Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CONTENT
Description Page
2/28
3/28
ABV STEEL MICROPILE SYSTEM
Installation Procedure
1. The pile main element is cut to the desired section length in the factory
(usually 2 or 3m length). The section length will depend, among other
factors, on the site condition and the driving equipment. One end of the
main element will be fitted with the coupling sleeve by heating the sleeve
to plasticise the polyethylene and then pressing the sleeve into the main
element.
2. Before installation, the bottom end of the first main element section is fitted
with a mild steel pile shoe of the appropriate size. Joining of the individual
sections during installation is accomplished in the same manner described
in paragraph 1.
4. During driving, the vertically tolerances of vertical piles shall not exceed the
following limits:
Vertically tolerance : 1:50
6. The installed pile will be cut perpendicular to its longitudinal direction at the
required cut-off level. The pile interior will be infilled with cement grout and
the pile top will then be fitted with an appropriately sized mild steel capping
plate, which is fabricated together with the capping ring and high yield
steel bar.
4/28
MICROPILE SYSTEM – MP75
SPECIFICATION
1. MATERIALS
1.3. PILE SHOE Solid mild steel with mild steel dowel
epoxy cemented into shoe.
(a) Driven with a free drop hammer with minimum rated energy of 2.4 kNm. Final
set shall be 10mm per 10 blows of the hammer.
(b) Driven with a pneumatic jack hammer with minimum 200 kg weight to not less
than 5 mm per minutes for 3 minutes consecutively.
The indicated allowable loads are based on previous experience and load testing.
The loads shall be verified and may be changed depending on the subsurface
soil condition.
2.3. BUCKLING
When the undrained shear strength of the soil is less than 7 kN/m2 from a mean
value of a 2-metre layer or more, the allowable load should be reduced to prevent
buckling. The allowable load may be calculated as follows:
𝑄𝑎𝑙𝑙 = √15 Cu El
Where : Cu = undrained shear strength
EI = pile stiffness
5/28
6/28
MICROPILE SYSTEM – MP100
SPECIFICATION
1. MATERIALS
1.3. PILE SHOE Solid mild steel with mild steel dowel
epoxy cemented into shoe.
Driven with a free drop hammer with minimum rated energy of 4.5 kNm. Final set
shall be 10mm per 10 blows of the hammer.
The indicated allowable loads are based on previous experience and load testing.
The loads shall be verified and may be changed depending on the subsurface
soil condition.
2.3. BUCKLING
When the undrained shear strength of the soil is less than 7 kN/m2 from a mean
value of a 2-metre layer or more, the allowable load should be reduced to prevent
buckling. The allowable load may be calculated as follows:
𝑄𝑎𝑙𝑙 = √15 Cu El
7/28
8/28
MICROPILE SYSTEM – MP125
SPECIFICATION
1. MATERIALS
1.3. PILE SHOE Solid mild steel with mild steel dowel
epoxy cemented into shoe.
Driven with a free drop hammer with minimum rated energy of 5.0 kNm. Final set
shall be 10mm per 10 blows of the hammer.
The indicated allowable loads are based on previous experience and load testing.
The loads shall be verified and may be changed depending on the subsurface
soil condition.
2.3. BUCKLING
When the undrained shear strength of the soil is less than 7 kN/m2 from a mean
value of a 2-metre layer or more, the allowable load should be reduced to prevent
buckling. The allowable load may be calculated as follows:
𝑄𝑎𝑙𝑙 = √15 Cu El
9/28
10/28
MICROPILE SYSTEM - MP150
SPECIFICATION
1. MATERIALS
1.3. PILE SHOE Solid mild steel with mild steel dowel
epoxy cemented into shoe.
Driven with a free drop hammer with minimum rated energy of 5.5 kNm. Final set
shall be 10mm per 10 blows of the hammer.
The indicated allowable loads are based on previous experience and load testing.
The loads shall be verified and may be changed depending on the subsurface
soil condition.
2.3. BUCKLING
When the undrained shear strength of the soil is less than 7 kN/m2 from a mean
value of a 2-metre layer or more, the allowable load should be reduced to prevent
buckling. The allowable load may be calculated as follows:
𝑄𝑎𝑙𝑙 = √15 Cu El
11/28
12/28
3H25
3H28
3H32
3H40
4H40
13/28
BORED MICROPILE SYSTEM
1 MATERIAL SPECIFICATION
1.1 Grout
1.1.1 Materials
7 days 28 days
0.40 to 0.45 C 20 / 25 C 30 / 37
14/28
BORED MICROPILE SYSTEM
1.2.2 Joints
15/28
BORED MICROPILE SYSTEM
INSTALLATION PROCEDURE OF MICROPILE
16/28
17/28
18/28
METHOD STATEMENT FOR INSTALLATION OF
ABV GRIP JACK-IN PILE SYSTEM
1. The existing ground surface to be prepared and compacted by the
main contractor.
6. Once the position and verticality confirmed, first section of the pile is
grip and jack into the ground by means of hydraulic jack mounted
on the grip-jack box. The grip and jack installation process for first
section of the pile continues until the whole section is pitched below
the grip-jack box.
7. Placed second section of the pile in the center of the grip-jack box
and jointed to the first section by means of welding or mechanical
joint in accordance to construction drawing. (Same process
repeated for all subsequent sections ). Since compressive jacking
force will not disturb the weld, thus no cooling time is required
8. Continues the grip and jack installation process for the pile until the
pre-determined set pressure for jacking is achieved. (Please refer to
the attached jack-in force table)
9. Carry out setting of the piles by maintaining the jacking set pressure
for 30 seconds for (3) cycles with set criteria of 0-5 mm.
19/28
20/28
21/28
22/28
23/28
METHOD STATEMENT
PATENTED SETTABLE FLUID PRE-LOADING SYSTEM
3. Prepare “MAPEI EPOJET LV” grouting mixing ratio – A:B by volume – 2:1
4. After mixing the epoxy, pressure grout the load-cell through inlet-pipe
immediately by using high-pressure spraying pump. The pressure apply
shall be in accordance to Appendix I.
5. Lock the one way value once the required pressure is achieved.
7. The inlet-pipe will be cut accordingly, within 24hrs after the preloading is
completed.
24/28
PATENTED SETTABLE FLUID PRE-LOADING SYSTEM
The Patented Settable Fluid Pre-loading system is used where preloading is required for
underpinning works.
25/28
26/28
PATENTED SETTABLE FLUID PRE-LOADING SYSTEM
ON SITE PHOTOS
KALLANG LEISURE PARK
PRE-LOADING SETUP
27/28
PATENTED SETTABLE FLUID PRE-LOADING SYSTEM
ON SITE PHOTOS
KALLANG LEISURE PARK
28/28