00 1.60 M3
Pjg/KG (M1) JML B H PJG B H ST KG B H KG B.H/M3 JML B V PJG B V ST KG B V KG B.V/M3 KG/M3 DIBULATKAN
2.50 56 56 0.888 49.83 23 57.75 1.579 91.20 141.03 140.00 KG

2. TANGGA BETON
- Tangga Beton/Pond.Tangga & Blk Bordes
LEBAR SATUAN Tinggi LUAS PANJANG LEBAR JUMLAH VOLUME
1.00 M1 0.15 M1 0.15 M2 9.00 M1 1.10 M1 1 1.49 M3
Pjg/KG (M1) JML B H PJG B H ST KG B H KG B.H/M3 JML B V PJG B V ST KG B V KG B.V/M3 KG/M3 DIBULATKAN
6.67 99 99 0.617 60.99 16 105.11 0.617 64.84 125.83 120.00 KG

PEKERJAAN KAYU DAN ATAP


1. KOSEN PENTU, JENDELAN DAN VENTILASI
- PV.1
Panjang Kayu Vert Panjang Kayu Hors Panjang Kayu Total Ukuran Kayu Jumlah Kosen Volume
5.04 M1 2.04 M1 7.08 M1 0.06 X 0.12 15.00 Bh 0.76 M3
- PV.2
Panjang Kayu Vert Panjang Kayu Hors Panjang Kayu Total Ukuran Kayu Jumlah Kosen Volume
5.04 M1 2.24 M1 7.28 M1 0.08 X 0.12 17.00 Bh 1.19 M3
- PV.3
Panjang Kayu Vert Panjang Kayu Hors Panjang Kayu Total Ukuran Kayu Jumlah Kosen Volume
0.84 M1 0.44 M1 1.28 M1 0.08 X 0.12 - Bh - M3
- P.1
Panjang Kayu Vert Panjang Kayu Hors Panjang Kayu Total Ukuran Kayu Jumlah Kosen Volume
4.24 M1 1.02 M1 5.26 M1 0.08 X 0.12 4.00 Bh 0.20 M3
- JV.1
Panjang Kayu Vert Panjang Kayu Hors Panjang Kayu Total Ukuran Kayu Jumlah Kosen Volume
3.96 M1 2.56 M1 6.52 M1 0.08 X 0.12 41.00 Bh 2.57 M3
- JV.2
0.18 M1 0.58 M1 0.76 M1 0.08 X 0.12 - Bh - M3
- JV.3
Panjang Kayu Vert Panjang Kayu Hors Panjang Kayu Total Ukuran Kayu Jumlah Kosen Volume
0.18 M1 0.58 M1 0.76 M1 0.08 X 0.12 - Bh - M3
- JV.4
Panjang Kayu Vert Panjang Kayu Hors Panjang Kayu Total Ukuran Kayu Jumlah Kosen Volume
0.18 M1 0.58 M1 0.76 M1 0.08 X 0.12 - Bh - M3
- JV.5
Panjang Kayu Vert Panjang Kayu Hors Panjang Kayu Total Ukuran Kayu Jumlah Kosen Volume
0.18 M1 0.58 M1 0.76 M1 0.08 X 0.12 - Bh - M3
- V.1
Panjang Kayu Vert Panjang Kayu Hors Panjang Kayu Total Ukuran Kayu Jumlah Kosen Volume
0.84 M1 1.84 M1 2.68 M1 0.08 X 0.12 4.00 Bh 0.10 M3
- V.2
Panjang Kayu Vert Panjang Kayu Hors Panjang Kayu Total Ukuran Kayu Jumlah Kosen Volume
0.52 M1 0.52 M1 1.04 M1 0.08 X 0.12 - Bh - M3
- V.3
Panjang Kayu Vert Panjang Kayu Hors Panjang Kayu Total Ukuran Kayu Jumlah Kosen Volume
0.12 M1 0.52 M1 0.64 M1 0.08 X 0.12 - Bh - M3
4.82 M3

1. KOSEN PENTU, JENDELAN DAN VENTILASI


- Pintu Panel
T. PV.1(M) L. PV.1(M) Luas PV.1 JML (Bh) T. PV.2(M) L. PV.2(M) Luas PV.1 JML (Bh) T. PV.3(M) L. PV.3(M) Luas PV.1 JML (Bh) VOLUME
0.80 0.80 0.64 15.00 2.10 0.90 1.89 17.00 - - - - 41.73 M2
- Pintu Double Triplex
T. PV.1(M) L. PV.1(M) Luas PV.1 JML (Bh) T. PV.2(M) L. PV.2(M) Luas PV.1 JML (Bh) T. PV.3(M) L. PV.3(M) Luas PV.1 JML (Bh) VOLUME
2.10 0.80 1.68 - 2.10 0.90 1.89 - - - - - - M2
- Pintu Double Plaiwood
T. PV.1(M) L. PV.1(M) Luas PV.1 JML (Bh) T. PV.2(M) L. PV.2(M) Luas PV.1 JML (Bh) T. PV.3(M) L. PV.3(M) Luas PV.1 JML (Bh) VOLUME
2.10 0.80 1.68 - 2.10 0.90 1.89 - - - - - - M2
- Pintu Triplex Douwbel Lapis Seng
T. P.1 (M) L. P.1 (M) Luas P.1 JML (Bh) VOLUME
2.00 0.70 1.40 4.00 5.60 M2
- Daun Jendelan dan Ventilasi
JV.1 JV. 2 JV. 3
Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen T. JV.3 (M) L. JV.3 (M) Luas JV.3 JML (Bh)
1.80 0.60 1.08 41.00 1.00 - - - - - - - - -
JV. 4 JV. 5
Lng Kosen Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen VOLUME
- - - - - - - - - - - 44.28 M2
- Pekerjaan Kaca
JV.1 JV. 2 JV. 3
Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen T. JV.3 (M) L. JV.3 (M) Luas JV.3 JML (Bh)
1.66 0.46 0.76 41.00 1.00 (0.14) (0.14) 0.02 - - (0.14) (0.14) 0.02 -
JV. 4 JV. 5
Lbg Kosen Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen VOLUME
- (0.14) (0.14) 0.02 - - (0.14) (0.14) 0.02 - - 31.31 M2
- Pekerjaan ventilasi ( Bingkai Kaca)
V.1 JV. 2
Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen VOLUME
0.30 0.60 0.18 4.00 1.00 0.40 0.60 0.24 - - 0.72 M2
- Pekerjaan ventilasi ( Kaca Mati )
V.1 JV. 2
Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen Tinggi (M) Lebar (M) Luas (M2) JML (Bh) Lbg Kosen
0.30 0.60 0.18 - 1.00 0.40 0.60 0.24 - -
V.3
Tinggi (M) Lebar (M) Luas (M2) JML (Bh) VOLUME
- - - - - M2

1. KUDA-KUDA
- Pek. Kuda-Kuda Type 1
Tinggi Kayu Lebar Kayu Luas Kayu Panjang Kayu Jumlak Kuda-Kuda VOLUME
0.12 M1 0.08 M1 0.01 M1 - M1 - Bh - M3
- Pek. Kuda-Kuda Type 2
Tinggi Kayu Lebar Kayu Luas Kayu Panjang Kayu Jumlak Kuda-Kuda VOLUME
- M1 - M1 - M1 - M1 - Bh - M3
- Pek. Kuda-Kuda Type 3
Tinggi Kayu Lebar Kayu Luas Kayu Panjang Kayu Jumlak Kuda-Kuda VOLUME
- M1 - M1 - M1 - M1 - Bh - M3

1. GORDING
- Gording Type 1
Lebar Atas Lebar Bawah Panjang Rata2 Tinggi Jumlah Gording Luas Kayu Dan Jlh Jenis VOLUME
- M1 - M1 - M1 - M1 1.00 Bh - - - M3
- Gording Type 2
Lebar Atas Lebar Bawah Panjang Rata2 Tinggi Jumlah Gording Luas Kayu VOLUME
- M1 - M1 - M1 - M1 1.00 Bh - - - M3
- Gording Type 2
Lebar Atas Lebar Bawah Panjang Rata2 Tinggi Jumlah Gording Luas Kayu VOLUME
- M1 - M1 - M1 - M1 1.00 Bh - - - M3
- Gording Type 2
Lebar Atas Lebar Bawah Panjang Rata2 Tinggi Jumlah Gording Luas Kayu VOLUME
- M1 - M1 - M1 - M1 1.00 Bh - - - M3
1. BALOK ANGIN
- Pek. Balok Angin
Tinggi Lebar Panjang Jumlah Jumlak Kuda-Kuda Luas Kayu VOLUME
- M1 - M1 - M1 - Bh - M2 - M3

- Pekerjaan Lisplank Type 1


P.S.Ka (M) P.S.Ki (M) P.Blkg (M) P.Dpn (M) Lebar (M) Lapis (M) P. Total (M) Luas (2) VOLUME
- - - - - - - - - M2
- Pekerjaan Lisplank Type 1
P.S.Ka (M) P.S.Ki (M) P.Blkg (M) P.Dpn (M) Lebar (M) Lapis (M) P. Total (M) Luas (2) VOLUME
- - - - - - - - - M2

Atap Genteng Metal Roof


Luas Type 1 Luas Type 2 Luas Type 3 Luas Type 4 Luas Type 5 VOLUME
- M2 - M2 - M2 - M2 - M2 - M2
Bubungan Genteng Metal Roof
Panjang Horison Panj. Diagonal 1 Panj. Diagonal 2 Panj. Diagonal 3 Panj. Diagonal 4 VOLUME
15.25 M1 22.00 M1 - M1 - M1 - M1 37.25 M1

- Pek. Plafond dan Rangka kayu


Luas Plafond 1 Luas Plafond 1 Luas Plafond 1 VOLUME
388.50 M1 68.25 M1 - M1 456.75 M1

- Pek. List Profil


Panjang Dinding Panjang Lisplank VOLUME
189.60 M1 - M1 189.60 M1

- Pek. Mur-Baut
VOLUME
- M1
- Pek. Angker-Baut
VOLUME
- M1
- Pek. Begel
VOLUME
- M1

- Rabat Beton Lantai


Luas Lantai Type 1 Luas Lantai Type 1 Luas Lantai Type 1 VOLUME
200.00 M2 21.00 M2 90.75 M2 311.75 M1

- Rabat Keliling
Panjamg Lebar Tebal VOLUME
- M1 1.00 M1 1.00 M1 - M2
- Rabat Saluran
Panjamg Lebar Tebal VOLUME
- M2 0.20 M2 1.00 M2 - M2
- Lantai Keramik WC/KM
Luas Type 1 Luas Type 2 Luas Type 3 VOLUME
2.40 M2 - M2 - M2 2.40 M2
- Dinding Keramik WC/KM
Luas Type 1 Luas Type 2 Luas Type 3 VOLUME
10.26 M2 - M2 - M2 10.26 M2
-Pekerjaan Dinding Keramik 40/40
Tinggi Panjang Luas Lubang VOLUME
1.20 M1 43.00 M1 51.60 M2 115.12 (63.52) M2

- Kunci Pintu 2 Slaag


PV.1 PV.2 PV.2 VOLUME
15.00 Bh 17.00 Bh - Bh 32.00 Bh

- Kunci Pintu 1 Slaag


P.1 VOLUME
4.00 Bh 4.00 Bh
- Engsel Pintu
PV.1 PV.2 PV.3 P.1 VOLUME
15.00 Bh 17.00 Bh - Bh 16.00 Bh 144.00 Bh
- Engsel Jendelah dan Ventilasi
PV.1 PV.2 PV.3 JV.1 JV.2 JV.3 JV.4
30.00 Bh 34.00 Bh - Bh 82.00 Bh - Bh - Bh - Bh
JV.5 V.1 V.2 VULUME
- Bh 4.00 Bh - Bh 150.00 Bh
REKAPITULASI
ANALISA BIAYA KONSTRUKSI
BANGUNAN GEDUNG DAN PERUMAHAN

BIAYA (Rp.)
NO URAIAN JENIS PEKERJAAN KETERANGAN
BAHAN TENAGA TOTAL

A PEKERJAAN PERSIAPAN

1 1 m' Pagar Sementara dari kayu tinggi 2 meter 376,168.40 76,788.80 452,957.20
2 1 m' Pagar Sementara dari Dari Seng Gelombang tinggi 2 meter 477,923.40 76,788.80 554,712.20
3 1 m' Pagar Sementara dari Kawat Duri tinggi 1,8 meter 419,771.20 65,128.80 484,900.00
4 1 m' Pengukuran dan Pemasangan Bouwplank 73,736.60 26,094.20 99,830.80
5 1 m2 Pembuatan Kantor Sementara, dengan Lantai Plesteran 12,945,126.70 653,422.00 13,598,548.70
6 1 m2 Pembuatan Gudang Semen dan Alat - alat 1,119,785.15 398,882.00 1,518,667.15
7 1 m2 Membersihkan Lapangan dan Perataan - 18,062.00 18,062.00
8 1 m2 Pembuatan Bak adukan Ukuran (40 x 50 x 20) cm 3,997,090.40 36,987.06 4,034,077.46
9 1 m2 Pembuatan Jalan Sementara 80,564.00 123,002.00 203,566.00
10 1 m3 Bongkaran Beton Bertulang - 820,009.52 820,009.52
11 1 m3 Bongkaran Dinding Tembok Bata Merah - 781,597.52 781,597.52

B PEKERJAAN TANAH

1 1 m3 Galian Tanah Biasa Sedalam 1 Meter - 51,761.60 51,761.60


2 1 m3 Galian Tanah Biasa Sedalam 2 Meter - 67,989.68 67,989.68
3 1 m3 Galian Tanah Biasa Sedalam 3 Meter - 95,047.92 95,047.92
4 1 m3 Galian Tanah Keras Sedalam 1 Meter - 80,877.50 80,877.50
5 1 m3 Galian Tanah Cadas Sedalam 1 Meter - 161,755.00 161,755.00
6 1 m3 Galian Tanah Lumpur Sedalam 1 Meter - 106,758.30 106,758.30
7 1 m3 Galian Pekerjaan Striping (Pembuangan Humus) Setinggi 1 Meter - 6,470.20 6,470.20
8 1 m3 Pembuangan Tanah Sejauh 150 Meter - 66,567.60 66,567.60
9 1 m3 Urugan Kembali - 24,819.96 24,819.96
10 1 m3 Pemadatan Tanah - 64,702.00 64,702.00
11 1 m3 Urugan Pasir 437,040.00 36,260.40 473,300.40
12 1 m3 Pemasangan Lapisan Ijuk 14,784.00 19,410.60 34,194.60
13 1 m3 Urugan Sirtu 421,920.00 32,351.00 454,271.00
14 1 m3 Urugan Tanah Biasa 349,680.00 32,351.00 382,031.00
15 1 m2 Pembuatan Jalan Sementara, Tebal 25 cm 131,237.00 129,404.00 260,641.00
C PEKERJAAN PONDASI

1 1 m3 Pasang Pondasi Batu Kali 1 Pc : 1 Ps 1,344,571.20 267,267.00 1,611,838.20


2 1 m3 Pasang Pondasi Batu Kali 1 Pc : 2 Ps 1,151,162.40 267,267.00 1,418,429.40
3 1 m3 Pasang Pondasi Batu Kali 1 Pc : 2,5 Ps 1,074,348.00 267,267.00 1,341,615.00
4 1 m3 Pasang Pondasi Batu Kali 1 Pc : 3 Ps 1,050,139.60 267,267.00 1,317,406.60
5 1 m3 Pasang Pondasi Batu Kali 1 Pc : 4 Ps 900,828.40 267,267.00 1,168,095.40
6 1 m3 Pasang Pondasi Batu Kali 1 Pc : 5 Ps 947,626.40 267,267.00 1,214,893.40
7 1 m3 Pasang Pondasi Batu Kali 1 Pc : 6 Ps 918,124.00 267,267.00 1,185,391.00
8 1 m3 Pasang Pondasi Kosong 482,460.00 149,738.16 632,198.16
9 1 m2 Pasang Pondasi Siklop 40 % Batu Kali 1,890,165.60 486,255.00 2,376,420.60
10 1 M3 Pasang Pondasi Sumuran Diameter 100 cm 1,272,242.00 329,133.20 1,601,375.20

C PEKERJAAN BETON

1 1 m3 Membuat Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr 1,139,950.40 237,118.20 1,377,068.60


2 1 m3 Membuat Beton Tumbuk, 1 Pc : 2 Ps : 3 Kr 1,242,317.20 237,118.20 1,479,435.40
3 1 m2 Membuat Lantai Kerja Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr, Tebal 5 cm 55,391.20 137,617.04 193,008.24
21 1 m3 Membuat pondasi beton bertulang ( 150 kg besi + bekisting ) 4,292,740.90 812,593.10 5,105,334.00
22 #REF! #REF! #REF! #REF!
23 #REF! #REF! #REF! #REF!
24 1 m3 Membuat Balok beton bertulang 8,332,674.40 1,279,315.40 9,611,989.80
25 1 m3 Membuat Balok beton bertulang 7,691,054.40 1,279,315.40 8,970,369.80
26 1 m3 Membuat Balok beton bertulang 9,981,356.40 1,488,955.16 11,470,311.56
27 1 m3 Membuat Tangga beton bertulang 5,517,205.40 1,234,337.72 6,751,543.12
D PEKERJAAN LISTRIK

E PEKERJAAN SANITASI

1 Memasang 1 buah kloset duduk 1,434,180.00 540,334.30 1,974,514.30


2 Memasang 1 buah kloset jongkok porselen 516,445.80 550,411.40 1,066,857.20
3 Memasang 1 buah kloset jongkok teraso 1,121,470.80 360,529.40 1,482,000.20
4 Memasang 1 buah urinoir 1,177,721.80 267,344.00 1,445,065.80
5 Memasang 1 buah westafel 1,080,447.10 645,268.80 1,725,715.90
6 Memasang 1 buah bak mandi batu bata volume 0.30 m3 645,268.80 330,181.50 975,450.30
7 Memasang 1 buah bak beton volume 1 m3 air 4,076,121.72 1,212,871.00 5,288,992.72
8 Memasang 1 m' pipa galvanis diameter 1/2 " 88,921.80 22,168.08 111,089.88
9 Memasang 1 m' pipa galvanis diameter 3/4 " 18,087.30 22,168.08 40,255.38
10 Memasang 1 m' pipa galvanis diameter 1 " 27,888.30 22,168.08 50,056.38
11 Memasang 1 m' pipa galvanis diameter 2 1/2 " 40,500.00 38,113.42 78,613.42
14 Memasang 1 m' pipa PVC tipe AW diameter 1/2 " 13,899.60 12,704.47 26,604.07
15 Memasang 1 m' pipa PVC tipe AW diameter 3/4 " 21,027.60 12,704.47 33,732.07
16 Memasang 1 m' pipa PVC tipe AW diameter 1 " 26,373.60 12,704.47 39,078.07
17 Memasang 1 m' pipa PVC tipe AW diameter 1 1/2 " 30,115.80 12,704.47 42,820.27
18 Memasang 1 m' pipa PVC tipe AW diameter 1 " 26,373.60 19,056.71 45,430.31
19 Memasang 1 m' pipa PVC tipe AW diameter 2 1/2 " 47,579.40 12,678.86 60,258.26
20 Memasang 1 m' pipa PVC tipe AW diameter 3 " 91,060.20 28,591.46 119,651.66
21 Memasang 1 m' pipa PVC tipe AW diameter 4 " 144,163.80 28,591.46 172,755.26
22 Memasang 1 buah bak cuci piring stainles steel 510,000.00 45,072.06 555,072.06
23 Memasang 1 buah kran diameter 3/4" atau 1/2" 44,487.50 15,600.20 60,087.70
24 Memasang 1 buah floor drain 30,925.00 15,600.20 46,525.20

F PEKERJAAN PENGECATAN

1 1 m2 Mendempul dan menggosok kayu 3,737.50 10,501.70 14,239.20


2 1 m2 Pengecatan Bidang Kayu Lama 19,742.10 18,827.60 38,569.70
3 1 m2 Pengecatan Plafond ( 1 lapis plamir ), 1 lapis cat dasar, 2 lapis cat 15,849.50 11,239.25 27,088.75
4 1 m2 Pengecatan Bidang Kayu Baru ( 1 lapis plamir ), 1 lapis cat dasar, 3 lapis cat 39,696.50 21,971.95 61,668.45
5 1 m2 Pengecatan Tembok Baru ( anti lumut ), 1 lapis cat dasar, 2 lapis cat 29,149.93 14,670.15 43,820.08
6 1 m2 Pengecatan Tembok Baru ( 1 lapis plamir ), 1 lapis cat dasar, 3 lapis cat 13,131.84 11,031.13 24,162.97
7 1 m2 Pelaburan bidang kayu dengan vernis 310.00 41,046.50 41,356.50
8 1 m2 Pelaburan bidang kayu dengan cat residu dan ter 1,750.00 12,428.24 14,178.24
9 1 m2 Pengecatan permukaan baja / Seng dengan meni besi 4,611.75 31,200.40 35,812.15
10 1 m2 Pengecatan permukaan baja dengan meni besi + Cat Besi dan perancah 26,922.05 61,146.80 88,068.85
G PEKERJAAN DINDING

1 1 m2 pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps 336,313.28 107,219.20 443,532.48


2 1 m2 pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps 305,993.80 107,219.20 413,213.00
3 1 m2 pasang bata merah tebal 1 bata, 1 Pc : 3 Ps 290,536.66 107,219.20 397,755.86
4 1 m2 pasang bata merah tebal 1 bata, 1 Pc : 4 Ps 194,391.54 107,219.20 301,610.74
5 1 m2 pasang bata merah tebal 1 bata, 1 Pc : 5 Ps 274,662.96 107,219.20 381,882.16
6 1 m2 pasang bata merah tebal 1 bata, 1 Pc : 6 Ps 274,662.96 107,219.20 381,882.16
7 1 m2 pasang bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps 250,038.36 107,219.20 357,257.56
8 1 m2 pasang bata merah tebal 1/2 bata, 1 Pc : 1 Ps 158,489.04 53,026.60 211,515.64
9 1 m2 pasang bata merah tebal 1/2 bata, 1 Pc : 1 Ps 145,980.26 53,026.60 199,006.86
10 1 M2 Pasang Bata Pres pabrikasi 1/2 Bata, 165,055.40 53,026.60 218,082.00
11 1 m2 pasang bata merah tebal 1/2 bata, 1 Pc : 4 Ps #REF! 53,026.60 #REF!
12 1 m2 pasang bata tebal 1/2 bata, 1 Pc : 5 Ps 130,819.50 53,026.60 183,846.10
13 1 m2 pasang bata merah tebal 1/2 bata, 1 Pc : 6 Ps 130,356.50 53,026.60 183,383.10
14 1 m2 pasang bata merah tebal 1/2 bata, 1 Pc : 8 Ps 127,158.20 53,026.60 180,184.80
15 1 m2 pasang bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps 126,367.60 53,026.60 179,394.20
16 1 m2 pasang bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 2 Ps 98,750.69 53,026.60 151,777.29
17 1 m2 pasang bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 2 Ps 103,766.36 53,026.60 156,792.96
18 1 m2 pasang dinding hollowblock (HB. 20) 27,998.00 63,677.68 91,675.68
19 1 m2 pasang dinding hollowblock (HB. 15) 24,938.00 55,785.40 80,723.40
20 1 m2 Pasangan dinding hollowblock (HB. 10) 21,977.00 53,026.60 75,003.60
21 1 m2 Pasangan dinding conblock (CB. 20) 30,508.00 17,019.75 47,527.75
22 1 m2 Pasangan dinding conblock (CB. 15) 23,894.30 21,522.66 45,416.96
23 1 m2 Pasangan dinding conblock (CB. 10) 22,285.00 18,558.76 40,843.76
24 1 m2 Pasang dinding Lantai 9,330.00 5,666.76 14,996.76
25 1 m2 Pasang dinding roster/terawang ( 12 x 11 x 24 ) Cm 48,835.00 15,180.00 64,015.00
26 1 m2 Pasang bata berongga ukuran ( 5 x 11 x 24 ) Cm 104,220.00 21,623.25 125,843.25
27 1 m2 Pasang dinding anyaman bambu, rangka kayu 1,529.00 6,749.05 8,278.05

H PEKERJAAN PLESTERAN

1 1 m2 Plesteran 1 Pc : 1 Ps, tebal 15 mm. 34,610.98 45,291.40 79,902.38


2 1 m2 Plesteran 1 Pc : 2 Ps, tebal 15 mm. 27,816.26 45,291.40 73,107.66
3 1 m2 Plesteran 1 Pc : 3 Ps, tebal 15 mm. 24,752.14 45,291.40 70,043.54
4 1 m2 Plesteran 1 Pc : 4 Ps, tebal 15 mm. 22,678.56 45,291.40 67,969.96
5 1 m2 Plesteran 1 Pc : 5 Ps, tebal 15 mm. 22,030.50 45,291.40 67,321.90
6 1 m2 Plesteran 1 Pc : 6 Ps, tebal 15 mm. 21,289.90 45,291.40 66,581.30
7 1 m2 Plesteran 1 Pc : 8 Ps, tebal 15 mm. 20,216.06 45,291.40 65,507.46
8 1 m2 Plesteran 1 Pc : 0.5 Kp : 3 Ps, tebal 15 mm. 20,511.73 45,291.40 65,803.13
9 1 m2 Plesteran 1 Pc : 3 Kp : 10 Ps, tebal 15 mm. 13,753.15 45,291.40 59,044.55
10 1 m2 Plesteran 0.5 Pc : 1 Kp : 4 Ps, tebal 15 mm. 18,860.00 45,291.40 64,151.40
12 1 m2 Plesteran 1 Kp : 1 Sm : 1 Ps, tebal 15 mm. 7,791.15 45,291.40 53,082.55
13 1 m2 Plesteran 1 Kp : 1 Sm : 2 Ps, tebal 15 mm. 29.00 45,291.40 45,320.40
14 1 m2 Plesteran 1 Pc : 2 Ps, tebal 20 mm. 14,303.00 58,338.50 72,641.50
15 1 m2 Plesteran 1 Pc : 3 Ps, tebal 20. mm. 37,896.64 29,284.75 67,181.39
16 1 m2 Plesteran 1 Pc : 4 Ps, tebal 20. mm. 34,665.90 27,684.25 62,350.15
17 1 m2 Plesteran 1 Pc : 5 Ps, tebal 20. mm. 31,770.81 29,284.75 61,055.56
18 1 m2 Plesteran 1 Pc : 6 Ps, tebal 20. mm. 30,768.67 29,284.75 60,053.42
19 1 m2 Plesteran 1 Kp : 1 Sm : 2 Ps, tebal 20. mm. 13,338.00 29,284.75 42,622.75
20 1 m2 Plesteran 1 Pc : 2 Ps, tebal 25. mm. 39,984.60 29,425.22 69,409.82
21 1 m2 Plesteran 1 Pc : 3 Ps, tebal 25. mm. 45,443.86 29,425.22 74,869.08
22 1 m2 Plesteran 1 Pc : 4 Ps, tebal 25. mm. 42,256.14 29,425.22 71,681.36
23 1 m2 Plesteran 1 Pc : 5 Ps, tebal 25. mm. 39,641.03 29,425.22 69,066.25
24 1 m2 Plesteran 1 Pc : 2 Ps, tebal 30. mm. 59,578.22 36,514.63 96,092.85
25 1 m2 Plesteran 1 Pc : 3 Ps, tebal 30. mm. 52,575.22 36,514.63 89,089.85
26 1 m2 Plesteran 1 Pc : 4 Ps, tebal 30. mm. 48,583.06 36,514.63 85,097.70
27 1 m2 Plesteran 1 Pc : 5 Ps, tebal 30. mm. 43,716.13 36,514.63 80,230.76
28 1 m2 Berapen 1 Pc : 3 Ps, tebal 30. mm. 7,091.00 11,268.07 18,359.07
29 1 m2 Berapen 1 Pc : 5 Ps, tebal 15. mm. 5,693.00 11,268.07 16,961.07
30 1 m2 Plesteran Beton 1 Pc : 2 Ps, tebal 15. mm. 30,033.24 29,425.22 59,458.46
31 1 m2 Plesteran Beton 1 Pc : 3 Ps, tebal 15. mm. 27,343.52 29,425.22 56,768.74
32 1 m Plesteran Profil 1 Pc : 2 Ps. 1,559.70 21,546.58 23,106.28
33 1 m2 Plesteran Granito 1 Pc warna : 2 Granito, tebal 10 mm. 3,751.80 3,982.00 7,733.80
34 1 m2 Plesteran Teraso 1 Pc warna : 2 Batu teraso, tebal 10 mm. 11,940.00 32,796.50 44,736.50
35 1 m2 Plesteran Ciprat 1 Pc : 2 Ps. 4,336.00 17,100.60 21,436.60
36 1 m2 Plesteran Siar adukan 1 Pc : 2 Ps. 4,336.00 11,268.07 15,604.07
37 1 m2 Plesteran Waterproof batacote 3 lapis. 1,406.00 29,987.10 31,393.10

I PEKERJAAN KAYU

1 1 m3 pasang kusen pintu dan jendela kayu Kls. I 7,075,640.00 3,496,812.00 10,572,452.00
2 1 m3 pasang kusen pintu dan jendela kayu Kls. II A 4,242,040.00 3,251,512.00 7,493,552.00
3 1 m3 pasang kusen pintu dan jendela kayu borneo 7,718,880.00 2,428,382.00 10,147,262.00
4 1 m3 pasang kusen pintu dan jendela kayu Kls. II 4,627,680.00 2,428,382.00 7,056,062.00
5 1 m2 pasang pintu klamp kayu Kls. I 50.00 140,365.17 140,415.17
6 1 m2 pasang pintu klam kayu Kls. II 139,992.90 187,951.72 327,944.62
7 1 m2 pasang pintu panel kayu Kls. I 277,410.00 467,852.00 745,262.00
8 1 m2 pasang pintu panel kayu Kls. II 154,256.00 467,852.00 622,108.00
9 1 m2 pasang pintu dan jendela kaca kayu Kls. I 225,134.00 374,281.60 599,415.60
10 1 m2 pasang pintu dan jendela kaca kayu Kls.II 134,974.00 374,281.60 509,255.60
11 1 m2 pasang pintu dan jendela kaca kayu borneo 225,134.00 374,281.60 599,415.60
12 1 m2 pasang jalusi ventilasi kayu Kls. I 411,673.60 568,832.00 980,505.60
13 1 m2 pasang pintu dan jendela jalusi kayu Kls. II 246,809.60 594,440.00 841,249.60
14 1 m2 pasang pintu Taekwood rangkap, rangka kayu Kls. I 204,682.54 349,681.20 554,363.74
15 1 m2 pasang pintu plywood rangkap, rangka kayu Kls. II 154,192.94 349,681.20 503,874.14
16 1 m2 pasang Ventilasi kayu Kls. II 61,333.50 337,381.00 398,714.50
17 1 m2 pasang jalusi mati kusen kayu Kls. II 234,871.50 337,381.00 572,252.50
18 1 m2 pasang pintu plywood rangkap, rangka kayu borneo 77,910.00 349,681.20 427,591.20
19 1 m2 pasang pintu teakwood rangkap, rangka kayu jati 194,290.00 349,681.20 543,971.20
20 1 m2 pasang pintu teakwood rangkap, rangka kayu Kls. I 194,290.00 349,681.20 543,971.20
21 1 m2 pasang pintu plywood & formika, rangka kayu Kls. I 253,401.80 443,251.60 696,653.40
22 1 m2 pasang pintu plywood &formika rangka kayu Kls. II 203,555.44 443,251.60 646,807.04
23 1 m2 pasang pintu teakwood & formika rangka kayu Kls. I 216,860.04 443,251.60 660,111.64
24 1 m2 pasang pintu teakwood & formika rangka kayu Kls. I ( divernis ) 156,250.00 443,251.60 599,501.60
25 1 m2 pasang pintu formika double, rangka kayu Kls. I 295,950.04 481,646.00 777,596.04
26 1 m2 pasang pintu formika double, rangka kayu Kls. II 245,460.44 481,646.00 727,106.44
27 1 m3 pasang konstruksi kuda - kuda kayu Kls. I 7,304,420.00 2,147,288.00 9,451,708.00
28 1 m3 pasang konstruksi kuda - kuda kayu Kls. II 4,470,820.00 4,086,280.00 8,557,100.00
29 1 m3 pasang konstruksi kuda -kuda kayu borneo 7,304,420.00 4,086,280.00 11,390,700.00
30 1 m3 pasang konstruksi kuda-kuda kayu kruing 7,304,420.00 4,086,280.00 11,390,700.00
31 1 m3 pasang kaso + reng genteng kodok kayu Kls. II 49,764.30 52,019.00 101,783.30
32 1 m3 pasang kaso + reng genteng kodok kayu borneo 49,764.30 52,019.00 101,783.30
33 1 m3 pasang kaso + reng genteng monier kayu Kls. II 57,477.10 52,019.00 109,496.10
34 1 m2 pasang kaso + reng genteng monier kayu kamper 57,477.10 52,019.00 109,496.10
35 1 m2 pasang kaso + reng genteng Metal kayu Kls. II 57,477.10 52,019.00 109,496.10
36 1 m2 pasang kaso + reng atap sirap kayu Kls. II 640,956.00 62,422.80 703,378.80
37 1 m2 pasang kaso + reng atap sirap kayu barneo 640,956.00 62,422.80 703,378.80
38 1 m2 pasang angka langit - langit (0.61 x 1.22) m, kayu jati 79,513.80 103,097.50 182,611.30
39 1 m2 pasang rangka langit - langit (0.61 x 1.22) m, kayu Kls. II 48,601.80 103,097.50 151,699.30
40 1 m2 pasang angka langit - langit (1.00 x 1.00) m, kayu borneo 112.00 103,097.50 103,209.50
41 1 m2 pasang angka langit - langit (0.305 x 0.61) M, kayu jati 151,432.70 129,107.00 280,539.70
42 1 m2 pasang angka langit - langit (0.305 x 0.61) m, kayu Kls. II 92,184.70 129,107.00 221,291.70
43 1 m2 pasang angka langit - langit (30 x 60) cm, kayu borneo 92,184.70 129,107.00 221,291.70
44 1 m2 pasang rangka langit - langit (0.305 x 0.305) cm, kayu Kls. II 178,324.80 155,116.50 333,441.30
45 1 m2 pasang angka langit - langit (30 x 30) cm, kayu kamper 108,772.80 79,029.50 187,802.30
46 1 m2 pasang angka langit - langit (30 x 30) cm, kayu borneo 108,772.80 79,029.50 187,802.30
47 1 m2 pasang lisplang ukuran (2 x 25) cm, kayu Kls. I 258,458.50 40,652.70 299,111.20
48 1 m2 pasang lisplang ukuran (3 x 20) cm, kayu Kls. II 155,418.50 39,888.20 195,306.70
49 1 m2 pasang lisplang ukuran (3 x 20) cm, kayu jati 71,918.90 43,813.00 115,731.90
50 1 m2 pasang lisplang ukuran (3 x 20) cm, kayu kamper 43,582.90 43,813.00 87,395.90
51 1 m2 pasang lisplang ukuran 2 x (3 x 20) cm, kayu Klas. I 515,987.00 61,578.00 577,565.00
52 1 m2 pasang lisplang ukuran 2 x (2 x 20) cm, kayu Kls. I 323,015.00 31,856.00 354,871.00
53 1 m2 pasang lisplang ukuran 2 x (2 x 20) cm, kayu Kls. II 194,215.00 31,856.00 226,071.00
54 1 m2 pasang rangka dinding pemisah kayu Kls. II 104,519.60 89,166.00 193,685.60
55 1 m2 pasang rangka dinding pemisah kayu borneo 104,519.60 89,166.00 193,685.60
56 1 m2 pasang rangka dinding pemisah teakwood rangkap, rangka kayu Kls. II 104,519.60 89,166.00 193,685.60
57 1 m2 pasang rangka dinding pemisah plywood rangkap, rangka kayu Kls. II 185,497.60 107,364.40 292,862.00
58 1 m2 pasang dinding lambrizring dari papan Kls. I 50,839.30 322,093.20 372,932.50
59 1 m2 pasang plywood tebal 4 mm, + Rangka untuk dinding 65,039.88 13,426.95 78,466.83
60 1 m1 pasang list plafon Gipsum 49,113.75 5,458.09 54,571.84

J PEKERJAAN KUNCI DAN KACA

1 1 buah pasang kunci tanam antik 385,000.00 90,144.12 475,144.12


2 1 buah pasang kunci tanam 1 Slaag 151,470.00 90,144.12 241,614.12
3 1 buah pasang kunci tanam kamar mandi 151,470.00 62,992.60 214,462.60
4 1 buah pasang engsel pintu 54,670.00 22,536.03 77,206.03
5 1 buah pasang engsel jendela 42,570.00 15,024.02 57,594.02
6 1 buah pasang Grendel Pintu / Jendela 49,500.00 30,048.04 79,548.04
7 1 buah pasang kait angin 24,420.00 22,536.03 46,956.03
8 1 buah pasang kunci selot 5,500.00 30,048.04 35,548.04
9 1 buah pasang pegangan pintu / door holder 3,000.00 62,992.60 65,992.60
10 1 m2 pasang kaca, tebal 3 mm 213,455.00 22,536.03 235,991.03
11 1 m2 pasang kaca, tebal 5 mm 287,100.00 22,536.03 309,636.03
12 1 m2 pasang kaca, tebal 8 mm 470,725.00 24,786.43 495,511.43
13 1 m2 pasang kaca buram tebal 12 mm 914,135.00 37,560.05 951,695.05
14 1 m2 pasang kaca patri, tebal 2 mm 213,455.00 22,536.03 235,991.03

K PEKERJAAN BESI DAN ALUMINIUM

1 1 Kg pasang rangka kuda-kuda atap baja WF 35,420.00 15,656.52 51,076.52


2 1 m2 pasang pintu besi baja 600,000.00 169,548.28 769,548.28
3 1 m2 pasang jendela besi 242,550.00 267,939.21 510,489.21
8 1 m2 pasang rolling door 363,550.00 330,005.81 693,555.81
9 1 m' pasang pintu alluminium strip lebar 8 mm #REF! - #REF!
12 1 m2 pasang terali besi 19,161.76 289,011.62 308,173.38
17 1 m2 pasang jendela nako & dan tralis 4,532,771.56 51,036.04 4,583,807.60
18 1 m2 pasang talang datar, seng BJLS 2.8 mm 124,637.69 70,532.55 195,170.24
19 1 m2 pasang talang miring, seng BJLS 2.8 mm 162,781.35 57,706.55 220,487.90
20 1 m2 pasang talang 1/2 lingkaran D-10 cm, seng BJLS 2.8 mm 141,211.60 52,135.05 193,346.65
21 1 m2 pasang talang 1/2 lingkaran D-10 cm, seng BJLS 2.4 mm 117,781.60 52,135.05 169,916.65

L PEKERJAAN ATAP
1 1 m2 pasang atap genteng palentong kecil 25,000.00 28,936.27 53,936.27
2 1 m2 pasang atap genteng kodok / glazzur 25,000.00 28,936.27 53,936.27
3 1 m2 pasang atap genteng palentong super / besar 12,000.00 26,790.72 38,790.72
4 1 m2 pasang genteng bubung palentong 13,032.00 26,790.72 39,822.72
5 1 m2 pasang bubung genteng kodok glazzur 13,032.00 74,484.08 87,516.08
6 1 m2 pasang bubung genteng palentong besar 12,032.00 74,484.08 86,516.08
7 1 m2 pasang roof light fibreglass (180 x 90 ) cm 45,712.50 26,508.13 72,220.63
8 1 m2 pasang atap asbes gelombang ( 2.50 x 0.92 m ) x 5 mm 34,122.40 27,770.27 61,892.67
9 1 m2 pasang atap asbes gelombang ( 2.25 x 0.92 m ) x 5 mm 35,882.40 27,770.27 63,652.67
10 1 m2 pasang atap asbes gelombang ( 2.00 x 0.92 m ) x 5 mm 33,242.40 26,876.08 60,118.48
11 1 m2 pasang atap asbes gelombang ( 1.80 x 0.92 m ) x 5 mm 870.00 26,876.08 27,746.08
12 1 m2 pasang atap asbes gelombang ( 3.00 x 1.05 m ) x 4 mm 470.00 26,876.08 27,346.08
13 1 m2 pasang atap asbes gelombang ( 2.70 x 1.05 m ) x 4 mm 540.00 26,876.08 27,416.08
14 1 m2 pasang atap asbes gelombang ( 2.40 x 1.05 m ) x 4 mm 560.00 26,508.13 27,068.13
15 1 m2 pasang atap asbes gelombang ( 2.10 x 1.05 m ) x 4 mm 630.00 26,508.13 27,138.13
16 1 m2 pasang atap asbes gelombang ( 1.5 x 1.05 m ) x 4 mm 920.00 26,508.13 27,428.13
17 1 m2 pasang atap asbes gelombang ( 3.00 x 1.08 m ) x 6 mm 490.00 26,508.13 26,998.13
18 1 m2 pasang atap asbes gelombang ( 2.70 x 1.08 m ) x 6 mm 500.00 26,508.13 27,008.13
19 1 m2 pasang atap asbes gelombang ( 2.4 x 1.08 m ) x 6 mm 580.00 26,508.13 27,088.13
20 1 m2 pasang atap asbes gelombang ( 2.1 x 1.08 m ) x 6 mm 610.00 26,508.13 27,118.13
21 1 m2 pasang atap asbes gelombang ( 1.80 x 1.08 m ) x 6 mm 690.00 26,508.13 27,198.13
22 1 m2 pasang Atap steel gelombang 0.92 m 120,875.00 27,625.51 148,500.51
23 1 m2 pasang nok steel gelombang 1.05 m 40,250.00 27,625.51 67,875.51
24 1 m2 pasang nok stel gelombang 1.08 m 45,750.00 27,625.51 73,375.51
25 1 m2 pasang nok paten 0.92 m 7,200.00 27,625.51 34,825.51
26 1 m2 pasang nok paten 1.05 m 7,200.00 27,625.51 34,825.51
27 1 m2 pasang nok paten 1.08 m 7,200.00 27,625.51 34,825.51
28 1 m2 pasang nok sel rata 0.92 m 7,100.00 32,557.36 39,657.36
29 1 m2 pasang nok sel rata 1.05 m 7,100.00 27,625.51 34,725.51
30 1 m2 pasang atap genteng beton 61,604.50 38,394.40 99,998.90
31 1 m2 pasang atap genteng aspal 7,780.00 61,854.10 69,634.10
32 1 m2 pasang atap Multi roof 69,327.40 37,242.04 106,569.44
33 1 m2 pasang atap sirap 60,200.00 54,864.92 115,064.92
34 1 m2 pasang Nok genteng Beton 334,419.30 76,788.80 411,208.10
35 1 m2 pasang Rangka Atap Kayu Gording kls 1 78,351.30 46,785.20 125,136.50
36 1 m pasang Bubungan/Nok Kayu kls 1 116,146.46 41,653.20 157,799.66
J PEKERJAAN LANTAI

1 1 m2 pasang dinding keramik ukuran 40x40 cm 184,089.86 124,412.20 308,502.06


2 1 m2 pasang lantai keramik ukuran 20x20 cm 175,069.86 90,445.30 265,515.16
3 1 m2 pasang lantai keramik ukuran 60x60 cm 292,879.86 90,445.30 383,325.16
4 1 m2 pasang lantai keramik artistik ukuran 10x20 cm 148,229.86 90,445.30 238,675.16
5 1 m2 pasang lantai keramik artistik ukuran 10x10 cm 153,529.86 90,445.30 243,975.16
6 1 m2 pasang dinding keramik artistik ukuran 10x20 cm 133,443.24 124,412.20 257,855.44
7 1 m2 pasang batu alam ukuran 20x20 cm 359,220.44 124,412.20 483,632.64
PEKERJAAN PERSIAPAN

4. 1 m' Pengukuran dan Pemasangan Bouwplank

a. Bahan

- Kayu 5/7 0.012 m3 x Rp. 3,856,400.00 = Rp. 46,276.80


- Paku Biasa 2" - 5" 0.020 Kg x Rp. 23,250.00 = Rp. 465.00
- Kayu Papan 3/20 0.007 m3 x Rp. 3,856,400.00 = Rp. 26,994.80
JUMLAH = Rp. 73,736.60
b. Tenaga

- Tukang Kayu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00


- Pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 26,094.20

JUMLAH (a) + (b) = Rp. 99,830.80

5. 1 m2 Pembuatan Kantor Sementara, dengan Lantai Plesteran

a. Bahan
- Dolken Kayu Ø 8-10/400 cm 1.250 Btg x Rp. 59,800.00 = Rp. 74,750.00
- Kayu 0.180 M3 x Rp. 3,856,400.00 = Rp. 694,152.00
- kayu Biasa 0.850 Kg x Rp. 3,856,400.00 = Rp. 3,277,940.00
- Besi Strip 1.100 Kg x Rp. 14,012.00 = Rp. 15,413.20
- Semen Portland 35.000 Kg x Rp. 2,082.80 = Rp. 72,898.00
- Pasir Pasang 0.150 M3 x Rp. 592,400.00 = Rp. 88,860.00
- Pasir Beton 0.100 M3 x Rp. 421,600.00 = Rp. 42,160.00
- Koral Beton 0.150 M3 x Rp. 536,400.00 = Rp. 80,460.00
- Bata Merah 30.000 Bh x Rp. 2,400.00 = Rp. 72,000.00
- Seng Plat 1.500 Lbr x Rp. 155,600.00 = Rp. 233,400.00
- Jendela Nako 2.000 Bh x Rp. 4,119,900.00 = Rp. 8,239,800.00
- Kaca Polos 0.080 M2 x Rp. 261,000.00 = Rp. 20,880.00
- Kunci Tanam 0.150 Bh x Rp. 151,470.00 = Rp. 22,720.50
- Plywood 4 mm 0.060 Lbr x Rp. 161,550.00 = Rp. 9,693.00
JUMLAH = Rp. 12,945,126.70

b. Tenaga

- Tukang Kayu 2.000 Oh x Rp. 122,650.00 = Rp. 245,300.00


- Tukang Bata 1.000 Oh x Rp. 122,650.00 = Rp. 122,650.00
- Pekerja 2.000 Oh x Rp. 116,600.00 = Rp. 233,200.00
- Kepala Tukang 0.300 Oh x Rp. 152,900.00 = Rp. 45,870.00
- Mandor 0.050 Oh x Rp. 128,040.00 = Rp. 6,402.00
JUMLAH = Rp. 653,422.00

JUMLAH (a) + (b) = Rp. 13,598,548.70

6. 1 m2 Pembuatan Gudang Semen dan Alat - alat

a. Bahan

- Dolken Kayu Ø 8-10/400 cm 1.700 Btg x Rp. 59,800.00 = Rp. 101,660.00


- Kayu 0.210 M3 x Rp. 3,856,400.00 = Rp. 809,844.00
- Paku Biasa 0.300 Kg x Rp. 23,250.00 = Rp. 6,975.00
- Semen Portland 10.500 Kg x Rp. 2,082.80 = Rp. 21,869.40
- Pasir beton 0.030 M3 x Rp. 421,600.00 = Rp. 12,648.00
- Koral Beton 0.050 M3 x Rp. 536,400.00 = Rp. 26,820.00
- Seng Gelombang BLJS 30 1.500 Lbr x Rp. 93,312.50 = Rp. 139,968.75
JUMLAH = Rp. 1,119,785.15

b. Tenaga

- Tukang Kayu 2.000 Oh x Rp. 122,650.00 = Rp. 245,300.00


- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00
- Kepala Tukang 0.200 Oh x Rp. 152,900.00 = Rp. 30,580.00
- Mandor 0.050 Oh x Rp. 128,040.00 = Rp. 6,402.00
JUMLAH = Rp. 398,882.00
JUMLAH (a) + (b) = Rp. 1,518,667.15
7. 1 m2 Membersihkan Lapangan dan Perataan
a. Tenaga

- Pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00


- Mandor 0.050 Oh x Rp. 128,040.00 = Rp. 6,402.00
JUMLAH = Rp. 18,062.00
JUMLAH (a) = Rp. 18,062.00

8. 1 m2 Pembuatan Bak adukan Ukuran (40 x 50 x 20) cm

a. Bahan

- Kayu Terentang 0.036 M3 x Rp. 3,856,400.00 = Rp. 138,830.40


- Paku Biasa 0.080 Kg x Rp. 23,250.00 = Rp. 1,860.00
- Kaso 5/7 1.000 Btg x Rp. 3,856,400.00 = Rp. 3,856,400.00
JUMLAH = Rp. 3,997,090.40

b. Tenaga

- Tukang Kayu 0.300 Oh x Rp. 122,650.00 = Rp. 36,795.00


- Mandor 0.0015 Oh x Rp. 128,040.00 = Rp. 192.06
JUMLAH = Rp. 36,987.06

JUMLAH (a) + (b) = Rp. 4,034,077.46

9. 1 m2 Pembuatan Jalan Sementara

a. Bahan

- Batu Belah 15/20 0.150 M3 x Rp. 311,000.00 = Rp. 46,650.00


- Batu Pecah 5/7 0.090 M3 x Rp. 311,000.00 = Rp. 27,990.00
- Pasing Pasang 0.010 M3 x Rp. 592,400.00 = Rp. 5,924.00
JUMLAH = Rp. 80,564.00

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Mandor 0.050 Oh x Rp. 128,040.00 = Rp. 6,402.00
JUMLAH = Rp. 123,002.00
JUMLAH (a) + (b) = Rp. 203,566.00

10. 1 m3 Bongkaran Beton Bertulang

a. Tenaga

- Pekerja 6.667 Oh x Rp. 116,600.00 = Rp. 777,372.20


- Mandor 0.333 Oh x Rp. 128,040.00 = Rp. 42,637.32
JUMLAH = Rp. 820,009.52
JUMLAH (a) = Rp. 820,009.52

11. 1 m3 Bongkaran Dinding Tembok Bata Merah

a. Tenaga
- Pekerja 6.667 Oh x Rp. 116,600.00 = Rp. 777,372.20
- Mandor 0.033 Oh x Rp. 128,040.00 = Rp. 4,225.32
JUMLAH = Rp. 781,597.52
JUMLAH (a) = Rp. 781,597.52

8. 1 m2 Membersihkan Semak belukar

a. Tenaga

- Pekerja 0.125 Oh x Rp. 116,600.00 = Rp. 14,575.00


- Mandor 0.050 Oh x Rp. 128,040.00 = Rp. 6,402.00
JUMLAH = Rp. 20,977.00

JUMLAH (a) = Rp. 20,977.00


PEKERJAAN TANAH

1. 1 m3 Galian Tanah Biasa Sedalam 1 Meter

b. Tenaga

- Pekerja 0.400 Oh x Rp. 116,600.00 = Rp. 46,640.00


- Mandor 0.040 Oh x Rp. 128,040.00 = Rp. 5,121.60
JUMLAH = Rp. 51,761.60

2 1 m3 Galian Tanah Biasa Sedalam 2 Meter

b. Tenaga

Pekerja 0.526 Oh x Rp. 116,600.00 = Rp. 61,331.60


Mandor 0.052 Oh x Rp. 128,040.00 = Rp. 6,658.08
JUMLAH = Rp. 67,989.68

3 1 m3 Galian Tanah Biasa Sedalam 3 Meter

b. Tenaga

Pekerja 0.735 Oh x Rp. 116,600.00 = Rp. 85,701.00


Mandor 0.073 Oh x Rp. 128,040.00 = Rp. 9,346.92
JUMLAH = Rp. 95,047.92

4 1 m3 Galian Tanah Keras Sedalam 1 Meter

b. Tenaga

Pekerja 0.625 Oh x Rp. 116,600.00 = Rp. 72,875.00


Mandor 0.063 Oh x Rp. 128,040.00 = Rp. 8,002.50
JUMLAH = Rp. 80,877.50

5 1 m3 Galian Tanah Cadas Sedalam 1 Meter

b. Tenaga

Pekerja 1.250 Oh x Rp. 116,600.00 = Rp. 145,750.00


Mandor 0.125 Oh x Rp. 128,040.00 = Rp. 16,005.00
JUMLAH = Rp. 161,755.00

5 1 m3 Galian Tanah Sumur

b. Tenaga

Pekerja 3.250 Oh x Rp. 116,600.00 = Rp. 378,950.00


Mandor 0.325 Oh x Rp. 128,040.00 = Rp. 41,613.00
JUMLAH = Rp. 420,563.00

6 1 m3 Galian Tanah Lumpur Sedalam 1 Meter

b. Tenaga

Pekerja 0.825 Oh x Rp. 116,600.00 = Rp. 96,195.00


Mandor 0.083 Oh x Rp. 128,040.00 = Rp. 10,563.30
JUMLAH = Rp. 106,758.30

7 1 m3 Galian Pekerjaan Striping (Pembuangan Humus) Setinggi 1 Meter

b. Tenaga

Pekerja 0.050 Oh x Rp. 116,600.00 = Rp. 5,830.00


Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 6,470.20

8 1 m3 Pembuangan Tanah Sejauh 150 Meter

b. Tenaga

Pekerja 0.516 Oh x Rp. 116,600.00 = Rp. 60,165.60


Mandor 0.050 Oh x Rp. 128,040.00 = Rp. 6,402.00
JUMLAH = Rp. 66,567.60

9 1 m3 Urugan Kembali

b. Tenaga

Pekerja 0.192 Oh x Rp. 116,600.00 = Rp. 22,387.20


Mandor 0.019 Oh x Rp. 128,040.00 = Rp. 2,432.76
JUMLAH = Rp. 24,819.96

11 1 m3 Urugan Pasir
a. Bahan

Pasir Urug 1.200 M3 x Rp. 364,200.00 = Rp. 437,040.00


JUMLAH = Rp. 437,040.00

b. Tenaga

Pekerja 0.300 Oh x Rp. 116,600.00 = Rp. 34,980.00


Mandor 0.010 Oh x Rp. 128,040.00 = Rp. 1,280.40
JUMLAH = Rp. 36,260.40

JUMLAH (a) + (b) = Rp. 473,300.40

14 1 m3 Urugan Tanah Biasa

a. Bahan

Tanah Urug / Timbunan 1.200 M3 x Rp. 291,400.00 = Rp. 349,680.00


JUMLAH = Rp. 349,680.00

b. Tenaga

Pekerja 0.250 Oh x Rp. 116,600.00 = Rp. 29,150.00


Mandor 0.025 Oh x Rp. 128,040.00 = Rp. 3,201.00
JUMLAH = Rp. 32,351.00

JUMLAH (a) + (b)+ Pemadatan = Rp. 382,031.00


1 m Pasang Canstil SNI-PD05
a. Bahan
- Castil 15 x 30 x 50 2.000 Bh x Rp. 39,570.00 = Rp. 79,140.00
- Pasir Pasang 0.004 m3 x Rp. 645,900.00 = Rp. 2,583.60
- Semen Portland 0.150 Kg x Rp. 4,320.00 = Rp. 648.00
Sub Jumlah (a) = Rp. 82,371.60
b. Tenaga
- Pekerja 0.250 OH x Rp. 116,600.00 = Rp. 29,150.00
- Tukang Batu 0.070 OH x Rp. 122,650.00 = Rp. 8,585.50
- Mandor 0.040 OH x Rp. 128,040.00 = Rp. 5,121.60
Sub Jumlah (b) = Rp. 42,857.10
JUMLAH (a) + (b) = Rp. 125,228.70

1 m Pasang Pembatas Paving Taman SNI-PD05


a. Bahan
- Bataco 10.000 Bh x Rp. 2,520.00 = Rp. 25,200.00
- Pasir Pasang 0.004 m3 x Rp. 645,900.00 = Rp. 2,583.60
- Semen Portland 0.313 Kg x Rp. 4,320.00 = Rp. 1,352.16
Sub Jumlah (a) = Rp. 29,135.76
b. Tenaga
- Pekerja 0.250 OH x Rp. 116,600.00 = Rp. 29,150.00
- Tukang Batu 0.070 OH x Rp. 122,650.00 = Rp. 8,585.50
- Mandor 0.040 OH x Rp. 128,040.00 = Rp. 5,121.60
Sub Jumlah (b) = Rp. 42,857.10
JUMLAH (a) + (b) = Rp. 71,992.86

1 m2 Pasang Paving Block K-300 SNI-PD05


a. Bahan
- Paving Block-K300 50.000 Bh x Rp. 4,095.00 = Rp. 204,750.00
- Pasir Urug 0.070 m3 x Rp. 200,400.00 = Rp. 14,028.00
- Alat Bantu 0.025 Unit x Rp. 100,000.00 = Rp. 2,500.00
Sub Jumlah (a) = Rp. 221,278.00
b. Alat
- Jam Vibroroler 0.040 Unit x Rp. 100,000.00 = Rp. 4,000.00

c. Tenaga
- Pekerja 0.500 OH x Rp. 116,600.00 = Rp. 58,300.00
- Tukang Batu 0.200 OH x Rp. 122,650.00 = Rp. 24,530.00
- Operator 0.003 OH x Rp. 152,900.00 = Rp. 458.70
- Mandor 0.050 OH x Rp. 128,040.00 = Rp. 6,402.00
Sub Jumlah (b) = Rp. 89,690.70
JUMLAH (a) + (b) = Rp. 314,968.70
PEKERJAAN PONDASI

5 1 m3 Pasang Pondasi Batu Kali 1 Pc : 4 Ps

a. Bahan

- Batu Belah 15 / 20 cm 1.100 M3 x Rp. 311,000.00 = Rp. 342,100.00


- Semen Portland 163.000 Kg x Rp. 2,082.80 = Rp. 339,496.40
- Pasir pasang 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
JUMLAH = Rp. 900,828.40

b. Tenaga

- Pekerja 1.500 Oh x Rp. 116,600.00 = Rp. 174,900.00


- Tukang Batu 0.600 Oh x Rp. 122,650.00 = Rp. 73,590.00
- Kepala Tukang 0.060 Oh x Rp. 152,900.00 = Rp. 9,174.00
- Mandor 0.075 Oh x Rp. 128,040.00 = Rp. 9,603.00
JUMLAH = Rp. 267,267.00

JUMLAH (a) + (b) = Rp. 1,168,095.40

6 1 m3 Pasang Pondasi Batu Kali 1 Pc : 5 Ps

a. Bahan

- Batu Belah 15 / 20 cm 1.100 M3 x Rp. 311,000.00 = Rp. 342,100.00


- Semen Portland 136.000 Kg x Rp. 2,082.80 = Rp. 283,260.80
- Pasir pasang 0.544 M3 x Rp. 592,400.00 = Rp. 322,265.60
JUMLAH = Rp. 947,626.40

b. Tenaga

- Pekerja 1.500 Oh x Rp. 116,600.00 = Rp. 174,900.00


- Tukang Batu 0.600 Oh x Rp. 122,650.00 = Rp. 73,590.00
- Kepala Tukang 0.060 Oh x Rp. 152,900.00 = Rp. 9,174.00
- Mandor 0.075 Oh x Rp. 128,040.00 = Rp. 9,603.00
JUMLAH = Rp. 267,267.00

JUMLAH (a) + (b) = Rp. 1,214,893.40

7 1 m3 Pasang Pondasi Batu Kali 1 Pc : 6 Ps

a. Bahan

- Batu Belah 15 / 20 cm 1.100 M3 x Rp. 311,000.00 = Rp. 342,100.00


- Semen Portland 117.000 Kg x Rp. 2,082.80 = Rp. 243,687.60
- Pasir pasang 0.561 M3 x Rp. 592,400.00 = Rp. 332,336.40
JUMLAH = Rp. 918,124.00

b. Tenaga

- Pekerja 1.500 Oh x Rp. 116,600.00 = Rp. 174,900.00


- Tukang Batu 0.600 Oh x Rp. 122,650.00 = Rp. 73,590.00
- Kepala Tukang 0.060 Oh x Rp. 152,900.00 = Rp. 9,174.00
- Mandor 0.075 Oh x Rp. 128,040.00 = Rp. 9,603.00
JUMLAH = Rp. 267,267.00

JUMLAH (a) + (b) = Rp. 1,185,391.00

8 1 m3 Pasang Pondasi Kosong

a. Bahan

- Batu Belah 15 / 20 cm 1.200 M3 x Rp. 311,000.00 = Rp. 373,200.00


- Pasir Urug 0.300 M3 x Rp. 364,200.00 = Rp. 109,260.00
JUMLAH = Rp. 482,460.00

b. Tenaga

- Pekerja 0.780 Oh x Rp. 116,600.00 = Rp. 90,948.00


- Tukang Batu 0.390 Oh x Rp. 122,650.00 = Rp. 47,833.50
- Kepala Tukang 0.039 Oh x Rp. 152,900.00 = Rp. 5,963.10
- Mandor 0.039 Oh x Rp. 128,040.00 = Rp. 4,993.56
JUMLAH = Rp. 149,738.16

JUMLAH (a) + (b) = Rp. 632,198.16


PEKERJAAN DINDING

10 1 M2 Pasang Bata Pres pabrikasi 1/2 Bata,

a. Bahan

- Batu Pres pabrikasi 8x25x50 8.000 Bh x Rp. 19,200.00 = Rp. 153,600.00


- Semen Portland 5.500 Kg x Rp. 2,082.80 = Rp. 11,455.40
JUMLAH = Rp. 165,055.40

b. Tenaga

- Pekerja 0.320 Oh x Rp. 116,600.00 = Rp. 37,312.00


- Tukang Batu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.015 Oh x Rp. 128,040.00 = Rp. 1,920.60
JUMLAH = Rp. 53,026.60

JUMLAH (a) + (b) = Rp. 218,082.00

12 1 m2 pasang bata tebal 1/2 bata, 1 Pc : 5 Ps

a. Bahan

- Batu Bata 35.000 Bh x Rp. 2,400.00 = Rp. 84,000.00


- Semen Portland 9.680 Kg x Rp. 2,082.80 = Rp. 20,161.50
- Pasir pasang 0.045 M3 x Rp. 592,400.00 = Rp. 26,658.00
JUMLAH = Rp. 130,819.50

b. Tenaga

- Pekerja 0.320 Oh x Rp. 116,600.00 = Rp. 37,312.00


- Tukang Batu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.015 Oh x Rp. 128,040.00 = Rp. 1,920.60
JUMLAH = Rp. 53,026.60

JUMLAH (a) + (b) = Rp. 183,846.10


13 1 m2 pasang bata merah tebal 1/2 bata, 1 Pc : 6 Ps

a. Bahan

- Batu Bata 35.000 Bh x Rp. 2,400.00 = Rp. 84,000.00


- Semen Portland 8.320 Kg x Rp. 2,082.80 = Rp. 17,328.90
- Pasir pasang 0.049 M3 x Rp. 592,400.00 = Rp. 29,027.60
JUMLAH = Rp. 130,356.50

b. Tenaga

- Pekerja 0.320 Oh x Rp. 116,600.00 = Rp. 37,312.00


- Tukang Batu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.015 Oh x Rp. 128,040.00 = Rp. 1,920.60
JUMLAH = Rp. 53,026.60

JUMLAH (a) + (b) = Rp. 183,383.10

14 1 m2 pasang bata merah tebal 1/2 bata, 1 Pc : 8 Ps

a. Bahan

- Batu Bata 35.000 Bh x Rp. 2,400.00 = Rp. 84,000.00


- Semen Portland 6.500 Kg x Rp. 2,082.80 = Rp. 13,538.20
- Pasir pasang 0.050 M3 x Rp. 592,400.00 = Rp. 29,620.00
JUMLAH = Rp. 127,158.20

b. Tenaga

- Pekerja 0.320 Oh x Rp. 116,600.00 = Rp. 37,312.00


- Tukang Batu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.015 Oh x Rp. 128,040.00 = Rp. 1,920.60
JUMLAH = Rp. 53,026.60

JUMLAH (a) + (b) = Rp. 180,184.80

15 1 m2 pasang bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps

a. Bahan

- Batu Bata 35.000 Bh x Rp. 2,400.00 = Rp. 84,000.00


- Semen Portland 4.500 Kg x Rp. 2,082.80 = Rp. 9,372.60
- Pasir pasang 0.050 M3 x Rp. 592,400.00 = Rp. 29,620.00
- kapur padam 0.015 M3 x Rp. 225,000.00 = Rp. 3,375.00
JUMLAH = Rp. 126,367.60

b. Tenaga

- Pekerja 0.320 Oh x Rp. 116,600.00 = Rp. 37,312.00


- Tukang Batu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.015 Oh x Rp. 128,040.00 = Rp. 1,920.60
JUMLAH = Rp. 53,026.60

JUMLAH (a) + (b) = Rp. 179,394.20


1 m Pekerjaan Saluran Keliling pasang bata tebal 1/2 bata + Plesteran, 1 Pc : SNI-DG09
a. Bahan
- Bata Tela 35.000 Bh x Rp. 2,520.00 = Rp. 88,200.00
- Semen Portland 10.680 Kg x Rp. 4,320.00 = Rp. 46,137.60
- Pasir pasang 0.120 M3 x Rp. 592,400.00 = Rp. 71,088.00
- Pasir Kasar 0.050 M 3
x Rp. 335,637.50 = Rp. 16,781.88
Sub Jumlah (a) = Rp. 222,207.48
b. Tenaga
- Pekerja 0.260 Oh x Rp. 116,600.00 = Rp. 30,316.00
- Tukang Batu 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00
- Kepala Tukang 0.020 Oh x Rp. 152,900.00 = Rp. 3,058.00
- Mandor 0.013 Oh x Rp. 128,040.00 = Rp. 1,664.52
Sub Jumlah (b) = Rp. 59,568.52
JUMLAH (a) + (b) = Rp. 281,776.00
PEKERJAAN PLESTERAN

3 1 m2 Plesteran 1 Pc : 3 Ps, tebal 15 mm.

a. Bahan

- Semen Portland 6.480 Kg x Rp. 2,082.80 = Rp. 13,496.54


- Pasir pasang 0.019 M3 x Rp. 592,400.00 = Rp. 11,255.60
JUMLAH = Rp. 24,752.14

b. Tenaga

- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang Batu 0.150 Oh x Rp. 122,650.00 = Rp. 18,397.50
- Kepala Tukang 0.015 Oh x Rp. 152,900.00 = Rp. 2,293.50
- Mandor 0.010 Oh x Rp. 128,040.00 = Rp. 1,280.40
JUMLAH = Rp. 45,291.40

JUMLAH (a) + (b) = Rp. 70,043.54

4 1 m2 Plesteran 1 Pc : 4 Ps, tebal 15 mm.

a. Bahan

- Semen Portland 5.200 Kg x Rp. 2,082.80 = Rp. 10,830.56


- Pasir pasang 0.020 M3 x Rp. 592,400.00 = Rp. 11,848.00
JUMLAH = Rp. 22,678.56

b. Tenaga

- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang Batu 0.150 Oh x Rp. 122,650.00 = Rp. 18,397.50
- Kepala Tukang 0.015 Oh x Rp. 152,900.00 = Rp. 2,293.50
- Mandor 0.010 Oh x Rp. 128,040.00 = Rp. 1,280.40
JUMLAH = Rp. 45,291.40

JUMLAH (a) + (b) = Rp. 67,969.96

32. 1 m Plesteran Profil 1 Pc : 2 Ps.

a. Bahan

- Semen Portland 0.180 Kg x Rp. 2,082.80 = Rp. 374.90


- Pasir pasang 0.002 M3 x Rp. 592,400.00 = Rp. 1,184.80
JUMLAH = Rp. 1,559.70

b. Tenaga

- Pekerja 0.260 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang Batu 0.140 Oh x Rp. 122,650.00 = Rp. 4,660.70
- Kepala Tukang 0.038 Oh x Rp. 152,900.00 = Rp. 305.80
- Mandor 0.002 Oh x Rp. 128,040.00 = Rp. 256.08
JUMLAH = Rp. 21,546.58

JUMLAH (a) + (b) = Rp. 23,106.28


PEKERJAAN KAYU

1 1 m3 pasang kusen pintu dan jendela kayu Kls. I

a. Bahan

- kayu balok 1.100 m3 x Rp. 6,432,400.00 = Rp. 7,075,640.00


JUMLAH = Rp. 7,075,640.00

b. Tenaga

- Pekerja 6.000 Oh x Rp. 116,600.00 = Rp. 699,600.00


- Tukang kayu 20.000 Oh x Rp. 122,650.00 = Rp. 2,453,000.00
- Kepala Tukang 2.000 Oh x Rp. 152,900.00 = Rp. 305,800.00
- Mandor 0.300 Oh x Rp. 128,040.00 = Rp. 38,412.00
JUMLAH = Rp. 3,496,812.00

JUMLAH (a) + (b) = Rp. 10,572,452.00

7 1 m2 pasang pintu panel kayu Kls. I

a. Bahan

- papan 0.040 m3 x Rp. 6,432,400.00 = Rp. 257,296.00


- papan 1.000 m2 x Rp. 20,114.00 = Rp. 20,114.00
JUMLAH = Rp. 277,410.00

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang kayu 2.500 Oh x Rp. 122,650.00 = Rp. 306,625.00
- Kepala Tukang 0.250 Oh x Rp. 152,900.00 = Rp. 38,225.00
- Mandor 0.050 Oh x Rp. 128,040.00 = Rp. 6,402.00
JUMLAH = Rp. 467,852.00

JUMLAH (a) + (b) = Rp. 745,262.00

8 1 m2 pasang pintu panel kayu Kls. II

a. Bahan

- papan 0.040 m3 x Rp. 3,856,400.00 = Rp. 154,256.00


JUMLAH = Rp. 154,256.00

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang kayu 2.500 Oh x Rp. 122,650.00 = Rp. 306,625.00
- Kepala Tukang 0.250 Oh x Rp. 152,900.00 = Rp. 38,225.00
- Mandor 0.050 Oh x Rp. 128,040.00 = Rp. 6,402.00
JUMLAH = Rp. 467,852.00

JUMLAH (a) + (b) = Rp. 622,108.00

9 1 m2 pasang pintu dan jendela kaca kayu Kls. I

a. Bahan

- papan 0.035 m3 x Rp. 6,432,400.00 = Rp. 225,134.00


JUMLAH = Rp. 225,134.00

b. Tenaga
- Pekerja 0.800 Oh x Rp. 116,600.00 = Rp. 93,280.00
- Tukang kayu 2.000 Oh x Rp. 122,650.00 = Rp. 245,300.00
- Kepala Tukang 0.200 Oh x Rp. 152,900.00 = Rp. 30,580.00
- Mandor 0.040 Oh x Rp. 128,040.00 = Rp. 5,121.60
JUMLAH = Rp. 374,281.60
JUMLAH (a) + (b) = Rp. 599,415.60
10 1 m2 pasang pintu dan jendela kaca kayu Kls.II

a. Bahan
- papan 0.035 m3 x Rp. 3,856,400.00 = Rp. 134,974.00
JUMLAH = Rp. 134,974.00

b. Tenaga
- Pekerja 0.800 Oh x Rp. 116,600.00 = Rp. 93,280.00
- Tukang kayu 2.000 Oh x Rp. 122,650.00 = Rp. 245,300.00
- Kepala Tukang 0.200 Oh x Rp. 152,900.00 = Rp. 30,580.00
- Mandor 0.040 Oh x Rp. 128,040.00 = Rp. 5,121.60
JUMLAH = Rp. 374,281.60

JUMLAH (a) + (b) = Rp. 509,255.60

11 1 m2 pasang pintu dan jendela kaca kayu borneo

a. Bahan

- kayu borneo, papan 0.035 m3 x Rp. 6,432,400.00 = Rp. 225,134.00


JUMLAH = Rp. 225,134.00

b. Tenaga

- Pekerja 0.800 Oh x Rp. 116,600.00 = Rp. 93,280.00


- Tukang kayu 2.000 Oh x Rp. 122,650.00 = Rp. 245,300.00
- Kepala Tukang 0.200 Oh x Rp. 152,900.00 = Rp. 30,580.00
- Mandor 0.040 Oh x Rp. 128,040.00 = Rp. 5,121.60
JUMLAH = Rp. 374,281.60

JUMLAH (a) + (b) = Rp. 599,415.60

12 1 m2 pasang jalusi ventilasi kayu Kls. I

a. Bahan

- papan 0.064 m3 x Rp. 6,432,400.00 = Rp. 411,673.60


JUMLAH = Rp. 411,673.60

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang kayu 3.000 Oh x Rp. 122,650.00 = Rp. 367,950.00
- Kepala Tukang 0.300 Oh x Rp. 152,900.00 = Rp. 45,870.00
- Mandor 0.300 Oh x Rp. 128,040.00 = Rp. 38,412.00
JUMLAH = Rp. 568,832.00

JUMLAH (a) + (b) = Rp. 980,505.60

11 1 m2 pasang pintu dan jendela jalusi kayu Kls. II

a. Bahan

- papan 0.064 m3 x Rp. 3,856,400.00 = Rp. 246,809.60


JUMLAH = Rp. 246,809.60

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang kayu 3.000 Oh x Rp. 122,650.00 = Rp. 367,950.00
- Kepala Tukang 0.300 Oh x Rp. 152,900.00 = Rp. 45,870.00
- Mandor 0.500 Oh x Rp. 128,040.00 = Rp. 64,020.00
JUMLAH = Rp. 594,440.00

JUMLAH (a) + (b) = Rp. 841,249.60

12 1 m2 pasang Pintu Teakwood Lapis Aluminium Kayu Kls. II A

a. Bahan

- papan 0.019 m3 x Rp. 3,856,400.00 = Rp. 73,271.60


- Seng Plat bjls.03 0.500 Lbr x Rp. 155,600.00 = Rp. 77,800.00
- teakwood 122 x 244 x 3 mm 0.500 Lbr x Rp. 190,750.00 = Rp. 95,375.00
- paku biasa 1/2 " -1 " 0.300 kg x Rp. 26,000.00 = Rp. 7,800.00
JUMLAH = Rp. 254,246.60

b. Tenaga

- Pekerja 0.600 Oh x Rp. 116,600.00 = Rp. 69,960.00


- Tukang kayu 2.000 Oh x Rp. 122,650.00 = Rp. 245,300.00
- Kepala Tukang 0.200 Oh x Rp. 152,900.00 = Rp. 30,580.00
- Mandor 0.030 Oh x Rp. 128,040.00 = Rp. 3,841.20
JUMLAH = Rp. 349,681.20

JUMLAH (a) + (b) = Rp. 603,927.80

14 1 m2 pasang pintu Taekwood rangkap, rangka kayu Kls. I


a. Bahan

- papan 0.020 m3 x Rp. 6,432,400.00 = Rp. 126,075.04


- paku biasa 1/2 " -1 " 0.030 kg x Rp. 23,250.00 = Rp. 697.50
- lem kayu 0.300 Lt x Rp. 11,800.00 = Rp. 3,540.00
- play wood 4 x 3 x 3 mm 1.000 Lbr x Rp. 74,370.00 = Rp. 74,370.00
JUMLAH = Rp. 204,682.54

b. Tenaga

- Pekerja 0.600 Oh x Rp. 116,600.00 = Rp. 69,960.00


- Tukang kayu 2.000 Oh x Rp. 122,650.00 = Rp. 245,300.00
- Kepala Tukang 0.200 Oh x Rp. 152,900.00 = Rp. 30,580.00
- Mandor 0.030 Oh x Rp. 128,040.00 = Rp. 3,841.20
JUMLAH = Rp. 349,681.20

JUMLAH (a) + (b) = Rp. 554,363.74

16 1 m2 pasang Ventilasi Ram Besi

a. Bahan

- Besi List 2 cm 4.4 m1 x Rp. 9,350.00 = Rp. 41,140.00


- Besi dia 6 mm 9.7 kg x Rp. 14,012.00 = Rp. 135,916.40
JUMLAH = Rp. 177,056.40

b. Tenaga

- pekerja 1.600 Oh x Rp. 116,600.00 = Rp. 186,560.00


- Tukang Las 2.000 Oh x Rp. 122,650.00 = Rp. 245,300.00
- Kepala Tukang 0.480 Oh x Rp. 152,900.00 = Rp. 73,392.00
- Mandor 0.067 Oh x Rp. 128,040.00 = Rp. 8,578.68
JUMLAH = Rp. 513,830.68

JUMLAH (a) + (b) = Rp. 690,887.08

20 1 m2 pasang pintu teakwood rangkap, rangka kayu Kls. II

a. Bahan

- papan 0.0196 m3 x Rp. 3,856,400.00 = Rp. 75,585.44


- paku biasa 1/2 " -1 " 0.3 kg x Rp. 23,250.00 = Rp. 6,975.00
- lem kayu 0.3 Lt x Rp. 11,800.00 = Rp. 3,540.00
- teakwood 4 x 8 x 4 mm 1 Lbr x Rp. 16,280.00 = Rp. 16,280.00
JUMLAH = Rp. 19,820.00

b. Tenaga

- pekerja 0.600 Oh x Rp. 116,600.00 = Rp. 69,960.00


- Tukang kayu 2.000 Oh x Rp. 122,650.00 = Rp. 245,300.00
- Kepala Tukang 0.200 Oh x Rp. 152,900.00 = Rp. 30,580.00
- Mandor 0.030 Oh x Rp. 128,040.00 = Rp. 3,841.20
JUMLAH = Rp. 349,681.20

JUMLAH (a) + (b) = Rp. 369,501.20

21 1 m2 pasang pintu plywood & formika, rangka kayu Kls. I

a. Bahan

- papan 0.0195 m3 x Rp. 6,432,400.00 = Rp. 125,431.80


- paku biasa 1/2 " -1 " 0.3 kg x Rp. 23,250.00 = Rp. 6,975.00
- lem kayu 0.8 Lt x Rp. 11,800.00 = Rp. 9,440.00
- play wood 4 x 8 x 4 mm 1 Lbr x Rp. 74,370.00 = Rp. 74,370.00
- formika 0.5 Lbr x Rp. 74,370.00 = Rp. 37,185.00
JUMLAH = Rp. 253,401.80

b. Tenaga

- pekerja 0.800 Oh x Rp. 116,600.00 = Rp. 93,280.00


- Tukang kayu 2.500 Oh x Rp. 122,650.00 = Rp. 306,625.00
- Kepala Tukang 0.250 Oh x Rp. 152,900.00 = Rp. 38,225.00
- Mandor 0.040 Oh x Rp. 128,040.00 = Rp. 5,121.60
JUMLAH = Rp. 443,251.60

JUMLAH (a) + (b) = Rp. 696,653.40

22 1 m2 pasang pintu plywood &formika rangka kayu Kls. II

a. Bahan

- papan 0.0196 m3 x Rp. 3,856,400.00 = Rp. 75,585.44


- paku biasa 1/2 " -1 " 0.3 kg x Rp. 23,250.00 = Rp. 6,975.00
- lem kayu 0.8 Lt x Rp. 11,800.00 = Rp. 9,440.00
- play wood 4 x 8 x 4 mm 1 Lbr x Rp. 74,370.00 = Rp. 74,370.00
- formika 4 x 3 0.5 Lbr x Rp. 74,370.00 = Rp. 37,185.00
JUMLAH = Rp. 203,555.44

b. Tenaga
- pekerja 0.800 Oh x Rp. 116,600.00 = Rp. 93,280.00
- Tukang kayu 2.500 Oh x Rp. 122,650.00 = Rp. 306,625.00
- Kepala Tukang 0.250 Oh x Rp. 152,900.00 = Rp. 38,225.00
- Mandor 0.040 Oh x Rp. 128,040.00 = Rp. 5,121.60
JUMLAH = Rp. 443,251.60

JUMLAH (a) + (b) = Rp. 646,807.04

23 1 m2 pasang pintu teakwood & formika rangka kayu Kls. I

a. Bahan
- papan 0.0196 m3 x Rp. 6,432,400.00 = Rp. 126,075.04
- paku biasa 1/2 " -1 " 0.3 kg x Rp. 23,250.00 = Rp. 6,975.00
- lem kayu 0.8 Lt x Rp. 11,800.00 = Rp. 9,440.00
- play wood 4 x 8 x 4 mm 0.5 Lbr x Rp. 74,370.00 = Rp. 37,185.00
- formika 4 x 8 0.5 Lbr x Rp. 74,370.00 = Rp. 37,185.00
JUMLAH = Rp. 216,860.04

b. Tenaga
- pekerja 0.800 Oh x Rp. 116,600.00 = Rp. 93,280.00
- Tukang kayu 2.500 Oh x Rp. 122,650.00 = Rp. 306,625.00
- Kepala Tukang 0.250 Oh x Rp. 152,900.00 = Rp. 38,225.00
- Mandor 0.040 Oh x Rp. 128,040.00 = Rp. 5,121.60
JUMLAH = Rp. 443,251.60

JUMLAH (a) + (b) = Rp. 660,111.64

23 1 m2 pasang pintu teakwood & formika rangka kayu Kls. II

a. Bahan

- Papan 0.0196 m3 x Rp. 3,856,400.00 = Rp. 75,585.44


- paku biasa 1/2 " -1 " 0.3 kg x Rp. 23,250.00 = Rp. 6,975.00
- lem kayu 0.8 Lt x Rp. 11,800.00 = Rp. 9,440.00
- play wood 4 x 8 x 4 mm 0.5 Lbr x Rp. 74,370.00 = Rp. 37,185.00
- formika 4 x 8 0.5 Lbr x Rp. 74,370.00 = Rp. 37,185.00
JUMLAH = Rp. 166,370.44

b. Tenaga

- pekerja 0.800 Oh x Rp. 116,600.00 = Rp. 93,280.00


- Tukang kayu 2.500 Oh x Rp. 122,650.00 = Rp. 306,625.00
- Kepala Tukang 0.250 Oh x Rp. 152,900.00 = Rp. 38,225.00
- Mandor 0.040 Oh x Rp. 128,040.00 = Rp. 5,121.60
JUMLAH = Rp. 443,251.60

JUMLAH (a) + (b) = Rp. 609,622.04

24 1 m2 pasang pintu teakwood & formika rangka kayu Kls. I ( divernis )

a. Bahan

- papan 0.0196 m3 x Rp. 6,432,400.00 = Rp. 126,075.04


- paku biasa 1/2 " -1 " 0.3 kg x Rp. 23,250.00 = Rp. 6,975.00
- lem kayu 0.8 Lt x Rp. 11,800.00 = Rp. 9,440.00
- teakwood 4 x 8 x 4 mm 0.5 Lbr x Rp. 190,750.00 = Rp. 95,375.00
- vernis 0.5 Ltr x Rp. 14,550.00 = Rp. 7,275.00
- formika 4 x 8 0.5 Lbr x Rp. 74,370.00 = Rp. 37,185.00
JUMLAH = Rp. 156,250.00

b. Tenaga

- pekerja 0.800 Oh x Rp. 116,600.00 = Rp. 93,280.00


- Tukang kayu 2.500 Oh x Rp. 122,650.00 = Rp. 306,625.00
- Kepala Tukang 0.250 Oh x Rp. 152,900.00 = Rp. 38,225.00
- Mandor 0.040 Oh x Rp. 128,040.00 = Rp. 5,121.60
JUMLAH = Rp. 443,251.60

JUMLAH (a) + (b) = Rp. 599,501.60

24 1 m2 pasang pintu teakwood & formika rangka kayu Kls. II ( divernis )

a. Bahan

- papan 0.0196 m3 x Rp. 3,856,400.00 = Rp. 75,585.44


- paku biasa 1/2 " -1 " 0.3 kg x Rp. 23,250.00 = Rp. 6,975.00
- lem kayu 0.8 Lt x Rp. 11,800.00 = Rp. 9,440.00
- teakwood 4 x 8 x 4 mm 0.5 Lbr x Rp. 190,750.00 = Rp. 95,375.00
- vernis 0.5 Ltr x Rp. 14,550.00 = Rp. 7,275.00
- formika 4 x 8 0.5 Lbr x Rp. 74,370.00 = Rp. 37,185.00
JUMLAH = Rp. 156,250.00
b. Tenaga

- pekerja 0.800 Oh x Rp. 116,600.00 = Rp. 93,280.00


- Tukang kayu 2.500 Oh x Rp. 122,650.00 = Rp. 306,625.00
- Kepala Tukang 0.250 Oh x Rp. 152,900.00 = Rp. 38,225.00
- Mandor 0.040 Oh x Rp. 128,040.00 = Rp. 5,121.60
JUMLAH = Rp. 443,251.60

JUMLAH (a) + (b) = Rp. 599,501.60

25 1 m2 pasang pintu formika double, rangka kayu Kls. I

a. Bahan

- papan 0.0196 m3 x Rp. 6,432,400.00 = Rp. 126,075.04


- paku biasa 1/2 " -1 " 0.3 kg x Rp. 23,250.00 = Rp. 6,975.00
- lem kayu 1.2 Lt x Rp. 11,800.00 = Rp. 14,160.00
- playwood 4 x 8 x 4 mm 1 Lbr x Rp. 74,370.00 = Rp. 74,370.00
- formika 4 x 8 1 Lbr x Rp. 74,370.00 = Rp. 74,370.00
JUMLAH = Rp. 295,950.04

b. Tenaga

- pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang kayu 2.600 Oh x Rp. 122,650.00 = Rp. 318,890.00
- Kepala Tukang 0.260 Oh x Rp. 152,900.00 = Rp. 39,754.00
- Mandor 0.050 Oh x Rp. 128,040.00 = Rp. 6,402.00
JUMLAH = Rp. 481,646.00

JUMLAH (a) + (b) = Rp. 777,596.04

26 1 m2 pasang pintu formika double, rangka kayu Kls. II

a. Bahan

- papan 0.0196 m3 x Rp. 3,856,400.00 = Rp. 75,585.44


- paku biasa 1/2 " -1 " 0.3 kg x Rp. 23,250.00 = Rp. 6,975.00
- lem kayu 1.2 Lt x Rp. 11,800.00 = Rp. 14,160.00
- playwood 4 x 8 x 4 mm 1 Lbr x Rp. 74,370.00 = Rp. 74,370.00
- formika 4 x 8 1 Lbr x Rp. 74,370.00 = Rp. 74,370.00
JUMLAH = Rp. 245,460.44

b. Tenaga

- pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang kayu 2.600 Oh x Rp. 122,650.00 = Rp. 318,890.00
- Kepala Tukang 0.260 Oh x Rp. 152,900.00 = Rp. 39,754.00
- Mandor 0.050 Oh x Rp. 128,040.00 = Rp. 6,402.00
JUMLAH = Rp. 481,646.00

JUMLAH (a) + (b) = Rp. 727,106.44

27 1 m3 pasang konstruksi kuda - kuda kayu Kls. I

a. Bahan

- kayu balok 1.1 m3 x Rp. 6,432,400.00 = Rp. 7,075,640.00


- besi strip 15 kg x Rp. 14,012.00 = Rp. 210,180.00
- paku biasa 2" - 5" 0.8 kg x Rp. 23,250.00 = Rp. 18,600.00
JUMLAH = Rp. 7,304,420.00

b. Tenaga

- pekerja 4.000 Oh x Rp. 116,600.00 = Rp. 466,400.00


- Tukang kayu 12.000 Oh x Rp. 122,650.00 = Rp. 1,471,800.00
- Kepala Tukang 1.200 Oh x Rp. 152,900.00 = Rp. 183,480.00
- Mandor 0.200 Oh x Rp. 128,040.00 = Rp. 25,608.00
JUMLAH = Rp. 2,147,288.00

JUMLAH (a) + (b) = Rp. 9,451,708.00

28 1 m3 pasang konstruksi kuda - kuda kayu Kls. II

a. Bahan

- kayu balok 1.1 m3 x Rp. 3,856,400.00 = Rp. 4,242,040.00


- besi strip 15 kg x Rp. 14,012.00 = Rp. 210,180.00
- paku biasa 2" - 5" 0.8 kg x Rp. 23,250.00 = Rp. 18,600.00
JUMLAH = Rp. 4,470,820.00

b. Tenaga

- pekerja 4.000 Oh x Rp. 116,600.00 = Rp. 466,400.00


- Tukang kayu 12.000 Oh x Rp. 122,650.00 = Rp. 1,471,800.00
- Kepala Tukang 1.200 Oh x Rp. 152,900.00 = Rp. 611,600.00
- Mandor 0.200 Oh x Rp. 128,040.00 = Rp. 1,536,480.00
JUMLAH = Rp. 4,086,280.00

JUMLAH (a) + (b) = Rp. 8,557,100.00


29 1 m3 pasang konstruksi kuda -kuda kayu borneo

a. Bahan

- kayu borneo, balok 1.1 m3 x Rp. 6,432,400.00 = Rp. 7,075,640.00


- besi strip 15 kg x Rp. 14,012.00 = Rp. 210,180.00
- paku biasa 2" - 5" 0.8 kg x Rp. 23,250.00 = Rp. 18,600.00
JUMLAH = Rp. 7,304,420.00

b. Tenaga

- pekerja 4.000 Oh x Rp. 116,600.00 = Rp. 466,400.00


- Tukang kayu 12.000 Oh x Rp. 122,650.00 = Rp. 1,471,800.00
- Kepala Tukang 1.200 Oh x Rp. 152,900.00 = Rp. 611,600.00
- Mandor 0.200 Oh x Rp. 128,040.00 = Rp. 1,536,480.00
JUMLAH = Rp. 4,086,280.00

JUMLAH (a) + (b) = Rp. 11,390,700.00

30 1 m3 pasang konstruksi kuda-kuda kayu kruing

a. Bahan

- kayu kruing, balok 1.1 m3 x Rp. 6,432,400.00 = Rp. 7,075,640.00


- besi strip 15 kg x Rp. 14,012.00 = Rp. 210,180.00
- paku biasa 2" - 5" 0.8 kg x Rp. 23,250.00 = Rp. 18,600.00
JUMLAH = Rp. 7,304,420.00

b. Tenaga

- pekerja 4.000 Oh x Rp. 116,600.00 = Rp. 466,400.00


- Tukang kayu 12.000 Oh x Rp. 122,650.00 = Rp. 1,471,800.00
- Kepala Tukang 1.200 Oh x Rp. 152,900.00 = Rp. 611,600.00
- Mandor 0.200 Oh x Rp. 128,040.00 = Rp. 1,536,480.00
JUMLAH = Rp. 4,086,280.00

JUMLAH (a) + (b) = Rp. 11,390,700.00


28 1 m3 Pekerjaan Gording/ Skor angin kayu Kls. II

a. Bahan

- kayu balok 1.1 m3 x Rp. 3,856,400.00 = Rp. 4,242,040.00


- besi strip kg x Rp. 14,012.00 = Rp. -
- paku biasa 2" - 5" 0.8 kg x Rp. 23,250.00 = Rp. 18,600.00
JUMLAH = Rp. 4,260,640.00

b. Tenaga

- pekerja 4.000 Oh x Rp. 116,600.00 = Rp. 466,400.00


- Tukang kayu 12.000 Oh x Rp. 122,650.00 = Rp. 1,471,800.00
- Kepala Tukang 1.200 Oh x Rp. 152,900.00 = Rp. 183,480.00
- Mandor 0.200 Oh x Rp. 128,040.00 = Rp. 25,608.00
JUMLAH = Rp. 2,147,288.00

JUMLAH (a) + (b) = Rp. 6,407,928.00

31 1 m3 pasang kaso + reng genteng kodok kayu Kls. II

a. Bahan

- kayu balok 0.012 m3 x Rp. 3,856,400.00 = Rp. 46,276.80


- paku biasa 2" - 5" 0.150 kg x Rp. 23,250.00 = Rp. 3,487.50
JUMLAH = Rp. 49,764.30

b. Tenaga

- pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00


- Tukang kayu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 15,290.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 52,019.00

JUMLAH (a) + (b) = Rp. 101,783.30

32 1 m3 pasang kaso + reng genteng kodok kayu borneo

a. Bahan

- kayu barneo, balok 0.012 m3 x Rp. 3,856,400.00 = Rp. 46,276.80


- paku biasa 2" - 5" 0.150 kg x Rp. 23,250.00 = Rp. 3,487.50
JUMLAH = Rp. 49,764.30

b. Tenaga

- pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00


- Tukang kayu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 15,290.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 52,019.00

JUMLAH (a) + (b) = Rp. 101,783.30

33 1 m3 pasang kaso + reng genteng monier kayu Kls. II

a. Bahan

- kayu balok 0.014 m3 x Rp. 3,856,400.00 = Rp. 53,989.60


- paku biasa 2" - 5" 0.150 kg x Rp. 23,250.00 = Rp. 3,487.50
JUMLAH = Rp. 57,477.10

b. Tenaga

- pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00


- Tukang kayu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 15,290.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 52,019.00

JUMLAH (a) + (b) = Rp. 109,496.10

34 1 m2 pasang kaso + reng genteng monier kayu kamper

a. Bahan

- kayu kamper, balok 0.014 m3 x Rp. 3,856,400.00 = Rp. 53,989.60


- paku biasa 2" - 5" 0.150 kg x Rp. 23,250.00 = Rp. 3,487.50
JUMLAH = Rp. 57,477.10

b. Tenaga

- pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00


- Tukang kayu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 15,290.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 52,019.00

JUMLAH (a) + (b) = Rp. 109,496.10

35 1 m2 pasang kaso + reng genteng Metal kayu Kls. II

a. Bahan

- kayu balok 0.014 m3 x Rp. 3,856,400.00 = Rp. 53,989.60


- paku biasa 2" - 5" 0.150 kg x Rp. 23,250.00 = Rp. 3,487.50
JUMLAH = Rp. 57,477.10

b. Tenaga

- pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00


- Tukang kayu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 15,290.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 52,019.00

JUMLAH (a) + (b) = Rp. 109,496.10

36 1 m2 pasang kaso + reng atap sirap kayu Kls. II

a. Bahan

- kayu balok 0.165 m3 x Rp. 3,856,400.00 = Rp. 636,306.00


- paku biasa 2" - 5" 0.200 kg x Rp. 23,250.00 = Rp. 4,650.00
JUMLAH = Rp. 640,956.00

b. Tenaga

- pekerja 0.120 Oh x Rp. 116,600.00 = Rp. 13,992.00


- Tukang kayu 0.120 Oh x Rp. 122,650.00 = Rp. 14,718.00
- Kepala Tukang 0.012 Oh x Rp. 152,900.00 = Rp. 18,348.00
- Mandor 0.006 Oh x Rp. 128,040.00 = Rp. 15,364.80
JUMLAH = Rp. 62,422.80

JUMLAH (a) + (b) = Rp. 703,378.80

37 1 m2 pasang kaso + reng atap sirap kayu barneo

a. Bahan

- kayu borneo, balok 0.165 m3 x Rp. 3,856,400.00 = Rp. 636,306.00


- paku biasa 2" - 5" 0.200 kg x Rp. 23,250.00 = Rp. 4,650.00
JUMLAH = Rp. 640,956.00

b. Tenaga

- pekerja 0.120 Oh x Rp. 116,600.00 = Rp. 13,992.00


- Tukang kayu 0.120 Oh x Rp. 122,650.00 = Rp. 14,718.00
- Kepala Tukang 0.012 Oh x Rp. 152,900.00 = Rp. 18,348.00
- Mandor 0.006 Oh x Rp. 128,040.00 = Rp. 15,364.80
JUMLAH = Rp. 62,422.80

JUMLAH (a) + (b) = Rp. 703,378.80

38 1 m2 pasang angka langit - langit (0.61 x 1.22) m, kayu jati

a. Bahan

- kayu balok 0.012 m3 x Rp. 6,432,400.00 = Rp. 77,188.80


- paku biasa 2" - 5" 0.100 kg x Rp. 23,250.00 = Rp. 2,325.00
JUMLAH = Rp. 79,513.80

b. Tenaga

- pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00


- Tukang kayu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.075 Oh x Rp. 128,040.00 = Rp. 32,010.00
JUMLAH = Rp. 103,097.50

JUMLAH (a) + (b) = Rp. 182,611.30

39 1 m2 pasang rangka langit - langit (0.61 x 1.22) m, kayu Kls. II

a. Bahan

- kayu balok 0.012 m3 x Rp. 3,856,400.00 = Rp. 46,276.80


- paku biasa 2" - 5" 0.100 kg x Rp. 23,250.00 = Rp. 2,325.00
JUMLAH = Rp. 48,601.80

b. Tenaga

- pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00


- Tukang kayu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.075 Oh x Rp. 128,040.00 = Rp. 32,010.00
JUMLAH = Rp. 103,097.50

JUMLAH (a) + (b) = Rp. 151,699.30

40 1 m2 pasang angka langit - langit (1.00 x 1.00) m, kayu borneo

a. Bahan

- kayu borneo, balok 0.012 m3 x Rp. 1,000.00 = Rp. 12.00


- paku biasa 2" - 5" 0.100 kg x Rp. 1,000.00 = Rp. 100.00
JUMLAH = Rp. 112.00

b. Tenaga

- pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00


- Tukang kayu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.075 Oh x Rp. 128,040.00 = Rp. 32,010.00
JUMLAH = Rp. 103,097.50

JUMLAH (a) + (b) = Rp. 103,209.50

41 1 m2 pasang angka langit - langit (0.305 x 0.61) M, kayu jati

a. Bahan

- kayu balok 0.023 m3 x Rp. 6,432,400.00 = Rp. 147,945.20


- paku biasa 2" - 5" 0.150 kg x Rp. 23,250.00 = Rp. 3,487.50
JUMLAH = Rp. 151,432.70

b. Tenaga

- pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang kayu 0.300 Oh x Rp. 122,650.00 = Rp. 36,795.00
- Kepala Tukang 0.030 Oh x Rp. 152,900.00 = Rp. 30,580.00
- Mandor 0.010 Oh x Rp. 128,040.00 = Rp. 38,412.00
JUMLAH = Rp. 129,107.00

JUMLAH (a) + (b) = Rp. 280,539.70

42 1 m2 pasang angka langit - langit (0.305 x 0.61) m, kayu Kls. II

a. Bahan

- kayu balok 0.023 m3 x Rp. 3,856,400.00 = Rp. 88,697.20


- paku biasa 2" - 5" 0.150 kg x Rp. 23,250.00 = Rp. 3,487.50
JUMLAH = Rp. 92,184.70

b. Tenaga

- pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang kayu 0.300 Oh x Rp. 122,650.00 = Rp. 36,795.00
- Kepala Tukang 0.030 Oh x Rp. 152,900.00 = Rp. 30,580.00
- Mandor 0.010 Oh x Rp. 128,040.00 = Rp. 38,412.00
JUMLAH = Rp. 129,107.00

JUMLAH (a) + (b) = Rp. 221,291.70

43 1 m2 pasang angka langit - langit (30 x 60) cm, kayu borneo

a. Bahan

- kayu borneo, balok 0.023 m3 x Rp. 3,856,400.00 = Rp. 88,697.20


- paku biasa 2" - 5" 0.150 kg x Rp. 23,250.00 = Rp. 3,487.50
JUMLAH = Rp. 92,184.70

b. Tenaga

- pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang kayu 0.300 Oh x Rp. 122,650.00 = Rp. 36,795.00
- Kepala Tukang 0.030 Oh x Rp. 152,900.00 = Rp. 30,580.00
- Mandor 0.010 Oh x Rp. 128,040.00 = Rp. 38,412.00
JUMLAH = Rp. 129,107.00

JUMLAH (a) + (b) = Rp. 221,291.70

44 1 m2 pasang rangka langit - langit (0.305 x 0.305) cm, kayu Kls. II

a. Bahan

- kayu balok 0.027 m3 x Rp. 6,432,400.00 = Rp. 173,674.80


- paku biasa 2" - 5" 0.200 kg x Rp. 23,250.00 = Rp. 4,650.00
JUMLAH = Rp. 178,324.80

b. Tenaga

- pekerja 0.250 Oh x Rp. 116,600.00 = Rp. 29,150.00


- Tukang kayu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Kepala Tukang 0.036 Oh x Rp. 152,900.00 = Rp. 38,225.00
- Mandor 0.013 Oh x Rp. 128,040.00 = Rp. 44,814.00
JUMLAH = Rp. 155,116.50

JUMLAH (a) + (b) = Rp. 333,441.30

45 1 m2 pasang angka langit - langit (30 x 30) cm, kayu kamper

a. Bahan

- kayu kamper, balok 0.027 m3 x Rp. 3,856,400.00 = Rp. 104,122.80


- paku biasa 2" - 5" 0.200 kg x Rp. 23,250.00 = Rp. 4,650.00
JUMLAH = Rp. 108,772.80

b. Tenaga

- pekerja 0.250 Oh x Rp. 116,600.00 = Rp. 29,150.00


- Tukang kayu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Kepala Tukang 0.035 Oh x Rp. 152,900.00 = Rp. 5,351.50
- Mandor 0.013 Oh x Rp. 128,040.00 = Rp. 1,600.50
JUMLAH = Rp. 79,029.50

JUMLAH (a) + (b) = Rp. 187,802.30

46 1 m2 pasang angka langit - langit (30 x 30) cm, kayu borneo

a. Bahan

- kayu borneo, balok 0.027 m3 x Rp. 3,856,400.00 = Rp. 104,122.80


- paku biasa 2" - 5" 0.200 kg x Rp. 23,250.00 = Rp. 4,650.00
JUMLAH = Rp. 108,772.80

b. Tenaga

- pekerja 0.250 Oh x Rp. 116,600.00 = Rp. 29,150.00


- Tukang kayu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Kepala Tukang 0.035 Oh x Rp. 152,900.00 = Rp. 5,351.50
- Mandor 0.013 Oh x Rp. 128,040.00 = Rp. 1,600.50
JUMLAH = Rp. 79,029.50

JUMLAH (a) + (b) = Rp. 187,802.30


36 1 m2 pasang Plafon Tripleks 3 mm+ Rangka Kayu Kls II

a. Bahan

- Kayu Kls II 0.012 m3 x Rp. 3,856,400.00 = Rp. 46,276.80


- Tripleks 3 mm 0.382 m2 x Rp. 99,500.00 = Rp. 38,009.00
- Paku Campur 0.100 kg x Rp. 23,250.00 = Rp. 2,325.00
JUMLAH = Rp. 86,610.80

b. Tenaga

- Pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00


- Tukang kayu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.075 Oh x Rp. 128,040.00 = Rp. 9,603.00
JUMLAH = Rp. 61,578.00

JUMLAH (a) + (b) = Rp. 148,188.80

2. 1 m2 pasang Plafon Gipsum + Rangka Kayu Kls II

a. Bahan

- Kayu Kls II 0.027 m3 x Rp. 3,856,400.00 = Rp. 104,122.80


- Gipsum 0.382 Lbr x Rp. 110,025.00 = Rp. 42,029.55
- Paku Campur 0.150 kg x Rp. 34,466.67 = Rp. 5,170.00
JUMLAH = Rp. 151,322.35

b. Tenaga

- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang kayu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.075 Oh x Rp. 128,040.00 = Rp. 9,603.00
JUMLAH = Rp. 67,408.00

JUMLAH (a) + (b) = Rp. 218,730.35

2. 1 m2 pasang Plafon Tripleks 3 mm

a. Bahan

- Kayu Kls II m3 x Rp. 3,856,400.00 = Rp. -


- Tripleks 3 mm 0.382 m3 x Rp. 99,500.00 = Rp. 38,009.00
- Paku Campur 0.100 m3 x Rp. 23,250.00 = Rp. 2,325.00
JUMLAH = Rp. 40,334.00

b. Tenaga

- Pekerja 0.075 Oh x Rp. 116,600.00 = Rp. 8,745.00


- Tukang kayu 0.125 Oh x Rp. 122,650.00 = Rp. 15,331.25
- Kepala Tukang 0.013 Oh x Rp. 152,900.00 = Rp. 1,911.25
- Mandor 0.038 Oh x Rp. 128,040.00 = Rp. 4,801.50
JUMLAH = Rp. 30,789.00

JUMLAH (a) + (b) = Rp. 71,123.00

47 1 m2 pasang lisplang ukuran (2 x 25) cm, kayu Kls. I

a. Bahan

- kayu papan 0.04 m3 x Rp. 6,432,400.00 = Rp. 257,296.00


- paku biasa 2" - 5" 0.050 kg x Rp. 23,250.00 = Rp. 1,162.50
JUMLAH = Rp. 258,458.50

b. Tenaga

- pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00


- Tukang kayu 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 40,652.70

JUMLAH (a) + (b) = Rp. 299,111.20


60 1 m1 pasang list plafon Gipsum

a. Bahan

- profil gipsum 1.05 m1 x Rp. 46,775.00 = Rp. 49,113.75


JUMLAH = Rp. 49,113.75

b. Tenaga

- pekerja 0.021 Oh x Rp. 116,600.00 = Rp. 2,448.60


- Tukang kayu 0.021 Oh x Rp. 122,650.00 = Rp. 2,575.65
- Kepala Tukang 0.002 Oh x Rp. 152,900.00 = Rp. 305.80
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 128.04
JUMLAH = Rp. 5,458.09

JUMLAH (a) + (b) = Rp. 54,571.84


PEKERJAAN BETON

1. 1 m3 Membuat Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr

a. Bahan

- Semen Portland 218.000 Kg x Rp. 2,082.80 = Rp. 454,050.40


- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.870 M3 x Rp. 536,400.00 = Rp. 466,668.00
JUMLAH = Rp. 1,139,950.40

b. Tenaga

- Pekerja 1.650 Oh x Rp. 116,600.00 = Rp. 192,390.00


- Tukang Batu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.080 Oh x Rp. 128,040.00 = Rp. 10,243.20
JUMLAH = Rp. 237,118.20

JUMLAH (a) + (b) = Rp. 1,377,068.60

2 1 m3 Membuat Beton Tumbuk, 1 Pc : 2 Ps : 3 Kr

a. Bahan

- Semen Portland 239.000 Kg x Rp. 2,082.80 = Rp. 497,789.20


- Pasir Beton 0.570 M3 x Rp. 421,600.00 = Rp. 240,312.00
- Koral Beton 0.940 M3 x Rp. 536,400.00 = Rp. 504,216.00
JUMLAH = Rp. 1,242,317.20

b. Tenaga

- Pekerja 1.650 Oh x Rp. 116,600.00 = Rp. 192,390.00


- Tukang Batu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.080 Oh x Rp. 128,040.00 = Rp. 10,243.20
JUMLAH = Rp. 237,118.20

JUMLAH (a) + (b) = Rp. 1,479,435.40

3 1 m2 Membuat Lantai Kerja Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr, Tebal 5 cm

a. Bahan

- Semen Portland 10.000 Kg x Rp. 2,082.80 = Rp. 20,828.00


- Pasir Beton 0.026 M3 x Rp. 421,600.00 = Rp. 10,961.60
- Koral Beton 0.044 M3 x Rp. 536,400.00 = Rp. 23,601.60
JUMLAH = Rp. 55,391.20

b. Tenaga

- Pekerja 1.150 Oh x Rp. 116,600.00 = Rp. 134,090.00


- Tukang Batu 0.020 Oh x Rp. 122,650.00 = Rp. 2,453.00
- Kepala Tukang 0.002 Oh x Rp. 152,900.00 = Rp. 305.80
- Mandor 0.006 Oh x Rp. 128,040.00 = Rp. 768.24
JUMLAH = Rp. 137,617.04

JUMLAH (a) + (b) = Rp. 193,008.24

20 1 m3 Membuat pondasi beton bertulang 200.00 Kg + Strous

a. Bahan
- Kayu Terentang 0.200 M3 x Rp. 3,856,400.00 = Rp. 771,280.00
- Paku biasa 2" - 5" 1.500 Kg x Rp. 23,250.00 = Rp. 34,875.00
- Pipa PVC 3" 4.000 M x Rp. 56,210.00 = Rp. 224,840.00
- Besi Beton Polos 200.000 Kg x Rp. 14,012.00 = Rp. 2,802,400.00
- Kawat Beton 2.500 Kg x Rp. 25,990.00 = Rp. 64,975.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
JUMLAH = Rp. 5,208,738.40

b. Tenaga
- Pekerja 3.900 Oh x Rp. 116,600.00 = Rp. 454,740.00
- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 1.040 Oh x Rp. 122,650.00 = Rp. 127,556.00
- Tukang besi 1.050 Oh x Rp. 122,650.00 = Rp. 128,782.50
- Kepala Tukang 0.245 Oh x Rp. 152,900.00 = Rp. 37,460.50
- Mandor 0.165 Oh x Rp. 128,040.00 = Rp. 21,126.60
JUMLAH = Rp. 812,593.10

JUMLAH (a) + (b) = Rp. 6,021,331.50


21 1 m3 Membuat beton cor lantai + besi Wermes

a. Bahan
- Kayu Terentang 0.200 M3 x Rp. - = Rp. -
- Paku biasa 2" - 5" 1.500 Kg x Rp. - = Rp. -
- Minyak bekisting 0.400 Lt x Rp. - = Rp. -
- Besi Wermes 10.000 M2 x Rp. 22,000.00 = Rp. 220,000.00
- Kawat Beton 0.500 Kg x Rp. 25,990.00 = Rp. 12,995.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
JUMLAH = Rp. 1,543,363.40

b. Tenaga
- Pekerja 3.900 Oh x Rp. 116,600.00 = Rp. 454,740.00
- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 1.040 Oh x Rp. 122,650.00 = Rp. 127,556.00
- Tukang besi 1.050 Oh x Rp. 122,650.00 = Rp. 128,782.50
- Kepala Tukang 0.245 Oh x Rp. 152,900.00 = Rp. 37,460.50
- Mandor 0.165 Oh x Rp. 128,040.00 = Rp. 21,126.60
JUMLAH = Rp. 812,593.10

JUMLAH (a) + (b) = Rp. 2,355,956.50

21 1 m3 Membuat Tapak/pondasi beton bert 170.000 + 1 bekisting

a. Bahan
- Kayu Terentang 0.200 M3 x Rp. 3,856,400.00 = Rp. 771,280.00
- Paku biasa 2" - 5" 1.500 Kg x Rp. 23,250.00 = Rp. 34,875.00
- Minyak bekisting 0.400 Lt x Rp. 39,850.00 = Rp. 15,940.00
- Besi Beton Polos 170.000 Kg x Rp. 14,012.00 = Rp. 2,382,040.00
- Kawat Beton 3.000 Kg x Rp. 25,990.00 = Rp. 77,970.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
JUMLAH = Rp. 4,592,473.40

b. Tenaga
- Pekerja 3.900 Oh x Rp. 116,600.00 = Rp. 454,740.00
- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 1.040 Oh x Rp. 122,650.00 = Rp. 127,556.00
- Tukang besi 1.050 Oh x Rp. 122,650.00 = Rp. 128,782.50
- Kepala Tukang 0.245 Oh x Rp. 152,900.00 = Rp. 37,460.50
- Mandor 0.165 Oh x Rp. 128,040.00 = Rp. 21,126.60
JUMLAH = Rp. 812,593.10

JUMLAH (a) + (b) = Rp. 5,405,066.50

23 1 m3 Membuat Sloof beton bertulang 200.00 Kg + bekisting

a. Bahan
- Kayu Terentang 0.270 M3 x Rp. 3,856,400.00 = Rp. 1,041,228.00
- Paku biasa 2" - 5" 2.000 Kg x Rp. 23,250.00 = Rp. 46,500.00
- Minyak bekisting 0.600 Lt x Rp. 39,850.00 = Rp. 23,910.00
- Besi Beton Polos 200.000 Kg x Rp. 14,012.00 = Rp. 2,802,400.00
- Kawat Beton 4.000 Kg x Rp. 25,990.00 = Rp. 103,960.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
JUMLAH = Rp. 5,328,366.40

b. Tenaga
- Pekerja 4.850 Oh x Rp. 116,600.00 = Rp. 565,510.00
- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 1.560 Oh x Rp. 122,650.00 = Rp. 191,334.00
- Tukang besi 1.400 Oh x Rp. 122,650.00 = Rp. 171,710.00
- Kepala Tukang 0.331 Oh x Rp. 152,900.00 = Rp. 50,609.90
- Mandor 0.170 Oh x Rp. 128,040.00 = Rp. 21,766.80
JUMLAH = Rp. 1,043,858.20

JUMLAH (a) + (b) = Rp. 6,372,224.60

23 1 m3 Membuat Sloof beton bertulang 120.00 Kg + bekisting

a. Bahan
- Kayu Terentang 0.270 M3 x Rp. 3,856,400.00 = Rp. 1,041,228.00
- Paku biasa 2" - 5" 2.000 Kg x Rp. 23,250.00 = Rp. 46,500.00
- Minyak bekisting 0.600 Lt x Rp. 39,850.00 = Rp. 23,910.00
- Besi Beton Polos 120.000 Kg x Rp. 14,012.00 = Rp. 1,681,440.00
- Kawat Beton 2.400 Kg x Rp. 25,990.00 = Rp. 62,376.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
JUMLAH = Rp. 4,165,822.40

b. Tenaga
- Pekerja 4.850 Oh x Rp. 116,600.00 = Rp. 565,510.00
- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 1.560 Oh x Rp. 122,650.00 = Rp. 191,334.00
- Tukang besi 1.400 Oh x Rp. 122,650.00 = Rp. 171,710.00
- Kepala Tukang 0.331 Oh x Rp. 152,900.00 = Rp. 50,609.90
- Mandor 0.170 Oh x Rp. 128,040.00 = Rp. 21,766.80
JUMLAH = Rp. 1,043,858.20

JUMLAH (a) + (b) = Rp. 5,209,680.60


23 1 m3 Membuat Sloof beton bertulang 150.00 Kg + bekisting

a. Bahan
- Kayu Terentang 0.270 M3 x Rp. 3,856,400.00 = Rp. 1,041,228.00
- Paku biasa 2" - 5" 2.000 Kg x Rp. 23,250.00 = Rp. 46,500.00
- Minyak bekisting 0.600 Lt x Rp. 39,850.00 = Rp. 23,910.00
- Besi Beton Polos 150.000 Kg x Rp. 14,012.00 = Rp. 2,101,800.00
- Kawat Beton 3.000 Kg x Rp. 25,990.00 = Rp. 77,970.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
JUMLAH = Rp. 4,601,776.40

b. Tenaga
- Pekerja 4.850 Oh x Rp. 116,600.00 = Rp. 565,510.00
- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 1.560 Oh x Rp. 122,650.00 = Rp. 191,334.00
- Tukang besi 1.400 Oh x Rp. 122,650.00 = Rp. 171,710.00
- Kepala Tukang 0.331 Oh x Rp. 152,900.00 = Rp. 50,609.90
- Mandor 0.170 Oh x Rp. 128,040.00 = Rp. 21,766.80
JUMLAH = Rp. 1,043,858.20

JUMLAH (a) + (b) = Rp. 5,645,634.60

24 1 m3 Membuat Kolom beton bertulang 300.00 Kg + bekisting

a. Bahan
- Kayu Terentang 0.400 M3 x Rp. 3,856,400.00 = Rp. 1,542,560.00
- Paku biasa 2" - 5" 4.000 Kg x Rp. 23,250.00 = Rp. 93,000.00
- Minyak bekisting 2.000 Lt x Rp. 39,850.00 = Rp. 79,700.00
- Besi Beton Polos 300.000 Kg x Rp. 14,012.00 = Rp. 4,203,600.00
- Kawat Beton 6.000 Kg x Rp. 25,990.00 = Rp. 155,940.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
- Kayu Balok 0.150 M3 x Rp. 3,856,400.00 = Rp. 578,460.00
- Plywood 9 mm 3.500 Lbr x Rp. 161,550.00 = Rp. 565,425.00
- Dolken kayu galam Ø 8-10/4 m 26.000 Btg x Rp. 59,800.00 = Rp. 1,554,800.00
JUMLAH = Rp. 10,083,853.40

b. Tenaga
- Pekerja 7.300 Oh x Rp. 116,600.00 = Rp. 851,180.00
- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 3.300 Oh x Rp. 122,650.00 = Rp. 404,745.00
- Tukang besi 2.100 Oh x Rp. 122,650.00 = Rp. 257,565.00
- Kepala Tukang 0.750 Oh x Rp. 152,900.00 = Rp. 114,675.00
- Mandor 0.250 Oh x Rp. 128,040.00 = Rp. 32,010.00
JUMLAH = Rp. 1,703,102.50

JUMLAH (a) + (b) = Rp. 11,786,955.90

27 1 m3 Membuat Kolom beton bertulang 170.00 Kg + bekisting

a. Bahan

- Kayu Terentang 0.400 M3 x Rp. 3,856,400.00 = Rp. 1,542,560.00


- Paku biasa 2" - 5" 4.000 Kg x Rp. 23,250.00 = Rp. 93,000.00
- Minyak bekisting 2.000 Lt x Rp. 39,850.00 = Rp. 79,700.00
- Besi Beton Polos 170.000 Kg x Rp. 14,012.00 = Rp. 2,382,040.00
- Kawat Beton 3.400 Kg x Rp. 25,990.00 = Rp. 88,366.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
- Kayu Balok 0.102 M3 x Rp. 3,856,400.00 = Rp. 393,352.80
- Plywood 9 mm 3.500 Lbr x Rp. 161,550.00 = Rp. 565,425.00
- Dolken kayu galam Ø 8-10/4 m 21.200 Btg x Rp. 59,800.00 = Rp. 1,267,760.00
JUMLAH = Rp. 7,722,572.20

b. Tenaga

- Pekerja 7.060 Oh x Rp. 116,600.00 = Rp. 823,196.00


- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 3.300 Oh x Rp. 122,650.00 = Rp. 404,745.00
- Tukang besi 1.860 Oh x Rp. 122,650.00 = Rp. 228,129.00
- Kepala Tukang 0.510 Oh x Rp. 152,900.00 = Rp. 77,979.00
- Mandor 0.226 Oh x Rp. 128,040.00 = Rp. 28,937.04
JUMLAH = Rp. 1,605,913.54

JUMLAH (a) + (b) = Rp. 9,328,485.74


27 1 m3 Membuat Kolom beton tak bertulan 150.00 Kg + bekisting
a. Bahan

- Kayu Terentang 0.400 M3 x Rp. 3,856,400.00 = Rp. 1,542,560.00


- Paku biasa 2" - 5" 4.000 Kg x Rp. 23,250.00 = Rp. 93,000.00
- Minyak bekisting 2.000 Lt x Rp. 39,850.00 = Rp. 79,700.00
- Besi Beton Polos 150.000 Kg x Rp. 14,012.00 = Rp. 2,101,800.00
- Kawat Beton 3.000 Kg x Rp. 25,990.00 = Rp. 77,970.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
- Kayu Balok 0.102 M3 x Rp. 3,856,400.00 = Rp. 393,352.80
- Plywood 9 mm 3.500 Lbr x Rp. 161,550.00 = Rp. 565,425.00
- Dolken kayu galam Ø 8-10/4 m 21.200 Btg x Rp. 59,800.00 = Rp. 1,267,760.00
JUMLAH = Rp. 7,431,936.20

b. Tenaga

- Pekerja 7.060 Oh x Rp. 116,600.00 = Rp. 823,196.00


- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 3.300 Oh x Rp. 122,650.00 = Rp. 404,745.00
- Tukang besi 1.860 Oh x Rp. 122,650.00 = Rp. 228,129.00
- Kepala Tukang 0.510 Oh x Rp. 152,900.00 = Rp. 77,979.00
- Mandor 0.226 Oh x Rp. 128,040.00 = Rp. 28,937.04
JUMLAH = Rp. 1,605,913.54

JUMLAH (a) + (b) = Rp. 9,037,849.74

30 1 m3 Membuat Balok beton bertulang 170.00 Kg + bekisting


a. Bahan

- Kayu Terentang 0.320 M3 x Rp. 3,856,400.00 = Rp. 1,234,048.00


- Paku biasa 2" - 5" 3.200 Kg x Rp. 23,250.00 = Rp. 74,400.00
- Minyak bekisting 1.600 Lt x Rp. 39,850.00 = Rp. 63,760.00
- Besi Beton Polos 170.000 Kg x Rp. 14,012.00 = Rp. 2,382,040.00
- Kawat Beton 3.400 Kg x Rp. 25,990.00 = Rp. 88,366.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
- Kayu Balok 0.180 M3 x Rp. 3,856,400.00 = Rp. 694,152.00
- Plywood 9 mm 2.800 Lbr x Rp. 161,550.00 = Rp. 452,340.00
- Dolken kayu galam Ø 8-10/4 m 34.000 Btg x Rp. 59,800.00 = Rp. 2,033,200.00
JUMLAH = Rp. 8,332,674.40

b. Tenaga

- Pekerja 5.800 Oh x Rp. 116,600.00 = Rp. 676,280.00


- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 2.800 Oh x Rp. 122,650.00 = Rp. 343,420.00
- Tukang besi 1.050 Oh x Rp. 122,650.00 = Rp. 128,782.50
- Kepala Tukang 0.420 Oh x Rp. 152,900.00 = Rp. 64,218.00
- Mandor 0.185 Oh x Rp. 128,040.00 = Rp. 23,687.40
JUMLAH 1,279,315.40
JUMLAH (a) + (b) = Rp. 9,611,989.80

34 1 m3 Membuat Balok beton bertulang 150.00 Kg + bekisting

a. Bahan
- Kayu Terentang 0.320 M3 x Rp. 3,856,400.00 = Rp. 1,234,048.00
- Paku biasa 2" - 5" 3.200 Kg x Rp. 23,250.00 = Rp. 74,400.00
- Minyak bekisting 1.600 Lt x Rp. 39,850.00 = Rp. 63,760.00
- Besi Beton Polos 150.000 Kg x Rp. 14,012.00 = Rp. 2,101,800.00
- Kawat Beton 3.000 Kg x Rp. 25,990.00 = Rp. 77,970.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
- Kayu Balok 0.120 M3 x Rp. 3,856,400.00 = Rp. 462,768.00
- Plywood 9 mm 2.800 Lbr x Rp. 161,550.00 = Rp. 452,340.00
- Dolken kayu galam Ø 8-10/4 m 32.000 Btg x Rp. 59,800.00 = Rp. 1,913,600.00
JUMLAH = Rp. 7,691,054.40

b. Tenaga
- Pekerja 5.800 Oh x Rp. 116,600.00 = Rp. 676,280.00
- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 2.800 Oh x Rp. 122,650.00 = Rp. 343,420.00
- Tukang besi 1.050 Oh x Rp. 122,650.00 = Rp. 128,782.50
- Kepala Tukang 0.420 Oh x Rp. 152,900.00 = Rp. 64,218.00
- Mandor 0.185 Oh x Rp. 128,040.00 = Rp. 23,687.40
JUMLAH = Rp. 1,279,315.40
JUMLAH (a) + (b) = Rp. 8,970,369.80
30 1 m3 Membuat Balok beton bertulang 100.00 Kg + bekisting
a. Bahan

- Kayu Terentang 0.320 M3 x Rp. 3,856,400.00 = Rp. 1,234,048.00


- Paku biasa 2" - 5" 3.200 Kg x Rp. 23,250.00 = Rp. 74,400.00
- Minyak bekisting 1.600 Lt x Rp. 39,850.00 = Rp. 63,760.00
- Besi Beton Polos 100.000 Kg x Rp. 14,012.00 = Rp. 1,401,200.00
- Kawat Beton 2.000 Kg x Rp. 25,990.00 = Rp. 51,980.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
- Kayu Balok 0.180 M3 x Rp. 3,856,400.00 = Rp. 694,152.00
- Plywood 9 mm 2.800 Lbr x Rp. 161,550.00 = Rp. 452,340.00
- Dolken kayu galam Ø 8-10/4 m 24.000 Btg x Rp. 59,800.00 = Rp. 1,435,200.00
JUMLAH = Rp. 6,717,448.40

b. Tenaga

- Pekerja 5.800 Oh x Rp. 116,600.00 = Rp. 676,280.00


- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 2.800 Oh x Rp. 122,650.00 = Rp. 343,420.00
- Tukang besi 1.050 Oh x Rp. 122,650.00 = Rp. 128,782.50
- Kepala Tukang 0.420 Oh x Rp. 152,900.00 = Rp. 64,218.00
- Mandor 0.185 Oh x Rp. 128,040.00 = Rp. 23,687.40
JUMLAH 1,279,315.40
JUMLAH (a) + (b) = Rp. 7,996,763.80

37 1 m3 Membuat Plat beton bertulang 120.000 Kg + bekisting

a. Bahan

- Kayu Terentang 0.240 M3 x Rp. 3,856,400.00 = Rp. 925,536.00


- Paku biasa 2" - 5" 3.200 Kg x Rp. 23,250.00 = Rp. 74,400.00
- Minyak bekisting 1.600 Lt x Rp. 39,850.00 = Rp. 63,760.00
- Besi Beton Polos 120.000 Kg x Rp. 14,012.00 = Rp. 1,681,440.00
- Kawat Beton 2.250 Kg x Rp. 25,990.00 = Rp. 58,477.50
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
- Kayu Balok 0.160 M3 x Rp. 3,856,400.00 = Rp. 617,024.00
- Plywood 9 mm 2.800 Lbr x Rp. 161,550.00 = Rp. 452,340.00
- Dolken kayu galam Ø 8-10/4 m 14.000 Btg x Rp. 59,800.00 = Rp. 837,200.00
JUMLAH = Rp. 6,020,545.90

b. Tenaga

- Pekerja 5.600 Oh x Rp. 116,600.00 = Rp. 652,960.00


- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 2.640 Oh x Rp. 122,650.00 = Rp. 323,796.00
- Tukang besi 1.050 Oh x Rp. 122,650.00 = Rp. 128,782.50
- Kepala Tukang 0.400 Oh x Rp. 152,900.00 = Rp. 61,160.00
- Mandor 0.193 Oh x Rp. 128,040.00 = Rp. 24,711.72
JUMLAH = Rp. 1,234,337.72

JUMLAH (a) + (b) = Rp. 7,254,883.62

38 1 m3 Membuat Tangga beton bertulang 100.000 Kg + bekisting

a. Bahan

- Kayu Terentang 0.250 M3 x Rp. 3,856,400.00 = Rp. 964,100.00


- Paku biasa 2" - 5" 3.000 Kg x Rp. 23,250.00 = Rp. 69,750.00
- Minyak bekisting 1.200 Lt x Rp. 39,850.00 = Rp. 47,820.00
- Besi Beton Polos 100.000 Kg x Rp. 14,012.00 = Rp. 1,401,200.00
- Kawat Beton 3.000 Kg x Rp. 25,990.00 = Rp. 77,970.00
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
- Kayu Balok 0.105 M3 x Rp. 3,856,400.00 = Rp. 404,922.00
- Plywood 9 mm 2.500 Lbr x Rp. 161,550.00 = Rp. 403,875.00
- Dolken kayu Ø 8-10/4 m 14.000 Btg x Rp. 59,800.00 = Rp. 837,200.00
JUMLAH = Rp. 5,517,205.40

b. Tenaga

- Pekerja 5.600 Oh x Rp. 116,600.00 = Rp. 652,960.00


- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 2.640 Oh x Rp. 122,650.00 = Rp. 323,796.00
- Tukang besi 1.050 Oh x Rp. 122,650.00 = Rp. 128,782.50
- Kepala Tukang 0.400 Oh x Rp. 152,900.00 = Rp. 61,160.00
- Mandor 0.193 Oh x Rp. 128,040.00 = Rp. 24,711.72
JUMLAH = Rp. 1,234,337.72

JUMLAH (a) + (b) = Rp. 6,751,543.12


36 1 m3 Membuat Plat beton bertulang 100.000 Kg + bekisting

a. Bahan

- Kayu Terentang 0.240 M3 x Rp. 3,856,400.00 = Rp. 925,536.00


- Paku biasa 2" - 5" 3.200 Kg x Rp. 23,250.00 = Rp. 74,400.00
- Minyak bekisting 1.600 Lt x Rp. 39,850.00 = Rp. 63,760.00
- Besi Beton Polos 100.000 Kg x Rp. 14,012.00 = Rp. 1,401,200.00
- Kawat Beton 2.250 Kg x Rp. 25,990.00 = Rp. 58,477.50
- Semen Portland 323.000 Kg x Rp. 2,082.80 = Rp. 672,744.40
- Pasir Beton 0.520 M3 x Rp. 421,600.00 = Rp. 219,232.00
- Koral Beton 0.780 M3 x Rp. 536,400.00 = Rp. 418,392.00
- Kayu Balok 0.160 M3 x Rp. 3,856,400.00 = Rp. 617,024.00
- Plywood 9 mm 2.800 Lbr x Rp. 161,550.00 = Rp. 452,340.00
- Dolken kayu galam Ø 8-10/4 m 8.000 Btg x Rp. 59,800.00 = Rp. 478,400.00
JUMLAH = Rp. 5,381,505.90

b. Tenaga

- Pekerja 5.600 Oh x Rp. 116,600.00 = Rp. 652,960.00


- Tukang Batu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Tukang kayu 2.640 Oh x Rp. 122,650.00 = Rp. 323,796.00
- Tukang besi 1.050 Oh x Rp. 122,650.00 = Rp. 128,782.50
- Kepala Tukang 0.400 Oh x Rp. 152,900.00 = Rp. 61,160.00
- Mandor 0.193 Oh x Rp. 128,040.00 = Rp. 24,711.72
JUMLAH = Rp. 1,234,337.72

JUMLAH (a) + (b) = Rp. 6,615,843.62


PEKERJAAN PENGECATAN

1 1 m2 Mendempul dan menggosok kayu

a. Bahan

- Dempul Jadi 0.080 Kg x Rp. 35,120.00 = Rp. 2,809.60


- Minyak Cat 0.020 Kg x Rp. 36,220.00 = Rp. 724.40
- Batu Apung 0.010 Kg x Rp. 20,350.00 = Rp. 203.50
JUMLAH = Rp. 3,737.50

b. Tenaga

- Pekerja 0.040 Oh x Rp. 116,600.00 = Rp. 4,664.00


- Tukang Cat 0.040 Oh x Rp. 122,650.00 = Rp. 4,906.00
- Kepala Tukang 0.004 Oh x Rp. 152,900.00 = Rp. 611.60
- Mandor 0.0025 Oh x Rp. 128,040.00 = Rp. 320.10
JUMLAH = Rp. 10,501.70

JUMLAH (a) + (b) = Rp. 14,239.20

2 1 m2 Membersihkan cat dinding lama dari lumut/ jamur

a. Bahan

- Pisau Dempul 0.005 Bh x Rp. 42,000.00 = Rp. 210.00


- Kertas Pasir 0.020 Lbr x Rp. 8,000.00 = Rp. 160.00
- Batu Apung 0.010 Kg x Rp. 20,350.00 = Rp. 203.50
JUMLAH = Rp. 573.50

b. Tenaga

- Pekerja 0.050 Oh x Rp. 116,600.00 = Rp. 5,830.00


- Tukang Cat 0.050 Oh x Rp. 122,650.00 = Rp. 6,132.50
- Kepala Tukang 0.005 Oh x Rp. 152,900.00 = Rp. 764.50
- Mandor 0.0025 Oh x Rp. 128,040.00 = Rp. 320.10
JUMLAH = Rp. 13,047.10

JUMLAH (a) + (b) = Rp. 13,620.60

3 1 m2 Pengecatan Bidang Kayu Lama

a. Bahan

- Plamir 0.150 Kg x Rp. 10,744.00 = Rp. 1,611.60


- Cat dasar 0.170 Kg x Rp. 37,870.00 = Rp. 6,437.90
- Cat penutup 0.170 Kg x Rp. 68,780.00 = Rp. 11,692.60
JUMLAH = Rp. 19,742.10

b. Tenaga

- Pekerja 0.070 Oh x Rp. 116,600.00 = Rp. 8,162.00


- Tukang Cat 0.075 Oh x Rp. 122,650.00 = Rp. 9,198.75
- Kepala Tukang 0.0075 Oh x Rp. 152,900.00 = Rp. 1,146.75
- Mandor 0.0025 Oh x Rp. 128,040.00 = Rp. 320.10
JUMLAH = Rp. 18,827.60

JUMLAH (a) + (b) = Rp. 38,569.70

4 1 m2 Pengecatan Bidang Kayu Baru ( 1 lapis plamir ), 1 lapis cat dasar, 3 lapis cat
penutup
a. Bahan

- Cat Meni 0.200 Kg x Rp. 37,870.00 = Rp. 7,574.00


- Plamir 0.150 Kg x Rp. 10,744.00 = Rp. 1,611.60
- Cat dasar 0.170 Kg x Rp. 37,870.00 = Rp. 6,437.90
- Cat penutup 2 kali 0.350 Kg x Rp. 68,780.00 = Rp. 24,073.00
JUMLAH = Rp. 39,696.50

b. Tenaga

- Pekerja 0.070 Oh x Rp. 116,600.00 = Rp. 8,162.00


- Tukang Cat 0.105 Oh x Rp. 122,650.00 = Rp. 12,878.25
- Kepala Tukang 0.004 Oh x Rp. 152,900.00 = Rp. 611.60
- Mandor 0.0025 Oh x Rp. 128,040.00 = Rp. 320.10
JUMLAH = Rp. 21,971.95

JUMLAH (a) + (b) = Rp. 61,668.45


5 1 m2 Pengecatan Tembok Baru ( anti lumut ), 1 lapis cat dasar, 2 lapis cat
penutup
a. Bahan

- Cat Alkalin 0.150 Kg x Rp. 47,220.00 = Rp. 7,083.00


- Cat Dasar 0.170 Kg x Rp. 41,635.71 = Rp. 7,078.07
- Cat penutup 2 kali 0.360 Kg x Rp. 41,635.71 = Rp. 14,988.86
JUMLAH = Rp. 29,149.93

b. Tenaga

- Pekerja 0.035 Oh x Rp. 116,600.00 = Rp. 4,081.00


- Tukang Cat 0.075 Oh x Rp. 122,650.00 = Rp. 9,198.75
- Kepala Tukang 0.0070 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.0025 Oh x Rp. 128,040.00 = Rp. 320.10
JUMLAH = Rp. 14,670.15

JUMLAH (a) + (b) = Rp. 43,820.08

5 1 m2 Pengecatan Tembok Baru Eksterior ( anti lumut ), 1 lapis cat dasar, 2 lapis cat
penutup
a. Bahan

- Cat Alkalin 0.150 Kg x Rp. 47,220.00 = Rp. 7,083.00


- Cat Dasar 0.170 Kg x Rp. 56,815.71 = Rp. 9,658.67
- Cat penutup 2 kali 0.360 Kg x Rp. 56,815.71 = Rp. 20,453.66
JUMLAH = Rp. 37,195.33

b. Tenaga

- Pekerja 0.035 Oh x Rp. 116,600.00 = Rp. 4,081.00


- Tukang Cat 0.075 Oh x Rp. 122,650.00 = Rp. 9,198.75
- Kepala Tukang 0.0070 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.0025 Oh x Rp. 128,040.00 = Rp. 320.10
JUMLAH = Rp. 14,670.15

JUMLAH (a) + (b) = Rp. 51,865.48

5 1 m2 Pengecatan Tembok lama ( anti lumut ), 2 lapis cat


penutup
a. Bahan

- Cat penutup 2 kali 0.360 Kg x Rp. 41,635.71 = Rp. 14,988.86


JUMLAH = Rp. 14,988.86

b. Tenaga

- Pekerja 0.020 Oh x Rp. 116,600.00 = Rp. 2,332.00


- Tukang Cat 0.040 Oh x Rp. 122,650.00 = Rp. 4,906.00
- Kepala Tukang 0.0030 Oh x Rp. 152,900.00 = Rp. 458.70
- Mandor 0.0015 Oh x Rp. 128,040.00 = Rp. 192.06
JUMLAH = Rp. 7,888.76

JUMLAH (a) + (b) = Rp. 22,877.62

5 1 m2 Pengecatan Tembok Lama Eksterior ( anti lumut ), 2 lapis cat


penutup
a. Bahan

- Cat penutup 2 kali 0.360 Kg x Rp. 56,815.71 = Rp. 20,453.66


JUMLAH = Rp. 20,453.66

b. Tenaga

- Pekerja 0.020 Oh x Rp. 116,600.00 = Rp. 2,332.00


- Tukang Cat 0.040 Oh x Rp. 122,650.00 = Rp. 4,906.00
- Kepala Tukang 0.0030 Oh x Rp. 152,900.00 = Rp. 458.70
- Mandor 0.0015 Oh x Rp. 128,040.00 = Rp. 192.06
JUMLAH = Rp. 7,888.76

JUMLAH (a) + (b) = Rp. 28,342.42


6 1 m2 Pengecatan Tembok Baru ( 1 lapis plamir ), 1 lapis cat dasar, 3 lapis cat
penutup
a. Bahan

- Plamir 0.150 Kg x Rp. 10,744.00 = Rp. 1,611.60


Cat dasar 0.100 Kg x Rp. 25,044.00 2,504.40
- Cat penutup 2 kali 0.360 Kg x Rp. 25,044.00 = Rp. 9,015.84
JUMLAH = Rp. 13,131.84

b. Tenaga

- Pekerja 0.028 Oh x Rp. 116,600.00 = Rp. 3,264.80


- Tukang Cat 0.055 Oh x Rp. 122,650.00 = Rp. 6,745.75
- Kepala Tukang 0.0050 Oh x Rp. 152,900.00 = Rp. 764.50
- Mandor 0.0020 Oh x Rp. 128,040.00 = Rp. 256.08
JUMLAH = Rp. 11,031.13

JUMLAH (a) + (b) = Rp. 24,162.97

7 1 m2 Pelaburan bidang kayu dengan vernis

a. Bahan

- Vernis 0.150 ltr x Rp. 1,000.00 = Rp. 150.00


- Dempul 0.050 kg x Rp. 1,000.00 = Rp. 50.00
- Ampelas 0.100 lbr x Rp. 1,000.00 = Rp. 100.00
- Kuas 0.010 bh x Rp. 1,000.00 = Rp. 10.00
JUMLAH = Rp. 310.00

b. Tenaga

- Pekerja 0.160 Oh x Rp. 116,600.00 = Rp. 18,656.00


- Tukang Cat 0.160 Oh x Rp. 122,650.00 = Rp. 19,624.00
- Kepala Tukang 0.016 Oh x Rp. 152,900.00 = Rp. 2,446.40
- Mandor 0.0025 Oh x Rp. 128,040.00 = Rp. 320.10
JUMLAH = Rp. 41,046.50

JUMLAH (a) + (b) = Rp. 41,356.50

8 1 m2 Pelaburan bidang kayu dengan cat residu dan ter

a. Bahan

- Residu atau ter 0.350 ltr x Rp. 5,000.00 = Rp. 1,750.00


JUMLAH = Rp. 1,750.00

b. Tenaga

- Pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00


- Mandor 0.006 Oh x Rp. 128,040.00 = Rp. 768.24
JUMLAH = Rp. 12,428.24

JUMLAH (a) + (b) = Rp. 14,178.24

9 1 m2 Pengecatan permukaan baja / Seng dengan meni besi

a. Bahan

- Meni besi 0.100 Kg x Rp. 37,870.00 = Rp. 3,787.00


- Kuas 0.010 Bh x Rp. 82,475.00 = Rp. 824.75
JUMLAH = Rp. 4,611.75

b. Tenaga

- Pekerja 0.020 Oh x Rp. 116,600.00 = Rp. 2,332.00


- Tukang Cat 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00
- Kepala Tukang 0.0200 Oh x Rp. 152,900.00 = Rp. 3,058.00
- Mandor 0.0100 Oh x Rp. 128,040.00 = Rp. 1,280.40
JUMLAH = Rp. 31,200.40

JUMLAH (a) + (b) = Rp. 35,812.15


10 1 m2 Pengecatan permukaan baja dengan meni besi + Cat Besi dan perancah

a. Bahan
- Meni besi 0.200 Kg x Rp. 72,987.50 = Rp. 14,597.50
- Meni besi 0.100 Kg x Rp. 37,870.00 = Rp. 3,787.00
- Kuas 0.010 Bh x Rp. 82,475.00 = Rp. 824.75
- Perancah 0.002 M3 x Rp. 3,856,400.00 = Rp. 7,712.80
JUMLAH = Rp. 26,922.05

b. Tenaga

- Pekerja 0.250 Oh x Rp. 116,600.00 = Rp. 29,150.00


- Tukang Cat 0.225 Oh x Rp. 122,650.00 = Rp. 27,596.25
- Kepala Tukang 0.0225 Oh x Rp. 152,900.00 = Rp. 3,440.25
- Mandor 0.0075 Oh x Rp. 128,040.00 = Rp. 960.30
JUMLAH = Rp. 61,146.80

JUMLAH (a) + (b) = Rp. 88,068.85


BAHAN FABRIKASI
LOKASI : PULAU TERNATE

ANGKUT
HARGA KEUNTUNGA
NO JENIS BAHAN SPESIFIKASI SATUAN DILOKASI
DASAR (Rp) N PIHAK KE
(Rp.)
II (Rp.)
1 Semen (PC) Tonasa Zak 50 kg 87,400.00 8,000.00 8,740.00
Kg 1,748.00 160.00 174.80
2 Semen warna Kg 23,000.00 700.00 2,300.00
Semen (PC) Bosowa Zak 50 kg 85,000.00 8,000.00 8,500.00
3 Kawat Beton Kg 23,000.00 690.00 2,300.00
4 Kawat Bronjong /m 14,100.00 423.00 1,410.00
5 Kawat Duri /Rol 12,300.00 369.00 1,230.00
6 Kawat Ram Besi /m 17,800.00 534.00 1,780.00
Kawat Ram /m2 28,600.00 858.00 2,860.00
7 Besi Beton Kg 12,400.00 372.00 1,240.00
7 Besi Beton Dia. 6 mm Staf 33,900.00 1,017.00 3,390.00
8 Besi Beton Dia. 8 mm Staf 46,000.00 1,380.00 4,600.00
9 Besi Beton Dia. 10 mm Staf 71,000.00 2,130.00 7,100.00
10 Besi Beton Dia. 12 mm Staf 104,000.00 3,120.00 10,400.00
11 Besi Beton Dia. 14 mm Staf 153,000.00 4,590.00 15,300.00
12 Besi Beton Dia. 16 mm Staf 187,000.00 5,610.00 18,700.00
13 Besi Beton Dia. 19 mm Staf 267,000.00 8,010.00 26,700.00
14 Besi Beton Dia. 22 mm Staf 351,000.00 10,530.00 35,100.00
15 Besi Beton Dia. 25 mm Staf 414,000.00 12,420.00 41,400.00
16 Besi Beton Dia. 32 mm Staf 728,000.00 21,840.00 72,800.00

17 Paku Campuran Kg 20,500.00 700.00 2,050.00


18 Paku Tripleks Kg 23,000.00 700.00 2,300.00
19 Paku Seng Kg 28,700.00 700.00 2,870.00
20 Paku Beton Kg 27,200.00 700.00 2,720.00
21 Kapur Padam M3 240,000.00 7,200.00 24,000.00
22 Teakwood 3 mm Uk. 122 x 244 cm Lbr 172,500.00 1,000.00 17,250.00
23 Tripleks 4 mm Uk. 122 x 244 cm Lbr 66,700.00 1,000.00 6,670.00
24 Tripleks 6 mm Uk. 122 x 244 cm Lbr 105,500.00 1,500.00 10,550.00
25 Tripleks 9 mm Uk. 122 x 244 cm Lbr 145,500.00 1,500.00 14,550.00
Tripleks 10 mm Uk. 122 x 244 cm Lbr 166,700.00 1,500.00 16,670.00
Tripleks 20 mm Uk. 122 x 244 cm Lbr 316,200.00 2,500.00 31,620.00
26 Lisplank GRC 6 mm 20x 250 Lbr 45,000.00 1,000.00 4,500.00
27 Hard Board Uk. 122 x 244 cm Lbr 78,000.00 1,000.00 7,800.00
28 Gipsum (elephant) 9 mm Lbr 97,750.00 2,500.00 9,775.00
29 List Profil Gipsum 15 cm Staf 40,250.00 2,500.00 4,025.00
List Profil Gipsum 12 cm Staf 34,500.00 2,500.00 3,450.00
List Profil Gipsum 10 cm Staf 31,000.00 2,500.00 3,100.00

30 Pipa Galvanis Medium B Uk. 1/2 " M' 49,900.00 4,990.00


31 Pipa Galvanis Medium B Uk. 3/4 " M' 60,900.00 6,090.00
32 Pipa Galvanis Medium B Uk. 1 " M' 93,900.00 9,390.00
33 Pipa Galvanis Medium B Uk. 11/4 " M' 110,400.00 11,040.00
34 Pipa Galvanis Medium B Uk. 1 1/2 " M' 54,050.00 5,405.00
35 Pipa Galvanis Medium B Uk. 2 " M' 72,916.67 7,291.67
36 Pipa Galvanis Medium B Uk. 2 1/2 " M' 88,500.00 8,850.00
37 Pipa Besi Hollow M' 24,166.67 2,416.67
38 Pipa GIP Medium A Uk. 1 1/2 " M' 31,333.33 3,133.33
39 Pipa GIP Medium A Uk. 2 " M' 124,833.33 12,483.33
40 Pipa GIP Medium A Uk. 3 " M' 208,233.33 20,823.33
41 Pipa GIP Medium A Uk. 4 " M' 250,000.00 25,000.00
42 Pipa GIP Medium A Uk. 6 " M' 325,000.00 32,500.00

43 Pipa PVC Uk. 1/2 " M' 7,800.00 780.00


44 Pipa PVC Uk. 3/4 " M' 11,800.00 1,180.00
45 Pipa PVC Uk. 1 " M' 14,800.00 1,480.00
46 Pipa PVC Uk. 11/4 " M' 9,700.00 970.00
47 Pipa PVC Uk. 11/2 " M' 16,900.00 1,690.00
48 Pipa PVC Uk. 2 " M' 26,700.00 2,670.00
49 Pipa PVC Uk. 3 " M' 51,100.00 5,110.00
50 Pipa PVC Uk. 4 " M' 80,900.00 8,090.00
51 Pipa PVC Uk.5 " M' 95,550.00 9,555.00
52 Knee PVC Uk. 1/2 " Bh 1,800.00 180.00
53 Knee PVC Uk. 3/4 " Bh 1,800.00 180.00
54 Knee PVC Uk. 1 " Bh 2,400.00 240.00
55 Knee PVC Uk. 11/4 " Bh 4,000.00 400.00
56 Knee PVC Uk. 11/2 " Bh 5,700.00 570.00
57 Knee PVC Uk. 2 1/2" Bh 7,900.00 790.00
58 Knee PVC Uk. 3 " Bh 13,400.00 1,340.00
59 Knee PVC Uk. 4 " Bh 16,700.00 1,670.00
60 Batu Bata semen Uk.12 x 25 x 8 Bh 2,000.00 200.00 200.00
Batu Bata Pres Apung Uk.25 x 50 x 8 Bh 17,000.00 500.00 1,700.00
61 Paving Stone K-300 Bh 3,450.00 300.00 345.00
62 Canstil/ pembatas jalan uk. 12x30x50 Bh 28,700.00 8,000.00 2,870.00
Wermes/ Ram lantai M2 20,000.00 2,000.00
63 Besi Plat tbl 1.2 cm M2 350,000.00 35,000.00
64 Besi List 2 cm M' 8,500.00 850.00
65 Besi Siku Uk. 30.30.3 M' 52,600.00 5,260.00
66 Besi Siku Uk. 40.40.4 M' 70,800.00 7,080.00
67 Besi Siku Uk. 50.50.5 M' 108,700.00 10,870.00
Mur baut dia. 14 mm Bh 22,200.00 2,220.00
angker Mur baut dia. 16 mm Bh 25,500.00 2,550.00
Trekstank dia. 12 mm + baut Bh 45,500.00 4,550.00
Besi Holow Alumunium 40 x 40 x 2 mm M' 32,000.00 700.00 3,200.00
Besi Holow Alumunium 20 x 40 x 2 mm M' 30,000.00 700.00 3,000.00
Metal wall stud 35mm x 40mm M' 22,500.00 200.00 2,250.00
Metal wall track 30mm x 40mm M' 19,125.00 200.00 1,912.50
Paku rivet Bh 7,000.00 700.00
Textile tape Roll 33,625.00 3,362.50
Compound gypsum Kg 6,200.00 620.00
Sekrup gypsum bh 300.00 30.00
Rangka besi siku 40.40.4 btg 210,000.00 1,600.00 21,000.00
Aluminium composite panel Lbr 1,750,000.00 2,500.00 175,000.00
Paku skrup kg 37,200.00 200.00 3,720.00
68 Seng Gelombang BJLS 0.20 mm Lbr 48,875.00 1,600.00 4,887.50
69 Seng Gelombang BJLS 0.25 mm Lbr 69,000.00 1,600.00 6,900.00
Seng Gelombang BJLS 0.30 mm Lbr 83,375.00 1,600.00 8,337.50
Seng Plat Bubungan BJLS 0.25 mm Lbr 71,875.00 1,600.00 7,187.50
Seng plat BJLS 0.30 mm Lbr 83,375.00 1,600.00 8,337.50
70 Seng Alumunium Gelombang BJLS 0.25 mm Lbr 101,200.00 1,600.00 10,120.00
Seng Aluminium Gelombang BJLS 0.30 mm Lbr 138,000.00 1,600.00 13,800.00
71 Bubungan Atap Ondoline Lbr 140,000.00 1,600.00 14,000.00
72 Atap Asbes Gelombang Lbr 72,000.00 1,600.00 7,200.00
73 Multi Roof ( Giga Steel) Lbr 49,700.00 700.00 4,970.00
74 Sakura Roof Lbr 40,250.00 700.00 4,025.00
75 Seng Plastik Gelombang Lbr 124,200.00 700.00 12,420.00
76 Atap Ondoline Lbr 260,000.00 2,500.00 26,000.00
77 Nok Atap Ondoline Bh 44,100.00 700.00 4,410.00
Nok Giga Steel Bh 43,100.00 700.00 4,310.00
Atap Spandek Lbr 240,000.00 1,000.00 24,000.00
78 Rangka Baja Ringan Giga Steel Profil C-75/75 Staf 120,175.00 10,000.00 12,017.50
Reng Baja Ringan BR-32/045 Staf 69,575.00 10,000.00 6,957.50
Skrup Baja Ringan Bh 345.00 10.00 34.50
Skrup Spandek Bh 575.00 10.00 57.50
79 Tegel Semen 30 x 30 cm M2 82,000.00 800.00 8,200.00
80 Tegel Semen 20 x 20 cm M2 62,000.00 800.00 6,200.00
81 Tegel Porselin 10 x 20 cm M2 57,100.00 1,600.00 5,710.00
82 Tegel Porselin 10 x 10 cm M2 50,100.00 1,600.00 5,010.00
83 Tegel Keramik 10 x 20 cm M2 57,100.00 1,600.00 5,710.00
84 Tegel Keramik 20 x 20 cm M2 81,500.00 1,600.00 8,150.00
85 Tegel Keramik 20 x 25 cm M2 82,800.00 1,600.00 8,280.00
86 Tegel Keramik 30 x 30 cm M2 71,300.00 1,600.00 7,130.00
87 Tegel Keramik 40 x 40 cm M2 89,700.00 1,600.00 8,970.00
88 Tegel Keramik tektur kasar 60 x60 cm M2 188,600.00 1,600.00 18,860.00
89 Granit Tile 60 x 60 cm M2 425,000.00 1,600.00 42,500.00
90 Batu alam Kasar 10 x 20 cm M2 555,000.00 8,000.00 55,500.00
Batu alam Halus 10 x 20 cm M2 258,000.00 8,000.00 25,800.00
91 Profil Tank Satinless 1100 L Bh 4,408,300.00 440,830.00
Profil Tank Fiberglass 1000 L Bh 2,242,700.00 224,270.00
92 Cat Kayu / Besi Platone Kg 62,300.00 250.00 6,230.00
Cat Kayu / Besi Dulux Kg 227,700.00 250.00 22,770.00
93 Cat Tembok Metrolite 1 Kg 22,540.00 250.00 2,254.00
94 Cat Tembok Metrolite 5 Kg 112,700.00 1,250.00 11,270.00
95 Cat Tembok anti lumut No Drop 1 Kg 69,000.00 250.00 6,900.00
Cat alkalin No Drop 1 Kg 42,700.00 250.00 4,270.00
96 Cat Meni Kayu Altex 1 Kg 34,200.00 250.00 3,420.00
Cat Meni Besi Altex 1 Kg 34,200.00 250.00 3,420.00
97 Cat Besi Avian 1 Kg 66,125.00 250.00 6,612.50
98 Minyak Cat Thinner Liter 32,700.00 250.00 3,270.00
Minyak Cat Afduner Liter 11,500.00 250.00 1,150.00
99 Cat Jotun Interior 3.5 Kg 132,250.00 250.00 13,225.00
Cat Jotun Eksterior 3.5 Kg 180,550.00 250.00 18,055.00
100 Pelumas / Olie 1 Kg 36,000.00 250.00 3,600.00
101 Solar Liter 8,500.00 250.00 850.00
102 Dempul Kayu Altex Kg 31,700.00 250.00 3,170.00
103 Plamir Tembok 5 Kg Kaleng 47,700.00 250.00 4,770.00
104 Plamir Tembok 1 Kg Kaleng 9,540.00 250.00 954.00
105 Kuas Cat Bh 74,750.00 250.00 7,475.00
106 Residu Ltr 23,000.00 250.00 2,300.00
107 Lem Kayu 1 Ltr 10,500.00 250.00 1,050.00
108 Vernis 1 Ltr 13,000.00 250.00 1,300.00
109 Batu Apung 1 Kg 18,500.00 1,850.00
110 Kaca Rayban 3 mm M2 195,000.00 4,300.00 19,500.00
111 Kaca Rayban 5 mm M2 295,000.00 8,000.00 29,500.00
112 Kaca Bening 2 mm M2 69,000.00 3,500.00 6,900.00
113 Kaca Bening 3 mm M2 172,500.00 4,300.00 17,250.00
114 Kaca Bening 5 mm M2 230,000.00 8,000.00 23,000.00
Kaca Bening 8 mm M2 380,000.00 8,000.00 38,000.00
Kaca Temperet 12 mm M2 3,737,000.00 9,200.00 373,700.00
115 Kaca Cermin 3 mm M2 276,000.00 4,300.00 27,600.00

116 Kran (Kualitas Baik) Bh 40,250.00 125.00 4,025.00


117 Avour / Saringan Air Kotor Bh 186,300.00 125.00 18,630.00
118 Floor Drain TOTO Bh 28,000.00 125.00 2,800.00
119 Kloset Jongkok INA Bh 442,750.00 11,000.00 44,275.00
120 Kloset Jongkok TOTO Bh 977,500.00 11,000.00 97,750.00
121 Kloset Duduk / Lengkap INA Bh 1,220,000.00 11,000.00 122,000.00
122 Kloset Duduk / Lengkap TOTO Bh 3,162,000.00 11,000.00 316,200.00
123 Wastafel/ Lengkap TOTO Bh 802,700.00 8,800.00 80,270.00
124 Hand Shower Uk Besar/ I Tiang Bh 4,600,000.00 750.00 460,000.00
Hand Shower Uk Kecil/WC Bh 266,000.00 750.00 26,600.00
125 Pompa Air Automatick 400 Ltr/Menit Bh 3,850,000.00 385,000.00
126 Acesoris Pipa Pkt 500,000.00 50,000.00
127 IJUK Kg 11,200.00 1,120.00
128 Kunci Pintu Bh 137,700.00 13,770.00
129 Kunci Pintu Utama+Pegangan Bh 350,000.00 35,000.00
130 Grendel Jendela Bh 45,000.00 4,500.00
131 Kait Angin Bh 22,200.00 2,220.00
132 Engsel Jendela Kuningan Bh 38,700.00 3,870.00
133 Engsel Pintu Kuningan Bh 49,700.00 4,970.00
134 Engsel Jendela Kuningan Bh 1,700,000.00 170,000.00
134 Lis Profil 5 cm M' 82,700.00 8,270.00
135 Profil Baja WF ( Pabrikan ) 200x200x12x12 Kg 28,000.00 2,800.00
136 Plat Eiser M2 220,500.00 22,050.00
137 Besi Strip Kg 7,500.00 750.00
138 Pintu Rooling Door 1 M2 330,500.00 33,050.00
139 Pintu Alumanium 1 M2 275,000.00 27,500.00
140 Fibreglass M2 67,500.00 6,750.00
141 Alumunium Foil 1 M2 27,500.00 2,750.00
142 Geotekstil 1 M2 45,000.00 4,500.00
143 Oxigen 1 Btl 125,000.00 12,500.00
144 Elpiji 1 Kg 9,250.00 925.00
145 Seng Multiruf ( Type Kls. I ) 1 Lbr 140,000.00 14,000.00
146 Seng Multiruf ( Type Kls. II ) 1 Lbr 95,000.00 9,500.00
147 Asbes Gelombang (2.5x0.92 ) 5 mm M2 55,000.00 5,500.00
148 Asbes Gelombang (2.25x0.92 ) 5 mm M2 48,500.00 4,850.00
149 Asbes Gelombang (2.0x0.92 ) 5 mm M2 44,500.00 4,450.00
150 Atap Steel Gelombang / Spandec M2 87,500.00 8,750.00
151 Nok Steel 0.92 Bh 27,500.00 2,750.00
152 Nok Steel 1.05 Bh 32,500.00 3,250.00
153 Kertas Ampelas Lbr 9,000.00 900.00
154 Mur / Baut / Beugel / Angker Kg 45,090.00 4,509.00
155 Box Sekring 2 Group Bh 445,200.00 44,520.00
156 Box Sekring sedang 4 Group Bh 890,000.00 89,000.00
157 Pagar BRC M2 594,400.00 59,440.00
158 MCB 2 Ampere Bh 55,200.00 5,520.00
159 MCB 4 Ampere Bh 79,800.00 7,980.00
160 MCB 6 Ampere Bh 100,000.00 10,000.00
161 MCB 10 Ampere Bh 101,400.00 10,140.00
162 Profil Daun Pintu Aluminium lbr. 8cm M1 135,000.00 2,500.00 13,500.00
163 Profil Kusen Aluminium Tbl 4" M1 149,500.00 4,000.00 14,950.00
163 Saklar Tunggal Tanam Broko Bh 46,700.00 4,670.00
164 Saklar Ganda Tanam Broko Bh 46,700.00 4,670.00
165 Saklar Tunggal Timbul Broko Bh 8,900.00 890.00
166 Saklar Ganda Timbul Broko Bh 11,600.00 1,160.00
167 Stop Kontak Tanam Broko Bh 46,700.00 4,670.00
168 Stop Kontak Timbul Broko Bh 46,700.00 4,670.00
169 Titik Lampu Bh 200,000.00 20,000.00
170 Lampu Pijar 5 Watt Bh 2,100.00 210.00
171 Lampu Pijar 10 Watt Bh 3,500.00 350.00
172 Lampu Pijar 15 Watt Bh 3,600.00 360.00
173 Lampu Pijar 25 Watt Bh 3,700.00 370.00
174 Lampu Pijar 40 Watt Bh 4,200.00 420.00
175 Lampu Pijar 60 Watt Bh 4,200.00 420.00
176 Lampu Pijar 75 Watt Bh 4,800.00 480.00
177 Lampu Pijar 100 Watt Bh 5,600.00 560.00
178 Lampu Jari-jari 20 Watt Philips Bh 72,500.00 7,250.00
179 Lampu Jari-jari 13 Watt Philips Bh 55,000.00 5,500.00
Lampu Jari-jari 8 Watt Philips Bh 45,000.00 4,500.00
180 Lampu Don Lite ( Jari-jari Tanam ) 25 Watt Philips Bh 120,000.00 12,000.00
181 Kabel Listrik NYY NYY 3 x 2.5 mm M1 17,704.55 1,770.45
182 Alat Bantu Khusus 1 Set 100,000.00 -
183 Lapis Karvet Genteng M2 109,300.00 10,930.00
BAHAN FABRIKASI

HARGA
KET
DILOKASI (Rp.)

104,140.00
2,082.80
26,000.00
101,500.00
25,990.00
15,933.00
13,899.00
20,114.00
32,318.00
14,012.00
38,307.00
51,980.00
80,230.00
117,520.00
172,890.00
211,310.00
301,710.00
396,630.00
467,820.00
822,640.00

23,250.00
26,000.00
32,270.00
30,620.00
271,200.00
190,750.00
74,370.00
117,550.00
161,550.00
184,870.00
350,320.00
50,500.00
86,800.00
110,025.00
46,775.00
40,450.00
36,600.00

54,890.00
66,990.00
103,290.00
121,440.00
59,455.00
80,208.33
97,350.00
26,583.33
34,466.67
137,316.67
229,056.67
275,000.00
357,500.00

8,580.00
12,980.00
16,280.00
10,670.00
18,590.00
29,370.00
56,210.00
88,990.00
105,105.00
1,980.00
1,980.00
2,640.00
4,400.00
6,270.00
8,690.00
14,740.00
18,370.00
2,400.00
19,200.00
4,095.00
39,570.00
22,000.00
385,000.00
9,350.00
57,860.00
77,880.00
119,570.00
24,420.00
28,050.00
50,050.00
35,900.00
33,700.00
24,950.00
21,237.50
7,700.00
36,987.50
6,820.00
330.00
232,600.00
1,927,500.00
41,120.00
55,362.50
77,500.00
93,312.50
80,662.50
93,312.50
112,920.00
153,400.00
155,600.00
80,800.00
55,370.00
44,975.00
137,320.00
288,500.00
49,210.00
48,110.00
265,000.00
142,192.50
86,532.50
389.50
642.50
91,000.00
69,000.00
64,410.00
56,710.00
64,410.00
91,250.00
92,680.00
80,030.00
100,270.00
209,060.00
469,100.00
618,500.00
291,800.00
4,849,130.00
2,466,970.00
68,780.00
250,720.00
25,044.00
125,220.00
76,150.00
47,220.00
37,870.00
37,870.00
72,987.50
36,220.00
12,900.00
145,725.00
198,855.00
39,850.00
9,600.00
35,120.00
52,720.00
10,744.00
82,475.00
25,550.00
11,800.00
14,550.00
20,350.00
218,800.00
332,500.00
79,400.00
194,050.00
261,000.00
426,000.00
4,119,900.00
307,900.00

44,400.00
205,055.00
30,925.00
498,025.00
1,086,250.00
1,353,000.00
3,489,200.00
891,770.00
5,060,750.00
293,350.00
4,235,000.00
550,000.00
12,320.00
151,470.00
385,000.00
49,500.00
24,420.00
42,570.00
54,670.00
1,870,000.00
90,970.00
30,800.00
242,550.00
8,250.00
363,550.00
302,500.00
74,250.00
30,250.00
49,500.00
137,500.00
10,175.00
154,000.00
104,500.00
60,500.00
53,350.00
48,950.00
96,250.00
30,250.00
35,750.00
9,900.00
49,599.00
489,720.00
979,000.00
653,840.00
60,720.00
87,780.00
110,000.00
111,540.00
151,000.00
168,450.00
51,370.00
51,370.00
9,790.00
12,760.00
51,370.00
51,370.00
220,000.00
2,310.00
3,850.00
3,960.00
4,070.00
4,620.00
4,620.00
5,280.00
6,160.00
79,750.00
60,500.00
49,500.00
132,000.00
19,475.00
100,000.00
120,230.00
PEKERJAAN SANITASI

1 Memasang 1 buah kloset duduk / monoblok

a. Bahan

- Kloset duduk/monoblok 1.000 Bh x Rp. 1,353,000.00 = Rp. 1,353,000.00


- Perlengkapan 0.060 - x Rp. 1,353,000.00 = Rp. 81,180.00
JUMLAH = Rp. 1,434,180.00

b. Tenaga

- Pekerja 3.300 Oh x Rp. 116,600.00 = Rp. 384,780.00


- Tukang batu 1.100 Oh x Rp. 122,650.00 = Rp. 134,915.00
- Kepala Tukang 0.001 Oh x Rp. 152,900.00 = Rp. 152.90
- Mandor 0.160 Oh x Rp. 128,040.00 = Rp. 20,486.40
JUMLAH = Rp. 540,334.30

JUMLAH (a) + (b) = Rp. 1,974,514.30

2 Memasang 1 buah kloset jongkok porselen

a. Bahan

- Kloset Jongkok Porselen 1.000 Bh x Rp. 498,025.00 = Rp. 498,025.00


- Semen Portland 6.000 Kg x Rp. 2,082.80 = Rp. 12,496.80
- Pasir Pasang 0.010 Kg x Rp. 592,400.00 = Rp. 5,924.00
JUMLAH = Rp. 516,445.80

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang batu 1.500 Oh x Rp. 122,650.00 = Rp. 183,975.00
- Kepala Tukang 1.500 Oh x Rp. 152,900.00 = Rp. 229,350.00
- Mandor 0.160 Oh x Rp. 128,040.00 = Rp. 20,486.40
JUMLAH = Rp. 550,411.40

JUMLAH (a) + (b) = Rp. 1,066,857.20

3 Memasang 1 buah kloset jongkok teraso

a. Bahan

- Kloset Jongkok teraso 1.000 Bh x Rp. 1,086,250.00 = Rp. 1,086,250.00


- Bata Merah 5x11x22 cm 7.000 Bh x Rp. 2,400.00 = Rp. 16,800.00
- Semen Portland 6.000 Kg x Rp. 2,082.80 = Rp. 12,496.80
- Pasir Pasang 0.010 Kg x Rp. 592,400.00 = Rp. 5,924.00
JUMLAH = Rp. 1,121,470.80

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang batu 1.500 Oh x Rp. 122,650.00 = Rp. 183,975.00
- Kepala Tukang 0.300 Oh x Rp. 152,900.00 = Rp. 45,870.00
- Mandor 0.110 Oh x Rp. 128,040.00 = Rp. 14,084.40
JUMLAH = Rp. 360,529.40

JUMLAH (a) + (b) = Rp. 1,482,000.20


4 Memasang 1 buah urinoir

a. Bahan

- Urinoir 1.000 Bh x Rp. 891,770.00 = Rp. 891,770.00


- Perlengkapan 0.300 Bh x Rp. 891,770.00 = Rp. 267,531.00
- Semen Portland 6.000 Kg x Rp. 2,082.80 = Rp. 12,496.80
- Pasir Pasang 0.010 Kg x Rp. 592,400.00 = Rp. 5,924.00
JUMLAH = Rp. 1,177,721.80

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang batu 1.000 Oh x Rp. 122,650.00 = Rp. 122,650.00
- Kepala Tukang 0.100 Oh x Rp. 152,900.00 = Rp. 15,290.00
- Mandor 0.100 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 267,344.00

JUMLAH (a) + (b) = Rp. 1,445,065.80

5 Memasang 1 buah westafel

a. Bahan

- Wastafel 1.000 Bh x Rp. 891,770.00 = Rp. 891,770.00


- Perlengkapan 0.030 Bh x Rp. 891,770.00 = Rp. 26,753.10
- Semen abu-abu 6.000 Kg x Rp. 26,000.00 = Rp. 156,000.00
- Pasir Pasang 0.010 Kg x Rp. 592,400.00 = Rp. 5,924.00
JUMLAH = Rp. 1,080,447.10

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang batu 1.450 Oh x Rp. 122,650.00 = Rp. 177,842.50
- Kepala Tukang 0.150 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.100 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 330,181.50

JUMLAH (a) + (b) = Rp. 1,410,628.60

6 Memasang 1 buah bak mandi batu bata volume 0.30 m3

a. Bahan

- Batu bata 0.400 m3 x Rp. 2,400.00 = Rp. 960.00


- Semen Portland 120.000 kg x Rp. 2,082.80 = Rp. 249,936.00
- Pasir Pasang 0.300 m3 x Rp. 592,400.00 = Rp. 177,720.00
- Porselen ( 11x11 ) cm 3.600 m2 x Rp. 56,710.00 = Rp. 204,156.00
- Semen nat 6.000 Kg x Rp. 2,082.80 = Rp. 12,496.80
JUMLAH = Rp. 645,268.80
b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang batu 1.450 Oh x Rp. 122,650.00 = Rp. 177,842.50
- Kepala Tukang 0.150 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.100 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 330,181.50

JUMLAH (a) + (b) = Rp. 975,450.30

7 Memasang 1 buah bak beton volume 1 m3 air

a. Bahan

- Beton 1 : 1.5 : 2.5 0.400 m3 x Rp. 1,657,623.00 = Rp. 663,049.20


- Besi beton 120.000 kg x Rp. 14,012.00 = Rp. 1,681,440.00
- Kayu cetakan 0.300 m3 x Rp. 3,856,400.00 = Rp. 1,156,920.00
- Ubin porselin 3.600 m2 x Rp. 56,710.00 = Rp. 204,156.00
- Perlengkapan 0.100 - x Rp. 3,705,565.20 = Rp. 370,556.52
JUMLAH = Rp. 4,076,121.72

b. Tenaga

- Pekerja 3.500 Oh x Rp. 116,600.00 = Rp. 408,100.00


- Tukang batu 4.500 Oh x Rp. 122,650.00 = Rp. 551,925.00
- Kepala Tukang 0.900 Oh x Rp. 152,900.00 = Rp. 137,610.00
- Mandor 0.900 Oh x Rp. 128,040.00 = Rp. 115,236.00
JUMLAH = Rp. 1,212,871.00

JUMLAH (a) + (b) = Rp. 5,288,992.72

8 Memasang 1 m' pipa galvanis diameter 1/2 "

a. Bahan

- Pipa galvanis 1.200 m' x Rp. 9,148.33 = Rp. 10,978.00


- Perlengkapan 0.350 - x Rp. 10,978.00 = Rp. 3,842.30
JUMLAH = Rp. 14,820.30

b. Tenaga

- Pekerja 0.054 Oh x Rp. 116,600.00 = Rp. 6,296.40


- Tukang besi 0.090 Oh x Rp. 122,650.00 = Rp. 11,038.50
- Kepala Tukang 0.009 Oh x Rp. 152,900.00 = Rp. 1,376.10
- Mandor 0.027 Oh x Rp. 128,040.00 = Rp. 3,457.08
JUMLAH = Rp. 22,168.08

JUMLAH (a) + (b) = Rp. 36,988.38

9 Memasang 1 m' pipa galvanis diameter 3/4 "

a. Bahan

- Pipa galvanis 1.200 m' x Rp. 11,165.00 = Rp. 13,398.00


- Perlengkapan 0.350 - x Rp. 13,398.00 = Rp. 4,689.30
JUMLAH = Rp. 18,087.30
b. Tenaga

- Pekerja 0.054 Oh x Rp. 116,600.00 = Rp. 6,296.40


- Tukang besi 0.090 Oh x Rp. 122,650.00 = Rp. 11,038.50
- Kepala Tukang 0.009 Oh x Rp. 152,900.00 = Rp. 1,376.10
- Mandor 0.027 Oh x Rp. 128,040.00 = Rp. 3,457.08
JUMLAH = Rp. 22,168.08

JUMLAH (a) + (b) = Rp. 40,255.38

10 Memasang 1 m' pipa galvanis diameter 1 "

a. Bahan

- Pipa galvanis 1.200 m' x Rp. 17,215.00 = Rp. 20,658.00


- Perlengkapan 0.350 - x Rp. 20,658.00 = Rp. 7,230.30
JUMLAH = Rp. 27,888.30

b. Tenaga

- Pekerja 0.054 Oh x Rp. 116,600.00 = Rp. 6,296.40


- Tukang besi 0.090 Oh x Rp. 122,650.00 = Rp. 11,038.50
- Kepala Tukang 0.009 Oh x Rp. 152,900.00 = Rp. 1,376.10
- Mandor 0.027 Oh x Rp. 128,040.00 = Rp. 3,457.08
JUMLAH = Rp. 22,168.08

JUMLAH (a) + (b) = Rp. 50,056.38

11 Memasang 1 m' pipa galvanis diameter 2 1/2 "

a. Bahan

- Pipa galvanis 1.200 m' x Rp. 25,000.00 = Rp. 30,000.00


- Perlengkapan 0.350 - x Rp. 30,000.00 = Rp. 10,500.00
JUMLAH = Rp. 40,500.00

b. Tenaga

- Pekerja 0.108 Oh x Rp. 116,600.00 = Rp. 12,592.80


- Tukang besi 0.180 Oh x Rp. 122,650.00 = Rp. 22,077.00
- Kepala Tukang 0.018 Oh x Rp. 152,900.00 = Rp. 2,752.20
- Mandor 0.0054 Oh x Rp. 128,040.00 = Rp. 691.42
JUMLAH = Rp. 38,113.42

JUMLAH (a) + (b) = Rp. 78,613.42

12 Memasang 1 m' pipa PVC tipe AW diameter 1/2 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 8,580.00 = Rp. 10,296.00


- Perlengkapan 0.350 - x Rp. 10,296.00 = Rp. 3,603.60
JUMLAH = Rp. 13,899.60

b. Tenaga

- Pekerja 0.036 Oh x Rp. 116,600.00 = Rp. 4,197.60


- Tukang pipa 0.060 Oh x Rp. 122,650.00 = Rp. 7,359.00
- Kepala Tukang 0.006 Oh x Rp. 152,900.00 = Rp. 917.40
- Mandor 0.0018 Oh x Rp. 128,040.00 = Rp. 230.47
JUMLAH = Rp. 12,704.47

JUMLAH (a) + (b) = Rp. 26,604.07


15 Memasang 1 m' pipa PVC tipe AW diameter 3/4 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 12,980.00 = Rp. 15,576.00


- Perlengkapan 0.350 - x Rp. 15,576.00 = Rp. 5,451.60
JUMLAH = Rp. 21,027.60

b. Tenaga

- Pekerja 0.036 Oh x Rp. 116,600.00 = Rp. 4,197.60


- Tukang pipa 0.060 Oh x Rp. 122,650.00 = Rp. 7,359.00
- Kepala Tukang 0.006 Oh x Rp. 152,900.00 = Rp. 917.40
- Mandor 0.0018 Oh x Rp. 128,040.00 = Rp. 230.47
JUMLAH = Rp. 12,704.47

JUMLAH (a) + (b) = Rp. 33,732.07

16 Memasang 1 m' pipa PVC tipe AW diameter 1 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 16,280.00 = Rp. 19,536.00


- Perlengkapan 0.350 - x Rp. 19,536.00 = Rp. 6,837.60
JUMLAH = Rp. 26,373.60

b. Tenaga

- Pekerja 0.036 Oh x Rp. 116,600.00 = Rp. 4,197.60


- Tukang pipa 0.060 Oh x Rp. 122,650.00 = Rp. 7,359.00
- Kepala Tukang 0.006 Oh x Rp. 152,900.00 = Rp. 917.40
- Mandor 0.0018 Oh x Rp. 128,040.00 = Rp. 230.47
JUMLAH = Rp. 12,704.47

JUMLAH (a) + (b) = Rp. 39,078.07

17 Memasang 1 m' pipa PVC tipe AW diameter 1 1/2 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 18,590.00 = Rp. 22,308.00


- Perlengkapan 0.350 - x Rp. 22,308.00 = Rp. 7,807.80
JUMLAH = Rp. 30,115.80

b. Tenaga

- Pekerja 0.036 Oh x Rp. 116,600.00 = Rp. 4,197.60


- Tukang pipa 0.060 Oh x Rp. 122,650.00 = Rp. 7,359.00
- Kepala Tukang 0.006 Oh x Rp. 152,900.00 = Rp. 917.40
- Mandor 0.0018 Oh x Rp. 128,040.00 = Rp. 230.47
JUMLAH = Rp. 12,704.47

JUMLAH (a) + (b) = Rp. 42,820.27


18 Memasang 1 m' pipa PVC tipe AW diameter 2 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 29,370.00 = Rp. 35,244.00


- Perlengkapan 0.350 - x Rp. 35,244.00 = Rp. 12,335.40
JUMLAH = Rp. 47,579.40

b. Tenaga

- Pekerja 0.054 Oh x Rp. 116,600.00 = Rp. 6,296.40


- Tukang pipa 0.090 Oh x Rp. 122,650.00 = Rp. 11,038.50
- Kepala Tukang 0.009 Oh x Rp. 152,900.00 = Rp. 1,376.10
- Mandor 0.0027 Oh x Rp. 128,040.00 = Rp. 345.71
JUMLAH = Rp. 19,056.71

JUMLAH (a) + (b) = Rp. 66,636.11

19 Memasang 1 m' pipa PVC tipe AW diameter 2 1/2 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 29,370.00 = Rp. 35,244.00


- Perlengkapan 0.350 - x Rp. 35,244.00 = Rp. 12,335.40
JUMLAH = Rp. 47,579.40

b. Tenaga

- Pekerja 0.036 Oh x Rp. 116,600.00 = Rp. 4,197.60


- Tukang pipa 0.060 Oh x Rp. 122,650.00 = Rp. 7,359.00
- Kepala Tukang 0.006 Oh x Rp. 152,900.00 = Rp. 917.40
- Mandor 0.0016 Oh x Rp. 128,040.00 = Rp. 204.86
JUMLAH = Rp. 12,678.86

JUMLAH (a) + (b) = Rp. 60,258.26

20 Memasang 1 m' pipa PVC tipe AW diameter 3 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 56,210.00 = Rp. 67,452.00


- Perlengkapan 0.350 - x Rp. 67,452.00 = Rp. 23,608.20
JUMLAH = Rp. 91,060.20

b. Tenaga

- Pekerja 0.081 Oh x Rp. 116,600.00 = Rp. 9,444.60


- Tukang pipa 0.135 Oh x Rp. 122,650.00 = Rp. 16,557.75
- Kepala Tukang 0.0135 Oh x Rp. 152,900.00 = Rp. 2,064.15
- Mandor 0.0041 Oh x Rp. 128,040.00 = Rp. 524.96
JUMLAH = Rp. 28,591.46

JUMLAH (a) + (b) = Rp. 119,651.66


21 Memasang 1 m' pipa PVC tipe AW diameter 4 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 88,990.00 = Rp. 106,788.00


- Perlengkapan 0.350 - x Rp. 106,788.00 = Rp. 37,375.80
JUMLAH = Rp. 144,163.80

b. Tenaga

- Pekerja 0.081 Oh x Rp. 116,600.00 = Rp. 9,444.60


- Tukang pipa 0.135 Oh x Rp. 122,650.00 = Rp. 16,557.75
- Kepala Tukang 0.0135 Oh x Rp. 152,900.00 = Rp. 2,064.15
- Mandor 0.0041 Oh x Rp. 128,040.00 = Rp. 524.96
JUMLAH = Rp. 28,591.46

JUMLAH (a) + (b) = Rp. 172,755.26

22 Memasang 1 buah bak cuci piring stainles steel

a. Bahan

- Bak cuci stainles steel 1.000 Bh x Rp. 360,000.00 = Rp. 360,000.00


- Water drain + asesories 1.000 set x Rp. 150,000.00 = Rp. 150,000.00
JUMLAH = Rp. 510,000.00

b. Tenaga

- Pekerja 0.030 Oh x Rp. 116,600.00 = Rp. 3,498.00


- Tukang batu 0.300 Oh x Rp. 122,650.00 = Rp. 36,795.00
- Kepala Tukang 0.030 Oh x Rp. 152,900.00 = Rp. 4,587.00
- Mandor 0.0015 Oh x Rp. 128,040.00 = Rp. 192.06
JUMLAH = Rp. 45,072.06

JUMLAH (a) + (b) = Rp. 555,072.06

23 Memasang 1 buah kran diameter 3/4" atau 1/2"

a. Bahan

- Kran air 1.000 Bh x Rp. 44,400.00 = Rp. 44,400.00


- Seal tape 0.025 Bh x Rp. 3,500.00 = Rp. 87.50
JUMLAH = Rp. 44,487.50

b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang batu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 15,600.20

JUMLAH (a) + (b) = Rp. 60,087.70


24 Memasang 1 buah floor drain
a. Bahan

- Floor drain 1.000 Bh x Rp. 30,925.00 = Rp. 30,925.00


JUMLAH = Rp. 30,925.00
b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang batu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 15,600.20
JUMLAH (a) + (b) = Rp. 46,525.20

25 Memasang 1 buah Knee Pvc 3/4"


a. Bahan

- Knee Pvc 3/4" 1.000 Bh x Rp. 1,980.00 = Rp. 1,980.00


JUMLAH = Rp. 1,980.00
b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.001 Oh x Rp. 152,900.00 = Rp. 152.90
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 14,224.10
JUMLAH (a) + (b) = Rp. 16,204.10

26 Memasang 1 buah Knee Pvc 3"


a. Bahan

- Knee Pvc 3" 1.000 Bh x Rp. 14,740.00 = Rp. 14,740.00


JUMLAH = Rp. 14,740.00
b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.001 Oh x Rp. 152,900.00 = Rp. 152.90
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 14,224.10
JUMLAH (a) + (b) = Rp. 28,964.10

27 Memasang 1 buah Knee Pvc 2"


a. Bahan

- Knee Pvc " 1.000 Bh x Rp. 8,690.00 = Rp. 8,690.00


JUMLAH = Rp. 8,690.00
b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.001 Oh x Rp. 152,900.00 = Rp. 152.90
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 14,224.10
JUMLAH (a) + (b) = Rp. 22,914.10

25 Memasang 1 buah Knee Pvc 1 1/2"


a. Bahan

- Knee Pvc 1 1/2" 1.000 Bh x Rp. 6,270.00 = Rp. 6,270.00


JUMLAH = Rp. 6,270.00
b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.001 Oh x Rp. 152,900.00 = Rp. 152.90
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 14,224.10
JUMLAH (a) + (b) = Rp. 20,494.10

26 Memasang 1 buah Profil Tank Stainless 1100 Ltr


a. Bahan

- Profil Tank Stainless 1100 Lt 1.000 Bh x Rp. 3,993,000.00 = Rp. 3,993,000.00


JUMLAH = Rp. 3,993,000.00
b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.001 Oh x Rp. 152,900.00 = Rp. 152.90
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 14,224.10
JUMLAH (a) + (b) = Rp. 4,007,224.10
PEKERJAAN SANITASI

1 Memasang 1 buah kloset duduk

a. Bahan

- Kloset duduk/monoblok 1.000 Bh x Rp. 1,353,000.00 = Rp. 1,353,000.00


- Perlengkapan 0.060 - x Rp. 1,353,000.00 = Rp. 81,180.00
JUMLAH = Rp. 1,434,180.00

b. Tenaga

- Pekerja 3.300 Oh x Rp. 116,600.00 = Rp. 384,780.00


- Tukang batu 1.100 Oh x Rp. 122,650.00 = Rp. 134,915.00
- Kepala Tukang 0.001 Oh x Rp. 152,900.00 = Rp. 152.90
- Mandor 0.160 Oh x Rp. 128,040.00 = Rp. 20,486.40
JUMLAH = Rp. 540,334.30

JUMLAH (a) + (b) = Rp. 1,974,514.30

2 Memasang 1 buah kloset jongkok porselen

a. Bahan

- Kloset Jongkok Porselen 1.000 Bh x Rp. 498,025.00 = Rp. 498,025.00


- Semen Portland 6.000 Kg x Rp. 2,082.80 = Rp. 12,496.80
- Pasir Pasang 0.010 Kg x Rp. 592,400.00 = Rp. 5,924.00
JUMLAH = Rp. 516,445.80

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang batu 1.500 Oh x Rp. 122,650.00 = Rp. 183,975.00
- Kepala Tukang 1.500 Oh x Rp. 152,900.00 = Rp. 229,350.00
- Mandor 0.160 Oh x Rp. 128,040.00 = Rp. 20,486.40
JUMLAH = Rp. 550,411.40

JUMLAH (a) + (b) = Rp. 1,066,857.20

3 Memasang 1 buah kloset jongkok teraso

a. Bahan

- Kloset Jongkok teraso 1.000 Bh x Rp. 1,086,250.00 = Rp. 1,086,250.00


- Bata Merah 5x11x22 cm 7.000 Bh x Rp. 2,400.00 = Rp. 16,800.00
- Semen Portland 6.000 Kg x Rp. 2,082.80 = Rp. 12,496.80
- Pasir Pasang 0.010 Kg x Rp. 592,400.00 = Rp. 5,924.00
JUMLAH = Rp. 1,121,470.80

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang batu 1.500 Oh x Rp. 122,650.00 = Rp. 183,975.00
- Kepala Tukang 0.300 Oh x Rp. 152,900.00 = Rp. 45,870.00
- Mandor 0.110 Oh x Rp. 128,040.00 = Rp. 14,084.40
JUMLAH = Rp. 360,529.40

JUMLAH (a) + (b) = Rp. 1,482,000.20

4 Memasang 1 buah urinoir

a. Bahan

- Urinoir 1.000 Bh x Rp. 891,770.00 = Rp. 891,770.00


- Perlengkapan 0.300 Bh x Rp. 891,770.00 = Rp. 267,531.00
- Semen Portland 6.000 Kg x Rp. 2,082.80 = Rp. 12,496.80
- Pasir Pasang 0.010 Kg x Rp. 592,400.00 = Rp. 5,924.00
JUMLAH = Rp. 1,177,721.80

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang batu 1.000 Oh x Rp. 122,650.00 = Rp. 122,650.00
- Kepala Tukang 0.100 Oh x Rp. 152,900.00 = Rp. 15,290.00
- Mandor 0.100 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 267,344.00

JUMLAH (a) + (b) = Rp. 1,445,065.80

5 Memasang 1 buah westafel

a. Bahan

- Wastafel 1.000 Bh x Rp. 891,770.00 = Rp. 891,770.00


- Perlengkapan 0.030 Bh x Rp. 891,770.00 = Rp. 26,753.10
- Semen abu-abu 6.000 Kg x Rp. 26,000.00 = Rp. 156,000.00
- Pasir Pasang 0.010 Kg x Rp. 592,400.00 = Rp. 5,924.00
JUMLAH = Rp. 1,080,447.10

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang batu 1.450 Oh x Rp. 122,650.00 = Rp. 177,842.50
- Kepala Tukang 0.150 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.100 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 330,181.50

JUMLAH (a) + (b) = Rp. 1,410,628.60


6 Memasang 1 buah bak mandi batu bata volume 0.30 m3

a. Bahan

- Batu bata 0.400 m3 x Rp. 2,400.00 = Rp. 960.00


- Semen Portland 120.000 kg x Rp. 2,082.80 = Rp. 249,936.00
- Pasir Pasang 0.300 m3 x Rp. 592,400.00 = Rp. 177,720.00
- Porselen ( 11x11 ) cm 3.600 m2 x Rp. 56,710.00 = Rp. 204,156.00
- Semen nat 6.000 Kg x Rp. 2,082.80 = Rp. 12,496.80
JUMLAH = Rp. 645,268.80

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang batu 1.450 Oh x Rp. 122,650.00 = Rp. 177,842.50
- Kepala Tukang 0.150 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.100 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 330,181.50

JUMLAH (a) + (b) = Rp. 975,450.30

7 Memasang 1 buah bak beton volume 1 m3 air

a. Bahan

- Beton 1 : 1.5 : 2.5 0.400 m3 x Rp. 1,657,623.00 = Rp. 663,049.20


- Besi beton 120.000 kg x Rp. 14,012.00 = Rp. 1,681,440.00
- Kayu cetakan 0.300 m3 x Rp. 3,856,400.00 = Rp. 1,156,920.00
- Ubin porselin 3.600 m2 x Rp. 56,710.00 = Rp. 204,156.00
- Perlengkapan 0.100 - x Rp. 3,705,565.20 = Rp. 370,556.52
JUMLAH = Rp. 4,076,121.72

b. Tenaga

- Pekerja 3.500 Oh x Rp. 116,600.00 = Rp. 408,100.00


- Tukang batu 4.500 Oh x Rp. 122,650.00 = Rp. 551,925.00
- Kepala Tukang 0.900 Oh x Rp. 152,900.00 = Rp. 137,610.00
- Mandor 0.900 Oh x Rp. 128,040.00 = Rp. 115,236.00
JUMLAH = Rp. 1,212,871.00

JUMLAH (a) + (b) = Rp. 5,288,992.72

8 Memasang 1 m' pipa galvanis diameter 1/2 "

a. Bahan

- Pipa galvanis 1.200 m' x Rp. 54,890.00 = Rp. 65,868.00


- Perlengkapan 0.350 - x Rp. 65,868.00 = Rp. 23,053.80
JUMLAH = Rp. 88,921.80

b. Tenaga

- Pekerja 0.054 Oh x Rp. 116,600.00 = Rp. 6,296.40


- Tukang besi 0.090 Oh x Rp. 122,650.00 = Rp. 11,038.50
- Kepala Tukang 0.009 Oh x Rp. 152,900.00 = Rp. 1,376.10
- Mandor 0.027 Oh x Rp. 128,040.00 = Rp. 3,457.08
JUMLAH = Rp. 22,168.08

JUMLAH (a) + (b) = Rp. 111,089.88

9 Memasang 1 m' pipa galvanis diameter 3/4 "

a. Bahan

- Pipa galvanis 1.200 m' x Rp. 11,165.00 = Rp. 13,398.00


- Perlengkapan 0.350 - x Rp. 13,398.00 = Rp. 4,689.30
JUMLAH = Rp. 18,087.30

b. Tenaga

- Pekerja 0.054 Oh x Rp. 116,600.00 = Rp. 6,296.40


- Tukang besi 0.090 Oh x Rp. 122,650.00 = Rp. 11,038.50
- Kepala Tukang 0.009 Oh x Rp. 152,900.00 = Rp. 1,376.10
- Mandor 0.027 Oh x Rp. 128,040.00 = Rp. 3,457.08
JUMLAH = Rp. 22,168.08

JUMLAH (a) + (b) = Rp. 40,255.38

12 Memasang 1 m' pipa PVC tipe AW diameter 1/2 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 8,580.00 = Rp. 10,296.00


- Perlengkapan 0.350 - x Rp. 10,296.00 = Rp. 3,603.60
JUMLAH = Rp. 13,899.60

b. Tenaga

- Pekerja 0.036 Oh x Rp. 116,600.00 = Rp. 4,197.60


- Tukang pipa 0.060 Oh x Rp. 122,650.00 = Rp. 7,359.00
- Kepala Tukang 0.006 Oh x Rp. 152,900.00 = Rp. 917.40
- Mandor 0.0018 Oh x Rp. 128,040.00 = Rp. 230.47
JUMLAH = Rp. 12,704.47

JUMLAH (a) + (b) = Rp. 26,604.07


15 Memasang 1 m' pipa PVC tipe AW diameter 3/4 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 12,980.00 = Rp. 15,576.00


- Perlengkapan/Acesoris 0.350 - x Rp. 15,576.00 = Rp. 5,451.60
JUMLAH = Rp. 21,027.60

b. Tenaga

- Pekerja 0.036 Oh x Rp. 116,600.00 = Rp. 4,197.60


- Tukang pipa 0.060 Oh x Rp. 122,650.00 = Rp. 7,359.00
- Kepala Tukang 0.006 Oh x Rp. 152,900.00 = Rp. 917.40
- Mandor 0.0018 Oh x Rp. 128,040.00 = Rp. 230.47
JUMLAH = Rp. 12,704.47

JUMLAH (a) + (b) = Rp. 33,732.07

18 Memasang 1 m' pipa PVC tipe AW diameter 1 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 16,280.00 = Rp. 19,536.00


- Perlengkapan/Acesoris 0.350 - x Rp. 19,536.00 = Rp. 6,837.60
JUMLAH = Rp. 26,373.60

b. Tenaga

- Pekerja 0.054 Oh x Rp. 116,600.00 = Rp. 6,296.40


- Tukang pipa 0.090 Oh x Rp. 122,650.00 = Rp. 11,038.50
- Kepala Tukang 0.009 Oh x Rp. 152,900.00 = Rp. 1,376.10
- Mandor 0.0027 Oh x Rp. 128,040.00 = Rp. 345.71
JUMLAH = Rp. 19,056.71

JUMLAH (a) + (b) = Rp. 45,430.31

20 Memasang 1 m' pipa PVC tipe AW diameter 3 "

a. Bahan

- Pipa PVC 1.200 m' x Rp. 56,210.00 = Rp. 67,452.00


- Perlengkapan 0.350 - x Rp. 67,452.00 = Rp. 23,608.20
JUMLAH = Rp. 91,060.20

b. Tenaga

- Pekerja 0.081 Oh x Rp. 116,600.00 = Rp. 9,444.60


- Tukang pipa 0.135 Oh x Rp. 122,650.00 = Rp. 16,557.75
- Kepala Tukang 0.0135 Oh x Rp. 152,900.00 = Rp. 2,064.15
- Mandor 0.0041 Oh x Rp. 128,040.00 = Rp. 524.96
JUMLAH = Rp. 28,591.46

JUMLAH (a) + (b) = Rp. 119,651.66

23 Memasang 1 buah kran diameter 3/4" atau 1/2"

a. Bahan

- Kran air 1.000 Bh x Rp. 44,400.00 = Rp. 44,400.00


- Seal tape 0.025 Bh x Rp. 3,500.00 = Rp. 87.50
JUMLAH = Rp. 44,487.50

b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang batu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 15,600.20

JUMLAH (a) + (b) = Rp. 60,087.70

24 Memasang 1 buah floor drain


a. Bahan

- Floor drain 1.000 Bh x Rp. 30,925.00 = Rp. 30,925.00


JUMLAH = Rp. 30,925.00
b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang batu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 15,600.20
JUMLAH (a) + (b) = Rp. 46,525.20
25 Memasang 1 buah Knee Pvc 3/4"
a. Bahan

- Knee Pvc 3/4" 1.000 Bh x Rp. 7,800.00 = Rp. 7,800.00


JUMLAH = Rp. 7,800.00
b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.001 Oh x Rp. 152,900.00 = Rp. 152.90
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 14,224.10
JUMLAH (a) + (b) = Rp. 22,024.10

26 Memasang 1 buah Knee Pvc 3"


a. Bahan

- Knee Pvc 3" 1.000 Bh x Rp. 14,740.00 = Rp. 14,740.00


JUMLAH = Rp. 14,740.00
b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.001 Oh x Rp. 152,900.00 = Rp. 152.90
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 14,224.10
JUMLAH (a) + (b) = Rp. 28,964.10

27 Memasang 1 buah Knee Pvc 2"


a. Bahan

- Knee Pvc " 1.000 Bh x Rp. 8,690.00 = Rp. 8,690.00


JUMLAH = Rp. 8,690.00
b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.001 Oh x Rp. 152,900.00 = Rp. 152.90
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 14,224.10
JUMLAH (a) + (b) = Rp. 22,914.10

28 Memasang 1 buah Hand Shower

a. Bahan

- Hand Shower 1.000 Bh x Rp. 5,060,750.00 = Rp. 5,060,750.00


- Perlengkapan 0.030 Bh x Rp. 5,060,750.00 = Rp. 151,822.50
- Seal tape 0.025 Bh x Rp. 3,500.00 = Rp. 87.50
JUMLAH = Rp. 5,212,660.00

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang batu 1.450 Oh x Rp. 122,650.00 = Rp. 177,842.50
- Kepala Tukang 0.150 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.100 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 330,181.50

JUMLAH (a) + (b) = Rp. 5,542,841.50

31 1 Unit Pembuatan Septicktank + Peresapan

a. Item Pek,
- Galian Tanah 10.500 m3 x Rp. 51,761.60 = Rp. 543,496.80
- Urugan Pasir 0.650 m3 x Rp. 473,300.40 = Rp. 307,645.26
- Pas, Batu Bata 1 : 3 14.000 m2 x Rp. 218,082.00 = Rp. 3,053,148.00
- Rabat Beton 1 : 3 : 5 0.660 m3 x Rp. 1,377,068.60 = Rp. 908,865.28
- Plesteran 1 : 3 8.000 m2 x Rp. 70,043.54 = Rp. 560,348.35
- Plat Beton 0.370 m3 x Rp. 6,615,843.62 = Rp. 2,447,862.14
- Balok Beton 0.035 m3 x Rp. 7,996,763.80 = Rp. 279,886.73
- Batu Kerikil 0.730 m3 x Rp. 536,400.00 = Rp. 391,572.00
- Batu Karang/Gunung 0.630 m3 x Rp. 311,000.00 = Rp. 195,930.00
- Pipa Penguapan 1 1/2 inc 1.500 m1 x Rp. 59,455.00 = Rp. 89,182.50

JUMLAH (a) + (b) = Rp. 8,777,937.06

32 Memasang 1 buah Pompa Automatick

a. Bahan

- Pompa Automatick 400 Ltr/M 1.000 Bh x Rp. 4,235,000.00 = Rp. 4,235,000.00


- Perlengkapan 0.350 Ls x Rp. 150,000.00 = Rp. 52,500.00
- Acesoris 0.520 Ls x Rp. 100,000.00 = Rp. 52,000.00
JUMLAH = Rp. 4,339,500.00

b. Tenaga

- Pekerja 1.000 Oh x Rp. 116,600.00 = Rp. 116,600.00


- Tukang 1.450 Oh x Rp. 122,650.00 = Rp. 177,842.50
- Kepala Tukang 0.150 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.100 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 330,181.50

JUMLAH (a) + (b) = Rp. 4,669,681.50


PEKERJAAN KUNCI DAN KACA

1. 1 buah pasang kunci tanam antik

a. Bahan

- kunci tanam antik 1.000 Bh x Rp. 385,000.00 = Rp. 385,000.00


JUMLAH = Rp. 385,000.00

b. Tenaga

- Pekerja 0.060 Oh x Rp. 116,600.00 = Rp. 6,996.00


- Tukang Kayu 0.600 Oh x Rp. 122,650.00 = Rp. 73,590.00
- Kepala Tukang 0.060 Oh x Rp. 152,900.00 = Rp. 9,174.00
- Mandor 0.003 Oh x Rp. 128,040.00 = Rp. 384.12
JUMLAH = Rp. 90,144.12

JUMLAH (a) + (b) = Rp. 475,144.12

2 1 buah pasang kunci tanam 1 Slaag

a. Bahan

- kunci tanam biasa 1.000 Bh x Rp. 151,470.00 = Rp. 151,470.00


JUMLAH = Rp. 151,470.00

b. Tenaga

- Pekerja 0.060 Oh x Rp. 116,600.00 = Rp. 6,996.00


- Tukang Kayu 0.600 Oh x Rp. 122,650.00 = Rp. 73,590.00
- Kepala Tukang 0.060 Oh x Rp. 152,900.00 = Rp. 9,174.00
- Mandor 0.003 Oh x Rp. 128,040.00 = Rp. 384.12
JUMLAH = Rp. 90,144.12

JUMLAH (a) + (b) = Rp. 241,614.12

3. 1 buah pasang kunci tanam kamar mandi

a. Bahan

- kunci tanam kamar mandi 1.000 Bh x Rp. 151,470.00 = Rp. 151,470.00


JUMLAH = Rp. 151,470.00

b. Tenaga

- Pekerja 0.005 Oh x Rp. 116,600.00 = Rp. 583.00


- Tukang Kayu 0.500 Oh x Rp. 122,650.00 = Rp. 61,325.00
- Kepala Tukang 0.005 Oh x Rp. 152,900.00 = Rp. 764.50
- Mandor 0.0025 Oh x Rp. 128,040.00 = Rp. 320.10
JUMLAH = Rp. 62,992.60

JUMLAH (a) + (b) = Rp. 214,462.60

4. 1 buah pasang engsel pintu

a. Bahan

- Engsel pintu 1.000 Bh x Rp. 54,670.00 = Rp. 54,670.00


JUMLAH = Rp. 54,670.00

b. Tenaga

- Pekerja 0.015 Oh x Rp. 116,600.00 = Rp. 1,749.00


- Tukang Kayu 0.150 Oh x Rp. 122,650.00 = Rp. 18,397.50
- Kepala Tukang 0.015 Oh x Rp. 152,900.00 = Rp. 2,293.50
- Mandor 0.00075 Oh x Rp. 128,040.00 = Rp. 96.03
JUMLAH = Rp. 22,536.03

JUMLAH (a) + (b) = Rp. 77,206.03

5. 1 buah pasang engsel jendela

a. Bahan

- Engsel jendela 1.000 Bh x Rp. 42,570.00 = Rp. 42,570.00


JUMLAH = Rp. 42,570.00

b. Tenaga

- Pekerja 0.010 Oh x Rp. 116,600.00 = Rp. 1,166.00


- Tukang Kayu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.0005 Oh x Rp. 128,040.00 = Rp. 64.02
JUMLAH = Rp. 15,024.02

JUMLAH (a) + (b) = Rp. 57,594.02

6. 1 buah pasang Grendel Pintu / Jendela

a. Bahan

- Engsel angin 1.000 Bh x Rp. 49,500.00 = Rp. 49,500.00


JUMLAH = Rp. 49,500.00

b. Tenaga

- Pekerja 0.020 Oh x Rp. 116,600.00 = Rp. 2,332.00


- Tukang Kayu 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00
- Kepala Tukang 0.020 Oh x Rp. 152,900.00 = Rp. 3,058.00
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 128.04
JUMLAH = Rp. 30,048.04

JUMLAH (a) + (b) = Rp. 79,548.04


6. 1 buah pasang Mur-Baut/AngkerBaut/Begel

a. Bahan

- Mur-Baut/Angker Baut/Begel 0.030 Kg x Rp. 49,599.00 = Rp. 1,487.97


JUMLAH = Rp. 1,487.97

b. Tenaga

- Pekerja 0.020 Oh x Rp. 116,600.00 = Rp. 2,332.00


- Tukang Kayu 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00
- Kepala Tukang 0.020 Oh x Rp. 152,900.00 = Rp. 3,058.00
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 128.04
JUMLAH = Rp. 30,048.04

JUMLAH (a) + (b) = Rp. 31,536.01

7. 1 buah pasang kait angin

a. Bahan

- Kait angin 1.000 Bh x Rp. 24,420.00 = Rp. 24,420.00


JUMLAH = Rp. 24,420.00

b. Tenaga

- Pekerja 0.015 Oh x Rp. 116,600.00 = Rp. 1,749.00


- Tukang Kayu 0.150 Oh x Rp. 122,650.00 = Rp. 18,397.50
- Kepala Tukang 0.015 Oh x Rp. 152,900.00 = Rp. 2,293.50
- Mandor 0.00075 Oh x Rp. 128,040.00 = Rp. 96.03
JUMLAH = Rp. 22,536.03

JUMLAH (a) + (b) = Rp. 46,956.03

8. 1 buah pasang kunci selot

a. Bahan

- Kunci selot 1.000 Bh x Rp. 5,500.00 = Rp. 5,500.00


JUMLAH = Rp. 5,500.00

b. Tenaga

- Pekerja 0.020 Oh x Rp. 116,600.00 = Rp. 2,332.00


- Tukang Kayu 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00
- Kepala Tukang 0.020 Oh x Rp. 152,900.00 = Rp. 3,058.00
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 128.04
JUMLAH = Rp. 30,048.04

JUMLAH (a) + (b) = Rp. 35,548.04

10. 1 m2 pasang kaca, tebal 3 mm

a. Bahan

- Kaca 1.100 m2 x Rp. 194,050.00 = Rp. 213,455.00


JUMLAH = Rp. 213,455.00

b. Tenaga

- Pekerja 0.015 Oh x Rp. 116,600.00 = Rp. 1,749.00


- Tukang Kayu 0.150 Oh x Rp. 122,650.00 = Rp. 18,397.50
- Kepala Tukang 0.015 Oh x Rp. 152,900.00 = Rp. 2,293.50
- Mandor 0.00075 Oh x Rp. 128,040.00 = Rp. 96.03
JUMLAH = Rp. 22,536.03

JUMLAH (a) + (b) = Rp. 235,991.03

11. 1 m2 pasang kaca, tebal 5 mm

a. Bahan

- Kaca 1.100 m2 x Rp. 261,000.00 = Rp. 287,100.00


JUMLAH = Rp. 287,100.00

b. Tenaga

- Pekerja 0.015 Oh x Rp. 116,600.00 = Rp. 1,749.00


- Tukang Kayu 0.150 Oh x Rp. 122,650.00 = Rp. 18,397.50
- Kepala Tukang 0.015 Oh x Rp. 152,900.00 = Rp. 2,293.50
- Mandor 0.00075 Oh x Rp. 128,040.00 = Rp. 96.03
JUMLAH = Rp. 22,536.03

JUMLAH (a) + (b) = Rp. 309,636.03

12. 1 m2 pasang kaca, tebal 8 mm

a. Bahan
- Sealent 0.050 kg x Rp. 42,500.00 = Rp. 2,125.00
- Kaca 1.100 m2 x Rp. 426,000.00 = Rp. 468,600.00
JUMLAH = Rp. 470,725.00

b. Tenaga

- Pekerja 0.0165 Oh x Rp. 116,600.00 = Rp. 1,923.90


- Tukang Kayu 0.165 Oh x Rp. 122,650.00 = Rp. 20,237.25
- Kepala Tukang 0.0165 Oh x Rp. 152,900.00 = Rp. 2,522.85
- Mandor 0.0008 Oh x Rp. 128,040.00 = Rp. 102.43
JUMLAH = Rp. 24,786.43

JUMLAH (a) + (b) = Rp. 495,511.43

13. 1 m2 pasang kaca buram tebal 12 mm

a. Bahan

- Kaca 10 mm 1.100 m2 x Rp. 829,100.00 = Rp. 912,010.00


- Sealent 0.050 kg x Rp. 42,500.00 = Rp. 2,125.00
JUMLAH = Rp. 914,135.00

b. Tenaga

- Pekerja 0.025 Oh x Rp. 116,600.00 = Rp. 2,915.00


- Tukang Kayu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.00125 Oh x Rp. 128,040.00 = Rp. 160.05
JUMLAH = Rp. 37,560.05

JUMLAH (a) + (b) = Rp. 951,695.05

14. 1 m2 pasang kaca patri, tebal 2 mm

a. Bahan

- Kaca patri 1.100 m2 x Rp. 194,050.00 = Rp. 213,455.00


JUMLAH = Rp. 213,455.00

b. Tenaga

- Pekerja 0.015 Oh x Rp. 116,600.00 = Rp. 1,749.00


- Tukang Kayu 0.150 Oh x Rp. 122,650.00 = Rp. 18,397.50
- Kepala Tukang 0.015 Oh x Rp. 152,900.00 = Rp. 2,293.50
- Mandor 0.00075 Oh x Rp. 128,040.00 = Rp. 96.03
JUMLAH = Rp. 22,536.03

JUMLAH (a) + (b) = Rp. 235,991.03


PEKERJAAN BESI ALUMANIUM

1. 1 Kg pasang rangka kuda-kuda atap baja WF

a. Bahan

- Besi Profil WF 1.150 Kg x Rp. 30,800.00 = Rp. 35,420.00


JUMLAH = Rp. 35,420.00

b. Tenaga

- Tukang Las Konstruksi 0.060 Oh x Rp. 122,650.00 = Rp. 7,359.00


- Pekerja 0.060 Oh x Rp. 116,600.00 = Rp. 6,996.00
- Kepala Tukang 0.006 Oh x Rp. 152,900.00 = Rp. 917.40
- Mandor 0.003 Oh x Rp. 128,040.00 = Rp. 384.12
JUMLAH = Rp. 15,656.52

JUMLAH (a) + (b) = Rp. 51,076.52

2. Mengerjakan 100 Kg Perakitan baja WF

a. Bahan
- Solar 1.000 Ltr x Rp. 9,600.00 = Rp. 9,600.00
- Minyak pelumas 0.100 Ltr x Rp. 39,850.00 = Rp. 3,985.00
JUMLAH = Rp. 3,985.00

b. Tenaga

- Tukang Besi Konstruksi 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00


- Pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00
- Kepala Tukang 0.001 Oh x Rp. 152,900.00 = Rp. 152.90
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 24,718.10
c. Alat Bantu
- Sewa alat 0.800 Jam x Rp. 60,000.00 = Rp. 48,000.00
JUMLAH (a) + (b) + ( C) = Rp. 76,703.10

3 1 m2 pasang pintu besi baja

a. Bahan

- Pintu Besi Baja 1.000 m2 x Rp. 600,000.00 = Rp. 600,000.00


JUMLAH = Rp. 600,000.00

b. Tenaga

- Tukang Besi Konstruksi 0.650 Oh x Rp. 122,650.00 = Rp. 79,722.50


- Pekerja 0.650 Oh x Rp. 116,600.00 = Rp. 75,790.00
- Kepala Tukang 0.065 Oh x Rp. 152,900.00 = Rp. 9,938.50
- Mandor 0.032 Oh x Rp. 128,040.00 = Rp. 4,097.28
JUMLAH = Rp. 169,548.28

JUMLAH (a) + (b) = Rp. 769,548.28


3 1 m2 pasang jendela besi

a. Bahan

- jendela besi 1.000 m2 x Rp. 242,550.00 = Rp. 242,550.00


JUMLAH = Rp. 242,550.00

b. Tenaga

- Tukang Besi Konstruksi 1.050 Oh x Rp. 122,650.00 = Rp. 128,782.50


- Pekerja 1.050 Oh x Rp. 116,600.00 = Rp. 122,430.00
- Kepala Tukang 0.105 Oh x Rp. 152,900.00 = Rp. 16,054.50
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 672.21
JUMLAH = Rp. 267,939.21

JUMLAH (a) + (b) = Rp. 510,489.21

3 1 m2 pasang jendela Ram Besi

a. Bahan

- Kawat Ram Besi 1.000 m2 x Rp. 20,114.00 = Rp. 20,114.00


JUMLAH = Rp. 20,114.00

b. Tenaga

- Tukang Besi Konstruksi 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00


- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00
- Kepala Tukang 0.150 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 665.81
JUMLAH = Rp. 71,450.81

JUMLAH (a) + (b) = Rp. 91,564.81

4 1 m2 pasang rolling door

a. Bahan

- Rolling Door 1.000 m2 x Rp. 363,550.00 = Rp. 363,550.00


JUMLAH = Rp. 363,550.00

b. Tenaga

- Tukang Besi Konstruksi 1.500 Oh x Rp. 122,650.00 = Rp. 183,975.00


- Pekerja 1.050 Oh x Rp. 116,600.00 = Rp. 122,430.00
- Kepala Tukang 0.150 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 665.81
JUMLAH = Rp. 330,005.81

JUMLAH (a) + (b) = Rp. 693,555.81


5 1 m pasang Kosend alluminium

a. Bahan

- profil kusend alluminium 1.100 m' x Rp. 168,450.00 = Rp. 185,295.00


- Skrup fixer 2.000 bh x Rp. 389.50 = Rp. 779.00
- Sealant 0.060 Tube x Rp. 75,000.00 = Rp. 4,500.00
JUMLAH = Rp. 190,574.00

b. Tenaga

- Tukang khusus alumunium 0.043 Oh x Rp. 122,650.00 = Rp. 5,273.95


- Pekerja 0.043 Oh x Rp. 116,600.00 = Rp. 5,013.80
- Kepala Tukang 0.004 Oh x Rp. 152,900.00 = Rp. 657.47
- Mandor 0.002 Oh x Rp. 128,040.00 = Rp. 268.88
JUMLAH = Rp. 11,214.10

JUMLAH (a) + (b) = Rp. 201,788.10


5 1 m' pasang pintu alluminium strip lebar 8 mm

a. Bahan

- Alluminium strip 8 mm 1.100 m' x Rp. 151,000.00 = Rp. 166,100.00


- Skrup fixer 2.000 bh x Rp. 389.50 = Rp. 779.00
- Sealant 0.060 Tube x Rp. 75,000.00 = Rp. 4,500.00
JUMLAH = Rp. 171,379.00
b. Tenaga

- Tukang khusus alumunium 0.085 Oh x Rp. 122,650.00 = Rp. 10,425.25


- Pekerja 0.085 Oh x Rp. 116,600.00 = Rp. 9,911.00
- Kepala Tukang 0.009 Oh x Rp. 152,900.00 = Rp. 1,299.65
- Mandor 0.004 Oh x Rp. 128,040.00 = Rp. 537.77
JUMLAH = Rp. 22,173.67

JUMLAH (a) + (b) = Rp. 193,552.67

6 1 m2 pasang pintu/ Jendela alluminium + Kaca 5 mm

a. Bahan

- Alluminium strip 8 mm 5.500 m' x Rp. 151,000.00 = Rp. 830,500.00


- Skrup fixer 12.000 bh x Rp. 389.50 = Rp. 4,674.00
- Kaca 5mm 0.950 m2 x Rp. 261,000.00 = Rp. 247,950.00
- Karet 5.500 m' x Rp. 15,000.00 = Rp. 82,500.00
JUMLAH = Rp. 1,165,624.00

b. Tenaga

- Tukang khusus alumunium 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00


- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00
- Kepala Tukang 0.020 Oh x Rp. 152,900.00 = Rp. 3,058.00
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 128.04
JUMLAH = Rp. 51,036.04

JUMLAH (a) + (b) = Rp. 1,216,660.04

6 1 m2 pasang terali besi

a. Bahan

- Besi Strip 2 x 3 1.150 m2 x Rp. 16,662.40 = Rp. 19,161.76


JUMLAH = Rp. 19,161.76

b. Tenaga

- Tukang Las 1.200 Oh x Rp. 122,650.00 = Rp. 147,180.00


- Pekerja 1.200 Oh x Rp. 116,600.00 = Rp. 139,920.00
- Kepala Tukang 0.012 Oh x Rp. 152,900.00 = Rp. 1,834.80
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 76.82
JUMLAH = Rp. 289,011.62

JUMLAH (a) + (b) = Rp. 308,173.38

7 1 m2 pasang jendela nako & dan tralis

a. Bahan

- jendela nako 1.100 m2 x Rp. 4,119,900.00 = Rp. 4,531,890.00


- paku biasa 1/2" - 1" 0.020 Kg x Rp. 23,250.00 = Rp. 465.00
- besi strip 0.025 m3 x Rp. 16,662.40 = Rp. 416.56
JUMLAH = Rp. 4,532,771.56

b. Tenaga
- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00
- Tukang Kayu 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00
- Kepala Tukang 0.020 Oh x Rp. 152,900.00 = Rp. 3,058.00
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 128.04
JUMLAH = Rp. 51,036.04

JUMLAH (a) + (b) = Rp. 4,583,807.60


8 1 m2 pasang talang datar, seng BJLS 2.8 mm

a. Bahan
- seng plat 3 x 6 bjls 28 0.500 Lbr x Rp. 155,600.00 = Rp. 77,800.00
- paku biasa 1/2" - 1" 0.015 Kg x Rp. 23,250.00 = Rp. 348.75
- kayu borneo, papan 0.010 m3 x Rp. 3,856,400.00 = Rp. 37,021.44
- flincote / meni besi 0.250 Kg x Rp. 37,870.00 = Rp. 9,467.50
JUMLAH = Rp. 124,637.69

b. Tenaga
- Pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00
- Tukang Kayu 0.400 Oh x Rp. 122,650.00 = Rp. 49,060.00
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 160.05
JUMLAH = Rp. 70,532.55

JUMLAH (a) + (b) = Rp. 195,170.24

9 1 m2 pasang talang miring, seng BJLS 2.8 mm

a. Bahan
- seng plat 3 x 6 bjls 28 0.500 Lbr x Rp. 155,600.00 = Rp. 77,800.00
- paku biasa 1/2" - 1" 0.015 Kg x Rp. 23,250.00 = Rp. 348.75
- kayu borneo, papan 0.019 m3 x Rp. 3,856,400.00 = Rp. 73,271.60
- flincote / meni besi 0.300 Kg x Rp. 37,870.00 = Rp. 11,361.00
JUMLAH = Rp. 162,781.35

b. Tenaga
- Pekerja 0.040 Oh x Rp. 116,600.00 = Rp. 4,664.00
- Tukang Kayu 0.400 Oh x Rp. 122,650.00 = Rp. 49,060.00
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 160.05
JUMLAH = Rp. 57,706.55

JUMLAH (a) + (b) = Rp. 220,487.90

10 1 m2 pasang talang 1/2 lingkaran D-10 cm, seng BJLS 2.8 mm

a. Bahan
- seng plat 3 x 6 bjls 28 0.300 Lbr x Rp. 155,600.00 = Rp. 46,680.00
- paku biasa 1/2" - 1" 0.100 Kg x Rp. 23,250.00 = Rp. 2,325.00
- kayu borneo, papan 0.019 m3 x Rp. 3,856,400.00 = Rp. 73,271.60
- flincote / meni besi 0.500 Kg x Rp. 37,870.00 = Rp. 18,935.00
JUMLAH = Rp. 141,211.60

b. Tenaga
- Pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00
- Tukang Kayu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 160.05
JUMLAH = Rp. 52,135.05

JUMLAH (a) + (b) = Rp. 193,346.65

11 1 m2 pasang talang 1/2 lingkaran D-10 cm, seng BJLS 2.4 mm

a. Bahan
- seng plat 3 x 6 bjls 24 0.300 Lbr x Rp. 77,500.00 = Rp. 23,250.00
- paku biasa 1/2" - 1" 0.100 Kg x Rp. 23,250.00 = Rp. 2,325.00
- kayu borneo, papan 0.019 m3 x Rp. 3,856,400.00 = Rp. 73,271.60
- flincote / meni besi 0.500 Kg x Rp. 37,870.00 = Rp. 18,935.00
JUMLAH = Rp. 117,781.60

b. Tenaga

- Pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00


- Tukang Kayu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 160.05
JUMLAH = Rp. 52,135.05
JUMLAH (a) + (b) = Rp. 169,916.65
12 1 m1 pasang besi Siku 60x60x6

a. Bahan

- Besi Siku 60x60x6 1.100 m1 x Rp. 97,350.00 = Rp. 107,085.00


JUMLAH = Rp. 107,085.00

b. Tenaga

- Tukang Las 1.200 Oh x Rp. 122,650.00 = Rp. 147,180.00


- Pekerja 1.200 Oh x Rp. 116,600.00 = Rp. 139,920.00
- Kepala Tukang 0.012 Oh x Rp. 152,900.00 = Rp. 1,834.80
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 76.82
JUMLAH = Rp. 289,011.62

JUMLAH (a) + (b) = Rp. 396,096.62

13 1 m2 pasang Pagar besi

a. Bahan

- Pipa Besi Kotak / Hollow 13.920 m1 x Rp. 35,900.00 = Rp. 499,728.00


- Acecoris 0.300 Ls x Rp. 499,728.00 149,918.40
JUMLAH = Rp. 649,646.40

b. Tenaga

- Tukang Las 1.200 Oh x Rp. 122,650.00 = Rp. 147,180.00


- Pekerja 1.200 Oh x Rp. 116,600.00 = Rp. 139,920.00
- Kepala Tukang 0.012 Oh x Rp. 152,900.00 = Rp. 1,834.80
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 76.82
JUMLAH = Rp. 289,011.62

JUMLAH (a) + (b) = Rp. 938,658.02

14 1 m1 pasang besi Stenlis 2"

a. Bahan

- Pipa Besi Stenliss 1.100 m1 x Rp. 46,200.00 = Rp. 50,820.00


- Acecoris 0.300 Ls x Rp. 10,000.00 = Rp. 3,000.00
JUMLAH = Rp. 53,820.00

b. Tenaga

- Tukang Las 1.200 Oh x Rp. 122,650.00 = Rp. 147,180.00


- Pekerja 1.200 Oh x Rp. 116,600.00 = Rp. 139,920.00
- Kepala Tukang 0.012 Oh x Rp. 152,900.00 = Rp. 1,834.80
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 76.82
JUMLAH = Rp. 289,011.62

JUMLAH (a) + (b) = Rp. 342,831.62

15 1 m2 Pasang atap Rangka Baja Ringan

a. Bahan

- Rangka Baja Ringan Giga Steel 4.400 m1 x Rp. 23,698.75 = Rp. 104,274.50
- Reng Baja Ringan 3.300 m1 x Rp. 14,422.08 = Rp. 47,592.88
- Baut/ Acesoris 0.310 kg x Rp. 49,599.00 = Rp. 15,375.69
JUMLAH = Rp. 167,243.07

b. Tenaga

- Tukang Besi Konstruksi 0.650 Oh x Rp. 122,650.00 = Rp. 79,722.50


- Pekerja 0.450 Oh x Rp. 116,600.00 = Rp. 52,470.00
- Kepala Tukang 0.065 Oh x Rp. 152,900.00 = Rp. 9,938.50
- Mandor 0.032 Oh x Rp. 128,040.00 = Rp. 4,097.28
JUMLAH = Rp. 146,228.28

JUMLAH (a) + (b) = Rp. 313,471.35


16 1 m2 Pasang Alumunium Foil

a. Bahan

- Alumunium Foil 1.050 m2 x Rp. 30,250.00 = Rp. 31,762.50


JUMLAH = Rp. 31,762.50

b. Tenaga

- Tukang Besi Konstruksi 0.050 Oh x Rp. 122,650.00 = Rp. 6,132.50


- Pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00
- Kepala Tukang 0.005 Oh x Rp. 152,900.00 = Rp. 764.50
- Mandor 0.008 Oh x Rp. 128,040.00 = Rp. 1,024.32
JUMLAH = Rp. 25,411.32

JUMLAH (a) + (b) = Rp. 57,173.82

a. Bahan

- Titik Lampu 0.300 Lbr x Rp. 220,000.00 = Rp. 66,000.00


JUMLAH = Rp. 66,000.00

b. Tenaga

- Pekerja 0.450 Oh x Rp. 116,600.00 = Rp. 52,470.00


- Tukang Listrik 0.620 Oh x Rp. 122,650.00 = Rp. 76,043.00
- Mandor 0.010 Oh x Rp. 128,040.00 = Rp. 1,280.40
JUMLAH = Rp. 129,793.40

JUMLAH (a) + (b) = Rp. 195,793.40


17 1 m2 pasang Rangka Plafond besi Holow Modul 60 x 120

a. Bahan
- Besi Holow 40 x 40 1.500 Btg x Rp. 35,900.00 = Rp. 53,850.00
- Besi Holow 40 x20 0.800 Btg x Rp. 33,700.00 = Rp. 26,960.00
- Paku Riffet 8.000 Bj x Rp. 500.00 = Rp. 4,000.00
JUMLAH = Rp. 84,810.00

b. Tenaga
- Pekerja 0.250 Oh x Rp. 116,600.00 = Rp. 29,150.00
- Tukang Besi Konstruksi 0.150 Oh x Rp. 122,650.00 = Rp. 18,397.50
Kepala Tukang 0.015 Oh x Rp. 152,900.00 = Rp. 2,293.50
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 50,737.28

JUMLAH (a) + (b) = Rp. 135,547.28

18 1 m2 pasang Plafond Gipsum

a. Bahan
- Gipsum 0.382 Lbr x Rp. 110,025.00 = Rp. 42,029.55
- Paku Riffet 12.000 Bj x Rp. 500.00 = Rp. 6,000.00
JUMLAH = Rp. 48,029.55

b. Tenaga
- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00
- Tukang Besi Konstruksi 0.150 Oh x Rp. 122,650.00 = Rp. 18,397.50
Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 43,886.70

JUMLAH (a) + (b) = Rp. 91,916.25

19 1 m pasang Lisplank GRC 6 mm

a. Bahan
- Besi Holow 40 x 40 1.500 Btg x Rp. 35,900.00 = Rp. 53,850.00
- Plat GRC 6mm 0.400 Lbr x Rp. 50,500.00 = Rp. 20,200.00
- Paku Riffet 6.000 Bj x Rp. 7,700.00 = Rp. 46,200.00
JUMLAH = Rp. 120,250.00

b. Tenaga
- Pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00
- Tukang Besi Konstruksi 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.002 Oh x Rp. 128,040.00 = Rp. 256.08
JUMLAH = Rp. 25,710.08

JUMLAH (a) + (b) = Rp. 145,960.08

22 1 m2 pasang Dinding Gipsum doubel ( Muka Belakang )Rangka Aluminium

a. Bahan
- Metal wall stud 35mm x 40mm 2.000 m' x Rp. 24,950.00 = Rp. 49,900.00
- Metal wall track 30mm x 40mm 0.750 m' x Rp. 21,237.50 = Rp. 15,928.13
- Paku rivet 4.000 bh x Rp. 7,700.00 = Rp. 30,800.00
- Sekrup 6x1-1,5 8.000 bh x Rp. 7,700.00 = Rp. 61,600.00
- Gypsumboard 120x240 cm 9 mm 0.694 lbr x Rp. 110,025.00 = Rp. 76,357.35
- Textile tape 0.240 roll x Rp. 36,987.50 = Rp. 8,877.00
- Compound gypsum 6.000 Kg x Rp. 6,820.00 = Rp. 40,920.00
- Sekrup gypsum 16.000 bh x Rp. 330.00 = Rp. 5,280.00
- Amplas 0.500 lbr x Rp. 9,900.00 = Rp. 4,950.00
JUMLAH = Rp. 294,612.48

b. Tenaga
- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00
- Tukang Besi Konstruksi 0.600 Oh x Rp. 122,650.00 = Rp. 73,590.00
Kepala Tukang 0.060 Oh x Rp. 152,900.00 = Rp. 9,174.00
- Mandor 0.100 Oh x Rp. 128,040.00 = Rp. 12,804.00
JUMLAH = Rp. 118,888.00

JUMLAH (a) + (b) = Rp. 413,500.48


22 6.26 1 m2 Pekerjaan dinding aluminium composite panel

a. Bahan
- Rangka besi siku 40.40.4 0.900 btg x Rp. 232,600.00 = Rp. 209,340.00
- Aluminium composite panel 0.328 m2 x Rp. 1,927,500.00 = Rp. 632,220.00
- Paku skrup 0.200 kg x Rp. 41,120.00 = Rp. 8,224.00
- Paku rivet 16.000 bh x Rp. 7,700.00 = Rp. 123,200.00
JUMLAH = Rp. 972,984.00

b. Tenaga
- Pekerja 0.600 Oh x Rp. 116,600.00 = Rp. 69,960.00
- Tukang Besi Konstruksi 0.600 Oh x Rp. 122,650.00 = Rp. 73,590.00
Kepala Tukang 0.050 Oh x Rp. 152,900.00 = Rp. 7,645.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 151,835.20

JUMLAH (a) + (b) = Rp. 1,124,819.20


PEKERJAAN LANTAI

1 1 m2 pasang dinding keramik ukuran 40x40 cm

a. Bahan

- Keramik warna 40x40 cm 6.250 bh x Rp. 16,043.20 = Rp. 100,270.00


- Semen Portland 11.38 Kg x Rp. 2,082.80 = Rp. 23,702.26
- Pasir Pasang 0.042 m3 x Rp. 502,800.00 = Rp. 21,117.60
- Semen Warna 1.5 Kg x Rp. 26,000.00 = Rp. 39,000.00
JUMLAH = Rp. 184,089.86

b. Tenaga

- Pekerja 0.620 Oh x Rp. 116,600.00 = Rp. 72,292.00


- Tukang kayu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Kepala Tukang 0.035 Oh x Rp. 152,900.00 = Rp. 5,351.50
- Mandor 0.030 Oh x Rp. 128,040.00 = Rp. 3,841.20
JUMLAH = Rp. 124,412.20

JUMLAH (a) + (b) = Rp. 308,502.06

2 1 m2 pasang lantai keramik ukuran 20x20 cm

a. Bahan

- Keramik 20x20 cm 25.000 bh x Rp. 3,650.00 = Rp. 91,250.00


- Semen Portland 11.38 Kg x Rp. 2,082.80 = Rp. 23,702.26
- Pasir Pasang 0.042 m3 x Rp. 502,800.00 = Rp. 21,117.60
- Semen Warna 1.5 Kg x Rp. 26,000.00 = Rp. 39,000.00
JUMLAH = Rp. 175,069.86

b. Tenaga

- Pekerja 0.620 Oh x Rp. 116,600.00 = Rp. 72,292.00


- Tukang kayu 0.120 Oh x Rp. 122,650.00 = Rp. 14,718.00
- Kepala Tukang 0.012 Oh x Rp. 152,900.00 = Rp. 1,834.80
- Mandor 0.0125 Oh x Rp. 128,040.00 = Rp. 1,600.50
JUMLAH = Rp. 90,445.30

JUMLAH (a) + (b) = Rp. 265,515.16

3 1 m2 pasang lantai keramik ukuran 60x60 cm

a. Bahan

- Keramik warna 60x60 cm 3.000 bh x Rp. 69,686.67 = Rp. 209,060.00


- Semen Portland 11.38 Kg x Rp. 2,082.80 = Rp. 23,702.26
- Pasir Pasang 0.042 m3 x Rp. 502,800.00 = Rp. 21,117.60
- Semen Warna 1.5 Kg x Rp. 26,000.00 = Rp. 39,000.00
JUMLAH = Rp. 292,879.86

b. Tenaga

- Pekerja 0.620 Oh x Rp. 116,600.00 = Rp. 72,292.00


- Tukang kayu 0.120 Oh x Rp. 122,650.00 = Rp. 14,718.00
- Kepala Tukang 0.012 Oh x Rp. 152,900.00 = Rp. 1,834.80
- Mandor 0.0125 Oh x Rp. 128,040.00 = Rp. 1,600.50
JUMLAH = Rp. 90,445.30

JUMLAH (a) + (b) = Rp. 383,325.16

1 m2 pasang lantai Granit Tile ukuran 60x60 cm

a. Bahan

- Granit Tile warna 60x60 cm 3.000 bh x Rp. 156,366.67 = Rp. 469,100.00


- Semen Portland 11.38 Kg x Rp. 2,082.80 = Rp. 23,702.26
- Pasir Pasang 0.042 m3 x Rp. 502,800.00 = Rp. 21,117.60
- Semen Warna 1.5 Kg x Rp. 26,000.00 = Rp. 39,000.00
JUMLAH = Rp. 552,919.86

b. Tenaga

- Pekerja 0.620 Oh x Rp. 116,600.00 = Rp. 72,292.00


- Tukang kayu 0.120 Oh x Rp. 122,650.00 = Rp. 14,718.00
- Kepala Tukang 0.012 Oh x Rp. 152,900.00 = Rp. 1,834.80
- Mandor 0.0125 Oh x Rp. 128,040.00 = Rp. 1,600.50
JUMLAH = Rp. 90,445.30

JUMLAH (a) + (b) = Rp. 643,365.16


4 1 m2 pasang lantai keramik artistik ukuran 10x20 cm

a. Bahan

- Keramik artistik 10x20 cm 50.000 bh x Rp. 1,288.20 = Rp. 64,410.00


- Semen Portland 11.38 Kg x Rp. 2,082.80 = Rp. 23,702.26
- Pasir Pasang 0.042 m3 x Rp. 502,800.00 = Rp. 21,117.60
- Semen Warna 1.5 Kg x Rp. 26,000.00 = Rp. 39,000.00
JUMLAH = Rp. 148,229.86

b. Tenaga

- Pekerja 0.620 Oh x Rp. 116,600.00 = Rp. 72,292.00


- Tukang kayu 0.120 Oh x Rp. 122,650.00 = Rp. 14,718.00
- Kepala Tukang 0.012 Oh x Rp. 152,900.00 = Rp. 1,834.80
- Mandor 0.0125 Oh x Rp. 128,040.00 = Rp. 1,600.50
JUMLAH = Rp. 90,445.30

JUMLAH (a) + (b) = Rp. 238,675.16

5 1 m2 pasang lantai keramik artistik ukuran 10x10 cm

a. Bahan

- Keramik artistik 10x10 cm 50.000 bh x Rp. 1,134.20 = Rp. 56,710.00


- Semen Portland 11.38 Kg x Rp. 2,082.80 = Rp. 23,702.26
- Pasir Pasang 0.042 m3 x Rp. 502,800.00 = Rp. 21,117.60
- Semen Warna 2.00 Kg x Rp. 26,000.00 = Rp. 52,000.00
JUMLAH = Rp. 153,529.86

b. Tenaga

- Pekerja 0.620 Oh x Rp. 116,600.00 = Rp. 72,292.00


- Tukang kayu 0.120 Oh x Rp. 122,650.00 = Rp. 14,718.00
- Kepala Tukang 0.012 Oh x Rp. 152,900.00 = Rp. 1,834.80
- Mandor 0.0125 Oh x Rp. 128,040.00 = Rp. 1,600.50
JUMLAH = Rp. 90,445.30

JUMLAH (a) + (b) = Rp. 243,975.16

7 1 m2 pasang batu alam ukuran 20x20 cm

a. Bahan

- batu alam buatan artistik 25.000 bh x Rp. 11,672.00 = Rp. 291,800.00


- Semen Portland 9.30 Kg x Rp. 2,082.80 = Rp. 19,370.04
- Pasir Pasang 0.018 m3 x Rp. 502,800.00 = Rp. 9,050.40
- Semen Warna 1.50 Kg x Rp. 26,000.00 = Rp. 39,000.00
JUMLAH = Rp. 359,220.44

b. Tenaga

- Pekerja 0.620 Oh x Rp. 116,600.00 = Rp. 72,292.00


- Tukang kayu 0.350 Oh x Rp. 122,650.00 = Rp. 42,927.50
- Kepala Tukang 0.035 Oh x Rp. 152,900.00 = Rp. 5,351.50
- Mandor 0.030 Oh x Rp. 128,040.00 = Rp. 3,841.20
JUMLAH = Rp. 124,412.20

JUMLAH (a) + (b) = Rp. 483,632.64


PEKERJAAN ATAP

1 1 m2 pasang atap genteng palentong kecil

a. Bahan

- Genteng palentong 25 Buah x Rp. 1,000.00 = Rp. 25,000.00


JUMLAH = Rp. 25,000.00

b. Tenaga

- Pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00


- Tukang kayu 0.075 Oh x Rp. 122,650.00 = Rp. 9,198.75
- Kepala Tukang 0.008 Oh x Rp. 152,900.00 = Rp. 1,223.20
- Mandor 0.008 Oh x Rp. 128,040.00 = Rp. 1,024.32
JUMLAH = Rp. 28,936.27

JUMLAH (a) + (b) = Rp. 53,936.27

2 1 m2 pasang atap genteng kodok / glazzur

a. Bahan

- Genteng kodok 25 Buah x Rp. 1,000.00 = Rp. 25,000.00


JUMLAH = Rp. 25,000.00

b. Tenaga

- Pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00


- Tukang kayu 0.075 Oh x Rp. 122,650.00 = Rp. 9,198.75
- Kepala Tukang 0.008 Oh x Rp. 152,900.00 = Rp. 1,223.20
- Mandor 0.008 Oh x Rp. 128,040.00 = Rp. 1,024.32
JUMLAH = Rp. 28,936.27

JUMLAH (a) + (b) = Rp. 53,936.27

3 1 m2 pasang atap genteng palentong super / besar

a. Bahan

- Genteng palentong super 12 Buah x Rp. 1,000.00 = Rp. 12,000.00


JUMLAH = Rp. 12,000.00

b. Tenaga

- Pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00


- Tukang kayu 0.060 Oh x Rp. 122,650.00 = Rp. 7,359.00
- Kepala Tukang 0.006 Oh x Rp. 152,900.00 = Rp. 917.40
- Mandor 0.008 Oh x Rp. 128,040.00 = Rp. 1,024.32
JUMLAH = Rp. 26,790.72

JUMLAH (a) + (b) = Rp. 38,790.72

4 1 m2 pasang genteng bubung palentong

a. Bahan

- Genteng bubung palentong 5 Bh x Rp. 1,000.00 = Rp. 5,000.00


- semen portland 8 Kg x Rp. 1,000.00 = Rp. 8,000.00
- pasir pasang 0.032 M3 x Rp. 1,000.00 = Rp. 32.00
JUMLAH = Rp. 13,032.00

b. Tenaga

- Pekerja 0.150 Oh x Rp. 116,600.00 = Rp. 17,490.00


- Tukang kayu 0.060 Oh x Rp. 122,650.00 = Rp. 7,359.00
- Kepala Tukang 0.006 Oh x Rp. 152,900.00 = Rp. 917.40
- Mandor 0.008 Oh x Rp. 128,040.00 = Rp. 1,024.32
JUMLAH = Rp. 26,790.72

JUMLAH (a) + (b) = Rp. 39,822.72

5 1 m2 pasang bubung genteng kodok glazzur

a. Bahan

- Genteng bubung kodok 5 Bh x Rp. 1,000.00 = Rp. 5,000.00


- semen portland 8 Kg x Rp. 1,000.00 = Rp. 8,000.00
- pasir pasang 0.032 M3 x Rp. 1,000.00 = Rp. 32.00
JUMLAH = Rp. 13,032.00

b. Tenaga

- Pekerja 0.400 Oh x Rp. 116,600.00 = Rp. 46,640.00


- Tukang kayu 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00
- Kepala Tukang 0.020 Oh x Rp. 152,900.00 = Rp. 3,058.00
- Mandor 0.002 Oh x Rp. 128,040.00 = Rp. 256.08
JUMLAH = Rp. 74,484.08

JUMLAH (a) + (b) = Rp. 87,516.08

6 1 m2 pasang bubung genteng palentong besar

a. Bahan

- Genteng bubung palentong 4 Bh x Rp. 1,000.00 = Rp. 4,000.00


- semen portland 8 Kg x Rp. 1,000.00 = Rp. 8,000.00
- pasir pasang 0.032 M3 x Rp. 1,000.00 = Rp. 32.00
JUMLAH = Rp. 12,032.00

b. Tenaga

- Pekerja 0.400 Oh x Rp. 116,600.00 = Rp. 46,640.00


- Tukang kayu 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00
- Kepala Tukang 0.020 Oh x Rp. 152,900.00 = Rp. 3,058.00
- Mandor 0.002 Oh x Rp. 128,040.00 = Rp. 256.08
JUMLAH = Rp. 74,484.08

JUMLAH (a) + (b) = Rp. 86,516.08


1 1 m2 pasang roof light fibreglass (180 x 90 ) cm

a. Bahan

- roof light fibreglass 0.6 Lbr x Rp. 74,250.00 = Rp. 44,550.00


- paku biasa 1/2" - 1" 0.05 Kg x Rp. 23,250.00 = Rp. 1,162.50
JUMLAH = Rp. 45,712.50

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.067 Oh x Rp. 122,650.00 = Rp. 8,217.55
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,508.13

JUMLAH (a) + (b) = Rp. 72,220.63

2 1 m2 pasang atap asbes gelombang ( 2.50 x 0.92 m ) x 5 mm

a. Bahan

- asbes gelombang 0.5 Lbr x Rp. 60,500.00 = Rp. 30,250.00


- paku pancing 60 x 230 0.12 Kg x Rp. 32,270.00 = Rp. 3,872.40
JUMLAH = Rp. 34,122.40

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.075 Oh x Rp. 122,650.00 = Rp. 9,198.75
- Kepala Tukang 0.008 Oh x Rp. 152,900.00 = Rp. 1,223.20
- Mandor 0.008 Oh x Rp. 128,040.00 = Rp. 1,024.32
JUMLAH = Rp. 27,770.27

JUMLAH (a) + (b) = Rp. 61,892.67

3 1 m2 pasang atap asbes gelombang ( 2.25 x 0.92 m ) x 5 mm

a. Bahan

- Asbes gelombang 0.6 Lbr x Rp. 53,350.00 = Rp. 32,010.00


- Paku pancing 60 x 230 0.12 Kg x Rp. 32,270.00 = Rp. 3,872.40
JUMLAH = Rp. 35,882.40

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.075 Oh x Rp. 122,650.00 = Rp. 9,198.75
- Kepala Tukang 0.008 Oh x Rp. 152,900.00 = Rp. 1,223.20
- Mandor 0.008 Oh x Rp. 128,040.00 = Rp. 1,024.32
JUMLAH = Rp. 27,770.27

JUMLAH (a) + (b) = Rp. 63,652.67

4 1 m2 pasang atap asbes gelombang ( 2.00 x 0.92 m ) x 5 mm

a. Bahan

- Asbes gelombang 0.6 Lbr x Rp. 48,950.00 = Rp. 29,370.00


- Paku pancing 60 x 230 0.12 Kg x Rp. 32,270.00 = Rp. 3,872.40
JUMLAH = Rp. 33,242.40

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.070 Oh x Rp. 122,650.00 = Rp. 8,585.50
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,876.08

JUMLAH (a) + (b) = Rp. 60,118.48

5 1 m2 pasang atap asbes gelombang ( 1.80 x 0.92 m ) x 5 mm

a. Bahan

- Asbes gelombang 0.75 Lbr x Rp. 1,000.00 = Rp. 750.00


- Paku pancing 60 x 230 0.12 Kg x Rp. 1,000.00 = Rp. 120.00
JUMLAH = Rp. 870.00

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.070 Oh x Rp. 122,650.00 = Rp. 8,585.50
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,876.08

JUMLAH (a) + (b) = Rp. 27,746.08

6 1 m2 pasang atap asbes gelombang ( 3.00 x 1.05 m ) x 4 mm

a. Bahan

- Asbes gelombang 0.35 Lbr x Rp. 1,000.00 = Rp. 350.00


- Paku pancing 0.12 Kg x Rp. 1,000.00 = Rp. 120.00
JUMLAH = Rp. 470.00

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.070 Oh x Rp. 122,650.00 = Rp. 8,585.50
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,876.08

JUMLAH (a) + (b) = Rp. 27,346.08

7 1 m2 pasang atap asbes gelombang ( 2.70 x 1.05 m ) x 4 mm

a. Bahan

- Asbes gelombang 0.42 Lbr x Rp. 1,000.00 = Rp. 420.00


- Paku pancing 0.12 Kg x Rp. 1,000.00 = Rp. 120.00
JUMLAH = Rp. 540.00

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.070 Oh x Rp. 122,650.00 = Rp. 8,585.50
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,876.08

JUMLAH (a) + (b) = Rp. 27,416.08

8 1 m2 pasang atap asbes gelombang ( 2.40 x 1.05 m ) x 4 mm

a. Bahan

- Asbes gelombang 0.44 Lbr x Rp. 1,000.00 = Rp. 440.00


- Paku pancing 0.12 Kg x Rp. 1,000.00 = Rp. 120.00
JUMLAH = Rp. 560.00

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.067 Oh x Rp. 122,650.00 = Rp. 8,217.55
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,508.13

JUMLAH (a) + (b) = Rp. 27,068.13

9 1 m2 pasang atap asbes gelombang ( 2.10 x 1.05 m ) x 4 mm

a. Bahan

- Asbes gelombang 0.51 Lbr x Rp. 1,000.00 = Rp. 510.00


- Paku pancing 0.12 Kg x Rp. 1,000.00 = Rp. 120.00
JUMLAH = Rp. 630.00

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.067 Oh x Rp. 122,650.00 = Rp. 8,217.55
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,508.13

JUMLAH (a) + (b) = Rp. 27,138.13

10 1 m2 pasang atap asbes gelombang ( 1.5 x 1.05 m ) x 4 mm

a. Bahan

- Asbes gelombang 0.8 Lbr x Rp. 1,000.00 = Rp. 800.00


- Paku pancing 0.12 Kg x Rp. 1,000.00 = Rp. 120.00
JUMLAH = Rp. 920.00

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.067 Oh x Rp. 122,650.00 = Rp. 8,217.55
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,508.13

JUMLAH (a) + (b) = Rp. 27,428.13

11 1 m2 pasang atap asbes gelombang ( 3.00 x 1.08 m ) x 6 mm

a. Bahan

- Asbes gelombang 0.37 Lbr x Rp. 1,000.00 = Rp. 370.00


- Paku pancing 0.12 Kg x Rp. 1,000.00 = Rp. 120.00
JUMLAH = Rp. 490.00

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.067 Oh x Rp. 122,650.00 = Rp. 8,217.55
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,508.13

JUMLAH (a) + (b) = Rp. 26,998.13

12 1 m2 pasang atap asbes gelombang ( 2.70 x 1.08 m ) x 6 mm

a. Bahan

- Asbes gelombang 0.38 Lbr x Rp. 1,000.00 = Rp. 380.00


- Paku pancing 0.12 Kg x Rp. 1,000.00 = Rp. 120.00
JUMLAH = Rp. 500.00

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.067 Oh x Rp. 122,650.00 = Rp. 8,217.55
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,508.13

JUMLAH (a) + (b) = Rp. 27,008.13

13 1 m2 pasang atap asbes gelombang ( 2.4 x 1.08 m ) x 6 mm

a. Bahan

- Asbes gelombang 0.46 Lbr x Rp. 1,000.00 = Rp. 460.00


- Paku pancing 0.12 Kg x Rp. 1,000.00 = Rp. 120.00
JUMLAH = Rp. 580.00

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.067 Oh x Rp. 122,650.00 = Rp. 8,217.55
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,508.13

JUMLAH (a) + (b) = Rp. 27,088.13

14 1 m2 pasang atap asbes gelombang ( 2.1 x 1.08 m ) x 6 mm

a. Bahan

- Asbes gelombang 0.49 Lbr x Rp. 1,000.00 = Rp. 490.00


- Paku pancing 0.12 Kg x Rp. 1,000.00 = Rp. 120.00
JUMLAH = Rp. 610.00

b.
Tenaga
- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00
- Tukang kayu 0.067 Oh x Rp. 122,650.00 = Rp. 8,217.55
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,508.13

JUMLAH (a) + (b) = Rp. 27,118.13

15 1 m2 pasang atap asbes gelombang ( 1.80 x 1.08 m ) x 6 mm

a. Bahan

- Asbes gelombang 0.57 Lbr x Rp. 1,000.00 = Rp. 570.00


- Paku pancing 0.12 Kg x Rp. 1,000.00 = Rp. 120.00
JUMLAH = Rp. 690.00

b. Tenaga

- Pekerja 0.140 Oh x Rp. 116,600.00 = Rp. 16,324.00


- Tukang kayu 0.067 Oh x Rp. 122,650.00 = Rp. 8,217.55
- Kepala Tukang 0.007 Oh x Rp. 152,900.00 = Rp. 1,070.30
- Mandor 0.007 Oh x Rp. 128,040.00 = Rp. 896.28
JUMLAH = Rp. 26,508.13

JUMLAH (a) + (b) = Rp. 27,198.13

5 1 m2 pasang Atap steel gelombang 0.92 m

a. Bahan

- Atap steel gelombang 1.10 Lbr x Rp. 96,250.00 = Rp. 105,875.00


- Paku skrup 3.5 " 6 Bh x Rp. 2,500.00 = Rp. 15,000.00
JUMLAH = Rp. 120,875.00

b. Tenaga

- Pekerja 0.084 Oh x Rp. 116,600.00 = Rp. 9,794.40


- Tukang kayu 0.125 Oh x Rp. 122,650.00 = Rp. 15,331.25
- Kepala Tukang 0.013 Oh x Rp. 152,900.00 = Rp. 1,987.70
- Mandor 0.004 Oh x Rp. 128,040.00 = Rp. 512.16
JUMLAH = Rp. 27,625.51

JUMLAH (a) + (b) = Rp. 148,500.51

6 1 m2 pasang nok steel gelombang 1.05 m

a. Bahan

- nok stel gelombang 1 Bh x Rp. 30,250.00 = Rp. 30,250.00


- Paku skrup 3.5 " 4 Bh x Rp. 2,500.00 = Rp. 10,000.00
JUMLAH = Rp. 40,250.00

b. Tenaga

- Pekerja 0.084 Oh x Rp. 116,600.00 = Rp. 9,794.40


- Tukang kayu 0.125 Oh x Rp. 122,650.00 = Rp. 15,331.25
- Kepala Tukang 0.013 Oh x Rp. 152,900.00 = Rp. 1,987.70
- Mandor 0.004 Oh x Rp. 128,040.00 = Rp. 512.16
JUMLAH = Rp. 27,625.51

JUMLAH (a) + (b) = Rp. 67,875.51

7 1 m2 pasang nok stel gelombang 1.08 m

a. Bahan

- nok stel gelombang 1 Bh x Rp. 35,750.00 = Rp. 35,750.00


- Paku skrup 3.5 " 4 Bh x Rp. 2,500.00 = Rp. 10,000.00
JUMLAH = Rp. 45,750.00

b. Tenaga

- Pekerja 0.084 Oh x Rp. 116,600.00 = Rp. 9,794.40


- Tukang kayu 0.125 Oh x Rp. 122,650.00 = Rp. 15,331.25
- Kepala Tukang 0.013 Oh x Rp. 152,900.00 = Rp. 1,987.70
- Mandor 0.004 Oh x Rp. 128,040.00 = Rp. 512.16
JUMLAH = Rp. 27,625.51

JUMLAH (a) + (b) = Rp. 73,375.51

19 1 m2 pasang nok paten 0.92 m

a. Bahan

- nok paten 1.2 Lbr x Rp. 1,000.00 = Rp. 1,200.00


- Paku skrup 3.5 " 6 Bh x Rp. 1,000.00 = Rp. 6,000.00
JUMLAH = Rp. 7,200.00

b. Tenaga

- Pekerja 0.084 Oh x Rp. 116,600.00 = Rp. 9,794.40


- Tukang kayu 0.125 Oh x Rp. 122,650.00 = Rp. 15,331.25
- Kepala Tukang 0.013 Oh x Rp. 152,900.00 = Rp. 1,987.70
- Mandor 0.004 Oh x Rp. 128,040.00 = Rp. 512.16
JUMLAH = Rp. 27,625.51

JUMLAH (a) + (b) = Rp. 34,825.51

20 1 m2 pasang nok paten 1.05 m

a. Bahan

- nok paten 1.2 Lbr x Rp. 1,000.00 = Rp. 1,200.00


- Paku skrup 3.5 " 6 Bh x Rp. 1,000.00 = Rp. 6,000.00
JUMLAH = Rp. 7,200.00

b. Tenaga

- Pekerja 0.084 Oh x Rp. 116,600.00 = Rp. 9,794.40


- Tukang kayu 0.125 Oh x Rp. 122,650.00 = Rp. 15,331.25
- Kepala Tukang 0.013 Oh x Rp. 152,900.00 = Rp. 1,987.70
- Mandor 0.004 Oh x Rp. 128,040.00 = Rp. 512.16
JUMLAH = Rp. 27,625.51

JUMLAH (a) + (b) = Rp. 34,825.51

21 1 m2 pasang nok paten 1.08 m

a. Bahan

- nok paten 1.2 Lbr x Rp. 1,000.00 = Rp. 1,200.00


- Paku skrup 3.5 " 6 Bh x Rp. 1,000.00 = Rp. 6,000.00
JUMLAH = Rp. 7,200.00

b. Tenaga

- Pekerja 0.084 Oh x Rp. 116,600.00 = Rp. 9,794.40


- Tukang kayu 0.125 Oh x Rp. 122,650.00 = Rp. 15,331.25
- Kepala Tukang 0.013 Oh x Rp. 152,900.00 = Rp. 1,987.70
- Mandor 0.004 Oh x Rp. 128,040.00 = Rp. 512.16
JUMLAH = Rp. 27,625.51

JUMLAH (a) + (b) = Rp. 34,825.51

22 1 m2 pasang nok sel rata 0.92 m

a. Bahan

- nok stel rata 1.1 Lbr x Rp. 1,000.00 = Rp. 1,100.00


- Paku skrup 3.5 " 6 Bh x Rp. 1,000.00 = Rp. 6,000.00
JUMLAH = Rp. 7,100.00

b. Tenaga

- Pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00


- Tukang kayu 0.150 Oh x Rp. 122,650.00 = Rp. 18,397.50
- Kepala Tukang 0.013 Oh x Rp. 152,900.00 = Rp. 1,987.70
- Mandor 0.004 Oh x Rp. 128,040.00 = Rp. 512.16
JUMLAH = Rp. 32,557.36

JUMLAH (a) + (b) = Rp. 39,657.36

23 1 m2 pasang nok sel rata 1.05 m

a. Bahan

- nok stel rata 1.1 Lbr x Rp. 1,000.00 = Rp. 1,100.00


- Paku skrup 3.5 " 6 Bh x Rp. 1,000.00 = Rp. 6,000.00
JUMLAH = Rp. 7,100.00

b. Tenaga

- Pekerja 0.084 Oh x Rp. 116,600.00 = Rp. 9,794.40


- Tukang kayu 0.125 Oh x Rp. 122,650.00 = Rp. 15,331.25
- Kepala Tukang 0.013 Oh x Rp. 152,900.00 = Rp. 1,987.70
- Mandor 0.004 Oh x Rp. 128,040.00 = Rp. 512.16
JUMLAH = Rp. 27,625.51

JUMLAH (a) + (b) = Rp. 34,725.51

24 1 m2 pasang atap genteng beton

a. Bahan

- genteng beton 1.1 Lbr x Rp. 55,370.00 = Rp. 60,907.00


- Paku skrup 3.5 " 0.03 Kg x Rp. 23,250.00 = Rp. 697.50
JUMLAH = Rp. 61,604.50

b. Tenaga

- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang kayu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.010 Oh x Rp. 128,040.00 = Rp. 1,280.40
JUMLAH = Rp. 38,394.40

JUMLAH (a) + (b) = Rp. 99,998.90


31 1 m2 pasang atap genteng aspal

a. Bahan

- genteng aspal 6.9 Lbr x Rp. 1,000.00 = Rp. 6,900.00


- plywood 4" x 8" x 6 mm 0.35 Lbr x Rp. 1,000.00 = Rp. 350.00
- paku biasa 1/2" - 1" 0.03 Kg x Rp. 1,000.00 = Rp. 30.00
- plastik aerator 0.5 Bh x Rp. 1,000.00 = Rp. 500.00
JUMLAH = Rp. 7,780.00

b. Tenaga

- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang kayu 0.300 Oh x Rp. 122,650.00 = Rp. 36,795.00
- Kepala Tukang 0.003 Oh x Rp. 152,900.00 = Rp. 458.70
- Mandor 0.010 Oh x Rp. 128,040.00 = Rp. 1,280.40
JUMLAH = Rp. 61,854.10

JUMLAH (a) + (b) = Rp. 69,634.10

9 1 m2 pasang atap Multi roof

a. Bahan

- multi roof 1.02 Lbr x Rp. 55,370.00 = Rp. 56,477.40


- Skrup 20 Bh x Rp. 642.50 = Rp. 12,850.00
JUMLAH = Rp. 69,327.40

b. Tenaga

- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang kayu 0.100 Oh x Rp. 122,650.00 = Rp. 12,265.00
- Kepala Tukang 0.010 Oh x Rp. 152,900.00 = Rp. 1,529.00
- Mandor 0.001 Oh x Rp. 128,040.00 = Rp. 128.04
JUMLAH = Rp. 37,242.04

JUMLAH (a) + (b) = Rp. 106,569.44

33 1 m2 pasang atap sirap

a. Bahan

- genteng sirap 60 Lbr x Rp. 1,000.00 = Rp. 60,000.00


- paku biasa 1/2 - 1" 0.2 Kg x Rp. 1,000.00 = Rp. 200.00
JUMLAH = Rp. 60,200.00

b. Tenaga

- Pekerja 0.166 Oh x Rp. 116,600.00 = Rp. 19,355.60


- Tukang kayu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.008 Oh x Rp. 128,040.00 = Rp. 1,024.32
JUMLAH = Rp. 54,864.92

JUMLAH (a) + (b) = Rp. 115,064.92

10 1 m2 pasang Nok genteng Beton

a. Bahan

- nok genteng beton 0.5 Bh x Rp. 15,000.00 = Rp. 7,500.00


- paku biasa 2" x 5" 0.05 Kg x Rp. 23,250.00 = Rp. 1,162.50
- semen abu-abu 10.8 Kg x Rp. 26,000.00 = Rp. 280,800.00
- pasir pasang 0.032 m3 x Rp. 592,400.00 = Rp. 18,956.80
- semen warna 1 Kg x Rp. 26,000.00 = Rp. 26,000.00
JUMLAH = Rp. 334,419.30

b. Tenaga

- Pekerja 0.400 Oh x Rp. 116,600.00 = Rp. 46,640.00


- Tukang kayu 0.200 Oh x Rp. 122,650.00 = Rp. 24,530.00
- Kepala Tukang 0.020 Oh x Rp. 152,900.00 = Rp. 3,058.00
- Mandor 0.020 Oh x Rp. 128,040.00 = Rp. 2,560.80
JUMLAH = Rp. 76,788.80

JUMLAH (a) + (b) = Rp. 411,208.10

35 1 m2 pasang Rangka Atap Kayu Gording kls 1

a. Bahan

- Kayu Kls I 0.012 Bh x Rp. 6,432,400.00 = Rp. 77,188.80


- paku biasa 1/2" - 1" 0.05 Kg x Rp. 23,250.00 = Rp. 1,162.50
JUMLAH = Rp. 78,351.30

b. Tenaga

- Pekerja 0.100 Oh x Rp. 116,600.00 = Rp. 11,660.00


- Tukang kayu 0.250 Oh x Rp. 122,650.00 = Rp. 30,662.50
- Kepala Tukang 0.025 Oh x Rp. 152,900.00 = Rp. 3,822.50
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 46,785.20

JUMLAH (a) + (b) = Rp. 125,136.50

11 1 m pasang Bubungan/Nok Kayu kls 1

a. Bahan

- Seng plat 0.25 lbr x Rp. 63,700.00 = Rp. 15,925.00


paku biasa 1/2" - 1" 0.05 Kg x Rp. 23,250.00 = Rp. 1,162.50
- Balok kayu 6/12 0.011 m3 x Rp. 6,432,400.00 = Rp. 70,756.40
- Papan 2/20 0.0044 m3 x Rp. 6,432,400.00 = Rp. 28,302.56
JUMLAH = Rp. 116,146.46

b. Tenaga

- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang kayu 0.020 Oh x Rp. 122,650.00 = Rp. 2,453.00
- Kepala Tukang 0.150 Oh x Rp. 101,600.00 = Rp. 15,240.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 41,653.20

JUMLAH (a) + (b) = Rp. 157,799.66

12 1 m2 Pemasangan Atap Seng Gelombang BJLS 0.25 mm

a. Bahan

- Seng Gelombang 0.98 Lbr x Rp. 55,362.50 = Rp. 54,255.25


- Paku Seng 0.036 Kg x Rp. 32,270.00 = Rp. 1,161.72
JUMLAH = Rp. 55,416.97

b. Tenaga

- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang kayu 0.020 Oh x Rp. 122,650.00 = Rp. 2,453.00
- Kepala Tukang 0.150 Oh x Rp. 152,900.00 = Rp. 22,935.00
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 49,348.20

JUMLAH (a) + (b) = Rp. 104,765.17

1 1 m2 pasang atap Ondoline

a. Bahan

- Atap Ondoline 0.25 Lbr x Rp. 288,500.00 = Rp. 72,125.00


- Baut/Mur + Acesoris 0.289 Kg x Rp. 52,720.00 = Rp. 15,236.08
JUMLAH = Rp. 87,361.08

b. Tenaga

- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang kayu 0.020 Oh x Rp. 122,650.00 = Rp. 2,453.00
- Kepala Tukang 0.015 Oh x Rp. 152,900.00 = Rp. 2,293.50
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 28,706.70

JUMLAH (a) + (b) = Rp. 116,067.78

1 1 m2 pasang atap Spandek

a. Bahan

- Atap Spandek 0.25 Lbr x Rp. 265,000.00 = Rp. 66,250.00


- Baut/Mur + Acesoris 0.289 Kg x Rp. 49,599.00 = Rp. 14,334.11
JUMLAH = Rp. 80,584.11

b. Tenaga

- Pekerja 0.200 Oh x Rp. 116,600.00 = Rp. 23,320.00


- Tukang kayu 0.020 Oh x Rp. 122,650.00 = Rp. 2,453.00
- Kepala Tukang 0.015 Oh x Rp. 152,900.00 = Rp. 2,293.50
- Mandor 0.005 Oh x Rp. 128,040.00 = Rp. 640.20
JUMLAH = Rp. 28,706.70

JUMLAH (a) + (b) = Rp. 109,290.81


DAFTAR HARGA SATUAN BAHAN & PEMASANGAN ACCESSORIES PIPA
HARGA HARGA
No. JENIS UPAH / BAHAN SATUAN
SATUAN BAHAN (Rp.) PEMASANGAN (Rp.)
1 2 3 4 5
S Accessories Pipa
1 Clamp Saddle 3" x 1/2" Bh 15,120.00 2,570.40
2 Clamp Saddle 2" x 1/2" Bh 12,880.00 2,189.60
3 Tee PVC AW 3" Bh 54,500.00 9,265.00
4 Tee PVC AW 3" x 2" x 3" Bh 54,500.00 9,265.00
5 Tee PVC AW 2" Bh 47,500.00 8,075.00
6 Tee PVC AW 1 1/2 " x 1" x 1 1/2" Bh 51,300.00 8,721.00
7 Tee PVC AW 1 1/2" x 1/2" x 1 1/2" Bh 12,500.00 2,125.00
8 Tee PVC AW 1" x 1/2" x 1" Bh 9,800.00 1,666.00
9 Tee PVC AW 1 1/2 Bh 42,500.00 7,225.00
10 Tee PVC AW 1" Bh 28,500.00 4,845.00
11 Tee PVC AW 1/2" Bh 6,800.00 1,156.00
12 Reducer PVC AW 2" - 1 1/2" Bh 25,400.00 4,318.00
13 Reducer PVC RR 3" - 2" Bh 79,000.00 13,430.00
14 Reducer PVC RR 4" - 3" Bh 125,200.00 21,284.00
15 Bend/Knee PVC AW 90o 1/2" Bh 7,600.00 1,292.00
16 Bend/Knee PVC AW 90 1" o
Bh 14,600.00 2,482.00
Bend Knee PVC 5" Bh 165,500.00 2,482.00
17 Bend/Knee PVC Rubber Ring-Spigot 90 1 1/2"
o
Bh 59,200.00 10,064.00
18 Bend/Knee PVC Rubber Ring-Spigot 90o 2" Bh 69,800.00 11,866.00
19 Bend/Knee PVC Rubber Ring-Spigot 45o 3" Bh 140,500.00 23,885.00
20 Bend/Knee PVC Rubber Ring-Spigot 90o 3" Bh 162,700.00 27,659.00
21 Valve/Kran 1/2 " Bh 38,600.00 6,562.00
22 Gate Valve 2 " Bh 738,800.00 125,596.00
23 Gate Valve 3" FF Bh 848,400.00 144,228.00
24 Gate Valve 4" FF Bh 1,350,000.00 229,500.00
Gate Valve 5" FF Bh 1,850,000.00 229,500.00
25 Flange Adaptor PVC 2" Bh 144,000.00 24,480.00
26 Flange Spigot PVC 2" Bh 133,000.00 22,610.00
27 Flange Spigot PVC 4" Bh 312,500.00 53,125.00
28 Flange GIP 4" Bh 220,500.00 25,721.00
29 Flange GIP 3" Bh 188,200.00 25,721.00
30 Flange GIP 2" Bh 151,300.00 25,721.00
31 Sock Drat Dalam PVC AW 1/2" Bh 6,500.00 1,105.00
32 Sock Drat Luar PVC AW 1/2" Bh 7,800.00 1,105.00
33 Sock Drat Luar PVC AW 1 1/2" Bh 26,200.00 4,454.00
34 Stub Flange HDPE 110 mm Bh 248,500.00 42,245.00
35 Stub Flange HDPE 90 mm Bh 234,200.00 39,814.00
36 Stub Flange HDPE 63 mm Bh 198,200.00 33,694.00
37 Klemp Pipa/Strap Saddle HDPE 110 mm Bh 16,500.00 2,805.00
38 Klemp Pipa/Strap Saddle HDPE 90 mm Bh 14,200.00 2,414.00
39 Klemp Pipa/Strap Saddle HDPE 63 mm Bh 12,500.00 2,125.00
40 Reducer HDPE 110 mm - 90 mm Bh 272,400.00 46,308.00
41 Reducer HDPE 90 mm - 63 mm Bh 228,400.00 38,828.00
42 Air Valve/Katup Udara 1/2" Bh 384,500.00 65,365.00
43 Bend HDPE 45o 90 mm Bh 451,600.00 76,772.00
44 Bend HDPE 90 90 mm
o
Bh 352,000.00 59,840.00
45 Bend HDPE 90o 63 mm Bh 294,500.00 50,065.00
46 Bend/Knee GIP 1/2" Bh 18,000.00 3,060.00
47 Tee GIP 1/2" Bh 22,500.00 3,825.00
48 Tee GIP 2" x 1" x 2" Bh 82,000.00 13,940.00
49 Dop GIP 1" Bh 36,000.00 6,120.00
50 Sock GIP 1/2" Bh 24,800.00 4,216.00
51 Bend/Knee GIP 90O 2" Bh 41,400.00 7,038.00
56 Bend/Knee GIP 90 3" O
Bh 53,200.00 9,044.00
57 Bend/Knee GIP 45O 4" Bh 194,200.00 33,014.00
58 Nepel GIP 2" Bh 92,600.00 15,742.00
59 Dop GIP 2" Bh 65,000.00 11,050.00
60 Klemp Pompa 2" Bh 45,000.00 7,650.00
61 Ceck Valve 2" Bh 75,000.00 12,750.00
62 Lem Pipa Kaleng 6,000.00 1,020.00
63 Isolatip Doz 36,500.00 6,205.00
64 Lubricate Kaleng 50,500.00 8,585.00
65 Pompa Grundfos 3 Ltr/dtk + Panel Unit 30,000,000.00 5,100,000.00
66 Mesin Genset Yanmar 3 Kwh + Panel Unit 18,750,000.00 3,187,500.00
67 Pompa Submersable 7.5 PK Unit 33,500,000.00 5,695,000.00
68
ANALISA HARGA SATUAN
(Analisa SNI)
I PEMASANGAN PIPA
C PENGADAAN/PEMASANGAN 1 M 1 PIPA GIP Medium A 2"
1 Pengadaan 1 M 1 GIP Medium A All Flange 2" Lengkap (Karet Seal, Mur-baut + Ring)
a Bahan
- Pipa GIP Medium A 2" 1.000 Oh x Rp. 105,105.00 = Rp. 105,105.00
Jumlah 1. a = Rp. 105,105.00 1 Oh = Rp. 105,105.00
2 Pemasangan 1 M 1 GIP Medium A All Flange 2" Lengkap (Karet Seal, Mur-baut + Ring)
a Tenaga Pemasang
- Pekerja 0.108 Oh x Rp. 116,600.00 = Rp. 12,592.80
- Tukang pipa 0.180 Oh x Rp. 122,650.00 = Rp. 22,077.00
- Kepala Tukang 0.018 Oh x Rp. 152,900.00 = Rp. 2,752.20
- Mandor 0.0054 Oh x Rp. 128,040.00 = Rp. 691.42
Jumlah 2. a = Rp. 38,113.42 1 Oh = Rp. 38,113.42
b Tenaga Pengangkut dari lokasi penumpukan ke lokasi pemasangan
- Pipa GIP 2" 1.000 M1 x Rp. 5,000.00 = Rp. 5,000.00
Jumlah 2. b = Rp. 5,000.00 1 Oh = Rp. 5,000.00
c Alat Bantu
- Sewa Alat Pemasang 1.000 Set x Rp. 10,000.00 = Rp. 10,000.00
Jumlah 2. b = Rp. 10,000.00 1 Set = Rp. 10,000.00
JUMLAH ( 1.a + 2.a + 2.b + 2.c) = Rp. 158,218.42
BAHAN MATERIAL ALAMI

ANGKUT
GALIAN C KEUNTUNGAN HARGA
NO JENIS BAHAN SATUAN HARGA DASAR DILOKASI KET
15% PIHAK KE II (Rp.) DILOKASI (Rp.)
(Rp.)
1 Batu Kali / Batu Gunung M3 115,000.00 150,000.00 17,250.00 28,750.00 311,000.00
2 Batu Belah 15 - 20 cm M3 115,000.00 150,000.00 17,250.00 28,750.00 311,000.00
3 Batu Belah 10 - 15 cm M3 115,000.00 150,000.00 17,250.00 28,750.00 311,000.00
4 Batu Belah 7 - 10 cm M3 115,000.00 150,000.00 17,250.00 28,750.00 311,000.00
5 Batu Belah 5 - 7 cm M3 115,000.00 150,000.00 17,250.00 28,750.00 311,000.00
6 Batu Belah 3 - 5 cm M3 144,000.00 150,000.00 21,600.00 36,000.00 351,600.00
7 Batu Belah 2 - 3 cm M3 216,000.00 150,000.00 32,400.00 54,000.00 452,400.00
8 Batu Belah 1 - 2 cm M3 345,000.00 150,000.00 51,750.00 86,250.00 633,000.00
9 Batu Belah 0.5 - 1 cm (Split) M3 276,000.00 150,000.00 41,400.00 69,000.00 536,400.00
10 Kerikil Beton / Koral M3 276,000.00 150,000.00 41,400.00 69,000.00 536,400.00

11 Sirtu M3 144,000.00 150,000.00 21,600.00 36,000.00 351,600.00


12 Timbunan Pilihan / Pasir Urug M3 153,000.00 150,000.00 22,950.00 38,250.00 364,200.00
13 Timbunan Biasa / Tanah Urug M3 101,000.00 150,000.00 15,150.00 25,250.00 291,400.00
14 Pasir Kasar / Pasir Beton M3 194,000.00 150,000.00 29,100.00 48,500.00 421,600.00
15 Pasir Halus / Pasir Ayak M3 252,000.00 150,000.00 37,800.00 63,000.00 502,800.00
16 Pasir Kasar Pantai M3 230,000.00 150,000.00 34,500.00 57,500.00 472,000.00
17 Pasir Halus Pantai M3 316,000.00 150,000.00 47,400.00 79,000.00 592,400.00
Pasir batu apung M3 194,000.00 150,000.00 20,000.00 48,500.00 412,500.00
16 Balok Kayu Klas I M3 5,520,000.00 250,000.00 662,400.00 6,432,400.00
18 Balok kayu Klas II M3 3,220,000.00 250,000.00 386,400.00 3,856,400.00
19 Papan Klas I M3 5,520,000.00 250,000.00 662,400.00 6,432,400.00
20 Papan Klas II M3 3,220,000.00 250,000.00 386,400.00 3,856,400.00
21 Kayu Dolken P. 4M Btg 40,000.00 15,000.00 4,800.00 59,800.00
UPAH KERJA
LOKASI : PULAU TERNATE

UPAH KEUNTUNGA UPAH


NO TENAGA KERJA KODE SATUAN KETERANGAN
DASAR (Rp ) N PIHAK KE (Rp./Hari)
II (Rp.)
1 Mandor Lapangan MAN Org/ Hr 116,400.00 11,640.00 128,040.00
2 Mekanik MEK Org/ Hr 139,500.00 13,950.00 153,450.00
3 Pembantu Mekanik PMEK Org/ Hr 106,000.00 10,600.00 116,600.00
4 Kepala Tukang KTUK Org/ Hr 139,000.00 13,900.00 152,900.00
5 Tukang TUK Org/ Hr 111,500.00 11,150.00 122,650.00
6 Operator Terlatih Org/ Hr 139,500.00 13,950.00 153,450.00
7 Operator Kurang Terlatih Org/ Hr 106,000.00 10,600.00 116,600.00
8 Pembantu Operator Org/ Hr 106,000.00 10,600.00 116,600.00
9 Supir Truck (Material) SUP Org/ Hr 116,000.00 11,600.00 127,600.00
10 Supir Personil SUP2 Org/ Hr 106,000.00 10,600.00 116,600.00
11 Pembantu Supir (Kernet) PSUP Org/ Hr 106,000.00 10,600.00 116,600.00
12 Buruh Lapangan Terlatih PKRT Org/ Hr 106,000.00 10,600.00 116,600.00
13 Buruh Lapangan Tidak Terlatih PKR Org/ Hr 95,000.00 9,500.00 104,500.00
HARGA SATUAN BAHAN FABRIKASI

LOKASI : PULAU TERNATE

SPESIFIKASI ONGKOS ANGKUT


NO JENIS BAHAN MERK / MOFDEL SATUAN HPS KE LOKASI
UKURAN PROYEK
1 2 3 4 5 6
1 Semen (PC) 50 kg Zak 86,000.00 1,950.00
Kg 1,720.00 50.00
2 Semen warna Kg 18,000.00 250.00

3 Kawat Beton Kg 26,000.00 250.00


4 Kawat Bronjong Kg 12,600.00 250.00
5 Kawat Duri Kg 11,000.00 250.00
6 Besi Beton Dia. 6 mm Staf 15,500.00 750.00
7 Besi Beton Dia. 8 mm Staf 25,300.00 750.00
8 Besi Beton Dia. 10 mm Staf 36,900.00 750.00
9 Besi Beton Dia. 12 mm Staf 53,600.00 750.00
10 Besi Beton Dia. 14 mm Staf 80,900.00 1,000.00
11 Besi Beton Dia. 16 mm Staf 108,600.00 1,000.00
12 Besi Beton Dia. 19 mm Staf 173,000.00 1,000.00
13 Besi Beton Dia. 22 mm Staf 266,500.00 1,300.00
14 Besi Beton Dia. 25 mm Staf 325,100.00 1,300.00
15 Besi Beton Dia. 32 mm Staf 486,000.00 1,600.00

16 Paku Campuran Kg 18,700.00 250.00


17 Paku Tripleks Kg 20,000.00 250.00
18 Paku Seng Kg 25,000.00 250.00
19 Paku Beton Kg 16,900.00 250.00

20 Teakwood 3 mm Uk. 122 x 244 cm Lbr 1,250,000.00 500.00


21 Tripleks 3 mm Uk. 122 x 244 cm Lbr 60,000.00 500.00
22 Tripleks 5 mm Uk. 122 x 244 cm Lbr 90,000.00 500.00
23 Tripleks 8 mm Uk. 122 x 244 cm Lbr 104,500.00 500.00
24 Tripleks 10 mm Uk. 122 x 244 cm Lbr 124,800.00 500.00
25 Tripleks 20 mm Uk. 122 x 244 cm Lbr 216,600.00 500.00

26 Pipa Galvanis Medium B Uk. 1/2 " M1 45,000.00 375.00


27 Pipa Galvanis Medium B Uk. 3/4 " M1 55,000.00 375.00
28 Pipa Galvanis Medium B Uk. 1 " M1 85,000.00 375.00
29 Pipa Galvanis Medium B Uk. 11/4 " M1 100,000.00 375.00

30 Pipa GIP Medium A Uk. 1/2 " M1 116,500.00 400.00


31 Pipa GIP Medium A Uk. 3/4 " M1 151,600.00 400.00

32 Pipa PVC Uk. 1/2 " M1 6800 375.00


33 Pipa PVC Uk. 3/4 " M1 10400 375.00
34 Pipa PVC Uk. 1 " M1 13100 375.00
35 Pipa PVC Uk. 11/4 " M1 8,500.00 375.00
36 Pipa PVC Uk. 11/2 " M1 15,000.00 375.00
37 Pipa PVC Uk. 2 " M1 23,900.00 375.00
38 Pipa PVC Uk. 3 " M1 46,000.00 475.00
39 Pipa PVC Uk. 4 " M1 73,100.00 475.00

40 Knee PVC Uk. 1/2 " Bh 1,500.00 200.00


41 Knee PVC Uk. 3/4 " Bh 1,500.00 200.00
42 Knee PVC Uk. 1 " Bh 2,000.00 200.00
43 Knee PVC Uk. 11/4 " Bh 3,500.00 200.00
44 Knee PVC Uk. 11/2 " Bh 5,000.00 200.00
45 Knee PVC Uk. 2 1/2" Bh 7,000.00 200.00
46 Knee PVC Uk. 3 " Bh 12,000.00 200.00
47 Knee PVC Uk. 4 " Bh 15,000.00 200.00

48 Batu Bata Bh 1,800.00 200.00


49 Paving Stone Bh 1,500.00 200.00
50 Bowling Bh 16,000.00 200.00

51 Besi Siku Uk. 30.30.3 M' 47,500.00 400.00


52 Besi Siku Uk. 40.40.4 M' 64,000.00 400.00
53 Besi Siku Uk. 50.50.5 M' 98,500.00 400.00

54 Seng Gelombang BJLS 0.20 mm Lbr 36,200.00 475.00


55 Seng Gelombang BJLS 0.25 mm Lbr 60,000.00 475.00
56 Seng Gelombang BJLS 0.30 mm Lbr 65,000.00 475.00
57 Seng Pelat Bubungan BJLS 0.30 mm Lbr 55,000.00 475.00
58 Atap Asbes Gelombang Lbr 65,000.00 475.00
59 Genteng Semen (Beton) Bh 45,000.00 250.00
Seng Plastik Gelombang Lbr 21,700.00 475.00
60 Tegel Semen 30 x 30 cm M2 32,500.00 550.00
61 Tegel Semen 20 x 20 cm M2 40,000.00 550.00
62 Tegel Porselin 10 x 20 cm M2 45,000.00 550.00
63 Tegel Porselin 10 x 10 cm M2 45,000.00 550.00
64 Tegel Keramik 10 x 20 cm M2 51,400.00 550.00
65 Tegel Keramik 20 x 20 cm M2 55,000.00 550.00
66 Tegel Keramik 20 x 25 cm M2 56,400.00 550.00
67 Tegel Keramik 30 x 30 cm M2 79,000.00 550.00
68 Tegel Keramik 40 x 40 cm M2 85,000.00 550.00
Granit stil 60 x 60 cm M2 275,000.00 550.00
69 Cat Kayu / Besi Glotex Kg 56,500.00 250.00
70 Cat Kayu / Besi Platone Kg 56,500.00 250.00
71 Cat Dasar/Alkalin 1 Kg 32,300.00 250.00
72 Cat Tembok Dulux 1 Kg 47,100.00 250.00
Cat Tembok Matek 1 Kg 27,100.00 250.00
73 Cat Meni Kayu Altex Kg 36,800.00 250.00
74 Cat Meni Besi Altex Kg 45,000.00 250.00
75 Minyak Cat Thinner Liter 31,700.00 250.00
76 Minyak Cat Afduner Liter 31,700.00 250.00
77 Pelumas / Olie Liter 4,500.00 250.00
78 Dempul Kayu Altex Kg 39,600.00 250.00
79 Plamir Tembok Kaleng 5 Kg 11,900.00 1,250.00
80 Kuas Cat Bh 11,100.00 200.00
Residu Liter 15,000.00 250.00
81 Kaca Rayban 3 mm M2 125,000.00 3,750.00
82 Kaca Rayban 5 mm M2 359,800.00 3,750.00
83 Kaca Bening 2 mm M2 95,000.00 3,750.00
84 Kaca Bening 3 mm M2 105,000.00 3,750.00
85 Kaca Bening 5 mm M2 300,000.00 3,750.00
Kaca Bening 10 mm M2 750,000.00 3,750.00
Dudukan Nako Bh 25,000.00 200.00
86 Kran (Kualitas Baik) Bh 39,500.00 200.00
87 Avour / Saringan Air Kotor Bh 25,400.00 200.00
88 Floor Drain Bh 16,700.00 200.00
89 Kloset Jongkok INA Bh 330,000.00 500.00
90 Kloset Jongkok TOTO Bh 330,000.00 500.00
91 Kloset Duduk / Lengkap INA Bh 3,086,500.00 1,000.00
92 Kloset Duduk / Lengkap TOTO Bh 3,086,500.00 1,000.00
93 Wastafel INA / TOTO Bh 1,696,300.00 750.00
IJUK Kg 10,000.00 200.00
94 Kunci Pintu 1 Slaag Cap Kuda Terbang Bh 125,000.00 200.00
95 Kunci Pintu 2 Slaag Cap SES Bh 200,000.00 200.00
96 Grendel Jendela Bh 22,500.00 200.00
97 Kait Angin Bh 20,000.00 200.00
98 Engsel Jendela Kuningan Bh 35,000.00 200.00
99 Engsel Pintu Kuningan Bh 45,000.00 200.00
100 Lis Profil 5 cm M' 75000 200.00

101 Kertas Ampelas Lbr 2,750.00 200.00

102 Mur / Baut / Beugel / Angker Kg 20,000.00 200.00

103 Box Sekring 1 Group Bh 150,000.00 200.00


104 Box Sekring 2 Group Bh 200,000.00 200.00

105 MCB 2 Ampere Bh 50,000.00 200.00


106 MCB 4 Ampere Bh 72,400.00 200.00
107 MCB 6 Ampere Bh 72,600.00 200.00
108 MCB 10 Ampere Bh 92,000.00 200.00

109 Saklar Tunggal Tanam Bh 42,300.00 200.00


110 Saklar Ganda Tanam Bh 42,300.00 200.00
111 Saklar Tunggal Timbul Bh 7,900.00 200.00
112 Saklar Ganda Timbul Bh 10,400.00 200.00
113 Stop Kontak Tanam Bh 42,300.00 200.00
114 Stop Kontak Timbul Bh 42,300.00 200.00
115 Titik Lampu Bh 60,000.00 200.00
116 Lampu Pijar 5 Watt Bh 1,750.00 200.00
117 Lampu Pijar 10 Watt Bh 3,000.00 200.00
118 Lampu Pijar 15 Watt Bh 3,100.00 200.00
119 Lampu Pijar 25 Watt Bh 3,200.00 200.00
120 Lampu Pijar 40 Watt Bh 3,700.00 200.00
121 Lampu Pijar 60 Watt Bh 3,700.00 200.00
122 Lampu Pijar 75 Watt Bh 4,200.00 200.00
123 Lampu Pijar 100 Watt Bh 4,900.00 200.00
124 Lampu Jari-jari 14 Watt Philips Bh 35,000.00 1,000.00
125 Lampu Jari-jari 25 Watt Philips Bh 50,000.00 1,000.00
126 Profil Tank Satinless 1100 L Bh 3,575,000.00 55,000.00
127 Profil Tank Fiberglass 1000 L Bh 1,925,000.00 55,000.00
128 Profil Tank Fiberglass 2000 L Bh
BAHAN FABRIKASI

PROFIT PPN JAMSOSTEK HARGA SATUAN


10% 10% 0.50% DILOKASI PROYEK PEMBULATAN
(Rp) (Rp) (Rp) (Rp) (Rp)
7=10% *(5+6) 8 9=0.5%*(5+6+7) 10 11
8,795.00 483.73 96,745.00 96,700.00 50
177.00 9.74 1,947.00 1,900.00
1,825.00 100.38 20,075.00 20,000.00

2,625.00 144.38 28,875.00 28,800.00


1,285.00 70.68 14,135.00 14,100.00
1,125.00 61.88 12,375.00 12,300.00
1,625.00 89.38 17,875.00 17,800.00 6 7.46064
2,605.00 143.28 28,655.00 28,600.00 8 13.26336
3,765.00 207.08 41,415.00 41,400.00 10 20.724
5,435.00 298.93 59,785.00 59,700.00 12 29.84256
8,190.00 450.45 90,090.00 90,000.00 14 40.61904
10,960.00 602.80 120,560.00 120,500.00 16 53.05344
17,400.00 957.00 191,400.00 191,400.00 19 74.81364
26,780.00 1,472.90 294,580.00 294,500.00 22 100.30416
32,640.00 1,795.20 359,040.00 359,000.00 25 129.525
48,760.00 2,681.80 536,360.00 536,300.00 32 212.21376

1,895.00 104.23 20,845.00 20,800.00


2,025.00 111.38 22,275.00 22,200.00
2,525.00 138.88 27,775.00 27,700.00
1,715.00 94.33 18,865.00 18,800.00

125,050.00 6,877.75 1,375,550.00 1,375,500.00


6,050.00 332.75 66,550.00 66,500.00
9,050.00 497.75 99,550.00 99,500.00
10,500.00 577.50 115,500.00 115,500.00
12,530.00 689.15 137,830.00 137,800.00
21,710.00 1,194.05 238,810.00 238,800.00

4,537.50 249.56 49,912.50 49,900.00


5,537.50 304.56 60,912.50 60,900.00
8,537.50 469.56 93,912.50 93,900.00
10,037.50 552.06 110,412.50 110,400.00

11,690.00 642.95 128,590.00 128,500.00


15,200.00 836.00 167,200.00 167,200.00

717.50 39.46 7,892.50 7,800.00


1,077.50 59.26 11,852.50 11,800.00
1,347.50 74.11 14,822.50 14,800.00
887.50 48.81 9,762.50 9,700.00
1,537.50 84.56 16,912.50 16,900.00
2,427.50 133.51 26,702.50 26,700.00
4,647.50 255.61 51,122.50 51,100.00
7,357.50 404.66 80,932.50 80,900.00

170.00 9.35 1,870.00 1,800.00


170.00 9.35 1,870.00 1,800.00
220.00 12.10 2,420.00 2,400.00
370.00 20.35 4,070.00 4,000.00
520.00 28.60 5,720.00 5,700.00
720.00 39.60 7,920.00 7,900.00
1,220.00 67.10 13,420.00 13,400.00
1,520.00 83.60 16,720.00 16,700.00

200.00 11.00 2,200.00 2,200.00


170.00 9.35 1,870.00 1,800.00
1,620.00 89.10 17,820.00 17,800.00

4,790.00 263.45 52,690.00 52,600.00


6,440.00 354.20 70,840.00 70,800.00
9,890.00 543.95 108,790.00 108,700.00

3,667.50 201.71 40,342.50 40,300.00


6,047.50 332.61 66,522.50 66,500.00
6,547.50 360.11 72,022.50 72,000.00
5,547.50 305.11 61,022.50 61,000.00
6,547.50 360.11 72,022.50 72,000.00
4,525.00 248.88 49,775.00 49,700.00
2,217.50 121.96 24,392.50 24,300.00
3,305.00 181.78 36,355.00 36,300.00
4,055.00 223.03 44,605.00 44,600.00
4,555.00 250.53 50,105.00 50,100.00
4,555.00 250.53 50,105.00 50,100.00
5,195.00 285.73 57,145.00 57,100.00
5,555.00 305.53 61,105.00 61,100.00
5,695.00 313.23 62,645.00 62,600.00
7,955.00 437.53 87,505.00 87,500.00
8,555.00 470.53 94,105.00 94,100.00
27,555.00 1,515.53 303,105.00 303,100.00
5,675.00 312.13 62,425.00 62,400.00
5,675.00 312.13 62,425.00 62,400.00
3,255.00 179.03 35,805.00 35,800.00
4,735.00 260.43 52,085.00 52,000.00
2,735.00 150.43 30,085.00 30,000.00
3,705.00 203.78 40,755.00 40,700.00
4,525.00 248.88 49,775.00 49,700.00
3,195.00 175.73 35,145.00 35,100.00
3,195.00 175.73 35,145.00 35,100.00
475.00 26.13 5,225.00 5,200.00
3,985.00 219.18 43,835.00 43,800.00
1,315.00 72.33 14,465.00 14,400.00 5 2,380
1,130.00 62.15 12,430.00 12,400.00
1,525.00 83.88 16,775.00 16,700.00
12,875.00 708.13 141,625.00 141,600.00
36,355.00 1,999.53 399,905.00 399,900.00
9,875.00 543.13 108,625.00 108,600.00
10,875.00 598.13 119,625.00 119,600.00
30,375.00 1,670.63 334,125.00 334,100.00
75,375.00 4,145.63 829,125.00 829,100.00
2,520.00 138.60 27,720.00 27,700.00
3,970.00 218.35 43,670.00 43,600.00
2,560.00 140.80 28,160.00 28,100.00
1,690.00 92.95 18,590.00 18,500.00
33,050.00 1,817.75 363,550.00 363,500.00
33,050.00 1,817.75 363,550.00 363,500.00
308,750.00 16,981.25 3,396,250.00 3,396,200.00
308,750.00 16,981.25 3,396,250.00 3,396,200.00
169,705.00 9,333.78 1,866,755.00 1,866,700.00
1,020.00 56.10 11,220.00 11,200.00
12,520.00 688.60 137,720.00 137,700.00
20,020.00 1,101.10 220,220.00 220,200.00
2,270.00 124.85 24,970.00 24,900.00
2,020.00 111.10 22,220.00 22,200.00
3,520.00 193.60 38,720.00 38,700.00
4,520.00 248.60 49,720.00 49,700.00
7,520.00 413.60 82,720.00 82,700.00

295.00 16.23 3,245.00 3,200.00

2,020.00 111.10 22,220.00 22,200.00

15,020.00 826.10 165,220.00 165,200.00


20,020.00 1,101.10 220,220.00 220,200.00

5,020.00 276.10 55,220.00 55,200.00


7,260.00 399.30 79,860.00 79,800.00
7,280.00 400.40 80,080.00 80,000.00
9,220.00 507.10 101,420.00 101,400.00

4,250.00 233.75 46,750.00 46,700.00


4,250.00 233.75 46,750.00 46,700.00
810.00 44.55 8,910.00 8,900.00
1,060.00 58.30 11,660.00 11,600.00
4,250.00 233.75 46,750.00 46,700.00
4,250.00 233.75 46,750.00 46,700.00
6,020.00 331.10 66,220.00 66,200.00
195.00 10.73 2,145.00 2,100.00
320.00 17.60 3,520.00 3,500.00
330.00 18.15 3,630.00 3,600.00
340.00 18.70 3,740.00 3,700.00
390.00 21.45 4,290.00 4,200.00
390.00 21.45 4,290.00 4,200.00
440.00 24.20 4,840.00 4,800.00
510.00 28.05 5,610.00 5,600.00
3,600.00 198.00 39,600.00 39,600.00
5,100.00 280.50 56,100.00 56,100.00
363,000.00 19,965.00 3,993,000.00 3,993,000.00
198,000.00 10,890.00 2,178,000.00 2,178,000.00
2,078
1,908
1,781
1,796
1,992
2,047
2,312
2,657
2,510
2,290
21,370 2,137 / kg