BILL OF QUANTITY ( BOQ )

BoQ 5 : REKAPITULASI HARGA

PROYEK : SUTT 150 kV INCOMER DOUBLE PHI (MUARA TEWEH - PURUK CAHU) GI PURUK CAHU 4 CCT TWIN KONDUKTOR (ACSR/AS 250)

TOTAL
ITEM DESCRIPTION
IDR

I BoQ 1 PEKERJAAN SIPIL


I.1 PEKERJAAN PEMBERSIHAN JALUR & PERSIAPAN 252,708,024
I.2 TOWER & ACCESSORIES SYSTEM TERMASUK PEMERIKSAAN AKHIR 11,102,015,021
I.3 PEKERJAAN PONDASI TERMASUK PEMERIKSAAN AKHIR 7,416,929,741

II BoQ 2 PEKERJAAN ELEKTROMEKANIKAL


II.1 CONDUCTORS, INCLUDING DOWNLEADS TO SUBSTATION GANTRY 901,174,237
II.2 OPTICAL GROUND WIRE (OPGW), INCLUDING DOWNLEADS TO SUBSTATION GANTRY (refer to the related TPG) 543,292,733
II.3 ALUMINIUM-CLAD STEEL (AS), INCLUDING DOWNLEADS TO SUBSTATION GANTRY (refer to the related TPG) -
II.5.1 INSULATOR STRING SETS COMPLETE WITH ALL FITTINGS (refer to the related drawing and TPG) 1,995,043,113
II.6 CONDUCTOR FITTING AND ACCESSORIES SYSTEM 395,975,579
II.7 OPTICAL GROUND WIRE (OPGW) FITTING AND ACCESSORIES SYSTEM 73,769,103
II.8 ALUMINIUM-CLAD STEEL (AS) FITTING AND ACCESSORIES SYSTEM -
II.10 SUPPORTING STRINGING WORKS -
KONTRAKTOR WAJIB MENYEDIAKAN
II.11 HEALTH SAFETY AND ENVIRONMENT
APD

III BoQ 3 PEKERJAAN KOMISIONING


III.1.1 TEST AND COMMISSIONING (UNTIL RLB CERTIFICATE ISSUED) 26,261,600
III.1.2 COMPLETION DOCUMENTS 25,000,000

IV BoQ 4 PEKERJAAN ENJINIRING


IV.1 ENGINEERING DESIGN 33,300,000

TOTAL HARGA 22,765,469,150


PEMBULATAN 22,765,469,000
PPN 10% 2,276,546,900
TOTAL HARGA TERMASUK PPN 25,042,015,900
*) HARGA SUDAH TERMASUK PERALATAN APD
Terbilang :

Jakarta, 26 November 2018


PT. Prima Power Nusantara

SARONO
Direktur Utama
BILL OF QUANTITY ( BOQ )

BoQ 2 : PEKERJAAN ELEKTROMEKANIKAL

PROYEK : SUTT 150 kV INCOMER DOUBLE PHI (MUARA TEWEH - PURUK CAHU) GI PURUK CAHU 4 CCT TWIN KONDUKTOR (ACSR/AS 250)

TRANSPORTASI DAN KONSTRUKSI


HARGA SATUAN TRANSPORTASI
Peralatan/Material KONSTRUKSI GRAND TOTAL
KE LOKASI
VOLUME SATUAN On Site TOTAL (Erection and TOTAL
NO. DESKRIPSI PEKERJAAN **)
Installation)
Local (Trmsk Asuransi)
IDR IDR IDR IDR IDR
1 2 3 4 = (1 x 3) 5 6 7 = 1 x (5 + 6) 8 = (4 + 7)
II PEKERJAAN ELEKTROMEKANIKAL 3%

II.1 CONDUCTORS, INCLUDING DOWNLEADS TO SUBSTATION GANTRY


II.1.1 Six Twin line conductors ACSR 250 N/A kmr N/A N/A N/A N/A N/A N/A
II.1.2 Six Twin line conductors ACSR/AS 250 6.66 kmr Pengadaan Terpusat 25,650,000 109,600,913 901,174,237 901,174,237
901,174,237
OPTICAL GROUND WIRE (OPGW), INCLUDING DOWNLEADS TO SUBSTATION GANTRY (refer to the related
II.2
TPG)
II.2.1 Set of single OPGW 90,4 kN conductors 6.66 kmr 53,664,188 357,563,451 1,609,926 17,826,747 129,506,174 487,069,625
II.2.2 Set of Joint boxes of OPGW 2 Sets 9,095,625 18,191,250 272,869 4,375,000 9,295,738 27,486,988
II.2.3 Set of Gantry Boxes (GB) complete, installed on substation gantry 2 Sets 9,702,000 19,404,000 291,060 4,375,000 9,332,120 28,736,120
543,292,733
ALUMINIUM-CLAD STEEL (AS), INCLUDING DOWNLEADS TO SUBSTATION GANTRY (refer to the related
II.3
TPG)
II.3.1 One earth conductor, AS 70 0.00 kmr - - -
II.3.2 Armour Rod for earthwire AS 70 0 Sets - - -
II.3.3 Mind spand joint GSW/AS 0 Sets - - -
-
Total Item II.1-II.4 : 1,444,466,969

II.5 INSULATOR SETS SYSTEM

INSULATOR POLYMER STRING SETS COMPLETE WITH ALL FITTINGS (refer to the related drawing and
II.5.1
TPG)
II.5.1.1 Heavy Pollution
II.5.1.1.1 Tension set single string 210 kN 36 Sets 5,032,913 181,184,850 150,987 661,229 29,239,772 210,424,622
II.5.1.1.2 Tension set double string 210 kN 132 Sets 8,489,250 1,120,581,000 254,678 971,687 161,880,048 1,282,461,048
II.5.1.1.3 Suspension set single string 120 kN 0 Sets 4,790,363 - 143,711 440,819 - -
II.5.1.1.4 Suspension set double string 120 kN 12 Sets 8,125,425 97,505,100 243,763 647,791 10,698,645 108,203,745
II.5.1.1.5 Inverted Single string 210 kN 12 Sets 5,032,913 60,394,950 150,987 971,687 13,472,087 73,867,037
II.5.1.1.6 Inverted Double string 210 kN N/A Sets N/A N/A N/A N/A N/A N/A
II.5.1.1.7 Jumper Suspension Set Single String 120 kN 69 Sets 3,941,438 271,959,188 118,243 579,257 48,127,474 320,086,662
Total Item II.5.1.1 : 1,995,043,113

II.6 CONDUCTOR FITTING AND ACCESSORIES SYSTEM

II.6.1 VIBRATION DAMPERS AND CONDUCTOR SPACERS


II.6.1.1 Line conductor spacer dampers N/A Sets N/A N/A N/A N/A N/A N/A
II.6.1.2 Line span vibration damper for Zebra N/A Sets N/A N/A N/A N/A N/A N/A
II.6.1.3 Line span vibration damper for Hawk N/A Sets N/A N/A N/A N/A N/A N/A

II.6.2 CONDUCTOR SPACER


II.6.2.1 Line conductor spacer dampers (span) 400 mm for ACSR/AS 250 612 Sets 460,845 282,037,140 13,825 62,500 46,711,114 328,748,254
II.6.2.2 Line conductor spacers (jumper) 200 mm for ACSR/AS 250 204 Sets 181,913 37,110,150 5,457 31,250 7,488,305 44,598,455

II.6.3 JOINT
II.6.3.1 Mid span joint 24 Sets 278,933 6,694,380 8,368 125,000 3,200,831 9,895,211
II.6.3.2 Repair sleeves 6 Sets 303,188 1,819,125 9,096 260,722 1,618,906 3,438,031
BILL OF QUANTITY ( BOQ )

BoQ 2 : PEKERJAAN ELEKTROMEKANIKAL

PROYEK : SUTT 150 kV INCOMER DOUBLE PHI (MUARA TEWEH - PURUK CAHU) GI PURUK CAHU 4 CCT TWIN KONDUKTOR (ACSR/AS 250)

TRANSPORTASI DAN KONSTRUKSI


HARGA SATUAN TRANSPORTASI
Peralatan/Material KONSTRUKSI GRAND TOTAL
KE LOKASI
VOLUME SATUAN On Site TOTAL (Erection and TOTAL
NO. DESKRIPSI PEKERJAAN **)
Installation)
Local (Trmsk Asuransi)
IDR IDR IDR IDR IDR

II.6.4 ACCESSORIES
II.6.4.1 Armour Rod for conductor 2 X ACSR/AS 250 24 Sets 254,678 6,112,260 7,640 125,000 3,183,368 9,295,628
II.6.4.2 Counterweight per 100 kg N/A Sets N/A N/A N/A N/A N/A N/A
II.6.4.3 Aircraft warning system (if neccessary) N/A Sets N/A N/A N/A N/A N/A N/A
395,975,579
II.7 OPTICAL GROUND WIRE (OPGW) FITTING AND ACCESSORIES SYSTEM

II.7.1 GROUND WIRE DAMPERS


II.7.1.1 Ground Wire OPGW vibration dampers 60 Sets 272,869 16,372,125 8,186 157,910 9,965,734 26,337,859

II.7.2 FITTINGS
II.7.2.1 Ground wire suspension set (OPGW 90,4 kN) including armour rod 2 Sets 909,563 1,819,125 27,287 255,069 564,712 2,383,837
II.7.2.2 Ground wire tension set (OPGW 90,4 kN) including armour rod 30 Sets 1,334,025 40,020,750 40,021 127,535 5,026,658 45,047,408
73,769,103
II.8 ALUMINIUM-CLAD STEEL (AS) FITTING AND ACCESSORIES SYSTEM

II.8.1 GROUND WIRE DAMPERS


II.8.1.1 Ground Wire AS vibration dampers 0 Sets - - -

II.8.2 FITTINGS
II.8.2.1 Ground wire suspension clamp (AS 70) 0 Sets - - -
II.8.2.2 Ground wire tension clamp (AS 70) 0 Sets - - -
-
Total Item II.6 - II.9 : 469,744,682

II.10 SUPPORTING STRINGING WORKS

Include in erection
II.10.1 Bush Clearing 1 Ls N/A N/A N/A -
and installation

Include in erection
II.10.2 Pemasangan Stegger termasuk backstay (if any) 1 Ls N/A N/A N/A -
and installation

Total Item II.10 : -

II.11 HEALTH SAFETY AND ENVIRONMENT


II.11.1 Sepatu Boots Safety 52 Pcs
II.11.2 Helm Safety 52 Pcs
II.11.3 Sarung Tangan 52 Pcs
KONTRAKTOR WAJIB MENYEDIAKAN APD
II.11.4 Safety Belt 22 Pcs
II.11.5 Kaca Mata Safety 22 Pcs
II.11.6 Rambu K3 7 Set

Note : **) Biaya transportasi tower dan konduktor (Kontrak KHS Terpusat) ditawarkan berdasarkan lokasi pabrik
**) Biaya transportasi fiting, GSW dan OPGW termasuk harga pengadaan
BILL OF QUANTITY ( BOQ )

BoQ 3 : PEKERJAAN KOMISIONING

PROYEK : SUTT 150 kV INCOMER DOUBLE PHI (MUARA TEWEH - PURUK CAHU) GI PURUK CAHU 4 CCT TWIN KONDUKTOR (ACSR/AS 250)

HARGA SATUAN TOTAL


JUMLAH SATUAN KOMISIONING
NO. URAIAN
IDR IDR
1 2 3 4 = (1 x 3)

III PEKERJAAN KOMISIONING

III.1 PEKERJAAN KOMISIONING

III.1.2.1 Pengujian Pentanahan 8 Set 157,700 1,261,600


III.1.3.1 Pengujian Tahanan Isolasi 1 Ls 10,000,000 10,000,000
III.1.4.1 Pengujian OTDR 1 Ls 15,000,000 15,000,000

Total Item III.1 : 26,261,600

III.2 COMPLETION DOCUMENTS

III.2.1 Completion Documents 1 Lot 25,000,000 25,000,000


III.2.1.1 Technical specification and brochure/leaflet of transmission line materials Include item III.2.1
III.2.1.2 Design of Calculation and design drawings Include item III.2.1
III.2.1.3 Test Report for Tower foundation, and Transmission Materials (including Megger Test) Include item III.2.1
III.2.1.4 As built Drawing including documentation Include item III.2.1

Total Item III.2 : 25,000,000


BILL OF QUANTITY ( BOQ )

BoQ 4 : PEKERJAAN ENJINIRING

PROYEK : SUTT 150 kV INCOMER DOUBLE PHI (MUARA TEWEH - PURUK CAHU) GI PURUK CAHU 4 CCT TWIN KONDUKTOR (ACSR/AS 250)

ENJINIRING TOTAL
NO. URAIAN JUMLAH SATUAN
IDR IDR

IV PEKERJAAN ENJINIRING

IV.1 ENGINEERING DESIGN 1 Lot 33,300,000 33,300,000


IV.1.1 Civil (Desan, Calculation, Drawing & Document) Include item IV.1 5
IV.1.2 Electromechanical (Desan, Calculation, Drawing & Document) Include item IV.1
(Desain Tower Nonstandar, Leg Extension, Stub Extension, Chimney Extension dan
IV.1.3 Include item IV.1
Pondasi Nonstandar) if any

Total Item IV: 33,300,000


BILL OF QUANTITY ( BOQ )

BoQ 2 : PEKERJAAN ELEKTROMEKANIKAL

PROYEK : SUTT 150 kV INCOMER DOUBLE PHI (MUARA TEWEH - PURUK CAHU) GI PURUK CAHU 4 CCT TWIN KONDUKTOR (ACSR/AS 250)

TRANSPORTASI DAN KONSTRUKSI


HARGA SATUAN GRAND TOTAL
VOLUME SATUAN TRANSPORTASI ASURANSI ROK
NO. DESKRIPSI EXCLUDE PPN INCLUDE PPN
110% 0% 0.25% 10%

II PEKERJAAN ELEKTROMEKANIKAL

II.1 CONDUCTORS, INCLUDING DOWNLEADS TO SUBSTATION GANTRY


II.1.1 Six Twin line conductors ACSR 250 N/A kmr N/A N/A N/A N/A N/A N/A
II.1.2 Six Twin line conductors ACSR/AS 250 6.66 kmr Pengadaan Terpusat - - -
-
II.2 OPTICAL GROUND WIRE (OPGW), INCLUDING DOWNLEADS TO SUBSTATION GANTRY (refer to the related TPG)
II.2.1 Set of single OPGW 90,4 kN conductors 6.66 kmr 44,250,000 48,675,000 - 121,688 4,867,500 53,664,188
II.2.2 Set of Joint boxes of OPGW 2 Sets 7,500,000 8,250,000 - 20,625 825,000 9,095,625
II.2.3 Set of Gantry Boxes (GB) complete, installed on substation gantry 2 Sets 8,000,000 8,800,000 - 22,000 880,000 9,702,000

II.3 ALUMINIUM-CLAD STEEL (AS), INCLUDING DOWNLEADS TO SUBSTATION GANTRY (refer to the related TPG)
II.3.1 One earth conductor, AS 70 0.00 kmr - - - - -
II.3.2 Armour Rod for earthwire AS 70 0 Sets - - - - -
II.3.3 Mind spand joint GSW/AS 0 Sets - - - - -
-
Total Item II.1-II.4 : -

II.5 INSULATOR SETS SYSTEM

II.5.1 INSULATOR POLYMER STRING SETS COMPLETE WITH ALL FITTINGS (refer to the related drawing and TPG)
II.5.1.1 Heavy Pollution
II.5.1.1.1 Tension set single string 210 kN 36 Sets 4,150,000 4,565,000 - 11,413 456,500 5,032,913
II.5.1.1.2 Tension set double string 210 kN 132 Sets 7,000,000 7,700,000 - 19,250 770,000 8,489,250
II.5.1.1.3 Suspension set single string 120 kN 0 Sets 3,950,000 4,345,000 - 10,863 434,500 4,790,363
II.5.1.1.4 Suspension set double string 120 kN 12 Sets 6,700,000 7,370,000 - 18,425 737,000 8,125,425
II.5.1.1.5 Inverted Single string 210 kN 12 Sets 4,150,000 4,565,000 - 11,413 456,500 5,032,913
II.5.1.1.6 Inverted Double string 210 kN N/A Sets N/A N/A N/A N/A N/A N/A
II.5.1.1.7 Jumper Suspension Set Single String 120 kN 69 Sets 3,250,000 3,575,000 - 8,938 357,500 3,941,438
INSULATOR POLYMER STRING SETS 405 2,150,000 2,365,000 - 5,913 236,500 2,607,413
Total Item II.5.1.1 : 35,412,300

II.6 CONDUCTOR FITTING AND ACCESSORIES SYSTEM

II.6.1 VIBRATION DAMPERS AND CONDUCTOR SPACERS


II.6.1.1 Line conductor spacer dampers N/A Sets N/A N/A N/A N/A N/A N/A
II.6.1.2 Line span vibration damper for Zebra N/A Sets N/A N/A N/A N/A N/A N/A
II.6.1.3 Line span vibration damper for Hawk N/A Sets N/A N/A N/A N/A N/A N/A

II.6.2 CONDUCTOR SPACER


II.6.2.1 Line conductor spacer dampers (span) 400 mm for ACSR/AS 250 612 Sets 380,000 418,000 - 1,045 41,800 460,845
II.6.2.2 Line conductor spacers (jumper) 200 mm for ACSR/AS 250 204 Sets 150,000 165,000 - 413 16,500 181,913
BILL OF QUANTITY ( BOQ )

BoQ 2 : PEKERJAAN ELEKTROMEKANIKAL

PROYEK : SUTT 150 kV INCOMER DOUBLE PHI (MUARA TEWEH - PURUK CAHU) GI PURUK CAHU 4 CCT TWIN KONDUKTOR (ACSR/AS 250)

TRANSPORTASI DAN KONSTRUKSI


HARGA SATUAN GRAND TOTAL
VOLUME SATUAN TRANSPORTASI ASURANSI ROK
NO. DESKRIPSI EXCLUDE PPN INCLUDE PPN
110% 0% 0.25% 10%
II.6.3 JOINT
II.6.3.1 Mid span joint 24 Sets 230,000 253,000 - 633 25,300 278,933
II.6.3.2 Repair sleeves 6 Sets 250,000 275,000 - 688 27,500 303,188

II.6.4 ACCESSORIES
II.6.4.1 Armour Rod for conductor 2 X ACSR/AS 250 24 Sets 210,000 231,000 - 578 23,100 254,678
II.6.4.2 Counterweight per 100 kg N/A Sets N/A N/A N/A N/A N/A N/A
II.6.4.3 Aircraft warning system (if neccessary) N/A Sets N/A N/A N/A N/A N/A N/A
1,479,555.00
II.7 OPTICAL GROUND WIRE (OPGW) FITTING AND ACCESSORIES SYSTEM

II.7.1 GROUND WIRE DAMPERS


II.7.1.1 Ground Wire OPGW vibration dampers 60 Sets 225,000 247,500 - 619 24,750 272,869

II.7.2 FITTINGS
II.7.2.1 Ground wire suspension set (OPGW 90,4 kN) including armour rod 2 Sets 750,000 825,000 - 2,063 82,500 909,563
II.7.2.2 Ground wire tension set (OPGW 90,4 kN) including armour rod 30 Sets 1,100,000 1,210,000 - 3,025 121,000 1,334,025
2,516,456.25
II.8 ALUMINIUM-CLAD STEEL (AS) FITTING AND ACCESSORIES SYSTEM

II.8.1 GROUND WIRE DAMPERS


II.8.1.1 Ground Wire AS vibration dampers 0 Sets - - - - -

II.8.2 FITTINGS
II.8.2.1 Ground wire suspension clamp (AS 70) 0 Sets - - - - -
II.8.2.2 Ground wire tension clamp (AS 70) 0 Sets - - - - -
-
Total Item II.6 - II.9 : 3,996,011.25

II.10 SUPPORTING STRINGING WORKS


Include in erection
II.10.1 Bush Clearing 1 Ls N/A N/A N/A -
and installation
Include in erection
II.10.2 Pemasangan Stegger termasuk backstay (if any) 1 Ls N/A N/A N/A -
and installation
Total Item II.10 : -

II.11 HEALTH SAFETY AND ENVIRONMENT


II.11.1 Sepatu Boots Safety 52 Pcs
II.11.2 Helm Safety 52 Pcs
II.11.3 Sarung Tangan 52 Pcs
KONTRAKTOR WAJIB MENYEDIAKAN APD
II.11.4 Safety Belt 22 Pcs
II.11.5 Kaca Mata Safety 22 Pcs
II.11.6 Rambu K3 7 Set

Note : **) Biaya transportasi tower dan konduktor (Kontrak KHS Terpusat) ditawarkan berdasarkan lokasi pabrik
**) Biaya transportasi fiting, GSW dan OPGW termasuk harga pengadaan
PT. PLN (PERSERO)
PROYEK INDUK PEMBANGKIT DAN JARINGAN

DAFTAR MATERIAL SCHEDULE


SUTT 150 KV INCOMER DOUBLE PHI (MUARA TEWEH - PURUK CAHU) GI PURUK CAHU
DI KALIMANTAN TENGAH
TAHUN 2017/2018

Type Insulator 2 X ACSR/AS 250 OPGW 70 SQMM


LATOR Suspension Tension
NOMOR TYPE SUDUT SPAN TOTAL JARAK KETERANGAN Spacer Spacer Vib. Armour
NO Mid Span armour rod Join Box Susp. Set Tension Set
TOWER TOWER BELOK (M) (M) LOKASI SS DS ST DT RVS JMP Damper Jumper Damper Rod

GI PURUK CAHU 0.00 RVS 0 0 0 0 12 0 0 0 0 2 0


90.00 12 4
1 T.01R 4DDR + 3 0O 90.00 ST/DT 0 0 12 12 0 18 30 0 0 4 0
Semak Belukar, Jalan,
258.35 48 4
TM 20 kV
2 T.02R 4BB + 6 5O 348.35 DT/ST 0 0 12 12 0 0 24 0 0 4 0
349.48 Hutan, Kebun Karet 72 4

3 T.03R 4AA + 9 0O 697.83 DS 0 12 0 0 0 0 0 24 2 0 2


380.96 Hutan, Kebun Karet, 72 8
Pertambangan Rakyat
4 T.04R 4CC + 15 26O 1078.79 ST/DT 0 0 12 12 0 12 30 0 0 4 0
368.92 Rawa, Jalan, TM 20kV 72 8

5 T.05R 4DD + 15 51O 1447.71 DT/DT 0 0 0 24 0 12 30 0 0 4 0


357.198 Hutan, Rawa 72 8

6 T.06R 4CC + 15 20O 1804.91 DT/DT 0 0 0 24 0 12 30 0 0 4 0


518.674 Hutan, Kebun Palawija 24 96 8

7 T.07R 4BB + 15 2O 2323.58 DT/DT 0 0 0 24 0 0 30 0 0 4 0


417.103 Sungai Barito 84 8

8 T.08R 4DDR + 9 10O 2740.69 DT/DT 0 0 0 24 0 15 30 0 2 0 4 0


432.162 Hutan, Kebun Karet 84 8
T.134 & AA + 6
9 0O 3172.85 0 0 0 0 0 0 0 0 0 0
T.137

TITIK INTERKONEKSI 0 0 0 0 0

TOTAL 3,172.85 0 12 36 132 12 69 24 612 204 24 2 60 2 30 2


PROYEK : SUTT 150 kV INCOMER DOUBLE PHI (MUARA TEWEH - PURUK CAHU) GI PURUK CAHU 4 CCT TWIN KONDUKTOR (ACSR/AS 250)
SCHEDULE 2 : BREAKDOWN PRICE ANALYSIS FOR CIVIL WORKS

UNIT PRICE TOTAL PRICE


UNIT QTY LOCAL CURRENCY LOCAL
NO DESCRIPTION
PORTION
(RUPIAH) (RUPIAH)
A. PREPARATION WORK
An 1 Temporary Site Office and Site Storage (lantai Plesteran) m2 2,280,786
Remuneration
- Worker man/day 2.000 130,000 260,000
- Brick Layer man/day 1.000 120,000 120,000
- BricklayerChief man/day 0.300 170,000 51,000
- Foreman man/day 0.050 215,000 10,750
- Carpenter man/day 2.000 120,000 240,000
- CarpenterChief man/day 0.300 157,500 47,250

Material
- Dolken dia 8-10 cm / 400 cm pcs 3.000 16,500 49,500
- Beam meranti 5/7 m3 0.276 2,200,000 607,200
- Nail 2 "5 " kg 0.700 13,750 9,625
- Semen portland' kg 35.000 1,320 46,200
- Pasir Pasang m3 0.150 258,742 38,811
- Pasir Beton m3 0.100 258,750 25,875
- Koral Beton m3 0.150 577,500 86,625
- Bata Merah pcs 30.000 770 23,100
- Zinc sheet 1.400 100,100 140,140
- plywood 4 mm sheet 0.060 79,200 4,752
- pondasi pas batu m3 0.076 1,436,618 109,183
- Paku asbes kg 0.100 23,870 2,387
- Kunci Tanam pcs 0.150 200,000 30,000
- Kaca Polos m2 0.080 96,250 7,700
- Teakwood double door m2 0.100 301,829 30,183
- Louvre frame window sheet 1.000 264,605 264,605
- cat dinding plafond m2 3.000 25,300 75,900

An 2 Temporary Rumah Jaga (Konstruksi Kayu) m2 1,501,702


Remuneration
- Worker man/day 1.000 130,000 130,000
- Foreman man/day 0.050 215,000 10,750
- Carpenter man/day 1.500 120,000 180,000
- Carpenter Chief man/day 0.150 157,500 23,625

Material
- Dolken dia 8-10 cm / 400 cm pcs 3.000 16,500 49,500
- Beam meranti 5/7 m3 0.276 2,200,000 607,200
- Nail 2 "5 " kg 0.700 13,750 9,625
- Zinc sheet 1.500 100,100 150,150
- plywood 4 mm sheet 0.060 79,200 4,752
- pondasi pas batu m3 0.076 16,125 1,226
- Paku asbes kg 0.100 23,870 2,387
- Kunci Tanam pcs 0.150 200,000 30,000
- Kaca Polos m2 0.080 96,250 7,700
- teakwood double door m2 0.100 301,829 30,183
- Louvre frame window sheet 1.000 264,605 264,605

An 3 Temporary Gudang Semen dan Peralatan m2 1,173,303


Remuneration
- Worker man/day 1.000 130,000 130,000
- Foreman man/day 0.050 215,000 10,750
- Carpenter man/day 2.000 120,000 240,000
- Carpenter Chief man/day 0.200 157,500 31,500

Material
- Dolken dia 8-10 cm / 400 cm pcs 1.700 16,500 28,050
- Beam meranti 5/7 m3 0.210 2,200,000 462,000
- Nail 2 "5 " kg 0.300 13,750 4,125
- Semen portland' kg 10.500 1,320 13,860
- Pasir Beton m3 0.030 258,750 7,762
- Koral Beton m3 0.050 577,500 28,875
- Zinc sheet 1.500 100,100 150,150
- Seng Pelat sheet 0.250 100,100 25,025
- plywood 4 mm sheet 0.060 79,200 4,752
- pondasi pas batu m3 0.076 53,504 4,066
- Paku asbes kg 0.100 23,870 2,387
- Kunci Tanam pcs 0.150 200,000 30,000

An 4 Plank name of project (0.8 x 1.2 m2) unit 1,496,288


Material
- plywood 18 mm sheet 1.000 343,200 343,200
- Beam meranti 8/12 Class II m3 0.077 2,200,000 169,400
- Paint Wood kg 2.500 60,500 151,250
- Nail (5 cm and 7 cm) kg 1.250 13,750 17,188
- Steel L.30.30.3 kg 5.800 60,000 348,000

Remuneration
- Worker man/day 1.000 130,000 130,000
- Carpenter man/day 1.000 120,000 120,000
- Carpenter Chief man/day 0.100 157,500 15,750
- Paint worker man/day 1.500 120,000 180,000
- Foreman man/day 0.100 215,000 21,500

An 5 Fence security of project 2 m height (wooden + Zinc) m 272,961


Material
Dolkenφ 8-10/400 cm stick 1.250 16,500 20,625
PortlandCement Kg 5.000 1,320 6,600
Zinc / Seng Gelombang sheet 1.200 100,100 120,120
Sand (Pasir Beton) m3 0.005 258,750 1,294
Split m3 0.009 577,500 5,198
Nail 2'5' kg 0.060 13,750 825
Beam meranti 5/7 m3 0.010 2,200,000 22,000
Naturally Paint (Meni Besi) liter 0.450 33,000 14,850

Remuneration
Carpenter man/day 0.400 120,000 48,000
Worker man/day 0.200 130,000 26,000
Carpenter Chief man/day 0.020 157,500 3,150
Foreman man/day 0.020 215,000 4,300

An 6 Bouwplank m' 63,084


Material
- Plank meranti 3/20 m3 0.007 2,457,400 17,202
- Beam meranti 5/7 m3 0.013 2,200,000 28,600
- Nail 5-7cm kg 0.020 13,750 275

Remuneration
- Carpenter man/day 0.010 120,000 1,200
- Worker man/day 0.100 130,000 13,000
- Carpenter chief man/day 0.010 157,500 1,575
- Foreman man/day 0.005 215,000 1,075

Equipment
- Waterpass unit/day 0.004 39,380 158

An 7 Site clearing & Grubbing m2 7,635


Remuneration
- Worker man/day 0.050 130,000 6,500
- Foreman man/day 0.005 215,000 1,075

Equipment
- Mesin Potong Rumput unit/day 0.002 30,000 60

An 8 Soil Stripping with Heavy Equipment (t : 20 cm) m3 52,504


Remuneration
Worker man/hour 0.014 130,000 1,768
Operator man/hour 0.007 425,000 2,890

Equipment
Buldozer hour 0.007 770,000 5,236
Alat Bantu Ls 1.000 15,000 15,000

Material
BBM (solar) Ltr 2.000 13,805 27,610

An 9 Soil Stripping manual heigth 1 m m2 10,090


Remuneration
Worker man/day 0.060 130,000 7,800
Foreman man/day 0.006 215,000 1,290

Equipment
Alat Bantu Ls 1.000 1,000 1,000

An 10 Tebas Tebang Berupa Memotong dan membersihkan lokasi dari tanaman dan tumbuhan m2 57,250
Remuneration
- Worker man/day 0.200 130,000 26,000
- Foreman man/day 0.020 215,000 4,300

Equipment
- Chain saw unit-day 0.100 269,500 26,950

An 10 Dewatering m3 38,413
Remuneration
Worker man/day 0.010 130,000 1,300
Foreman man/day 0.050 215,000 10,750

-Equipment
Water Pump unit/day 0.005 352,000 1,760
Tools (wrench, rope) unit/day 0.200 50,000 10,000
Genset unit/day 0.002 1,100,000 2,200

-Material:
Wire kg 0.100 25,000 2,500
Water Hose layflat m 0.020 150,000 3,000
BBM/solar litre 0.500 13,805 6,903

An 11 Concrete Test (per usia/7,14,28) unit 1,339,018


Equipment
- Cube Molding pcs 1.000 5,000 5,000
- Compression Test pcs 12.000 100,000 1,200,000
-
Remuneration -
- Worker man-day 0.250 130,000 32,500
- Engineer man-day 0.125 612,140 76,518

Transportation ls 1.000 25,000 25,000

An
B. SOIL WORK
An 1 General Excavation of Soil (h=1 meter) m3 102,875
- Worker man/day 0.750 130,000 97,500
- Foreman man/day 0.025 215,000 5,375

An 2 General Excavation of Soil (h=2 meter) m3 126,675


- Worker man/day 0.900 130,000 117,000
- Foreman man/day 0.045 215,000 9,675

An 3 General Excavation of Soil (h=3 meter) m3 150,905


- Worker man/day 1.050 130,000 136,500
- Foreman man/day 0.067 215,000 14,405

An 4 General Excavation of Soil (h=4 meter) with heavy equipment m3 267,111


- Worker man/day 1.270 130,000 165,100
- Foreman man/day 0.089 215,000 19,135

Equipment
- Excavator Setara Komatsu PC-200-6 (0.8 - 0.9 m3) hour 0.007 352,000 2,394
- Dump Truck hour 0.256 187,000 47,872
- Alat Bantu Ls 1.000 5,000 5,000

Material
- BBM (solar) Ltr 2.000 13,805 27,610
267,111
An 5 Excavation of Soil (h=3 meter) semi mekanis m3 66,653
Renumeration
- Worker man/day 0.300 130,000 39,000
- Foreman man/day 0.030 215,000 6,450

Material
- BBM ltr 0.500 13,805 6,903

Tools
- Jack Hammer unit-day 0.050 286,000 14,300
66,653
An 6 Excavation of Rock (h=1 meter) m3 136,880
- Worker man/day 1.000 130,000 130,000
- Foreman man/day 0.032 215,000 6,880

An 7 Excavation of Soft Rock (h=1 meter) m3 207,900


Remuneration
- Worker man/day 1.500 130,000 195,000
- Foreman man/day 0.060 215,000 12,900
207,900
An 8 Excavation of Mud/day m3 165,675
Remuneration
- Worker man/day 1.200 130,000 156,000
- Foreman man/day 0.045 215,000 9,675
165,675
An 9 Excavation with Heavy Equipment m3 87,534
- Remuneration
Worker man/hour 0.014 130,000 1,768
Operator man/hour 0.007 425,000 2,890

- Equipment
Excavator Setara Komatsu PC-200-6 (0.8 - 0.9 m3) hour 0.007 352,000 2,394
Dump Truck hour 0.256 187,000 47,872
Alat Bantu Ls 1.000 5,000 5,000

- Material
BBM (solar) Ltr 2.000 13,805 27,610
87,534
An 10 Galian tanah keras/cadas sampai kedalaman 2-3 m m3 325,906
- Worker man/day 2.000 130,000 260,000
- Foreman man/day 0.060 215,000 12,900

Equipment
- Jack Hammer unit-day 0.125 286,000 35,750

Material
- BBM (solar) Ltr 1.250 13,805 17,256
325,906
An 11 Back Filling Include Compaction every 20 cm m3 80,150
Remuneration
- Worker man/day 0.500 130,000 65,000
- Foreman man/day 0.050 215,000 10,750

Rent of Equipment
- Stamper hour 0.100 44,000 4,400

An 12 Soil Disposal (dist. 30 meter) m3 45,050


Remuneration
- Worker man/day 0.330 130,000 42,900
- Foreman man/day 0.010 215,000 2,150
45,050

An 13 Soil Disposal with Dump Truck m3 135,118


Remuneration
- Worker man/hour 0.014 130,000 1,768
- Operator man/hour 0.007 425,000 2,890

Equipment
- Dump Truck hour 0.550 187,000 102,850

Material
- BBM (solar) Ltr 2.000 13,805 27,610

An 14 Import Filling (with sand) m3 351,650


- Material
Sand (Pasir Urug) m3 1.200 258,750 310,500

- Remuneration
Worker man/day 0.300 130,000 39,000
Foreman man/day 0.010 215,000 2,150
351,650
An 15 Import Filling (with Humous Soil) m3 239,150
- Material
Humous Soil m3 1.200 165,000 198,000

- Remuneration
Worker man/day 0.300 130,000 39,000
Foreman man/day 0.010 215,000 2,150
239,150
An 16 Import Filling with compacted soil (out side project area) m3 375,342
Material
- Soil (tanah merah) m3 1.400 165,000 231,000
- Solar liter 2.000 13,805 27,610

Remuneration
- Worker man/hour 0.044 130,000 5,655
- Operator man/hour 0.011 425,000 4,633

Rent of Equipment
- Excavator hour 0.011 352,000 3,837
- Truck hour 0.514 187,000 96,174
- Vibro roller hour 0.004 981,915 4,124
- Water Truck hour 0.007 330,000 2,310
375,342

An 17 Compacted Sand layer m3 390,640


Material
- Sand m3 1.200 258,742 310,490

Rent of Equipment
- Stamper hour 0.100 44,000 4,400

Remuneration
- Worker man/day 0.500 130,000 65,000
- Foreman man/day 0.050 215,000 10,750
390,640
1 m2 Compacted Sand layer (tebal 10 Cm) 39,064
1 m2 Compacted Sand layer (tebal 5 Cm) 23,540

An 18 Compacted Soil (Tanah Merah) m3 278,150


Material
- Soil (tanah merah) m3 1.200 165,000 198,000

Rent of Equipment
- Stamper hour 0.100 44,000 4,400

Remuneration
- Worker man/day 0.500 130,000 65,000
- Foreman man/day 0.050 215,000 10,750
278,150
1 m2 Compacted Soil layer (tebal 10 Cm) 27,815
1 m2 Compacted Soil layer (tebal 5 Cm) 17,915

An 19 Gravelling m3 734,150
Material
- Gravel m3 1.200 577,500 693,000

Remuneration
- Worker man/day 0.300 130,000 39,000
- Foreman man/day 0.010 215,000 2,150
734,150
1 m2 Compacted gravel(tebal 20 Cm) 146,830

An 20 Urug Sirtu padat untuk peninggian lantai bangunan m3 730,875


Material
- Sirtu m3 1.200 577,500 693,000

Remuneration
- Worker man/day 0.250 130,000 32,500
- Foreman man/day 0.025 215,000 5,375

An 21 Tanah dihampar, diratakan dan dirapihkan m3 36,849


Remuneration
- Worker man/day 0.076 130,000 9,932
- Foreman man/day 0.008 215,000 1,643

Equipment
- Buldozer (100 - 150 HP) unit/hour 0.019 1,323,941 25,274
- Biaya Sewa Alat
- Bahan Bakar
- Pelumas
- Biaya Bengkel
- Perawatan & perbaikan
- Operator
- Pembantu Operator

An 22 Tanah dihampar, diratakan dan dirapihkan (Manual) m3 75,750


Remuneration
- Worker man/day 0.500 130,000 65,000
- Foreman man/day 0.050 215,000 10,750

An 22 Cut and Fill include compaction m3 97,090


- Remuneration
Worker man/day 0.150 130,000 19,500
Foreman man/day 0.015 215,000 3,225

- Equipment
Buldozer (100 - 150 HP) unit/hour 0.019 770,000 14,699
Excavator Setara Komatsu PC-200-6 (0.8 - 0.9 m3) hour 0.007 352,000 2,394
Dump Truck hour 0.256 187,000 47,872
Alat Bantu Ls 1.000 5,000 5,000
-Stamper hour 0.100 44,000 4,400

An 23 Soil Compaction (per 20 cm) m3 77,950


Remuneration
- Worker man/day 0.500 130,000 65,000
- Foreman man/day 0.050 215,000 10,750

Equipment
- Stamper hour 0.050 44,000 2,200
An
C. CONCRETE WORK (Brick, Concrete, steel, foundation, piling)
An 1 Bataco 1 pc : 2 ps m2 90,911

Material
Bataco m3 0.015 9,295 139
Portland cement (PC) kg 18.950 1,320 25,014
Sand (Pasir Pasang) m3 0.038 258,742 9,832

Remuneration
Brick layer man/day 0.100 120,000 12,000
Worker man/day 0.300 130,000 39,000
Foreman man/day 0.015 215,000 3,225
Brick Layer chief man/day 0.010 170,000 1,700

An 2 Bataco 1 pc : 3 ps m2 83,625

Material
Bataco pcs 0.150 9,295 1,394
Portland cement (PC) kg 11.500 1,320 15,180
Sand (Pasir Pasang) m3 0.043 258,742 11,126

Remuneration
Brick layer man/day 0.100 120,000 12,000
Worker man/day 0.300 130,000 39,000
Foreman man/day 0.015 215,000 3,225
Brick Layer chief man/day 0.010 170,000 1,700
83,625

An 3 Half Brick 1 pc : 2 ps m2 144,671

Material
Red brick m3 70.000 770 53,900
Portland cement (PC) kg 18.950 1,320 25,014
Sand (Pasir Pasang) m3 0.038 258,742 9,832

Remuneration
Brick layer man/day 0.100 120,000 12,000
Worker man/day 0.300 130,000 39,000
Foreman man/day 0.015 215,000 3,225
Brick Layer chief man/day 0.010 170,000 1,700

An 4 Half Brick 1 pc : 4 ps m2 136,131

Material
Red brick pcs 70.000 770 53,900
Portland cement (PC) kg 11.500 1,320 15,180
Sand (Pasir Pasang) m3 0.043 258,742 11,126

Remuneration
Brick layer man/day 0.100 120,000 12,000
Worker man/day 0.300 130,000 39,000
Foreman man/day 0.015 215,000 3,225
Brick Layer chief man/day 0.010 170,000 1,700

An 5 one Brick (1 pc : 4 ps) uk.5x11x22 cm m2 278,759


Material
Red brick pcs 140.000 770 107,800
Portland cement (PC) kg 26.550 1,320 35,046
Sand (Pasir Pasang) m3 0.093 258,742 24,063

Remuneration
Brick layer man/day 0.200 120,000 24,000
Worker man/day 0.600 130,000 78,000
Foreman man/day 0.030 215,000 6,450
Brick Layer chief man/day 0.020 170,000 3,400
278,759

An 6 Pas. Roster 1 pc : 3 ps m2 694,737

Material
Roster pcs 30.000 20,350 610,500
Portland cement (PC) kg 14.000 1,320 18,480
Sand (Pasir Pasang) m3 0.038 258,742 9,832

Remuneration
Brick layer man/day 0.100 120,000 12,000
Worker man/day 0.300 130,000 39,000
Foreman man/day 0.015 215,000 3,225
Brick Layer chief man/day 0.010 170,000 1,700
694,737

An 7 Plaster cement 1 pc : 4 ps thickness 15 mm m2 94,534

Material
Portland cement (PC) kg 6.280 1,320 8,290
Sand (Pasir Pasang) m3 0.024 258,742 6,210

Remuneration
Brick layer man/day 0.190 120,000 22,800
Worker man/day 0.384 130,000 49,920
Foreman man/day 0.019 215,000 4,085
Brick Layer chief man/day 0.019 170,000 3,230
94,534

An 8 Plaster cement 1 pc : 2 ps thickness 15 mm m2 98,706

Material
Portland cement (PC) kg 10.224 1,320 13,496
Sand (Pasir Pasang) m3 0.020 258,742 5,175

Remuneration
Brick layer man/day 0.190 120,000 22,800
Worker man/day 0.384 130,000 49,920
Foreman man/day 0.019 215,000 4,085
Brick Layer chief man/day 0.019 170,000 3,230
98,706

An 9 Trasram tebal 1,5 cm dengan mortar PC-PP m2 98,706

Material
Portland cement (PC) kg 10.224 1,320 13,496
Sand (Pasir Pasang) m3 0.020 258,742 5,175

Remuneration
Brick layer man/day 0.190 120,000 22,800
Worker man/day 0.384 130,000 49,920
Foreman man/day 0.019 215,000 4,085
Brick Layer chief man/day 0.019 170,000 3,230
98,706

An 10 Acian m2 46,140

Material
Portland cement (PC) kg 3.250 1,320 4,290

Remuneration
Brick layer man/day 0.100 120,000 12,000
Worker man/day 0.200 130,000 26,000
Foreman man/day 0.010 215,000 2,150
Brick Layer chief man/day 0.010 170,000 1,700
46,140

An 11 Brafend 1 pc : 4 ps m2 68,713

Material
Portland cement (PC) kg 4.340 1,366 5,928
Sand (Pasir Pasang) m3 0.040 195,300 7,812

Remuneration
Brick layer man/day 0.100 121,230 12,123
Brick layer Chief man/day 0.010 170,000 1,700
Worker man/day 0.300 130,000 39,000
Foreman man/day 0.010 215,000 2,150
68,713
An 12 Brafend 1 pc : 5 ps m2 69,861

Material
Portland cement (PC) kg 5.180 1,366 7,076
Sand (Pasir Pasang) m3 0.040 195,300 7,812

Remuneration
Brick layer man/day 0.100 121,230 12,123
Brick layer Chief man/day 0.010 170,000 1,700
Worker man/day 0.300 130,000 39,000
Foreman man/day 0.010 215,000 2,150
69,861
An 13 Concrete f'c = 7.4 MPa (K-100) (lean concrete), slump (3-6) cm m3 1,009,227
Material
- Portland cement (PC) kg 230.000 1,366 314,180
- Sand (Pasir Beton) m3 0.638 258,750 165,045
- Split 2/3 m3 0.571 577,500 329,496
- Water liter 200.000 20 3,960

Remuneration
- Brick layer man/day 0.200 121,230 24,246
- Worker man/day 1.200 130,000 156,000
- Foreman man/day 0.060 215,000 12,900
- Brick Layer chief man/day 0.020 170,000 3,400

An 14 Concrete f'c = 7.4 MPa (K-100), slump (12±2) 1 : 3.5 : 4 m3 1,225,294


Material
- Portland cement (PC) kg 247.000 1,366 337,402
- Sand (Pasir Beton) m3 0.621 258,750 160,610
- Split 2/3 m3 0.555 577,500 320,513
- Water liter 215.000 20 4,257

Equipment
- Mollen 0.3 m3 unit/day 0.250 704,000 176,000

Remuneration
- Worker man/day 1.323 130,000 171,990
- Brick layer man/day 0.189 121,230 22,912
- Brick layer chief man/day 0.019 170,000 3,230
- Foreman man/day 0.132 215,000 28,380

An 15 Concrete f'c = 14,5 MPa (K 175), slump (12±2) m3 1,413,362


Material
- Portland cement (PC) kg 326.000 1,366 445,316
- Sand (Pasir Beton) m3 0.543 258,750 140,464
- Split 2/3 m3 0.572 577,500 330,138
- Water liter 215.000 20 4,257

Equipment
- Mollen 0.3 m3 unit/day 0.250 704,000 176,000
- Vibrator unit/day 0.100 528,000 52,800

Remuneration
- Worker man/day 1.573 130,000 204,490
- Brick layer man/day 0.189 121,230 22,912
- Brick layer chief man/day 0.019 170,000 3,230
- Foreman man/day 0.157 215,000 33,755

An 16 Concrete f'c = 19,3 MPa (K 225), slump (12±2) m3 1,469,148


Material
- Portland cement (PC) kg 371.000 1,366 506,786
- Sand (Pasir Beton) m3 0.499 258,750 129,005
- Split 2/3 m3 0.582 577,500 335,913
- Water liter 215.000 20 4,257

Equipment
- Mollen 0.3 m3 unit/day 0.250 704,000 176,000
- Vibrator unit/day 0.100 528,000 52,800

Remuneration
- Worker man/day 1.573 130,000 204,490
- Brick layer man/day 0.189 121,230 22,912
- Brick layer chief man/day 0.019 170,000 3,230
- Foreman man/day 0.157 215,000 33,755

An 17 Concrete Ready mix K- m3 #REF!


Material
- Ready Mixed K- m3 1.050

Equipment
- Pompa dan Conveyor unit-day 0.120
- Vibrator hour 1.200 #REF! #REF!

Remuneration
- Worker man/day 1.000 #REF! #REF!
- Brick layer man/day 0.250 #REF! #REF!
- Brick layer chief man/day 0.025 #REF! #REF!
- Foreman man/day 0.100 #REF! #REF!

An 18 Concrete f'c = 21,7 MPa (K 250), slump (12±2) m3 1,483,231


Material
- Portland cement (PC) kg 384.000 1,366 524,544
- Sand (Pasir Beton) m3 0.494 258,750 127,896
- Split 2/3 m3 0.577 577,500 333,346
- Water liter 215.000 20 4,257

Equipment
- Mollen 0.3 m3 unit/day 0.250 704,000 176,000
- Vibrator unit/day 0.100 528,000 52,800
-
Remuneration
- Worker man/day 1.573 130,000 204,490
- Brick layer man/day 0.189 121,230 22,912
- Brick layer chief man/day 0.019 170,000 3,230
- Foreman man/day 0.157 215,000 33,755

An 19 Concrete f'c = 26.4 MPa (K 300), slump (12±2) m3 1,515,037


Material
- Portland cement (PC) kg 413.000 1,366 564,158
- Sand (Pasir Beton) m3 0.486 258,750 125,863
- Split 2/3 m3 0.567 577,500 327,571
- Water liter 215.000 20 4,257

Equipment
- Mollen 0.3 m3 unit/day 0.250 704,000 176,000
- Vibrator unit/day 0.100 528,000 52,800

Remuneration
- Worker man/day 1.573 130,000 204,490
- Brick layer man/day 0.189 121,230 22,912
- Brick layer chief man/day 0.019 170,000 3,230
- Foreman man/day 0.157 215,000 33,755

An 20 Concrete f'c = 31,2 MPa (K 350), slump (12±2) m3 2,157,629


Material
- Portland cement (PC) kg 448.000 1,366 611,968
- Sand (Pasir Beton) m3 0.476 258,750 123,276
- Split 2/3 m3 0.556 577,500 320,833
- Water liter 215.000 20 4,257

Equipment
- Mollen 0.3 m3 unit/day 0.250 704,000 176,000
- Vibrator hour 1.200 528,000 633,600

Remuneration
- Worker man/day 1.680 130,000 218,400
- Brick layer man/day 0.240 121,230 29,095
- Brick layer chief man/day 0.024 170,000 4,080
- Foreman man/day 0.168 215,000 36,120
2,157,629

An 21 Concrete f'c = 45 MPa (K 500), slump (12±2) m3 4,040,595


Material
Portland cement (PC) kg 588.000 1,366 803,208
Sand (Pasir Beton) m3 0.540 258,750 139,725
Split 2/3 m3 0.850 577,500 490,875
Water liter 215.000 20 4,257

Equipment
Mollen 0.35 m3 hour 1.200 704,000 844,800
Vibrator hour 1.500 528,000 792,000

Remuneration
Brick layer man/day 1.000 121,230 121,230
Worker man/day 6.000 130,000 780,000
Foreman man/day 0.300 215,000 64,500
4,040,595
An 22 Concrete dicorkan untuk kenaikan 4 m (Vertical) m3 30,300
Equipment
- Pompa dan Conveyor unit-day 0.120 352,000

Remuneration
- Worker man/day 0.200 130,000 26,000
- Foreman man/day 0.020 215,000 4,300

An 23 Stone Masonry 1 PC : 2 Sand (Mortar tipe M) m3 1,496,130

Material
Crushed stone m3 1.200 528,000 633,600
Portland cement (PC) kg 252.000 1,366 344,232
Sand (Pasir Pasang) m3 0.440 195,300 85,932

Remuneration
Brick layer man/day 0.750 121,230 90,923
Worker man/day 1.500 130,000 195,000
Foreman man/day 0.075 215,000 16,125
Brick layer chief man/day 0.075 170,000 12,750

Equipment
Molen of Machine unit/day 0.167 704,000 117,568
1,496,130

An 24 Stone Masonry 1 PC : 3 Sand (Mortar Tipe S) m3 1,436,618


Material
- Crushed stone m 3
1.200 528,000 633,600
- Portland cement (PC) kg 202.000 1,366 275,932
- Sand (Pasir Pasang) m3 0.485 195,300 94,721

Remuneration
- Brick layer man/day 0.750 121,230 90,923
- Worker man/day 1.500 130,000 195,000
- Foreman man/day 0.075 215,000 16,125
- Brick layer chief man/day 0.075 170,000 12,750

Equipment
- Molen Machine unit/day 0.167 704,000 117,568
1,436,618
An 25 Stone Masonry 1 PC : 4 Sand m3 1,390,180
Material
- Crushed stone m 3
1.200 528,000 633,600
- Portland cement (PC) kg 163.000 1,366 222,658
- Sand (Pasir Pasang) m3 0.520 195,300 101,556

Remuneration
- Brick layer man/day 0.750 121,230 90,923
- Worker man/day 1.500 130,000 195,000
- Foreman man/day 0.075 215,000 16,125
- Brick layer chief man/day 0.075 170,000 12,750

Equipment
- Molen Machine unit/day 0.167 704,000 117,568
1,390,180
An 26 Stone Masonry 1 PC : 5 Sand m3 1,293,921
Material
- Crushed stone m3 1.200 528,000 633,600
- Portland cement (PC) kg 136.000 1,366 185,776
- Sand (Pasir Pasang) m3 0.544 195,300 106,243

Remuneration
- Brick layer man/day 0.750 121,230 90,923
- Worker man/day 1.500 130,000 195,000
- Foreman man/day 0.075 215,000 16,125
- Brick layer chief man/day 0.075 170,000 12,750

Equipment
- Molen Machine unit/day 0.076 704,000 53,504
1,293,921
An 27 Stone Masonry 1 PC : 6 Sand m3 1,271,287
Material
- Crushed stone m3 1.200 528,000 633,600
- Portland cement (PC) kg 117.000 1,366 159,822
- Sand (Pasir Pasang) m3 0.561 195,300 109,563

Remuneration
- Brick layer man/day 0.750 121,230 90,923
- Worker man/day 1.500 130,000 195,000
- Foreman man/day 0.075 215,000 16,125
- Brick layer chief man/day 0.075 170,000 12,750

Equipment
- Molen Machine unit/day 0.076 704,000 53,504

An 28 Stone Masonry 1 PC : 8 Sand m3 1,240,263


Material
- Crushed stone m3 1.200 528,000 633,600
- Portland cement (PC) kg 91.000 1,366 124,306
- Sand (Pasir Pasang) m3 0.584 195,300 114,055

Remuneration
- Brick layer man/day 0.750 121,230 90,923
- Worker man/day 1.500 130,000 195,000
- Foreman man/day 0.075 215,000 16,125
- Brick layer chief man/day 0.075 170,000 12,750

Equipment
- Molen Machine unit/day 0.076 704,000 53,504

An 29 Batu Kosong (Aanstamping) m3 877,128


Material
- Crushed stone m3 1.200 528,000 633,600
- Sand (Pasir Urug) m3 0.432 184,800 79,834

Remuneration
- Brick layer man/day 0.390 121,230 47,280
- Worker man/day 0.780 130,000 101,400
- Foreman man/day 0.039 215,000 8,385
- Brick layer chief man/day 0.039 170,000 6,630

An 30 Formwork for Supporting (Beam meranti 5/7 height 4 m) m2 192,531

Material
beam meranti 5/7 m3 0.095 2,200,000 207,900
Nail kg 0.350 13,750 4,813

Remuneration
Carpenter man/day 0.600 120,000 72,000
Worker man/day 0.600 130,000 78,000
Foreman man/day 0.060 215,000 12,900
Carpenter chief man/day 0.060 157,500 9,450
192,531

An 31 Formwork Multiplex 12/18mm m2 241,222

Material
Multiplex 12 mm/18 mm lembar 0.128 343,200 43,930
beam meranti 5/7 m3 0.006 2,200,000 13,200
Nail kg 0.280 13,750 3,850
Minyak Bekisting ltr 0.250 31,570 7,893

Remuneration
Carpenter man/day 0.600 120,000 72,000
Worker man/day 0.600 130,000 78,000
Foreman man/day 0.060 215,000 12,900
Carpenter chief man/day 0.060 157,500 9,450
241,222

An 32 Formwork Foundation with multiplex m2 323,887

Material
Multiplex 12 mm/18 mm lembar 0.350 343,200 120,120
beam meranti 5/7 m3 0.040 2,200,000 88,000
Nail kg 0.300 13,750 4,125
Minyak Bekisting ltr 0.100 31,570 3,157

Remuneration
Carpenter man/day 0.260 120,000 31,200
Worker man/day 0.520 130,000 67,600
Foreman man/day 0.026 215,000 5,590
Carpenter chief man/day 0.026 157,500 4,095
323,887
An 33 Formwork Foundation with wooden plank m2 467,611

Material
- 3/20 cm Wooden plank class II m3 0.030 2,457,400 73,722
- Wooden 5/7 cm m3 0.120 2,200,000 264,000
- Paku 5 cm and 7 cm kg 0.400 13,750 5,500
- Minyak Bekisting ltr 0.200 31,570 6,314

Remuneration
- Carpenter man/day 0.270 120,000 32,400
- Worker man/day 0.540 130,000 70,200
- Foreman man/day 0.050 215,000 10,750
- Carpenter chief man/day 0.030 157,500 4,725
467,611

An 34 Formwork For Beam (SNI 7394-2008-23) m2 362,082

Material
Plywood 9 mm/12 mm lembar 0.350 148,500 51,975
beam meranti 5/7 Class II or III m3 0.058 2,200,000 127,600
Nail kg 0.400 13,750 5,500
Minyak Bekisting ltr 0.200 31,570 6,314
Dolken Kayu dia 8 cm btg 2.000 16,500 33,000

Remuneration
Carpenter man/day 0.330 120,000 39,600
Worker man/day 0.660 130,000 85,800
Foreman man/day 0.033 215,000 7,095
Carpenter chief man/day 0.033 157,500 5,198
362,082
An 35 Formwork For Column (SNI 7394-2008-22) m2 355,482

Material
Plywood 9 mm/12 mm lembar 0.350 148,500 51,975
beam meranti 5/7 Class II or III m3 0.055 2,200,000 121,000
Nail kg 0.400 13,750 5,500
Minyak Bekisting ltr 0.200 31,570 6,314
Dolken Kayu dia 8 cm btg 2.000 16,500 33,000

Remuneration
Carpenter man/day 0.330 120,000 39,600
Worker man/day 0.660 130,000 85,800
Foreman man/day 0.033 215,000 7,095
Carpenter chief man/day 0.033 157,500 5,198
355,482
An 36 Formwork For Slab (SNI 7394-2008-24) m2 421,482

Material
Plywood 9 mm/12 mm lembar 0.350 148,500 51,975
beam meranti 5/7 Class II or III m3 0.055 2,200,000 121,000
Nail kg 0.400 13,750 5,500
Minyak Bekisting ltr 0.200 31,570 6,314
Dolken Kayu dia 8 cm btg 6.000 16,500 99,000

Remuneration
Carpenter man/day 0.330 120,000 39,600
Worker man/day 0.660 130,000 85,800
Foreman man/day 0.033 215,000 7,095
Carpenter chief man/day 0.033 157,500 5,198
421,482
An 37 Formwork For Stair (SNI 7394-2008-26) m2 331,903

Material
Plywood 9 mm/12 mm lembar 0.350 148,500 51,975
beam meranti 5/7 Class II or III m3 0.045 2,200,000 99,000
Nail kg 0.400 13,750 5,500
Minyak Bekisting ltr 0.150 31,570 4,736
Dolken Kayu dia 8 cm btg 2.000 16,500 33,000

Remuneration
Carpenter man/day 0.330 120,000 39,600
Worker man/day 0.660 130,000 85,800
Foreman man/day 0.033 215,000 7,095
Carpenter chief man/day 0.033 157,500 5,198

An 38 Demolishing Formwork of Foundation m2 6,060

Remuneration
- Worker man/day 0.040 130,000 5,200
- Foreman man/day 0.004 215,000 860

An 39 Steel work U24 or BJTP 24 (100 kg) For Plate Kg 18,992


Material
- Steel Bar (Reinforcement) U 24 or BJTP 24 kg 105.000 15,400 1,617,000
- Concrete wire kg 1.500 63,756 95,634

Remuneration
- Steel worker man/day 0.700 100,000 70,000
- Worker man/day 0.700 130,000 91,000
- Foreman man/day 0.070 215,000 15,050
- Chief of steel Worker man/day 0.070 150,000 10,500
1,899,184
Per kg 18,992

An 40 Steel work U39 or BJTD 39 (100 kg) for Plate Kg 18,992


Material
- Steel Bar (Reinforcement) U 39 or BJTD 39 kg 105.000 15,400 1,617,000
- Concrete wire kg 1.500 63,756 95,634
Remuneration
- Steel worker man/day 0.700 100,000 70,000
- Worker man/day 0.700 130,000 91,000
- Foreman man/day 0.070 215,000 15,050
- Chief of steel Worker man/day 0.070 150,000 10,500
1,899,184
Per kg 18,992

An 41 Steel work U24 or BJTP 24 Beam and Colomn Kg 22,300


Material
- Steel Bar (Reinforcement) U 24 or BJTP 24 kg 105.000 15,400 1,617,000
- Concrete wire kg 2.100 63,756 133,888

Remuneration
- Steel worker man/day 1.400 100,000 140,000
- Worker man/day 2.100 130,000 273,000
- Foreman man/day 0.210 215,000 45,150
- Chief of steel Worker man/day 0.140 150,000 21,000
2,230,038
Per kg 22,300

An 42 Steel work U39 or BJTD 39 Beam and Colomn Kg 22,300


Material
- Steel Bar (Reinforcement) U 39 or BJTD 39 kg 105.000 15,400 1,617,000
- Concrete wire kg 2.100 63,756 133,888

Remuneration
- Steel worker man/day 1.400 100,000 140,000
- Worker man/day 2.100 130,000 273,000
- Foreman man/day 0.210 215,000 45,150
- Chief of steel Worker man/day 0.140 150,000 21,000
2,230,038
Per kg 22,300

An 43 Steel Structure ton 25,431,977

Material
Steel Structure (HTS) ton 0.748 17,600,000 13,156,000
Steel Structure (MS) ton 0.403 17,600,000 7,084,000
Bolt and Nuts pcs 120.000 9,680 1,161,600
Band plate ton 0.035 10,780 377

Remuneration
Steel worker man/day 10.000 100,000 1,000,000
Worker man/day 20.000 130,000 2,600,000
Foreman man/day 2.000 215,000 430,000
25,431,977
Per kg 25,432

An 44 IWF trusses complete with connection and steel painting Kg

Material
Profil IWF kg 1.150 29,370 33,776
Steel painting kg 0.080 118,800 9,504

Remuneration
Worker man/day 0.060 130,000 7,800
Foreman man/day 0.003 215,000 645
Welder man/day 0.060 150,000 9,000
Welder chief man/day 0.006 120,000 720

- Equipment
Welding Machine unit/day 0.020 544,500 10,890
72,335

An 45 Wiremesh / Sheet 10 Kg 3,515,349


Material
- Wiremesh sheet 1.000 3,410,000 3,410,000
- Concrete wire kg 1.500 63,756 95,634

Remuneration
- Steel worker man/day 0.025 100,000 2,500
- Worker man/day 0.025 130,000 3,250
- Foreman man/day 0.001 215,000 215
- Chief of steel Worker man/day 0.025 150,000 3,750
3,515,349
Per kg 35,153

An 46 Pilling (Driven Pile 30 x 30 cm) m 686,247

Material
- Driven Pile with reinforced concrete 30x30 cm m' 1.100 550,000 605,000

Equipment
- Tripod height 5 m hour 0.031 66,000 2,059
- Hammer 1-2 ton manual hour 0.031 145,200 4,530
- Pile connection hour 0.250 132,000 33,000

Remuneration
- Worker man/day 0.250 130,000 32,500
- Foreman man/day 0.025 215,000 5,375
- Brick layer man/day 0.031 121,230 3,782

An 47 Pilling (Driven Pile 40 x 40 cm) m 647,747

Material
Driven Pile with reinforced concrete 30x30 cm m' 1.030 550,000 566,500

Equipment
Tripod height 5 m unit/day 0.031 66,000 2,059
Hammer 1-2 ton manual unit/day 0.031 145,200 4,530
Pile connection pcs 0.250 132,000 33,000

Remuneration
Worker man/day 0.250 130,000 32,500
Foreman man/day 0.025 215,000 5,375
Brick layer man/day 0.031 121,230 3,782
647,747

An 48 Bored Pile (dia 40 cm) m 881,108


Material
- Drilling pile hole m 0.000 200,000 -
- Concrete K-175 m3 0.126 1,413,362 177,518
- Screew Reinfoced of Steel U 32BJTD 40 kg 17.147 18,992 325,649
- Casing ls 1.000 151,200 151,200
- Fuel ltr 0.500 13,805 6,903

Equipment
- Drilling Pile of Machine hour 0.150 897,422 134,613
- Pipe Tremi hour 0.150 35,640 5,346
- Theodolit hour 0.083 27,500 2,292
- Supporting of Equipment ( Welder and Cutting Machine ) hour 0.150 29,856 4,478

Mobilization
- Mobilisasion of Drilling or Driven Machine ls 0.005 1,000,000 5,000

Remuneration
- Worker man/day 0.100 130,000 13,000
- Foreman man/day 0.010 215,000 2,150
- Operator man/day 0.100 425,000 42,500
- Engineer man/day 0.010 612,140 6,121
- Surveyor man/day 0.010 433,800 4,338

An 49 Pilling (Driven Pile 20 x 20 cm) m

Material
Driven Pile with reinforced concrete 20x20 cm m 1.030 176,000 181,280

Equipment
Tripod height 5 m unit/day 0.019 66,000 1,221
Hammer 1-2 ton manual unit/day 0.019 145,200 2,687
Pile connection unit 0.250 132,000 33,000

Remuneration
Worker man/day 0.149 130,000 19,308
Foreman man/day 0.012 215,000 2,555
Brick layer man/day 0.023 121,230 2,803
242,855

An 50 Pilling (Sheet Pile Corrugated Precast) 40 x 15 m

Material
Sheet Pile Corrugated Precast 40 x 15 m' 1.030 1,419,000 1,461,570

Remuneration
Worker man/day 0.200 130,000 26,000
Foreman man/day 0.020 215,000 4,300
Brick Layer man/day 0.025 121,230 3,031

Equipment
Tripod height 5 m unit/day 0.025 66,000 1,650
Hammer 1-2 ton manual unit/day 0.025 145,200 3,630
Pile connection pcs 0.250 132,000 33,000
1,533,181

An 51 Wooden Driven Pile m 130,022


Material
- Dolken dia 10 cm m 1.200 16,500 19,800

Rent of Equipment
- Hammer 1-2 ton (manually) hour 0.050 145,200 7,260
- Tripod height 5 m hour 0.050 66,000 3,300
- Pile Connection hour 0.250 132,000 33,000

Remuneration
- Worker man/day 0.400 130,000 52,000
- Foreman man/day 0.040 215,000 8,600
- Brick Layer man/day 0.050 121,230 6,062

An 52 Steel Structure Transportation (+ 54 km) ton


Remuneration
Operator man/day 1.000
Worker man/day 5.000
Steel Worker man/day 1.000
Foreman man/day 1.000

Equipment
Truk Trailer 20 feet unit/day 0.200
Forklift kapasitas 3 ton unit/day 0.150

Tools (include sling, clamp, etc) ls 0.050

BBM + Tolls
BBM / Solar liter 5.000
Tolls ls 1.000
An 53 Installment Anchor Steel Bolt Kg
Remuneration
Steel worker man/day 0.030 100,000 3,000
Worker man/day 0.020 130,000 2,600
Foreman man/day 0.002 215,000 430
Chief of steel Worker man/day 0.003 150,000 450

Material
Anchor Bar kg 0.200 84,000 16,800
Bolt kg 2.040 -

An 54 Installment Profil IWF or Canal Kg 40,219


Remuneration
Steel worker man/day 0.030 100,000 3,000
Worker man/day 0.020 130,000 2,600
Foreman man/day 0.002 215,000 430
Chief of steel Worker man/day 0.003 150,000 450
-
Material -
Baja IWF kg 1.050 29,370 30,839
Las Wire kg 0.022 63,756 1,403

Equipment
Las Machine hour 0.022 68,063 1,497

An 55 Pekerjaan Bored Pile dia 60 cm (Breakdown)


A Mobilisasi Alat Bored Pile titik 0.720 800,000 576,000
B Pekerjaan Pengeboran Bored Pile (dia 60 cm) m' 199,102
Remuneration -
- Worker man/day 0.125 130,000 16,250
- Operator man/day 0.063 425,000 26,563
- Foreman man/day 0.031 215,000 6,719
-
Equipment -
- Drilling Pile of Machine hour 0.167 897,422 149,570
-
Cutting Kepala Bored Pile Pcs 84,025
Remuneration -
- Worker man/day 0.250 130,000 32,500
- Foreman man/day 0.063 215,000 13,438
-
Equipment -
- Hammer day 0.125 145,200 18,150
- Steel Saw day 0.125 159,500 19,938
-
C Bored pile dia 60 cm (include beton K-225, Penulangan BJTP 24 dan BJTD 32, dan langsir Material bored pile) 1,164,618
- Concrete K-225 m3 0.311 1,469,148 456,699
- Screew Reinfoced of Steel U 32BJTD 40 kg 32.937 18,992 625,541
- Langsir Material Bored Pile m3 0.311 265,000 82,378

An 56 Turap Kayu Dolken m' 244,125


Remuneration
Worker man/day 0.250 130,000 32,500
Foreman man/day 0.025 215,000 5,375
-
Material -
Dolken dia. 8-10 cm, length 4 m. Stick 12.500 16,500 206,250

D. DEMOLISHING WORK
An 1 Demolishing Formwork for foundation m2 #REF!
Remuneration
Worker man/day 0.040 #REF! #REF!
Foreman' man/day 0.004 #REF! #REF!
#REF!
An 2 Demolishing Stone Masonry with Jack Hammer m3 116,695
Remuneration
- Worker man/day 0.600 130,000 78,000
- Foreman man/day 0.060 215,000 12,900

Equipment
- Jack Hammer unit/day 0.050 286,000 14,300
- Palu / Godam pcs 0.050 229,900 11,495

An 3 Demolishing Brick Wall manual m #REF!


Remuneration
Worker man/day 6.667 #REF! #REF!
Foreman man/day 0.333 #REF! #REF!

Equipment (supporting tools) unit


Palu / Godam unit 0.002 #REF! #REF!
Pahat Beton (Baja Keras) unit 0.003 #REF! #REF!
Linggis (Baja Keras) unit 0.007 #REF! #REF!
#REF!

An 4 Demolishing Red Brick with Jack Hammer m3 #REF!


Remuneration
Worker man/day 0.200 #REF! #REF!
Foreman man/day 0.020 #REF! #REF!

Equipment
Sewa Jack Hammer day 0.020 #REF! #REF!
#REF!
An 5 Demolishing Reinforced Concrete Manual m3 #REF!
Remuneration
- Worker man/day 3.600 #REF! #REF!
- Foreman man/day 0.360 #REF! #REF!

Material
- Cuka Bibit Liter 1.200 18,000 21,600

Equipment
- Palu / Godam pcs 0.020 #REF! #REF!
- Gergaji Besi pcs 0.100 #REF! #REF!
- Pahat Beton (Baja Keras) pcs 0.030 #REF! #REF!
- Linggis pcs 0.050 #REF! #REF!

An 6 Demolishing Concrete with Jack Hammer m3 356,178


Remuneration
- Worker man/day 1.200 130,000 156,000
- Foreman man/day 0.120 215,000 25,800

Equipment
- Jack Hammer unit/day 0.250 286,000 71,500
- Hammer (Palu) bh 0.050 229,900 11,495
- Steel Saw bh 0.100 159,500 15,950
- Steel Chisel (Baja Keras) bh 0.200 204,600 40,920

Material
- BBM liter 2.500 13,805 34,513

An 7 Demolishing Concrete with heavy equip m3 #REF!


Remuneration
Worker man/day 0.090 #REF! #REF!
Foreman man/day 0.045 #REF! #REF!
Operator man/day 0.200 #REF! #REF!

Equipment
Excavatormounted hydraulic jackhammer hour 0.250 #REF! #REF!
Scaffholding
Main Frame Scaffolding 1.9 m unit/day 0.500 #REF! #REF!
Horizontal Frame Scaffolding unit/day 0.500 #REF! #REF!
Cross Brace unit/day 0.500 #REF! #REF!
Jack Base Scaffolding unit/day 0.500 #REF! #REF!
Sling unit/day 0.200 #REF! #REF!
Anchor pcs 0.200 #REF! #REF!

Material
BBM / Solar liter 0.500 #REF! #REF!
#REF!
An 8 Demolished Concrete Disposal (Outside Project Area) m3 #REF!
Remuneration
Worker man/day 0.120 #REF! #REF!
Foreman man/day 0.013 #REF! #REF!
Operator man/day 0.024 #REF! #REF!

Equipment
Excavator hour 0.384 #REF! #REF!
Dump Truck hour 0.384 #REF! #REF!

Material
BBM (Solar) liter 2.000 #REF! #REF!
#REF!
An 9 Steel Structure Dismantling ton #REF!
Remuneration
Steel Worker man/day 5.000 #REF! #REF!
Worker man/day 10.000 #REF! #REF!
Foreman man/day 1.000 #REF! #REF!
Welder man/day 0.500 #REF! #REF!
-
Equipment -
Scaffholding -
Main Frame Scaffolding 1.9 m unit/day 0.500 #REF! #REF!
Horizontal Frame Scaffolding unit/day 0.500 #REF! #REF!
Cross Brace unit/day 0.500 #REF! #REF!
Jack Base Scaffolding unit/day 0.500 #REF! #REF!
Sling unit/day 0.200 #REF! #REF!
Anchor pcs 0.200 #REF! #REF!
Welding Machine unit/day 0.250 #REF! #REF!
Genset unit/day 0.250 #REF! #REF!
-
Material -
BBM (Solar) liter 0.500 #REF! #REF!
#REF!
An 10 Demolishing conductor m
Remuneration
Worker man/day 0.050
Steel Worker man/day 0.020
Foreman man/day 0.002

Equipment
Tools (seling, tirfor, etc) unit/day 0.100
Steel saw unit/day 0.015

An 11 Demolishing isolator & accesories ton


Remuneration
Worker man/day 0.500
Steel Worker man/day 0.200
Foreman man/day 0.020

Equipment
Tools (seling, tirfor, etc) unit/day 0.200
Chain block unit/day 0.150

An 12 Dismlanting Fence/gate Unit 594,128


Remuneration
Steel Worker man/day 1.000 100,000 100,000
Worker man/day 2.000 130,000 260,000
Foreman man/day 0.500 215,000 107,500
Welder man/day 0.250 150,000 37,500

Equipment
Welding Machine unit/day 0.050 544,500 27,225
Genset unit/day 0.050 1,100,000 55,000

Material
BBM (Solar) liter 0.500 13,805 6,903

An 13 Demolishing and rewinding existing cable m


Remuneration
Worker man/day 0.200
Foreman man/day 0.080

Material
Haspel unit 0.005

An 14 Rewinding existing cable m


Equipment
Truck crane 3 ton unit-day 0.125 2,576,000 322,000
Forklift unit-day 0.063 #REF! #REF!
Tripod unit-day 0.500 #REF! #REF!
Chain block 5 ton unit-day 0.500 #REF! #REF!

Renumeration
Worker man-day 0.160 #REF! #REF!
Steel worker man-day 0.160 #REF! #REF!
Supervision man-day 0.080 #REF! #REF!
Foreman man-day 0.080 #REF! #REF!
#REF!
An 15 Relocated pre cast concrete/sheet pile (inside project area) lbr
Remuneration
Worker man/day 0.500 #REF! #REF!
Foreman man/day 0.050 #REF! #REF!
Operator man/day 0.025 #REF! #REF!
-
Equipment -
Mobile crane unit/day 0.020 #NAME? #NAME?
-
Material -
BBM (Solar) liter 0.500 #REF! #REF!
#REF!
An 16 Demolished pipe and disposal (Outside Project Area) m
Remuneration
Worker man/day 0.120 #REF! #REF!
Foreman man/day 0.013 #REF! #REF!
Operator man/day 0.024 #REF! #REF!

Equipment
Excavator hour 0.120 #REF! #REF!
Dump Truck hour 0.120 #REF! #REF!

Material
BBM (Solar) liter 2.000 #REF! #REF!
#REF!
An 17 Dismlanting Sliding Door (4000x5000)mm unit
Remuneration
Steel Worker man/day 5.000
Worker man/day 10.000
Foreman man/day 1.000
Welder man/day 0.500

Equipment
Scaffholding
Main Frame Scaffolding 1.9 m unit/day 0.500
Horizontal Frame Scaffolding unit/day 0.500
Cross Brace unit/day 0.500
Jack Base Scaffolding unit/day 0.500
Anchor pcs 0.200
Welding Machine unit/day 0.250
Genset unit/day 0.250

Material
BBM (Solar) liter 0.500

An 18 Dismantling Thermal Insulation Glasswool t=10 cm m2


Remuneration
Carpenter man/day 0.050
Worker man/day 0.150
Foreman man/day 0.008
Carpenter chief man/day 0.005

An 19 Demolishing Roofing klip lock HITEN (atap aluminium) m2


Remuneration
Carpenter man/day 0.750
Worker man/day 0.150
Foreman man/day 0.006
Carpenter chief man/day 0.080

An 20 Demolishing Nok Standard HITEN m


Remuneration
Carpenter man/day 1.000
Worker man/day 0.100
Foreman man/day 0.050
Carpenter chief man/day 0.100

An 21 Demolishing Roofing (asbes) m2


Remuneration
Carpenter man/day 0.375 #REF! #REF!
Worker man/day 0.075 #REF! #REF!
Foreman man/day 0.003 #REF! #REF!
Carpenter chief man/day 0.040 #REF! #REF!
#REF!
An 22 Demolishing Plesteran Dinding m2 279,350
Remuneration
Worker man/day 2.000 130,000 260,000
Foreman man/day 0.090 215,000 19,350

An 23 Demolishing Plafond (jika bongkaran dipakai) m2


Remuneration
Worker man/day 0.100
Foreman man/day 0.005
Carpenter man/day 0.250
Carpenter Chief man/day 0.003

An 24 Demolishing Plafond (jika bongkaran tidak dipakai) m2


Remuneration
Worker man/day 0.125
Foreman man/day 0.125

An 25 Demolishing Lighting road (including pole and cable) unit


Remuneration
Worker man/day 0.850 #REF! #REF!
Foreman man/day 0.325 #REF! #REF!
#REF!
An 26 Demolishing CCTV unit
Remuneration
Worker man/day 0.750 #REF! #REF!
Foreman man/day 0.250 #REF! #REF!
#REF!
E. FINISHING WORK
An 1 Ceilling Gypsum board 1200 x 2400 x 9 mm m2 60,831

- Material
Gypsum board 9 mm sheet 0.347 106,920 37,125
Nail screws kg 0.110 25,850 2,844
- Remuneration
Carpenter man/day 0.050 120,000 6,000
Worker man/day 0.100 130,000 13,000
Foreman man/day 0.005 215,000 1,075
Carpenter chief man/day 0.005 157,500 788
60,831

An 2 Ceilling Frame (Hollow steel 40 x 40 x 2 mm, modul 60x120 cm) m2 613,733

Material
- Hollow steel 40.40.2 mm m' 3.500 121,000 423,500
- Accessories Ls 1.000 121,000 121,000

Remuneration
- Carpenter man/day 0.250 120,000 30,000
- Worker man/day 0.250 130,000 32,500
- Foreman man/day 0.013 215,000 2,795
- Carpenter chief man/day 0.025 157,500 3,938
613,733

An 3 List plafon gypsum profil m 64,043

- Material
list gypsum profil m' 1.050 43,560 45,738
Tepung gypsum kg 0.150 9,130 1,370

- Remuneration
Carpenter man/day 0.060 120,000 7,200
Worker man/day 0.060 130,000 7,800
Foreman man/day 0.009 215,000 1,935
64,043

An 4 Granite floor tiles 600 x 600 mm m2 688,351

- Material
Granite tile 600 x 600 mm m2 1.050 536,360 563,178
Portland Cement (PC) kg 9.600 1,320 12,672
Sand (Pasir Pasang) m3 0.045 258,742 11,643
Colour Cement (PC) kg 1.500 33,660 50,490

- Remuneration
Brick layer man/day 0.120 121,230 14,548
Worker man/day 0.240 130,000 31,200
Foreman man/day 0.012 215,000 2,580
Brick layer chief man/day 0.012 170,000 2,040
688,351

An 5 Granite floor tiles 300 x 300 mm m2 415,183

- Material
Granite tile 300 x 300 mm m2 1.050 271,700 285,285
Portland Cement (PC) kg 10.000 1,320 13,200
Sand (Pasir Pasang) m3 0.045 258,742 11,643
Colour Cement kg 1.500 33,660 50,490

- Remuneration
Brick layer man/day 0.130 121,230 15,760
Worker man/day 0.260 130,000 33,800
Foreman man/day 0.013 215,000 2,795
Brick layer chief man/day 0.013 170,000 2,210
415,183

An 6 Granite floor tiles 300 x 600 mm m2 573,480

- Material
Granite tile 300 x 600 mm m2 1.050 429,550 451,028
Portland Cement (PC) kg 10.000 1,320 13,200
Sand (Pasir Pasang) m3 0.045 258,742 11,643
Colour Cement kg 1.300 33,660 43,758

- Remuneration
Brick layer man/day 0.125 121,230 15,154
Worker man/day 0.260 130,000 33,800
Foreman man/day 0.013 215,000 2,688
Brick layer chief man/day 0.013 170,000 2,210
573,480

An 7 Non glazed ceramic floor tiles 400 x 400 mm m2 493,016

- Material
Not glazed ceramic floor tiles 400 x 400 mm m2 1.000 372,020 372,020
Portland Cement (PC) kg 9.800 1,320 12,936
Sand (Pasir Pasang) m3 0.045 258,742 11,643
Colour Cement kg 1.300 33,660 43,758

- Remuneration
Brick layer man/day 0.125 121,230 15,154
Worker man/day 0.250 130,000 32,500
Foreman man/day 0.013 215,000 2,795
Brick layer chief man/day 0.013 170,000 2,210
493,016

An 8 Granite wall tiles 400 x 400 mm m2 812,696

- Material
Granite wall tiles 400 x 400 mm m2 1.100 372,020 409,222
Portland Cement (PC) kg 9.800 1,320 12,936
Colour Cement kg 1.300 258,742 336,365
Sand (Pasir Pasang) m3 0.045 33,660 1,515

- Remuneration
Brick layer man/day 0.125 121,230 15,154
Worker man/day 0.250 130,000 32,500
Foreman man/day 0.013 215,000 2,795
Brick layer chief man/day 0.013 170,000 2,210
812,696
An 9 Granite plint tile 100 x 300 mm m 122,529

- Material
Granite plint tile 100 x 300 mm m 3.333 27,500 91,667
Portland Cement (PC) kg 1.140 1,320 1,505
Sand (Pasir Pasang) m3 0.003 258,742 776
Colour Cement kg 0.100 33,660 3,366

- Remuneration
Brick layer man/day 0.090 121,230 10,911
Worker man/day 0.090 130,000 11,700
Foreman man/day 0.005 215,000 1,075
Brick layerr chief man/day 0.009 170,000 1,530
122,529

An 10 Glazed plint tiles 100 x 400 mm m 99,793

- Material
Glazed plint tiles 100 x 400 mm m2 2.500 27,500 68,750
Portland Cement (PC) kg 1.140 1,320 1,505
Sand (Pasir Pasang) m3 0.003 258,742 776
Colour Cement kg 0.100 33,660 3,366
-
- Remuneration -
Brick layer man/day 0.090 121,230 10,911
Worker man/day 0.090 130,000 11,700
Foreman man/day 0.009 215,000 1,935
Brick layer chief man/day 0.005 170,000 850
99,793

An 11 Ceramic floor tiles 200 x 200 mm m2 327,522


- Material
Ceramic tile 200 x 200 mm m2 1.200 83,930 100,716
Portland Cement (PC) kg 10.400 1,320 13,728
Sand (Pasir Pasang) m3 0.045 258,742 11,643
Colour Cement (PC) kg 1.620 33,660 54,529

- Remuneration
Brick layer man/day 0.350 121,230 42,431
Worker man/day 0.700 130,000 91,000
Foreman man/day 0.035 215,000 7,525
Brick layer chief man/day 0.035 170,000 5,950

An 12 Ceramic floor tiles 300 x 300 mm m2 322,955


- Material
Ceramic tile 300 x 300 mm m2 1.200 83,930 100,716
Portland Cement (PC) kg 10.000 1,320 13,200
Sand (Pasir Pasang) m3 0.045 258,742 11,643
Colour Cement (PC) kg 1.500 33,660 50,490

- Remuneration
Brick layer man/day 0.350 121,230 42,431
Worker man/day 0.700 130,000 91,000
Foreman man/day 0.035 215,000 7,525
Brick layer chief man/day 0.035 170,000 5,950

An 13 Ceramic floor tiles 600 x 600 mm m2 262,145


- Material
Ceramic tile 600 x 600 mm m2 1.100 124,520 136,972
Portland Cement (PC) kg 9.600 1,320 12,672
Sand (Pasir Pasang) m3 0.045 258,742 11,643
Colour Cement (PC) kg 1.500 33,660 50,490

- Remuneration
Brick layer man/day 0.120 121,230 14,548
Worker man/day 0.240 130,000 31,200
Foreman man/day 0.012 215,000 2,580
Brick layer chief man/day 0.012 170,000 2,040
262,145

An 14 Ceramic wall tiles 100 x 200 mm m2 330,512


- Material
Ceramic tile 100 x 200 mm m2 1.200 49,500 59,400
Portland Cement (PC) kg 9.300 1,320 12,276
Sand (Pasir Pasang) m3 0.018 258,742 4,657
Colour Cement (PC) kg 1.940 33,660 65,300

- Remuneration
Brick layer man/day 0.450 121,230 54,554
Worker man/day 0.900 130,000 117,000
Foreman man/day 0.045 215,000 9,675
Brick layer chief man/day 0.045 170,000 7,650
An 15 Ceramic wall tiles 200 x 200 mm m2 371,828
- Material
Ceramic tile 200 x 200 mm m2 1.200 83,930 100,716
Portland Cement (PC) kg 9.300 1,320 12,276
Sand (Pasir Pasang) m3 0.018 258,742 4,657
Colour Cement (PC) kg 1.940 33,660 65,300

- Remuneration
Brick layer man/day 0.450 121,230 54,554
Worker man/day 0.900 130,000 117,000
Foreman man/day 0.045 215,000 9,675
Brick layer chief man/day 0.045 170,000 7,650

An 16 Ceramic plint tile 100 x 600 mm m 113,363

- Material
Granite plint tile 100 x 600 mm m2 1.667 49,500 82,500
Portland Cement (PC) kg 1.140 1,320 1,505
Sand (Pasir Pasang) m3 0.003 258,742 776
Colour Cement kg 0.100 33,660 3,366

- Remuneration
Brick layer man/day 0.090 121,230 10,911
Worker man/day 0.090 130,000 11,700
Foreman man/day 0.005 215,000 1,075
Brick layerr chief man/day 0.009 170,000 1,530

An 17 Glazed Ceramic wall tiles 200 x 250 mm m2 169,757


- Material
Ceramic tile 200 x 250 mm m2 1.200 27,500 33,000
Portland Cement (PC) kg 10.400 1,320 13,728
Sand (Pasir Pasang) m3 0.045 258,742 11,643
Colour Cement (PC) kg 1.620 33,660 54,529

- Remuneration
Brick layer man/day 0.135 121,230 16,366
Worker man/day 0.270 130,000 35,100
Foreman man/day 0.014 215,000 3,010
Brick layer chief man/day 0.014 170,000 2,380
169,757

An 18 Granite plint tile 100 x 600 mm m 113,363

- Material
Granite plint tile 100 x 600 mm m2 1.667 49,500 82,500
Portland Cement (PC) kg 1.140 1,320 1,505
Sand (Pasir Pasang) m3 0.003 258,742 776
Colour Cement kg 0.100 33,660 3,366

- Remuneration
Brick layer man/day 0.090 121,230 10,911
Worker man/day 0.090 130,000 11,700
Foreman man/day 0.005 215,000 1,075
Brick layerr chief man/day 0.009 170,000 1,530
113,363

An 19 Stepnosing 100 x 400 mm m 59,819

- Material
Stepnosing 100 x 400 mm m2 1.000 32,010 32,010
Portland Cement (PC) kg 1.240 1,320 1,637
Sand (Pasir Pasang) m3 0.003 258,742 776

- Remuneration
Brick layer man/day 0.090 121,230 10,911
Worker man/day 0.090 130,000 11,700
Foreman man/day 0.009 215,000 1,935
Brick layer chief man/day 0.005 170,000 850
59,819

An 20 Roofing klip lock HI-TEN (atap aluminium) m2 195,210

- Material
Roofing klip lock HI-TEN sheet 1.050 68,085 71,490
Nail drat (Paku hak panjang 15 cm) kg 0.020 16,500 330

- Remuneration
Carpenter man/day 0.750 120,000 90,000
Worker man/day 0.150 130,000 19,500
Foreman man/day 0.006 215,000 1,290
Carpenter chief man/day 0.080 157,500 12,600
195,210

An 21 Roofing Onduline Classic m2 291,195


- Material
Roofing Onduline Classic sheet 1.050 159,500 167,475
Nail drat kg 0.020 16,500 330

- Remuneration
Carpenter man/day 0.750 120,000 90,000
Worker man/day 0.150 130,000 19,500
Foreman man/day 0.006 215,000 1,290
Carpenter chief man/day 0.080 157,500 12,600

An 22 Roofing Spandek Colorbond m2 324,344


- Material
Roofing Spandek Colorbond m2 1.050 191,070 200,624
Nail drat kg 0.020 16,500 330

- Remuneration
Carpenter man/day 0.750 120,000 90,000
Worker man/day 0.150 130,000 19,500
Foreman man/day 0.006 215,000 1,290
Carpenter chief man/day 0.080 157,500 12,600
324,344

An 23 Nok Standard HI-TEN m 250,712

- Material
Nok StandardHI-TEN (40x18) pc 1.200 75,460 90,552
Nail drat (Paku hak panjang 15 cm) kg 0.040 16,500 660

- Remuneration
Carpenter man/day 1.000 120,000 120,000
Worker man/day 0.100 130,000 13,000
Foreman man/day 0.050 215,000 10,750
Carpenter chief man/day 0.100 157,500 15,750
250,712

An 24 Nok Onduline Classic m 261,800


- Material
Nok Onduline Classic pc 1.200 84,700 101,640
Nail drat kg 0.040 16,500 660

- Remuneration
Carpenter man/day 1.000 120,000 120,000
Worker man/day 0.100 130,000 13,000
Foreman man/day 0.050 215,000 10,750
Carpenter chief man/day 0.100 157,500 15,750
261,800

An 25 Nok Spandek Colorbond m 236,456


- Material
Nok Spandek Colorbond pc 1.200 63,580 76,296
Nail drat kg 0.040 16,500 660

- Remuneration
Carpenter man/day 1.000 120,000 120,000
Worker man/day 0.100 130,000 13,000
Foreman man/day 0.050 215,000 10,750
Carpenter chief man/day 0.100 157,500 15,750
236,456

An 26 Thermal Insulation Glasswool t=10 cm m2 158,523

- Material
Glasswool t=10 cm, aluminium foil (single sided) with 2 (two) layer m2 1.050 30,800 32,340
Roof mesh kg 3.000 32,725 98,175

- Remuneration
Carpenter man/day 0.050 120,000 6,000
Worker man/day 0.150 130,000 19,500
Foreman man/day 0.008 215,000 1,720
Carpenter chief man/day 0.005 157,500 788
158,523

An 27 Cat Kayu (2 lapis) m2 108,960


- Material
Plamur Kayu kg 0.200 25,300 5,060
Cat Dasar kg 0.150 25,300 3,795
Cat kayu Glotex kg 0.300 60,500 18,150
Kuas pc 0.050 27,500 1,375
Thinner liter 0.200 38,500 7,700
Amplas lmb 0.500 13,200 6,600

- Remuneration
Paint worker man/day 0.250 120,000 30,000
Worker man/day 0.250 130,000 32,500
Foreman man/day 0.001 215,000 280
Chief of paint worker man/day 0.025 140,000 3,500

An 28 Steel painting (4 layers manually) m2 82,934


- Material
-Naturally Paint (Meni) A kg 0.100 31,900 3,190
-Naturally Paint (Meni) B kg 0.100 33,000 3,300
Colour painting steel kg 0.080 118,800 9,504
Kuas pc 0.010 27,500 275
Thinner liter 0.010 38,500 385

- Remuneration
Paint worker man/day 0.250 120,000 30,000
Worker man/day 0.250 130,000 32,500
Foreman man/day 0.001 215,000 280
Chief of paint worker man/day 0.025 140,000 3,500
82,934

An 29 Wall painting (Emulsi) 1 x plamur, 3 x paint m2 23,985


- Material
Plamur kg 0.100 25,300 2,530
Naturally paint kg 0.100 31,900 3,190
Colour painting wall emulsi kg 0.260 25,300 6,578

- Remuneration
Paint Worker man/day 0.063 120,000 7,560
Worker man/day 0.020 130,000 2,600
Foreman man/day 0.003 215,000 645
Chief of paint worker man/day 0.006 140,000 882

An 30 Wall painting (weathershield) 1 x plamur, 3 x paint m2 46,121


- Material
Plamur kg 0.100 25,300 2,530
Naturally paint kg 0.100 31,900 3,190
Colour painting wall weathershield kg 0.260 110,440 28,714

- Remuneration
Paint Worker man/day 0.063 120,000 7,560
Worker man/day 0.020 130,000 2,600
Foreman man/day 0.003 215,000 645
Chief of paint worker man/day 0.006 140,000 882
46,121

An 31 Flintkote for waterproffing concrete roofing m2 51,837


- Material
Flintkote liter 0.500 80,300 40,150

- Remuneration
Paint Worker man/day 0.063 120,000 7,560
Worker man/day 0.020 130,000 2,600
Foreman man/day 0.003 215,000 645
Chief of paint worker man/day 0.006 140,000 882

An 32 Landscape Work m2 2,686,499


- Remuneration
Worker man/hour 0.044 130,000 5,655
Foreman man/hour 0.011 215,000 2,344

Material :
Pupuk kandang kering (1 karung = 7 kg) karung 1.000 22,000 22,000
Tanaman pohon
Pohon Mangga ukuran tinggi + 2 m unit 1.000 440,000 440,000
Tanaman Perdu (tanaman teh - tehan tinggi 25 - 35 cm) unit 25.000 88,000 2,200,000
Rumput Gajah Mini m2 1.000 16,500 16,500
2,686,499

An 33 INSTALLMENT ALL TYPE DOOR


Glass door (t=5mm) complete with aluminium frame and accessories: -
a. Type PJ1(single door+boven) 2600 x 2850 mm m2 7.410 1,650,000 12,226,500
a. Type P1(single door+boven) 2850 x 1700 mm m2 4.845 1,650,000 7,994,250
b. Type P2(double door+boven) 2850 x 1100 mm m2 3.135 1,650,000 5,172,750
c. Type P3 (Single fibre door) 2850 x 800 mm m2 2.280 1,650,000 3,762,000
d. Type P4 (Aluminium Door) 2150 x 700 mm m2 1.505 1,650,000 2,483,250
d. Type PB (Steel Galvanizing Door) 2700 x 2450 mm m2 6.615 1,650,000 10,914,750
Glass windows (t=5mm) & ventilation complete with aluminium frame and accessories:
a. Type boven (1 casement glass) total area 700 x 800 mm m2 0.560 1,650,000 924,000
b. Type J1 (2 casement glass ) total area 2650 x 2850 mm m2 7.553 1,650,000 12,461,625
c. Type J2 (2 window glass, 2 casement glass) total area 2100 x 600 mm m2 1.260 1,650,000 2,079,000
d. Type B1 (bovenlight, 2 fix glass) total area 1150 x 600 mm m2 0.690 1,650,000 1,138,500
e. Type B2 (bovenlight, 6 fix glass) total area 2250 x 600 mm m2 1.350 1,650,000 2,227,500
f. Type B3 (bovenlight, 4 fix glass) total area 2250 x 600 mm m2 1.350 1,650,000 2,227,500
g. Type B4 (bovenlight, 1 fix glass) total area 600 x 600 mm m2 0.360 1,650,000 594,000
f. Type V1 (boven, 2 fix glass) total area 1650 x 400 mm m2 0.660 1,650,000 1,089,000
Type V2 (2 alumunium louver) total area 1650 x 300 mm inc 0.495 600,000 297,000

An 34 Waterproofing m2 54,043

- Material
Waterproofing kg 0.350 80,300 28,105
Serat Fiber m2 1.000 9,900 9,900

- Remuneration
Worker man/day 0.050 130,000 6,500
Foreman man/day 0.003 215,000 538
Carpenter man/day 0.075 120,000 9,000
54,043

An 35 Floorhardener m2 276,542

- Material
Floorhardener kg 5.000 33,000 165,000
BBM ltr 0.313 13,805 4,314

- Equipment
Sewa Trowel unit/day 0.250 295,000 73,750

- Remuneration
Worker man/day 0.120 130,000 15,600
Foreman man/day 0.006 215,000 1,290
Brick Layer man/day 0.120 121,230 14,548
Brick layer Chief man/day 0.012 170,000 2,040
276,542

An 36 Closet-coupled with eco washer unit 3,795,112

- Material
Close-coupled unit 1.000 3,197,700 3,197,700
Jet Washer unit 1.000 291,500 291,500
Accessories 6% x price water closed ls 0.060 191,862 11,512

- Remuneration
Worker man/day 2.000 130,000 260,000
Foreman man/day 0.160 215,000 34,400
3,795,112
An 37 Lavatory basin unit 963,289

- Material
Lavatory unit 1.000 666,490 666,490
Accessories 6% x price water closed ls 0.060 39,989 2,399

- Remuneration
Worker man/day 2.000 130,000 260,000
Foreman man/day 0.160 215,000 34,400
963,289

An 38 Urinoir work unit 7,663,047


- Material
Urinoir unit 1.000 5,778,300 5,778,300
Portland Cement kg 6.000 1,320 7,920
Sand (Pasir Pasang) m3 0.010 258,742 2,587
Accessories 30% x price urinoir % 30.000 5,778,300 1,733,490

- Remuneration
Worker man/day 1.000 130,000 130,000
Foreman man/day 0.050 215,000 10,750
7,663,047

An 39 Wash basin unit 4,977,519


- Material
Portland Cement kg 6.000 1,320 7,920
Sand (Pasir Pasang) m3 0.010 258,742 2,587
Wastafel unit 1.000 4,730,000 4,730,000
Accessories 12% x price wastafel % 12.000 567,600 68,112

- Remuneration
Worker man/day 1.200 130,000 156,000
Foreman man/day 0.060 215,000 12,900
4,977,519

An 40 Sink Complete unit 4,977,519


- Material
Portland Cement kg 6.000 1,320 7,920
Sand (Pasir Pasang) m3 0.010 258,742 2,587
Sink unit 1.000 4,730,000 4,730,000
Accessories 12% x price wastafel % 12.000 567,600 68,112

- Remuneration
Worker man/day 1.200 130,000 156,000
Foreman man/day 0.060 215,000 12,900
4,977,519
Septictank cap 3 m3 (1 x 1.5 xh = 2 )m included infiltrate cap1 m3 (1 x 1 x 1)
An 41 unit 7,386,143
complete with PVC, palm fibre and sand stone
- Exavation Soil m3 4.000 150,905 603,620
- Half Brick 1 pc : 4 ps m2 19.000 136,131 2,586,487

- Material
Pipa PVC 4" stick 1.000 534,820 534,820
Pipa PVC 1" stick 0.250 70,840 17,710
Elbow 1" bh 1.000 99,000 99,000
seal tape bh 1.000 3,850 3,850
lem pipa kaleng 0.500 37,500 18,750
palm fibre kg 5.000 24,640 123,200
split (t=20cm) m3 1.000 577,500 577,500
lantai kerja K-100 m3 1.500 1,225,294 1,837,940
penutup septic tank K - 175 Fe = 100 m3 0.300 1,469,148 440,744

- Remuneration
Worker man/day 1.150 130,000 149,500
Brick Layer man/day 3.200 121,230 387,936
Brick Layer Chief man/day 0.016 170,000 2,720
Foreman man/day 0.011 215,000 2,365

An 42 Water tank and steel structures tower ( cap : 2 m3 ) and installation of pipe unit 14,185,271

- Material
Water torn Plastic Cap 2 m3 setara Penguin unit 1.000 3,575,000 3,575,000
Pipa PVC 1" stick 2.500 99,000 247,500
Elbow 1" unit 5.000 3,850 19,250
Knee 1" unit 5.000 37,500 187,500
seal tape unit 2.000 24,640 49,280
lem pipa kaleng 1.000 577,500 577,500
Steel angle L.50.50.5 kg 450.000 15,950 7,177,500
- Fondation work ( Conc K-300 ; Fe = 100 kg/m3 ; andformwork) m3 1.120 1,225,294 1,372,329
Soil Excavation m3 2.500 126,675 316,688
Back filling m3 1.500 80,150 120,225

- Remuneration
Worker man/day 2.000 130,000 260,000
Steel Worker man/day 1.000 100,000 100,000
Steel Worker Chief man/day 0.500 150,000 75,000
Foreman man/day 0.500 215,000 107,500
14,185,271
An 43 Tanam Rumput Gajah m2 17,957
- Excavation Soil m3 0.010 126,675 1,267

- Material
Supporting tools ls 0.100 15,000 1,500
Pupuk Kandang krg 0.040 22,000 880
Rumput gajah mini m2 0.500 16,500 8,250

- Remuneration
Worker man/day 0.040 130,000 5,200
Foreman man/day 0.004 215,000 860
17,957
An 44 Mild steel Framework for roofing m2 219,028
Mobillization ls 1.000 20,000 20,000
-
- Material -
Main truss C-75-75 m' 2.800 16,000 44,800
Roof bottom/Reng R 33-0,45 m' 5.100 9,000 45,900
Self drilling screw dia 6 x 20 mm (truss screw) bh 25.000 413 10,313
Self drilling screw dia 4 x 20 mm (roof bottom screw) bh 35.000 385 13,475
dynabolt dia 12 x 120 mm bh 1.000 2,970 2,970
-
- Remuneration -
Worker man/day 0.247 130,000 32,110
Foreman man/day 0.025 215,000 5,311
Steel Worker man/day 0.176 100,000 17,600
Steel Worker Chief man/day 0.117 150,000 17,550
-
- Tools -
Supporting tools (Genset/Bor Machine) ls 1.000 9,000 9,000
219,028
An 45 Alumunium framework + aqustic for plafond m2 184,465
-
- Material -
Profil Alumunium T m' 3.600 7,639 27,500
Kawat f 4 mm m' 0.150 37,224 5,584
Akustik t-9 bh 1.500 34,100 51,150
dynabolt dia 12 x 120 mm bh 1.050 2,970 3,119
-
- Remuneration -
Worker man/day 0.150 130,000 19,500
Foreman man/day 0.008 215,000 1,613
Carpenter man/day 0.500 120,000 60,000
Carpenter Chief man/day 0.050 140,000 7,000
-
- Tools -
Supporting tools (Genset/Bor Machine) ls 1.000 9,000 9,000
An

F. ROAD WORK
An 1 Road Work (Flexible Pavement) m2
a Base Structure, Consist of : m2 1.000
- Sub Base Coarse (Component Sand Gravel / Sirtu 300 mm thick)
- Base Coarse (Crush Stone 3/5, 250 mm thick)
b 50 mm Asphalt hotmix m2 1.000
c 50 mm Asphalt penetration m2 1.000

Road (New) m2
1 m2 Base Structure
Common Excavation m3 1.000
Back filling m3 1.000
- Sub Base Coarce
Comp. Sand gravel (sirtu) 300 mm thick m3 0.360
- Base Coarse
Crush stone 3 - 5, 250 mm thick m 3
0.263

- Remuneration

Worker man/day 0.675


Foreman man/day 0.063
Stomwalls operator man/day 0.024
An 2 Penetration Coarse thickness 5 cm (Lapisan makadam) m2 179,470
- Material
Asphalt hot 60/70 kg 7.000 10,450 73,150
Split 2/3 m3 0.050 577,500 28,875
Dust split m3 0.010 577,500 5,775
Split 1/2 m3 0.020 577,500 11,550
Firewood m3 0.009 170,000 1,530

- Remuneration

Worker man/day 0.360 130,000 46,800


Asphalt Worker man/day 0.060 120,000 7,200
Foreman man/day 0.018 215,000 3,870
Stomwalls operator hour 0.006 120,000 720
179,470

An 3 Wearing surface Hotmix 5 cm (AC-WC) m2 112,807


Material
Hot mix kg 7.000 4,000 28,000

Remuneration
Worker man/day 0.360 130,000 46,800
Worker Aspalt man/day 0.060 120,000 7,200
Foreman man/day 0.018 215,000 3,870
Stomwalls operator hour 0.006 120,000 720
-
Baby Roller hour 0.167 157,300 26,217

An 4 Asphalt hot mix with thickness 5 cm (include tack coat) m2 67,103


- Material
Asphalt pen 60/70 kg 54.000 10,450 564,300
Asphalt cair kg 54.000 10,450 564,300

- Remuneration
Worker man/hour 0.201 130,000 26,104
Operator man/hour 0.020 425,000 8,543

- Equipment
Dump Truck hour 0.370 330,000 122,034
Tandem Roller hour 0.014 157,300 2,124
Water Tanker hour 0.014 330,000 4,653
Alat Bantu Ls 1.000 50,000 50,000
1,342,057
67,103

An 5 Prepare compacted subgrade thickness 20 cm m2 191,759


- Material
Split 2/3 m3 1.259 577,500 726,842

- Remuneration
Worker man/day 0.050 130,000 6,448
Operator man/day 0.007 425,000 3,018

- Equipment
Dump Truck hour 0.502 330,000 165,726
Tandem Roller hour 0.013 157,300 2,108
Water Tanker hour 0.014 330,000 4,653
Alat Bantu Ls 1.000 50,000 50,000
1 m2 958,794
20 cm 191,759

An 6 Base structure with thickness 15 cm m2 143,819


- Material
Split 1/2 m 3
1.259 577,500 726,842

- Remuneration
Worker man/day 0.050 130,000 6,448
Operator man/day 0.007 425,000 3,018

- Equipment
Dump Truck hour 0.502 330,000 165,726
Tandem Roller hour 0.013 157,300 2,108
Water Tanker hour 0.014 330,000 4,653
Alat Bantu Ls 1.000 50,000 50,000
1 m2 958,794
15 cm 143,819
An 7 Macadam surface course thickness 20 cm m2 173,697
- Material
Crushed stone 3/4 cm m3 0.240 528,000 126,720
Dust split m3 0.010 577,500 5,775

- Remuneration
Worker man/day 0.300 130,000 39,000
Foreman man/day 0.010 157,300 1,573
Rent Stomwalls /stamper day 0.004 157,300 629
173,697
An 8 Perkerasan Jalan Beton m3 2,207,490
Remuneration
- Worker hour 1.406 130,000 182,728
- Brick Worker hour 0.703 120,000 84,336
- Foreman hour 0.151 157,300 23,689

Material
- Portland Cement (PC) kg 410.000 1,320 541,200
- Sand Urug m3 0.624 184,800 115,260
- Aggregat Kasar m3 0.789 577,500 455,359
- Baja Tulangan Polos kg 15.775 15,400 242,935
- Joint Sealant kg 0.956 37,510 35,871
- Cat Anti Karat kg 0.020 39,325 787
- Expansion Joint m2 0.170 6,655 1,131
- Polietilin 125 mikron kg 0.438 21,175 9,264
- Curing Compound Ltr 0.870 42,350 36,845
- Multiplex 12 mm Lbr 0.160 240,790 38,526
- Kayu Acuan m3 0.096 2,200,000 211,200
- Paku kg 1.024 13,750 14,080
- Additive Ltr 0.914 42,350 38,704
Tools
- Wheel Loader Hour 0.024 249,700 6,093
- Batching Plant Hour 0.050 542,592 27,238
- Truck Mixer Hour 0.244 412,500 100,526
- Concrete Vibrator Hour 0.050 528,000 26,506
- Water Tank Truck Hour 0.042 41,250 1,741
- Concrete Paver/Slipform Paver Hour 0.007 469,291 3,473
- Alat Bantu Ls 1.000 10,000 10,000

An 9 Perkerasan Beton Semen dengan Anyaman Tulangan Tunggal m3 3,547,245


Remuneration
- Worker hour 1.406 130,000 182,728
- Brick Worker hour 0.703 120,000 84,336
- Foreman hour 0.151 157,300 23,689

Material
- Portland Cement (PC) kg 410.000 1,320 541,200
- Sand m3 0.624 184,800 115,260
- Aggregat Kasar m3 0.789 577,500 455,359
- Baja Wiremesh M10 kg 28.377 15,400
- Baja Tulangan Polos/dowel D32 kg 16.169 37,510 606,514
- Joint Sealant kg 0.956 39,325 37,606
- Cat Anti Karat kg 0.020 6,655 133
- Expansion Joint m2 0.170 21,175 3,600
- Polietilin 125 mikron kg 0.328 42,350 13,895
- Curing Compound Ltr 0.653 240,790 157,115
- Multiplex 12 mm m2 0.570 2,200,000 1,254,000
- Paku kg 0.350 13,750 4,813
- Additive Ltr 0.857 42,350 36,285

Tools
- Wheel Loader Hour 0.024 -
- Batching Plant Hour 0.050 542,592 27,238
- Truck Mixer Hour 0.195 -
- Concrete Vibrator Hour 0.050 -
- Water Tank Truck Hour 0.042 -
- Concrete Paver/Slipform Paver Hour 0.007 469,291 3,473
- Alat Bantu Ls 1.000 -

An 10 Lapis Resap Pengikat - Aspal Cair Ltr #REF!


Remuneration
- Worker hour 0.0021 #REF! #REF!
- Foreman hour 0.0004 #REF! #REF!

Material
- Aspal kg 0.6790 7,040 4,780
- Kerosene m3 0.3700 1,815 672

Tools
- Aspal Distributor Hour 0.0002 271,340 54
- Compressor Hour 0.0002 117,579 24

An 11 Kerbs (10x20x60 cm) m' 149,704


- Kerb concrete K-175 pcs 1.670 77,000 128,590
- Plaster 1 PC : 4 PS m2 0.045 94,534 4,254
- Compacted sand t = 10 cm m2 0.400 39,064 15,626
- Common excavation m3 0.012 102,875 1,235

An 12 Kerbs (25x30x50 cm) m' 172,618

- Kerb concrete K-175 pcs 2.000 77,000 154,000


- Plaster 1 PC : 4 PS m2 0.045 39,064 1,758
- Compacted sand t = 10 cm m2 0.400 39,064 15,626
- Common excavation m3 0.012 102,875 1,235
172,618

G. CABEL FOR SWITCHYARD


An 1 Cable Trench Type 1 (1000x1000) m' 1,993,099

- Excavation of soil m3 1.500 126,675 190,013


- Backfilling m3 1.500 80,150 120,225
- Compacted sand layer m3 0.120 390,640 46,877
- Lean concrete K100 m3 0.060 1,225,294 73,518
- Reinforced Concrete Grade 225 Fe 100 for trench m3 0.340 3,368,332.18 1,145,233
- Reinforced Concrete Grade 225 Fe 100 for cover m3 0.096 3,368,332 323,360
- L.50.50.5 m 1.000 15,950 15,950
- PVC pipe 1 in m 1.100 70,840 77,924
1,993,099
An 2 Cable Tray Type 1 m' 332,038
- Material
Steel L50x50x5 for Cable Tray kg 10.614 15,950 169,293
Dyna Bolt M20 bh 6.000 8,800 52,800

- Equipment
Bor Machine unit/hour 0.080 379,500 30,360
Welding Machine unit/hour 0.050 544,500 27,225
Tools ls 1.000 20,000 20,000
-
- Remuneration -
Steel Worker man/day 0.300 100,000 30,000
Chief of Steel Worker man/day 0.010 150,000 1,500
Foreman man/day 0.004 215,000 860
332,038

An 3 Cable Trench Type 2 (800x800) m' 1,522,919

- Excavation of soil m3 1.050 126,675 133,009


- Backfilling m3 1.050 80,150 84,158
- Compacted sand layer m3 0.100 390,640 39,064
- Lean concrete K100 m3 0.050 1,225,294 61,265
- Reinforced Concrete Grade 175, Fe 100 for trench m3 0.250 3,368,332 842,083
- Reinforced Concrete Grade 175, Fe 100 for cover m3 0.080 3,368,332 269,467
- L.50.50.5 m 1.000 15,950 15,950
- PVC pipe 1 in m 1.100 70,840 77,924
1,522,919
An 4 Cable Trench (600x600x1200) m' 1,349,926

- Excavation of soil m 3
0.768 126,675 97,286
- Backfilling m3 0.768 80,150 61,555
- Compacted sand layer m3 0.120 390,640 46,877
- Lean concrete K100 m3 0.060 1,225,294 73,518
- Reinforced Concrete Grade 225, Fe 100 for trench m3 0.230 3,368,332 774,716
- Reinforced Concrete Grade 225, Fe 100 for cover m3 0.060 3,368,332 202,100
- L.50.50.5 m 1.000 15,950 15,950
- PVC pipe 1 in m 1.100 70,840 77,924
1,349,926
An 5 Cable Trench (400x400x1200) m' 1,028,695

- Excavation of soil m3 0.192 126,675 24,322


- Backfilling m3 0.192 80,150 15,389
- Compacted sand layer m3 0.120 390,640 46,877
- Lean concrete K100 m3 0.060 1,225,294 73,518
- Reinforced Concrete Grade 225, Fe 100 for trench m3 0.190 3,368,332 639,983
- Reinforced Concrete Grade 225, Fe 100 for cover m3 0.040 3,368,332 134,733
- L.50.50.5 m 1.000 15,950 15,950
- PVC pipe 1 in m 1.100 70,840 77,924
1,028,695
An 6 Cable Tray Type 2 m' 329,263
- Material
Steel L50x50x5 for Cable Tray kg 10.440 15,950 166,518
- Dyna Bolt M20 bh 6.000 8,800 52,800

- Equipment
Bor Machine unit/hour 0.080 379,500 30,360
Welding Machine unit/hour 0.050 544,500 27,225
Tools ls 1.000 20,000 20,000

- Remuneration
Steel Worker man/day 0.300 100,000 30,000
Chief of Steel Worker man/day 0.010 150,000 1,500
Foreman man/day 0.004 215,000 860
329,263

An 7 Cable Trench Type 3 (500x500) without tray m' 993,700

- Excavation of soil m 3
0.525 126,675 66,504
- Backfilling m3 0.525 80,150 42,079
- Compacted sand layer m3 0.070 390,640 27,345
- Lean concrete K100 m3 0.035 1,225,294 42,885
- Reinforced Concrete Grade 175 Fe 100 for trench m3 0.190 3,312,546.09 629,384
- Reinforced Concrete Grade 175 Fe 100 for cover kg 0.056 3,312,546 185,503
993,700

An 8 Cable Trench Type 4 (500x350) without tray m' 865,944

- Excavation of soil m3 0.413 126,675 52,253


- Backfilling m3 0.413 80,150 33,062
- Compacted sand layer m3 0.055 390,640 21,485
- Lean concrete K100 m3 0.028 1,225,294 33,696
- Reinforced Concrete Grade 175 Fe 100 for trench m3 0.175 3,312,546 579,696
- Reinforced Concrete Grade 175 Fe 100 for cover kg 0.044 3,312,546 145,752
865,944

An 9 Cable Trench Crossing Road Type 1 (1000x1000) m' 3,898,775


- Remuneration
Worker man/day 0.900 130,000 30,876
Foreman man/day 0.045 215,000 1,579

- Excavation of soil m3 1.500 126,675 190,013


- Backfilling m3 1.500 80,150 120,225
- Compacted sand layer m3 0.120 390,640 46,877
- Lean concrete K100 m3 0.060 1,225,294 73,518
- U-Ditch 1000/1000 (panjang 1.2 m) unit 0.800 1,881,000 1,504,800
- U-Ditch Cover 1000 (panjang 0.6 m) unit 1.700 940,500 1,598,850
- Steel L50x50x5 for cable tray large m' 1.000 332,038 332,038

3,898,775

An 10 Cable Trench Crossing Road Type 2 (800x800) m' 2,807,353


- Remuneration
Worker man/day 0.900 130,000 30,876
Foreman man/day 0.045 215,000 1,579

- Excavation of soil m3 1.050 126,675 133,009


- Backfilling m3 1.050 80,150 84,158
- Compacted sand layer m3 0.100 390,640 39,064
- Lean concrete K100 m3 0.050 1,225,294 61,265
- U-Ditch 800/800 (panjang 1.2 m) unit 0.800 1,288,100 1,030,480
- U-Ditch Cover 800 (panjang 0.6 m) unit 1.700 644,050 1,094,885
- Steel L50x50x5 for cable tray large m' 1.000 332,038 332,038
` 2,807,353

F. FOR CABLE TRENCH 20 kV CONTROL BUILDING ROOM


An 1 Cable Trench Type I (20 kV Room) m' 19,145,202

Excavation of soil m 3
3.704 126,675 469,141
Backfilling m3 2.160 80,150 173,124
Compacted sand layer m3 0.255 390,640 99,613
Lean concrete K100 m3 0.128 1,225,294 156,225
Reinforced Concrete Grade 175/ Fe 100 m3 1.161 3,312,546 3,845,866
Steel L50x50x5 kg 37.800 332,038 12,551,048
Plat Bordes 6 mm kg 97.420 18,992 1,850,185
19,145,202

An 2 Cable Trench Type II m' 7,260,583

Excavation of soil m3 1.470 126,675 186,212


Backfilling m3 1.010 80,150 80,952
Compacted sand layer m3 0.120 390,640 46,877
Lean concrete K100 m3 0.060 1,225,294 73,518
Reinforced Concrete Grade 175/20 m3 0.280 3,312,546 927,513
Steel L50x50x5 kg 15.120 332,038 5,020,419
Plat Bordes 6 mm kg 48.710 18,992 925,093

An 3 Cable Trench Type III m' 5,464,316

Excavation of soil m 3
0.850 126,675 107,674
Backfilling m3 0.530 80,150 42,480
Compacted sand layer m3 0.080 390,640 31,251
Lean concrete K100 m3 0.040 1,225,294 49,012
Reinforced Concrete Grade 175/20 m3 0.200 3,312,546 662,509
Steel L50x50x5 kg 12.096 332,038 4,016,335
Plat Bordes 6 mm kg 29.226 18,992 555,056
5,464,316
An 4 Cable Trench Type IV m' 6,210,111

Excavation of soil m3 0.935 126,675 118,441


Backfilling m3 0.590 80,150 47,289
Compacted sand layer m3 0.090 390,640 35,158
Lean concrete K100 m3 0.045 1,225,294 55,138
Reinforced Concrete Grade 175/20 m3 0.210 3,312,546 695,635
Steel L50x50x5 kg 13.608 332,038 4,518,377
Plat Bordes 6 mm kg 38.968 18,992 740,074
6,210,111
An 5 Cable Trench Type V m' 4,637,963

Excavation of soil m3 0.637 126,675 80,692


Backfilling m3 0.371 80,150 29,736
Compacted sand layer m3 0.060 390,640 23,438
Lean concrete K100 m3 0.030 1,225,294 36,759
Reinforced Concrete Grade 175/20 m3 0.176 3,312,546 583,008
Steel L50x50x5 kg 10.584 332,038 3,514,293
Plat Bordes 6 mm kg 19.484 18,992 370,037
4,637,963
An 11 Cable Trench Type I (800 x 800) 150 kV Room m' 4,447,009

- Equipment
Bor Machine unit/hour 0.080 379,500 30,360
Welding Machine unit/hour 0.050 544,500 27,225
Tools ls 1.000 20,000 20,000

- Remuneration
Steel Worker man/day 0.300 100,000 30,000
Chief of Steel Worker man/day 0.010 150,000 1,500
Foreman man/day 0.004 215,000 860

Excavation of soil m3 1.050 126,675 133,009


Backfilling m3 1.050 80,150 84,158
Compacted sand layer m3 0.100 390,640 39,064
Lean concrete K100 m3 0.050 1,225,294 61,265
Reinforced Concrete Grade 175 Fe 100 m3 0.250 3,312,546 828,137
Steel L50x50x5 kg 7.202 332,038 2,391,340
Plat Bordes 6 mm kg 37.680 18,992 715,613
Dyna Bolt bh 12.000 7,040 84,480
4,447,009

An 12 Cable Trench Type II (500 x 500) 150 kV Room m' 2,893,108

- Equipment
Bor Machine unit/hour 0.080 379,500 30,360
Welding Machine unit/hour 0.050 544,500 27,225
Tools ls 1.000 20,000 20,000

- Remuneration
Steel Worker man/day 0.300 100,000 30,000
Chief of Steel Worker man/day 0.010 150,000 1,500
Foreman man/day 0.004 215,000 860

Excavation of soil m3 0.525 126,675 66,504


Backfilling m3 0.525 80,150 42,079
Compacted sand layer m3 0.070 390,640 27,345
Lean concrete K100 m3 0.035 1,225,294 42,885
Reinforced Concrete Grade 175 Fe 100 m3 0.190 3,312,546 629,384
Steel L50x50x5 kg 4.601 332,038 1,527,708
Plat Bordes 6 mm kg 23.550 18,992 447,258
Dyna Bolt bh 6.000 7,040 42,240
2,893,108

An 13 Open Drainage (stone masonry) 40/70 cm m' 1,121,755

Excavation of soil m3 1.330 126,675 168,478


Backfilling m3 0.560 80,150 44,884
Compacted sand layer m3 0.080 390,640 31,251
Plaster cement 1:4 m3 2.440 94,534 230,664
Stone Masonry 1 PC : 3 Sand m3 0.450 1,436,618 646,478
1,121,755

An 14 Open Drainage (brick) 30/40 cm m' 550,346

Excavation of soil m3 0.600 126,675 76,005


Backfilling m3 0.370 80,150 29,656
Compacted sand layer m3 0.060 390,640 23,438
Plaster cement 1:4 m3 2.440 94,534 230,664
Brick 1 pc : 4 ps m3 1.400 136,131 190,583
550,346

An 15 Sub Soil Drainage m' 606,661

Excavation of soil m3 0.700 126,675 88,673


Backfilling m3 0.200 80,150 16,030
Compacted sand layer m3 0.200 390,640 78,128
Pipe Concrete Ø 30 cm m' 1.000 69,630 69,630
Palm Fibre kg 5.000 24,640 123,200
Gravel m3 0.400 577,500 231,000
606,661
An 16 Control Box (Brick 60x60x65 cm) Unit 994,326

- Material
Brick pc 123.000 770 94,710
Portland cement (PC) kg 114.000 1,320 150,480
Sand (Pasir Pasang) m3 0.184 258,742 47,609
Concrete Sand (Pasir Beton) m3 0.120 258,750 31,050
Split 2/3 m3 0.033 577,500 19,058
Reinforced Concrete BJTP-24 kg 4.850 18,992 92,110

- Remuneration
Brick layer man/day 1.150 120,000 138,000
Worker man/day 3.200 130,000 416,000
Foreman man/day 0.016 215,000 3,440
Brick layer chief man/day 0.011 170,000 1,870
994,326
An
H. INSTALLATION WORK
An 1 Erection Gabion (Tipe B kawat uk. L=3m, B=1m, T=1m) m3 14,104,938
Material
- Crushed Stone m3 4.200 528,000 2,217,600
- Galvanised Wire Mash dia 2,7 mm Kg 31.358 341,000 10,693,078

Remuneration
- Worker (Pengisi Batu) man/day 2.100 130,000 273,000
- Worker (Pekerja Penganyam) man/day 4.740 130,000 616,200
- Foreman man/day 0.684 215,000 147,060
- Steel Worker (Tukang Penganyam) man/day 1.580 100,000 158,000
14,104,938

An 2 Fence BRC height 1.90 m m' 2,145,715


Material
- BRC height 1.90 m m 1.000 877,800 877,800
- Steel pipe dia 2 inc and clamp m 1.330 156,316 207,900
- Barbed wire kg 7.628 18,700 142,644
- Foundation 0.3 x 0.3 m2 reinforced concrete K 175; m3 0.080 3,553,768 284,301
Fe : 100 kg/m3
- Sloof 20/30 reinforced concrete K 175; m3 0.030 3,553,768 106,613
Fe : 100 kg/m3

Remuneration
- Excavation of Soil m3 2.250 126,675 285,019
- Back Filling m3 1.500 80,150 120,225
- Erection of Fence ls 1.000 121,213 121,213
2,145,715
An 3 Fence BRC height 1.50 m m' 1,677,761
Material
- BRC height 1.50 m m 1.000 577,500 577,500
- Steel pipe dia 2 inc and clamp m 1.170 156,316 182,889
- Foundation 0.30 x 0.30 m2 reinforced concrete K 175; m3 0.080 3,553,768 284,301
Fe : 100 kg/m3
- Sloof 20/30 reinforced concrete K 175; m3 0.030 3,553,768 106,613
Fe : 100 kg/m3

Remuneration
- Excavation of Soil m3 2.250 126,675 285,019
- Back Filling m3 1.500 80,150 120,225
- Erection of Fence ls 1.000 121,213 121,213
1,677,761
An 4 Fence Galvanized Wire Mesh height 2.00 m m' 898,102
Material
- Galvanized Wire Mesh height 2.00 m m 1.000 22,300 22,300
- Galvanized steel angle 40.40.5 kg 10.692 12,266 131,148
- Strip plat 20.3 kg 1.685 13,500 22,745
- Foundation 0,80x0,80 m2 reinforced concrete K 175; m3 0.120 3,553,768 426,452
Fe : 100 kg/m3
- Sloof 20/30 reinforced concrete K 175; m3 0.030 3,553,768 106,613
Fe : 100 kg/m3

Remuneration
- Excavation of Soil m3 0.420 126,675 53,204
- Back Filling m3 0.180 80,150 14,427
- Erection of Fence ls 1.000 121,213 121,213
898,102

An 5 Sliding Gate BRC height 1.50 m wide 6.3 m Unit 8,389,873


Material
- BRC height 1.50 m m 6.300 577,500 3,638,250
- Steel pipe dia 3 inc m 3.200 156,316 500,211
- Pipe of support dia 2 inc and clamp m 20.340 156,316 3,179,463
- Foundation 0.3 x 0.3 m2 reinforced concrete K 175; m3 0.090 3,553,768 319,839
Fe : 100 kg/m3
- Colom 30/60 reinforced concrete K 175; m3 0.090 3,553,768 319,839
Fe : 100 kg/m3

Remuneration
- Excavation of Soil m3 2.000 126,675 253,350
- Back Filling m3 0.720 80,150 57,708
- Erection of Gate ls 1.000 121,213 121,213
8,389,873

An 6 Fence from Concrete height 2.00 m m' 5,482,415


Material
- Concrete height 2.00 m m3 0.200 3,553,768 710,754
(K 175; Fe : 100 kg/m3)
- Foundation 1,50x1,50 m2 reinforced concrete K 175; m3 0.450 3,553,768 1,599,196
Fe : 120 kg/m3
- Colom 30/50 rinforced concrete K 175; m3 0.640 3,553,768 2,274,412
Fe : 120 kg/m3
- Sloof 30/40 reinforced concrete K 175; m3 0.060 3,553,768 213,226
Fe : 120 kg/m3

Remuneration
- Excavation of Soil m3 3.380 126,675 428,162
- Back Filling m3 1.690 80,150 135,454
- Erection of Fence ls 1.000 121,213 121,213
5,482,415

An 7 Fence from Brick Wall height 2.40 m (lower) and barbed wire 0,60 m (upper) m' 4,550,519
Material
- Brick 1pc : 4ps m3 0.720 136,131 98,014
- Plaster cement 1 pc : 4 ps thickness 10 mm m2 4.800 94,534 453,765
- Foundation 1,00x1,00 m2 reinforced concrete K 175; m3 0.300 3,553,768 1,066,130
Fe : 120 kg/m3
- Colom 20/30 reinforced concrete K 175; m3 0.300 3,553,768 1,066,130
Fe : 120 kg/m3
- Sloof 20/30 reinforced concrete K 175; m3 0.300 3,553,768 1,066,130
Fe : 120 kg/m3
- Galvanized steel angle 40.40.5 kg 5.346 17,600 94,090
- Barbed wire kg 7.628 18,700 142,644

Remuneration
- Excavation of Soil m3 3.380 126,675 428,162
- Back Filling m3 1.690 80,150 135,454
4,550,519

An 8 Listplank Superplank (GRC board) m' 108,797

- Material
listplank Superplank (GRC board) m' 1.100 60,179 66,197
Nail kg 0.100 13,750 1,375

- Remuneration
Worker man/day 0.100 130,000 13,000
Foreman man/day 0.005 215,000 1,075
Carpenter man/day 0.200 120,000 24,000
Carpenter chief man/day 0.020 157,500 3,150
108,797

An 9 Profil complete with connection and steel painting Kg 57,082

- Material
Profil Channel kg 1.150 15,950 18,343
Steel painting kg 0.080 118,800 9,504

- Remuneration
Worker man/day 0.060 130,000 7,800
Foreman man/day 0.003 215,000 645
Welder man/day 0.060 150,000 9,000
Welder chief man/day 0.006 150,000 900

- Equipment
Welding Machine unit/day 0.020 544,500 10,890
57,082

An 10 Wind Bracing and Tie Rod with connection and steel painting Kg 35,659

- Material
Wind Bracing kg 1.150 15,400 17,710
Steel painting kg 0.080 118,800 9,504

- Remuneration
Worker man/day 0.060 130,000 7,800
Foreman man/day 0.003 215,000 645

35,659

An 11 Raised Floor m2 1,004,300


- Material
Raised Floor m2 1.000 924,000 924,000

-Remuneration
-Worker man/day 0.400 130,000 52,000
-Brick Layer man/day 0.200 120,000 24,000
-Foreman man/day 0.020 215,000 4,300
1,004,300

An 12 Pipa Resapan PVC 2" Untuk Dinding Penahan Tanah m' 24,201
-Remuneration
Worker man/day 0.010 130,000 1,300
- Foreman man-day 0.005 120,000 600

-Material
PVC Pipe dia 2" stick 0.125 176,440 22,055
Ijuk Kg 0.010 24,640 246

An 13 Water Supply PVC Pipe (include installation) m' 278,735


-Remuneration
Worker man/day 0.900 130,000 117,000
Foreman man/day 0.045 120,000 5,400

- Equipment
Sewa peralatan (Auger, Kunci Inggris, Pipa besi) unit/day 0.050 50,500 2,525

-Material
PVC Pipe dia 4 " stick 0.250 534,820 133,705
PVC Pipe dia 1" stick 0.250 70,840 17,710
Knee bh 0.250 3,500 875
-Pipe Tape bh 0.200 3,850 770
-Lem Pipa klg 0.020 37,500 750
278,735

An 14 Water Supply PVC Pipe 1/2" (include installation) m' 139,128


-Remuneration
Worker man/day 0.900 130,000 117,000
Foreman man/day 0.045 120,000 5,400

- Equipment
Sewa peralatan (Auger, Kunci Inggris, Pipa besi) unit/day 0.050 50,500 2,525
-Material
PVC Pipe dia 1./2" stick 0.250 40,590 10,148
elbow dia 1./2" bh 0.250 8,140 2,035
Knee dia 1./2" bh 0.250 2,000 500
-Pipe Tape bh 0.200 3,850 770
-Lem Pipa klg 0.020 37,500 750
139,128

An 15 Water Supply PVC Pipe 1" (include installation) m' 148,055


-Remuneration
Worker man/day 0.900 130,000 117,000
Foreman man/day 0.045 120,000 5,400

- Equipment
Sewa peralatan (Auger, Kunci Inggris, Pipa besi) unit/day 0.050 50,500 2,525

-Material
PVC Pipe dia 1" stick 0.250 70,840 17,710
elbow dia 1" bh 0.250 12,100 3,025
Knee dia 1" bh 0.250 3,500 875
-Pipe Tape bh 0.200 3,850 770
-Lem Pipa klg 0.020 37,500 750
148,055

An 16 Water Supply PVC Pipe 2" (include installation) m' 199,430


-Remuneration
Worker man/day 0.900 130,000 117,000
Foreman man/day 0.045 120,000 5,400

- Equipment
Sewa peralatan (Auger, Kunci Inggris, Pipa besi) unit/day 0.050 50,500 2,525

-Material
PVC Pipe dia 2" stick 0.250 176,440 44,110
elbow dia 2" bh 0.250 99,000 24,750
Knee dia 2" bh 0.250 16,500 4,125
-Pipe Tape bh 0.200 3,850 770
-Lem Pipa klg 0.020 37,500 750
199,430
An 17 Water Supply PVC Pipe 3" (include installation) m' 269,390
-Remuneration
Worker man/day 0.900 130,000 117,000
Foreman man/day 0.045 120,000 5,400

- Equipment
Sewa peralatan (Auger, Kunci Inggris, Pipa besi) unit/day 0.050 50,500 2,525

-Material
PVC Pipe dia 3" stick 0.250 345,950 86,488
elbow dia 3" bh 0.250 188,100 47,025
Knee dia 3" bh 0.250 37,730 9,433
-Pipe Tape bh 0.200 3,850 770
-Lem Pipa klg 0.020 37,500 750
269,390
An 18 Water Supply PVC Pipe 4" (include installation) m' 389,455
-Remuneration
Worker man/day 0.900 130,000 117,000
Foreman man/day 0.045 120,000 5,400

- Equipment
Sewa peralatan (Auger, Kunci Inggris, Pipa besi) unit/day 0.050 50,500 2,525

-Material
PVC Pipe dia 4" stick 0.250 534,820 133,705
elbow dia 4" bh 0.250 446,600 111,650
Knee dia 4" bh 0.250 70,620 17,655
-Pipe Tape bh 0.200 3,850 770
-Lem Pipa klg 0.020 37,500 750
389,455
An 19 Water Supply Pipe Medium Pipe 2" (include installation) m' 369,325
-Remuneration
Worker man/day 0.900 130,000 117,000
Foreman man/day 0.045 120,000 5,400

- Equipment
Sewa peralatan (Auger, Kunci Inggris, Pipa besi) unit/day 0.050 50,500 2,525

-Material
-GIP Medium Pipe dia 2" stick 0.250 809,600 202,400
Accessories GIP medium Pipe dia 2 " bh 0.250 161,920 40,480
-Pipe Tape bh 0.200 3,850 770
-Lem Pipa klg 0.020 37,500 750
369,325
An 20 Sewa Buldozer (100 - 150 HP) Jam 1,323,941
- Sewa alat unit/hour 1.000 770,000 770,000
- Bahan bakar liter 19.950 13,805 275,410
- Pelumas liter 3.990 31,900 127,281
- Biaya Bengkel ls 1.000 28,125 28,125
- BiayaPerawatan ls 1.000 56,250 56,250
-Operator man/hour 0.125 425,000 53,125
-Pembantu Operator man/hour 0.125 110,000 13,750
1,323,941

An 21 Pemasangan Mercury Vapour Flouresent Light 1 x 250 W + Tiang 9 m Unit 17,555,253


- Remuneration
Instalator man/day 3.333 175,000 583,275
Foreman man/day 0.333 120,000 39,960

Material :
Tiang Lampu Octagonal tinggi 9 m (3 - 4.5 m), desain diameter per segmen 2.5" -
5", flandes 30 x 30 x 1.4 cm, ornamen 1.5" x 2 meter, anti clim 1 set, Hot Deep unit 1.000 4,730,000 4,730,000
Galvanized
Lampu Phillips HPL/N (Mercury) 250 Watt unit 1.000 1,466,300 1,466,300
Kabel NYM 3x2,5MM @100M m 0.150 1,133,000 169,950
Accessories ( fuse box, grounding system and installation of cable conduit and
wiring and all accessories ) set 1.000 10,000,000 10,000,000

Excavation Soil m3 0.045 102,875 4,629


Concrete K-175 m3 0.045 1,225,294 55,138
Angkur Bolt 24 mm pcs 4.000 126,500 506,000

An 22 Pemasangan Mercury Vapour Flouresent Light 1 x 150 W for Access Road Unit 7,371,485
Remuneration
Instalator man/day 3.333 175,000 583,275
Foreman man/day 0.333 120,000 39,960

Material :
Lampu Jalan Model Cobra Starlight untuk Lampu Mercury HPL-N 250 Watt atau HPI-T
250 Watt - 400 Watt, bisa untuk SON-T 150 Watt - 400 Watt. Terbuat dari Bahan unit 1.000 660,000 660,000
Almunium Cor.Octagonal tinggi 6 m (3 - 4.5 m), desain diameter per segmen 2,5"-4",
Tiang Lampu
flandes 30 x 30 x 1.4 cm, ornamen 1.5" x 2 meter, anti clim 1 set, Hot Deep unit 1.000 2,750,000 2,750,000
Galvanized
Lampu Phillips SON-T (Mercury) 150 Watt unit 1.000 168,300 168,300
Kabel NYM 3x2,5MM @100M m 0.150 1,133,000 169,950
Accessories ( fuse box, grounding system and installation of cable conduit and
wiring and all accessories ) set 1.000 3,000,000 3,000,000
7,371,485
An 23 Pondasi Tiang Besi 9 meter Unit 380,721
- Galian Tanah biasa m3 0.600 150,905 90,543
- Pemadatan Sirtu m3 0.600 390,640 234,384
- Beton K-225 m3 0.030 1,469,148 44,074
- Urugan Pasir m3 0.030 390,640 11,719

380,721

An 24 Pemasangan Mercury Vapour Flouresent Light 1 x 250 W Unit 11,511,375


- Remuneration
Instalator man/day 3.333 175,000 583,275
Foreman man/day 0.333 120,000 39,960
-
Material : -
Lampu Jalan Model Cobra Starlight untuk Lampu Mercury HPL-N 250 Watt atau HPI-T 2 unit 1.000 660,000 660,000
Lampu Phillips HPL/N (Mercury) 250 Watt unit 1.000 58,190 58,190
Kabel NYM 3x2,5MM @100M m 0.150 1,133,000 169,950
Accessories ( fuse box, grounding system and installation of cable conduit and
wiring and all accessories ) set 1.000 10,000,000 10,000,000
11,511,375

An 25 Pemasangan Mercury Vapour Flouresent Light 1 x 80 W + Tiang 2 m Unit 10,924,478


- Remuneration
Instalator man/day 3.333 139,574 465,200
Foreman man/day 0.333 157,901 52,581

Material :
Kap Lampu Jalan Setara PJU Philips SPP 165, untuk SON-T 70 Watt unit 1.000 880,000 880,000
-4", flandes 30 x 30 x 1.4 cm, ornamen 1.5" x 2 meter, anti clim 1 set, Hot Deep
Galvanized unit 1.000 2,500,000 2,500,000
Lampu Setara Phillips SON 70 W E27 unit 1.000 190,080 190,080
Kabel NYM 3x2,5MM @100M m 0.150 1,133,000 169,950
Accessories ( fuse box, grounding system and installation of cable conduit and wiring set 1.000 6,666,667 6,666,667

An 26 Pondasi Tiang Besi 2 meter Unit 886,721


- Galian Tanah biasa m3 0.600 150,905 90,543
- Pemadatan Sirtu m3 0.600 390,640 234,384
- Beton K-225 m3 0.030 1,469,148 44,074
- Urugan Pasir m3 0.030 390,640 11,719
Angkur Bolt 24 mm pcs 4.000 126,500 506,000

An 27 Water tank and steel structures tower ( cap : 2 m3 ) and installation of pipe Unit 25,584,394
- Material
Water Torn Plastic Cap 2m3 setara Penguin bh 1.000 3,575,000 3,575,000
Pipa PVC 1" stick 2.500 3,575,000 8,937,500
elbow 1" bh 5.000 12,100 60,500
knee 1" bh 5.000 3,500 17,500
seal tape bh 2.000 3,850 7,700
lem pipa kaleng 1.000 37,500 37,500
besi siku L 50.50.5 kg 450.000 15,950 7,177,500
Foundation work (concrete f'c = 26.4 MPa (K 300), Fe : 150 kg/m3, Formwork) m3 1.120 4,831,424 5,411,194

- Remuneration
Worker man/day 2.000 130,000 260,000
Steel Worker man/day 1.000 100,000 100,000

An 28 Bak penampungan air dari beton bertulang Cap 12 m3 Unit 24,642,223


- Material
Excavation 3 m m3 12.000 150,905 1,810,860
Concrete K-175 m3 3.840 1,413,362 5,427,310
Besi U24 (150 kg/m3) kg 576.000 18,992 10,939,300
Formwork m2 26.800 241,222 6,464,752

An 29 Deepwell including submersible water pump 150 lt/m capacity and accessories Unit 42,866,808
- Material
Submersible water pump 150 ltr/minutes bh 1.000 28,880,280 28,880,280
Pipa PVC 3" m' 30.000 345,950 10,378,500
Accessories water pump ls 1.000 2,888,028 2,888,028

- Remuneration
Worker man/day 4.000 130,000 520,000
Steel Worker man/day 2.000 100,000 200,000
42,866,808
An 30 Instalasi Listrik Titik 213,050
- Remuneration
Worker man/day 0.375 130,000 48,750
Technician Electrical man/day 0.125 175,000 21,875

- Equipment
Tools (tang kabel, selotip, test pen, multitester) lot 1.000 25,000 25,000

- Material
Kabel NYM 3x2,5MM @100M roll 0.100 1,133,000 113,300
Clamp kabel beton 4-10 mm pack 0.500 8,250 4,125
213,050

An 31 Bath basin (fiber) installment Unit 956,625


- Material
Bath basin Fiber unit 1.000 831,600 831,600
Portland Cement (PC) kg 9.600 1,320 12,672
Sand (Pasir Pasang) m3 0.045 258,742 11,643
Colour Cement (PC) kg 1.500 33,660 50,490

- Remuneration
Brick layer man/day 0.120 120,000 14,400
Worker man/day 0.240 130,000 31,200
Foreman man/day 0.012 215,000 2,580
Brick layer chief man/day 0.012 170,000 2,040
956,625

An 32 PVC 3" work for roof (include installation) m' 274,770


-Remuneration
Worker man/day 0.900 130,000 117,000
Foreman man/day 0.045 215,000 9,675

-Material
PVC Pipe dia 3" stick 0.250 345,950 86,488
elbow dia 3" bh 0.250 188,100 47,025
Knee dia 3" bh 0.250 37,730 9,433
-Pipe Tape bh 0.200 3,850 770
-Lem Pipa klg 0.020 37,500 750
-Clamp Pipa unit 0.200 18,150 3,630
274,770

An 33 Instalasi Anti Petir, 150 kV Room Lot 18,779,940


Remuneration
Worker man/day 4.000 130,000 520,000
Technician Electrical man/day 1.000 563,940 563,940

Equipment
Tools (martil, mesin bor, tang kabel, selotip, test pen, multitester) lot 1.000 200,000 200,000

Material
Tiang splitzen 1/2' ; 50-60 cm unit 50.000 192,000 9,600,000
Kabel BC 25 m' 100.000 24,600 2,460,000
Clamp kabel / skun kabel unit 10.000 33,600 336,000
Cooper rod/pentanahan m' 4.000 1,200,000 4,800,000
Control box, brick 60x60 cm2 m3 2.000 150,000 300,000

18,779,940

An 34 Instalasi Antipetir 20 kV Room Lot 23,441,940


Remuneration
Worker man/day 4.000 130,000 520,000
Technician Electrical man/day 1.000 563,940 563,940

Equipment
Tools (martil, mesin bor, tang kabel, selotip, test pen, multitester) lot 1.000 200,000 200,000

Material
Tiang splitzen 1/2' ; 50-60 cm unit 50.000 192,000 9,600,000
Kabel BC 25 m' 250.000 24,600 6,150,000
Clamp kabel / skun kabel unit 30.000 33,600 1,008,000
Cooper rod/pentanahan m' 4.000 1,200,000 4,800,000
Control box, brick 60x60 cm2 m3 4.000 150,000 600,000
23,441,940
An 35 Pemasangan Geotekstil atau Plastik m2
Material
Geotekstil m2 1.080
Plastik m2 1.080

Renumeration
Worker man-day 0.160
Digger man-day 0.032
Foreman man-day 0.016

An 36 Installation Stainlesss Steel Pipe ᴓ 100mm m'


Remuneration
Worker man/day 0.499 130,000
Welder man/day 0.200 150,000
Fitter man/day 0.216 175,000
Rigger man/day 0.108 110,000
Supervsion man/day 0.050 215,000
Safety man/day 0.050 200,000

Material
Electroda Kg 0.350 200,000
Argon btl 0.050 550,000
Grinding disk pcs 0.150 125,000

Equipment
Tackel & Handle crane 2T unit/day 0.004 -
Welding Machine unit/day 0.200 -
Safety equipment (Gas detector) unit 1.000 -

An 37 Demolishing Stainlesss Steel Pipe ᴓ 100mm m'


Remuneration
Worker man/day 0.499 130,000
Welder man/day 0.200 150,000
Supervsion man/day 0.050 215,000
Safety man/day 0.050 200,000

Equipment
Tackel & Handle crane 2T unit/day 0.004
Welding Machine unit/day 0.200
Exavator unit/hour 0.028
Oxigen Tabung 0.050
Acetelin Tabung 0.050

An 38 Installation Steel Pipe ᴓ 125mm m'


Remuneration
Worker man/day 0.579
Welder man/day 0.216
Fitter man/day 0.216
Rigger man/day 0.108
Supervsion man/day 0.058

Material
Electroda Kg 0.350
Argon btl 0.050
Grinding disk pcs 0.150

Equipment
Tackel & Handle crane 2T unit/day 0.004
Welding Machine unit/day 0.216

An 39 Demolishing Steel Pipe ᴓ 125mm m'


Remuneration
Worker man/day 0.579
Welder man/day 0.216
Supervsion man/day 0.058

Equipment
Tackel & Handle crane 2T unit/day 0.004
Welding Machine unit/day 0.216

An 40 Installation Steel Pipe ᴓ 250mm m'


Remuneration
Worker man/day 1.325
Welder man/day 0.365
Fitter man/day 0.216
Rigger man/day 0.108
Supervsion man/day 0.133

Material
Electroda Kg 0.350
Argon btl 0.050
Grinding disk pcs 0.150

Equipment
Tackel & Handle crane 2T unit/day 0.004
Welding Machine unit/day 0.365

An 41 Demolishing Steel Pipe ᴓ 250mm m'


Remuneration
Worker man/day 1.325 #REF! #REF!
Welder man/day 0.365 #REF! #REF!
Supervsion man/day 0.133 #NAME? #NAME?
Safety man/day 0.050 #REF! #REF!
-
Equipment -
Tackel & Handle crane 2T unit/day 0.004 4,485,000 17,940
Welding Machine unit/day 0.365 #REF! #REF!
Excavator unit/hour 0.028 #REF! #REF!
Oxigen Tabung 0.050 #NAME? #NAME?
Acetelin Tabung 0.050 #NAME? #NAME?
#REF!
An 42 Installation Valve ᴓ 25mm m'
Remuneration
Worker man/day 1.429
Welder man/day 0.715
Supervsion man/day 0.143

Equipment
Tackel & Handle crane 2T unit/day 0.100

An 43 Installation Elbow/Tee ᴓ 100mm m'


Remuneration
Worker man/day 0.848
Welder man/day 0.424
Fitter man/day 1.728
Rigger man/day 0.000
Supervsion man/day 0.088
Safety man/day 0.400

Material
Electroda Kg 2.800
Argon btl 0.400
Grinding disk pcs 1.200

Equipment
Tackel & Handle crane 2T unit/day 0.000
Welding Machine unit/day 2.920
Safety equipment (Gas detector) Lot 1.000

An 44 Installation Elbow/Tee ᴓ 250mm m'


Remuneration
Worker man/day 2.120
Welder man/day 1.060
Fitter man/day 4.320
Rigger man/day 0.000
Supervsion man/day 0.220
Safety man/day 1.000

Material
Electroda Kg 7.000
Argon btl 1.000
Grinding disk pcs 3.000

Equipment
Tackel & Handle crane 2T unit/day 0.004
Welding Machine unit/day 2.920
Safety equipment (Gas detector) Lot 1.000

An
I. TOWER WORK
An 1 Steel of Structures for Tower and Gantry 1 ton 26,175,856
Material
- Galvanis of Steel angle HTS ton 0.650 17,600,000 11,440,000
- Galvanis of Steel angle MS ton 0.350 17,600,000 6,160,000
- Galvanis Bolt and Nuts kg 120.000 17,600 2,112,000
- Galvanis of Steel Plate ton 0.040 17,600,000 704,000

Rent of Equipment
- Drilling of Machine hour 1.000 550,000 550,000
- Supporting of Equipment ( Welder and Cutting Machine ) hour 1.000 29,856 29,856

Remuneration
- Worker man/day 25.000 130,000 3,250,000
- Steel Worker man/day 15.000 100,000 1,500,000
- Foreman man/day 2.000 215,000 430,000

An 2 Sortir Material of Tower 1 ton 237,500


Remuneration
- Worker man/day 1.000 130,000 130,000
- Foreman man/day 0.500 215,000 107,500

An 3 Erection Tower for 150 kV 1 ton 2,405,005


Remuneration
- Steel Erection Worker man-day 4.000 220,000 880,000
- Worker man-day 3.000 130,000 390,000
- Foreman man-day 1.000 215,000 215,000
- Engineer expert man-day 0.500 1,000,150 500,075
-
Rent of Equipment -
- Bamboo stick 8.000 25,300 202,400
- Pully unit / day 3.000 37,950 113,850
- Cord meter 10.000 10,368 103,680

An 4 Erection Tower for 500 kV 1 ton 5,163,325


Remuneration
- Steel Erection Worker man-day 5.000 220,000 1,100,000
- Worker man-day 10.000 130,000 1,300,000
- Foreman man-day 1.000 215,000 215,000
- Engineer expert man-day 0.500 1,000,150 500,075
-
Rent of Equipment -
- Bamboo stick 0.000 25,300 -
- Pully unit / day 3.000 37,950 113,850
- Cord meter 50.000 10,368 518,400
- Winch Machine dan Gin Pole unit/day 2.000 675,000 1,350,000
- Sling unit/day 2.000 33,000 66,000

An 5 Dismantling Materials and Accessories Tower 1 ton 3,253,355


Remuneration
- Steel Erection Worker man-day 4.000 220,000 880,000
- Worker man-day 10.000 130,000 1,300,000
- Foreman man-day 1.000 215,000 215,000
- Engineer expert man-day 0.500 1,000,150 500,075
-
Rent of Equipment -
- Bamboo stick 8.000 25,300 202,400
- Pully unit / day 3.000 17,400 52,200
- Cord meter 10.000 10,368 103,680

An 6 Transportation of Material Tower and Foundation 1 ton


6.1 Transportation of Material Tower (0 - 20 km) 1 ton 219,548
Remuneration
- Driver man-day 0.100 150,000 15,000
- Worker man-day 0.500 130,000 65,000
- Steel Worker man-day 0.100 100,000 10,000
- Foreman man-day 0.100 215,000 21,500
-
Rent of Equipment -
- Car ( Truck ) unit / day 0.020 748,000 14,960
- Forklift hour 0.100 240,625 24,063
-
Material : -
- BBM / solar lt 5.000 13,805 69,025

6.2 Transportation of Material Tower (20 - 40 km) 1 ton 439,095


Remuneration
- Driver man-day 0.200 150,000 30,000
- Worker man-day 1.000 130,000 130,000
- Steel Worker man-day 0.200 100,000 20,000
- Foreman man-day 0.200 215,000 43,000
-
Rent of Equipment -
- Car ( Truck ) unit / day 0.040 748,000 29,920
- Forklift hour 0.200 240,625 48,125
-
Material : -
- BBM / solar lt 10.000 13,805 138,050

6.3 Transportation of Material Tower (40 - 60 km) 1 ton 658,643


Remuneration
- Driver man-day 0.300 150,000 45,000
- Worker man-day 1.500 130,000 195,000
- Steel Worker man-day 0.300 100,000 30,000
- Foreman man-day 0.300 215,000 64,500
-
Rent of Equipment -
- Car ( Truck ) unit / day 0.060 748,000 44,880
- Forklift hour 0.300 240,625 72,188
-
Material : -
- BBM / solar lt 15.000 13,805 207,075

6.4 Transportation of Material Tower (60 - 80 km) 1 ton 878,190


Remuneration
- Driver man-day 0.400 150,000 60,000
- Worker man-day 2.000 130,000 260,000
- Steel Worker man-day 0.400 100,000 40,000
- Foreman man-day 0.400 215,000 86,000
-
Rent of Equipment -
- Car ( Truck ) unit / day 0.080 748,000 59,840
- Forklift hour 0.400 240,625 96,250
-
Material : -
- BBM / solar lt 20.000 13,805 276,100

6.5 Transportation of Material Tower (80 - 100 km) 1 ton 1,097,738


Remuneration
- Driver man-day 0.500 150,000 75,000
- Worker man-day 2.500 130,000 325,000
- Steel Worker man-day 0.500 100,000 50,000
- Foreman man-day 0.500 215,000 107,500
-
Rent of Equipment -
- Car ( Truck ) unit / day 0.100 748,000 74,800
- Forklift hour 0.500 240,625 120,313
-
Material : -
- BBM / solar lt 25.000 13,805 345,125

An A Langsir Material Pondasi Medan Datar 1 Kg


A .1 Langsir Material Medan Datar (0 - 500 meter) 1 Kg 226
Remuneration
- Worker man-day 0.0013 130,000 170
- Foreman man-day 0.0003 215,000 56

A .2 Langsir Material Medan Datar (500 - 1000 meter) 1 Kg 384


Remuneration
- Worker man-day 0.0022 130,000 289
- Foreman man-day 0.0004 215,000 96

A .3 Langsir Material Medan Datar (1000 - 1500 meter) 1 Kg 481


Remuneration
- Worker man-day 0.0028 130,000 361
- Foreman man-day 0.0006 215,000 119

An B Langsir Material Pondasi Medan Datar + Klotok 1 Kg


B .1 Langsir Material Medan Datar + Klotok (0 - 500 meter) 1 Kg 446
Remuneration
- Worker man-day 0.0022 130,000 289
- Foreman man-day 0.0004 215,000 96

Rent of Equipment
- Klotok Unit-day 0.0002 275,000 61
-
B .2 Langsir Material Medan Datar + Klotok (500 - 1000 meter) 1 Kg 810
Remuneration
- Worker man-day 0.0037 130,000 481
- Foreman man-day 0.0007 215,000 159

Rent of Equipment
- Klotok Unit-day 0.0006 275,000 170

B .2 Langsir Material Medan Datar + Klotok (1000 - 1500 meter) 1 Kg 1,410


Remuneration
- Worker man-day 0.0056 130,000 722
- Foreman man-day 0.0011 275,000 306

Rent of Equipment
- Klotok Unit-day 0.0014 275,000 382

An C Langsir Material Pondasi Medan Bukit / Rawa 1 Kg


C .1 Langsir Material Medan Bukit / Rawa (0 - 500 meter) 1 Kg 685
Remuneration
- Worker man-day 0.004 130,000 481
- Foreman man-day 0.001 275,000 204

-
C .2 Langsir Material Medan Bukit / Rawa (500 - 1000 meter) 1 Kg 1,370
Remuneration
- Worker man-day 0.007 130,000 963
- Foreman man-day 0.001 275,000 407

C .3 Langsir Material Medan Bukit / Rawa (1000 - 1500 meter) 1 Kg 2,056


Remuneration
- Worker man-day 0.011 130,000 1,444
- Foreman man-day 0.002 275,000 611

An D Langsir Material Pondasi Medan Bukit / Rawa + Klotok 1 Kg


D .1 Langsir Material Medan Bukit / Rawa + Klotok (0 - 500 meter) 1 Kg 477
Remuneration
- Worker man-day 0.002 130,000 271
- Foreman man-day 0.000 275,000 115

Rent of Equipment
- Klotok Unit-day 0.000 275,000 92
-
D .2 Langsir Material Medan Bukit / Rawa + Klotok (500 - 1000 meter) 1 Kg 954
Remuneration
- Worker man-day 0.004 130,000 542
- Foreman man-day 0.001 275,000 229

Rent of Equipment
- Klotok Unit-day 0.001 275,000 183

D .2 Langsir Material Medan Bukit / Rawa + Klotok (1000 - 1500 meter) 1 Kg 1,356
Remuneration
- Worker man-day 0.006 130,000 813
- Foreman man-day 0.001 215,000 269

Rent of Equipment
- Klotok Unit-day 0.001 275,000 275

An 7 Transportation Stringing of Equipment 1 Unit 2,670,625


Remuneration
- Driver man-day 1.000 150,000 150,000
- Worker Stringging man-day 1.000 250,000 250,000
- Foreman man-day 1.000 215,000 215,000

Rent of Equipment
- Car ( Truck ) unit / day 1.000 748,000 748,000
- Forklift hour 4.000 240,625 962,500

Material :
- BBM / solar lt 25.000 13,805 345,125

An 8 Handling of Material Foundation m3 182,975


Remuneration
- Worker man-day 1.300 130,000 169,000
- Foreman man-day 0.065 215,000 13,975

An 9 Bus Clearing 1 KM 8,950,110


Remuneration
- Worker man-day 50.000 130,000 6,500,000
- Foreman man-day 5.000 215,000 1,075,000

Rent of Equipment
- Chain Saw unit-day 5.000 269,500 1,347,500

Material :
- BBM / solar lt 2.000 13,805 27,610
8,950,110
1 KMS 1,491,685
An 10 Stringing of conductor (2 cct) 1 KMR 109,600,913
Remuneration
- Worker Stringging man-day 200.0 250,000 50,000,000
- Foreman TL man-day 15.0 215,000 3,225,000
- Engineer man-day 5.0 612,140 3,060,700
- Operator man-day 10.0 425,000 4,250,000
- Engineer expert man-day 0.0 1,000,150 -

Rent of Equipment
- Stringing of Equipment unit / day 5.0 9,166,667 45,833,333
- Theodolit hour 8.0 27,500 220,000
- Communication of Equipment unit / day 15.0 97,900 1,468,500

Material :
- Bamboo stick 50.0 25,300 1,265,000
- Galvanis of Wiredia4 mm kg 25.0 11,135 278,380

An 11 Stringing of Earthing conductor 1 KMR 17,826,747


Remuneration
- Worker Stringging man-day 20.000 250,000 5,000,000
- Foreman TL man-day 2.000 215,000 430,000
- Engineer man-day 2.000 612,140 1,224,280
- Operator man-day 4.000 425,000 1,700,000
- Engineer expert man-day 0.000 1,000,150 -

Rent of Equipment
- Stringing of Equipment unit / day 1.000 9,166,667 9,166,667
- Theodolit hour 4.000 27,500 110,000
- Communication of Equipment unit / day 2.000 97,900 195,800

Material :
- Bamboo stick 0.000 25,300 -
- Galvanis of Wire dia 4 mm kg 0.000 11,135 -

An 12 Sagging of Stringing 9,555,000


Remuneration
Worker Stringging man-day 24.000 250,000 6,000,000
Foreman TL man-day 4.000 215,000 860,000
-
Rent of Equipment -
Sagging of Equipment unit / day 4.000 605,000 2,420,000
Theodolit unit / day 10.000 27,500 275,000

An 13 Dismantling of conductor (2 cct) 1 KMR 66,383,400


Remuneration
- Worker Stringging man-day 120.0 250,000 30,000,000
- Foreman TL man-day 9.0 215,000 1,935,000
- Engineer man-day 3.0 612,140 1,836,420
- Operator man-day 6.0 425,000 2,550,000
- Engineer expert man-day 0.0 1,000,150 -
-
Rent of Equipment -
- Stringing of Equipment unit / day 3.0 9,166,667 27,500,000
- Theodolit hour 5.0 27,500 137,500
- Communication of Equipment unit / day 9.0 97,900 881,100
-
Material : -
- Bamboo stick 50.0 25,300 1,265,000
- Galvanis of Wiredia4 mm kg 25.0 11,135 278,380

An 14 Installed of Single Tension Insulator set & Hardware ( incl. Clamp & Armour rod ) Pcs 661,229

Remuneration
- Worker Stringging man-day 1.500 250,000 375,000
- Foreman TL man-day 0.188 215,000 40,313
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit / day 1.500 163,944 245,916

An 15 Installed of Double Tension Insulator set & Hardware ( incl. Clamp & Armour rod ) Pcs 971,687

Remuneration
- Worker Stringging man-day 2.250 250,000 562,500
- Foreman TL man-day 0.188 215,000 40,313
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit / day 2.250 163,944 368,874
An 16 Installed of Inverted Insulator stringset & Hardware ( incl. Clamp & Armour rod ) Pcs 971,687

Remuneration
- Worker Stringging man-day 2.250 250,000 562,500
- Foreman TL man-day 0.188 215,000 40,313
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit / day 2.250 163,944 368,874

An 17 Installed of Single Suspension Insulator set & Hardware( incl. Clamp & Armour rod ) Pcs 440,819

Remuneration
- Worker Stringging man-day 1.000 250,000 250,000
- Foreman TL man-day 0.125 215,000 26,875
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 1.000 163,944 163,944

An 18 Installed of Double Suspension Insulator set & Hardware( incl. Clamp & Armour rod ) Pcs 647,791

Remuneration
- Worker Stringging man-day 1.500 250,000 375,000
- Foreman TL man-day 0.125 215,000 26,875
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 1.500 163,944 245,916

An 19 Installed of Earthwire Suspension set( incl. Clamp & Armour rod ) Pcs 255,069

Remuneration
- Worker Stringging man-day 0.300 250,000 75,000
- Foreman TL man-day 0.075 215,000 16,125
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 1.000 163,944 163,944

An 20 Installed of Earthwire Tension set ( incl. Clamp & Armour rod ) Pcs 127,535

Remuneration
- Worker Stringging man-day 0.150 250,000 37,500
- Foreman TL man-day 0.038 215,000 8,063
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 0.500 163,944 81,972

An 21 Installed of Jumper Support Insulator set ( incl. Clamp & Armour rod ) Pcs 579,257

Remuneration
- Worker Stringging man-day 1.500 250,000 375,000
- Foreman TL man-day 0.188 215,000 40,313
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 1.000 163,944 163,944

An 22 Installed Armour Rod of Earthwire Pcs 112,347

Remuneration
- Worker Stringging man-day 0.100 250,000 25,000
- Foreman TL man-day 0.025 215,000 5,375
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 0.500 163,944 81,972

An 23 Installed of Spacer damper for ACSR/AS or TACSR Pcs 108,847


Remuneration
- Worker Stringging man-day 0.250 250,000 62,500
- Foreman TL man-day 0.125 215,000 26,875
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 0.500 163,944 81,972

An 24 Installed of Spacer for Jumper ACSR/AS or TACSR Pcs 88,691


Remuneration
- Worker Stringging man-day 0.125 250,000 31,250
- Foreman TL man-day 0.031 215,000 6,719
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 0.500 163,944 81,972

An 25 Installed Vibration damper for AS 95 or OPGW 100 mm2 Pcs 157,910


Remuneration
- Worker Stringging man-day 0.250 250,000 62,500
- Foreman TL man-day 0.063 215,000 13,438
- Engineer expert man-day 0.000 1,000,150 -
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 0.500 163,944 81,972

An 26 Installed of Mid Span Joint for ACSR/AS or TACSR Pcs 233,847


Remuneration
- Worker Stringging man-day 0.500 250,000 125,000
- Foreman TL man-day 0.125 215,000 26,875
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 0.500 163,944 81,972

An 27 Installed of Mid Span Joint for AS 95 or OPGW 100 mm2 Pcs 195,878
Remuneration
- Worker Stringging man-day 0.375 250,000 93,750
- Foreman TL man-day 0.094 215,000 20,156
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 0.500 163,944 81,972

An 28 Installed of Repair Sleeve for ACSR/AS or TACSR Pcs 260,722


Remuneration
- Worker Stringging man-day 0.500 250,000 125,000
- Foreman TL man-day 0.250 215,000 53,750
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 0.500 163,944 81,972

An 29 Installed of Anti Climbing Device 1 set / twr 260,722


Remuneration
- Worker Stringging man-day 0.500 250,000 125,000
- Foreman TL man-day 0.250 215,000 53,750
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 0.500 163,944 81,972

An 30 Danger plate / Number Plate Unit 325,422


Remuneration
- Worker man-day 1.000 250,000 250,000
- Foreman man-day 0.100 215,000 21,500
-
Material -
- Aluminium plate uk. 12cm x 12 cm kg 3.900 10,780 42,042
- Colour steel paint kg 0.100 118,800 11,880

An 31 Installed of Danger Plate 2 pcs/twr 260,722


Remuneration
- Worker Stringging man-day 0.500 250,000 125,000
- Foreman TL man-day 0.250 215,000 53,750
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 0.500 163,944 81,972

An 32 Installed of Number Plate Phase 2 pcs/twr 260,722


Remuneration
- Worker Stringging man-day 0.500 250,000 125,000
- Foreman TL man-day 0.250 215,000 53,750
-
Rent of Equipment -
- Supporting of Equipment ( Key and Safety belt ) unit-day 0.500 163,944 81,972

An 33 Installed of Earthing of Tower Set 535,375


Remuneration
- Worker man-day 2.000 130,000 260,000
- Test Engineer (Electrical Technician) man-day 0.250 482,000 120,500
- Supervisor man-day 0.375 215,000 80,625

Rent of Equipment -
- Insulation Test Equipment unit-day 0.250 165,000 41,250
- Supporting of Earthing Device unit-day 0.250 132,000 33,000

An 34 Installed of Junction Box and Gantry Box Set 576,625


Remuneration
- Worker man-day 2.000 130,000 260,000
- Test Engineer (Electrical Technician) man-day 0.250 482,000 120,500
- Supervisor man-day 0.375 215,000 80,625

Rent of Equipment -
- Insulation Test Equipment unit-day 0.500 165,000 82,500
- Supporting of Earthing Device unit-day 0.250 132,000 33,000

An 33 Dewatering with pump ( 24 hours, capacity 30 m3/s) Ls 1,915,543


Material
- Solar Ltr 72.600 13,805 1,002,243
- Oil Ltr 0.300 66,000 19,800
-
Rent of Equipment -
- Water Pump 30 m3/day hari 1.000 352,000 352,000
-
Remuneration -
- Worker man-day 4.000 130,000 520,000
- Foreman man-day 0.100 215,000 21,500

An 34 1 Tarikan (Section) Steger bamboo m2 31,824,067


Remuneration
- Worker man-day 18.000 130,000 2,340,000
- Carpenter man-day 18.000 120,000 2,160,000
- Worker chief man-day 3.000 157,500 472,500
- Foreman man-day 3.000 215,000 645,000

Material
- Bamboo no 945.000 25,300 23,908,500
- Rope fibers m3 160.704 14,300 2,298,067

An 35 Patok beton uk. 10 cm x 10 cm Unit 204,018


Material
- Patok beton uk. 10cm x 10 cm Ls 1.250 38,250 47,813
- Cat tembok kg 0.186 25,300 4,706
-
Remuneration -
- Worker man-day 1.000 130,000 130,000
- Foreman man-day 0.100 215,000 21,500

An 36 Rewinding Konduktor Hawk Haspel


Material
- Kayu Klas II 2/20cm m3 1.000 2,897,500 2,897,500
- Besi baja 16mm, 12 meter kg 19.000 20,933 397,727
- Paku kg 8.000 31,400 251,200
- Baut 5/8, 30 cm baut 64.000 13,200 844,800
-
Equipment -
- Truck crane 3 ton unit-day 0.125 #NAME? #NAME?
- Forklift unit-day 0.063 #REF! #REF!
- Tripod unit-day 0.500 220,000 110,000
- Jack drum unit-day 0.500 #REF! #REF!
- Chain block 5 ton unit-day 0.500 #REF! #REF!
-
Remuneration -
- Worker man-day 4.000 #REF! #REF!
- Steel worker man-day 1.000 #REF! #REF!
- Carpenter man-day 8.000 #REF! #REF!
- Foreman man-day 0.500 #REF! #REF!
#NAME?
An 37 Rewinding Konduktor Hawk Haspel
Material
- Pipa GIP 2 inch stick 12.000 #NAME? #NAME?
- Kawat las harmonika m 2.826 #NAME? #NAME?
- Baut 5/8, 30 cm baut 16.000 13,200 211,200
-
Equipment -
- Truck crane 3 ton unit-day 0.125 #NAME? #NAME?
- Forklift unit-day 0.063 #REF! #REF!
- Tripod unit-day 0.500 220,000 110,000
- Jack drum unit-day 0.250 #REF! #REF!
- Chain block 5 ton unit-day 0.500 #REF! #REF!
- Welding Machine unit-day 2.000 #REF! #REF!
-
Remuneration -
- Worker man-day 4.000 #REF! #REF!
- Steel worker man-day 0.750 #REF! #REF!
- Welder man-day 4.000 #REF! #REF!
- Foreman man-day 0.500 #REF! #REF!
#NAME?
An 38 Setting Stub Tower Foundation set/Twr 275,202
Remuneration
- Worker man/day 0.250 130,000 32,500
- Carpenter man/day 0.250 120,000 30,000
- Foreman man/day 0.025 215,000 5,375
- Surveyor man/day 0.250 433,800 108,450
-
Material -
- Meranti 3/20 m3 0.007 2,457,400 17,202
- Kayu Meranti 5/7 m3 0.012 2,200,000 26,400
- Paku 2-3cm pcs 0.020 13,750 275
-
Equipment -
- Theodolite hour 2.000 27,500 55,000

An 39 Pengukuran Situasi Tower set/Twr 180,325


Remuneration
- Worker man/day 0.500 130,000 65,000
- Surveyor man/day 0.250 433,800 108,450
-
Equipment -
- Theodolite day 0.250 27,500 6,875

An 40 Welding with electric 10 cm 39,258


Remuneration
- Worker man-day 0.013 130,000 1,625
- Weld worker man-day 0.013 150,000 1,875
- Worker chief man-day 0.001 170,000 213
- Foreman man-day 0.001 215,000 269
-
-
- Welding wire kg 0.010 24,750 248
- Solar Ltr 0.013 13,805 173
- Oil Ltr 0.013 66,000 825
-
Equipment -
- Welding Machine unit-day 0.063 544,500 34,031

An 41 Talk Welding Bolt & Nut of Tower up to Base Tower 1 Unit 5,736,388
Remuneration
- Weld worker man-day 4.000 130,000 520,000
- Operator man-day 1.000 425,000 425,000
- Supervisor man-day 0.500 215,000 107,500
-
Equipment -
- Welding Engine (Welder and Cutting Machine) hour 8.000 544,500 4,356,000
- Supporting of Equipment (Key and Safety Belt) unit-day 2.000 163,944 327,888

An 42 Installation PVC pipe type AW dia 2" m' 89,025


Remuneration
- Worker man-day 0.250 130,000 32,500
- Worker chief man-day 0.025 170,000 4,250
- Foreman man-day 0.025 215,000 5,375
-
Material -
- PVC pipe 2" no 0.250 176,440 44,110
- Fitting sets pcs 0.186 15,000 2,790

An 43 Earthing angle, including galvanized steel angle 1,5 m Set 335,028


Remuneration
- Worker man-day 1.000 130,000 130,000
- Foreman man-day 0.100 215,000 21,500
-
Material -
- Galvanis of Steel angle MS kg 5.655 17,600 99,528
- GSW 55 m 3.000 18,000 54,000
- Clamp pcs 2.000 15,000 30,000

An 44 Shifitng Conductor per span per phase Phase 26,762,320


Remuneration
- Driver man-day 1.000 150,000 150,000
- Worker man-day 25.000 130,000 3,250,000
- Engineer man-day 4.000 612,140 2,448,560
- Supervision man-day 1.000 215,000 215,000
- Mob & Demob man-day 1.000 10,000,000 10,000,000

Rent of Equipment
- Sling unit-day 8.000 33,000 264,000
- Tools (Turnbuckle. Tirfor, BV, sukle, come along, tacle, rope) set-day 1.000 3,000,000 3,000,000
- Total station unit-day 1.000 500,000 500,000
- Truck unit-day 1.000 186,000 186,000
- Truck Crane unit-day 1.000 3,000,000 3,000,000
- Genset unit-day 1.000 1,000,000 1,000,000
- Press machine unit-day 2.000 240,000 480,000
- Rope unit-day 5.000 150,000 750,000
- Jack Drum unit-day 1.000 500,000 500,000
- Safety Equipment unit-day 1.000 466,560 466,560

Material -
- BBM/Solar lt 40.000 13,805 552,200

An 45 Komisioning (Sistem Pentanahan) Tower 157,700


Remuneration
- Electrician man-day 0.250 175,000 43,750
- Worker man-day 0.500 130,000 65,000

Rent of Equipment
- Megger unit-day 0.250 30,800 7,700
- Earth Tester unit-day 0.250 165,000 41,250

An 46 Counterpoise 30 m long GSW and 0.45 m depth, including galvanized steel angle 1 m Tower 812,852
Remuneration
- Worker man-day 0.500 130,000 65,000
- Foreman man-day 0.100 215,000 21,500

Material
- Galvanis of Steel angle MS kg 3.770 17,600 66,352
- GSW 55 m 30.000 18,000 540,000
- Clamp pcs 8.000 15,000 120,000

An 47 Final Check Tower 771,444


Remuneration
- Worker man-day 2.000 250,000 500,000
- Supervisor man-day 0.500 215,000 107,500
-
Equipment -
- Supporting of Equipment (Key and Safety Belt) unit-day 1.000 163,944 163,944

An 48 Design Tabel Final of Sagging Ls 1,408,780


Remuneration
- Engineer man-day 2.000 612,140 1,224,280
- Supervisor man-day 0.500 215,000 107,500
-
Equipment -
- Computer + Printer unit-day 0.400 192,500 77,000

An 49 As Built Drawing and Shop Drawing Ls 35,142,700


Remuneration
- Engineer man-day 30.000 612,140 18,364,200
- Drafter man-day 60.000 174,000 10,440,000
-
Equipment -
- Computer + Printer unit-day 30.000 192,500 5,775,000
- Kertas A4 + Kertas A3 rim 5.000 112,700 563,500

An 50 Design of Calculation and Drawing Ls 123,955,900


Remuneration
- Engineer Expert man-day 60.000 1,000,150 60,009,000
- Engineer man-day 60.000 612,140 36,728,400
- Drafter man-day 120.000 174,000 20,880,000
-
Equipment -
- Computer + Printer unit-day 30.000 192,500 5,775,000
- Kertas A4 + Kertas A3 rim 5.000 112,700 563,500

An 51 Pemasangan & Pembongkaran Steger KMS 5,618,250


Remuneration
- Worker man-day 1.000 130,000 130,000
- Worker chief man-day 0.250 215,000 53,750
- Foreman man-day 0.250 215,000 53,750
- Driver man-day 0.250 150,000 37,500

Rent of Equipment
- Truck Unit-day 0.250 748,000 187,000

Material
- Bamboo Ls 50.000 25,300 1,265,000
- Tali Nilon Roll 1.000 132,000 132,000
- Nail Kg 1.000 13,750 13,750
Biaya Per Steger 1,872,750

An 52 Double Tension String Set Isolator (+Roll) Set 1,685,133


Remuneration
- Worker man-day 6.000 130,000 780,000
- Worker chief man-day 0.500 215,000 107,500
- Foreman man-day 0.500 215,000 107,500

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 3.000 163,944 491,832
- Chain Block Unit-day 0.500 132,603 66,301

Material
- Tali Nilon Roll 1.000 132,000 132,000

An 53 Single Tension String Set Isolator (+Roll) Set 714,425


Remuneration
- Worker man-day 2.250 130,000 292,500
- Worker chief man-day 0.188 215,000 40,313
- Foreman man-day 0.188 215,000 40,313

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 1.125 163,944 184,437
- Chain Block Unit-day 0.188 132,603 24,863

Material
- Tali Nilon Roll 1.000 132,000 132,000

An 54 Double Suspension String Set Isolator (+Roll) Set 1,486,133


Remuneration
- Worker man-day 4.800 130,000 624,000
- Worker chief man-day 0.400 215,000 86,000
- Foreman man-day 0.400 215,000 86,000

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 3.000 163,944 491,832
- Chain Block Unit-day 0.500 132,603 66,301

Material
- Tali Nilon Roll 1.000 132,000 132,000

An 55 Single Suspension String Set Isolator (+Roll) Set 520,283


Remuneration
- Worker man-day 1.500 130,000 195,000
- Worker chief man-day 0.125 215,000 26,875
- Foreman man-day 0.125 215,000 26,875

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 0.750 163,944 122,958
- Chain Block Unit-day 0.125 132,603 16,575

Material
- Tali Nilon Roll 1.000 132,000 132,000

An 56 Single Suspension String Set Isolator For Jumper Conductor Set 1,386,633
Remuneration
- Worker man-day 4.200 130,000 546,000
- Worker chief man-day 0.350 215,000 75,250
- Foreman man-day 0.350 215,000 75,250

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 3.000 163,944 491,832
- Chain Block Unit-day 0.500 132,603 66,301

Material
- Tali Nilon Roll 1.000 132,000 132,000

An 57 Penarikan ACSR 435/55 mm2 KMR #REF!


Remuneration
- Worker man-day 18.000 130,000 2,340,000
- Worker chief man-day 2.000 215,000 430,000
- Foreman man-day 2.000 215,000 430,000
- Operator man-day 2.000 425,000 850,000

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 8.000 163,944 1,311,552
- Peralatan Stringing Unit-day 2.000 #REF! #REF!
- Theodolit Unit-day 3.000 #REF! #REF!
- Peralatan Komunikasi Unit-day 5.000 #REF! #REF!

Material
- Bambu Btg 10.000 #REF! #REF!
- Kawat Galvanis 4 mm Kg 5.000 12,000 60,000
Biaya Penarikan Per km #REF!
Biaya Penarikan Per KMS #REF!

An 58 Penarikan GSW 70 mm2 KMR #REF!


Remuneration
- Worker man-day 4.800 #REF! #REF!
- Worker chief man-day 0.800 #REF! #REF!
- Foreman man-day 0.800 #REF! #REF!
- Operator man-day 1.600 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 6.400 #REF! #REF!
- Peralatan Stringing Unit-day 1.600 #REF! #REF!
- Theodolit Unit-day 0.800 #REF! #REF!
- Peralatan Komunikasi Unit-day 1.600 #REF! #REF!

Material
- Bambu Btg 5.000 #REF! #REF!
- Kawat Galvanis 4 mm Kg 3.000 12,000 36,000
Biaya Penarikan Per KMS #REF!

An 59 Penarikan OPGW 24 Core 70 mm2 KMR #REF!


Remuneration
- Worker man-day 4.800 #REF! #REF!
- Worker chief man-day 0.800 #REF! #REF!
- Foreman man-day 0.800 #REF! #REF!
- Operator man-day 1.600 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 5.600 #REF! #REF!
- Peralatan Stringing Unit-day 1.600 #REF! #REF!
- Theodolit Unit-day 0.800 #REF! #REF!
- Peralatan Komunikasi Unit-day 1.600 #REF! #REF!

Material
- Bambu Btg 5.000 #REF! #REF!
- Kawat Galvanis 4 mm Kg 3.000 12,000 36,000
Biaya Penarikan Per KMS #REF!

An 60 Sagging ACSR 435/55 mm2 KMR #REF!


Remuneration
- Worker man-day 4.000 #REF! #REF!
- Worker chief man-day 2.000 #REF! #REF!
- Foreman man-day 3.000 #REF! #REF!
- Operator man-day 2.000 #REF! #REF!
- Engineer man-day 1.000 #REF! #REF!
Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 4.000 #REF! #REF!
- Peralatan Sagging Unit-day 2.000 #REF! #REF!
- Theodolit Unit-day 2.000 #REF! #REF!
- Peralatan Komunikasi Unit-day 2.000 #REF! #REF!

Biaya Penarikan Per KMS #REF!

An 61 Sagging GSW 70 mm2 KMR #REF!


Remuneration
- Worker man-day 1.200 #REF! #REF!
- Worker chief man-day 0.300 #REF! #REF!
- Foreman man-day 0.600 #REF! #REF!
- Operator man-day 0.600 #REF! #REF!
- Engineer man-day 0.300 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 1.200 #REF! #REF!
- Peralatan Sagging Unit-day 0.600 #REF! #REF!
- Theodolit Unit-day 0.300 #REF! #REF!
- Peralatan Komunikasi Unit-day 0.600 #REF! #REF!

Biaya Penarikan Per KMS #REF!

An 62 Sagging OPGW 70 mm2 KMR #REF!


Remuneration
- Worker man-day 1.200 #REF! #REF!
- Worker chief man-day 0.300 #REF! #REF!
- Foreman man-day 0.600 #REF! #REF!
- Operator man-day 0.600 #REF! #REF!
- Engineer man-day 0.300 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 1.200 #REF! #REF!
- Peralatan Sagging Unit-day 0.600 #REF! #REF!
- Theodolit Unit-day 0.300 #REF! #REF!
- Peralatan Komunikasi Unit-day 0.600 #REF! #REF!

Biaya Penarikan Per KMS #REF!

An 63 Clamping Tower 2 Sirkit Tension Termasuk Jumper Set #REF!


Remuneration
- Worker man-day 0.500 #REF! #REF!
- Worker chief man-day 0.125 #REF! #REF!
- Foreman man-day 0.125 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 0.500 #REF! #REF!
- Mesin Press Complete Unit-day 0.125 #REF! #REF!
- Tackle Unit-day 0.125 #REF! #REF!
- Stringing Ladder Unit-day 0.125 #REF! #REF!
- Grounding Stick Unit-day 0.125 #REF! #REF!
- Came along/wire grip Unit-day 0.125 #REF! #REF!

Biaya Penarikan Per Set #REF!


Biaya Penarikan Per Tower #REF!

An 64 Clamping Tower 4 Sirkit Tension Termasuk Jumper Set #REF!


Remuneration
- Worker man-day 1.000 #REF! #REF!
- Worker chief man-day 0.125 #REF! #REF!
- Foreman man-day 0.125 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 1.000 #REF! #REF!
- Mesin Press Complete Unit-day 0.250 #REF! #REF!
- Tackle Unit-day 0.250 #REF! #REF!
- Stringing Ladder Unit-day 0.250 #REF! #REF!
- Grounding Stick Unit-day 0.250 #REF! #REF!
- Came along/wire grip Unit-day 0.250 #REF! #REF!

Biaya Clamping Per Set #REF!


Biaya Clamping Per Tower #REF!

An 65 Pek. Clamping & Pemasangan Armour Rod Tower Suspension 4 Sirkit Set #REF!
Remuneration
- Worker man-day 0.500 #REF! #REF!
- Worker chief man-day 0.063 #REF! #REF!
- Foreman man-day 0.063 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 1.500 #REF! #REF!
- Mesin Press Complete Unit-day 0.375 #REF! #REF!
- Tackle Unit-day 0.375 #REF! #REF!
- Stringing Ladder Unit-day 0.375 #REF! #REF!
- Grounding Stick Unit-day 0.375 #REF! #REF!
- Came along/wire grip Unit-day 0.375 #REF! #REF!

Biaya Clamping Per Set #REF!


Biaya Clamping Per Tower #REF!

An 66 Pek. Clamping GSW 55 mm2 Set #REF!


Remuneration
- Worker man-day 0.400 #REF! #REF!
- Worker chief man-day 0.200 #REF! #REF!
- Foreman man-day 0.200 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 0.400 #REF! #REF!
- Mesin Press Complete Unit-day 0.200 #REF! #REF!

Biaya Clamping Per Set #REF!

An 67 Pek. Clamping OPGW 70 mm2 Set #REF!


Remuneration
- Worker man-day 0.400 #REF! #REF!
- Worker chief man-day 0.200 #REF! #REF!
- Foreman man-day 0.200 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 0.400 #REF! #REF!
- Mesin Press Complete Unit-day 0.200 #REF! #REF!

Biaya Clamping Per Set #REF!

An 68 Pek. Pemasangan Joint Box dan OPGW Set #REF!


Remuneration
- Worker man-day 1.000 #REF! #REF!
- Enjineer man-day 0.500 #REF! #REF!
- Foreman man-day 0.500 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 2.500 #REF! #REF!

Biaya Joint Box dan OPGW Per Set #REF!

An 69 Pek. Accessories ACSR KMS #REF!


Remuneration
- Worker man-day 4.000 #REF! #REF!
- Worker chief man-day 1.000 #REF! #REF!
- Foreman man-day 1.000 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 4.000 #REF! #REF!

Biaya Accessories ACSR Per KMS #REF!

An 70 Pek. Pemasangan Spacer set #REF!


Remuneration
- Worker man-day 0.125 #REF! #REF!
- Worker chief man-day 0.063 #REF! #REF!
- Foreman man-day 0.063 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 0.125 #REF! #REF!

Biaya Accessories ACSR Per KMS #REF!

An 71 Pek. Pemasangan T-Clamp set #REF!


Remuneration
- Worker man-day 0.188 #REF! #REF!
- Worker chief man-day 0.094 #REF! #REF!
- Foreman man-day 0.094 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 0.188 #REF! #REF!

Biaya Accessories ACSR Per KMS #REF!

An 70 Pek. Accessories GSW/OPGW KMS #REF!


Remuneration
- Worker man-day 0.500 #REF! #REF!
- Foreman man-day 0.500 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 1.000 #REF! #REF!

Biaya Accessories GSW/OPGW Per KMS #REF!

An 71 Penyambungan Ke Switchyard Lot #REF!


Remuneration
- Worker man-day 4.500 #REF! #REF!
- Worker chief man-day 1.500 #REF! #REF!
- Foreman man-day 1.500 #REF! #REF!
- Operator man-day 1.500 #REF! #REF!
- Engineer man-day 0.500 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 4.500 #REF! #REF!
- Peralatan Stringing Unit-day 1.500 #REF! #REF!
- Mesin Press Complete Unit-day 1.500 #REF! #REF!

Biaya Per Sirkit #REF!

An 72 Pengujian dan Komisioning Lot #REF!


Remuneration
- Worker man-day 225.000 #REF! #REF!
- Foreman man-day 45.000 #REF! #REF!
- Operator man-day 45.000 #REF! #REF!
- Engineer man-day 45.000 #REF! #REF!
- Engineer Expert man-day 45.000 #REF! #REF!

Rent of Equipment
- Supporting (Kunci Momen, Kunci Pas, Tali Panjat, Sling, Tambang, Peralatan Safety, dll) Unit-day 225.000 #REF! #REF!
- Peralatan Komunikasi Unit-day 30.000 #REF! #REF!
- Peralatan Pengujian untuk Testing dan Komisioning Transmisi Unit-day 30.000 #REF! #REF!

Biaya Per Sirkit #REF!

An 73 Pembuatan Back Stay Set #REF!


Remuneration
- Worker man-day 10.000 #REF! #REF!
- Foreman man-day 2.000 #REF! #REF!

Material
- Batang Kelapa Btg 2.000 50,000 100,000
- Seling (@ 1Tower 2 Leg: @ 50 m) m 100.000 15,000 1,500,000

Transportation
- Transpotasi Material (Sewa Dump Truck, BBM + Supir) @ 1 hari
2024 kg 1.000 100 202,400
An 74 Pembuatan Sagging Schedule Ls 9,647,070
Remuneration
- Drafter man-day 7 232,236 1,625,655
- Pengawas/Koordinator man-day 7 777,773 5,444,409

Alat - Alat Tulis Kantor


- A4 Rim 2 35,000 70,000
- F4 Rim 1 35,000 35,000
- A3 Rim 1 70,000 70,000
- Kantor/Laptop Unit 1 350,000 350,000
- Printer Unit 1 175,000 175,000
- Toner/Tinta Printer Pcs 10 100,000 1,000,000
8,770,064

An 75 Pembersihan Jalur Transmisi (luas = 20 * 1000 = 20.000 m2) 1 km #REF!


Remuneration
- Worker man-day 16.000 #REF! #REF!
- Carpenter Worker man-day 16.000 #REF! #REF!
- Foreman man-day 8.000 #REF! #REF!

Rent of Equipment
- Chain Saw unit-day 20.00 #REF! #REF!
- Golok/Parang Tebas unit-day 8.00 5,000 40,000

An
Remuneration
- Supervisor manday #REF! #REF! #REF!
- Skill Worker manday #REF! #REF! #REF!
- Worker manday #REF! #REF! #REF!
- Engineer Expert manday #REF! #REF! #REF!
- Electrical Technician manday #REF! #REF! #REF!

Rent of Equipment :
- Megger unitday 0.50 #REF! #REF!
- Injection primer & sekunder unitday 0.50 #REF! #REF!
- HV Apparatus Analyzer unitday 0.50 #REF! #REF!

J. PEMASANGAN PERALATAN GARDU INDUK


An 1 Install DS 150 kV and Steel Structure include wiring Set 14,237,880
A Install Steel Structure DS
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 3.000 130,000 390,000
- Mekanik man-day 1.000 350,000 350,000

Rent of Equipment :
- Truck crane 3 ton unit-day 1.000 4,400,000 4,400,000
Total A 5,755,000
B Install Peralatan DS include wiring
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 5.000 200,000 1,000,000
- Worker man-day 8.000 130,000 1,040,000
- Mekanik man-day 2.000 350,000 700,000
- Electrical Technician man-day 2.000 563,940 1,127,880
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 1.000 4,400,000 4,400,000
Total B 8,482,880

An 2 Install DS+E 150 kV and Steel Structure include wiring Set 14,237,880
A Install Steel Structure DS+E
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 3.000 130,000 390,000
- Mekanik man-day 1.000 350,000 350,000
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 1.000 4,400,000 4,400,000
Total A 5,755,000
B Install Peralatan DS+E include wiring
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 5.000 200,000 1,000,000
- Worker man-day 8.000 130,000 1,040,000
- Mekanik man-day 2.000 350,000 700,000
- Electrical Technician man-day 2.000 563,940 1,127,880
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 1.000 4,400,000 4,400,000
Total B 8,482,880

An 3 Install CB 150 kV and Steel Structure include wiring Set 20,595,760


A Install Steel Structure CB
Remuneration
- Foreman man-day 2.000 215,000 430,000
- Skill Worker man-day 6.000 200,000 1,200,000
- Worker man-day 10.000 130,000 1,300,000
- Mekanik man-day 2.000 350,000 700,000

Rent of Equipment :
- Truck crane 3 ton unit-day 1.000 4,400,000 4,400,000
Total A 8,030,000
B Install Peralatan CB include wiring
Remuneration
- Foreman man-day 2.000 215,000 430,000
- Skill Worker man-day 10.000 200,000 2,000,000
- Worker man-day 16.000 130,000 2,080,000
- Mekanik man-day 4.000 350,000 1,400,000
- Electrical Technician man-day 4.000 563,940 2,255,760
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 1.000 4,400,000 4,400,000
Total B 12,565,760

An 4 Install CT 150 kV and Steel Structure include wiring Set 9,447,880


A Install Steel Structure CT
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 3.000 130,000 390,000
- Mekanik man-day 1.000 350,000 350,000
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 0.500 4,400,000 2,200,000
Total A 3,555,000
B Install Peralatan CT include wiring
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 5.000 200,000 1,000,000
- Worker man-day 5.000 130,000 650,000
- Mekanik man-day 2.000 350,000 700,000
- Electrical Technician man-day 2.000 563,940 1,127,880
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 0.500 4,400,000 2,200,000
Total B 5,892,880

An 5 Install CVT 150 kV and Steel Structure include wiring Set 9,447,880
A Install Steel Structure CVT
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 3.000 130,000 390,000
- Mekanik man-day 1.000 350,000 350,000
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 0.500 4,400,000 2,200,000
Total A 3,555,000
B Install Peralatan CVT include wiring
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 5.000 200,000 1,000,000
- Worker man-day 5.000 130,000 650,000
- Mekanik man-day 2.000 350,000 700,000
- Electrical Technician man-day 2.000 563,940 1,127,880
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 0.500 4,400,000 2,200,000
Total B 5,892,880

An 6 Install LA 150 kV and Steel Structure include wiring Set 9,447,880


A Install Steel Structure LA
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 3.000 130,000 390,000
- Mekanik man-day 1.000 350,000 350,000
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 0.500 4,400,000 2,200,000
Total A 3,555,000
B Install Peralatan LA include wiring
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 5.000 200,000 1,000,000
- Worker man-day 5.000 130,000 650,000
- Mekanik man-day 2.000 350,000 700,000
- Electrical Technician man-day 2.000 563,940 1,127,880
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 0.500 4,400,000 2,200,000
Total B 5,892,880

An 7 Install Line Trap include wiring and mounting plate pcs 3,977,407
A Install Peralatan LA include wiring
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 1.000 200,000 200,000
- Worker man-day 3.000 130,000 390,000
- Mekanik man-day 1.000 350,000 350,000
- Electrical Technician man-day 1.000 563,940 563,940

Rent of Equipment :
- Truck crane 3 ton unit-day 0.250 4,400,000 1,100,000

Material
Mounting plate set 1.000 63,467 63,467

A Install Steel Structure LT


Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 1.000 130,000 130,000
- Mekanik man-day 1.000 350,000 350,000

Rent of Equipment :
- Truck crane 3 ton hour 0.000 4,400,000 -

An 8 Install Post Insulator and Steel Structure , 150 kV (1 set = 3 unit) 8,897,880
A Install Steel Structure PI
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 3.000 130,000 390,000
- Mekanik man-day 1.000 350,000 350,000
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 0.375 4,400,000 1,650,000
Total A 3,005,000
B Install Peralatan PI
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 5.000 200,000 1,000,000
- Worker man-day 5.000 130,000 650,000
- Mekanik man-day 2.000 350,000 700,000
- Electrical Technician man-day 2.000 563,940 1,127,880
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 0.500 4,400,000 2,200,000
Total B 5,892,880

An 9 Install ES 150 kV and Steel Structure (1 unit) 6,203,940


A Install Steel Structure ES
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 1.000 130,000 130,000
- Mekanik man-day 1.000 350,000 350,000
-
Rent of Equipment : -
- Truck crane 3 ton hour 0.300 4,400,000 1,320,000
Total A 2,415,000
B Install Peralatan ES
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 1.000 200,000 200,000
- Worker man-day 2.000 130,000 260,000
- Mekanik man-day 1.000 350,000 350,000
- Electrical Technician man-day 1.000 563,940 563,940
-
Rent of Equipment : -
- Truck crane 3 ton hour 0.500 4,400,000 2,200,000
Total B 3,788,940
TOTAL Install ES 150 kV and Steel Structure (1 unit) 6,203,940
An 10 Install CT Netral Sistem 150 kV 6,890,940
1 Pengadaan Steel Structure CT / CVT kg 50.000 - -
2 Install Steel Structure NCT
Remuneration
Foreman man-hour 1.000 215,000 215,000
Skill Worker man-hour 2.000 200,000 400,000
Worker man-hour 1.000 130,000 130,000
- Steel Erection Worker man-hour 1.000 350,000 350,000
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) unit-day 0.300 4,400,000 1,320,000
- Peralatan bantu lot 1.000 11,000 11,000
2,426,000
3 Install NCT
Remuneration
- Foreman man-day 0.000 215,000 -
- Skill Worker man-day 1.000 200,000 200,000
- Worker man-day 2.000 130,000 260,000
- Mekanik man-day 1.000 350,000 350,000
- Electrical Technician man-day 1.000 563,940 563,940
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.700 4,400,000 3,080,000
- Peralatan bantu lot 1.000 11,000 11,000
4,464,940
Total Install CT Netral Sistem 150 kV 6,890,940
An 11 Install CT Netral Sistem 70 kV 15,223,750
1 Pengadaan Steel Structure CT / CVT kg 50.000
2 Install Steel Structure CT/ CVT
Remuneration
Foreman man-hour 1.000 215,000 215,000
Skill Worker man-hour 2.000 200,000 400,000
Worker man-hour 2.000 130,000 260,000
- Steel Erection Worker man-hour 1.000 350,000 350,000
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 3.000 1,031,250 3,093,750
- Peralatan bantu lot 0.000 - -
4,318,750
3 Install CT/ CVT
Remuneration
Foreman man-hour 1.000 215,000 215,000
Skill Worker man-hour 4.000 200,000 800,000
Worker man-hour 8.000 130,000 1,040,000
Skill Wiring Worker man-hour 3.000 200,000 600,000
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 8.000 1,031,250 8,250,000
- Peralatan bantu lot 1.000 - -
10,905,000
Total Install CT Netral Sistem 70 kV 15,223,750
An 12 Install Marshalling Kiosk 2,482,880
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 3.000 130,000 390,000
- Mekanik man-day 1.000 350,000 350,000
- Electrical Technician man-day 2.000 563,940 1,127,880
-

An 13 Install and Pengaktifan DFR Set 20,240,160


Remuneration
- Foreman man-day 7.000 215,000 1,505,000
- Skill Worker man-day 14.000 200,000 2,800,000
- Worker man-day 8.000 130,000 1,040,000
- Electrical Technician man-day 14.000 563,940 7,895,160

Rent of Equipment :
- Laptop unit-day 14.000 500,000 7,000,000
TOTAL Install and Pengaktifan DFR 20,240,160
An 13 Install 'LV power cable, control cable & optical cable bay 43,112,740
Remuneration
- Foreman man-day 28.000 215,000 6,020,000
- Skill Worker man-day 42.000 200,000 8,400,000
- Worker man-day 100.000 130,000 13,000,000
- Electrical Technician man-day 21.000 563,940 11,842,740
-
Rent of Equipment : -
- Forklift unit-day 2.000 1,925,000 3,850,000
TOTAL Install 'LV power cable, control cable & optical cable 43,112,740
An 14 Bare Alluminium conductor of 1 x TAL 850 sqmm/phase for 3 phase (m) m #REF!
Remuneration
- Foreman man-day 0.063 #REF! #REF!
- Skill Worker man-day 0.125 #REF! #REF!
- Worker man-day 0.250 #REF! #REF!
- Electrical Technician man-day 0.063 #REF! #REF!

Rent of Equipment :
- Truck crane 3 ton unit-day 0.000 #REF! #REF!
TOTAL Bare Alluminium conductor of 1 x TAL 850 sqmm/phase for 3 phase (m) #REF!
Panjang 3 phase per Line Bay = 14 m #REF!
Install untuk 2 Bay #REF!
An 15 Bare Alluminium conductor of 2 x TAL 630 sqmm/phase for 3 phase (m) m #REF!
Remuneration
- Foreman man-day 6.000 #REF! #REF!
- Skill Worker man-day 12.000 #REF! #REF!
- Worker man-day 30.000 #REF! #REF!
- Electrical Technician man-day 6.000 #REF! #REF!

Rent of Equipment :
- Truck crane 3 ton unit-day 0.000 #REF! #REF!
TOTAL Bare Alluminium conductor of 2 x TAL 630 sqmm/phase for 3 phase (m) #REF!
An 16 Bare Alluminium conductor of 1 x TAL 630 sqmm/phase for 3 phase (m) m #REF!
Remuneration
- Foreman man-day 6.000 #REF! #REF!
- Skill Worker man-day 12.000 #REF! #REF!
- Worker man-day 30.000 #REF! #REF!
- Electrical Technician man-day 6.000 #REF! #REF!

Rent of Equipment :
- Truck crane 3 ton unit-day 0.000 #REF! #REF!
TOTAL Bare Alluminium conductor of 1 x TAL 630 sqmm/phase for 3 phase (m) #REF!
An 17 Install Conventional control and protection panel (separated panel box) #REF!
Remuneration
- Foreman man-day 4.000 #REF! #REF!
- Skill Worker man-day 24.000 177,600 4,262,400
- Worker man-day 28.000 #REF! #REF!
- Mekanik man-day 12.000 #REF! #REF!
- Electrical Technician man-day 12.000 #REF! #REF!
-
Rent of Equipment : -
- Truck crane 3 ton unit-day 0.000 #REF! #REF!
TOTAL Install Conventional control and protection panel (separated panel box) #REF!
An 18 Install clamps connectors and accessories Bay 3,360,880
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 2.000 130,000 260,000
- Mekanik man-day 1.000 350,000 350,000
- Electrical Technician man-day 2.000 563,940 1,127,880
-
Rent of Equipment : -
- Scaffolding unit-day 1.000 1,008,000 1,008,000

An 19 Erection Post Steel and Beam Steel Structure (1 ton) 2,989,794


A Sortir Material of Steel Structure
Remuneration
- Worker man-day 0.000 130,000 -
- Foreman man-day 0.000 215,000 -
-
B Erection Steel Structure -
Remuneration -
- Steel Worker man-day 5.000 100,000 500,000
- Worker man-day 5.000 130,000 650,000
- Foreman man-day 1.000 215,000 215,000
- Foreman/Technician/Inspector man-day 1.000 482,000 482,000

C Penyetelan and Pengencangan baut


- Worker man-day 5.000 130,000 650,000
- Foreman man-day 1.000 215,000 215,000

Rent of Equipment : -
- Katrol and peralatan erection Gantry unit/day 3.000 37,950 113,850
- Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan safety unit/day 1.000 163,944 163,944
- Bambu stick 0.000 18,975 -
Harga Per Ton 2,989,794
Harga Per Kg 2,990
Post Steel Structure (18 m) 2862 8,556,790
Post Steel Structure (9 m) from Kg 1929 5,767,313
Beam steel structure Type-1 for Fly Bus (14 m) 1268 3,791,059
An 20 SUBSTATION EARTHING SYSTEM
Copper strip or flexible conductors of the cross section specified, installed so as to
A form a grid system laid directly in the ground enclosing the complete substation 1 Ls 12,967,135
together with all accessories
Remuneration
- Worker man-day 6.000 130,000 780,000
- Worker Leader man-day 1.000 170,000 170,000
- Foreman/Technician/Inspector man-day 1.000 215,000 215,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Alat elektronik untuk pengukuran unit/day 2.000 550,000 1,100,000
- Eskavator kecil unit/day 1.000 2,816,000 2,816,000
- Peralatan cangkul set/day 6.000 64,240 385,440
- Alat press conductor unit/day 2.000 220,000 440,000
Total 6,518,580
Copper strip or flexible conductors to connect metalclad parts of all equipment,
B 1 Ls
structures and overhead line gantry to main Earth System with all accessories
Remuneration
- Worker man-day 6.000 130,000 780,000
- Worker Leader man-day 1.000 170,000 170,000
- Foreman/Technician/Inspector man-day 1.000 215,000 215,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Alat elektronik untuk pengukuran unit/day 2.000 550,000 1,100,000
- Peralatan cangkul set/day 6.000 64,240 385,440
- Alat press conductor unit/day 2.000 220,000 440,000
Total 3,702,580
Copper strip or flexible conductors to bond all overhead line towers direct to the
C 1 Ls
substation Earth System.
Remuneration
- Worker man-day 3.000 130,000 390,000
- Worker Leader man-day 1.000 170,000 170,000
- Foreman/Technician/Inspector man-day 0.500 215,000 107,500
- Engineer man-day 0.250 612,140 153,035

Rent of Equipment :
- Alat elektronik untuk pengukuran unit/day 2.000 550,000 1,100,000
- Peralatan cangkul set/day 6.000 64,240 385,440
- Alat press conductor unit/day 2.000 220,000 440,000
Total 2,745,975
An 21 Fly Bus and Jumper connector (single/double conductor & string set) lenght 28 m' / set #REF!
Remuneration
- Worker man-hour 4.000 #REF! #REF!
- Skill Worker man-hour 1.000 #REF! #REF!
- Steel Erection Worker man-hour 0.000 #REF! #REF!
- Foreman man-hour 1.000 #REF! #REF!
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 -
- Peralatan bantu lot 1.000 10,880 10,880
Total #REF!
An 22 Fly Bus and Jumper connector (single/double conductor & string set) lenght 14 m' / set #REF!
Remuneration
- Worker man-hour 4.000 #REF! #REF!
- Skill Worker man-hour 1.000 #REF! #REF!
- Steel Erection Worker man-hour 0.000 #REF! #REF!
- Foreman man-hour 1.000 #REF! #REF!
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 139,800 -
- Peralatan bantu lot 1.000 11,000 11,000
Total #REF!
An 23 Fly Bus and Jumper connector untuk Kopel Back to Back (single/double conductor & string #REF!
Remuneration
- Worker man-hour 10.000 #REF! #REF!
- Skill Worker man-hour 10.000 #REF! #REF!
- Steel Erection Worker man-hour 4.000 #REF! #REF!
- Foreman man-hour 1.000 #REF! #REF!
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 139,800 -
- Peralatan bantu lot 1.000 11,000 11,000
Total #REF!
An 24 Install Sistem Grounding/ 100 m' #REF!
Remuneration
- Foreman man-hour 1.000 #REF! #REF!
- Skill Worker man-hour 10.000 #REF! #REF!
- Worker man-hour 20.000 #REF! #REF!
- Steel Erection Worker man-hour 0.000 #REF! #REF!
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 #REF! #REF!
- Peralatan bantu lot 1.000 10,880 10,880
#REF!
Total per Bay Panjang 404.000 #REF!
Total per 2 Bay Panjang 808.000 #REF!
An 25 Install Trafo and Accesoriesnya
A Install Trafo 150/70 kV, 100 MVA, and Accesoriesnya 30,658,944
Remuneration
- Foreman man-hour 3.000 215,000 645,000
- Skill Worker man-hour 6.000 200,000 1,200,000
- Worker man-hour 30.000 130,000 3,900,000
- Steel Erection Worker man-hour 0.000 100,000 -

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 24.000 1,031,250 24,750,000
- Peralatan bantu lot 1.000 163,944 163,944
30,658,944
B Install Trafo 150/70 kV, 60 MVA /30 MVA and Accesoriesnya 30,658,944
Remuneration
- Foreman man-hour 3.000 215,000 645,000
- Skill Worker man-hour 6.000 200,000 1,200,000
- Worker man-hour 30.000 130,000 3,900,000
- Steel Erection Worker man-hour 0.000 100,000 -

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 24.000 1,031,250 24,750,000
- Peralatan bantu lot 1.000 163,944 163,944
30,658,944
C Install Auxillary Tranformer 20/0,4 kV and Accesoriesnya 9,678,944
Remuneration
- Foreman man-hour 1.000 215,000 215,000
- Skill Worker man-hour 2.000 200,000 400,000
- Worker man-hour 5.000 130,000 650,000
- Steel Erection Worker man-hour 0.000 100,000 -

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 8.000 1,031,250 8,250,000
- Peralatan bantu lot 1.000 163,944 163,944
9,678,944
An 26 Neutral Grounding Resistor (NGR) 9,948,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 4.000 200,000 800,000
- Worker man-day 4.000 130,000 520,000
- Steel Erection Worker man-day 0.000 100,000 -
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 8.000 1,031,250 8,250,000
- Peralatan bantu lot 1.000 163,944 163,944
9,948,944
An 27 Install Fire Prevention System untuk Trafo 10,728,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 4.000 200,000 800,000
- Worker man-day 10.000 130,000 1,300,000
- Steel Erection Worker man-day 0.000 100,000 -
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 8.000 1,031,250 8,250,000
- Peralatan bantu lot 1.000 163,944 163,944
10,728,944
An 28 Install Capacitor 19,838,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 6.000 200,000 1,200,000
- Worker man-day 12.000 130,000 1,560,000
- Steel Erection Worker man-day 2.000 100,000 200,000
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 16.000 1,031,250 16,500,000
- Peralatan bantu lot 1.000 163,944 163,944
19,838,944
An 29 Install Supporting Structure For Y Connection of 1 x Shunt Reactor/IBT 500 kV 1,958,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 3.000 200,000 600,000
- Worker man-day 6.000 130,000 780,000
- Steel Erection Worker man-day 2.000 100,000 200,000
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 163,944 163,944
1,958,944
An 30 Gelar dan pemasangan Power Cable XLPE, 150 kV Single Core or Three Core
A Power Cable 150 kV, dalam Ducting, Cubicle include Cable Support/ 100 m' 6,278,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 10.000 200,000 2,000,000
- Worker man-day 30.000 130,000 3,900,000
- Steel Erection Worker man-day 0.000 100,000 -

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 163,944 163,944
6,278,944
B Power Cable 150 kV, dalam galian include Cable Support/ 100 m' 13,578,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 40.000 200,000 8,000,000
- Worker man-day 40.000 130,000 5,200,000
- Steel Erection Worker man-day 0.000 100,000 -

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 163,944 163,944
13,578,944
C Terminasi Kabel 150 kV / Set 1,368,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 3.000 200,000 600,000
- Worker man-day 3.000 130,000 390,000
- Steel Erection Worker man-day 0.000 100,000 -

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 163,944 163,944
1,368,944
D Pemasangan Link Box with SVL 1,368,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 3.000 200,000 600,000
- Worker man-day 3.000 130,000 390,000
- Steel Erection Worker man-day 0.000 100,000 -

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 163,944 163,944
1,368,944
An 31 Gelar dan pemasangan Power Cable XLPE, 20 kV Single Core or Three Core
A Power Cable 150 kV/20 kV, Transformer and 20 kV inc Cubicle incl Cable Support 14,928,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 12.000 200,000 2,400,000
- Worker man-day 30.000 130,000 3,900,000
- Steel Erection Worker man-day 0.000 100,000 -

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 8.000 1,031,250 8,250,000
- Peralatan bantu lot 1.000 163,944 163,944
14,928,944
B Power Cable 150 kV/20 kV Transformer, and NGR 1,758,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 3.000 200,000 600,000
- Worker man-day 6.000 130,000 780,000
- Steel Erection Worker man-day 0.000 100,000 -

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 163,944 163,944
1,758,944
C Power Cable between Bus Section Group-1 and Bus Riser Group-2 incl Cable Support 4,728,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 12.000 200,000 2,400,000
- Worker man-day 15.000 130,000 1,950,000
- Steel Erection Worker man-day 0.000 100,000 -

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 163,944 163,944
4,728,944
D Power Cable between 20 kV Aux, Trafo Cubicle, and the Aux Trafo, incl Cable Support 2,278,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 3.000 200,000 600,000
- Worker man-day 10.000 130,000 1,300,000
- Steel Erection Worker man-day 0.000 100,000 -
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 163,944 163,944
2,278,944
E Gelar Kabel Power 20 kV per 100 m (dalam Ducting) 3,328,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 5.000 200,000 1,000,000
- Worker man-day 15.000 130,000 1,950,000
- Steel Erection Worker man-day 0.000 100,000 -
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 163,944 163,944
3,328,944
An 32 Pemasangan LV power cable for Control and Protection/ Bay 6,956,000
Remuneration
- Foreman man-day 3.000 215,000 645,000
- Skill Worker man-day 12.000 200,000 2,400,000
- Worker man-day 30.000 130,000 3,900,000
- Steel Erection Worker man-day 0.000 100,000 -
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 11,000 11,000
6,956,000
An 33 20 kV Indoor Metalclad Switchgear Single-Busbar Scheme Comprising :
A Incoming Cubicle comprising : 5,538,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 2.000 130,000 260,000
- Steel Erection Worker man-day 1.000 100,000 100,000

Rent of Equipment :
- Sewa Crane 5 ton (incl. Opr + BBM) hour 8.000 550,000 4,400,000
- Peralatan bantu lot 1.000 163,944 163,944
5,538,944
B Outgoing Feeder Cubicle comprising : 5,538,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 2.000 130,000 260,000
- Steel Erection Worker man-day 1.000 100,000 100,000

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 8.000 550,000 4,400,000
- Peralatan bantu lot 1.000 163,944 163,944
5,538,944
C Bus Section Cubicle (Bus Couple Cubicle) comprising : 5,538,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 2.000 130,000 260,000
- Steel Erection Worker man-day 1.000 100,000 100,000

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 8.000 550,000 4,400,000
- Peralatan bantu lot 1.000 163,944 163,944
5,538,944
D Busbar PT + Earthing Switch Cubicle comprising : 5,538,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 2.000 130,000 260,000
- Steel Erection Worker man-day 1.000 100,000 100,000

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 8.000 550,000 4,400,000
- Peralatan bantu lot 1.000 163,944 163,944
5,538,944
E Auxiliary Transformer Cubicle 5,538,944
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 2.000 130,000 260,000
- Steel Erection Worker man-day 1.000 100,000 100,000

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 8.000 550,000 4,400,000
- Peralatan bantu lot 1.000 163,944 163,944
5,538,944
An 34 TELECOMUNICATION EQUIPMENT (Existing SDH Rembang S/S and Blora S/S AB 31,034,820
A Node SDH-ADM 9,064,560
Remuneration
- Foreman man-day 4.000 215,000 860,000
- Technician man-day 8.000 482,000 3,856,000
- Electrician man-day 4.000 175,000 700,000
- Engineer man-day 4.000 612,140 2,448,560

Rent of Equipment :
- Sewa Laptop hour 0.000 -
- Peralatan bantu lot 4.000 300,000 1,200,000
9,064,560
B STM-1/4 Line Interface 2,441,140
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Technician man-day 2.000 482,000 964,000
- Electrician man-day 2.000 175,000 350,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 300,000 300,000
2,441,140
C 2 MB Interface 2,441,140
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Technician man-day 2.000 482,000 964,000
- Electrician man-day 2.000 175,000 350,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 300,000 300,000
2,441,140
D DIU Data Interfacing Unit 64 Kbps 2,441,140
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Technician man-day 2.000 482,000 964,000
- Electrician man-day 2.000 175,000 350,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 300,000 300,000
2,441,140
E VF 2/4 Wire E/M Interface 2,441,140
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Technician man-day 2.000 482,000 964,000
- Electrician man-day 2.000 175,000 350,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 300,000 300,000
2,441,140
F FXO and FXS card included with telephone subscriber and extention PAX existing at Rembang & telephone subscriber 2,441,140
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Technician man-day 2.000 482,000 964,000
- Electrician man-day 2.000 175,000 350,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 300,000 300,000
2,441,140
G Ethernet Interface 2,441,140
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Technician man-day 2.000 482,000 964,000
- Electrician man-day 2.000 175,000 350,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 300,000 300,000
2,441,140
H All of the SDH-ADM software tools included MIB files for supporting telecommunication network management system (SNMO Protocols) 2,441,140
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Technician man-day 2.000 482,000 964,000
- Electrician man-day 2.000 175,000 350,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 300,000 300,000
2,441,140
I MDF Main Distribution Frame 2,441,140
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Technician man-day 2.000 482,000 964,000
- Electrician man-day 2.000 175,000 350,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 300,000 300,000
2,441,140
J Rack/Cabinet 2,441,140
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Technician man-day 2.000 482,000 964,000
- Electrician man-day 2.000 175,000 350,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 300,000 300,000
2,441,140
K Digital Teleprotection 2,441,140
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Technician man-day 2.000 482,000 964,000
- Electrician man-day 2.000 175,000 350,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 300,000 300,000
2,441,140
L Miscellaneous equipment and Material including cables, patch cord, pig tail, telephone cable, connectors, compression 2,441,140
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Technician man-day 2.000 482,000 964,000
- Electrician man-day 2.000 175,000 350,000
- Engineer man-day 1.000 612,140 612,140

Rent of Equipment :
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
- Peralatan bantu lot 1.000 300,000 300,000
2,441,140
An 35 AC SUPPLY EQUIPMENT FOR SUBSTATION AUTOMATIC
A Inverter 110VDC to 220VAC 50Hz dengan kapasitas 2X beban (redundant) #REF!
Remuneration
- Foreman man-hour 1.000 #REF! #REF!
- Skill Worker man-hour 2.000 #REF! #REF!
- Worker man-hour 2.000 #REF! #REF!
- Steel Erection Worker man-hour 1.000 #REF! #REF!
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 #REF! #REF!
- Peralatan bantu lot 1.000 #REF! #REF!
#REF!
B AC Distribution Board #REF!
Remuneration
- Foreman man-hour 1.000 #REF! #REF!
- Skill Worker man-hour 2.000 #REF! #REF!
- Worker man-hour 2.000 #REF! #REF!
- Steel Erection Worker man-hour 1.000 #REF! #REF!
-
Rent of Equipment : -
- Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 #REF! #REF!
- Peralatan bantu lot 1.000 #REF! #REF!
#REF!
An 36 150 kV SUBSTATION AUXILIARIES EQUIPMENT
A 110 V DC Battery suitable for supplying all 110 V DC load for 8 hours discharge 10,097,616
Remuneration
- Foreman man-day 4.000 215,000 860,000
- Technician man-day 8.000 482,000 3,856,000
- Electrician man-day 8.000 175,000 1,400,000
- Engineer man-day 4.000 612,140 2,448,560

Rent of Equipment : -
- Peralatan Pengujian Baterai hour 4.000 308,264 1,233,056
- Peralatan bantu lot 1.000 300,000 300,000
10,097,616
B Battery charger min. 60 A for 110V DC Battery complete with Panel Board (subject to calculation) 2,508,056
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Worker man-day 2.000 130,000 260,000
- Steel Erection Worker man-day 1.000 100,000 100,000

Rent of Equipment :
- Peralatan Pengujian Baterai hour 4.000 308,264 1,233,056
- Peralatan bantu lot 1.000 300,000 300,000
2,508,056
C 110V DC Switch Fuse Distribution Board suitable for 110V DC battery set, HV equipment of minimum 10 bays, MV switchgear, etc 2,237,500
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Electrician man-day 2.000 130,000 260,000
- Steel Erection Worker man-day 1.000 100,000 100,000

Rent of Equipment :
- Forklift hour 4.000 240,625 962,500
- Peralatan bantu lot 1.000 300,000 300,000
2,237,500
D 400V AC Switch Fuse Distribution Board suitable for the 2 (two) units station service transformer 2,237,500
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Electrician man-day 2.000 130,000 260,000
- Steel Erection Worker man-day 1.000 100,000 100,000

Rent of Equipment :
- Forklift hour 4.000 240,625 962,500
- Peralatan bantu lot 1.000 300,000 300,000
2,237,500
E 20/0.4 kV ≥ 200 kVA 3-phase station auxiliary transformer complete with necessary accessories (vector group DYn 5) 2,367,500
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Electrician man-day 3.000 130,000 390,000
- Steel Erection Worker man-day 1.000 100,000 100,000

Rent of Equipment :
- Forklift hour 4.000 240,625 962,500
- Peralatan bantu lot 1.000 300,000 300,000
2,367,500
F LV power cable, control cable and accesorries and necessary equipment (cable ladder, clamp, cable lug, terminal, etc.) 2,237,500
Remuneration
- Foreman man-day 1.000 215,000 215,000
- Skill Worker man-day 2.000 200,000 400,000
- Electrician man-day 2.000 130,000 260,000
- Steel Erection Worker man-day 1.000 100,000 100,000

Rent of Equipment :
- Forklift hour 4.000 240,625 962,500
- Peralatan bantu lot 1.000 300,000 300,000
2,237,500
An 37 Ground Wire Steel (GSW) 70 mm2 for shield wire for installation of shield wire as specifi 1,505,000
Remuneration
Foreman man-hour 1.000 215,000 215,000
Skill Worker man-hour 2.000 200,000 400,000
Electrician man-hour 3.000 130,000 390,000
Steel Erection Worker man-hour 2.000 100,000 200,000
-
Rent of Equipment : -
Sewa Crane 30 ton (incl. Opr + BBM) hour 0.000 1,031,250 -
Peralatan bantu lot 1.000 300,000 300,000
1,505,000
Total 2 Bay 3,010,000
An 38 Komisioning (Pengujian Individual dan Function) #REF!
Remuneration
- Supervisor manday 1.00 #REF! #REF!
- Skill Worker manday 2.00 #REF! #REF!
- Worker manday 3.00 #REF! #REF!
- Engineer Expert manday 1.00 #REF! #REF!
- Electrical Technician manday 2.00 #REF! #REF!

Rent of Equipment :
- Megger unitday 1.00 #REF! #REF!
- Injection primer & sekunder unitday 1.00 #REF! #REF!
- HV Apparatus Analyzer unitday 1.00 #REF! #REF!

An 39 Komisioning (Pengujian Individual dan Function) #REF!


Remuneration
- Supervisor manday 0.50 #REF! #REF!
- Skill Worker manday 1.00 #REF! #REF!
- Worker manday 1.50 #REF! #REF!
- Engineer Expert manday 0.50 #REF! #REF!
- Electrical Technician manday 1.00 #REF! #REF!

Rent of Equipment :
- Megger unitday 0.50 #REF! #REF!
- Injection primer & sekunder unitday 0.50 #REF! #REF!
- HV Apparatus Analyzer unitday 0.50 #REF! #REF!
REVISI Profil Kg/m
15/Apr/19 L.40.40.4 1.83
Jakarta L.40.40.5 2.95
L.45.45.4 2.74
L.45.45.5 3.38
L.50.50.4 3.06
KETERANGAN L.50.50.6 4.43

PERMEN PUPR 2016 HAL 573

L.50.50.5 3.77

0.076

PERMEN PUPR 2016 HAL 574

0.076

PERMEN PUPR 2016 HAL 574

0.076

LA. 03 hal 176 and PERMEN PUPR 2016 HAL 346

PERMEN PUPR 2016 HAL 571

Catatan: dalam PERMEN, satuan : liter, dalam jurnal, satuan: kaleng


PERMEN PUPR HAL 88
PERMEN PUPR HAL 572

SDA: A.1.1 hal 69 + tambahan sewa mesin pemotong rumput


PERMEN PUPR 2016 HAL 575

Permen PU halaman 207

PERMEN PUPR 2016 HAL 581


SNI 2835 TAHUN 2008, HAL 3

PERMEN PUPR 2016 HAL 581


SNI 2835 TAHUN 2008, HAL 3

SNI 2835 TAHUN 2008, HAL 3


galian tanah keras hingga kedalaman 2 meter

SNI 2835 TAHUN 2008, HAL 3


galian tanah keras hingga kedalaman 2 meter

SNI 2835 TAHUN 2008, HAL 3


galian tanah keras hingga kedalaman 2 meter

SNI 2835 TAHUN 2008, HAL 3


galian tanah keras hingga kedalaman 2 meter
Permen PUPR hal 92

SNI 2835 TAHUN 2008, HAL 3


PERMEN PUPR 2016 HAL 580

SNI 2835 TAHUtanah berbatuan Kedalaman 1 meter

SNI 2835 TAHUtanah berbatuan Kedalaman 1 meter

permen pu 2013 Halaman 207

SNI 2835 TAHUN 2008, HAL 3


galian tanah keras hingga kedalaman 2 meter

PERMEN PUPR 2016 HAL 582


UIP ISJ

PERMEN PUPR
SNI 2835 2008
PERMEN PUPR 2016 HAL 582

permen pu 2013 Halaman 207

3.4182636514

A.2.3.1.11 hal 381

A.2.3.1.11 hal 381

A.2.3.1.11
Orang Hari Koefisien

PERMEN PUPR
PU 2012 Hal 91
timbunan + Pemadatan pasir

PERMEN PUPR
timbunan + Pemadatan pasir

tidak ada dalam PERMEN


tidak tercantum upah

SNI 2835 TAHUN 2008, HAL 3

tidak ada dalam PERMEN


tidak tercantum upah

PERMEN PUPR 2016 HAL 582

A.4.4.1.7 hal 432

Catatan: dalam PERMEN, satuan: m3. dalam jurnal, satuan buah

A.4.4.1.9 hal 433

Catatan: dalam PERMEN, satuan: m3. dalam jurnal, satuan buah


A.4.4.1.7 hal 432

Catatan: dalam PERMEN, satuan: m3. dalam jurnal, satuan buah

A.4.4.1.9 hal 433

Catatan: dalam PERMEN, satuan: m3. dalam jurnal, satuan buah

SNI 6897:2008 No.6.3

Catatan: dalam PERMEN, satuan: m3. dalam jurnal, satuan buah

SNI 6897:2008 No.6.22

Catatan: dalam PERMEN, satuan: m3. dalam jurnal, satuan buah

PU 2012 Hal 106

PU 2012 Hal 106

PU 2012 Hal 106

A.4.4.2.27 hal 454


tidak ada dalam PERMEN

tidak ada dalam PERMEN

PUPR 2016 Hal 244/592

230 1
893 3.9
1027 4.5

PUPR 2016 Hal 244/590

247 1 50.816327
869 3.5 8.4693878
999 4.0 42.346939

PUPR 2016 Hal 246/592

326 1
760 2.3
1029 3.2

PUPR 2016 Hal 249 + 257

371 1
698 1.9
1047 2.8

PUPR 2016 HAL 254

PUPR 2016 HAL 250 + 257

384 1
692 1.8
1039 2.7

PUPR 2016 HAL 252 + 257

413 1
681 1.6
1021 2.5

PUPR 2016 HAL 254

448 1
667 1.5
1000 2.2

B.10 hal 129

PUPR 2016 HAL 258

P.01 hal 90
SNI 2836-2008 HAL 4
PermenPUPR 2016 Hal 184

PermenPUPR 2016 Hal 184


PermenPUPR 2016 Hal 184 SNI 2836-2008 HAL 4

PermenPUPR 2016 Hal 184 SNI 2836-2008 HAL 4

PermenPUPR 2016 Hal 184 SNI 2836-2008 HAL 4

PermenPUPR 2016 Hal 184 SNI 2836-2008 HAL 4

PermenPUPR 2016 Hal 589

B.27 hal 141

2 kali pemakaian

B.27 hal 141

1 kali pemakaian

B.27 hal 141


PM 78 thn 2014
SNI 7394-2008-20
1 kali pemakaian
B.27 hal 141
Permen PUPR Hal 283

2 kali pemakaian

B.27 hal 141


PM 78 th 2014 Hal 270

1 kali pemakaian
B.27 hal 141
PM 78 th 2014 Hal 270

1 kali pemakaian
B.27 hal 141
PM 78 th 2014 Hal 270

1 kali pemakaian
B.27 hal 141
PM 78 th 2014 Hal 270

1 kali pemakaian
B.27 hal 141
Permen PUPR Hal 283

2 kali pemakaian

PUPR 2016 HAL 259 SNI 7394-2008-17

PUPR 2016 HAL 259 SNI 7394-2008-17

Dia A (cm2)
Berat Nominal (Kg/m) keliling
8 0.5027 0.395 5.024
10 0.7854 0.617
13 1.327 1.04
16 2.011 1.58
19 2.835 2.23
22 3.801 2.96
25 4.909 3.85
29 60625 5.18
32 8.042 6.31

PUPR 2016 HAL 260 SNI 7394-2008-17

PUPR 2016 HAL 260 SNI 7394-2008-17

Dia A (cm2)
Berat Nominal (Kg/m) keliling
8 0.5027 0.395 5.024
10 0.7854 0.617
13 1.327 1.04
16 2.011 1.58
19 2.835 2.23
22 3.801 2.96
25 4.909 3.85
29 60625 5.18
32 8.042 6.31

tdk ada dalam PERMEN

PUPR 2016 HAL 260/600

F.03 hal 152

berbeda dengan permen, permen


F.03 hal langsung
152 menggambarka 1 tiang pancang sedangkan PLNE dengan harga masing2 bahan tiang pancang
diskusi ke uip V dahulu
berbeda dengan permen, permen
F.03 hal langsung
152 menggambarka 1 tiang pancang sedangkan PLNE dengan harga masing2 bahan tiang pancang

Dia A (cm2) W(Kg/m)


8 0.5027 0.395
10 0.7854 0.617 keliling
13 1.327 1.04 5.024
16 2.011 1.58
19 2.835 2.23
22 3.801 2.96
25 4.909 3.85
29 60625 5.18
32 8.042 6.31

tidak ada dalam PERMEN

F.08 hal. 154

tidak ada dalam PERMEN


Orang Hari
2 0.063
1 0.063
1 0.031

1 0.167

Orang Hari
2 0.125
1 0.063

1 0.125
1 0.125

Keliling tower Jumlah Dolken per meter


1 8 cm
0.125 2 0.25 1m 100 cm
0.0125 2 0.025 1 12.5

B.40 hal. 148

B.40 hal. 148

permen pu hal 94

A.2.2.1.13 hal. 375


permen pu hal 94

PUPR 2016 Hal 287

PUPR 2016 Hal 288


jumlah orang Hari
5 orang 0.5 hari
1 orang 0.5 hari

Jumlah Alat Hari


1 unit 0.5 hari
2 unit 0.5 hari
1 unit 0.5 hari
2 unit 0.5 hari

Permen PU Hal 148


permen pu 2013 Halaman 207

Rewinding
2 org 12.5 100 m / hari
2 org 12.5 hari
1 org 12.5 hari
1 org 12.5 hari
Permen PU Hal 375

Permen PU Hal 148

A.4.5.2.40 hal. 510

Jurnal 2016 hal 337

Jurnal 2016 hal 338

Jurnal 2016 hal 338

A.4.5.1.7 hal 489


A.4.5.1.7 hal 489

tidak ada dalam PERMEN

A.4.4.3.13 hal. 460

Cat: dalam PERMEN, satuan buah. Dalam jurnal, satuan m2

50,368

A.4.4.3.10 hal 459

Cat: dalam PERMEN, satuan buah. Dalam jurnal, satuan m2

tidak ada dalam PERMEN

A.4.4.3.11 hal 459

Cat: dalam PERMEN, satuan buah. Dalam jurnal, satuan m2

A.4.4.3.9 hal. 458

Cat: dalam PERMEN, satuan buah. Dalam jurnal, satuan m2


A.4.4.3.28 hal. 468

A.4.4.3.21 hal. 464

SNI 7395 2008

Cat: dalam PERMEN, satuan buah. Dalam jurnal, satuan m2

146,906

SNI 7395 2008

Cat: dalam PERMEN, satuan buah. Dalam jurnal, satuan m2

146,906

SNI 7395 2008

Cat: dalam PERMEN, satuan buah. Dalam jurnal, satuan m2

50,368

SNI 7395 2008

Cat: dalam PERMEN, satuan buah. Dalam jurnal, satuan m2

188,879
SNI 7395 2008

Cat: dalam PERMEN, satuan buah. Dalam jurnal, satuan m2

188,879

A.4.4.3.28 hal. SNI 7395-2008


SNI 7395 2008

Cat: dalam PERMEN, satuan buah. Dalam jurnal, satuan m2

56,856

A.4.4.3.28 hal. SNI 7395-2008

A.4.4.3.18 hal. 463

A.4.5.2.40 hal. 510

A.4.5.2.40 hal. 510

A.4.5.2.40 hal. 510

A.4.5.2.41 hal. 510

A.4.5.2.41 hal.510

A.4.5.2.41 hal.510
A.4.5.2.42 hal. 511

Cat: dalam PERMEN tidak tercantum material roof mesh

A.4.7.1.18 hal. 545

A.4.7.1.18 hal. 545

A.4.7.1.10 hal. 541

A.4.7.1.10 hal. 541

A.4.7.1.10 hal. 541


http://rollingdoorklu.com/
http://rollingdoorklu.com/

1.2 jt 2.2 m
0.5454545
###
3025000
3025000
3025000
3025000

http://olx.co.id/iklan/louvre-jalusi-aluminium-kusen-aluminium-IDiiuPX.html
435.62788

SNI 7395-2008

A.5.1.1.1 hal. 547

294,400

A.5.1.1.1 hal. 547

%
A.5.1.1.4 hal. 549

A.5.1.1.5 hal. 549

A.5.1.1.5 hal. 549

A.4.6.1.21 hal. Cat: dalam PERMEN menggunakan kayu kelas I atau kelas II

#REF!
3025000
435.62788
#REF!

#REF!
#REF!

#REF!
#REF!

SNI 2011
#REF!

tidak ada dalam PERMEN


tidak ada dalam PERMEN

tidak ada dalam PERMEN

kg/m3
bj 1.04
54 0.0192593

http://sewaalatberat-trimurtisugih.blogspot.co.id/p/list-harga-sewa-alat-berat.html

http://sewaalatberat-trimurtisugih.blogspot.co.id/p/list-harga-sewa-alat-berat.html

http://sewaalatberat-trimurtisugih.blogspot.co.id/p/list-harga-sewa-alat-berat.html

tidak ada dalam PERMEN

PUPR 2016 Hal. 523


PUPR 2016 Hal. 523

PUPR 2016 Hal. 523

tidak ada dalam PERMEN

A.4.4.3.61 hal. 484

tidak ada dalam PERMEN

2.1

0.15
0.15
6 m

berat 22.68 kg

1.6 6.048
tidak ada dalam PERMEN

1 3.78 kg Tipe 2

1.6 6.048 kg Tipe 1

2 7.56 kg steel cover

tidak ada dalam PERMEN

berat 22.68 kg
tidak ada dalam PERMEN

berat 22.68 kg

tidak ada dalam PERMEN

berat 22.68 kg

tidak ada dalam PERMEN


TRAY
1 3.78 kg

1.6 6.048 kg

2 7.56 kg

tidak ada dalam PERMEN

22.62
1220mm x 2440mm x 6 mm =145 kg

22.62

1.6666667 22.62
90
1220mm x 2440mm x 6 mm =145 kg
48.7100242

tidak ada dalam PERMEN tidak ada dalam PERMEN

tidak ada dalam PERMEN


tidak ada dalam PERMEN

tidak ada dalam PERMEN

tidak ada dalam PERMEN

22.62
90

1220mm x 2440mm x 6 mm =145 kg


48.710024187

tidak ada dalam PERMEN

2 0 kg steel cover

tidak ada dalam PERMEN

2 0 kg steel cover

tidak ada dalam PERMEN

tidak ada dalam PERMEN

A.5.1.1.17 hal. 555


P.06 hal. 98

F.05 hal 153

tidak ada dalam PERMEN

tidak ada dalam PERMEN

tidak ada dalam PERMEN

0.09

tidak ada dalam PERMEN

tidak ada dalam PERMEN


tidak ada dalam PERMEN
tidak tercantum upah

A.4.2.1.2 hal. 419

tidak ada dalam PERMEN

P.01 (G) hal. 92

A.2.2.1.14 hal. 376

Rata - rata jasa pengeboran sumur dalam di DKI tahun 2016

150,000

Rata - rata jasa pengeboran sumur dalam di DKI tahun 2016


150,000

Rata - rata jasa pengeboran sumur dalam di DKI tahun 2016

150,000

permen pu 2013 Halaman 207

3.4182636514

permen pu 2013 Halaman 207

3.4182636514

permen pu 2013 Halaman 207

3.4182636514

permen pu 2013 Halaman 207

3.4182636514

AHS AKLI DKI

886,721
AHS AKLI DKI

7,371,485

0.375

1.2 jt 2.2 m

P 2
L 2
H 3
12

Orang Target (hari)


2 2
1 2 2.2 m
permen pu 2013 Halaman 207

3.4182636514

http://sinarutamagrounding.indonetwork.co.id/product/air-terminal-tombak-penangkal-petir-splitzen-lapis-tembaga-4341776
http://www.materialgrounding.com/product/bare-copper-bc-p20382.aspx
https://www.bukalapak.com/p/industrial/mesin/148zpi-jual-skun-kabel-sc-240-cable-skun

http://sinarutamagrounding.indonetwork.co.id/product/air-terminal-tombak-penangkal-petir-splitzen-lapis-tembaga-4341776
http://www.materialgrounding.com/product/bare-copper-bc-p20382.aspx
https://www.bukalapak.com/p/industrial/mesin/148zpi-jual-skun-kabel-sc-240-cable-skun

Permen PUPR Hal 216


1 Group
Orang/grup total org Target Selesai Coefisien
2 2 0.5 hari 1
1 1 0.5 hari 0.5

1 Group
Orang/grup total org Hari Coef
4 4 1 4
3 3 1 3
1 1 1 1
1 1 0.5 0.5

1 Group
Orang/grup total org Hari Coef
5 5 1 5
10 10 1 10
1 1 1 1
1 1 0.5 0.5

Tools unit Coef


stick stick 0
unit / day unit / day 0
meter meter 0
unit/day unit/day 0
unit/day unit/day 0

1 Group
Orang/grup total org Hari Coef
4 4 1 4
10 10 1 10
1 1 1 1
1 1 0.5 0.5

Tools unit Coef


stick stick 0
unit / day unit / day 0
meter meter 0
1 Group
Orang/grup total org Hari Coef Kg beban angkut jarak langkah waktu pp istirahat total waktu kerja
1 1 1 1 765 45 500 1 9.00 18.00 10.00 28.00 480.00
1 1 1 1 kg meter m/detik menit menit menit menit menit

1 Group
Orang/grup total org Hari Coef Kg beban angkut jarak langkah waktu pp istirahat total waktu kerja
1 1 1 1 450 45 1000 1 17.00 34.00 10.00 44.00 480.00
1 1 1 1 kg meter m/detik menit menit menit menit menit

1 Group
Orang/grup total org Hari Coef Kg beban angkut jarak langkah waktu pp istirahat total waktu kerja
1 1 1 1 360 45 1500 1 25.00 50.00 10.00 60.00 480.00
1 1 1 1 kg meter m/detik menit menit menit menit menit

1 Group
Orang/grup total org Hari Coef Kg beban angkut jarak langkah waktu pp istirahat total waktu kerja
1 1 1 1 450 45 500 0.5 17.00 34.00 10.00 44.00 480.00
1 1 1 1 kg meter m/detik menit menit menit menit menit

Kapasitas per rit/hari Hari


450 10.00 1

1 Group
Orang/grup total org Hari Coef Kg beban angkut jarak langkah waktu pp istirahat total waktu kerja
1 1 1 1 270 45 1000 0.5 34.00 68.00 10.00 78.00 480.00
1 1 1 1 kg meter m/detik menit menit menit menit menit

Kapasitas per rit/hari Hari


270 6.00 1

1 Group
Orang/grup total org Hari Coef Kg beban angkut jarak langkah waktu pp istirahat total waktu kerja
1 1 1 1 180 45 1500 0.5 50.00 100.00 10.00 110.00 480.00
1 1 1 1 kg meter m/detik menit menit menit menit menit

Kapasitas per rit/hari Hari


180 4.00 1

1 Group
Orang/grup total org Hari Coef Kg beban angkut jarak langkah waktu pp istirahat total waktu kerja
1 1 1 1 270 45 500 0.25 34.00 68.00 10.00 78.00 480.00
1 1 1 1 kg meter m/detik menit menit menit menit menit

1 Group
Orang/grup total org Hari Coef Kg beban angkut jarak langkah waktu pp istirahat total waktu kerja
1 1 1 1 135 45 1000 0.25 67.00 134.00 10.00 144.00 480.00
1 1 1 1 kg meter m/detik menit menit menit menit menit

1 Group
Orang/grup total org Hari Coef Kg beban angkut jarak langkah waktu pp istirahat total waktu kerja
1 1 1 1 90 45 1500 0.25 100.00 200.00 10.00 210.00 480.00
1 1 1 1 kg meter m/detik menit menit menit menit menit

1 Group
Orang/grup total org Hari Coef Kg
1 1 1 1 480
0 0

Kapasitas per rit/hari Hari


300 10 1
1 Group
Orang/grup total org Target Selesai Coef
40 40 7 hari 280
3 3 7 hari 21

1 Group
Orang/grup total org Target Selesai Coef
50 50 1 hari 50
5 5 1 hari 5

1 Group
Orang/grup total org Target Selesai Coef
40 40 5 hari 200
3 3 5 hari 15
1 1 5 hari 5
2 2 5 hari 10
0 0 5 hari 0

Alat unit Coef


1 unit / day 5 hari 5
1 hour 8 jam 8
3 unit / day 5 hari 15

1 Group
Orang/grup total org Target Selesai Coef
10 10 2 hari 20
1 1 2 hari 2
1 1 2 hari 2
2 2 2 hari 4
0 0 2 hari 0

Alat unit
0.5 unit / day 2 hari 1
1 hour 4 jam 4
1 unit / day 2 hari 2

2 Group
Orang/grup total org Target Selesai Coef
6 12 2 hari 24
1 2 2 hari 4

Alat unit
2 unit / day 2 hari 4
2 unit / day 5 jam 10

1 Group
Orang/grup total org Target Selesai Coef
40 40 3 hari 120
3 3 3 hari 9
1 1 3 hari 3
2 2 3 hari 6
0 0 3 hari 0

Alat unit Coef


1 unit / day 3 hari 3
1 hour 5 jam 5
3 unit / day 3 hari 9

1 Group
Orang/grup total org Target Selesai Coef
4 4 0.375 hari 1.5
1 1 0.1875 hari 0.1875
0 0 0.1875 hari 0

Alat unit
4 unit / day 0.375 hari 1.5

1 Group
Orang/grup total org Target Selesai Coef
6 6 0.375 hari 2.25
1 1 0.1875 hari 0.1875
0 0 0.1875 hari 0

Alat unit
6 unit / day 0.375 hari 2.25
1 Group
Orang/grup total org Target Selesai Coef
6 6 0.375 hari 2.25
1 1 0.1875 hari 0.1875
0 0 0.1875 hari 0

Alat unit
6 unit / day 0.375 hari 2.25

1 Group
Orang/grup total org Target Selesai Coef
4 4 0.25 hari 1
1 1 0.125 hari 0.125
0 0 0.125 hari 0

Alat unit
4 unit-day 0.25 hari 1

1 Group
Orang/grup total org Target Selesai Coef
6 6 0.25 hari 1.5
1 1 0.125 hari 0.125
0 0 0.125 hari 0

Alat unit
6 unit-day 0.25 hari 1.5

1 Group
Orang/grup total org Target Selesai Coef
4 4 0.075 hari 0.3
1 1 0.075 hari 0.075
0 0 0.075 hari 0

Alat unit
4 unit-day 0.25 hari 1

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.075 hari 0.15
0.5 0.5 0.075 hari 0.0375
0 0 0.075 hari 0

Alat unit
2 unit-day 0.25 hari 0.5

1 Group
Orang/grup total org Target Selesai Coef
4 4 0.375 hari 1.5
1 1 0.1875 hari 0.1875
0 0 0.1875 hari 0

Alat unit
4 unit-day 0.25 hari 1

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.05 hari 0.1
0.5 0.5 0.05 hari 0.025
0 0 0.05 hari 0

Alat unit
2 unit-day 0.25 hari 0.5

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.125 hari 0.25
1 1 0.125 hari 0.125
0 0 0 hari 0

Alat unit
2 unit-day 0.25 hari 0.5

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.0625 hari 0.125
0.5 0.5 0.0625 hari 0.03125
0 0 0 hari 0

Alat unit
2 unit-day 0.25 hari 0.5

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.125 hari 0.25
0.5 0.5 0.125 hari 0.0625
0 0 0 hari 0

Alat unit
2 unit-day 0.25 hari 0.5

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.25 hari 0.5
0.5 0.5 0.25 hari 0.125

Alat unit
2 unit-day 0.25 hari 0.5

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.1875 hari 0.375
0.5 0.5 0.1875 hari 0.09375

Alat unit
2 unit-day 0.25 hari 0.5

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.25 hari 0.5
1 1 0.25 hari 0.25

Alat unit
2 unit-day 0.25 hari 0.5

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.25 hari 0.5
1 1 0.25 hari 0.25

Alat unit
2 unit-day 0.25 hari 0.5

1 Group
Orang/grup total org Target Selesai Coef
0 hari 0
0 hari 0

Alat unit
kg hari 0
kg hari 0

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.25 hari 0.5
1 1 0.25 hari 0.25

Alat unit
2 unit-day 0.25 hari 0.5

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.25 hari 0.5
1 1 0.25 hari 0.25

Alat unit
2 unit-day 0.25 hari 0.5

1 Group
Orang/grup total org Target Selesai Coef
4 4 0.5 hari 2
1 1 0.25 hari 0.25
1 1 0.375 hari 0.375

Alat unit
1 unit-day 0.25 hari 0.25
1 unit-day 0.25 hari 0.25

1 Group
Orang/grup total org Target Selesai Coef
4 4 0.5 hari 2
1 1 0.25 hari 0.25
1 1 0.375 hari 0.375

Alat unit Coef


2 unit-day 0.25 hari 0.5
1 unit-day 0.25 hari 0.25

1 Group
Orang/grup total org Target Selesai Coef
6 6 3 hari 18
6 6 3 hari 18
1 1 3 hari 3
1 1 3 hari 3

Material unit Luas Coef


1.25 no 756 m2 945
0.186 m3 864 m2 160.704

Jml Orng Target Selesai


1 batang 19 kg/batang

8 baut 8 batang besi


1 unit 0.125 day
1 unit 0.0625 day
2 unit 0.25 day
2 unit 0.25 day
2 unit 0.25 day

8 orang 0.5 hari


2 orang 0.5 hari
4 orang 2 hari
2 orang 0.25 hari

Jml Orng Target Selesai


12 batang 1

2 baut 8 batang besi

1 unit 0.125 hari


1 unit 0.0625 hari
2 unit 0.25 hari
1 unit 0.25 hari
2 unit 0.25 hari
1 unit 2 hari

8 orang 0.5 hari


2 orang 0.375 hari
2 orang 2 hari
2 orang 0.25 hari

1 Group
Orang/grup total org Target Selesai Coef
0 hari 0
0 hari 0
0 hari 0
0 hari 0

Material unit per Coef


m3 kg 0
m3 kg 0
pcs kg 0

Equipment unit per Coef


hour day 0

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.25 hari 0.5
1 1 0.25 hari 0.25

Equipment unit per Coef


1 day 0.25 day 0.25

1 Group
Orang/grup total org Target Selesai Coef
1 1 0.0125 hari 0.0125
1 1 0.0125 hari 0.0125
1 1 0.00125 hari 0.00125
1 1 0.00125 hari 0.00125

Material unit per Coef


0.01 kg 1 kg 0.01
0.0125 Ltr 1 kg 0.0125
0.0125 Ltr 1 kg 0.0125

Equipment unit per Coef


1 unit-day 0.0625 day 0.0625

1 Group
Orang/grup total org Target Selesai Coef
4 4 1 hari 4
1 1 1 hari 1
1 1 0.5 hari 0.5

Equipment unit per Coef


4 hour 2 hour 8
2 unit-day 1 day 2

1 Group
Orang/grup total org Target Selesai Coef
1 1 0.0125 hari 0.0125
1 1 0.00125 hari 0.00125
1 1 0.00125 hari 0.00125

Material unit per Coef


0.25 no 1 m 0.25
0.0125 pcs 1 pcs 0.0125

1 Group
Orang/grup total org Target Selesai Coef
0 hari 0
0 hari 0

Material unit per Coef


kg m 0
m pcs 0
pcs pcs 0
1 Group
Orang/grup total org Target Selesai Coef
1 1 0.25 hari 0.25
2 2 0.25 hari 0.5

Material unit per Coef


1 unit-day 0.25 day 0.25
1 unit-day 0.25 day 0.25

1 Group
Orang/grup total org Target Selesai Coef
2 2 0.25 hari 0.5
1 1 0.1 hari 0.1

Material unit per Coef


kg day 0
m day 0

1 Group
Orang/grup total org Target Selesai Coef
2 2 1 hari 2
1 1 0.5 hari 0.5

Equipment unit per Coef


1 unit-day 1 day 1

1 Group
Orang/grup total org Target Selesai Coef
2 2 1 hari 2
1 1 0.5 hari 0.5

Equipment unit per Coef


1 unit-day 0.4 day 0.4

1 Group
Orang/grup total org Target Selesai Coef
2 2 1 hari 2
1 1 0.5 hari 0.5

Equipment unit per Coef


1 unit-day 0.4 day 0.4

1 Group
Orang/grup total org Target Selesai Coef
2 2 1 hari 2
2 #VALUE! 1 hari #VALUE!
1 1 0.5 hari 0.5

Equipment unit per Coef


1 unit-day 0.4 day 0.4

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
4 4 0.25 hari 1
1 1 0.25 hari 0.25
1 1 0.25 hari 0.25
1 1 0.25 hari 0.25

Equipment unit per Coef


1 Unit-day 0.25 day 0.25

Material unit Luas Coef


1 Ls 50 btg 50
1 Roll 1 Roll 1
1 Kg 1 Kg 1

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
12 12 0.5 hari 6
1 1 0.5 hari 0.5
1 1 0.5 hari 0.5

Equipment unit per Coef


6 Unit-day 0.5 day 3
1 Unit-day 0.5 day 0.5

Material unit Luas Coef


1 Roll 1 Roll 1

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
12 12 0.1875 hari 2.25
1 1 0.1875 hari 0.1875
1 1 0.1875 hari 0.1875

Equipment unit per Coef


6 Unit-day 0.1875 day 1.125
1 Unit-day 0.1875 day 0.1875

Material unit Luas Coef


1 Roll 1 Roll 1

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
12 12 0.4 hari 4.8
1 1 0.4 hari 0.4
1 1 0.4 hari 0.4

Equipment unit per Coef


6 Unit-day 0.5 day 3
1 Unit-day 0.5 day 0.5

Material unit Luas Coef


1 Roll 1 Roll 1

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
12 12 0.125 hari 1.5
1 1 0.125 hari 0.125
1 1 0.125 hari 0.125

Equipment unit per Coef


6 Unit-day 0.125 day 0.75
1 Unit-day 0.125 day 0.125

Material unit Luas Coef


1 Roll 1 Roll 1

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
12 12 0.35 hari 4.2
1 1 0.35 hari 0.35
1 1 0.35 hari 0.35

Equipment unit per Coef


6 Unit-day 0.5 day 3
1 Unit-day 0.5 day 0.5

Material unit Luas Coef


1 Roll 1 Roll 1

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
12 12 1.5 hari 18
2 2 1 hari 2
2 2 1 hari 2
2 2 1 hari 2

Equipment unit per Coef


8 Unit-day 1 day 8
2 Unit-day 1 day 2
3 Unit-day 1 day 3
5 Unit-day 1 day 5

Material unit Luas Coef


10 Btg 1 Btg 10
5 Kg 1 Kg 5

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
6 6 0.8 hari 4.8
1 1 0.8 hari 0.8
1 1 0.8 hari 0.8
2 2 0.8 hari 1.6

Equipment unit per Coef


8 Unit-day 0.8 day 6.4
2 Unit-day 0.8 day 1.6
1 Unit-day 0.8 day 0.8
2 Unit-day 0.8 day 1.6

Material unit Luas Coef


5 Btg 1 Btg 5
3 Kg 1 Kg 3

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
6 6 0.8 hari 4.8
1 1 0.8 hari 0.8
1 1 0.8 hari 0.8
2 2 0.8 hari 1.6

Equipment unit per Coef


7 Unit-day 0.8 day 5.6
2 Unit-day 0.8 day 1.6
1 Unit-day 0.8 day 0.8
2 Unit-day 0.8 day 1.6

Material unit Luas Coef


5 Btg 1 Btg 5
3 Kg 1 Kg 3

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
4 4 1 hari 4
2 2 1 hari 2
3 3 1 hari 3
2 2 1 hari 2
1 1 1 hari 1
Equipment unit per Coef
4 Unit-day 1 day 4
2 Unit-day 1 day 2
2 Unit-day 1 day 2
2 Unit-day 1 day 2

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
4 4 0.3 hari 1.2
1 1 0.3 hari 0.3
2 2 0.3 hari 0.6
2 2 0.3 hari 0.6
1 1 0.3 hari 0.3

Equipment unit per Coef


4 Unit-day 0.3 day 1.2
2 Unit-day 0.3 day 0.6
1 Unit-day 0.3 day 0.3
2 Unit-day 0.3 day 0.6

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
4 4 0.3 hari 1.2
1 1 0.3 hari 0.3
2 2 0.3 hari 0.6
2 2 0.3 hari 0.6
1 1 0.3 hari 0.3

Equipment unit per Coef


4 Unit-day 0.3 day 1.2
2 Unit-day 0.3 day 0.6
1 Unit-day 0.3 day 0.3
2 Unit-day 0.3 day 0.6

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
4 4 0.125 hari 0.5
1 1 0.125 hari 0.125
1 1 0.125 hari 0.125

Equipment unit per Coef


4 Unit-day 0.125 day 0.5
1 Unit-day 0.125 day 0.125
1 Unit-day 0.125 day 0.125
1 Unit-day 0.125 day 0.125
1 Unit-day 0.125 day 0.125
1 Unit-day 0.125 day 0.125

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
8 8 0.125 hari 1
1 1 0.125 hari 0.125
1 1 0.125 hari 0.125

Equipment unit per Coef


8 Unit-day 0.125 day 1
2 Unit-day 0.125 day 0.25
2 Unit-day 0.125 day 0.25
2 Unit-day 0.125 day 0.25
2 Unit-day 0.125 day 0.25
2 Unit-day 0.125 day 0.25

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
8 8 0.0625 hari 0.5
1 1 0.0625 hari 0.0625
1 1 0.0625 hari 0.0625

Equipment unit per Coef


8 Unit-day 0.1875 day 1.5
2 Unit-day 0.1875 day 0.375
2 Unit-day 0.1875 day 0.375
2 Unit-day 0.1875 day 0.375
2 Unit-day 0.1875 day 0.375
2 Unit-day 0.1875 day 0.375

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
2 2 0.2 hari 0.4
1 1 0.2 hari 0.2
1 1 0.2 hari 0.2

Equipment unit per Coef


2 Unit-day 0.2 day 0.4
1 Unit-day 0.2 day 0.2

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
2 2 0.2 hari 0.4
1 1 0.2 hari 0.2
1 1 0.2 hari 0.2

Equipment unit per Coef


2 Unit-day 0.2 day 0.4
1 Unit-day 0.2 day 0.2

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
2 2 0.5 hari 1
1 1 0.5 hari 0.5
1 1 0.5 hari 0.5

Equipment unit per Coef


5 Unit-day 0.5 day 2.5

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
4 4 1 hari 4
1 1 1 hari 1
1 1 1 hari 1

Equipment unit per Coef


4 Unit-day 1 hari 4

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
2 2 0.0625 hari 0.125
1 1 0.0625 hari 0.0625
1 1 0.0625 hari 0.0625

Equipment unit per Coef


2 Unit-day 0.0625 hari 0.125

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
2 2 0.0938 hari 0.1875
1 1 0.0938 hari 0.09375
1 1 0.0938 hari 0.09375

Equipment unit per Coef


2 Unit-day 0.0938 hari 0.1875

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
1 1 0.5 hari 0.5
1 1 0.5 hari 0.5

Equipment unit per Coef


2 Unit-day 0.5 day 1

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
3 3 1.5 hari 4.5
1 1 1.5 hari 1.5
1 1 1.5 hari 1.5
1 1 1.5 hari 1.5
1 1 0.5 hari 0.5

Equipment unit per Coef


3 Unit-day 1.5 day 4.5
1 Unit-day 1.5 day 1.5
1 Unit-day 1.5 day 1.5

UIP ISJ 1 Group


Orang/grup total org Target Selesai Coef
15 15 15 hari 225
3 3 15 hari 45
3 3 15 hari 45
3 3 15 hari 45
3 3 15 hari 45

Equipment unit per Coef


15 Unit-day 15 day 225
2 Unit-day 15 day 30
1 Unit-day 30 day 30

UIP II 1 Group
Orang/grup total org Target Selesai Coef
5 5 2 hari 10
1 1 2 hari 2
UIP II 1 Group
Orang/grup total org Target Selesai Coef
1 1 7 hari 7
1 1 7 hari 7

UIP II 1 Group
Orang/grup total org Target Selesai Coef
4 4 4 day 16
4 4 4 day 16
2 2 4 day 8

5 5 4 day 20
2 2 4 day 8

Orang/grup total org Target Selesai Coef


0.5 #REF! 1 hari #REF!
1 #REF! 1 hari #REF!
1.5 #REF! 1 hari #REF!
0.5 #REF! 1 hari #REF!
1 #REF! 1 hari #REF!

Material unit per Coef


0.5 manday 1 day 0.5
0.5 unitday 1 day 0.5
0.5 unitday 1 day 0.5

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
2 2 1 hari 2
3 3 1 hari 3
1 1 1 hari 1

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
5 5 1 hari 5
8 8 1 hari 8
2 2 1 hari 2
2 2 1 hari 2

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
2 2 1 hari 2
3 3 1 hari 3
1 1 1 hari 1

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
5 5 1 hari 5
8 8 1 hari 8
2 2 1 hari 2
2 2 1 hari 2

1 Group
Orang/grup total org Target Selesai Coef
1 1 2 hari 2
3 3 2 hari 6
5 5 2 hari 10
1 1 2 hari 2

1 Group
Orang/grup total org Target Selesai Coef
1 1 2 hari 2
5 5 2 hari 10
8 8 2 hari 16
2 2 2 hari 4
2 2 2 hari 4
1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
2 2 1 hari 2
3 3 1 hari 3
1 1 1 hari 1

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
5 5 1 hari 5
5 5 1 hari 5
2 2 1 hari 2
2 2 1 hari 2

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
2 2 1 hari 2
3 3 1 hari 3
1 1 1 hari 1

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
5 5 1 hari 5
5 5 1 hari 5
2 2 1 hari 2
2 2 1 hari 2

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
2 2 1 hari 2
3 3 1 hari 3
1 1 1 hari 1

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
5 5 1 hari 5
5 5 1 hari 5
2 2 1 hari 2
2 2 1 hari 2

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
1 1 1 hari 1
3 3 1 hari 3
1 1 1 hari 1
1 1 1 hari 1

5.8875

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
2 2 1 hari 2
3 3 1 hari 3
1 1 1 hari 1
1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
5 5 1 hari 5
5 5 1 hari 5
2 2 1 hari 2
2 2 1 hari 2

Skill Worker 1 1 orang 1


Worker 2 2 orang 1
Mekanik 1 1 orang 1
Electrical Technician 1 1 orang 1

1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
2 2 1 hari 2
3 3 1 hari 3
1 1 1 hari 1
2 2 1 hari 2

Kebutuhan Orang Target


7 1 orang 7 hari
14 2 orang 7 hari
8 2 orang 4 hari
14 2 orang 7 hari
Kebutuhan Orang Target
28 2 orang 14 hari
42 6 orang 7 hari
100 10 orang 10 hari
21 3 orang 7 hari

Kebutuhan Orang Target


0.0625 1 orang 0.0625 hari
0.125 2 orang 0.0625 hari
0.25 4 orang 0.0625 hari
0.0625 1 orang 0.0625 hari

Kebutuhan Orang Target


6 2 orang 3 hari
12 4 orang 3 hari
30 10 orang 3 hari
6 2 orang 3 hari

Kebutuhan Orang Target


6 2 orang 3 hari
12 4 orang 3 hari
30 10 orang 3 hari
6 2 orang 3 hari

Kebutuhan Orang Target


4 1 orang 4 hari
24 6 orang 4 hari
28 7 orang 4 hari
12 3 orang 4 hari
12 3 orang 4 hari
1 Group
Orang/grup total org Target Selesai Coef
1 1 1 hari 1
2 2 1 hari 2
3 3 1 hari 3
1 1 1 hari 1
2 2 1 hari 2

Material unit per Coef


1 manday 1 day 1
1 unitday 1 day 1
1 unitday 1 day 1

1 Group
Orang/grup total org Target Selesai Coef
0.5 0.5 1 hari 0.5
1 1 1 hari 1
1.5 1.5 1 hari 1.5
0.5 0.5 1 hari 0.5
1 1 1 hari 1

Material unit per Coef


0.5 manday 1 day 0.5
0.5 unitday 1 day 0.5
0.5 unitday 1 day 0.5
kemampuan angkut
17.00
rit

kemampuan angkut
10.00
rit

kemampuan angkut
8.00
rit

kemampuan angkut
10.00
rit

kemampuan angkut
6.00
rit

kemampuan angkut
4.00
rit

kemampuan angkut
6.00
rit

kemampuan angkut
3.00
rit

kemampuan angkut
2.00
rit
PEMBANGUNAN SUTT 150 kV GI KASONGAN - KUALA KURUN SECTION 4 (T.302-T.377)
UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT

PRICE
NO. UNIT REMARK
(Rp.)
I MATERIAL :
i.A BAHAN BANGUNAN UTAMA
1 Portland Cemen (PC) kg 1,320 Jurnal Kalimantan Tengah 2018 hal 635
2 Colour Cement kg 33,660 Jurnal Kalimantan Tengah 2017 hal 587
3 Crushed Stone 15/20 m3 528,000 HSDS Puruk Cahu 2016
4 Split 1/2 m3 577,500 HSDS Puruk Cahu 2016
5 Split 2/3 m3 577,500 HSDS Puruk Cahu 2016
6 Split 3/5 m3 577,500 HSDS Puruk Cahu 2016
7 Gravel m3 577,500 HSDS Puruk Cahu 2016
8 Sirtu m3 577,500 Jurnal Kalimantan Tengah 2016 hal 765
9 Dust split m3 577,500 Jurnal Kalimantan Barat 2016 hal 753
10 Sand (Pasir Pasang) m3 258,742 HSDS Puruk Cahu 2016
11 Sand (Pasir Urug) m3 184,800 HSDS Puruk Cahu 2016
12 Sand (Pasir Beton) m3 258,750 HSDS Puruk Cahu 2016
13 Soil (Urug/Merah) m3 165,000 Jurnal Kalteng 2018
14 K-100 m3 1,144,000 Jurnal Jakarta 2018 hal
15 K-175 m3 1,232,000 Jurnal Jakarta 2018 hal
16 K-225 m3 1,254,000 Jurnal Jakarta 2018 hal
17 K-350 m3 1,375,000 Jurnal Jakarta 2018 hal
18 Kayu Papan (Meranti) m3 2,457,400 Jurnal Kalteng 2018
19 Kayu Balok - 4 M (Meranti) m3 2,200,000 Jurnal Kalteng 2018
20 Plywood 6 mm sheet 79,200 Jurnal Kalteng 2018
21 Plywood 9 mm sheet 148,500 Jurnal Kalteng 2018
22 Plywood 12 mm sheet 240,790 Jurnal Kalteng 2018
23 Plywood 18 mm sheet 343,200 Jurnal Kalteng 2018
24 Dolken dia. 10-12 cm, length 4 m. stick 16,500 Jurnal Kalteng 2018
25 Bambu m 3,614 Jurnal Jakarta 2018 hal
26 Ijuk kg 17,600 Jurnal Kalteng 2018
27 Firewood (kayu bakar) m3 170,000
28 Plain reinforced steel U 24 - BJTP 24 kg 15,400
29 Screew reinforced steel U 39 - BJTD 39 kg 15,400
30 Concrete wire kg 63,756 Jurnal Kalteng 2018
31 Kawat las dos 99,000 Jurnal Kalteng 2018
32 Nail 1 " - 4 " kg 13,750 Jurnal Kalteng 2018
33 Nail Asbestos kg 23,870 Jurnal Kalteng 2018
34 Nail Screws kg 25,850 Jurnal Kalteng 2018
35 Nail drat kg 16,500 Jurnal Kalteng 2018
36 Profil IWF kg 29,370 Jurnal Jakarta 2017 hal 250
37 Profil Kanal kg 15,950 Jurnal Jakarta 2017 hal 248
38 Profil Siku kg 15,950 Jurnal Jakarta 2017 hal 248
39 Besi Pelat Rata-rata kg 10,780 Jurnal Jakarta 2017 hal 249
40 Galvanis steel angle HTS kg 17,600 Pabrikan 2017
41 Galvanis steel angle MS kg 17,600 Pabrikan 2017
42 Galvanis Bolt and Nuts kg 17,600 Pabrikan 2017
43 Anchor bolt 24 mm pcs 126,500 http://www.kairosbaut.com/productlist.php
44 Angkur D30 unit 38,500
45 Anchor bolt 36 mm pcs 133,100
46 Dyna Bolt M 16 pcs 7,040 http://bisnisakurat.indonetwork.co.id/product/harga-sleeve-anchor-dyna-bolt-h
47 Dyna Bolt M 12 pcs 2,970 www.tokopedia.com
48 Self drilling screw dia 6 x 20 mm pcs 413 http://www.softwarerab.com/analisa-harga-satuan-pekerjaan-rangka-atap-baja

49 Self drilling screw dia 4 x 20 mm pcs 385 http://www.softwarerab.com/analisa-harga-satuan-pekerjaan-rangka-atap-baja


50 Galvanis of wire mesh dia 4 mm kg 11,135 Jurnal Bandung 2016
51 Wiremesh M6 roll 3,410,000 Jurnal Kalteng 2018
52 Wiremesh M6 (2,1m x 54 m x 347,6 kg) sheet 4,113,890
53 barbed wire kg 18,700 Jurnal Jakarta 2017
54 Kawat Anyam Harmonika dia lubang 27 mm x 27 m2 28,600 http://portalbangunan.com/harga-kawat-harmonika-
mm terbaru/
55 Alumunium foil m2 16,390 Jurnal Bekasi 2017 Hal. 343
i.B CAT dan Minyak
1 Paint of steel kg 118,800 Jurnal Jakarta 2017 hal 296
2 Paint of wooden kg 60,500 Jurnal Jakarta 2017 hal 294
PRICE
NO. UNIT REMARK
(Rp.)
3 Paint of wall Emulsi kg 25,300 Jurnal Jakarta 2017 hal 295
4 Paint of wall Weathershield kg 110,440 Jurnal Jakarta 2017 hal 295
5 Flintkote waterproffing for dak liter 80,300 Jurnal Jakarta 2017 hal 295
6 Naturally paint (Meni Kayu) liter 31,900 Jurnal Jakarta 2017 hal 294
7 Naturally paint (Meni besi) liter 33,000 Jurnal Jakarta 2017 hal 294
8 Waterproofing kg 80,300 Jurnal Jakarta 2017 hal 296
9 Thinner Liter 38,500 Jurnal Jakarta 2017 hal 297
10 Kuas / Rol pcs 27,500 Jurnal Jakarta 2017 hal 297
11 Amplas pcs 13,200 Jurnal Jakarta 2017 hal 297
12 Plamur of wall kg 25,300 Jurnal Jakarta 2017 hal 297
13 Plamur of wood kg 38,500 Jurnal Jakarta 2017 hal 297
14 Minyak bekisting litre 31,570 Jurnal Jakarta 2017 hal 294
15 BBM / solar litre 13,805 http://www.infohargabbm.com/2017/01/harga-keekonomian-bbm-solar-indust
16 Water litre 20
17 Oil Machine ltr 66,000
18 Oil Machine (Hydroulis) ltr 88,000
19 Solar Industri liter 9,240 http://hargasolarterbaru.blogspot.co.id/
20 Pelumas Diesel Alat berat (Pertamina Meditran liter 31,900 http://oli68.blogspot.co.id/2014/10/daftar-harga-oli-
SX15 W-40) pertamina-terbaru-2014.html
21 Hotmix AC WC liter 1,100,000 https://jasaaspalindo.com/daftar-harga-per-april-2017/
22 Hot mix kg 1,358 Jurnal Bekasi 2017 Hal 346
23 Asphalt 60/70 kg 10,450 Jurnal Bekasi 2017 Hal 346
i.C LANTAI DAN KERAMIK
1 Ceramic uk.20 cm x 20 cm m2 86,790
2 Ceramic uk.30 cm x 30 cm m2 83,930
3 Ceramic uk.60 cm x 60 cm setipe Platinum m2 124,520 Jurnal Jakarta 2017 hal 266
4 Granite wall tiles 400 x 400 mm m2 372,020 Jurnal Jakarta 2017 Hal 267
5 Granite floor tiles 600 x 600 mm m2 536,360 Jurnal Jakarta 2017 Hal 267
6 Granite floor tiles 300 x 300 mm m2 271,700 Jurnal Jakarta 2017 Hal 267

7 Granite floor tiles 300 x 600 mm m 2


429,550 http://www.hargabangunane.com/harga-granit-marmer-murah/#

Glazed ceramic wall tiles 200 x 250 mm setara


8 roman class C m2 139,700 Jurnal Jakarta 2017 Hal 265

9 Non glazed ceramic floor tiles 400 x 400 mm setara 87,120 Jurnal Jakarta 2017 Hal 265
milan m2
10 Glazed plint tiles 100 x 400 mm setara granito pcs 32,010 Jurnal Jakarta 2017 Hal 267
11 Granite plint tiles 100 x 300 mm setara granito pcs 27,500 Jurnal Jakarta 2017 Hal 267
12 Ceramic Plint tiles 100 x 600 mm pcs 49,500
13 Stepnosing 100 x 400 mm pcs 21,500 Jurnal Jakarta 2017
14 Vynyl Lantai + installation setara Kayu Jati KW 1 m2 346,500 http://www.hargamaterialbangunan.com/2016/10/harga-lantai-kayu-vinyl.html
15 Floorhardener ex sika kg 33,000 Jurnal Jakarta 2017
16 Raised Floor m2 924,000 http://mytrijaya.produkanda.com/sell/index.php?itemid=17091
i.DPERPIPAAN
1 Sambungan knee AW 1" bh 3,300 Jurnal Jakarta 2017
2 Lem Pipa (400 gram) klg 37,500 Jurnal Jakarta 2017 Hal 284
3 elbow 1/2" 90 bh 8,140 Jurnal Jakarta 2017 Hal 278
4 elbow 1" 90 bh 12,100 Jurnal Jakarta 2017 Hal 278
5 elbow 2" 90 bh 99,000 Jurnal Jakarta 2017 Hal 278
6 elbow 3" 90 bh 188,100 Jurnal Jakarta 2017 Hal 278
7 elbow 4" 90 bh 446,600 Jurnal Jakarta 2017 Hal 278
8 knee 1/2" bh 2,000 Jurnal Jakarta 2017 Hal 281
9 knee 1" bh 3,500 Jurnal Jakarta 2017 Hal 281
10 knee 2" bh 16,500 Jurnal Jakarta 2017 Hal 281
11 knee 3" bh 37,730 Jurnal Jakarta 2017 Hal 281
12 knee 4" bh 70,620 Jurnal Jakarta 2017 Hal 281
13 PVC Pipe dia 1/2 " setara AW L = 4 m stick 40,590 Jurnal Jakarta 2017 Hal 273
14 PVC Pipe dia 1 " setara AW L = 4 m stick 70,840 Jurnal Jakarta 2017 Hal 273
15 PVC Pipe dia 2 " setara AW L = 6 m stick 176,440 Jurnal Jakarta 2017 Hal 273
16 PVC Pipe dia 3 " setara AW L = 6 m stick 345,950 Jurnal Jakarta 2017 Hal 273
17 PVC Pipe dia 4 " setara AW L = 6 m stick 534,820 Jurnal Jakarta 2017 Hal 273
18 PVC Pipe dia 6 " setara AW L = 6 m stick 1,051,050 Jurnal Jakarta 2017 Hal 273
19 Pipa GIP Medium dia 2" L=6m stick 809,600 Jurnal Bekasi 2017 Hal 341
20 Sambungan-Sambungan Pipa GIP Medium 2" unit 23,210 Jurnal Bekasi 2017 Hal 341
21 PTFE Thread Seal Tape ISO 9002, Certified 10 m bh 3,850 Jurnal Jakarta 2017
(12 mm x 0.075 mm x 10 m)
22 Pipe of steel Dia 2 inc lenght 6,00 m stick 676,500 Jurnal Jakarta Hal 253
PRICE
NO. UNIT REMARK
(Rp.)
23 Pipe of steel Dia 3 inc lenght 6,00 m stick 1,116,500 Jurnal Jakarta Hal 253
24 Clamp pipa PVC 3'/4' unit 18,150
https://www.tokopedia.com/mitratools/klem-pipa-pvc-klem-pipa-pvc-4
25 Ball Valve pcs 150,150 Jurnal Jakarta 2017 Hal 282
i.E SANITAIR
1 Water Torn cap 2m3 setara Penguin Plastic unit 3,575,000 Jurnal Jakarta 2017
2 Chromium plate toiled roll holder no 278,740 Jurnal Jakarta 2016
3 Chromium plate soap dish no 219,450 Jurnal Jakarta 2016
4 Chromium plated hat and coat hook no 252,670 Jurnal Jakarta 2016
5 Closet Jongkok setara INA unit 236,390 Jurnal Kalimantan Tengah 2017 Hal 586
6 Close-coupled (Toto CW660NJ/SW660J) unit 3,197,700 Jurnal Jakarta 2017 hal 299
7 Squatting water closed complete (Toto CE9) no 3,971,880 Jurnal Jakarta 2017
8 Ceramic bowl urinoir complete (Toto U370) unit 5,778,300 Jurnal Jakarta 2017 Hal 300
9 Lavatory basin including spectacles (Toto LW230J) unit 666,490 Jurnal Jakarta 2017 Hal 301
10 Wash basin complete (Toto LW 820J ) no 3,063,500 Jurnal Jakarta 2017
11 Wash Basin Stainless Steel Setara Blanco unit 4,730,000 http://www.hargamaterialbangunan.com/2016/10/harga-wastafel.html
12 Kitchen Sink Stainless setara Delizia unit 1,430,000 www.blibli.com
13 Kran Cuci Piring unit 163,900 http://www.lazada.co.id/beli-keran-cuci-piring-bar
14 Kran ledeng standar pcs 21,560 Jurnal Kalimantan Tengah 2017 Hal 585
15 Jet washer setara toto unit 291,500 Jurnal Jakarta 2017 Hal 303
16 Bath basin (fiber) oval capacity 200 ltr unit 831,600 Jurnal Jakarta 2017
17 Bak Cuci Piring Stainless Steel 2 Pool unit 551,430 Jurnal Kalimantan Tengah 2017 Hal 586
i.F PINTU DAN KUSEN
1 Steel folding door 0.8 mm m2 825,000 http://www.hargamaterialbangunan.com/2016/10/harga-rolling-door-folding-g
2 Door Glass + Frame Aluminium m2 1,650,000 survey harga pasar
(Steel Galvanizing Automatic Roling door) 3500 x
3 2200 m2 715,000

4 Teakwood double door (nyatoh) m2 301,829 http://www.mediabangunan.com/2012/06/daftar-harga-kusen-dan-pintu-kayu.


5 Louvre frame window sheet 264,605
6 Kusen Aluminium m' 190,575 Jurnal Jakarta 2017
http://portalbangunan.com/harga-kusen-dan-pintu-kayu-
7 Kusen Kayu setara kayu Samarinda uk. 6/12 m' 302,500 terbaru/
8 Kaca Bening m2 96,250 http://www.lensarumah.com/harga-kaca/
9 Window Glass + Frame Aluminium m2 1,650,000 survey harga pasar
10 Door Closer pcs 617,100 Jurnal Jakarta 2017 Hal 291
11 Door Lock pcs 539,000 Jurnal Jakarta 2015
12 Door Holder (1 set = 2 pcs) set 542,300 Jurnal Jakarta 2015
13 Kunci Tanam pintu pcs 204,820 Jurnala Kalimantan Tengah 2017 Hal 585
14 Hinge For Door 5 in (engsel) (1 set = 3 pcs) pcs 159,390 Jurnal Jakarta 2017 Hal 291
15 Hinge For Window 4 in (1 set = 2 pcs) pcs 68,530 Jurnal Jakarta 2017 Hal 291
16 Grendel for Door pcs 82,500 Jurnal Jakarta 2017 Hal 292
17 Grendel for Door double Swing Steel Door pcs 337,810 Jurnal Jakarta 2017
18 Grendel for window (1 set = 2 pcs) pcs 248,050 Jurnal Jakarta 2017
19 Wind Hook For Window (1 set = 2 pcs) pcs 195,800 Jurnal Jakarta 2015
i.G RANGKA ATAP DAN PLAFOND
1 Zinc sheet 100,100 Jurnal Jakarta 2017
2 Asbes Plafond 5mm m2 43,120 Jurnal Jakarta 2017
3 Roofing Klip-lock Hi-Ten t=0.50 mm m2 234,190 http://www.mediabangunan.com/2013/06/daftar-harga-atap-metal-bluescope.

4 Roofing Spandek Colorbond m2 191,070 http://www.mediabangunan.com/2013/06/daftar-harga-atap-metal-bluescope.


5 Roofing Onduline sheet 159,500 http://agenbajaringan.com/atap-upvc-onduline.php
6 Nok Standard Hi-Ten m' 75,460 Jurnal Jakarta 2015
7 Nok Spandek Colorbond m' 63,580 Jurnal Jakarta 2015
8 Nok Onduline m' 84,700 https://atapmurahonduline.wordpress.com/tag/harga-atap-onduline/

9 Talang Jurai Zincalum m' 91,300 http://agentasocimanggis.blogspot.co.id/2016/01/talang-jurai-zincalume-murah


10 Panel Acoustic Armstrong 120x60cm, tebal 9 mm sheet 34,100 http://kutamandiri.blogspot.co.id/p/plafond-acoustic.html
11 Main Tee for plafond m' 7,639 http://kutamandiri.blogspot.co.id/p/plafond-acoustic.html
12 Gypsum board 9 mm sheet 106,920 Jurnal Jakarta 2017 hal 269
13 Alumunium Plafond + installation m2 423,500 http://spandrealumuniuml.blogspot.co.id/2016/06/plafon-aluminium-spandrel-

14 Rangka Plafond besi Hollow Galvanis m2 121,000 https://www.verticaldesign.id/harga-pasang-plafon-gypsum-partisi

http://www.lantaikayu.biz/plafon/harga-plafon-kayu-tahun-
15 Plafon Luar Lambersiring + installation m2 418,000 2016-dan-biaya-pasang-indonesia.html
16 Listplank Superplank (GRC board) sheet 144,430 Jurnal Jakarta 2016
PRICE
NO. UNIT REMARK
(Rp.)
17 List profil gypsum m' 43,560 Jurnal Jakarta 2017 hal 269
18 Tepung gypsum kg 9,130 Jurnal Bekasi 2017 Hal 337
Glasswool t=5 cm 2 layer density 16 kg/m3,
19 aluminium foil (single sided) m2 30,800 Jurnal Jakarta 2017
20 Roof mesh kg 32,725 Jurnal Jakarta 2015
i.H ELEKTRICAL
1 Stop contact incl installation wiring pcs 211,090 Jurnal Jawa Barat 2016 (Kerawang)
2 Exhaust Van setara Panasonic 16" Unit 770,000 www.hargaglodok.com
3 Exhaus fan wall 60 W/220 Volt (16") industrial pcs 528,000 http://harga.link/elektronik-rumah-tangga/list-daftar-harga-exhaust-fan-saat-ini/

4 Exhaus fan ceiling 40 W/220 Volt (10") very low pcs 434,500 http://harga.link/elektronik-rumah-tangga/list-daftar-harga-exhaust-fan-saat-ini/
noice
5 Serat Fiber m2 9,900 Jurnal Kerawang 2016
6 AC 3/4 PK setara Panasonic unit 3,382,500 http://www.hargaac.co.id/harga-ac-panasonic/cs-pn7skj/
7 AC split 1 PK setara Panasonic unit 3,520,000 http://www.harga-ac.com/daftar-harga-ac-daikin.html
8 AC split 2PK setara Panasonic unit 6,160,000 http://www.harga-ac.com/daftar-harga-ac-daikin.html
9 Exhaus fan wall 60 W/220 Volt (16") industrial unit 649,000
http://harga.link/elektronik-rumah-tangga/list-daftar-harga-exhaust-fan-saat-ini/
Exhaus fan ceiling 40 W/220 Volt (10") very low
10 noice unit 327,800
http://harga.link/elektronik-rumah-tangga/list-daftar-harga-exhaust-fan-saat-ini/
11 TL Lamp 18 watt equal phillips unit 77,880 Jurnal Jakarta 2017 Hal 306
12 T/L 1 x 36 Watt (incld armateur) no 424,600 Jurnal Jakarta 2015
13 T/L 2 x 36 Watt (incld armateur) no 577,830 Jurnal Jakarta 2015
14 T/L CDL E27 (1 x 8 W) no 114,950 Jurnal Jakarta 2015
15 T/L CDL E27 (1 x 23 W) no 171,600 Jurnal Jakarta 2015
16 Clear lamp celling 60 watt no 686,180 Jurnal Jakarta 2015
17 Lampu setara Phillips HPL/N (Mercury) 250 Watt pcs 58,190 Jurnal Jakarta 2016
18 Lampu Setara Phillips SON 70 W E27 unit 190,080 Jurnal Jakarta 2017 Hal 311
19 Lampu LED setara Philips 10 watt unit 121,000 Jurnal Jakarta 2017 Hal 306
20 Lampu sorot 250 watt setara philips unit 1,466,300 Jurnal Jakarta 2017 Hal 312
21 Lampu SON-T 150 watt unit 168,300
http://tokolampuglodok.com/index.php?route=product/category&path=57
22 Downlight no 85,360 Jurnal Jakarta 2015
Downlight 9 Watt inculding fitting spotlight
23 installation wiring and switch unit 154,000 http://www.depo-led.com/3-downlight-led
24 Downlight 18 watt unit http://agenlampusorot.com/index.php?route=product/product&product_id=254
291,500
25 Lampu LED 9 Watt Putih unit 59,400 https://www.tokopedia.com/mitraled/lampu-led-philips-9-watt
26 Fitting lampu unit 19,800 Jurnal Jakarta 2017 Hal314
27 Emergency lighting lamp 40 W complete pcs 154,000 http://harga.link/peralatan-rumah-tangga/list-daftar-harga-emergency-lamp-ter
28 Stop Contact stara Panasonic in bow single unit 41,800 Jurnal Jakarta 2017
29 Saklar tunggal unit 27,610 Jurnal Kalimantan Tengah 2017 hal 589
30 Saklar stara Panasonic Double Inbow unit 40,810 Jurnal Jakarta 2017 Hal 305
Double switch equal SCHNEIDER
31 unit 36,300 http://www.bhinneka.com/category/saklar.aspx
32 Saklar Multi 3 Qty 1 setara Brocco unit 44,880 https://jayamapan.com/clipsal/
33 Saklar Multi 4 Qty 1 unit 57,970 https://jayamapan.com/clipsal/
34 Ground Rod 5/8 inch L 4 m unit 710,985http://pusatantipetir.com/harga-ground-rod-copper-rod-58-inch/
35 Cable Grounding (BC) 50 mm m 82,940 Jurnal Kalimantan Tengah 2017 hal 590
36 Kabel NYM 3x2,5MM @100M 1 roll 1,133,000 Jurnal Bekasi 2017 Hal 344
Kap Lampu Jalan Model Cobra Starlight untuk
37 Lampu Mercury HPL-N 250 Watt atau HPI-T 250 pcs 660,000 http://lampujalanutama.com/?lampu-led=3&idc=1
Watt - 400 Watt, bisa untuk SON-T 150 Watt - 400
Watt. Terbuat dari Bahan Almunium Cor.

Tiang Lampu Octagonal tinggi 9 m (3 - 4.5 m),


38 desain diameter per segmen 2.5" - 5", flandes 30 x pcs 4,730,000 http://distributorpanelsurya.com/products.php?product=PILIHAN-TIANG-PJU
30 x 1.4 cm, ornamen 1.5" x 2 meter, anti clim 1
set, Hot Deep Galvanized
Kap Lampu Jalan Setara PJU Philips SPP 165, untuk
39 SON-T 70 Watt unit 880,000 http://lampujalanutama.com/?lampu-led=3&idc=1

Tiang Lampu Octagonal tinggi 6 m (3 - 4.5 m),


40 desain diameter per segmen 2,5"-4", flandes 30 x unit 2,750,000 http://distributorpanelsurya.com/products.php?
30 x 1.4 cm, ornamen 1.5" x 2 meter, anti clim 1 product=PILIHAN-TIANG-PJU
set, Hot Deep Galvanized
41 Clamp kabel beton no 4-10 pack 8,250 Jurnal Jakarta 2017
42 Railling Tangga m' 770,000 https://www.indosteel.net/daftar-harga/
43 Spiral Staircase set 5,500,000 https://www.indosteel.net/daftar-harga/
44 Balcony fence m2 605,000 https://www.indosteel.net/daftar-harga/
45 Penangkal petir radius 125 setara Thomas set 5,596,800 Jurnal Jakarta 2017 Hal 305
46 Pompa Submersible Cap. 150 ltr/menit 3 kW unit 28,880,280 Jurnal Bekasi 2017 Hal 346
47 Pompa air cap 670 liter/menit unit 3,135,000 http://www.hargatipemesin.com/2016/11/harga-mesin-
pompa-air-honda-tenaga.html
PRICE
NO. UNIT REMARK
(Rp.)
Panel Box MCB complete with R.S.T lamp indicator
48 and contactor grounding Panel Box 80x120x25 cm unit 2,499,200 https://jayamapan.com/panel-box/

Emergency lighting including wiring and lamp 30


49 Watt unit 126,500 www.tokopedia.com

50 Alarm bell 6'' ( 150 mm ) diameter to approval unit http://anekapemadamkebakaran.blogspot.co.id/2016/08/jual-alarm-bell-6-inch-diameter-untuk.htm


302,500
surface mounted in Lobby
51 Smoke detector unit 275,000 http://www.indotrading.com/showcase/smoke-detector
52 Fixed and rate of rice temperature detector unit 127,050
http://utamaservice045.blogspot.co.id/2012/09/appron-fire-alarm.html
MCFA ( Master control fire alarm ) kap 15 zone
53 included indication lamp, battery rectifier and all unit
https://www.tokopedia.com/hanselindo/mcfafacp-fire-alarm-control-panel-kap-15-zone-murah-berkualitas?
7,672,500
accessories
Portable fire extinghuister type dry chemical ( 5 kg
54 hallon ) unit 1,210,000 http://www.jualalatpemadamapi.net/harga-produk

55 Mobile unit powder fire extinghuister ( 50 kg unit 15,728,900 http://www.jualalatpemadamapi.net/harga-produk


hallon )
56 Portable type 6 kg CO2 c/w wall bracket unit 4,207,500 http://www.jualalatpemadamapi.net/harga-produk
57 APAR media isi Gas liquid Foam Cap 12 kg unit http://www.pasar-harga.com/2015/03/harga-alat-pemadam-kebakaran-api-besar.html
770,000
58 APAR 60 kg unit 27,775,000
http://pemadam-kebakaran.com/daftar-harga-alat-pemadam-api/daftar-harga-alat-pemadam-api-yama
i.I FENCE
1 Tiang Pagar BRC height 1,2 m pcs 220,000 http://www.hargamaterialbangunan.com/2016/08/harga-pagar-tiang-brc.html#

2 Tiang Pagar BRC height 1,5 m pcs 269,500 http://www.hargamaterialbangunan.com/2016/08/harga-pagar-tiang-brc.html

3 Tiang Pagar BRC height 1,9 m pcs 297,000 http://www.hargamaterialbangunan.com/2016/08/harga-pagar-tiang-brc.html

4 Fence BRC height 1,20 m lenght 2,40 m dia 7 mm pcs 523,600 http://www.hargamaterialbangunan.com/2016/08/harga-pagar-tiang-brc.html#
5 Fence BRC height 1,50 m lenght 2,40 m set 1,386,000 Jurnal Jakarta 2017
6 Fence BRC height 1,90 m lenght 2,40 m set 1,755,600 Jurnal Jakarta 2017
7 Double Gate BRC height 1,90 m lenght 3,30 m unit 1,397,550 Jurnal Jakarta 2017
complete
Single Gate BRC height 1,90 m lenght 1,10 m
8 complete unit 804,650 Jurnal Jakarta 2017
9 BRC Swing tunggal Uk. 100x120 unit 495,000 http://pagarbrc-mjs.com/harga/pagarbrc
10 Pintu Swing BRC single h :1.5 m, lebar 2.4 m unit 1,386,000 Jurnal Jakarta 2017
i.J BAHAN CETAKAN DAN PRECAST
1 Red brick (bata merah oven) pcs 770 Jurnal Semarang 2018 Hal 414
2 Paving Stone pcs 4,180
3 Hebel 10 x 20 x 60 cm pcs
4 Roster uk.22x22 cm pcs 20,350 www.seputarbangunan.com
5 Bataco 7x17x36 pcs 9,295
6 Buis Beton dia 60 cm/m m 101,310 Jurnal Kalimantan Tengah 2017 hal 593
7 Buis Beton dia 80 cm/m m 144,650 Jurnal Kalimantan Tengah 2017 hal 593
8 U-ditch 400/400 (panjang 1.2 m) unit 479,600 Jurnal Jakarta 2017 Hal 285
9 U-ditch 600/600 unit 873,400 Jurnal Jakarta 2017 Hal 285
10 U-ditch 1000/1000 unit 1,881,000 Jurnal Jakarta 2017 Hal 285
11 U-ditch 1200/1200 umit 2,626,800 Jurnal Jakarta 2017 Hal 285
12 U-ditch 800/800 unit 1,288,100 Jurnal Jakarta 2017 Hal 285
13 U-ditch BC 1000/1200 unit 2,101,000 Jurnal Jakarta 2017 Hal 285
14 Cover U 400 LD (panjang 0.6 m) unit 179,300 Jurnal Jakarta 2017 Hal 285
15 Cover U 600 LD unit 345,400 Jurnal Jakarta 2017 Hal 285
16 Cover U 800 LD unit 463,100 Jurnal Jakarta 2017 Hal 285
17 Cover U 1000 LD unit 564,300 Jurnal Jakarta 2017 Hal 285
18 Cover U 1200 LD unit 667,700 Jurnal Jakarta 2017 Hal 285
19 Pipa Concrete dia 30 cm m' 69,630
20 Kansteen (10 x 20 x 60) cm pcs 66,440 Jurnal Jakarta 2016
21 Kansteen (25 x 30 x 50) cm pcs 77,000 Jurnal Jakarta 2016
22 Driven Pile with reinforced concrete 40x40 cm m' 641,667 http://pt-bekah-beton.blogspot.co.id/p/blog-page.html
23 Driven Pile with reinforced concrete 30x30 cm m' 550,000 http://pt-bekah-beton.blogspot.co.id/p/blog-page.html
24 Driven Pile with reinforced concrete 20x20 cm m' 176,000 http://pt-bekah-beton.blogspot.co.id/p/blog-page.html
25 Driven Concrete Pile dia 40 cm m 2,035,000 harga survey
26 Sheet Pile Corrugated m' 1,419,000 Jurnal Jakarta 2016
i.K LANDSCAPE DAN LAINNYA
1 Sodding (gebalan rumput) m2 49,280 Jurnal Banten 2016
2 Pupuk Kandang (1 karung = 7 kg) karung 22,000 https://www.tokopedia.com/ismailtoys/for-sale-pupuk-
kandang-sapi-1
https://www.tokopedia.com/sm2/bibit-pohon-mangga-
3 Pohon Mangga (tinggi bibit 50 - 70 ) unit 440,000 gincu-pendopo

4 Rumput Gajah Mini m2 16,500 https://www.tokopedia.com/tukangrumput/rumput-gajah-mini-harga-petani


PRICE
NO. UNIT REMARK
(Rp.)
5 Palm Fibre kg 24,640 Jurnal Bekasi 2016
https://www.tokopedia.com/berdikari-indah/pohon-teh-
6 Tanaman Teh-tehan (tinggi 25 - 35 cm) unit 5,500 tehan-i-tanaman-pagar
7 Ladder Ø 16 mm & painted kg 26,400
8 Grill Oil Pit kg 20,104
9 Baut 5/8 - 30 cm baut 13,200

10 Haspel dia 1.2 m tinggi 0.9 m unit 3,025,000 https://www.bukalapak.com/p/rumah-tangga/furniture-interior/intwi-jual-meja

11 Sling unit/day 33,000


12 Rope fiber m 14,300 http://marine-rope.weebly.com/product.html
13 Plastic m2 39,160 Jurnal Jakarta 2017 Hal 256
14 Tali Nilon Roll 132,000
II SAFETY EQUIPMENT
A CIVIL
1 Safety Helmet Unit 132,000 survey harga pasar 2017
2 Baju Rompi Unit 179,400 survey harga pasar 2017
3 Sepatu Boot Sepasang 95,000 survey harga pasar 2017
4 Sarung Tangan Sepasang 15,000 survey harga pasar 2017
5 Rambu Ls 5,000,000 survey harga pasar 2017
6 Baricade/Safety Line Meter 5,955 survey harga pasar 2017
7 Kacamata (Safety Glasses) Unit 71,400 survey harga pasar 2017
8 Masker Pcs 2,500 survey harga pasar 2017
9 Jas Hujan Pcs 75,000 survey harga pasar 2018

B ELEKTROMEKANIKAL
1 Sabuk Keselamatan (Body Hardness) Unit 4,540,100 survey harga pasar 2017
2 Safety Helmet Unit 132,000 survey harga pasar 2017
3 Baju Rompi Unit 179,400 survey harga pasar 2017
4 Safety Shoes Sepasang 1,096,000 survey harga pasar 2017
5 Sarung Tangan Sepasang 15,000 survey harga pasar 2017
6 Kacamata (Safety Glasses) Unit 71,400 survey harga pasar 2017

C OTHERS
1 First Aid Month 800,000 survey harga pasar 2017
2 Alat Pemadam Portable (9 kg) Unit 3,000,000 survey harga pasar 2017
3 TOA untuk Briefing Pekerja Unit 5,975,000 survey harga pasar 2017
4 Report Pelaksanaan K3 Month 500,000 survey harga pasar 2017
5
III REMUNERATION
1 Worker man/day 130,000 Jurnal Kalteng 2018
2 Foreman man/day 215,000 Jurnal Kalteng 2018
3 Brick Layer leader man/day 170,000 Jurnal Kalteng 2018
4 Steel worker leader man/day 150,000 Jurnal Kalteng 2018
5 Carpenter leader man/day 157,500 Jurnal Kalteng 2018
6 Paint worker leader man/day 140,000 Jurnal Kalteng 2018
7 Plumber leader man/day 150,000 Jurnal Kalteng 2018
8 Brick Layer Worker man/day 120,000 Jurnal Kalteng 2018
9 Steel worker man/day 100,000 Jurnal Kalteng 2018
10 Carpenter man/day 120,000 Jurnal Kalteng 2018
11 Paint worker man/day 120,000 Jurnal Kalteng 2018
12 Mechanic man/day 350,000 Jurnal Kalteng 2018
13 Asphalt worker man/day 120,000 Jurnal Kalteng 2018
14 Digger man/day 120,000 Jurnal Kalteng 2018
15 Plumber man/day 120,000 Jurnal Kalteng 2018
16 Welder man/day 150,000 Jurnal Kalteng 2018
17 Instalator man/day 175,000 Jurnal Kalteng 2018
18 Engineer man/day 612,140 Billing Rate 2018 (Sul Sel (Goa)) 1 year experience
19 Engineer Expert man/day 1,000,150 Billing Rate 2018 (Sul Sel (Goa)) 5 year experience
20 Surveyor man/day 433,800 Jurnal Kalteng 2018
21 Electrician man/day 175,000 Jurnal Kalteng 2018
22 Electrical Technician man/day 563,940 Jurnal Kalteng 2018
23 Technician man/day 482,000 Jurnal Kalteng 2018
24 Steel Erection Worker man/day 220,000 Biaya Langsung Personil 2018
25 Stringing Worker man/day 250,000 Biaya Langsung Personil 2018
26 Skill Worker man/day 200,000 Biaya Langsung Personil 2018
27 Juru Ukur man/day 433,800
28 Pembantu Juru Ukur man/day 120,000
29 Operator man/day 425,000 Jurnal Kalteng 2018
PRICE
NO. UNIT REMARK
(Rp.)
30 Helper Operator man/day 110,000 Jurnal Kalteng 2018
31 Driver man/day 150,000 Jurnal Kalteng 2018
IV RENT OF EQUIPMENT
1 Molen of machine 0.5 m3 unit/day 704,000 Jurnal Semarang 2018 Hal 413
2 Concrete Vibrator unit/day 528,000 Jurnal Semarang 2018 Hal 413
3 Pipe Tremi hour 35,640
4 Concrete Pump cap 4 m3 hour 105,600
5 Dump Truck 5 m3 (4 hour/day) unit/day 748,000 Jurnal Semarang 2018 Hal 413
6 Water Tank Truck (2 hours / day) hour 330,000 Jurnal Semarang 2018 Hal 413
7 Water Pump 30m3/day unit-day 352,000 Jurnal Semarang 2018 Hal 413
8 Waterpass pcs 39,380 Jurnal Jawa Barat (Bandung) 2017 Hal 377
9 Theodolit unit/day 220,000 http://www.globalsurveybandung.com/p/rental.html
10 Stamper /Stomwalls unit/day 352,000 Jurnal Semarang 2018 Hal 413
11 Excavator Standard bucket 0.8 m3 hour 352,000 Jurnal Semarang 2018 Hal 413
12 Buldozer Setara Catterpillar D6D cap 0.8 m (4 hour 770,000 Jurnal Semarang 2018 Hal 413
hour/day)
13 Pile Driver Hammer cap. 2 ton hour 145,200
14 Drop Hammer hour 55,000
15 Bored Pile Machine hour 897,422
16 Pile connection pc 132,000
17 Greader Komatsu unit/day 1,248,500
18 Tandem Roller unit/hour 157,300
19 Vibro Roller 5-8 T unit/day 7,855,320
20 Forklift hour 240,625 http://www.rajarental.com/rental_forklift.html
21 Jack Hammer unit/day 286,000
22 Tripod tinggi 5 m unit/day 330,000
23 Mesin Potong rumput unit/day 30,000
24 Jack Hydrolic hour 17,820
25 Small crane unit/day 308,000 http://www.jasatirta1.co.id/pengusahaan.php?subaction=showfull&id=1192659
26 Truck Crane Cap. 5 ton hour 550,000 Harga Survey Lapangan 2018
27 Truck Crane 35 ton unit/day 8,250,000
http://rentalmobilecrane.blogspot.co.id/p/list-harga-rental-crane.html
28 Truck Mixer unit/day 3,300,000 nyewain.com
29 Mobilisasion Equipment ls 154,000
30 Mesin Press unit/day 220,000
31 Stringing Equipment unit/day 9,166,667
32 Sagging Equipment unit/day 605,000
33 Communication Equipment unit/day 97,900
34 Support equipment ( key + safety belt ) unit/day 163,944
35 Chain Block 5 ton hour 16,575
36 Pully unit/day 37,950
37 Winch Machine Cap 3-5 ton unit/day 625,000 achive.kaskus.co.id/tread/7883998/1
38 Sling unit/day 165,000
39 Megger unit/day 30,800
40 Alat Pengukuran Earthing unit/day 550,000
41 Earth Tester unit/day 165,000
42 Casing unit/day 132,000
43 Peralatan Pengujian Baterai unit/day 308,264
44 Insulation Test Equipment unit/day 165,000
45 Supporting of Earthing Device unit/day 132,000
46 Injection primer & sekunder unit/day 1,833,334
47 HV Apparatus Analyzer unit/day 1,145,834
48 Sewa Klotok (Perahu bermotor) unit/day 275,000
49 Tackle 5 ton' unit/day 165,000
50 Came along/Wire Grip unit/day 104,500
51 Ground stick unit/day 198,000
52 Stringing Ladder unit/day 275,000
Peralatan Pengujian untuk Testing dan Komisioning
53 Transmisi unit/day 440,000
54 Wheel Loader hour 249,700
V EQUIPMENT
1 Steel saw unit/day 159,500 indoteknik.com
2 Chain saw unit/day 269,500 sewastamperkuda.yolasite.com
3 Hammer 4,5 kg Sellery Heavy Duty unit/day 229,900 indoteknik.com
4 Steel Chisel unit/day 204,600 indoteknik.com
5 Water Jet Pump Kualitas 1 unit/day 6,325,000 Jurnal Jakarta 2017
6 Hand Bor Machine unit/day 379,500 http://sewastamperkuda.yolasite.com/
7 Drilling Machine unit/day 550,000 http://sewastamperkuda.yolasite.com/
8 Welding Machine unit/day 544,500 http://www.anekasewajasa.com/?prm=sewa&cmd=detail&id=38
PRICE
NO. UNIT REMARK
(Rp.)
9 Las Machine unit/day 252,890 Jurnal Bekasi 2017 Hal 348
Genset 5kvA include Bensin, Operator dan https://www.tokopedia.com/prayaorganize/sewa-genset-
10 transport 10 jam unit/day 1,100,000 kecil-di-antar-jemputtinggal-duduk-manis-aja

11 Main Frame Scaffolding 1.9 m unit 14,300 http://www.signalreadymix.co/harga-sewa-scaffolding-


steger-terbaru#popup

12 Jack Base Scaffolding unit 7,150 http://www.signalreadymix.co/harga-sewa-scaffolding-


steger-terbaru#popup
http://www.signalreadymix.co/harga-sewa-scaffolding-
13 Cross Brace unit 9,350 steger-terbaru#popup

14 Horizontal Frame Scaffolding unit 7,150 http://www.signalreadymix.co/harga-sewa-scaffolding-


steger-terbaru#popup
Supporting of Equipment ( Welder and Cutting
15 Machine ) hour 29,856 Jurnal Bekasi 2015
16 Cangkul unit 64,240 Jurnal Jawa Barat (Bandung) 2017 Hal 377
17 Singkup unit 64,240 Jurnal Jawa Barat (Bandung) 2017 Hal 377
18 Linggis Besi Ulir L=110 cm dia. 1/4-1 " unit 68,090 Jurnal Jawa Barat (Bandung) 2017 Hal 377
19 Pahat besi beton ujung lancip 19 mm unit https://www.tokopedia.com/madu-madu/pahat-besi-beton-ulir-ujung-lancip-19-mm-ujung-tajam-pe-lim
79,530
20 Computer + Printer unit/day 192,500
VI SOIL INVESTIGATION
1 Boring Mesin Kedalaman maksimum 30 m titik 19,965,000 http://surveysoil.blogspot.co.id/2016/02/menerima-jasa-
termasuk : survey-uji-sondir-dan.html
- Uji Penetrasi Standar (SPT) -
http://surveysoil.blogspot.co.id/2016/02/menerima-jasa-
- Uji Laboratorium Mektan 3,630,000 survey-uji-sondir-dan.html
- Uji Sifat Tanah 159,500
- Pengambilan contoh tanah terganggu (Disturbed
Sample) dilaksanakan pada setiap interval 2 meter -
atau pada setiap perubahan tanah.

2 Sondir titik 4,400,000 http://surveysoil.blogspot.co.id/2016/02/menerima-jasa-


survey-uji-sondir-dan.html
3 Laporan pengujian termasuk : set 550,000
- 1set laporan hard copy (uraian kondisi awal,
foto-foto pelaksanaan, hasil pengujian dan
pengambilan sampel di lapangan, analisa dan -
rekomendasi)

- 1set laporan soft copy dalam format CD (uraian


kondisi awal, foto-foto pelaksanaan, hasil
pengujian dan pengambilan sampel di lapangan, -
analisa dan rekomendasi)
4 Sand Cone Test per 20 cm Layer titik 249,260
5 Pembuatan Sumur Bor dia pipa 4 inch m 275,000 http://harga.web.id/berapa-biaya-membuat-sumur-bor-
sumur-air.info
Note: Schedule 2 (only owner Reference)
Referensi harga : material , upah dan alat "
JURNAL EDISI XXXVI TAHUN 2017"