LEVANTAMIENTO E INFORME DEL ESTADO ACTUAL

PARA LAS ADECUACIONES DE LA INFRAESTRUCTURA


DE CUBIERTA DEL CENTRO NACIONAL DE ATENCION
EN FRONTERA CENAF

San Juan de Pasto, Enero de 2019


LEVANTAMIENTO ESTRUCTURAL E INFORME DEL ESTADO
ACTUAL PARA LAS ADECUACIONES DE LA
INFRAESTRUCTURA DE CUBIERTA DEL CENTRO NACIONAL
DE ATENCION EN FRONTERA CENAF

CONTRATISTA

ARQ. JULIAN ESTEBAN ORTIZ

EQUIPO DE TRABAJO

ARQ. DANIEL MORA


ING. ALEJANDRO COLLAZOS
ING. GUSTAVO BURBANO

INGENIERO RESPONSABLE

ING. GUSTAVO BURBANO

SAN JUAN DE PASTO, ENERO DE 2019


CONTENIDO

1) INFORME DEL ESTADO ACTUAL PARA LAS ADECUACIONES DE LA


INFRAESTRUCTURA DE CUBIERTA DEL CENTRO NACIONAL DE ATENCION EN
FRONTERA CENAF ...................................................................................................................... 8
1.1) OBJETIVOS ......................................................................................................................................... 8
a) General ............................................................................................................................................ 8
b) Específicos ....................................................................................................................................... 8
1.2) ALCANCE ........................................................................................................................................... 9
1.3) DESCRIPCIÓN DE CONTEXTO ........................................................................................................... 10
2) DESCRIPCIÓN DE LA EDIFICACIÓN .................................................................................... 11
2.1) DESCRIPCIÓN ARQUITECTÓNICA ..................................................................................................... 12
2.2) DESCRIPCIÓN ESTRUCTURAL ........................................................................................................... 16
a) Cubierta Zona A Acceso peatonal.................................................................................................. 16
b) Cubierta Zona B Atención: ............................................................................................................. 16
c) Cubierta Zona C Oficinas: .............................................................................................................. 17
d) Cubierta Zona D Escaleras: ............................................................................................................ 17
e) Cubierta Zona E Puente: ................................................................................................................ 17
3) DESARROLLO DEL ANALISIS .............................................................................................. 18
3.1) METODOLOGÍA DEL ANÁLISIS ......................................................................................................... 18
a) Etapa 1: Verificación del alcance de la Norma NSR-10 A.10.1.3 ................................................... 18
b) Etapa 2: Recopilación de la información documental existente de la edificación ......................... 18
c) Etapa 3: Clasificación del sistema estructural ............................................................................... 20
3.2) EVALUACIÓN DE LA ESTRUCTURA EXISTENTE DESDE METODOS CUALITATIVOS Y CUANTITATIVOS21
a) Etapa 4: Solicitaciones equivalentes ............................................................................................. 21
b) Etapa 7: Resistencia efectiva de la estructura............................................................................... 29
c) Etapa 8: Índice de sobreesfuerzo ................................................................................................... 29
3.3) MODELACIÓN EN EL SOFTWARE ETABS........................................................................................... 30
a) Geometría estructural ................................................................................................................... 30
b) Materiales ..................................................................................................................................... 30
c) Elementos estructurales ................................................................................................................ 32
d) Apoyos ........................................................................................................................................... 34
e) Asignación de elementos al modelo .............................................................................................. 34
f) Definición del espectro de respuesta ............................................................................................. 34
g) Casos de carga estáticos definidos ................................................................................................ 35
h) Analisis de Viento .......................................................................................................................... 35
3.4) METODO CUALITATIVO ................................................................................................................. 110
EVALUACION CUALITATIVA POR INDICADORES ................................................................................... 110
3.5) EVALUACIÓN DE ANCLAJES Y APOYOS........................................................................................... 116
a) ZONA A ACCESO PEATONAL ........................................................................................................ 116
b) ZONA B ATENCION AL PUBLICO .................................................................................................. 118
c) ZONA C OFICINAS......................................................................................................................... 120
d) ZONA D ESCALERAS ..................................................................................................................... 123

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


3

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
e) ZONA E PUENTE........................................................................................................................... 124
3.6) EVALUACIÓN DE CORROSIÓN........................................................................................................ 126
4) CONCLUSIONES Y RECOMENDACIONES. ....................................................................... 135
4.1) CONCLUSION Y RECOMENDACIÓN PARA LA ESTABILIDAD GENERAL DE LA EDIFICACIÓN Y
PROYECCIÓN DE CUBIERTA .................................................................................................................. 135
4.2) CONCLUSION GENERAL ................................................................................................................. 188

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


4

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Índice de tablas

TABLA 1_CALIFICACIÓN DEL ESTADO DEL SISTEMA ESTRUCTURAL. .............................................................................. 20


TABLA 2_METODOLOGÍA DE EVALUACIÓN. ........................................................................................................... 21
TABLA 3_RELACIÓN DE COEFICIENTE DE DISIPACIÓN DE ENERGIA Y CLASIFICACIÓN DEL SISTEMA ESTRUCTURAL .................. 21
TABLA 4_PERFIL DEL SUELO ............................................................................................................................... 24
TABLA 5_GRUPO DE USO DE LA EDIFICACIÓN ......................................................................................................... 24
TABLA 6_DATOS DE ESPECTRO DE DISEÑO. ........................................................................................................... 26
TABLA 7_COMBINACIONES DE CARGA. ................................................................................................................. 28
TABLA 8_VALORES DE ΦC Y ΦE. ........................................................................................................................ 29
TABLA 9_RESULTADOS DE CHEQUEO DE DEFLEXIONES CUERDA INFERIOR, SUPERIOR Y DIAGONALES ................................ 78
TABLA 10_CUADRO DE DERIVAS EN VIRTUD DE CARGA DE EMPUJE PARA ANALISIS NO LINEAL MODAL ........................... 109
TABLA 11_TABLA DE VALORES DE ÍNDICE DE CAPACIDAD CUBIERTA TIPO. .................................................................. 175
TABLA 12_TABLA DE VALORES DE DESPLAZAMIENTO MÁXIMO ANÁLISIS NO LINEAL MODAL CON MODIFICACIÓN DE CUBIERTA.
......................................................................................................................................................... 183
TABLA 12_TABLA DE VALORES COMPARATIVOS DE PESO DE CUBIERTA PARA UN CASO DE CUBIERTA A DOS AGUAS SOBREPUESTA
A LA EXISTENTE CON UNA PENDIENTE DEL 13% Y CONFIGURADA A MITAD DEL TOTAL DE LA LONGITUD ................... 187

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


5

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Índice de figuras

FIGURA 1_LOCALIZACIÓN CENAF (FUENTE: GOOGLE EARTH).................................................................................. 11


FIGURA 2_REGISTRO FOTOGRÁFICO CONTEXTO (FUENTE: PROPIA) ............................................................................ 12
FIGURA 3_ REGISTRO FOTOGRÁFICO CONTEXTO (FUENTE: PROPIA) ........................................................................... 12
FIGURA 4_ LOCALIZACIÓN DE CUBIERTAS (FUENTE: ELABORACION PROPIA) ................................................................. 15
FIGURA 5_COEFICIENTE DE AMPLIFICACIÓN FA DEL SUELO. ...................................................................................... 23
FIGURA 6_COEFICIENTE DE AMPLIFICACIÓN FV DEL SUELO. ...................................................................................... 23
FIGURA 7_ESQUEMA DE CUBIERTA ..................................................................................................................... 25
FIGURA 8_ESPECTRO DE ACELERACIONES ............................................................................................................. 27
FIGURA 9_DEFINICIÓN DE MATERIALES. ............................................................................................................... 31
FIGURA 10_DEFINICIÓN DE SECCIÓN. .................................................................................................................. 32
FIGURA 11_DEFINICIÓN DE MATERIAL DE CUBIERTA ............................................................................................... 33
FIGURA 12_ASIGNACIÓN DE APOYOS. ................................................................................................................. 34
FIGURA 13_DEFINICIÓN DE CASOS DE CARGA ESTÁTICOS. ........................................................................................ 35
FIGURA 14_CHEQUEO DE DEFLEXIÓN CUERDA INFERIOR .......................................................................................... 42
FIGURA 15_CHEQUEO DE DEFLEXIÓN CUERDA SUPERIOR ......................................................................................... 43
FIGURA 16_CHEQUEO DE DEFLEXIÓN DIAGONALES ................................................................................................. 44
FIGURA 17_SECUENCIA DE FALLA MODO 1 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS ............................................ 80
FIGURA 18_SECUENCIA DE FALLA MODO 2 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS ............................................ 81
FIGURA 19_SECUENCIA DE FALLA MODO 3 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS ............................................ 82
FIGURA 20_SECUENCIA DE FALLA MODO 4 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS ............................................ 83
FIGURA 21_SECUENCIA DE FALLA MODO 5 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS ............................................ 84
FIGURA 22_SECUENCIA DE FALLA MODO 6 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS ............................................ 85
FIGURA 23_SECUENCIA DE FALLA MODO 7 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS ............................................ 86
FIGURA 24_SECUENCIA DE FALLA MODO 8 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS ............................................ 87
FIGURA 25_SECUENCIA DE FALLA MODO 9 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS ............................................ 88
FIGURA 26_SECUENCIA DE FALLA MODO 10 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS .......................................... 89
FIGURA 27_SECUENCIA DE FALLA MODO 11 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS .......................................... 90
FIGURA 28_SECUENCIA DE FALLA MODO 12 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS .......................................... 91
FIGURA 29_SECUENCIA DE FALLA MODO 13 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS .......................................... 92
FIGURA 30_SECUENCIA DE FALLA MODO 14 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS .......................................... 93
FIGURA 31_SECUENCIA DE FALLA MODO 15 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS .......................................... 94
FIGURA 32_SECUENCIA DE FALLA MODO 16 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS .......................................... 95
FIGURA 33_SECUENCIA DE FALLA MODO 17 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS .......................................... 96
FIGURA 34_SECUENCIA DE FALLA MODO 18 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS .......................................... 97
FIGURA 35_SECUENCIA DE FALLA MODO 19 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS .......................................... 98
FIGURA 36_SECUENCIA DE FALLA MODO 20 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS .......................................... 99
FIGURA 37_SECUENCIA DE FALLA MODO 21 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS ........................................ 100
FIGURA 38_SECUENCIA DE FALLA MODO 22 SENTIDO X FORMACIÓN DE ROTULAS PLASTICAS ........................................ 101
FIGURA 39_REGISTRO FOTOGRÁFICO CONEXIÓN COLUMNA EN ANGULO Y PILAR EN CONCRETO (FUENTE: PROPIA) .......... 117
FIGURA 40_REGISTRO FOTOGRÁFICO CONEXIÓN COLUMNA EN ANGULO Y PILAR EN CONCRETO (FUENTE: PROPIA) .......... 118
FIGURA 41_REGISTRO FOTOGRÁFICO CONEXIÓN DE NUDO APOYADO SOBRE MURO (FUENTE: PROPIA) .......................... 119
FIGURA 42_REGISTRO FOTOGRÁFICO CONEXIÓN DE NUDO DE CUBIERTA, PLATINA DE CONEXIÓN Y PILAR EN CONCRETO Y
ANGULO (FUENTE: PROPIA).................................................................................................................... 119

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


6

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
FIGURA 43_REGISTRO FOTOGRÁFICO CONEXIÓN DE NUDO DE CUBIERTA, CELOSIA, Y COLUMNA EN ANGULO ENTRE CUBIERTAS
ZONA B Y C (FUENTE: PROPIA)................................................................................................................ 121
FIGURA 44_DISCONTINUIDAD DE NUDO DE CUBIERTA RESPECTO A SU EJE DE APOYO ZONA B (FUENTE: PROPIA) .............. 122
FIGURA 45_CERCANIA DE NUDO DE CUBIERTA RESPECTO A SU EJE DE APOYO ZONA B (FUENTE: PROPIA) ........................ 122
FIGURA 46_COINCIDENCIA DE NUDO (FUENTE: PROPIA) ....................................................................................... 123
FIGURA 47_APOYOS DE PARED ZONA E PUENTE (FUENTE: PROPIA) ........................................................................ 124
FIGURA 48_APOYOS DE LOSA E PUENTE (FUENTE: PROPIA) ................................................................................... 125
FIGURA 49_CORROSIVIDAD SOBRE CANALES, ZONA B ATENCIÓN (FUENTE: PROPIA) ................................................... 126
FIGURA 50_AUSENCIA DE MANTENIMIENTO Y CONCENTRACIÓN DE COSTRAS DE POLVO SOBRE NUDOS, ZONA A ACCESO
PEATONAL (FUENTE: PROPIA) ................................................................................................................. 127
FIGURA 51_CORROSIÓN SUPERFICIAL DEBIDO A LA EXPOSICIÓN DE LLUVIA LATERAL, LUMINOSIDAD Y EXPOSICIÓN AL SMOKE,
ZONA C OFICINAS (FUENTE: PROPIA) ........................................................................................................ 127
FIGURA 52_PROCESO DE ESCARIFICACIÓN MANUAL, LIMPIEZA Y PULIDO CON THINER (FUENTE: PROPIA) ....................... 130
FIGURA 53_APLICACIÓN DE FENOLFTALEINA (FUENTE: PROPIA).............................................................................. 131
FIGURA 54_RESULTADO DE ENSAYO DE FENOLFTALEINA SOBRE COLUMNA ZONA A ACCESO PEATONAL (FUENTE: PROPIA) 132
FIGURA 55_RESULTADO DE ENSAYO DE FENOLFTALEINA SOBRE CELOSIA ENTRE ZONA B Y C (FUENTE: PROPIA) ............... 133
FIGURA 56_CAMBIO DE CARGA MUERTA DE 22.5KG A 13 KGM. REDUCCIÓN DEL 42% (FUENTE: PROPIA) ..................... 136
FIGURA 57_RELACIÓN DE DEFLEXIONES CORDON INFERIOR (FUENTE: PROPIA) .......................................................... 137
FIGURA 58_RELACIÓN DE DEFLEXIONES CORDON SUPERIOR (FUENTE: PROPIA) ......................................................... 138
FIGURA 59_RELACIÓN DE DEFLEXIONES E ÍNDICES DE CAPACIDAD CORDON SUPERIOR (FUENTE: PROPIA) ....................... 139
FIGURA 60_DIAGRAMA PARA REFUERZO Y CONSOLIDACIÓN DE APOYOS TIPO (FUENTE: PROPIA) ................................... 184
FIGURA 61_ESQUEMA DE MODULACIÓN DE CUBIERTA. ......................................................................................... 186

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


7

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
1) INFORME DEL ESTADO ACTUAL PARA LAS
ADECUACIONES DE LA INFRAESTRUCTURA DE CUBIERTA
DEL CENTRO NACIONAL DE ATENCION EN FRONTERA
CENAF
1.1) OBJETIVOS

a) General

Realizar un informe que determine el estado actual de los elementos de cubierta,


canales de recolección de aguas lluvias, elementos de anclaje a infraestructura,
domos de acrilico y demás elementos que la conformen desde la inspección
visual a las 5 cubiertas del CENAF.

Con el fin de proponer una intervención acorde con su importancia, basándose


en la recopilación y análisis de resultados fruto de algunas pruebas y ensayos
realizados al edificio, con el propósito de realizar un diagnóstico que conlleve a
su readecuación de cubiertas, según lo dispuesto en los nuevos requerimientos
que exige la actual Norma Colombiana de Construcción Sismo resistente NSR
10.

b) Específicos

Establecer si los elementos Metálicos Presentan algún tipo de deflexión

Identificar el estado de los elementos de Anclaje

Establecer el grado de Corrosión en los diferentes elementos metálicos

Verificar el estado de las Uniones sobre la estructura respecto al cambio de


Cubierta y sistema de recolección de aguas lluvias

Identificación, tipificación y localización de las diferentes lesiones (síntomas) que


se encuentran en la edificación.

Evaluar los niveles globales de las estructuras basados en la Norma NSR-10

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


8

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
1.2) ALCANCE

Los tipos de inspecciones que se realizaron en este estudio fueron:

A los elementos estructurales:


Análisis de deflexión de los elementos cuerdas y diagonales.

Verificacion de Carbonatacion a soldaduras:


En uniones de vigas, columnas y elementos principales

Para analizar el comportamiento general de la estructura de la edificación, se


realizó un modelamiento con dimensiones criticas que permita establecer un
comportamiento general de toda la estructura.

Los ensayos realizados en la edificación se determinaron mayormente


desde la inspección visual, por lo cual no debe ser considerado como un
estudio de detalle ni un estudio de vulnerabilidad. Esto es importante
resaltar en tanto, las conclusiones y recomendaciones elaboradas en este
informe no avalan:

Cortes, sustracción o reemplazo parcial o total de los elementos


estructurales de cuerdas inferiores, superiores y diagonales.

Reemplazo de platinas de anclaje y de base.

Aumento de cargas o implementación de sistemas de cubierta diferentes a


los expuestos.

Si se requieren conclusiones que determinen el comportamiento


estructural de la edificación ante una solicitación sísmica, es necesario
desarrollar un estudio de vulnerabilidad detallado que permita verificar
dichos comportamientos.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


9

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
1.3) DESCRIPCIÓN DE CONTEXTO

Ubicación:

Zona de Frontera del Municipio de Ipiales, Rumichaca, Departamento de Nariño.

Vías de Acceso:
Al lugar se accede por la ruta 25, conocida como vía Panamericana, en el que
funciona el punto de frontera entre el vecino país del Ecuador

Infraestructura de servicios públicos: El Predio cuenta con todos los servicios


de agua, luz, y comunicaciones.

Servicio de transporte

El sector cuenta con todos los servicios de transporte terrestre, como transporte
publico y privado

Usos del suelo del sector

Uso comercial e institucional

Actividades permitidas

Institucional
Comercio y servicio

Estratificación socioeconómica

Institucional

Descripción del sector

El sector de la frontera con el vecíno país del Ecuador es ampliamente reconocido


a nivel local y nacional como borde de transito entre ambos países, permitiendo
la dinámica comercial debido a la gran afluencia de turistas y locales quienes
generan un transito permanente.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


10

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
2) DESCRIPCIÓN DE LA EDIFICACIÓN

Figura 1_Localización CENAF (Fuente: Google Earth)

La edificación se ubica en la frontera entre los países de Ecuador y Colombia.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


11

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
2.1) DESCRIPCIÓN ARQUITECTÓNICA

Figura 2_Registro fotográfico contexto (Fuente: propia)

Figura 3_ Registro fotográfico contexto (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


12

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
La edificación corresponde a una configuración geométrica en planta de dos
cuerpos principales, uno rectangular y otro trapezoidal conexos en su sentido
mas largo

El desarrollo del programa arquitectónico se sustenta en las actividades


concernientes a la dinámica de aduanas y transito de personas provenientes
desde y hacia fuera del país.

En el primer nivel se encuentra el acceso vehicular y peatonal que se encuentra


cubierto por un sistema estructural de celosia tridimensional para soportar una
lamina de acrilico piramidal.

El acceso se desarrolla en una pendiente de aproximadamente 5° desde la calle


y niveles de parqueadero hasta el acceso al publico, en donde se encuentra
presente unas escaleras que conducen hasta el segundo nivel. Sobre el primer
nivel, se halla presente la Oficina de la Cruz Roja Colombiana y la Cruz Roja
Alemana.

En el segundo nivel, se encuentran las oficinas de control y registro para el


transito de personas, habiendo modulos de atención, oficinas de turismo, baterias
sanitarias, local comercial y oficinas varias.

En este nivel se hace presente una escalera que conduce hasta ultimo nivel de
la edificación, sirviendo de lugar para la oficina de Gerencia, y un puente en
estructura metálica que conecta con el Edificio de Impuestos y Aduanas DIAN

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


13

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Fotografía 1_Vista interior de la edificación.

Es una edificación de triple altura, en el que se enmarcan dos cuerpos de cubierta


definidos por su geometría en planta, y en cuya diferencia de nivel se evidencia
una celosia conectora para ambos sistemas. De igual manera el sistema de
celosia tridimensional predomina sobre gran parte del sistema de cubiertas con
teja piramidal de lamina de acrilico

Allí se desarrollan áreas administrativas y el aula de sistemas de la institución.

Las alturas de entrepiso de la edificación se encuentran así:

Piso 1 a Piso 2: 3.20 m libres


Piso 2 a Piso 3: 4.5 m libres
Nivel de cubierta a Cumbre: 0.70 m libres

Plara el Desarrollo de este Estudio se denominarán las cubiertas en sectores así:

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


14

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 4_ Localización de cubiertas (Fuente: Elaboracion propia)

A nivel de fachada, el Edificio, dispone de una modulacion de vanos para


ventanas con remate superior de arco de medio punto, trabajando contramarcos
en concreto rustico, y predomina el enchape y algunas veces el ladrillo visto.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


15

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
2.2) DESCRIPCIÓN ESTRUCTURAL

El edificio presenta un sistema estructural principal, es decir de la superestructura


d ela edificación, de porticos en concreto configurando un diafragma rigido
compuesto por columnas de sección de 30x30 y vigas de 30x30. Se presume el
trabajo de la Losa Maciza, en tanto el trabajo de los cielos falsos sobre las áreas
para el segundo nivel se encuentran cubiertos.

a) Cubierta Zona A Acceso peatonal

La estructura de cubierta se soporta sobre pilares conformados por angulos


metalicos de 2”x2” x 3/16” de espesor. En total son 12 pilares distribuidos en
distancias aproximadas de 9 metros hacia su sentido mas largo y 3 metros en su
sentido mas corto. Se sustentan en un pilar de Concreto de 50x50x50 y tiene una
altura de 2.80 metros aproximadamente

La celosia trimensional se conforma por tramos de tubo redondo modulados de


1 ½” de 3mm de espesor achatados en sus extremos para una perforación de
pernos de ½” de longitud de 1.40 metros en su sentido mas largo y 1.50 metros
en su sentido mas corto, articulados mediante unión mecánica de lamina de acero
perforada de 10 cm x 10 cm y 6 mm de espesor

b) Cubierta Zona B Atención:

La estructura de cubierta se soporta sobre pilares conformados por angulos


metalicos de 2”x2” x 3/16” de espesor que a su vez se apoyan sobre pilares de
concreto de 30x30x50 y directamente sobre los pilares en concreto o
mampostería sobre una platina base de 10cm x 10 cm x 3mm de espesor con 6
pernos de ½”. En total son 10 apoyos que sustentan a todo el sistema de cubierta

La celosia trimensional se conforma por tramos de tubo redondo modulados de


1 ½” de 3mm de espesor achatados en sus extremos para una perforación de
pernos de ½” de longitud de 1.50 metros en su sentido mas largo y 1.40 metros
en su sentido mas corto, articulados mediante unión mecánica de lamina de acero
perforada de 10 cm x 10 cm y 6 mm de espesor

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


16

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
c) Cubierta Zona C Oficinas:

La estructura de cubierta se soporta sobre pilares conformados por angulos


metalicos de 2”x2” x 3/16” de espesor que a su vez se apoyan sobre pilares de
concreto de 30x30x50 y directamente sobre los pilares en concreto o
mampostería sobre una platina base de 10cm x 10 cm x 3mm de espesor con 6
pernos de ½”. En total son 15 apoyos que sustentan a todo el sistema de
cubierta. Debe tenerse en cuenta que sobre el perímetro conexo con la
superestructura existe un templete a modo de apoyo, en tanto no hubo
coincidencia con la modulacion de la estructura de cubierta por lo cual se
improviso un apoyo artesanal sin ningún tipo de continuidad con la
superestructura.

La celosia trimensional se conforma por tramos de tubo redondo modulados de


1 ½” de 3mm de espesor achatados en sus extremos para una perforación de
pernos de ½” de longitud de 1.50 metros en su sentido mas largo y 1.40 metros
en su sentido mas corto, articulados mediante unión mecánica de lamina de acero
perforada de 10 cm x 10 cm y 6mm de espesor.

d) Cubierta Zona D Escaleras:

La estructura de cubierta se soporta sobre los pilares en concreto o mampostería


sobre una platina base de 15cm x 15 cm x 3mm de espesor con 6 pernos de ½”.
En total son 4 apoyos que sustentan a todo el sistema de cubierta

La celosia trimensional se conforma por tramos de tubo redondo modulados de


1 ½” de 3mm de espesor achatados en sus extremos para una perforación de
pernos de ½” de longitud de 1.00 metros en su sentido mas largo y 0.92 metros
en su sentido mas corto, articulados mediante unión mecánica de lamina de acero
perforada de 10 cm x 10 cm y 6 mm de espesor

e) Cubierta Zona E Puente:

La estructura de cubierta se soporta sobre los pilares en concreto o mampostería


sobre una platina base de 10cm x 10 cm x 3mm de espesor con 6 pernos de ½”
y sobre el Muro con Platinas de conexión de 15cm x 15 cm x 3mm. En total son
2 apoyos sobre platinas en losa y 7 apoyos sobre pared

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


17

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
La celosia trimensional se conforma por tramos de tubo redondo modulados de
1 ½” de 3mm de espesor achatados en sus extremos para una perforación de
pernos de ½” de longitud de 1.02 metros en su sentido mas largo y 0.95 metros
en su sentido mas corto, articulados mediante unión mecánica de lamina de acero
perforada de 10 cm x 10 cm y 6 mm de espesor

3) DESARROLLO DEL ANALISIS

El análisis estructural está basado por las disposiciones de las Normas


Colombianas de Construcciones Sismo-Resistente (NSR-10); trabajando una
metodología cualitativa que permite ponderar el estado de la edificación desde
diversas variables de análisis que permiten establecer su exposición ante el
riesgo sismico.

3.1) METODOLOGÍA DEL ANÁLISIS

a) Etapa 1: Verificación del alcance de la Norma NSR-10 A.10.1.3

La evaluación del estado estructural de la edificacion sísmica se aplica al edificio,


por tratarse de una construcción existente antes de la vigencia de la Norma NSR-
10. Los criterios presentados en la NSR-10 Capítulo A.10 se pueden utilizar en el
diagnóstico o evaluación de edificaciones existentes antes de la vigencia del
mismo.

b) Etapa 2: Recopilación de la información documental existente de la


edificación

Se ha recopilado la información existente encontrando un único Plano Estructural


entregado por la entidad Contratante, llevándose a cabo las siguientes
actividades:

• Inspección visual: Comprende la inspección preliminar realizada, en la


cual se ha realizado una caracterización general de los daños que
presenta la estructura de acuerdo a los objetivos planeados.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


18

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
• Recopilación de información: Solo se obtuvo un plano Estructural de la
edificación en el que difiere de la construcción actual, en tanto se puede
apreciar en planos que se pretendía trabajar con Varilla de acero y no con
tubo, razón por la cual solo corresponden algunas medidas de distribución
de los modulos para la proyección de la cubierta. 1

• Caracterización de daños: se percibe que la edificación no ha presentado


alteraciones significativas en tanto se hace evidente un mantenimiento
periódico de anticorrosivo y pintura por lo cual, el Estado de Conservación
de la Estructura según Tabla A.10.4-1 de la NSR-10 es Buena.

En las siguientes fotografías se muestra lo expuesto anteriormente:

Fotografía 2_Resolución de nudo de conexión, entre cuerdas y diagonales.

19
1
Según la información de los planos, la estructura se proyectó en el año 1998 y contó con un
diseño Preliminar que pese a que no se ejecutó se aprecian propiedades estructurales acordes a
las solicitaciones y requerimiento normal de este tipo de estructuras
INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Fotografía 3_Detalle de Nudo.

c) Etapa 3: Clasificación del sistema estructural

El sistema estructural está constituido por sistema de diagonales en acero


arriostradas mecánicamente por laminas de acero de 6 mm

La estructura es del tipo de muros de mampostería no reforzada a partir de la


definición de la NSR-10 en la tabla A.3-3, A. 5. Estructuras de Pendulo Invertido,
Porticos de Acero resistentes a momentos.

A partir de estas consideraciones se ha calificado la estructura así:

• Calidad del diseño y la construcción de la


Regular
estructura original.

• Estado de la estructura. Buena.


Tabla 1_Calificación del estado del sistema estructural.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


20

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
3.2) EVALUACIÓN DE LA ESTRUCTURA EXISTENTE DESDE METODOS
CUALITATIVOS Y CUANTITATIVOS

METODO CUANTITATIVO

a) Etapa 4: Solicitaciones equivalentes

Movimientos sísmicos equivalentes:

La estructura pertenece a Grupos III, Si


Fecha de diseño y construcción Posterior a 1998
Decreto 1400 Dic/84
NSR-982 x
Norma utilizada en el diseño
NSR-10
Ninguna
Se ha realizado intervención de
No
actualización
CRITERIOS DE EVALUACIÓN

Índice de sobreesfuerzo <1.0


Evaluación Cualitativa por X
Índice de flexibilidad <1.0
Indicadores
Índice de sobreesfuerzo <1.0
Índice de flexibilidad <1.5
A.10.4.2.2 Índice de sobreesfuerzo <1.0
Nivel de seguridad limitada Índice de flexibilidad <1.0
Tabla 2_Metodología de evaluación.

Tabla 3_Relación de coeficiente de Disipación de Energia y clasificación del Sistema estructural

21
2
Se presume por la existencia de planos
INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Clasificación del sistema estructural:

El sistema estructural de resistencia sísmica está conformado por un SISTEMA


DE PORTICOS DE ACERO RESISTENTE A MOMENTOS, en la totalidad de
todos los sistemas de cubierta. Cabe resaltar que la determinación de apoyos
rigidos constituye una articulación de tercer orden hacia la superestructura, lo
cual supone un comportamiento estructural de este tipo.

Coeficiente de capacidad de disipación de energía R’:

Como se trata de una edificación Porticos estructurales de Acero Resistentes a


momentos se usará 𝑅’ = 2.5 según lo estipulado en el capítulo A.10.4.2.4 (d).

Fuerzas sísmicas:

• Parámetros sísmicos de analisis:


Ubicación: Municipio de Ipiales. (NARIÑO)
NSR-10 A.2.3
Zona de Amenaza sísmicas: Alta.
NSR-10 A.2.3.3
Coeficiente de aceleración horizontal pico Aa = 0.30
efectiva: NSR-10 A.2.2.3
(APENDICE A-4)
Coeficiente de velocidad horizontal pico Av = 0.25
efectiva: NSR-10 A.2.2.3
(APENDICE A-4)
Sistema estructural: MUROS EN MAMPOSTERÍA
NO REFORZADA
Tipo de perfil del suelo: D
(Referencia estudio de suelos)
NSR-10 A.2.4
Coeficiente ampliación Fa del suelo 1.30
para la zona de periodos cortos del espectro: NSR-10 TABLA A.2.4-3

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


22

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Coeficiente ampliación Fv del suelo para 1.90
la zona de periodos intermedios del espectro: NSR-10 TABLA A.2.4-3

Figura 5_Coeficiente de amplificación Fa del suelo.

Figura 6_Coeficiente de amplificación Fv del suelo.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


23

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
CLASIFICACION DE LOS PERFILES
USADO
DE SUELO

D X

F
Tabla 4_Perfil del suelo

Grupo de Uso: Coeficiente de importancia. (NSR-10 A.2.5).

GRUPO DE COEFICIENTE DE
USADO
USO IMPORTANCIA

IV 1.50

III 1.25 X

II 1.10

I 1.0

Tabla 5_Grupo de uso de la edificación

Método de análisis Dinámico (CQC).


Masa Edificación: Peso propio estructura, cubierta
Características Vibratorias: Masa, Rigidez, Periodo de Vibración.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


24

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Mediante el espectro se evalúa los desplazamientos en los nodos, las fuerzas en
los miembros. Los modos de respuesta se combinan según las especificaciones
de NSR-10.
La solución se realiza mediante el método de la combinación cuadrática completa
(CQC).

Fuerzas gravitacionales

• Cargas de cubierta
O Esquema de Cubierta

Teja Piramidal en
acrilico 5 mm

Canal en lamina
Canal en lamina
metálica 3mm
metálica 3mm

Figura 7_Esquema de Cubierta

O Carga muerta
Peso de cubierta

Canal en Lamina 3 mm 7.15 kg/m2


Lamina de Acrilico 3 mm 10 kg/m2
Apoyos intermedios de
estructura para pendiente de 4.5 Kg/m2
canal

Total 22.5 kg/m2

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


25

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
O Carga viva

2.3.1 VIVA SEGÚN CODIGO (NSR-10) B.4.2 50 kg/m2

• Carga de granizo
2.3.1 GRANIZO SEGÚN CODIGO (NSR-10) B.4.8.3.2 100 kg/m2

Espectro sísmico de aceleraciones

ESPECTRO DE DISEÑO
CIUDAD: IPIALES
ZONA DE AMENAZA SÍSMICA: ALTA
Aa = 0.30 Dato entrada Apéndice A-4 Grupo de uso III
Av= 0.25 Dato entrada Apéndice A-4 SUELO TIPO D
Fv= 1.90 Dato salida Tabla A.2.4-4 Perfiles de suelos rígidos
Fa= 1.30 Dato salida Tabla A.2.4-3 que cumplan con el
criterio de velocidad de la
I = 1.25 Dato salida Tabla A.2.5-1
onda de cortante-Perfiles
To= 0.12 Dato salida For. A.2.6-6 de suelos rígidos que
Tc = 0.58 Dato salida For. A.2.6-2 cumplan cualquiera de las
TL = 4.56 Dato salida For. A.2.6-4 dos condiciones
PERIODOS DE VIBRACIÓN DIFERENTES DEL FUNDAMENTAL SI o NO? NO

2.000 Espectro elástico de diseño de aceleraciones


de diseño como fracción de g
Sa(g)

1.000

0.000
0.00 2.00 4.00 T(seg) 6.00 8.00 10.00

Tabla 6_Datos de espectro de diseño.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


26

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
DATOS ESPECTRO DE DISEÑO DATOS ESPECTRO DE DISEÑO
T (seg.) Sa(g) T (seg.) Sa(g) T (seg.) Sa(g) T (seg.) Sa(g)
0.00 1.219 2.150 0.34 4.30 0.166 6.45 0.078
0.05 1.219 2.200 0.33 4.35 0.164 6.50 0.077
0.10 1.219 2.250 0.32 4.40 0.162 6.55 0.076
0.15 1.219 2.300 0.32 4.45 0.160 6.60 0.075
0.20 1.219 2.350 0.31 4.50 0.158 6.65 0.073
0.25 1.219 2.400 0.30 4.55 0.157 6.70 0.072
0.30 1.219 2.450 0.30 4.60 0.154 6.75 0.071
0.35 1.219 2.500 0.29 4.65 0.150 6.80 0.070
0.40 1.219 2.550 0.29 4.70 0.147 6.85 0.069
0.45 1.219 2.600 0.28 4.75 0.144 6.90 0.068
0.50 1.219 2.650 0.27 4.80 0.141 6.95 0.067
0.55 1.219 2.700 0.27 4.85 0.138 7.00 0.066
0.60 1.188 2.750 0.26 4.90 0.135 7.05 0.065
0.65 1.096 2.800 0.26 4.95 0.133 7.10 0.064
0.70 1.018 2.850 0.25 5.00 0.130 7.15 0.064
0.75 0.950 2.900 0.25 5.05 0.127 7.20 0.063
0.80 0.891 2.950 0.25 5.10 0.125 7.25 0.062
0.85 0.838 3.000 0.24 5.15 0.122 7.30 0.061
0.90 0.792 3.050 0.24 5.20 0.120 7.35 0.060
0.95 0.750 3.100 0.23 5.25 0.118 7.40 0.059
1.00 0.713 3.150 0.23 5.30 0.116 7.45 0.059
1.05 0.679 3.200 0.23 5.35 0.114 7.50 0.058
1.10 0.648 3.250 0.22 5.40 0.111 7.55 0.057
1.15 0.620 3.300 0.22 5.45 0.109 7.60 0.056
1.20 0.594 3.350 0.22 5.50 0.107 7.65 0.056
1.25 0.570 3.400 0.21 5.55 0.105 7.70 0.055
1.30 0.548 3.450 0.21 5.60 0.104 7.75 0.054
1.35 0.528 3.500 0.21 5.65 0.102 7.80 0.053
1.40 0.509 3.550 0.20 5.70 0.100
1.45 0.491 3.600 0.20 5.75 0.098
1.50 0.475 3.650 0.20 5.80 0.097
1.55 0.460 3.700 0.20 5.85 0.095
1.60 0.445 3.750 0.19 5.90 0.093
1.65 0.432 3.800 0.19 5.95 0.092
1.70 0.419 3.850 0.19 6.00 0.090
1.75 0.407 3.900 0.19 6.05 0.089
1.80 0.396 3.950 0.18 6.10 0.087
1.85 0.385 4.000 0.18 6.15 0.086
1.90 0.375 4.050 0.18 6.20 0.085
1.95 0.365 4.100 0.18 6.25 0.083
2.00 0.356 4.150 0.17 6.30 0.082
2.05 0.348 4.200 0.17 6.35 0.081
2.10 0.339 4.250 0.17 6.40 0.079
Figura 8_Espectro de aceleraciones

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


27

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Combinaciones de carga
En el análisis de los elementos se emplearon las siguientes combinaciones de
carga:

1) D x 1.4

2) D x 1.2 + L x 1.6+ G x 0.5

3) D x 1.2 + L x 1.0+ G x 1.6

4) D x 1.20 + L x 1.0 + EX x 1. + EZ x .3

5) D x 1.20 + L x 1.0 + EX x 1. + EZ x -.3

6) D x 1.20 + L x 1.0 + EX x –1. + EZ x .3

7) D x 1.20 + L x 1.0 + EX x –1. + EZ x -.3

8) D x .9 + EX x 1. + EZ x .3

9) D x .9 + EX x 1. + EZ x -.3

10) D x .9 + EX x –1. + EZ x .3

11) D x .9 + EX x –1. + EZ x -.3

12) D x 1.20 + L x 1.0 + EX x .3 + EZ x 1.

13) D x 1.20 + L x 1.0 + EX x -.3 + EZ x 1.

14) D x 1.20 + L x 1.0 + EX x .3 + EZ x -1.

15) D x 1.20 + L x 1.0 + EX x -.3 + EZ x -1.

16) D x .9 + EX x .3 + EZ x 1.

17) D x .9 + EX x -.3 + EZ x 1.

18) D x .9 + EX x .3 + EZ x -1.

19) D x .9 + EX x -.3 + EZ x –1.

20) D x 1.2 + L x 1.6


Tabla 7_Combinaciones de carga.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


28

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Propiedades de los materiales

Para efectos de evaluación de la estructura, considerando el estado de la misma,


se han empleado los siguientes valores de resistencia de los materiales para los
elementos existentes:

• Acero 𝑓𝑦 = 420 𝑀𝑃𝑎 = 60000 𝑝𝑠𝑖

b) Etapa 7: Resistencia efectiva de la estructura

La resistencia efectiva de la estructura se obtiene a partir de la resistencia


existente, afectándola por los coeficientes de reducción determinados desde la
calificación de calidad y el estado de la estructura, de la siguiente forma:

𝑁𝑒𝑓 = Φ𝑐 ⋅ Φ𝑒 ⋅ 𝑁𝑒𝑥

Los coeficientes se han determinado de la tabla A.10.4-1 de la NSR-10


dependiendo de la calificación de calidad y estado de la estructura:

Calidad del diseño y la construcción,


o del estado de la construcción
Buena Regular Mala
Φc o Φe 1.0 0.8 0.6
Tabla 8_Valores de Φc y Φe.

Para este estudio se determino el coeficiente en 0.8

c) Etapa 8: Índice de sobreesfuerzo

El índice de sobreesfuerzo de la estructura se obtiene como el máximo cociente


entre las solicitaciones equivalentes y la resistencia efectiva que se calculan para
cada uno de los elementos estructurales individuales (Capítulo A.10.4.3.1 NSR-
A continuación, se presentan memorias graficas y descriptivas del análisis actual
de la cubierta mas critica. Zona B Atención

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


29

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
3.3) MODELACIÓN EN EL SOFTWARE ETABS

Con la información obtenida mediante los estudios previos realizados se procede


a la modelación de la estructura. A continuación se muestra el procedimiento
general efectuado.

a) Geometría estructural

La geometría de la estructura tanto en planta como en altura se realizó en el


software AutoCAD y posteriormente se importó a ETABS empleando el comando
File/Import/DXF File of 3D Model.

b) Materiales

En el menú Define/Material Properties/Add New Material se definió el material


existente en la estructura y sus propiedades. En la siguiente imagen se muestra
la ventana desplegada y cada una de las propiedades a introducir.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


30

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 9_Definición de materiales.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


31

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
c) Elementos estructurales

• Tipo frame

En el menú Define/Frame Sections/Add Pipe se definió la sección transversal


de los elementos tipo frame para cuerda inferior, superior y diagonal. En el botón.
A continuación se muestran las figuras correspondientes a esta definición:

Figura 10_Definición de sección.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


32

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
• Tipo Shell

En el menú Defíne/Slab Sections/Add New Slab se define la sección de


entrepiso a utilizar, en Thickness se proporciona el valor del espesor del
elemento.

Figura 11_Definición de material de cubierta

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


33

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
d) Apoyos

Se supone una cimentación totalmente rígida, que restringe el movimiento de los


nodos basales de la estructura. Utilizando el comando Assign/Joint/Restraints
se proporciona esta característica a los nodos, impidiendo tanto traslación como
rotación de los mismos lo cual restringe sus 6 grados de libertad.

Figura 12_Asignación de apoyos.

e) Asignación de elementos al modelo

Esta asignación se lleva a cabo empleando el comando Assign/Frame/Frame


Sections donde se encuentran las secciones previamente creadas para
asignarse a los elementos lineales del modelo.

f) Definición del espectro de respuesta

Teniendo previamente definido el espectro de respuesta para la ciudad de Ipiales


en un archivo de extensión .txt, en el menú Define/Response Spectrum
Functions, se escoge la opción Spectrum from File y se carga el archivo .txt
con la opción Period vs Value.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


34

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
g) Casos de carga estáticos definidos

Para definir los casos de carga a utilizar en el modelo, se llevó a cabo la definición
con el comando Define/Static Load Cases. Para el caso de carga muerta el
multiplicador del peso propio es uno (1) mientras que para los demás casos es
cero (0). La figura siguiente muestra la ventana emergente del programa en este
proceso:

Figura 13_Definición de casos de carga estáticos.

h) Analisis de Viento

El análisis de viento para la determinación de sobreesfuerzos sobre la estructura,


se definió por el software Corpasoft y se obtuvieron los siguientes resultados

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


35

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF
36

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF
37

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF
38

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF
39

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF
40

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Con lo anterior y tras el análisis matemático, se aprecia el comportamiento de
flexibilidad y resistencia de de la estructura demostrado en los siguientes gráficos:

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


41

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 14_Chequeo de deflexión cuerda Inferior

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


42

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 15_Chequeo de deflexión cuerda superior

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


43

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 16_Chequeo de deflexión diagonales

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


44

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
TABLE: Steel Frame
Summary - AISC LRFD
93
La Desig PMM M V
be Unique n Design Comb PMM Major V Major Major V Minor
Story l Name Type Section Status o Ratio Ratio Combo Ratio Combo

No Comb
Story1 B1 81F Beam tubo Message 5(T) 0.095 0.095 Comb3 0.011 Comb12
No Comb
Story1 B2 820 Beam tubo Message 5(T) 0.085 0.085 Comb3 0.01 Comb12
No Comb
Story1 B3 821 Beam tubo Message 3(T) 0.087 0.087 Comb3 0.01 Comb12
No Comb
Story1 B4 822 Beam tubo Message 5(T) 0.086 0.086 Comb3 0.01 Comb12
No Comb
Story1 B5 823 Beam tubo Message 5(T) 0.084 0.084 Comb3 0.01 Comb12
No Comb
Story1 B6 824 Beam tubo Message 5(T) 0.087 0.087 Comb3 0.01 Comb12
No Comb
Story1 B7 825 Beam tubo Message 5(T) 0.096 0.096 Comb5 0.011 Comb12
No Comb
Story1 B8 826 Beam tubo Message 5(T) 0.096 0.096 Comb5 0.011 Comb12
No Comb
Story1 B9 827 Beam tubo Message 5(T) 0.088 0.088 Comb3 0.01 Comb12
B1 No Comb
Story1 0 828 Beam tubo Message 4(T) 0.084 0.084 Comb3 0.01 Comb12
B1 No Comb
Story1 1 829 Beam tubo Message 3(T) 0.085 0.085 Comb3 0.01 Comb12
B1 No Comb
Story1 2 82A Beam tubo Message 5(T) 0.085 0.085 Comb3 0.01 Comb12
B1 No Comb
Story1 3 82B Beam tubo Message 5(T) 0.095 0.095 Comb3 0.011 Comb12
B1 No Comb
Story1 4 82C Beam tubo Message 4(T) 0.177 0.177 Comb4 0.02 Comb12
B1 No Comb
Story1 5 82D Beam tubo Message 4(T) 0.156 0.156 Comb5 0.018 Comb12
B1 No Comb
Story1 6 82E Beam tubo Message 5(T) 0.162 0.162 Comb5 0.018 Comb12
B1 No Comb
Story1 7 82F Beam tubo Message 5(C) 0.163 0.163 Comb4 0.018 Comb12
B1 No Comb
Story1 8 830 Beam tubo Message 5(T) 0.164 0.164 Comb5 0.018 Comb12
B1 No Comb
Story1 9 831 Beam tubo Message 5(T) 0.158 0.158 Comb5 0.018 Comb12
B2 No Comb
Story1 0 832 Beam tubo Message 5(T) 0.178 0.178 Comb5 0.02 Comb12
B2 No Comb
Story1 1 833 Beam tubo Message 5(T) 0.179 0.179 Comb5 0.02 Comb12
B2 No Comb
Story1 2 834 Beam tubo Message 5(T) 0.16 0.16 Comb5 0.018 Comb12
B2 No Comb
Story1 3 835 Beam tubo Message 5(T) 0.161 0.161 Comb4 0.018 Comb12
B2 No Comb
Story1 4 836 Beam tubo Message 5(T) 0.16 0.16 Comb5 0.018 Comb12
B2 No Comb
Story1 5 837 Beam tubo Message 3(C) 0.146 0.146 Comb4 0.018 Comb12
B2 No Comb
Story1 5 Beam tubo Message 4(T) 0.156 0.156
B2 No Comb
Story1 6 838 Beam tubo Message 4(T) 0.177 0.177 Comb4 0.02 Comb12
B2 No Comb
Story1 7 839 Beam tubo Message 4(T) 0.177 0.177 Comb5 0.02 Comb12

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


45

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B2 No Comb
Story1 8 83A Beam tubo Message 4(T) 0.157 0.157 Comb4 0.018 Comb12
B2 No Comb
Story1 9 83B Beam tubo Message 5(C) 0.161 0.161 Comb4 0.018 Comb12
B2 No Comb
Story1 9 Beam tubo Message 4(T) 0.161 0.161
B3 No Comb
Story1 0 83C Beam tubo Message 6(C) 0.054 0.054 Comb4 0.019 Comb12
B3 No Comb
Story1 0 Beam tubo Message 5(T) 0.176 0.176
B3 No Comb
Story1 1 83D Beam tubo Message 5(T) 0.177 0.177 Comb5 0.019 Comb12
B3 No Comb
Story1 2 83E Beam tubo Message 5(T) 0.163 0.163 Comb5 0.018 Comb12
B3 No Comb
Story1 3 83F Beam tubo Message 5(C) 0.164 0.164 Comb5 0.019 Comb12
B3 No Comb
Story1 4 840 Beam tubo Message 3(T) 0.109 0.109 Comb3 0.011 Comb12
B3 No Comb
Story1 5 841 Beam tubo Message 4(T) 0.073 0.073 Comb3 0.01 Comb12
B3 No Comb
Story1 6 842 Beam tubo Message 5(T) 0.073 0.073 Comb3 0.01 Comb12
B3 No Comb
Story1 7 843 Beam tubo Message 5(T) 0.071 0.071 Comb3 0.01 Comb12
B3 No Comb
Story1 8 844 Beam tubo Message 5(T) 0.073 0.073 Comb3 0.01 Comb12
B3 No Comb
Story1 9 845 Beam tubo Message 4(T) 0.077 0.077 Comb3 0.01 Comb12
B4 No Comb
Story1 0 846 Beam tubo Message 5(T) 0.077 0.077 Comb3 0.01 Comb12
B4 No Comb
Story1 1 847 Beam tubo Message 3(T) 0.122 0.122 Comb3 0.011 Comb12
B4 No Comb
Story1 2 848 Beam tubo Message 6(C) 0.05 0.05 Comb5 0.019 Comb12
B4 No Comb
Story1 2 Beam tubo Message 5(T) 0.167 0.167
B4 No Comb
Story1 3 849 Beam tubo Message 5(T) 0.176 0.176 Comb5 0.019 Comb12
B4 No Comb
Story1 4 84A Beam tubo Message 4(T) 0.172 0.172 Comb4 0.019 Comb12
B4 No Comb
Story1 5 84B Beam tubo Message 4(T) 0.159 0.159 Comb4 0.018 Comb12
B4 No Comb
Story1 6 84C Beam tubo Message 4(T) 0.158 0.158 Comb4 0.018 Comb12
B4 No Comb
Story1 7 84D Beam tubo Message 4(T) 0.177 0.177 Comb4 0.02 Comb12
B4 No Comb
Story1 8 84E Beam tubo Message 4(T) 0.096 0.096 Comb3 0.011 Comb12
B4 No Comb
Story1 9 84F Beam tubo Message 4(T) 0.085 0.085 Comb3 0.01 Comb12
B5 No Comb
Story1 0 850 Beam tubo Message 4(C) 0.113 0.113 Comb3 0.011 Comb12
B5 No Comb
Story1 1 851 Beam tubo Message 4(T) 0.178 0.178 Comb4 0.019 Comb12
B5 No Comb
Story1 2 852 Beam tubo Message 4(T) 0.177 0.177 Comb4 0.019 Comb12
B5 No Comb
Story1 3 853 Beam tubo Message 5(T) 0.165 0.165 Comb5 0.019 Comb12
B5 No Comb
Story1 4 854 Beam tubo Message 4(T) 0.159 0.159 Comb5 0.018 Comb12
B5 No Comb
Story1 5 855 Beam tubo Message 4(T) 0.156 0.156 Comb5 0.018 Comb12
B5 No Comb
Story1 6 856 Beam tubo Message 4(T) 0.15 0.15 Comb5 0.018 Comb12

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


46

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B5 No Comb
Story1 7 857 Beam tubo Message 5(T) 0.147 0.147 Comb4 0.018 Comb12
B5 No Comb
Story1 8 858 Beam tubo Message 5(T) 0.144 0.144 Comb4 0.018 Comb12
B5 No Comb
Story1 9 859 Beam tubo Message 5(T) 0.147 0.147 Comb4 0.018 Comb12
B6 No Comb
Story1 0 85A Beam tubo Message 4(T) 0.15 0.15 Comb5 0.018 Comb12
B6 No Comb
Story1 1 85B Beam tubo Message 4(T) 0.155 0.155 Comb5 0.018 Comb12
B6 No Comb
Story1 2 85C Beam tubo Message 4(T) 0.162 0.162 Comb5 0.019 Comb12
B6 No Comb
Story1 3 85D Beam tubo Message 4(T) 0.165 0.165 Comb5 0.019 Comb12
B6 No Comb
Story1 4 85E Beam tubo Message 4(T) 0.175 0.175 Comb4 0.019 Comb12
B6 No Comb
Story1 5 85F Beam tubo Message 4(T) 0.176 0.176 Comb4 0.019 Comb12
B6 No Comb
Story1 6 860 Beam tubo Message 4(T) 0.109 0.109 Comb3 0.011 Comb12
B6 No Comb
Story1 7 861 Beam tubo Message 4(T) 0.086 0.086 Comb3 0.01 Comb12
B6 No Comb
Story1 8 862 Beam tubo Message 4(T) 0.098 0.098 Comb3 0.011 Comb12
B6 No Comb
Story1 9 863 Beam tubo Message 4(T) 0.198 0.198 Comb5 0.021 Comb12
B7 No Comb
Story1 0 864 Beam tubo Message 4(T) 0.18 0.18 Comb4 0.019 Comb12
B7 No Comb
Story1 1 865 Beam tubo Message 4(T) 0.165 0.165 Comb5 0.019 Comb12
B7 No Comb
Story1 2 866 Beam tubo Message 4(T) 0.159 0.159 Comb4 0.018 Comb12
B7 No Comb
Story1 3 867 Beam tubo Message 4(T) 0.154 0.154 Comb4 0.018 Comb12
B7 No Comb
Story1 4 868 Beam tubo Message 4(T) 0.15 0.15 Comb4 0.018 Comb12
B7 No Comb
Story1 5 869 Beam tubo Message 4(T) 0.147 0.147 Comb4 0.018 Comb12
B7 No Comb
Story1 6 86A Beam tubo Message 5(T) 0.144 0.144 Comb4 0.018 Comb12
B7 No Comb
Story1 7 86B Beam tubo Message 4(T) 0.147 0.147 Comb4 0.018 Comb12
B7 No Comb
Story1 8 86C Beam tubo Message 4(T) 0.15 0.15 Comb4 0.018 Comb12
B7 No Comb
Story1 9 86D Beam tubo Message 4(T) 0.154 0.154 Comb5 0.018 Comb12
B8 No Comb
Story1 0 86E Beam tubo Message 4(T) 0.16 0.16 Comb4 0.018 Comb12
B8 No Comb
Story1 1 86F Beam tubo Message 4(T) 0.165 0.165 Comb4 0.019 Comb12
B8 No Comb
Story1 2 870 Beam tubo Message 4(T) 0.181 0.181 Comb5 0.019 Comb12
B8 No Comb
Story1 3 871 Beam tubo Message 4(T) 0.196 0.196 Comb4 0.02 Comb12
B8 No Comb
Story1 4 872 Beam tubo Message 4(T) 0.199 0.199 Comb4 0.021 Comb12
B8 No Comb
Story1 5 873 Beam tubo Message 4(T) 0.18 0.18 Comb4 0.019 Comb12
B8 No Comb
Story1 6 874 Beam tubo Message 4(T) 0.164 0.164 Comb4 0.019 Comb12
B8 No Comb
Story1 7 875 Beam tubo Message 4(T) 0.159 0.159 Comb4 0.018 Comb12
B8 No Comb
Story1 8 876 Beam tubo Message 4(T) 0.154 0.154 Comb4 0.018 Comb12

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


47

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B8 No Comb
Story1 9 877 Beam tubo Message 4(T) 0.15 0.15 Comb4 0.018 Comb12
B9 No Comb
Story1 0 878 Beam tubo Message 4(T) 0.146 0.146 Comb4 0.018 Comb12
B9 No Comb
Story1 1 879 Beam tubo Message 4(T) 0.144 0.144 Comb4 0.018 Comb12
B9 No Comb
Story1 2 87A Beam tubo Message 4(T) 0.147 0.147 Comb4 0.018 Comb12
B9 No Comb
Story1 3 87B Beam tubo Message 4(T) 0.15 0.15 Comb4 0.018 Comb12
B9 No Comb
Story1 4 87C Beam tubo Message 4(T) 0.154 0.154 Comb4 0.018 Comb12
B9 No Comb
Story1 5 87D Beam tubo Message 4(T) 0.159 0.159 Comb4 0.018 Comb12
B9 No Comb
Story1 6 87E Beam tubo Message 4(T) 0.164 0.164 Comb4 0.019 Comb12
B9 No Comb
Story1 7 87F Beam tubo Message 4(T) 0.18 0.18 Comb4 0.019 Comb12
B9 No Comb
Story1 8 880 Beam tubo Message 4(T) 0.197 0.197 Comb4 0.021 Comb12
B9 No Comb
Story1 9 881 Beam tubo Message 4(T) 0.184 0.184 Comb5 0.02 Comb12
B1 No Comb
Story1 00 882 Beam tubo Message 4(T) 0.166 0.166 Comb4 0.018 Comb12
B1 No Comb
Story1 01 883 Beam tubo Message 4(T) 0.162 0.162 Comb5 0.018 Comb12
B1 No Comb
Story1 02 884 Beam tubo Message 4(T) 0.158 0.158 Comb5 0.018 Comb12
B1 No Comb
Story1 03 885 Beam tubo Message 4(T) 0.154 0.154 Comb5 0.018 Comb12
B1 No Comb
Story1 04 886 Beam tubo Message 4(T) 0.15 0.15 Comb4 0.018 Comb12
B1 No Comb
Story1 05 887 Beam tubo Message 4(T) 0.146 0.146 Comb4 0.018 Comb12
B1 No Comb
Story1 06 888 Beam tubo Message 5(T) 0.144 0.144 Comb4 0.018 Comb12
B1 No Comb
Story1 07 889 Beam tubo Message 4(T) 0.147 0.147 Comb4 0.018 Comb12
B1 No Comb
Story1 08 88A Beam tubo Message 4(T) 0.15 0.15 Comb4 0.018 Comb12
B1 No Comb
Story1 09 88B Beam tubo Message 4(T) 0.154 0.154 Comb5 0.018 Comb12
B1 No Comb
Story1 10 88C Beam tubo Message 4(T) 0.158 0.158 Comb5 0.018 Comb12
B1 No Comb
Story1 11 88D Beam tubo Message 4(T) 0.162 0.162 Comb5 0.018 Comb12
B1 No Comb
Story1 12 88E Beam tubo Message 4(T) 0.167 0.167 Comb4 0.018 Comb12
B1 No Comb
Story1 13 88F Beam tubo Message 4(T) 0.183 0.183 Comb4 0.02 Comb12
B1 No Comb
Story1 14 890 Beam tubo Message 5(T) 0.199 0.199 Comb5 0.021 Comb12
B1 No Comb
Story1 15 891 Beam tubo Message 4(T) 0.179 0.179 Comb5 0.019 Comb12
B1 No Comb
Story1 16 892 Beam tubo Message 5(T) 0.165 0.165 Comb5 0.019 Comb12
B1 No Comb
Story1 17 893 Beam tubo Message 4(T) 0.159 0.159 Comb5 0.018 Comb12
B1 No Comb
Story1 18 894 Beam tubo Message 4(T) 0.154 0.154 Comb5 0.018 Comb12
B1 No Comb
Story1 19 895 Beam tubo Message 4(T) 0.15 0.15 Comb5 0.018 Comb12
B1 No Comb
Story1 20 896 Beam tubo Message 5(T) 0.146 0.146 Comb4 0.018 Comb12

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


48

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B1 No Comb
Story1 21 897 Beam tubo Message 5(T) 0.144 0.144 Comb4 0.018 Comb12
B1 No Comb
Story1 22 898 Beam tubo Message 5(T) 0.146 0.146 Comb4 0.018 Comb12
B1 No Comb
Story1 23 899 Beam tubo Message 4(T) 0.15 0.15 Comb5 0.018 Comb12
B1 No Comb
Story1 24 89A Beam tubo Message 4(T) 0.154 0.154 Comb5 0.018 Comb12
B1 No Comb
Story1 25 89B Beam tubo Message 4(T) 0.159 0.159 Comb5 0.018 Comb12
B1 No Comb
Story1 26 89C Beam tubo Message 5(T) 0.165 0.165 Comb5 0.019 Comb12
B1 No Comb
Story1 27 89D Beam tubo Message 5(T) 0.181 0.181 Comb5 0.019 Comb12
B1 No Comb
Story1 28 89E Beam tubo Message 5(T) 0.198 0.198 Comb4 0.021 Comb12
B1 No Comb
Story1 29 89F Beam tubo Message 5(T) 0.128 0.128 Comb5 0.012 Comb12
B1 No Comb
Story1 30 8A0 Beam tubo Message 5(T) 0.12 0.12 Comb5 0.011 Comb12
B1 No Comb
Story1 31 8A1 Beam tubo Message 5(T) 0.092 0.092 Comb3 0.01 Comb12
B1 No Comb
Story1 32 8A2 Beam tubo Message 5(T) 0.086 0.086 Comb5 0.01 Comb12
B1 No Comb
Story1 33 8A3 Beam tubo Message 3(T) 0.088 0.088 Comb3 0.01 Comb12
B1 No Comb
Story1 34 8A4 Beam tubo Message 4(T) 0.076 0.076 Comb3 0.01 Comb12
B1 No Comb
Story1 35 8A5 Beam tubo Message 5(T) 0.072 0.072 Comb3 0.01 Comb12
B1 No Comb
Story1 36 8A6 Beam tubo Message 5(T) 0.07 0.07 Comb3 0.01 Comb12
B1 No Comb
Story1 37 8A7 Beam tubo Message 4(T) 0.072 0.072 Comb3 0.01 Comb12
B1 No Comb
Story1 38 8A8 Beam tubo Message 4(T) 0.075 0.075 Comb3 0.01 Comb12
B1 No Comb
Story1 39 8A9 Beam tubo Message 5(T) 0.08 0.08 Comb3 0.01 Comb12
B1 No Comb
Story1 40 8AA Beam tubo Message 3(T) 0.093 0.093 Comb3 0.01 Comb12
B1 No Comb
Story1 41 8AB Beam tubo Message 5(T) 0.092 0.092 Comb5 0.01 Comb12
B1 No Comb
Story1 42 8AC Beam tubo Message 5(T) 0.121 0.121 Comb5 0.011 Comb12
B1 No Comb
Story1 43 8AD Beam tubo Message 5(T) 0.126 0.126 Comb4 0.012 Comb12
B1 No Comb
Story1 44 8AE Beam tubo Message 4(C) 0.081 0.081 Comb3 0.01 Comb12
B1 No Comb
Story1 45 8AF Beam tubo Message 4(T) 0.07 0.07 Comb3 0.009 Comb12
B1 No Comb
Story1 46 8B0 Beam tubo Message 4(T) 0.078 0.078 Comb3 0.01 Comb12
B1 No Comb
Story1 47 8B1 Beam tubo Message 7(C) 0.023 0.023 Comb4 0.018 Comb12
B1 No Comb
Story1 47 Beam tubo Message 4(T) 0.147 0.147
B1 No Comb
Story1 48 8B2 Beam tubo Message 4(C) 0.131 0.131 Comb4 0.016 Comb12
B1 No Comb
Story1 48 Beam tubo Message 3(T) 0.122 0.122
B1 No Comb
Story1 49 8B3 Beam tubo Message 4(T) 0.146 0.146 Comb5 0.018 Comb12
B1 No Comb
Story1 50 8B4 Beam tubo Message 5(T) 0.146 0.146 Comb5 0.018 Comb12

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


49

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B1 No Comb
Story1 51 8B5 Beam tubo Message 5(T) 0.129 0.129 Comb5 0.016 Comb12
B1 No Comb
Story1 52 8B6 Beam tubo Message 5(T) 0.147 0.147 Comb5 0.018 Comb12
B1 No Comb
Story1 53 8B7 Beam tubo Message 3(C) 0.12 0.12 Comb5 0.016 Comb12
B1 No Comb
Story1 53 Beam tubo Message 5(T) 0.131 0.131
B1 No Comb
Story1 54 8B8 Beam tubo Message 4(C) 0.13 0.13 Comb4 0.016 Comb12
B1 No Comb
Story1 54 Beam tubo Message 3(T) 0.119 0.119
B1 No Comb
Story1 55 8B9 Beam tubo Message 5(T) 0.148 0.148 Comb5 0.018 Comb12
B1 No Comb
Story1 56 8BA Beam tubo Message 5(T) 0.082 0.082 Comb3 0.01 Comb12
B1 No Comb
Story1 57 8BB Beam tubo Message 5(T) 0.081 0.081 Comb3 0.009 Comb12
B1 No Comb
Story1 58 8BC Beam tubo Message 4(T) 0.078 0.078 Comb3 0.009 Comb12
B1 No Comb
Story1 59 8BD Beam tubo Message 4(T) 0.066 0.066 Comb3 0.009 Comb12
B1 No Comb
Story1 60 8BE Beam tubo Message 5(T) 0.094 0.094 Comb5 0.01 Comb12
B1 No Comb
Story1 61 8BF Beam tubo Message 5(T) 0.143 0.143 Comb4 0.018 Comb12
B1 No Comb
Story1 62 8C0 Beam tubo Message 5(T) 0.133 0.133 Comb5 0.016 Comb12
B1 No Comb
Story1 63 8C1 Beam tubo Message 5(T) 0.135 0.135 Comb5 0.016 Comb12
B1 No Comb
Story1 64 8C2 Beam tubo Message 5(T) 0.13 0.13 Comb5 0.016 Comb12
B1 No Comb
Story1 65 8C3 Beam tubo Message 5(T) 0.129 0.129 Comb5 0.016 Comb12
B1 No Comb
Story1 66 8C4 Beam tubo Message 5(C) 0.134 0.134 Comb5 0.016 Comb12
B1 No Comb
Story1 66 Beam tubo Message 3(T) 0.124 0.124
B1 No Comb
Story1 67 8C5 Beam tubo Message 7(C) 0.014 0.014 Comb5 0.017 Comb12
B1 No Comb
Story1 67 Beam tubo Message 5(T) 0.139 0.139
B1 No Comb
Story1 68 8C6 Beam tubo Message 5(T) 0.147 0.147 Comb5 0.018 Comb12
B1 No Comb
Story1 69 8C7 Beam tubo Message 5(T) 0.145 0.145 Comb4 0.018 Comb12
B1 No Comb
Story1 70 8C8 Beam tubo Message 5(T) 0.132 0.132 Comb5 0.016 Comb12
B1 No Comb
Story1 71 8C9 Beam tubo Message 4(T) 0.129 0.129 Comb4 0.016 Comb12
B1 No Comb
Story1 72 8CA Beam tubo Message 4(T) 0.128 0.128 Comb5 0.016 Comb12
B1 No Comb
Story1 73 8CC Beam tubo Message 4(C) 0.128 0.128 Comb5 0.016 Comb12
B1 No Comb
Story1 73 Beam tubo Message 3(T) 0.119 0.119
B1 No Comb
Story1 74 8CD Beam tubo Message 4(C) 0.128 0.128 Comb4 0.016 Comb12
B1 No Comb
Story1 75 8CE Beam tubo Message 3(C) 0.122 0.122 Comb4 0.016 Comb12
B1 No Comb
Story1 75 Beam tubo Message 4(T) 0.132 0.132
B1 No Comb
Story1 76 8CF Beam tubo Message 5(T) 0.148 0.148 Comb5 0.018 Comb12

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


50

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B1 No Comb
Story1 77 8D0 Beam tubo Message 4(T) 0.145 0.145 Comb4 0.018 Comb12
B1 No Comb
Story1 78 8D1 Beam tubo Message 5(T) 0.13 0.13 Comb5 0.016 Comb12
B1 No Comb
Story1 79 8D2 Beam tubo Message 3(C) 0.113 0.113 Comb4 0.016 Comb12
B1 No Comb
Story1 79 Beam tubo Message 4(T) 0.126 0.126
B1 No Comb
Story1 80 8D3 Beam tubo Message 4(T) 0.126 0.126 Comb4 0.016 Comb12
B1 No Comb
Story1 81 8D4 Beam tubo Message 5(C) 0.052 0.052 Comb5 0.016 Comb12
B1 No Comb
Story1 81 Beam tubo Message 4(T) 0.127 0.127
B1 No Comb
Story1 82 8D5 Beam tubo Message 4(T) 0.127 0.127 Comb5 0.016 Comb12
B1 No Comb
Story1 83 8D6 Beam tubo Message 5(T) 0.075 0.075 Comb3 0.009 Comb12
B1 No Comb
Story1 84 8D7 Beam tubo Message 5(C) 0.078 0.078 Comb3 0.009 Comb12
B1 No Comb
Story1 84 Beam tubo Message 3(T) 0.074 0.074
B1 No Comb
Story1 85 8D8 Beam tubo Message 4(T) 0.145 0.145 Comb4 0.018 Comb12
B1 No Comb
Story1 86 8D9 Beam tubo Message 5(T) 0.13 0.13 Comb5 0.016 Comb12
B1 No Comb
Story1 87 8DA Beam tubo Message 5(T) 0.125 0.125 Comb5 0.016 Comb12
B1 No Comb
Story1 88 8DB Beam tubo Message 5(T) 0.125 0.125 Comb5 0.016 Comb12
B1 No Comb
Story1 89 8DC Beam tubo Message 5(C) 0.13 0.13 Comb5 0.016 Comb12
B1 No Comb
Story1 89 Beam tubo Message 3(T) 0.122 0.122
B1 No Comb
Story1 90 8DD Beam tubo Message 4(T) 0.144 0.144 Comb4 0.018 Comb12
B1 No Comb
Story1 91 8DE Beam tubo Message 4(T) 0.145 0.145 Comb4 0.018 Comb12
B1 No Comb
Story1 92 8DF Beam tubo Message 5(T) 0.129 0.129 Comb5 0.016 Comb12
B1 8.00E+ No Comb
Story1 93 00 Beam tubo Message 5(T) 0.125 0.125 Comb5 0.016 Comb12
B1 8.00E+ No Comb
Story1 94 01 Beam tubo Message 5(T) 0.125 0.125 Comb5 0.016 Comb12
B1 8.00E+ No Comb
Story1 95 02 Beam tubo Message 5(T) 0.13 0.13 Comb5 0.016 Comb12
B1 8.00E+ No Comb
Story1 96 03 Beam tubo Message 4(T) 0.145 0.145 Comb4 0.018 Comb12
B1 8.00E+ No Comb
Story1 97 04 Beam tubo Message 4(T) 0.145 0.145 Comb5 0.018 Comb12
B1 8.00E+ No Comb
Story1 98 05 Beam tubo Message 5(T) 0.129 0.129 Comb4 0.016 Comb12
B1 8.00E+ No Comb
Story1 99 06 Beam tubo Message 5(T) 0.125 0.125 Comb5 0.016 Comb12
B2 8.00E+ No Comb
Story1 00 07 Beam tubo Message 5(T) 0.125 0.125 Comb5 0.016 Comb12
B2 8.00E+ No Comb
Story1 01 08 Beam tubo Message 5(C) 0.13 0.13 Comb5 0.016 Comb12
B2 No Comb
Story1 01 Beam tubo Message 3(T) 0.122 0.122
B2 8.00E+ No Comb
Story1 02 09 Beam tubo Message 3(C) 0.136 0.136 Comb5 0.018 Comb12
B2 No Comb
Story1 02 Beam tubo Message 4(T) 0.145 0.145

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


51

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B2 No Comb
Story1 03 8EA Beam tubo Message 5(T) 0.145 0.145 Comb5 0.018 Comb12
B2 No Comb
Story1 04 8EB Beam tubo Message 5(T) 0.129 0.129 Comb5 0.016 Comb12
B2 No Comb
Story1 05 8EC Beam tubo Message 5(T) 0.126 0.126 Comb5 0.016 Comb12
B2 No Comb
Story1 06 8ED Beam tubo Message 5(T) 0.125 0.125 Comb5 0.016 Comb12
B2 No Comb
Story1 07 8EE Beam tubo Message 5(T) 0.129 0.129 Comb5 0.016 Comb12
B2 No Comb
Story1 08 8EF Beam tubo Message 5(T) 0.145 0.145 Comb5 0.018 Comb12
B2 No Comb
Story1 09 8F0 Beam tubo Message 5(T) 0.145 0.145 Comb5 0.018 Comb12
B2 No Comb
Story1 10 8F1 Beam tubo Message 5(T) 0.129 0.129 Comb5 0.016 Comb12
B2 No Comb
Story1 11 8F2 Beam tubo Message 5(T) 0.126 0.126 Comb5 0.016 Comb12
B2 No Comb
Story1 12 8F3 Beam tubo Message 5(T) 0.125 0.125 Comb5 0.016 Comb12
B2 No Comb
Story1 13 8F4 Beam tubo Message 5(T) 0.129 0.129 Comb5 0.016 Comb12
B2 No Comb
Story1 14 8F5 Beam tubo Message 5(T) 0.145 0.145 Comb5 0.018 Comb12
B2 No Comb
Story1 15 8F6 Beam tubo Message 4(T) 0.145 0.145 Comb5 0.018 Comb12
B2 No Comb
Story1 16 8F7 Beam tubo Message 5(T) 0.129 0.129 Comb4 0.016 Comb12
B2 No Comb
Story1 17 8F8 Beam tubo Message 5(T) 0.125 0.125 Comb5 0.016 Comb12
B2 No Comb
Story1 18 8F9 Beam tubo Message 5(T) 0.125 0.125 Comb5 0.016 Comb12
B2 No Comb
Story1 19 8FA Beam tubo Message 5(T) 0.13 0.13 Comb5 0.016 Comb12
B2 No Comb
Story1 20 8FB Beam tubo Message 4(T) 0.145 0.145 Comb5 0.018 Comb12
B2 No Comb
Story1 21 8FC Beam tubo Message 4(T) 0.145 0.145 Comb4 0.018 Comb12
B2 No Comb
Story1 22 8FD Beam tubo Message 5(T) 0.129 0.129 Comb5 0.016 Comb12
B2 No Comb
Story1 23 8FE Beam tubo Message 5(T) 0.125 0.125 Comb5 0.016 Comb12
B2 No Comb
Story1 24 8FF Beam tubo Message 7(C) 0.014 0.014 Comb5 0.016 Comb12
B2 No Comb
Story1 24 Beam tubo Message 5(T) 0.125 0.125
B2 No Comb
Story1 25 900 Beam tubo Message 7(C) 0.014 0.014 Comb5 0.016 Comb12
B2 No Comb
Story1 25 Beam tubo Message 5(T) 0.13 0.13
B2 No Comb
Story1 26 901 Beam tubo Message 4(C) 0.144 0.144 Comb4 0.018 Comb12
B2 No Comb
Story1 26 Beam tubo Message 1(T) 0.068 0.068
B2 No Comb
Story1 27 902 Beam tubo Message 4(T) 0.145 0.145 Comb4 0.018 Comb12
B2 No Comb
Story1 28 903 Beam tubo Message 4(C) 0.122 0.122 Comb5 0.016 Comb12
B2 No Comb
Story1 28 Beam tubo Message 5(T) 0.13 0.13
B2 No Comb
Story1 29 904 Beam tubo Message 4(C) 0.125 0.125 Comb5 0.016 Comb12
B2 No Comb
Story1 29 Beam tubo Message 5(T) 0.125 0.125

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


52

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B2 No Comb
Story1 30 905 Beam tubo Message 5(C) 0.125 0.125 Comb5 0.016 Comb12
B2 No Comb
Story1 30 Beam tubo Message 4(T) 0.126 0.126
B2 No Comb
Story1 31 906 Beam tubo Message 5(C) 0.127 0.127 Comb5 0.016 Comb12
B2 No Comb
Story1 31 Beam tubo Message 5(T) 0.124 0.124
B2 No Comb
Story1 32 907 Beam tubo Message 5(T) 0.13 0.13 Comb5 0.016 Comb12
B2 No Comb
Story1 33 908 Beam tubo Message 5(C) 0.076 0.076 Comb3 0.009 Comb12
B2 No Comb
Story1 33 Beam tubo Message 3(T) 0.07 0.07
B2 No Comb
Story1 34 909 Beam tubo Message 5(T) 0.077 0.077 Comb3 0.009 Comb12
B2 No Comb
Story1 35 90A Beam tubo Message 4(T) 0.145 0.145 Comb4 0.018 Comb12
B2 No Comb
Story1 36 90B Beam tubo Message 5(T) 0.13 0.13 Comb5 0.016 Comb12
B2 No Comb
Story1 37 90C Beam tubo Message 4(T) 0.126 0.126 Comb4 0.016 Comb12
B2 No Comb
Story1 38 90D Beam tubo Message 4(T) 0.127 0.127 Comb4 0.016 Comb12
B2 No Comb
Story1 39 90E Beam tubo Message 4(T) 0.127 0.127 Comb5 0.016 Comb12
B2 No Comb
Story1 40 90F Beam tubo Message 5(T) 0.127 0.127 Comb4 0.016 Comb12
B2 No Comb
Story1 41 910 Beam tubo Message 4(T) 0.129 0.129 Comb4 0.016 Comb12
B2 No Comb
Story1 42 911 Beam tubo Message 5(T) 0.147 0.147 Comb4 0.018 Comb12
B2 No Comb
Story1 43 912 Beam tubo Message 5(T) 0.145 0.145 Comb4 0.018 Comb12
B2 No Comb
Story1 44 913 Beam tubo Message 5(T) 0.132 0.132 Comb5 0.016 Comb12
B2 No Comb
Story1 45 914 Beam tubo Message 4(T) 0.13 0.13 Comb4 0.016 Comb12
B2 No Comb
Story1 46 915 Beam tubo Message 4(T) 0.129 0.129 Comb5 0.016 Comb12
B2 No Comb
Story1 47 916 Beam tubo Message 5(T) 0.129 0.129 Comb5 0.016 Comb12
B2 No Comb
Story1 48 917 Beam tubo Message 7(C) 0.013 0.013 Comb5 0.016 Comb12
B2 No Comb
Story1 48 Beam tubo Message 5(T) 0.129 0.129
B2 No Comb
Story1 49 918 Beam tubo Message 4(T) 0.131 0.131 Comb4 0.016 Comb12
B2 No Comb
Story1 50 919 Beam tubo Message 5(C) 0.148 0.148 Comb5 0.018 Comb12
B2 No Comb
Story1 50 Beam tubo Message 1(T) 0.07 0.07
B2 No Comb
Story1 51 91A Beam tubo Message 5(T) 0.145 0.145 Comb4 0.018 Comb12
B2 No Comb
Story1 52 91B Beam tubo Message 3(C) 0.123 0.123 Comb5 0.016 Comb12
B2 No Comb
Story1 52 Beam tubo Message 5(T) 0.132 0.132
B2 No Comb
Story1 53 91C Beam tubo Message 5(T) 0.134 0.134 Comb5 0.016 Comb12
B2 No Comb
Story1 54 91D Beam tubo Message 4(T) 0.13 0.13 Comb5 0.016 Comb12
B2 No Comb
Story1 55 91E Beam tubo Message 7(C) 0.015 0.015 Comb5 0.016 Comb12

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


53

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B2 No Comb
Story1 55 Beam tubo Message 5(T) 0.13 0.13
B2 No Comb
Story1 56 91F Beam tubo Message 5(T) 0.137 0.137 Comb5 0.016 Comb12
B2 No Comb
Story1 57 920 Beam tubo Message 5(T) 0.139 0.139 Comb5 0.017 Comb12
B2 No Comb
Story1 58 921 Beam tubo Message 7(C) 0.015 0.015 Comb5 0.018 Comb12
B2 No Comb
Story1 58 Beam tubo Message 5(T) 0.148 0.148
B2 No Comb
Story1 59 922 Beam tubo Message 5(T) 0.082 0.082 Comb3 0.01 Comb12
B2 No Comb
Story1 60 923 Beam tubo Message 5(T) 0.081 0.081 Comb3 0.009 Comb12
B2 No Comb
Story1 61 924 Beam tubo Message 4(T) 0.077 0.077 Comb3 0.009 Comb12
B2 No Comb
Story1 62 925 Beam tubo Message 5(T) 0.065 0.065 Comb3 0.009 Comb12
B2 No Comb
Story1 63 926 Beam tubo Message 5(T) 0.096 0.096 Comb5 0.01 Comb12
B2 No Comb
Story1 64 927 Beam tubo Message 4(T) 0.132 0.132 Comb5 0.016 Comb12
B2 No Comb
Story1 65 928 Beam tubo Message 4(C) 0.124 0.124 Comb4 0.016 Comb12
B2 No Comb
Story1 65 Beam tubo Message 4(T) 0.131 0.131
B2 No Comb
Story1 66 929 Beam tubo Message 5(T) 0.148 0.148 Comb5 0.018 Comb12
B2 No Comb
Story1 67 92A Beam tubo Message 5(C) 0.147 0.147 Comb5 0.018 Comb12
B2 No Comb
Story1 68 92B Beam tubo Message 3(C) 0.12 0.12 Comb5 0.016 Comb12
B2 No Comb
Story1 68 Beam tubo Message 5(T) 0.129 0.129
B2 No Comb
Story1 69 92C Beam tubo Message 5(T) 0.147 0.147 Comb5 0.018 Comb12
B2 No Comb
Story1 70 92D Beam tubo Message 5(T) 0.147 0.147 Comb5 0.018 Comb12
B2 No Comb
Story1 71 92E Beam tubo Message 4(C) 0.129 0.129 Comb4 0.016 Comb12
B2 No Comb
Story1 71 Beam tubo Message 3(T) 0.12 0.12
B2 No Comb
Story1 72 92F Beam tubo Message 4(T) 0.146 0.146 Comb5 0.018 Comb12
B2 No Comb
Story1 73 930 Beam tubo Message 4(T) 0.081 0.081 Comb3 0.01 Comb12
B2 No Comb
Story1 74 931 Beam tubo Message 5(C) 0.068 0.068 Comb3 0.009 Comb12
B2 No Comb
Story1 74 Beam tubo Message 4(T) 0.069 0.069
B2 No Comb
Story1 75 932 Beam tubo Message 4(T) 0.078 0.078 Comb3 0.01 Comb12
B2 No Comb
Base 76 933 Beam tubo Message 5(C) 0.114 0.013 Comb3 0.002 Comb4
B2 No Comb
Base 77 934 Beam tubo Message 5(C) 0.042 0.007 Comb3 0.002 Comb5
B2 No Comb
Base 78 935 Beam tubo Message 5(C) 0.038 0.01 Comb3 0.002 Comb4
B2 No Comb
Base 79 936 Beam tubo Message 4(C) 0.023 0.01 Comb3 0.002 Comb5
B2 No Comb
Base 79 Beam tubo Message 12(T) 0.009 0.008
B2 No Comb
Base 80 937 Beam tubo Message 5(C) 0.047 0.007 Comb3 0.002 Comb5

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


54

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B2 No Comb
Base 80 Beam tubo Message 12(T) 0.007 0.005
B2 No Comb
Base 81 938 Beam tubo Message 4(C) 0.014 0.01 Comb3 0.002 Comb5
B2 No Comb
Base 81 Beam tubo Message 3(T) 0.023 0.015
B2 No Comb
Base 82 939 Beam tubo Message 5(T) 0.087 0.012 Comb3 0.003 Comb4
B2 No Comb
Base 84 93B Beam tubo Message 5(C) 0.122 0.02 Comb3 0.003 Comb4
B2 No Comb
Base 85 93C Beam tubo Message 5(T) 0.077 0.02 Comb3 0.003 Comb4
B2 No Comb
Base 86 93D Beam tubo Message 5(C) 0.122 0.031 Comb3 0.003 Comb4
B2 No Comb
Base 87 93E Beam tubo Message 5(C) 0.573 0.049 Comb3 0.003 Comb4
B2 No Comb
Base 88 93F Beam tubo Message 5(C) 0.038 0.009 Comb3 0.002 Comb3
B2 No Comb
Base 88 Beam tubo Message 3(T) 0.02 0.015
B2 No Comb
Base 89 940 Beam tubo Message 3(T) 0.056 0.016 Comb3 0.002 Comb3
B2 No Comb
Base 90 941 Beam tubo Message 3(T) 0.083 0.009 Comb3 0.002 Comb5
B2 No Comb
Base 91 942 Beam tubo Message 3(T) 0.034 0.015 Comb3 0.002 Comb5
B2 No Comb
Base 92 943 Beam tubo Message 4(C) 0.067 0.008 Comb3 0.002 Comb5
B2 No Comb
Base 93 944 Beam tubo Message 5(C) 0.284 0.009 Comb3 0.002 Comb3
B2 No Comb
Base 94 945 Beam tubo Message 5(C) 0.339 0.011 Comb3 0.002 Comb3
B2 No Comb
Base 95 946 Beam tubo Message 5(C) 0.027 0.008 Comb3 0.002 Comb3
B2 No Comb
Base 95 Beam tubo Message 3(T) 0.023 0.013
B2 No Comb
Base 96 947 Beam tubo Message 3(T) 0.055 0.016 Comb3 0.002 Comb5
B2 No Comb
Base 97 948 Beam tubo Message 3(T) 0.073 0.009 Comb3 0.002 Comb5
B2 No Comb
Base 98 949 Beam tubo Message 3(T) 0.053 0.012 Comb3 0.002 Comb5
B2 No Comb
Base 99 94A Beam tubo Message 2(C) 0.01 0.008 Comb3 0.002 Comb5
B2 No Comb
Base 99 Beam tubo Message 3(T) 0.035 0.012
B3 No Comb
Base 00 94B Beam tubo Message 5(C) 0.048 0.008 Comb3 0.002 Comb5
B3 No Comb
Base 00 Beam tubo Message 3(T) 0.028 0.014
B3 No Comb
Base 01 94C Beam tubo Message 5(C) 0.095 0.012 Comb3 0.002 Comb3
B3 No Comb
Base 02 94D Beam tubo Message 5(C) 0.082 0.01 Comb3 0.002 Comb3
B3 No Comb
Base 03 94E Beam tubo Message 3(T) 0.047 0.015 Comb3 0.002 Comb3
B3 No Comb
Base 04 94F Beam tubo Message 3(T) 0.058 0.01 Comb3 0.002 Comb5
B3 No Comb
Base 05 950 Beam tubo Message 3(T) 0.055 0.011 Comb3 0.002 Comb5
B3 No Comb
Base 06 951 Beam tubo Message 3(T) 0.047 0.011 Comb3 0.002 Comb3
B3 No Comb
Base 07 952 Beam tubo Message 3(T) 0.04 0.011 Comb3 0.002 Comb5

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


55

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B3 No Comb
Base 08 953 Beam tubo Message 3(T) 0.031 0.015 Comb3 0.002 Comb3
B3 No Comb
Base 09 954 Beam tubo Message 3(T) 0.039 0.011 Comb3 0.002 Comb3
B3 No Comb
Base 10 955 Beam tubo Message 3(T) 0.041 0.011 Comb3 0.002 Comb5
B3 No Comb
Base 11 956 Beam tubo Message 3(T) 0.035 0.011 Comb3 0.002 Comb3
B3 No Comb
Base 12 957 Beam tubo Message 3(T) 0.023 0.015 Comb3 0.002 Comb3
B3 No Comb
Base 13 958 Beam tubo Message 3(T) 0.027 0.012 Comb3 0.002 Comb3
B3 No Comb
Base 14 959 Beam tubo Message 3(T) 0.029 0.012 Comb3 0.002 Comb5
B3 No Comb
Base 15 95A Beam tubo Message 3(T) 0.026 0.012 Comb3 0.002 Comb3
B3 No Comb
Base 16 95B Beam tubo Message 3(T) 0.022 0.015 Comb3 0.002 Comb3
B3 No Comb
Base 17 95C Beam tubo Message 3(T) 0.02 0.015 Comb3 0.002 Comb3
B3 No Comb
Base 18 95D Beam tubo Message 3(T) 0.021 0.012 Comb3 0.002 Comb5
B3 No Comb
Base 19 95E Beam tubo Message 3(T) 0.023 0.012 Comb3 0.002 Comb5
B3 No Comb
Base 20 95F Beam tubo Message 3(T) 0.021 0.012 Comb3 0.002 Comb3
B3 No Comb
Base 21 960 Beam tubo Message 3(T) 0.019 0.015 Comb3 0.002 Comb3
B3 No Comb
Base 22 961 Beam tubo Message 3(T) 0.02 0.015 Comb3 0.002 Comb3
B3 No Comb
Base 23 962 Beam tubo Message 3(T) 0.021 0.012 Comb3 0.002 Comb3
B3 No Comb
Base 24 963 Beam tubo Message 3(T) 0.022 0.012 Comb3 0.002 Comb4
B3 No Comb
Base 25 964 Beam tubo Message 3(T) 0.02 0.012 Comb3 0.002 Comb4
B3 No Comb
Base 26 965 Beam tubo Message 3(T) 0.019 0.015 Comb3 0.002 Comb4
B3 No Comb
Base 27 966 Beam tubo Message 3(T) 0.022 0.015 Comb3 0.002 Comb3
B3 No Comb
Base 28 967 Beam tubo Message 3(T) 0.024 0.012 Comb3 0.002 Comb3
B3 No Comb
Base 29 968 Beam tubo Message 3(T) 0.027 0.012 Comb3 0.002 Comb5
B3 No Comb
Base 30 969 Beam tubo Message 3(T) 0.024 0.012 Comb3 0.002 Comb5
B3 No Comb
Base 31 96A Beam tubo Message 3(T) 0.021 0.015 Comb3 0.002 Comb12
B3 No Comb
Base 32 96B Beam tubo Message 3(T) 0.028 0.015 Comb3 0.002 Comb3
B3 No Comb
Base 33 96C Beam tubo Message 3(T) 0.033 0.011 Comb3 0.002 Comb3
B3 No Comb
Base 34 96D Beam tubo Message 3(T) 0.036 0.011 Comb3 0.002 Comb5
B3 No Comb
Base 35 96E Beam tubo Message 3(T) 0.033 0.011 Comb3 0.002 Comb5
B3 No Comb
Base 36 96F Beam tubo Message 3(T) 0.026 0.015 Comb3 0.002 Comb12
B3 No Comb
Base 37 970 Beam tubo Message 3(T) 0.042 0.015 Comb3 0.002 Comb3
B3 No Comb
Base 38 971 Beam tubo Message 3(T) 0.049 0.011 Comb3 0.002 Comb5
B3 No Comb
Base 39 972 Beam tubo Message 3(T) 0.049 0.011 Comb3 0.002 Comb5

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


56

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B3 No Comb
Base 40 973 Beam tubo Message 3(T) 0.045 0.011 Comb3 0.002 Comb5
B3 No Comb
Base 41 974 Beam tubo Message 3(T) 0.037 0.011 Comb3 0.002 Comb5
B3 No Comb
Base 42 975 Beam tubo Message 3(T) 0.047 0.015 Comb3 0.002 Comb5
B3 No Comb
Base 43 976 Beam tubo Message 3(T) 0.057 0.01 Comb3 0.002 Comb5
B3 No Comb
Base 44 977 Beam tubo Message 3(T) 0.051 0.011 Comb3 0.002 Comb5
B3 No Comb
Base 45 978 Beam tubo Message 2(C) 0.01 0.008 Comb3 0.002 Comb5
B3 No Comb
Base 45 Beam tubo Message 3(T) 0.042 0.011
B3 No Comb
Base 46 979 Beam tubo Message 5(C) 0.032 0.007 Comb3 0.002 Comb5
B3 No Comb
Base 46 Beam tubo Message 3(T) 0.037 0.013
B3 No Comb
Base 47 97A Beam tubo Message 5(C) 0.057 0.01 Comb3 0.002 Comb3
B3 No Comb
Base 47 Beam tubo Message 3(T) 0.024 0.016
B3 No Comb
Base 48 97B Beam tubo Message 5(C) 0.057 0.009 Comb3 0.002 Comb3
B3 No Comb
Base 48 Beam tubo Message 12(T) 0.015 0.008
B3 No Comb
Base 49 97C Beam tubo Message 3(T) 0.044 0.016 Comb3 0.002 Comb12
B3 No Comb
Base 50 97D Beam tubo Message 3(T) 0.062 0.01 Comb3 0.002 Comb5
B3 No Comb
Base 51 97E Beam tubo Message 3(T) 0.04 0.013 Comb3 0.002 Comb5
B3 No Comb
Base 52 97F Beam tubo Message 4(C) 0.053 0.007 Comb3 0.002 Comb5
B3 No Comb
Base 52 Beam tubo Message 3(T) 0.017 0.013
B3 No Comb
Base 53 980 Beam tubo Message 4(C) 0.099 0.008 Comb3 0.002 Comb3
B3 No Comb
Base 54 981 Beam tubo Message 4(C) 0.109 0.008 Comb3 0.002 Comb3
B3 No Comb
Base 55 982 Beam tubo Message 5(C) 0.048 0.009 Comb3 0.002 Comb3
B3 No Comb
Base 55 Beam tubo Message 12(T) 0.013 0.008
B3 No Comb
Base 56 983 Beam tubo Message 3(T) 0.052 0.016 Comb3 0.002 Comb3
B3 No Comb
Base 57 984 Beam tubo Message 3(T) 0.077 0.01 Comb3 0.002 Comb12
B3 No Comb
Base 58 985 Beam tubo Message 5(C) 0.023 0.008 Comb3 0.002 Comb5
B3 No Comb
Base 58 Beam tubo Message 3(T) 0.026 0.015
B3 No Comb
Base 59 986 Beam tubo Message 4(C) 0.087 0.008 Comb3 0.002 Comb5
B3 No Comb
Base 60 987 Beam tubo Message 5(C) 0.334 0.01 Comb3 0.002 Comb3
B3 No Comb
Base 61 988 Beam tubo Message 5(C) 0.389 0.013 Comb3 0.002 Comb5
B3 No Comb
Base 62 989 Beam tubo Message 5(C) 0.027 0.008 Comb3 0.002 Comb3
B3 No Comb
Base 62 Beam tubo Message 3(T) 0.019 0.013
B3 No Comb
Base 63 98A Beam tubo Message 5(T) 0.093 0.015 Comb3 0.003 Comb4

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


57

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B3 No Comb
Base 65 98C Beam tubo Message 5(C) 0.125 0.018 Comb3 0.003 Comb4
B3 No Comb
Base 66 98D Beam tubo Message 5(T) 0.077 0.023 Comb3 0.003 Comb4
B3 No Comb
Base 67 98E Beam tubo Message 5(C) 0.118 0.02 Comb3 0.003 Comb4
B3 No Comb
Base 68 98F Beam tubo Message 5(C) 0.685 0.079 Comb3 0.004 Comb4
B3 No Comb
Base 69 990 Beam tubo Message 5(C) 0.048 0.009 Comb3 0.002 Comb5
B3 No Comb
Base 69 Beam tubo Message 3(T) 0.017 0.015
B3 No Comb
Base 70 991 Beam tubo Message 5(C) 0.055 0.008 Comb3 0.002 Comb5
B3 No Comb
Base 70 Beam tubo Message 12(T) 0.007 0.006
B3 No Comb
Base 71 992 Beam tubo Message 4(C) 0.018 0.01 Comb3 0.002 Comb5
B3 No Comb
Base 71 Beam tubo Message 3(T) 0.023 0.015
B3 No Comb
Base 72 993 Beam tubo Message 5(C) 0.036 0.011 Comb3 0.002 Comb5
B3 No Comb
Base 73 994 Beam tubo Message 4(C) 0.026 0.01 Comb3 0.002 Comb5
B3 No Comb
Base 73 Beam tubo Message 12(T) 0.009 0.008
B3 No Comb
Base 74 995 Beam tubo Message 5(C) 0.094 0.021 Comb3 0.002 Comb4
B3 No Comb
Base 75 996 Beam tubo Message 5(C) 0.038 0.008 Comb3 0.002 Comb5
B3 No Comb
Base 75 Beam tubo Message 12(T) 0.008 0.007
B3 No Comb
Base 76 997 Beam tubo Message 5(C) 0.049 0.009 Comb3 0.002 Comb5
B3 No Comb
Base 77 998 Beam tubo Message 5(C) 0.263 0.009 Comb3 0.002 Comb5
B3 No Comb
Base 78 999 Beam tubo Message 5(C) 0.544 0.015 Comb3 0.002 Comb5
B3 No Comb
Base 79 99A Beam tubo Message 5(C) 0.677 0.018 Comb3 0.002 Comb5
B3 No Comb
Base 80 99B Beam tubo Message 5(C) 0.485 0.014 Comb3 0.002 Comb3
B3 No Comb
Base 81 99C Beam tubo Message 5(C) 0.211 0.008 Comb3 0.002 Comb3
B3 No Comb
Base 82 99D Beam tubo Message 5(C) 0.275 0.009 Comb3 0.002 Comb3
B3 No Comb
Base 83 99E Beam tubo Message 5(C) 0.478 0.013 Comb3 0.002 Comb3
B3 No Comb
Base 84 99F Beam tubo Message 5(C) 0.389 0.011 Comb3 0.002 Comb12
B3 No Comb
Base 85 9A1 Beam tubo Message 5(C) 0.093 0.009 Comb3 0.002 Comb5
B3 No Comb
Base 86 9A2 Beam tubo Message 5(C) 0.035 0.01 Comb3 0.002 Comb5
B3 No Comb
Base 86 Beam tubo Message 12(T) 0.008 0.008
B3 No Comb
Base 87 9A3 Beam tubo Message 4(C) 0.04 0.011 Comb3 0.002 Comb4
B3 No Comb
Base 88 9A4 Beam tubo Message 5(C) 0.236 0.009 Comb3 0.002 Comb5
B3 No Comb
Base 89 9A5 Beam tubo Message 4(C) 0.709 0.022 Comb3 0.002 Comb4
B3 No Comb
Base 90 9A6 Beam tubo Message 5(C) 1.072 0.053 Comb3 0.002 Comb5

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


58

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B3 No Comb
Base 91 9A7 Beam tubo Message 5(C) 0.569 0.017 Comb3 0.002 Comb3
B3 No Comb
Base 92 9A8 Beam tubo Message 5(C) 0.099 0.007 Comb3 0.002 Comb3
B3 No Comb
Base 93 9A9 Beam tubo Message 5(C) 0.407 0.013 Comb3 0.002 Comb3
B3 No Comb
Base 94 9AA Beam tubo Message 5(C) 0.873 0.031 Comb3 0.002 Comb3
B3 No Comb
Base 95 9AB Beam tubo Message 4(C) 0.57 0.017 Comb3 0.002 Comb4
B3 No Comb
Base 96 9AC Beam tubo Message 5(C) 0.092 0.009 Comb3 0.002 Comb5
B3 No Comb
Base 97 9AD Beam tubo Message 4(C) 0.037 0.011 Comb3 0.002 Comb4
B3 No Comb
Base 98 9AE Beam tubo Message 6(C) 0.029 0.006 Comb3 0.002 Comb5
B3 No Comb
Base 98 Beam tubo Message 3(T) 0.02 0.017
B3 No Comb
Base 99 9AF Beam tubo Message 3(T) 0.018 0.014 Comb3 0.002 Comb5
B4 No Comb
Base 00 9B0 Beam tubo Message 4(C) 0.048 0.008 Comb3 0.002 Comb5
B4 Error: See Comb
Base 01 9B1 Beam tubo Message 12(C) 3.27 1.958 Comb3 0.004 Comb5
B4 No Comb
Base 02 9B2 Beam tubo Message 4(C) 0.872 0.023 Comb3 0.002 Comb3
B4 No Comb
Base 03 9B3 Beam tubo Message 3(C) 0.231 0.016 Comb3 0.002 Comb3
B4 No Comb
Base 04 9B4 Beam tubo Message 4(T) 0.06 0.004 Comb3 0.002 Comb5
B4 No Comb
Base 05 9B6 Beam tubo Message 3(T) 0.465 0.013 Comb3 0.002 Comb5
B4 No Comb
Base 06 9B7 Beam tubo Message 3(T) 0.468 0.013 Comb3 0.002 Comb5
B4 No Comb
Base 07 9B8 Beam tubo Message 3(T) 0.412 0.012 Comb3 0.002 Comb3
B4 No Comb
Base 08 9B9 Beam tubo Message 3(T) 0.06 0.015 Comb3 0.002 Comb3
B4 No Comb
Base 09 9BA Beam tubo Message 3(C) 0.569 0.026 Comb3 0.002 Comb5
B4 No Comb
Base 10 9BB Beam tubo Message 3(C) 0.937 0.044 Comb3 0.002 Comb3
B4 Error: See Comb 0.0001
Base 11 9BC Beam tubo Message 4(C) 1.999 624 Comb3 0.003 Comb3
B4 No Comb
Base 12 9BD Beam tubo Message 6(C) 0.033 0.011 Comb3 0.002 Comb5
B4 No Comb
Base 12 Beam tubo Message 4(T) 0.039 0.022
B4 No Comb
Base 13 9BE Beam tubo Message 3(T) 0.02 0.015 Comb3 0.002 Comb5
B4 No Comb
Base 14 9C0 Beam tubo Message 4(C) 0.062 0.014 Comb3 0.002 Comb4
B4 No Comb
Base 15 9C1 Beam tubo Message 4(C) 1.064 0.057 Comb3 0.002 Comb3
B4 No Comb
Base 16 9C2 Beam tubo Message 4(C) 0.595 0.019 Comb3 0.002 Comb3
B4 No Comb
Base 17 9C3 Beam tubo Message 3(C) 0.058 0.017 Comb3 0.002 Comb3
B4 No Comb
Base 18 9C4 Beam tubo Message 4(T) 0.084 0.006 Comb3 0.002 Comb5
B4 No Comb
Base 19 9C5 Beam tubo Message 4(T) 0.301 0.008 Comb3 0.002 Comb5
B4 No Comb
Base 20 9C6 Beam tubo Message 5(T) 0.397 0.009 Comb3 0.002 Comb12

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


59

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B4 No Comb
Base 21 9C7 Beam tubo Message 3(T) 0.453 0.012 Comb3 0.002 Comb5
B4 No Comb
Base 22 9C8 Beam tubo Message 3(T) 0.456 0.012 Comb3 0.002 Comb5
B4 No Comb
Base 23 9C9 Beam tubo Message 3(T) 0.402 0.012 Comb3 0.002 Comb3
B4 No Comb
Base 24 9CA Beam tubo Message 3(T) 0.292 0.01 Comb3 0.002 Comb3
B4 No Comb
Base 25 9CB Beam tubo Message 3(T) 0.077 0.015 Comb3 0.002 Comb3
B4 No Comb
Base 26 9CC Beam tubo Message 3(C) 0.106 0.019 Comb3 0.002 Comb5
B4 No Comb
Base 27 9CD Beam tubo Message 3(C) 0.65 0.031 Comb3 0.002 Comb3
B4 No Comb
Base 28 9CF Beam tubo Message 4(C) 1.047 0.056 Comb3 0.002 Comb3
B4 Error: See Comb
Base 29 9D0 Beam tubo Message 4(C) 2.25 0.001 Comb3 0.004 Comb5
B4 No Comb
Base 30 9D1 Beam tubo Message 4(C) 0.968 0.034 Comb3 0.002 Comb5
B4 No Comb
Base 31 9D2 Beam tubo Message 3(C) 0.097 0.019 Comb3 0.002 Comb5
B4 No Comb
Base 32 9D3 Beam tubo Message 4(T) 0.082 0.006 Comb3 0.002 Comb5
B4 No Comb
Base 33 9D4 Beam tubo Message 4(T) 0.302 0.008 Comb3 0.002 Comb5
B4 No Comb
Base 34 9D5 Beam tubo Message 4(T) 0.398 0.009 Comb3 0.002 Comb5
B4 No Comb
Base 35 9D6 Beam tubo Message 3(T) 0.446 0.012 Comb3 0.002 Comb5
B4 No Comb
Base 36 9D7 Beam tubo Message 3(T) 0.449 0.012 Comb3 0.002 Comb5
B4 No Comb
Base 37 9D8 Beam tubo Message 3(T) 0.396 0.012 Comb3 0.002 Comb5
B4 No Comb
Base 38 9D9 Beam tubo Message 3(T) 0.291 0.01 Comb3 0.002 Comb5
B4 No Comb
Base 39 9DC Beam tubo Message 3(T) 0.08 0.015 Comb3 0.002 Comb5
B4 No Comb
Base 40 9DD Beam tubo Message 3(C) 0.11 0.02 Comb3 0.002 Comb5
B4 No Comb
Base 41 9DE Beam tubo Message 4(C) 0.996 0.04 Comb3 0.002 Comb5
B4 Error: See Comb 0.0002
Base 42 9DF Beam tubo Message 4(C) 2.25 917 Comb3 0.003 Comb5
B4 9.00E+ No Comb
Base 43 00 Beam tubo Message 4(C) 0.763 0.034 Comb3 0.002 Comb3
B4 9.00E+ No Comb
Base 44 01 Beam tubo Message 4(C) 0.52 0.014 Comb3 0.002 Comb5
B4 9.00E+ No Comb
Base 45 02 Beam tubo Message 3(C) 0.049 0.018 Comb3 0.002 Comb5
B4 9.00E+ No Comb
Base 46 03 Beam tubo Message 4(T) 0.086 0.006 Comb3 0.002 Comb5
B4 9.00E+ No Comb
Base 47 04 Beam tubo Message 4(T) 0.306 0.008 Comb3 0.002 Comb5
B4 9.00E+ No Comb
Base 48 05 Beam tubo Message 4(T) 0.402 0.009 Comb3 0.002 Comb3
B4 9.00E+ No Comb
Base 49 06 Beam tubo Message 5(T) 0.45 0.01 Comb3 0.002 Comb3
B4 9.00E+ No Comb
Base 50 07 Beam tubo Message 3(T) 0.453 0.012 Comb3 0.002 Comb5
B4 9.00E+ No Comb
Base 51 08 Beam tubo Message 3(T) 0.401 0.012 Comb3 0.002 Comb5
B4 9.00E+ No Comb
Base 52 09 Beam tubo Message 4(T) 0.3 0.008 Comb3 0.002 Comb5

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


60

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B4 No Comb
Base 53 9EA Beam tubo Message 3(T) 0.087 0.014 Comb3 0.002 Comb5
B4 No Comb
Base 54 9EB Beam tubo Message 3(C) 0.051 0.018 Comb3 0.002 Comb5
B4 No Comb
Base 55 9EC Beam tubo Message 4(C) 0.532 0.015 Comb3 0.002 Comb5
B4 No Comb
Base 56 9ED Beam tubo Message 4(C) 0.763 0.026 Comb3 0.002 Comb3
B4 No Comb
Base 57 9EE Beam tubo Message 4(C) 0.798 0.035 Comb3 0.002 Comb5
B4 No Comb
Base 58 9EF Beam tubo Message 4(C) 0.571 0.016 Comb3 0.002 Comb3
B4 No Comb
Base 59 9F0 Beam tubo Message 3(C) 0.069 0.018 Comb3 0.002 Comb5
B4 No Comb
Base 60 9F1 Beam tubo Message 4(T) 0.087 0.006 Comb3 0.002 Comb5
B4 No Comb
Base 61 9F2 Beam tubo Message 4(T) 0.312 0.008 Comb3 0.002 Comb3
B4 No Comb
Base 62 9F3 Beam tubo Message 5(T) 0.411 0.01 Comb3 0.002 Comb3
B4 No Comb
Base 63 9F4 Beam tubo Message 3(T) 0.462 0.013 Comb3 0.002 Comb3
B4 No Comb
Base 64 9F5 Beam tubo Message 3(T) 0.467 0.013 Comb3 0.002 Comb3
B4 No Comb
Base 65 9F6 Beam tubo Message 3(T) 0.416 0.012 Comb3 0.002 Comb3
B4 No Comb
Base 66 9F7 Beam tubo Message 4(T) 0.31 0.008 Comb3 0.002 Comb3
B4 No Comb
Base 67 9F8 Beam tubo Message 3(T) 0.087 0.015 Comb3 0.002 Comb3
B4 No Comb
Base 68 9F9 Beam tubo Message 3(C) 0.077 0.019 Comb3 0.002 Comb5
B4 No Comb
Base 69 9FA Beam tubo Message 4(C) 0.579 0.017 Comb3 0.002 Comb3
B4 No Comb
Base 70 9FB Beam tubo Message 4(C) 0.809 0.027 Comb3 0.002 Comb5
B4 Error: See Comb
Base 71 9FC Beam tubo Message 5(C) 2.376 0.001 Comb3 0.004 Comb3
B4 No Comb
Base 72 9FD Beam tubo Message 4(C) 1.093 0.056 Comb3 0.002 Comb5
B4 No Comb
Base 73 9FE Beam tubo Message 3(C) 0.228 0.017 Comb3 0.002 Comb5
B4 No Comb
Base 74 9FF Beam tubo Message 4(T) 0.088 0.007 Comb3 0.002 Comb5
B4 No Comb
Base 75 A00 Beam tubo Message 5(T) 0.323 0.008 Comb3 0.002 Comb3
B4 No Comb
Base 76 A01 Beam tubo Message 5(T) 0.424 0.01 Comb3 0.002 Comb3
B4 No Comb
Base 77 A02 Beam tubo Message 3(T) 0.484 0.013 Comb3 0.002 Comb3
B4 No Comb
Base 78 A03 Beam tubo Message 3(T) 0.489 0.013 Comb3 0.002 Comb3
B4 No Comb
Base 79 A04 Beam tubo Message 3(T) 0.439 0.012 Comb3 0.002 Comb3
B4 No Comb
Base 80 A05 Beam tubo Message 3(T) 0.331 0.011 Comb3 0.002 Comb3
B4 No Comb
Base 81 A06 Beam tubo Message 4(T) 0.09 0.007 Comb3 0.002 Comb3
B4 No Comb
Base 82 A07 Beam tubo Message 3(C) 0.36 0.022 Comb3 0.002 Comb5
B4 No Comb
Base 83 A08 Beam tubo Message 4(C) 1.12 0.065 Comb3 0.002 Comb5
B4 Error: See Comb
Base 84 A09 Beam tubo Message 1(C) 4.276 2.929 Comb3 0.003 Comb3

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


61

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B4 No Comb
Base 85 A9D Beam tubo Message 4(T) 0.286 0.008 Comb3 0.002 Comb3
B4 No Comb
Base 86 A9E Beam tubo Message 3(T) 0.402 0.012 Comb3 0.002 Comb12
B4 No Comb
Base 87 2129 Beam tubo Message 5(C) 0.239 0.055 Comb3 0.006 Comb4
B4 No Comb
Base 88 2130 Beam tubo Message 5(T) 0.227 0.055 Comb3 0.006 Comb4
B4 No Comb
Base 89 2131 Beam tubo Message 5(C) 0.241 0.057 Comb3 0.006 Comb4
B4 No Comb
Base 90 2132 Beam tubo Message 5(T) 0.227 0.052 Comb3 0.006 Comb4
No Comb
Story1 D1 A0A Brace tubo Message 4(C) 0.064 0.057 Comb3 0.004 Comb5
No Comb
Story1 D1 Brace tubo Message 3(T) 0.06 0.055
No Comb
Story1 D2 A0B Brace tubo Message 5(C) 0.055 0.039 Comb3 0.003 Comb3
No Comb
Story1 D3 A0C Brace tubo Message 5(C) 0.046 0.029 Comb3 0.003 Comb3
No Comb
Story1 D4 A0D Brace tubo Message 4(C) 0.042 0.031 Comb3 0.003 Comb4
No Comb
Story1 D4 Brace tubo Message 3(T) 0.042 0.028
No Comb
Story1 D5 A0E Brace tubo Message 3(C) 0.069 0.028 Comb3 0.003 Comb3
No Comb
Story1 D6 A0F Brace tubo Message 3(T) 0.06 0.025 Comb3 0.003 Comb3
No Comb
Story1 D7 A10 Brace tubo Message 5(C) 0.071 0.029 Comb3 0.003 Comb3
No Comb
Story1 D7 Brace tubo Message 3(T) 0.045 0.024
No Comb
Story1 D8 A11 Brace tubo Message 3(C) 0.044 0.026 Comb3 0.003 Comb3
No Comb
Story1 D8 Brace tubo Message 5(T) 0.044 0.03
No Comb
Story1 D9 A12 Brace tubo Message 5(C) 0.062 0.027 Comb3 0.003 Comb5
D1 No Comb
Story1 0 A13 Brace tubo Message 3(T) 0.052 0.03 Comb3 0.003 Comb5
D1 No Comb
Story1 1 A14 Brace tubo Message 3(C) 0.071 0.024 Comb3 0.003 Comb3
D1 No Comb
Story1 2 A15 Brace tubo Message 3(T) 0.056 0.027 Comb3 0.003 Comb5
D1 No Comb
Story1 3 A16 Brace tubo Message 3(C) 0.088 0.031 Comb3 0.003 Comb3
D1 No Comb
Story1 4 A17 Brace tubo Message 5(C) 0.064 0.056 Comb3 0.004 Comb5
D1 No Comb
Story1 4 Brace tubo Message 3(T) 0.083 0.056
D1 No Comb
Story1 5 A18 Brace tubo Message 5(C) 0.063 0.056 Comb3 0.004 Comb5
D1 No Comb
Story1 5 Brace tubo Message 3(T) 0.074 0.055
D1 No Comb
Story1 6 A19 Brace tubo Message 3(C) 0.093 0.03 Comb3 0.003 Comb3
D1 No Comb
Story1 7 A1A Brace tubo Message 3(T) 0.06 0.027 Comb3 0.003 Comb5
D1 No Comb
Story1 8 A1B Brace tubo Message 5(C) 0.069 0.028 Comb3 0.003 Comb5
D1 No Comb
Story1 9 A1C Brace tubo Message 5(T) 0.049 0.033 Comb3 0.003 Comb3
D2 No Comb
Story1 0 A1D Brace tubo Message 5(C) 0.071 0.031 Comb3 0.003 Comb3

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


62

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D2 No Comb
Story1 0 Brace tubo Message 3(T) 0.038 0.025
D2 No Comb
Story1 1 A1E Brace tubo Message 3(T) 0.059 0.027 Comb3 0.003 Comb3
D2 No Comb
Story1 2 A1F Brace tubo Message 3(C) 0.065 0.029 Comb3 0.003 Comb3
D2 No Comb
Story1 3 A20 Brace tubo Message 4(C) 0.044 0.032 Comb3 0.003 Comb4
D2 No Comb
Story1 3 Brace tubo Message 3(T) 0.041 0.029
D2 No Comb
Story1 4 A21 Brace tubo Message 5(C) 0.043 0.03 Comb3 0.003 Comb3
D2 No Comb
Story1 5 A22 Brace tubo Message 5(C) 0.058 0.04 Comb3 0.003 Comb3
D2 No Comb
Story1 6 A23 Brace tubo Message 4(C) 0.064 0.057 Comb3 0.004 Comb5
D2 No Comb
Story1 6 Brace tubo Message 3(T) 0.06 0.055
D2 No Comb
Story1 7 A24 Brace tubo Message 4(C) 0.068 0.049 Comb3 0.004 Comb3
D2 No Comb
Story1 8 A25 Brace tubo Message 5(T) 0.033 0.013 Comb3 0.002 Comb3
D2 No Comb
Story1 9 A26 Brace tubo Message 5(C) 0.056 0.007 Comb3 0.001 Comb5
D3 No Comb
Story1 0 A27 Brace tubo Message 5(T) 0.037 0.007 Comb3 0.002 Comb5
D3 No Comb
Story1 1 A28 Brace tubo Message 5(C) 0.08 0.008 Comb3 0.002 Comb5
D3 No Comb
Story1 2 A29 Brace tubo Message 5(T) 0.045 0.006 Comb3 0.001 Comb4
D3 No Comb
Story1 3 A2A Brace tubo Message 3(C) 0.03 0.011 Comb3 0.001 Comb5
D3 No Comb
Story1 4 A2B Brace tubo Message 5(T) 0.035 0.008 Comb3 0.002 Comb5
D3 No Comb
Story1 5 A2C Brace tubo Message 4(T) 0.052 0.004 Comb3 0.001 Comb5
D3 No Comb
Story1 6 A2D Brace tubo Message 3(C) 0.093 0.013 Comb3 0.002 Comb5
D3 No Comb
Story1 7 A2E Brace tubo Message 3(T) 0.066 0.009 Comb3 0.002 Comb4
D3 No Comb
Story1 8 A2F Brace tubo Message 3(C) 0.216 0.014 Comb3 0.002 Comb5
D3 No Comb
Story1 9 A30 Brace tubo Message 3(T) 0.061 0.014 Comb3 0.002 Comb5
D4 No Comb
Story1 0 A31 Brace tubo Message 3(C) 0.127 0.038 Comb3 0.003 Comb3
D4 No Comb
Story1 1 A32 Brace tubo Message 5(C) 0.055 0.04 Comb3 0.003 Comb4
D4 No Comb
Story1 1 Brace tubo Message 3(T) 0.045 0.036
D4 No Comb
Story1 2 A33 Brace tubo Message 4(C) 0.037 0.008 Comb3 0.002 Comb4
D4 No Comb
Story1 3 A34 Brace tubo Message 3(C) 0.026 0.014 Comb3 0.002 Comb3
D4 No Comb
Story1 4 A35 Brace tubo Message 3(T) 0.022 0.016 Comb3 0.002 Comb4
D4 No Comb
Story1 5 A36 Brace tubo Message 3(C) 0.047 0.012 Comb3 0.002 Comb5
D4 No Comb
Story1 6 A37 Brace tubo Message 3(T) 0.026 0.019 Comb3 0.002 Comb4
D4 No Comb
Story1 7 A38 Brace tubo Message 5(C) 0.237 0.015 Comb3 0.002 Comb3
D4 No Comb
Story1 8 A39 Brace tubo Message 5(C) 0.103 0.02 Comb3 0.002 Comb4

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


63

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D4 No Comb
Story1 9 A3A Brace tubo Message 5(C) 0.101 0.02 Comb3 0.002 Comb4
D5 No Comb
Story1 0 A3B Brace tubo Message 5(C) 0.059 0.009 Comb3 0.002 Comb3
D5 No Comb
Story1 1 A3C Brace tubo Message 3(C) 0.067 0.023 Comb3 0.002 Comb5
D5 No Comb
Story1 2 A3D Brace tubo Message 5(C) 0.021 0.009 Comb3 0.002 Comb3
D5 No Comb
Story1 2 Brace tubo Message 3(T) 0.019 0.01
D5 No Comb
Story1 3 A3E Brace tubo Message 3(C) 0.065 0.016 Comb3 0.002 Comb5
D5 No Comb
Story1 4 A3F Brace tubo Message 3(T) 0.079 0.036 Comb3 0.003 Comb5
D5 No Comb
Story1 5 A40 Brace tubo Message 3(C) 0.131 0.035 Comb3 0.003 Comb3
D5 No Comb
Story1 6 A41 Brace tubo Message 3(T) 0.074 0.014 Comb3 0.002 Comb2
D5 No Comb
Story1 7 A42 Brace tubo Message 3(C) 0.112 0.018 Comb3 0.002 Comb5
D5 No Comb
Story1 8 A43 Brace tubo Message 4(T) 0.056 0.001 Comb3 0.002 Comb5
D5 No Comb
Story1 9 A44 Brace tubo Message 3(C) 0.017 0.01 Comb3 0.001 Comb5
D5 No Comb
Story1 9 Brace tubo Message 5(T) 0.022 0.006
D6 No Comb
Story1 0 A46 Brace tubo Message 3(C) 0.012 0.01 Comb3 0.001 Comb5
D6 No Comb
Story1 0 Brace tubo Message 4(T) 0.013 0.004
D6 No Comb
Story1 1 A47 Brace tubo Message 5(T) 0.035 0.007 Comb3 0.002 Comb4
D6 No Comb
Story1 2 A48 Brace tubo Message 5(C) 0.061 0.008 Comb3 0.002 Comb5
D6 No Comb
Story1 3 A49 Brace tubo Message 5(T) 0.029 0.007 Comb3 0.002 Comb5
D6 No Comb
Story1 4 A4A Brace tubo Message 5(C) 0.041 0.008 Comb3 0.002 Comb5
D6 No Comb
Story1 5 A4B Brace tubo Message 4(T) 0.03 0.013 Comb3 0.002 Comb12
D6 No Comb
Story1 6 A4C Brace tubo Message 4(C) 0.059 0.049 Comb3 0.004 Comb3
D6 No Comb
Story1 7 A4D Brace tubo Message 3(T) 0.081 0.035 Comb3 0.003 Comb5
D6 No Comb
Story1 8 A4E Brace tubo Message 3(C) 0.088 0.02 Comb3 0.002 Comb5
D6 No Comb
Story1 9 A4F Brace tubo Message 5(C) 0.035 0.009 Comb3 0.002 Comb3
D6 No Comb
Story1 9 Brace tubo Message 12(T) 0.007 0.005
D7 No Comb
Story1 0 A50 Brace tubo Message 5(C) 0.108 0.019 Comb3 0.002 Comb4
D7 No Comb
Story1 1 A51 Brace tubo Message 5(C) 0.081 0.015 Comb3 0.002 Comb4
D7 No Comb
Story1 2 A52 Brace tubo Message 5(C) 0.226 0.013 Comb3 0.002 Comb3
D7 No Comb
Story1 3 A53 Brace tubo Message 3(T) 0.024 0.016 Comb3 0.002 Comb4
D7 No Comb
Story1 4 A54 Brace tubo Message 3(C) 0.046 0.012 Comb3 0.002 Comb5
D7 No Comb
Story1 5 A55 Brace tubo Message 3(T) 0.019 0.014 Comb3 0.002 Comb4
D7 No Comb
Story1 6 A56 Brace tubo Message 3(C) 0.027 0.015 Comb3 0.002 Comb3

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


64

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D7 No Comb
Story1 7 A57 Brace tubo Message 4(C) 0.045 0.008 Comb3 0.002 Comb4
D7 No Comb
Story1 8 A58 Brace tubo Message 4(C) 0.063 0.04 Comb3 0.003 Comb4
D7 No Comb
Story1 9 A59 Brace tubo Message 4(C) 0.06 0.038 Comb3 0.003 Comb4
D8 No Comb
Story1 0 A5A Brace tubo Message 4(T) 0.034 0.01 Comb3 0.002 Comb4
D8 No Comb
Story1 1 A5B Brace tubo Message 4(C) 0.062 0.014 Comb3 0.002 Comb3
D8 No Comb
Story1 2 A5C Brace tubo Message 4(T) 0.035 0.006 Comb3 0.002 Comb4
D8 No Comb
Story1 3 A5D Brace tubo Message 4(C) 0.229 0.011 Comb3 0.002 Comb3
D8 No Comb
Story1 4 A5E Brace tubo Message 4(T) 0.078 0.007 Comb3 0.002 Comb4
D8 No Comb
Story1 5 A5F Brace tubo Message 12(C) 0.017 0.013 Comb3 0.002 Comb4
D8 No Comb
Story1 5 Brace tubo Message 4(T) 0.034 0.023
D8 No Comb
Story1 6 A60 Brace tubo Message 5(T) 0.128 0.029 Comb3 0.002 Comb4
D8 No Comb
Story1 7 A61 Brace tubo Message 4(T) 0.249 0.021 Comb3 0.002 Comb4
D8 No Comb
Story1 8 A62 Brace tubo Message 3(C) 0.207 0.003 Comb3 0.002 Comb5
D8 No Comb
Story1 9 A63 Brace tubo Message 3(T) 0.087 0.011 Comb3 0.002 Comb4
D9 No Comb
Story1 0 A64 Brace tubo Message 3(C) 0.247 0.017 Comb3 0.002 Comb5
D9 No Comb
Story1 1 A65 Brace tubo Message 3(T) 0.058 0.009 Comb3 0.002 Comb5
D9 No Comb
Story1 2 A66 Brace tubo Message 3(C) 0.235 0.011 Comb3 0.001 Comb5
D9 No Comb
Story1 3 A67 Brace tubo Message 4(C) 0.075 0.055 Comb3 0.004 Comb4
D9 No Comb
Story1 4 A68 Brace tubo Message 4(C) 0.103 0.019 Comb3 0.002 Comb4
D9 No Comb
Story1 5 A69 Brace tubo Message 4(T) 0.029 0.008 Comb3 0.002 Comb4
D9 No Comb
Story1 6 A6A Brace tubo Message 4(C) 0.029 0.007 Comb3 0.002 Comb4
D9 No Comb
Story1 7 A6B Brace tubo Message 4(T) 0.026 0.002 Comb3 0.001 Comb4
D9 No Comb
Story1 8 A6C Brace tubo Message 3(C) 0.023 0.015 Comb3 0.002 Comb4
D9 No Comb
Story1 8 Brace tubo Message 4(T) 0.018 0.012
D9 No Comb
Story1 9 A6D Brace tubo Message 4(C) 0.427 0.025 Comb3 0.002 Comb4
D1 No Comb
Story1 00 A6E Brace tubo Message 5(C) 1.532 0.239 Comb3 0.002 Comb4
D1 No Comb
Story1 01 A6F Brace tubo Message 5(T) 0.13 0.033 Comb3 0.002 Comb4
D1 No Comb
Story1 02 A70 Brace tubo Message 4(C) 0.354 0.017 Comb3 0.002 Comb5
D1 No Comb
Story1 03 A71 Brace tubo Message 5(T) 0.054 0.017 Comb3 0.002 Comb5
D1 No Comb
Story1 04 A72 Brace tubo Message 5(C) 0.069 0.004 Comb3 0.001 Comb3
D1 No Comb
Story1 05 A73 Brace tubo Message 12(C) 0.008 0.006 Comb3 0.002 Comb4
D1 No Comb
Story1 05 Brace tubo Message 5(T) 0.029 0.007

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


65

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D1 No Comb
Story1 06 A74 Brace tubo Message 5(C) 0.049 0.027 Comb3 0.002 Comb3
D1 No Comb
Story1 06 Brace tubo Message 12(T) 0.034 0.019
D1 No Comb
Story1 07 A75 Brace tubo Message 3(T) 0.093 0.011 Comb3 0.002 Comb3
D1 No Comb
Story1 08 A76 Brace tubo Message 3(C) 0.137 0.03 Comb3 0.003 Comb3
D1 No Comb
Story1 09 A77 Brace tubo Message 3(T) 0.085 0.043 Comb3 0.004 Comb5
D1 No Comb
Story1 10 A78 Brace tubo Message 3(C) 0.1 0.04 Comb3 0.003 Comb3
D1 No Comb
Story1 11 A79 Brace tubo Message 3(T) 0.064 0.042 Comb3 0.004 Comb5
D1 No Comb
Story1 12 A7A Brace tubo Message 3(C) 0.069 0.042 Comb3 0.004 Comb3
D1 No Comb
Story1 13 A7B Brace tubo Message 5(C) 0.05 0.047 Comb3 0.004 Comb5
D1 No Comb
Story1 13 Brace tubo Message 3(T) 0.049 0.043
D1 No Comb
Story1 14 A7C Brace tubo Message 5(T) 0.052 0.047 Comb3 0.004 Comb5
D1 No Comb
Story1 15 A7D Brace tubo Message 5(C) 0.071 0.046 Comb3 0.004 Comb5
D1 No Comb
Story1 16 A7E Brace tubo Message 5(T) 0.064 0.047 Comb3 0.004 Comb5
D1 No Comb
Story1 17 A7F Brace tubo Message 5(C) 0.094 0.044 Comb3 0.003 Comb3
D1 No Comb
Story1 18 A80 Brace tubo Message 3(T) 0.076 0.04 Comb3 0.003 Comb5
D1 No Comb
Story1 19 A81 Brace tubo Message 3(C) 0.127 0.036 Comb3 0.003 Comb3
D1 No Comb
Story1 20 A82 Brace tubo Message 3(T) 0.098 0.04 Comb3 0.003 Comb4
D1 No Comb
Story1 21 A83 Brace tubo Message 3(C) 0.29 0.022 Comb3 0.003 Comb3
D1 No Comb
Story1 22 A84 Brace tubo Message 3(T) 0.124 0.025 Comb3 0.002 Comb3
D1 No Comb
Story1 23 A85 Brace tubo Message 3(T) 0.048 0.014 Comb3 0.002 Comb3
D1 No Comb
Story1 24 A86 Brace tubo Message 3(C) 0.036 0.022 Comb3 0.002 Comb5
D1 No Comb
Story1 24 Brace tubo Message 5(T) 0.025 0.017
D1 No Comb
Story1 25 A87 Brace tubo Message 4(C) 0.253 0.012 Comb3 0.002 Comb5
D1 No Comb
Story1 26 A88 Brace tubo Message 5(T) 0.105 0.033 Comb3 0.002 Comb5
D1 No Comb
Story1 27 A89 Brace tubo Message 5(C) 1.204 0.043 Comb3 0.001 Comb3
D1 No Comb
Story1 28 A8A Brace tubo Message 4(C) 0.39 0.025 Comb3 0.002 Comb4
D1 No Comb
Story1 29 A8B Brace tubo Message 3(C) 0.021 0.012 Comb3 0.001 Comb4
D1 No Comb
Story1 29 Brace tubo Message 5(T) 0.011 0.009
D1 No Comb
Story1 30 A8C Brace tubo Message 4(T) 0.025 0.001 Comb3 0.001 Comb4
D1 No Comb
Story1 31 A8D Brace tubo Message 4(C) 0.036 0.006 Comb3 0.002 Comb4
D1 No Comb
Story1 32 A8E Brace tubo Message 4(T) 0.033 0.008 Comb3 0.002 Comb4
D1 No Comb
Story1 33 A8F Brace tubo Message 4(C) 0.247 0.013 Comb3 0.002 Comb4

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


66

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D1 No Comb
Story1 34 A90 Brace tubo Message 4(C) 0.083 0.052 Comb3 0.004 Comb4
D1 No Comb
Story1 35 A91 Brace tubo Message 3(C) 0.386 0.026 Comb3 0.002 Comb5
D1 No Comb
Story1 36 A92 Brace tubo Message 3(T) 0.097 0.007 Comb3 0.001 Comb3
D1 No Comb
Story1 37 A93 Brace tubo Message 3(C) 0.262 0.024 Comb3 0.002 Comb5
D1 No Comb
Story1 38 A94 Brace tubo Message 4(T) 0.25 0.019 Comb3 0.002 Comb4
D1 No Comb
Story1 39 A95 Brace tubo Message 5(T) 0.11 0.028 Comb3 0.002 Comb5
D1 No Comb
Story1 40 A96 Brace tubo Message 4(T) 0.034 0.019 Comb3 0.002 Comb4
D1 No Comb
Story1 41 A97 Brace tubo Message 4(T) 0.064 0.006 Comb3 0.002 Comb4
D1 No Comb
Story1 42 A98 Brace tubo Message 4(C) 0.098 0.011 Comb3 0.002 Comb3
D1 No Comb
Story1 43 A99 Brace tubo Message 4(T) 0.028 0.007 Comb3 0.002 Comb4
D1 No Comb
Story1 44 A9A Brace tubo Message 4(C) 0.045 0.015 Comb3 0.002 Comb3
D1 No Comb
Story1 45 A9B Brace tubo Message 4(T) 0.036 0.009 Comb3 0.002 Comb4
D1 No Comb
Story1 46 A9C Brace tubo Message 6(C) 0.018 0.011 Comb3 0.003 Comb4
D1 No Comb
Story1 46 Brace tubo Message 4(T) 0.05 0.037
D1 No Comb
Story1 47 A9F Brace tubo Message 4(C) 0.064 0.056 Comb3 0.004 Comb4
D1 No Comb
Story1 47 Brace tubo Message 3(T) 0.059 0.054
D1 No Comb
Story1 48 AA0 Brace tubo Message 3(C) 0.041 0.035 Comb3 0.003 Comb4
D1 No Comb
Story1 48 Brace tubo Message 4(T) 0.06 0.041
D1 No Comb
Story1 49 AA1 Brace tubo Message 4(C) 0.08 0.029 Comb3 0.003 Comb3
D1 No Comb
Story1 50 AA2 Brace tubo Message 4(T) 0.057 0.037 Comb3 0.003 Comb3
D1 No Comb
Story1 51 AA3 Brace tubo Message 4(C) 0.081 0.028 Comb3 0.003 Comb3
D1 No Comb
Story1 52 AA4 Brace tubo Message 6(C) 0.02 0.012 Comb3 0.002 Comb3
D1 No Comb
Story1 52 Brace tubo Message 3(T) 0.048 0.029
D1 No Comb
Story1 53 AA5 Brace tubo Message 4(T) 0.069 0.029 Comb3 0.002 Comb4
D1 No Comb
Story1 54 AA6 Brace tubo Message 5(C) 1.172 0.035 Comb3 0.002 Comb4
D1 No Comb
Story1 55 AA7 Brace tubo Message 5(T) 0.236 0.024 Comb3 0.002 Comb4
D1 No Comb
Story1 56 AA8 Brace tubo Message 4(C) 0.489 0.026 Comb3 0.002 Comb4
D1 No Comb
Story1 57 AA9 Brace tubo Message 5(T) 0.084 0.011 Comb3 0.002 Comb5
D1 No Comb
Story1 58 AAA Brace tubo Message 3(C) 0.313 0.014 Comb3 0.002 Comb4
D1 No Comb
Story1 59 AAB Brace tubo Message 5(T) 0.057 0.006 Comb3 0.002 Comb4
D1 No Comb
Story1 60 AAC Brace tubo Message 3(C) 0.244 0.011 Comb3 0.002 Comb3
D1 No Comb
Story1 61 AAD Brace tubo Message 5(T) 0.047 0.01 Comb3 0.002 Comb3

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


67

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D1 No Comb
Story1 62 AAE Brace tubo Message 3(C) 0.093 0.011 Comb3 0.002 Comb5
D1 No Comb
Story1 63 AAF Brace tubo Message 5(T) 0.038 0.014 Comb3 0.002 Comb3
D1 No Comb
Story1 64 AB0 Brace tubo Message 3(C) 0.066 0.019 Comb3 0.002 Comb3
D1 No Comb
Story1 65 AB1 Brace tubo Message 5(T) 0.029 0.016 Comb3 0.002 Comb3
D1 No Comb
Story1 66 AB2 Brace tubo Message 3(C) 0.042 0.019 Comb3 0.002 Comb3
D1 No Comb
Story1 67 AB3 Brace tubo Message 3(C) 0.02 0.02 Comb3 0.002 Comb3
D1 No Comb
Story1 67 Brace tubo Message 5(T) 0.02 0.018
D1 No Comb
Story1 68 AB4 Brace tubo Message 3(C) 0.022 0.02 Comb3 0.002 Comb3
D1 No Comb
Story1 69 AB5 Brace tubo Message 3(C) 0.039 0.02 Comb3 0.002 Comb3
D1 No Comb
Story1 70 AB6 Brace tubo Message 3(T) 0.027 0.019 Comb3 0.002 Comb3
D1 No Comb
Story1 71 AB7 Brace tubo Message 3(C) 0.06 0.018 Comb3 0.002 Comb3
D1 No Comb
Story1 72 AB8 Brace tubo Message 5(T) 0.035 0.014 Comb3 0.002 Comb3
D1 No Comb
Story1 73 AB9 Brace tubo Message 3(C) 0.087 0.017 Comb3 0.002 Comb5
D1 No Comb
Story1 74 ABA Brace tubo Message 5(T) 0.044 0.012 Comb3 0.002 Comb3
D1 No Comb
Story1 75 ABB Brace tubo Message 3(C) 0.231 0.007 Comb3 0.002 Comb4
D1 No Comb
Story1 76 ABC Brace tubo Message 5(T) 0.054 0.007 Comb3 0.002 Comb3
D1 No Comb
Story1 77 ABD Brace tubo Message 3(C) 0.344 0.013 Comb3 0.002 Comb5
D1 No Comb
Story1 78 ABE Brace tubo Message 5(T) 0.075 0.007 Comb3 0.002 Comb5
D1 No Comb
Story1 79 ABF Brace tubo Message 4(C) 0.474 0.026 Comb3 0.002 Comb4
D1 No Comb
Story1 80 AC0 Brace tubo Message 5(T) 0.225 0.022 Comb3 0.002 Comb5
D1 No Comb
Story1 81 AC1 Brace tubo Message 5(C) 1.099 0.037 Comb3 0.001 Comb5
D1 No Comb
Story1 82 AC2 Brace tubo Message 4(T) 0.082 0.037 Comb3 0.003 Comb4
D1 No Comb
Story1 83 AC3 Brace tubo Message 4(C) 0.043 0.026 Comb3 0.002 Comb3
D1 No Comb
Story1 83 Brace tubo Message 3(T) 0.041 0.028
D1 No Comb
Story1 84 AC4 Brace tubo Message 4(C) 0.068 0.028 Comb3 0.003 Comb3
D1 No Comb
Story1 85 AC5 Brace tubo Message 6(C) 0.02 0.01 Comb3 0.003 Comb4
D1 No Comb
Story1 85 Brace tubo Message 4(T) 0.05 0.036
D1 No Comb
Story1 86 AC6 Brace tubo Message 4(C) 0.068 0.028 Comb3 0.003 Comb3
D1 No Comb
Story1 87 AC7 Brace tubo Message 3(C) 0.053 0.038 Comb3 0.003 Comb4
D1 No Comb
Story1 87 Brace tubo Message 4(T) 0.057 0.044
D1 No Comb
Story1 88 AC8 Brace tubo Message 4(C) 0.065 0.058 Comb3 0.004 Comb4
D1 No Comb
Story1 88 Brace tubo Message 3(T) 0.061 0.056

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


68

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D1 No Comb
Story1 89 AC9 Brace tubo Message 3(C) 0.242 0.028 Comb3 0.002 Comb2
D1 No Comb
Story1 90 ACA Brace tubo Message 5(T) 0.223 0.018 Comb3 0.002 Comb3
D1 No Comb
Story1 91 ACB Brace tubo Message 5(T) 0.077 0.026 Comb3 0.002 Comb4
D1 No Comb
Story1 92 ACC Brace tubo Message 5(C) 0.05 0.013 Comb3 0.002 Comb5
D1 No Comb
Story1 93 ACD Brace tubo Message 5(T) 0.058 0.015 Comb3 0.002 Comb4
D1 No Comb
Story1 94 ACE Brace tubo Message 5(C) 0.056 0.004 Comb3 0.001 Comb3
D1 No Comb
Story1 95 ACF Brace tubo Message 5(T) 0.04 0.006 Comb3 0.001 Comb4
D1 No Comb
Story1 96 AD0 Brace tubo Message 5(C) 0.054 0.005 Comb3 0.002 Comb3
D1 No Comb
Story1 97 AD1 Brace tubo Message 3(T) 0.048 0.01 Comb3 0.002 Comb4
D1 No Comb
Story1 98 AD2 Brace tubo Message 3(C) 0.067 0.011 Comb3 0.002 Comb4
D1 No Comb
Story1 99 AD3 Brace tubo Message 3(T) 0.046 0.012 Comb3 0.002 Comb4
D2 No Comb
Story1 00 AD4 Brace tubo Message 3(C) 0.058 0.014 Comb3 0.002 Comb4
D2 No Comb
Story1 01 AD5 Brace tubo Message 3(T) 0.033 0.014 Comb3 0.002 Comb4
D2 No Comb
Story1 02 AD6 Brace tubo Message 3(C) 0.037 0.015 Comb3 0.002 Comb4
D2 No Comb
Story1 03 AD7 Brace tubo Message 5(C) 0.016 0.009 Comb3 0.002 Comb3
D2 No Comb
Story1 03 Brace tubo Message 3(T) 0.019 0.015
D2 No Comb
Story1 04 AD8 Brace tubo Message 3(T) 0.018 0.015 Comb3 0.002 Comb3
D2 No Comb
Story1 05 AD9 Brace tubo Message 3(C) 0.036 0.015 Comb3 0.002 Comb3
D2 No Comb
Story1 06 ADA Brace tubo Message 3(T) 0.031 0.014 Comb3 0.002 Comb3
D2 No Comb
Story1 07 ADB Brace tubo Message 3(C) 0.059 0.014 Comb3 0.002 Comb4
D2 No Comb
Story1 08 ADC Brace tubo Message 3(T) 0.045 0.013 Comb3 0.002 Comb4
D2 No Comb
Story1 09 ADD Brace tubo Message 3(C) 0.077 0.012 Comb3 0.002 Comb4
D2 No Comb
Story1 10 ADE Brace tubo Message 3(T) 0.056 0.01 Comb3 0.002 Comb4
D2 No Comb
Story1 11 ADF Brace tubo Message 3(C) 0.08 0.008 Comb3 0.001 Comb3
D2 No Comb
Story1 12 AE0 Brace tubo Message 3(T) 0.056 0.011 Comb3 0.002 Comb4
D2 No Comb
Story1 13 AE1 Brace tubo Message 5(C) 0.044 0.005 Comb3 0.001 Comb3
D2 No Comb
Story1 14 AE2 Brace tubo Message 5(T) 0.048 0.016 Comb3 0.002 Comb4
D2 No Comb
Story1 15 AE3 Brace tubo Message 5(C) 0.024 0.012 Comb3 0.002 Comb3
D2 No Comb
Story1 15 Brace tubo Message 3(T) 0.017 0.014
D2 No Comb
Story1 16 AE4 Brace tubo Message 5(T) 0.063 0.026 Comb3 0.002 Comb4
D2 No Comb
Story1 17 AE5 Brace tubo Message 5(T) 0.222 0.016 Comb3 0.002 Comb5
D2 No Comb
Story1 18 AE6 Brace tubo Message 3(C) 0.246 0.026 Comb3 0.002 Comb5

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


69

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D2 No Comb
Story1 19 AE7 Brace tubo Message 5(C) 0.463 0.032 Comb3 0.003 Comb5
D2 No Comb
Story1 20 AE8 Brace tubo Message 3(T) 0.076 0.021 Comb3 0.002 Comb5
D2 No Comb
Story1 21 AE9 Brace tubo Message 3(T) 0.057 0.029 Comb3 0.002 Comb3
D2 No Comb
Story1 22 AEA Brace tubo Message 5(C) 0.217 0.014 Comb3 0.002 Comb3
D2 No Comb
Story1 23 AEB Brace tubo Message 3(T) 0.057 0.014 Comb3 0.002 Comb4
D2 No Comb
Story1 24 AEC Brace tubo Message 3(C) 0.234 0.009 Comb3 0.001 Comb3
D2 No Comb
Story1 25 AED Brace tubo Message 3(T) 0.048 0.008 Comb3 0.001 Comb4
D2 No Comb
Story1 26 AEE Brace tubo Message 3(C) 0.098 0.011 Comb3 0.002 Comb3
D2 No Comb
Story1 27 AEF Brace tubo Message 5(T) 0.041 0.007 Comb3 0.002 Comb5
D2 No Comb
Story1 28 AF0 Brace tubo Message 3(C) 0.075 0.013 Comb3 0.002 Comb4
D2 No Comb
Story1 29 AF1 Brace tubo Message 5(T) 0.033 0.008 Comb3 0.002 Comb5
D2 No Comb
Story1 30 AF2 Brace tubo Message 3(C) 0.058 0.014 Comb3 0.002 Comb5
D2 No Comb
Story1 31 AF3 Brace tubo Message 5(T) 0.026 0.011 Comb3 0.002 Comb3
D2 No Comb
Story1 32 AF4 Brace tubo Message 3(C) 0.038 0.015 Comb3 0.002 Comb5
D2 No Comb
Story1 33 AF5 Brace tubo Message 12(C) 0.011 0.008 Comb3 0.002 Comb3
D2 No Comb
Story1 33 Brace tubo Message 5(T) 0.016 0.012
D2 No Comb
Story1 34 AF6 Brace tubo Message 3(C) 0.019 0.015 Comb3 0.002 Comb5
D2 No Comb
Story1 35 AF7 Brace tubo Message 3(C) 0.034 0.015 Comb3 0.002 Comb5
D2 No Comb
Story1 36 AF8 Brace tubo Message 5(T) 0.023 0.01 Comb3 0.002 Comb5
D2 No Comb
Story1 37 AFA Brace tubo Message 3(C) 0.054 0.014 Comb3 0.002 Comb5
D2 No Comb
Story1 38 AFB Brace tubo Message 5(T) 0.03 0.007 Comb3 0.002 Comb3
D2 No Comb
Story1 39 AFC Brace tubo Message 3(C) 0.074 0.012 Comb3 0.002 Comb4
D2 No Comb
Story1 40 AFD Brace tubo Message 5(T) 0.037 0.006 Comb3 0.002 Comb5
D2 No Comb
Story1 41 AFE Brace tubo Message 3(C) 0.092 0.01 Comb3 0.002 Comb3
D2 No Comb
Story1 42 AFF Brace tubo Message 5(T) 0.046 0.003 Comb3 0.001 Comb4
D2 No Comb
Story1 43 B00 Brace tubo Message 5(C) 0.233 0.006 Comb3 0.001 Comb3
D2 No Comb
Story1 44 B01 Brace tubo Message 3(T) 0.06 0.013 Comb3 0.002 Comb4
D2 No Comb
Story1 45 B02 Brace tubo Message 3(C) 0.228 0.018 Comb3 0.002 Comb3
D2 No Comb
Story1 46 B03 Brace tubo Message 3(T) 0.063 0.029 Comb3 0.002 Comb3
D2 No Comb
Story1 47 B04 Brace tubo Message 3(T) 0.075 0.022 Comb3 0.002 Comb5
D2 No Comb
Story1 48 B05 Brace tubo Message 5(C) 0.449 0.032 Comb3 0.003 Comb5
D2 No Comb
Story1 49 B06 Brace tubo Message 5(T) 0.165 0.058 Comb3 0.004 Comb5

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


70

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D2 No Comb
Story1 50 B07 Brace tubo Message 3(C) 0.88 0.057 Comb3 0.002 Comb4
D2 No Comb
Story1 51 B08 Brace tubo Message 5(T) 0.243 0.026 Comb3 0.002 Comb4
D2 No Comb
Story1 52 B09 Brace tubo Message 5(C) 0.354 0.019 Comb3 0.002 Comb4
D2 No Comb
Story1 53 B0A Brace tubo Message 5(T) 0.085 0.012 Comb3 0.002 Comb4
D2 No Comb
Story1 54 B0B Brace tubo Message 5(C) 0.106 0.006 Comb3 0.001 Comb3
D2 No Comb
Story1 55 B0C Brace tubo Message 5(T) 0.053 0.004 Comb3 0.001 Comb4
D2 No Comb
Story1 56 B0D Brace tubo Message 3(C) 0.077 0.011 Comb3 0.002 Comb3
D2 No Comb
Story1 57 B0E Brace tubo Message 3(T) 0.044 0.012 Comb3 0.002 Comb4
D2 No Comb
Story1 58 B0F Brace tubo Message 3(C) 0.066 0.013 Comb3 0.002 Comb12
D2 No Comb
Story1 59 B10 Brace tubo Message 3(T) 0.038 0.014 Comb3 0.002 Comb5
D2 No Comb
Story1 60 B11 Brace tubo Message 3(C) 0.051 0.015 Comb3 0.002 Comb4
D2 No Comb
Story1 61 B12 Brace tubo Message 3(T) 0.029 0.015 Comb3 0.002 Comb5
D2 No Comb
Story1 62 B13 Brace tubo Message 3(C) 0.034 0.016 Comb3 0.002 Comb5
D2 No Comb
Story1 63 B14 Brace tubo Message 5(C) 0.017 0.012 Comb3 0.002 Comb5
D2 No Comb
Story1 63 Brace tubo Message 3(T) 0.018 0.016
D2 No Comb
Story1 64 B15 Brace tubo Message 3(T) 0.018 0.016 Comb3 0.002 Comb5
D2 No Comb
Story1 65 B16 Brace tubo Message 3(C) 0.036 0.016 Comb3 0.002 Comb5
D2 No Comb
Story1 66 B17 Brace tubo Message 3(T) 0.03 0.015 Comb3 0.002 Comb5
D2 No Comb
Story1 67 B18 Brace tubo Message 3(C) 0.056 0.015 Comb3 0.002 Comb4
D2 No Comb
Story1 68 B19 Brace tubo Message 3(T) 0.04 0.014 Comb3 0.002 Comb4
D2 No Comb
Story1 69 B1A Brace tubo Message 3(C) 0.071 0.013 Comb3 0.002 Comb3
D2 No Comb
Story1 70 B1B Brace tubo Message 3(T) 0.049 0.012 Comb3 0.002 Comb4
D2 No Comb
Story1 71 B1C Brace tubo Message 3(C) 0.085 0.011 Comb3 0.002 Comb3
D2 No Comb
Story1 72 B1D Brace tubo Message 3(T) 0.055 0.009 Comb3 0.001 Comb4
D2 No Comb
Story1 73 B1E Brace tubo Message 5(C) 0.105 0.005 Comb3 0.001 Comb3
D2 No Comb
Story1 74 B1F Brace tubo Message 3(T) 0.079 0.016 Comb3 0.002 Comb4
D2 No Comb
Story1 75 B20 Brace tubo Message 5(C) 0.334 0.017 Comb3 0.002 Comb3
D2 No Comb
Story1 76 B21 Brace tubo Message 5(T) 0.231 0.027 Comb3 0.002 Comb3
D2 No Comb
Story1 77 B22 Brace tubo Message 5(C) 0.862 0.019 Comb3 0.001 Comb5
D2 No Comb
Story1 78 B23 Brace tubo Message 5(T) 0.167 0.061 Comb3 0.004 Comb3
D2 No Comb
Story1 79 B24 Brace tubo Message 5(T) 0.148 0.062 Comb3 0.004 Comb4
D2 No Comb
Story1 80 B25 Brace tubo Message 5(C) 1.328 0.102 Comb3 0.002 Comb4

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


71

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D2 No Comb
Story1 81 B26 Brace tubo Message 3(T) 0.127 0.03 Comb3 0.002 Comb4
D2 No Comb
Story1 82 B27 Brace tubo Message 5(C) 0.512 0.022 Comb3 0.002 Comb3
D2 No Comb
Story1 83 B28 Brace tubo Message 3(T) 0.063 0.013 Comb3 0.002 Comb4
D2 No Comb
Story1 84 B29 Brace tubo Message 5(C) 0.299 0.006 Comb3 0.001 Comb3
D2 No Comb
Story1 85 B2A Brace tubo Message 3(T) 0.049 0.009 Comb3 0.002 Comb4
D2 No Comb
Story1 86 B2B Brace tubo Message 5(C) 0.104 0.006 Comb3 0.002 Comb3
D2 No Comb
Story1 87 B2C Brace tubo Message 3(T) 0.043 0.012 Comb3 0.002 Comb4
D2 No Comb
Story1 88 B2D Brace tubo Message 5(C) 0.076 0.008 Comb3 0.002 Comb4
D2 No Comb
Story1 89 B2E Brace tubo Message 3(T) 0.035 0.014 Comb3 0.002 Comb5
D2 No Comb
Story1 90 B2F Brace tubo Message 3(C) 0.058 0.015 Comb3 0.002 Comb5
D2 No Comb
Story1 91 B30 Brace tubo Message 3(T) 0.028 0.016 Comb3 0.002 Comb5
D2 No Comb
Story1 92 B31 Brace tubo Message 3(C) 0.04 0.016 Comb3 0.002 Comb5
D2 No Comb
Story1 93 B32 Brace tubo Message 3(T) 0.018 0.016 Comb3 0.002 Comb5
D2 No Comb
Story1 94 B33 Brace tubo Message 3(C) 0.019 0.016 Comb3 0.002 Comb5
D2 No Comb
Story1 95 B34 Brace tubo Message 3(C) 0.035 0.016 Comb3 0.002 Comb5
D2 No Comb
Story1 96 B35 Brace tubo Message 3(T) 0.026 0.016 Comb3 0.002 Comb5
D2 No Comb
Story1 97 B36 Brace tubo Message 3(C) 0.055 0.015 Comb3 0.002 Comb5
D2 No Comb
Story1 98 B37 Brace tubo Message 3(T) 0.034 0.014 Comb3 0.002 Comb5
D2 No Comb
Story1 99 B38 Brace tubo Message 3(C) 0.075 0.013 Comb3 0.002 Comb4
D3 No Comb
Story1 00 B39 Brace tubo Message 3(T) 0.041 0.012 Comb3 0.002 Comb4
D3 No Comb
Story1 01 B3A Brace tubo Message 5(C) 0.099 0.006 Comb3 0.002 Comb3
D3 No Comb
Story1 02 B3B Brace tubo Message 3(T) 0.049 0.01 Comb3 0.002 Comb4
D3 No Comb
Story1 03 B3C Brace tubo Message 5(C) 0.294 0.006 Comb3 0.001 Comb3
D3 No Comb
Story1 04 B3D Brace tubo Message 3(T) 0.067 0.012 Comb3 0.002 Comb4
D3 No Comb
Story1 05 B3E Brace tubo Message 5(C) 0.518 0.022 Comb3 0.002 Comb3
D3 No Comb
Story1 06 B3F Brace tubo Message 3(T) 0.229 0.027 Comb3 0.002 Comb5
D3 No Comb
Story1 07 B40 Brace tubo Message 5(C) 1.352 0.095 Comb3 0.002 Comb3
D3 No Comb
Story1 08 B41 Brace tubo Message 5(T) 0.157 0.067 Comb3 0.005 Comb5
D3 No Comb
Story1 09 B42 Brace tubo Message 5(C) 0.342 0.026 Comb3 0.003 Comb5
D3 No Comb
Story1 10 B43 Brace tubo Message 5(T) 0.287 0.001 Comb3 0.002 Comb5
D3 No Comb
Story1 11 B44 Brace tubo Message 3(T) 0.09 0.029 Comb3 0.002 Comb4
D3 No Comb
Story1 12 B45 Brace tubo Message 3(C) 0.023 0.015 Comb3 0.002 Comb4

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


72

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D3 No Comb
Story1 12 Brace tubo Message 5(T) 0.018 0.011
D3 No Comb
Story1 13 B46 Brace tubo Message 3(T) 0.064 0.013 Comb3 0.002 Comb3
D3 No Comb
Story1 14 B47 Brace tubo Message 3(C) 0.065 0.009 Comb3 0.001 Comb3
D3 No Comb
Story1 15 B48 Brace tubo Message 3(T) 0.048 0.009 Comb3 0.002 Comb4
D3 No Comb
Story1 16 B49 Brace tubo Message 3(C) 0.072 0.011 Comb3 0.002 Comb3
D3 No Comb
Story1 17 B4A Brace tubo Message 3(T) 0.039 0.012 Comb3 0.002 Comb5
D3 No Comb
Story1 18 B4B Brace tubo Message 3(C) 0.062 0.013 Comb3 0.002 Comb4
D3 No Comb
Story1 19 B4C Brace tubo Message 3(T) 0.031 0.014 Comb3 0.002 Comb5
D3 No Comb
Story1 20 B4D Brace tubo Message 3(C) 0.049 0.015 Comb3 0.002 Comb5
D3 No Comb
Story1 21 B4E Brace tubo Message 3(T) 0.025 0.016 Comb3 0.002 Comb5
D3 No Comb
Story1 22 B4F Brace tubo Message 3(C) 0.032 0.016 Comb3 0.002 Comb5
D3 No Comb
Story1 23 B50 Brace tubo Message 3(C) 0.018 0.016 Comb3 0.002 Comb5
D3 No Comb
Story1 24 B51 Brace tubo Message 3(T) 0.018 0.016 Comb3 0.002 Comb5
D3 No Comb
Story1 25 B52 Brace tubo Message 3(C) 0.036 0.016 Comb3 0.002 Comb5
D3 No Comb
Story1 26 B53 Brace tubo Message 3(T) 0.027 0.015 Comb3 0.002 Comb5
D3 No Comb
Story1 27 B54 Brace tubo Message 3(C) 0.053 0.015 Comb3 0.002 Comb5
D3 No Comb
Story1 28 B55 Brace tubo Message 3(T) 0.034 0.014 Comb3 0.002 Comb5
D3 No Comb
Story1 29 B57 Brace tubo Message 3(C) 0.066 0.013 Comb3 0.002 Comb4
D3 No Comb
Story1 30 B58 Brace tubo Message 3(T) 0.039 0.012 Comb3 0.002 Comb5
D3 No Comb
Story1 31 B59 Brace tubo Message 3(C) 0.072 0.011 Comb3 0.002 Comb3
D3 No Comb
Story1 32 B5A Brace tubo Message 3(T) 0.046 0.009 Comb3 0.002 Comb4
D3 No Comb
Story1 33 B5B Brace tubo Message 3(C) 0.063 0.009 Comb3 0.001 Comb3
D3 No Comb
Story1 34 B5C Brace tubo Message 3(T) 0.062 0.013 Comb3 0.002 Comb3
D3 No Comb
Story1 35 B5D Brace tubo Message 3(C) 0.02 0.014 Comb3 0.002 Comb4
D3 No Comb
Story1 35 Brace tubo Message 5(T) 0.019 0.01
D3 No Comb
Story1 36 B5E Brace tubo Message 3(T) 0.089 0.031 Comb3 0.002 Comb4
D3 No Comb
Story1 37 B5F Brace tubo Message 5(T) 0.287 0.005 Comb3 0.002 Comb5
D3 No Comb
Story1 38 B60 Brace tubo Message 5(C) 0.359 0.028 Comb3 0.003 Comb5
D3 No Comb
Story1 39 B61 Brace tubo Message 5(C) 0.119 0.037 Comb3 0.003 Comb5
D3 No Comb
Story1 40 B62 Brace tubo Message 5(C) 0.071 0.021 Comb3 0.002 Comb3
D3 No Comb
Story1 41 B63 Brace tubo Message 3(C) 0.062 0.016 Comb3 0.002 Comb3
D3 No Comb
Story1 42 B64 Brace tubo Message 5(C) 0.082 0.008 Comb3 0.002 Comb3

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


73

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D3 No Comb
Story1 43 B65 Brace tubo Message 3(T) 0.026 0.009 Comb3 0.001 Comb12
D3 No Comb
Story1 44 B66 Brace tubo Message 5(C) 0.096 0.004 Comb3 0.001 Comb3
D3 No Comb
Story1 45 B67 Brace tubo Message 3(T) 0.042 0.01 Comb3 0.002 Comb4
D3 No Comb
Story1 46 B68 Brace tubo Message 5(C) 0.091 0.006 Comb3 0.002 Comb3
D3 No Comb
Story1 47 B69 Brace tubo Message 3(T) 0.046 0.012 Comb3 0.002 Comb4
D3 No Comb
Story1 48 B6A Brace tubo Message 3(C) 0.076 0.013 Comb3 0.002 Comb4
D3 No Comb
Story1 49 B6B Brace tubo Message 3(T) 0.043 0.014 Comb3 0.002 Comb4
D3 No Comb
Story1 50 B6C Brace tubo Message 3(C) 0.061 0.015 Comb3 0.002 Comb4
D3 No Comb
Story1 51 B6D Brace tubo Message 3(T) 0.033 0.016 Comb3 0.002 Comb4
D3 No Comb
Story1 52 B6E Brace tubo Message 3(C) 0.042 0.016 Comb3 0.002 Comb4
D3 No Comb
Story1 53 B6F Brace tubo Message 3(T) 0.02 0.016 Comb3 0.002 Comb5
D3 No Comb
Story1 54 B70 Brace tubo Message 3(C) 0.018 0.016 Comb3 0.002 Comb5
D3 No Comb
Story1 54 Brace tubo Message 2(T) 0.013 0.01
D3 No Comb
Story1 55 B71 Brace tubo Message 3(C) 0.034 0.016 Comb3 0.002 Comb4
D3 No Comb
Story1 56 B72 Brace tubo Message 3(T) 0.029 0.016 Comb3 0.002 Comb4
D3 No Comb
Story1 57 B73 Brace tubo Message 3(C) 0.057 0.015 Comb3 0.002 Comb4
D3 No Comb
Story1 58 B74 Brace tubo Message 3(T) 0.04 0.014 Comb3 0.002 Comb4
D3 No Comb
Story1 59 B75 Brace tubo Message 3(C) 0.075 0.013 Comb3 0.002 Comb4
D3 No Comb
Story1 60 B76 Brace tubo Message 3(T) 0.048 0.012 Comb3 0.002 Comb4
D3 No Comb
Story1 61 B77 Brace tubo Message 5(C) 0.088 0.006 Comb3 0.002 Comb3
D3 No Comb
Story1 62 B78 Brace tubo Message 3(T) 0.046 0.01 Comb3 0.002 Comb4
D3 No Comb
Story1 63 B79 Brace tubo Message 5(C) 0.095 0.004 Comb3 0.001 Comb3
D3 No Comb
Story1 64 B7A Brace tubo Message 3(T) 0.029 0.008 Comb3 0.001 Comb3
D3 No Comb
Story1 65 B7B Brace tubo Message 5(C) 0.084 0.008 Comb3 0.002 Comb3
D3 No Comb
Story1 66 B7C Brace tubo Message 3(C) 0.058 0.016 Comb3 0.002 Comb3
D3 No Comb
Story1 67 B7D Brace tubo Message 5(C) 0.068 0.017 Comb3 0.002 Comb3
D3 No Comb
Story1 68 B7E Brace tubo Message 5(C) 0.115 0.038 Comb3 0.003 Comb5
D3 No Comb
Story1 69 B7F Brace tubo Message 5(T) 0.072 0.038 Comb3 0.003 Comb5
D3 No Comb
Story1 70 B80 Brace tubo Message 5(T) 0.06 0.021 Comb3 0.002 Comb5
D3 No Comb
Story1 71 B81 Brace tubo Message 5(C) 0.031 0.012 Comb3 0.002 Comb4
D3 No Comb
Story1 72 B82 Brace tubo Message 3(C) 0.061 0.013 Comb3 0.002 Comb5
D3 No Comb
Story1 73 B83 Brace tubo Message 3(T) 0.028 0.01 Comb3 0.001 Comb4

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


74

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D3 No Comb
Story1 74 B84 Brace tubo Message 3(C) 0.083 0.007 Comb3 0.001 Comb4
D3 No Comb
Story1 75 B85 Brace tubo Message 3(T) 0.033 0.009 Comb3 0.002 Comb4
D3 No Comb
Story1 76 B86 Brace tubo Message 3(C) 0.08 0.01 Comb3 0.002 Comb3
D3 No Comb
Story1 77 B87 Brace tubo Message 5(T) 0.031 0.007 Comb3 0.002 Comb5
D3 No Comb
Story1 78 B88 Brace tubo Message 3(C) 0.064 0.012 Comb3 0.002 Comb4
D3 No Comb
Story1 79 B89 Brace tubo Message 5(T) 0.027 0.007 Comb3 0.002 Comb5
D3 No Comb
Story1 80 B8A Brace tubo Message 3(C) 0.049 0.014 Comb3 0.002 Comb5
D3 No Comb
Story1 81 B8B Brace tubo Message 5(T) 0.022 0.01 Comb3 0.002 Comb5
D3 No Comb
Story1 82 B8C Brace tubo Message 3(C) 0.032 0.015 Comb3 0.002 Comb5
D3 No Comb
Story1 83 B8D Brace tubo Message 3(C) 0.02 0.015 Comb3 0.002 Comb3
D3 No Comb
Story1 84 B8E Brace tubo Message 12(C) 0.009 0.008 Comb3 0.002 Comb5
D3 No Comb
Story1 84 Brace tubo Message 5(T) 0.017 0.012
D3 No Comb
Story1 85 B8F Brace tubo Message 3(C) 0.035 0.015 Comb3 0.002 Comb5
D3 No Comb
Story1 86 B90 Brace tubo Message 3(T) 0.024 0.015 Comb3 0.002 Comb5
D3 No Comb
Story1 87 B91 Brace tubo Message 3(C) 0.051 0.014 Comb3 0.002 Comb5
D3 No Comb
Story1 88 B92 Brace tubo Message 3(T) 0.029 0.014 Comb3 0.002 Comb5
D3 No Comb
Story1 89 B93 Brace tubo Message 3(C) 0.066 0.012 Comb3 0.002 Comb4
D3 No Comb
Story1 90 B94 Brace tubo Message 5(T) 0.03 0.007 Comb3 0.002 Comb5
D3 No Comb
Story1 91 B95 Brace tubo Message 3(C) 0.076 0.01 Comb3 0.002 Comb3
D3 No Comb
Story1 92 B96 Brace tubo Message 3(T) 0.03 0.01 Comb3 0.002 Comb4
D3 No Comb
Story1 93 B97 Brace tubo Message 3(C) 0.08 0.008 Comb3 0.001 Comb3
D3 No Comb
Story1 94 B98 Brace tubo Message 3(T) 0.026 0.01 Comb3 0.001 Comb4
D3 No Comb
Story1 95 B99 Brace tubo Message 3(C) 0.063 0.012 Comb3 0.002 Comb5
D3 No Comb
Story1 96 B9A Brace tubo Message 5(C) 0.037 0.013 Comb3 0.002 Comb4
D3 No Comb
Story1 97 B9B Brace tubo Message 5(T) 0.059 0.017 Comb3 0.002 Comb5
D3 No Comb
Story1 98 B9C Brace tubo Message 5(T) 0.071 0.039 Comb3 0.003 Comb5
D3 No Comb
Story1 99 B9D Brace tubo Message 5(C) 0.591 0.026 Comb3 0.002 Comb12
D4 No Comb
Story1 00 B9E Brace tubo Message 5(T) 0.332 0.061 Comb3 0.004 Comb3
D4 No Comb
Story1 01 B9F Brace tubo Message 4(C) 0.061 0.053 Comb3 0.004 Comb4
D4 No Comb
Story1 01 Brace tubo Message 3(T) 0.079 0.051
D4 No Comb
Story1 02 BA0 Brace tubo Message 5(T) 0.118 0.003 Comb3 0.002 Comb5
D4 No Comb
Story1 03 BA1 Brace tubo Message 5(T) 0.069 0.027 Comb3 0.002 Comb4

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


75

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D4 No Comb
Story1 04 BA2 Brace tubo Message 5(C) 0.045 0.016 Comb3 0.002 Comb5
D4 No Comb
Story1 05 BA3 Brace tubo Message 5(T) 0.07 0.011 Comb3 0.002 Comb3
D4 No Comb
Story1 06 BA4 Brace tubo Message 5(C) 0.095 0.009 Comb3 0.002 Comb3
D4 No Comb
Story1 07 BA5 Brace tubo Message 5(T) 0.059 0.003 Comb3 0.001 Comb4
D4 No Comb
Story1 08 BA6 Brace tubo Message 5(C) 0.093 0.005 Comb3 0.001 Comb3
D4 No Comb
Story1 09 BA7 Brace tubo Message 3(T) 0.059 0.01 Comb3 0.002 Comb4
D4 No Comb
Story1 10 BA8 Brace tubo Message 3(C) 0.084 0.012 Comb3 0.002 Comb4
D4 No Comb
Story1 11 BA9 Brace tubo Message 3(T) 0.052 0.013 Comb3 0.002 Comb4
D4 No Comb
Story1 12 BAA Brace tubo Message 3(C) 0.069 0.014 Comb3 0.002 Comb4
D4 No Comb
Story1 13 BAB Brace tubo Message 3(T) 0.037 0.014 Comb3 0.002 Comb4
D4 No Comb
Story1 14 BAC Brace tubo Message 3(C) 0.045 0.015 Comb3 0.002 Comb5
D4 No Comb
Story1 15 BAD Brace tubo Message 3(T) 0.022 0.015 Comb3 0.002 Comb3
D4 No Comb
Story1 16 BAE Brace tubo Message 3(C) 0.017 0.015 Comb3 0.002 Comb5
D4 No Comb
Story1 16 Brace tubo Message 4(T) 0.015 0.01
D4 No Comb
Story1 17 BAF Brace tubo Message 3(C) 0.034 0.015 Comb3 0.002 Comb3
D4 No Comb
Story1 18 BB0 Brace tubo Message 3(T) 0.03 0.015 Comb3 0.002 Comb3
D4 No Comb
Story1 19 BB1 Brace tubo Message 3(C) 0.061 0.014 Comb3 0.002 Comb4
D4 No Comb
Story1 20 BB2 Brace tubo Message 3(T) 0.046 0.013 Comb3 0.002 Comb4
D4 No Comb
Story1 21 BB3 Brace tubo Message 3(C) 0.084 0.012 Comb3 0.002 Comb4
D4 No Comb
Story1 22 BB4 Brace tubo Message 3(T) 0.061 0.011 Comb3 0.002 Comb4
D4 No Comb
Story1 23 BB5 Brace tubo Message 3(C) 0.095 0.01 Comb3 0.001 Comb3
D4 No Comb
Story1 24 BB6 Brace tubo Message 3(T) 0.067 0.007 Comb3 0.001 Comb4
D4 No Comb
Story1 25 BB7 Brace tubo Message 5(C) 0.095 0.009 Comb3 0.002 Comb3
D4 No Comb
Story1 26 BB8 Brace tubo Message 5(T) 0.073 0.01 Comb3 0.002 Comb3
D4 No Comb
Story1 27 BB9 Brace tubo Message 5(C) 0.047 0.017 Comb3 0.002 Comb5
D4 No Comb
Story1 27 Brace tubo Message 12(T) 0.014 0.01
D4 No Comb
Story1 28 BBA Brace tubo Message 5(T) 0.075 0.029 Comb3 0.003 Comb4
D4 No Comb
Story1 29 BBB Brace tubo Message 3(T) 0.122 0.005 Comb3 0.002 Comb5
D4 No Comb
Story1 30 BBC Brace tubo Message 5(C) 0.589 0.028 Comb3 0.003 Comb12
D4 No Comb
Story1 31 BBD Brace tubo Message 5(C) 0.952 0.053 Comb3 0.002 Comb4
D4 No Comb
Story1 32 BBE Brace tubo Message 3(T) 0.099 0.022 Comb3 0.002 Comb3
D4 No Comb
Story1 33 BBF Brace tubo Message 4(C) 0.441 0.011 Comb3 0.002 Comb5

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


76

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D4 No Comb
Story1 34 BC0 Brace tubo Message 3(T) 0.05 0.01 Comb3 0.001 Comb3
D4 No Comb
Story1 35 BC1 Brace tubo Message 3(C) 0.26 0.011 Comb3 0.002 Comb4
D4 No Comb
Story1 36 BC2 Brace tubo Message 5(T) 0.04 0.01 Comb3 0.002 Comb2
D4 No Comb
Story1 37 BC3 Brace tubo Message 3(C) 0.113 0.015 Comb3 0.002 Comb4
D4 No Comb
Story1 38 BC4 Brace tubo Message 5(T) 0.035 0.013 Comb3 0.002 Comb2
D4 No Comb
Story1 39 BC5 Brace tubo Message 3(C) 0.08 0.017 Comb3 0.002 Comb12
D4 No Comb
Story1 40 BC6 Brace tubo Message 5(T) 0.03 0.015 Comb3 0.002 Comb3
D4 No Comb
Story1 41 BC7 Brace tubo Message 3(C) 0.055 0.019 Comb3 0.002 Comb3
D4 No Comb
Story1 42 BC8 Brace tubo Message 5(T) 0.025 0.016 Comb3 0.002 Comb3
D4 No Comb
Story1 43 BC9 Brace tubo Message 3(C) 0.036 0.02 Comb3 0.002 Comb3
D4 No Comb
Story1 44 BCA Brace tubo Message 3(C) 0.025 0.02 Comb3 0.002 Comb3
D4 No Comb
Story1 45 BCB Brace tubo Message 12(C) 0.014 0.013 Comb3 0.002 Comb3
D4 No Comb
Story1 45 Brace tubo Message 3(T) 0.02 0.02
D4 No Comb
Story1 46 BCC Brace tubo Message 3(C) 0.039 0.02 Comb3 0.002 Comb3
D4 No Comb
Story1 47 BCD Brace tubo Message 3(T) 0.027 0.019 Comb3 0.002 Comb3
D4 No Comb
Story1 48 BCE Brace tubo Message 3(C) 0.055 0.019 Comb3 0.002 Comb3
D4 No Comb
Story1 49 BCF Brace tubo Message 3(T) 0.031 0.018 Comb3 0.002 Comb3
D4 No Comb
Story1 50 BD0 Brace tubo Message 3(C) 0.074 0.017 Comb3 0.002 Comb5
D4 No Comb
Story1 51 BD1 Brace tubo Message 5(T) 0.035 0.013 Comb3 0.002 Comb3
D4 No Comb
Story1 52 BD2 Brace tubo Message 3(C) 0.102 0.014 Comb3 0.002 Comb4
D4 No Comb
Story1 53 BD3 Brace tubo Message 5(T) 0.038 0.01 Comb3 0.002 Comb3
D4 No Comb
Story1 54 BD4 Brace tubo Message 3(C) 0.285 0.011 Comb3 0.002 Comb4
D4 No Comb
Story1 55 BD5 Brace tubo Message 5(T) 0.048 0.007 Comb3 0.001 Comb12
D4 No Comb
Story1 56 BD6 Brace tubo Message 3(C) 0.451 0.017 Comb3 0.002 Comb4
D4 No Comb
Story1 57 BD7 Brace tubo Message 3(T) 0.1 0.023 Comb3 0.002 Comb12
D4 No Comb
Story1 58 BD8 Brace tubo Message 5(C) 0.986 0.038 Comb3 0.002 Comb5
D4 No Comb
Story1 59 BD9 Brace tubo Message 5(T) 0.332 0.063 Comb3 0.004 Comb3
D4 No Comb
Story1 60 BDA Brace tubo Message 4(C) 0.629 0.032 Comb3 0.003 Comb4
D4 No Comb
Story1 61 BDB Brace tubo Message 5(T) 0.294 0.005 Comb3 0.002 Comb4
D4 No Comb
Story1 62 BDC Brace tubo Message 5(C) 0.455 0.018 Comb3 0.002 Comb5
D4 No Comb
Story1 63 BDD Brace tubo Message 5(T) 0.134 0.033 Comb3 0.003 Comb3
D4 No Comb
Story1 64 BDE Brace tubo Message 5(C) 0.335 0.028 Comb3 0.003 Comb4

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


77

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D4 No Comb
Story1 65 BDF Brace tubo Message 5(T) 0.108 0.039 Comb3 0.003 Comb3
D4 No Comb
Story1 66 BE0 Brace tubo Message 5(C) 0.252 0.032 Comb3 0.003 Comb3
D4 No Comb
Story1 66 Brace tubo Message 12(T) 0.037 0.024
D4 No Comb
Story1 67 BE1 Brace tubo Message 3(T) 0.118 0.034 Comb3 0.003 Comb3
D4 No Comb
Story1 68 BE2 Brace tubo Message 3(C) 0.249 0.031 Comb3 0.003 Comb3
D4 No Comb
Story1 69 BE3 Brace tubo Message 3(T) 0.09 0.043 Comb3 0.004 Comb5
D4 No Comb
Story1 70 BE4 Brace tubo Message 3(C) 0.107 0.04 Comb3 0.003 Comb3
D4 No Comb
Story1 71 BE5 Brace tubo Message 3(T) 0.069 0.044 Comb3 0.004 Comb5
D4 No Comb
Story1 72 BE6 Brace tubo Message 3(C) 0.075 0.042 Comb3 0.004 Comb3
D4 No Comb
Story1 73 BE7 Brace tubo Message 5(T) 0.053 0.048 Comb3 0.004 Comb5
D4 No Comb
Story1 74 BE8 Brace tubo Message 12(C) 0.039 0.036 Comb3 0.004 Comb3
D4 No Comb
Story1 74 Brace tubo Message 5(T) 0.051 0.048
D4 No Comb
Story1 75 BE9 Brace tubo Message 5(C) 0.068 0.047 Comb3 0.004 Comb5
D4 No Comb
Story1 76 BEA Brace tubo Message 5(T) 0.063 0.048 Comb3 0.004 Comb5
D4 No Comb
Story1 77 BEB Brace tubo Message 5(C) 0.092 0.045 Comb3 0.004 Comb3
D4 No Comb
Story1 78 BEC Brace tubo Message 3(T) 0.078 0.042 Comb3 0.004 Comb5
D4 No Comb
Story1 79 BED Brace tubo Message 3(C) 0.126 0.037 Comb3 0.003 Comb3
D4 No Comb
Story1 80 BEE Brace tubo Message 3(T) 0.1 0.04 Comb3 0.003 Comb4
D4 No Comb
Story1 81 BEF Brace tubo Message 3(C) 0.3 0.028 Comb3 0.003 Comb3
D4 No Comb
Story1 82 BF0 Brace tubo Message 3(T) 0.133 0.03 Comb3 0.003 Comb3
D4 No Comb
Story1 83 BF1 Brace tubo Message 5(C) 0.344 0.029 Comb3 0.003 Comb3
D4 No Comb
Story1 84 BF2 Brace tubo Message 5(T) 0.138 0.034 Comb3 0.003 Comb3
D4 No Comb
Story1 85 BF3 Brace tubo Message 5(C) 0.47 0.018 Comb3 0.002 Comb5
D4 No Comb
Story1 86 BF4 Brace tubo Message 5(T) 0.304 0.003 Comb3 0.002 Comb3
D4 No Comb
Story1 87 BF5 Brace tubo Message 5(C) 0.648 0.029 Comb3 0.003 Comb4
D4 No Comb
Story1 88 BF6 Brace tubo Message 5(C) 0.066 0.058 Comb3 0.004 Comb5
D4 No Comb
Story1 88 Brace tubo Message 3(T) 0.077 0.056

Tabla 9_Resultados de Chequeo de Deflexiones Cuerda inferior, Superior y Diagonales

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


78

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Como puede apreciarse, algunos elementos de la cubierta presentan Fallas
Criticas, especialmente los cercanos a los Apoyos, en tanto su distribución y
configuración no es la mas adecuada para el soporte de toda la estructura. No
obstante, aunque se presentan fallas en ciertos elementos, no puede
considerarse como no resistente o como insuficiente, en tanto las limitaciones de
modelación y de configuración hacen necesario un estudio mas detallado.

De igual manera en un análisis no lineal, se pueden ver representados los puntos


de falla a continuación expuestos que corroboran la secuencia de falla de la
estructura. Se reitera que el estado de comportamiento de la edificación ante sus
propias solicitaciones (peso propio + Carga de cubierta), carga de viento y carga
de sismo son satisfactorias.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


79

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 17_secuencia de Falla modo 1 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


80

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 18_secuencia de Falla modo 2 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


81

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 19_secuencia de Falla modo 3 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


82

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 20_secuencia de Falla modo 4 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


83

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 21_secuencia de Falla modo 5 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


84

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 22_secuencia de Falla modo 6 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


85

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 23_secuencia de Falla modo 7 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


86

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 24_secuencia de Falla modo 8 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


87

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 25_secuencia de Falla modo 9 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


88

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 26_secuencia de Falla modo 10 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


89

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 27_secuencia de Falla modo 11 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


90

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 28_secuencia de Falla modo 12 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


91

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 29_secuencia de Falla modo 13 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


92

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 30_secuencia de Falla modo 14 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


93

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 31_secuencia de Falla modo 15 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


94

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 32_secuencia de Falla modo 16 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


95

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 33_secuencia de Falla modo 17 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


96

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 34_secuencia de Falla modo 18 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


97

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 35_secuencia de Falla modo 19 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


98

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 36_secuencia de Falla modo 20 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


99

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 37_secuencia de Falla modo 21 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


100

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 38_secuencia de Falla modo 22 sentido x formación de rotulas plasticas

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


101

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
TABLE: Joint Drifts
Story Label Unique Name Load Case/Combo Displacement X Displacement Y Drift X Drift Y
cm cm
Story1 1 3 pushx Max 0 0 0.00% 0.01%
Story1 1 3 pushx Min -0.4707 -0.0168 0.16% 0.02%
Story1 2 4 pushx Max 0 0 0.00% 0.01%
Story1 2 4 pushx Min -0.4707 -0.0163 0.16% 0.02%
Story1 3 6 pushx Max 0 0 0.00% 0.00%
Story1 3 6 pushx Min -0.4707 -0.0158 0.13% 0.04%
Story1 4 8 pushx Max 0 0 0.00% 0.06%
Story1 4 8 pushx Min -0.4707 -0.0153 0.11% 0.00%
Story1 5 10 pushx Max 0 0 0.00% 0.05%
Story1 5 10 pushx Min -0.4707 -0.0149 0.13% 0.00%
Story1 6 12 pushx Max 0 0 0.00% 0.02%
Story1 6 12 pushx Min -0.4707 -0.0144 0.17% 0.02%
Story1 7 14 pushx Max 0 0 0.00% 0.00%
Story1 7 14 pushx Min -0.4707 -0.014 0.18% 0.04%
Story1 8 16 pushx Max 0 0 0.00% 0.00%
Story1 8 16 pushx Min -0.4707 -0.0136 0.18% 0.05%
Story1 9 19 pushx Max 0 0 0.01% 0.06%
Story1 9 19 pushx Min -0.4707 -0.0142 0.04% 0.00%
Story1 10 20 pushx Max 0 0 0.01% 0.06%
Story1 10 20 pushx Min -0.4707 -0.0147 0.04% 0.00%
Story1 11 22 pushx Max 0 0 0.00% 0.07%
Story1 11 22 pushx Min -0.4707 -0.0152 0.04% 0.00%
Story1 12 24 pushx Max 0 0 0.00% 0.02%
Story1 12 24 pushx Min -0.4707 -0.0157 0.06% 0.01%
Story1 13 26 pushx Max 0 0 0.00% 0.00%
Story1 13 26 pushx Min -0.4707 -0.0162 0.06% 0.04%
Story1 14 28 pushx Max 0 0 0.00% 0.02%
Story1 14 28 pushx Min -0.4707 -0.0167 0.05% 0.00%
Story1 15 30 pushx Max 0 0 0.00% 0.00%
Story1 15 30 pushx Min -0.4707 -0.0172 0.05% 0.02%
Story1 16 33 pushx Max 0 0 0.00% 0.01%
Story1 16 33 pushx Min -0.4704 -0.0168 0.16% 0.02%
Story1 17 34 pushx Max 0 0 0.00% 0.01%
Story1 17 34 pushx Min -0.4704 -0.0163 0.16% 0.02%
Story1 18 36 pushx Max 0 0 0.00% 0.00%
Story1 18 36 pushx Min -0.4704 -0.0158 0.13% 0.04%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


102

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 19 38 pushx Max 0 0 0.00% 0.06%
Story1 19 38 pushx Min -0.4704 -0.0153 0.11% 0.00%
Story1 20 40 pushx Max 0 0 0.00% 0.05%
Story1 20 40 pushx Min -0.4704 -0.0149 0.13% 0.00%
Story1 21 42 pushx Max 0 0 0.00% 0.02%
Story1 21 42 pushx Min -0.4704 -0.0144 0.17% 0.02%
Story1 22 44 pushx Max 0 0 0.00% 0.00%
Story1 22 44 pushx Min -0.4704 -0.014 0.18% 0.04%
Story1 23 46 pushx Max 0 0 0.00% 0.00%
Story1 23 46 pushx Min -0.4704 -0.0136 0.18% 0.05%
Story1 24 49 pushx Max 0 0 0.01% 0.06%
Story1 24 49 pushx Min -0.4704 -0.0142 0.04% 0.00%
Story1 25 50 pushx Max 0 0 0.01% 0.06%
Story1 25 50 pushx Min -0.4704 -0.0147 0.04% 0.00%
Story1 26 52 pushx Max 0 0 0.00% 0.07%
Story1 26 52 pushx Min -0.4704 -0.0152 0.04% 0.00%
Story1 27 54 pushx Max 0 0 0.00% 0.02%
Story1 27 54 pushx Min -0.4704 -0.0157 0.06% 0.01%
Story1 28 56 pushx Max 0 0 0.00% 0.00%
Story1 28 56 pushx Min -0.4704 -0.0162 0.06% 0.04%
Story1 29 58 pushx Max 0 0 0.00% 0.02%
Story1 29 58 pushx Min -0.4704 -0.0167 0.05% 0.00%
Story1 30 60 pushx Max 0 0 0.00% 0.00%
Story1 30 60 pushx Min -0.4704 -0.0172 0.05% 0.02%
Story1 31 63 pushx Max 0 0 0.00% 0.01%
Story1 31 63 pushx Min -0.4701 -0.0168 0.23% 0.02%
Story1 32 64 pushx Max 0 0 0.00% 0.01%
Story1 32 64 pushx Min -0.4701 -0.0163 0.23% 0.02%
Story1 33 66 pushx Max 0 0 0.00% 0.00%
Story1 33 66 pushx Min -0.4701 -0.0158 0.11% 0.05%
Story1 34 68 pushx Max 0 0 0.00% 0.09%
Story1 34 68 pushx Min -0.4701 -0.0153 0.08% 0.00%
Story1 35 70 pushx Max 0 0 0.00% 0.05%
Story1 35 70 pushx Min -0.4701 -0.0149 0.15% 0.00%
Story1 36 72 pushx Max 0 0 0.00% 0.01%
Story1 36 72 pushx Min -0.4701 -0.0144 0.21% 0.02%
Story1 37 74 pushx Max 0 0 0.00% 0.00%
Story1 37 74 pushx Min -0.4701 -0.014 0.21% 0.05%
Story1 38 76 pushx Max 0 0 0.00% 0.00%
Story1 38 76 pushx Min -0.4701 -0.0136 0.19% 0.05%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


103

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 39 78 pushx Max 0 0 0.02% 0.02%
Story1 39 78 pushx Min -0.4701 -0.0132 0.06% 0.01%
Story1 40 80 pushx Max 0 0 0.07% 0.04%
Story1 40 80 pushx Min -0.4701 -0.0129 0.00% 0.00%
Story1 41 82 pushx Max 0 0 0.11% 0.06%
Story1 41 82 pushx Min -0.4701 -0.0125 0.00% 0.00%
Story1 42 84 pushx Max 0 0 0.16% 0.08%
Story1 42 84 pushx Min -0.4701 -0.0122 0.00% 0.00%
Story1 43 86 pushx Max 0 0 0.20% 0.08%
Story1 43 86 pushx Min -0.4701 -0.0127 0.00% 0.00%
Story1 44 88 pushx Max 0 0 0.22% 0.08%
Story1 44 88 pushx Min -0.4701 -0.0132 0.00% 0.00%
Story1 45 90 pushx Max 0 0 0.21% 0.08%
Story1 45 90 pushx Min -0.4701 -0.0137 0.00% 0.00%
Story1 46 92 pushx Max 0 0 0.19% 0.07%
Story1 46 92 pushx Min -0.4701 -0.0142 0.00% 0.00%
Story1 47 94 pushx Max 0 0 0.13% 0.06%
Story1 47 94 pushx Min -0.4701 -0.0147 0.04% 0.00%
Story1 48 96 pushx Max 0 0 0.09% 0.08%
Story1 48 96 pushx Min -0.4701 -0.0152 0.12% 0.00%
Story1 49 98 pushx Max 0 0 0.00% 0.00%
Story1 49 98 pushx Min -0.4701 -0.0157 0.67% 0.02%
Story1 50 100 pushx Max 0 0 0.00% 0.00%
Story1 50 100 pushx Min -0.4701 -0.0162 0.08% 0.07%
Story1 51 102 pushx Max 0 0 0.08% 0.09%
Story1 51 102 pushx Min -0.4701 -0.0167 0.04% 0.00%
Story1 52 104 pushx Max 0 0 0.00% 0.00%
Story1 52 104 pushx Min -0.4701 -0.0172 0.67% 0.02%
Story1 53 107 pushx Max 0 0 0.00% 0.00%
Story1 53 107 pushx Min -0.4697 -0.0168 0.67% 0.02%
Story1 54 108 pushx Max 0 0 0.00% 0.00%
Story1 54 108 pushx Min -0.4697 -0.0163 0.67% 0.02%
Story1 55 110 pushx Max 0 0 0.00% 0.00%
Story1 55 110 pushx Min -0.4697 -0.0158 0.09% 0.05%
Story1 56 112 pushx Max 0 0 0.07% 0.15%
Story1 56 112 pushx Min -0.4697 -0.0153 0.04% 0.00%
Story1 57 114 pushx Max 0 0 0.00% 0.00%
Story1 57 114 pushx Min -0.4697 -0.0149 0.67% 0.02%
Story1 58 116 pushx Max 0 0 0.00% 0.01%
Story1 58 116 pushx Min -0.4697 -0.0144 0.41% 0.02%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


104

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 59 118 pushx Max 0 0 0.00% 0.00%
Story1 59 118 pushx Min -0.4697 -0.014 0.26% 0.04%
Story1 60 120 pushx Max 0 0 0.00% 0.00%
Story1 60 120 pushx Min -0.4697 -0.0136 0.16% 0.04%
Story1 61 122 pushx Max 0 0 0.02% 0.02%
Story1 61 122 pushx Min -0.4697 -0.0132 0.06% 0.01%
Story1 62 124 pushx Max 0 0 0.07% 0.04%
Story1 62 124 pushx Min -0.4697 -0.0129 0.00% 0.00%
Story1 63 126 pushx Max 0 0 0.11% 0.06%
Story1 63 126 pushx Min -0.4697 -0.0125 0.00% 0.00%
Story1 64 128 pushx Max 0 0 0.16% 0.08%
Story1 64 128 pushx Min -0.4697 -0.0122 0.00% 0.00%
Story1 65 130 pushx Max 0 0 0.20% 0.08%
Story1 65 130 pushx Min -0.4697 -0.0127 0.00% 0.00%
Story1 66 132 pushx Max 0 0 0.22% 0.08%
Story1 66 132 pushx Min -0.4697 -0.0132 0.00% 0.00%
Story1 67 134 pushx Max 0 0 0.22% 0.08%
Story1 67 134 pushx Min -0.4697 -0.0137 0.00% 0.00%
Story1 68 136 pushx Max 0 0 0.19% 0.07%
Story1 68 136 pushx Min -0.4697 -0.0142 0.00% 0.00%
Story1 69 138 pushx Max 0 0 0.13% 0.06%
Story1 69 138 pushx Min -0.4697 -0.0147 0.05% 0.00%
Story1 70 140 pushx Max 0 0 0.09% 0.08%
Story1 70 140 pushx Min -0.4697 -0.0152 0.12% 0.00%
Story1 71 142 pushx Max 0 0 0.00% 0.00%
Story1 71 142 pushx Min -0.4697 -0.0157 0.67% 0.02%
Story1 72 144 pushx Max 0 0 0.00% 0.00%
Story1 72 144 pushx Min -0.4697 -0.0162 0.08% 0.07%
Story1 73 146 pushx Max 0 0 0.08% 0.09%
Story1 73 146 pushx Min -0.4697 -0.0167 0.04% 0.00%
Story1 74 148 pushx Max 0 0 0.00% 0.00%
Story1 74 148 pushx Min -0.4697 -0.0172 0.67% 0.02%
Story1 75 151 pushx Max 0 0 0.00% 0.02%
Story1 75 151 pushx Min -0.4694 -0.0153 0.46% 0.00%
Story1 76 152 pushx Max 0 0 0.00% 0.02%
Story1 76 152 pushx Min -0.4694 -0.0149 0.46% 0.00%
Story1 77 154 pushx Max 0 0 0.00% 0.00%
Story1 77 154 pushx Min -0.4694 -0.0144 0.37% 0.01%
Story1 78 156 pushx Max 0 0 0.00% 0.00%
Story1 78 156 pushx Min -0.4694 -0.014 0.25% 0.02%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


105

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 79 158 pushx Max 0 0 0.00% 0.00%
Story1 79 158 pushx Min -0.4694 -0.0136 0.15% 0.02%
Story1 80 160 pushx Max 0 0 0.04% 0.02%
Story1 80 160 pushx Min -0.4694 -0.0132 0.05% 0.01%
Story1 81 162 pushx Max 0 0 0.09% 0.04%
Story1 81 162 pushx Min -0.4694 -0.0129 0.00% 0.00%
Story1 82 164 pushx Max 0 0 0.12% 0.06%
Story1 82 164 pushx Min -0.4694 -0.0125 0.00% 0.00%
Story1 83 166 pushx Max 0 0 0.17% 0.08%
Story1 83 166 pushx Min -0.4694 -0.0122 0.00% 0.00%
Story1 84 168 pushx Max 0 0 0.20% 0.08%
Story1 84 168 pushx Min -0.4694 -0.0127 0.00% 0.00%
Story1 85 170 pushx Max 0 0 0.22% 0.08%
Story1 85 170 pushx Min -0.4694 -0.0132 0.00% 0.00%
Story1 86 172 pushx Max 0 0 0.21% 0.08%
Story1 86 172 pushx Min -0.4694 -0.0137 0.00% 0.00%
Story1 87 174 pushx Max 0 0 0.19% 0.07%
Story1 87 174 pushx Min -0.4694 -0.0142 0.00% 0.00%
Story1 88 176 pushx Max 0 0 0.16% 0.05%
Story1 88 176 pushx Min -0.4694 -0.0147 0.05% 0.00%
Story1 89 178 pushx Max 0 0 0.13% 0.04%
Story1 89 178 pushx Min -0.4694 -0.0152 0.13% 0.00%
Story1 90 180 pushx Max 0 0 0.00% 0.00%
Story1 90 180 pushx Min -0.4694 -0.0157 0.56% 0.02%
Story1 91 183 pushx Max 0 0 0.00% 0.00%
Story1 91 183 pushx Min -0.4691 -0.0153 0.67% 0.02%
Story1 92 184 pushx Max 0 0 0.00% 0.00%
Story1 92 184 pushx Min -0.4691 -0.0149 0.67% 0.02%
Story1 93 186 pushx Max 0 0 0.00% 0.00%
Story1 93 186 pushx Min -0.4691 -0.0144 0.44% 0.00%
Story1 94 188 pushx Max 0 0 0.00% 0.00%
Story1 94 188 pushx Min -0.4691 -0.014 0.28% 0.01%
Story1 95 190 pushx Max 0 0 0.00% 0.01%
Story1 95 190 pushx Min -0.4691 -0.0136 0.15% 0.01%
Story1 96 192 pushx Max 0 0 0.05% 0.03%
Story1 96 192 pushx Min -0.4691 -0.0132 0.04% 0.01%
Story1 97 194 pushx Max 0 0 0.10% 0.05%
Story1 97 194 pushx Min -0.4691 -0.0129 0.00% 0.00%
Story1 98 196 pushx Max 0 0 0.13% 0.06%
Story1 98 196 pushx Min -0.4691 -0.0125 0.00% 0.00%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


106

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 99 198 pushx Max 0 0 0.17% 0.08%
Story1 99 198 pushx Min -0.4691 -0.0122 0.00% 0.00%
Story1 100 200 pushx Max 0 0 0.20% 0.08%
Story1 100 200 pushx Min -0.4691 -0.0127 0.00% 0.00%
Story1 101 202 pushx Max 0 0 0.22% 0.08%
Story1 101 202 pushx Min -0.4691 -0.0132 0.00% 0.00%
Story1 102 204 pushx Max 0 0 0.21% 0.08%
Story1 102 204 pushx Min -0.4691 -0.0137 0.00% 0.00%
Story1 103 206 pushx Max 0 0 0.19% 0.07%
Story1 103 206 pushx Min -0.4691 -0.0142 0.00% 0.00%
Story1 104 208 pushx Max 0 0 0.16% 0.05%
Story1 104 208 pushx Min -0.4691 -0.0147 0.06% 0.00%
Story1 105 210 pushx Max 0 0 0.13% 0.02%
Story1 105 210 pushx Min -0.4691 -0.0152 0.16% 0.00%
Story1 106 212 pushx Max 0 0 0.00% 0.00%
Story1 106 212 pushx Min -0.4691 -0.0157 0.67% 0.02%
Story1 107 215 pushx Max 0 0 0.00% 0.00%
Story1 107 215 pushx Min -0.4688 -0.0153 0.48% 0.02%
Story1 108 216 pushx Max 0 0 0.00% 0.00%
Story1 108 216 pushx Min -0.4688 -0.0149 0.48% 0.02%
Story1 109 218 pushx Max 0 0 0.00% 0.00%
Story1 109 218 pushx Min -0.4688 -0.0144 0.39% 0.00%
Story1 110 220 pushx Max 0 0 0.00% 0.01%
Story1 110 220 pushx Min -0.4688 -0.014 0.27% 0.01%
Story1 111 222 pushx Max 0 0 0.00% 0.01%
Story1 111 222 pushx Min -0.4688 -0.0136 0.15% 0.01%
Story1 112 224 pushx Max 0 0 0.06% 0.03%
Story1 112 224 pushx Min -0.4688 -0.0132 0.04% 0.00%
Story1 113 226 pushx Max 0 0 0.11% 0.05%
Story1 113 226 pushx Min -0.4688 -0.0129 0.00% 0.00%
Story1 114 228 pushx Max 0 0 0.14% 0.06%
Story1 114 228 pushx Min -0.4688 -0.0125 0.00% 0.00%
Story1 115 230 pushx Max 0 0 0.17% 0.08%
Story1 115 230 pushx Min -0.4688 -0.0122 0.00% 0.00%
Story1 116 232 pushx Max 0 0 0.21% 0.08%
Story1 116 232 pushx Min -0.4688 -0.0127 0.00% 0.00%
Story1 117 234 pushx Max 0 0 0.22% 0.09%
Story1 117 234 pushx Min -0.4688 -0.0132 0.00% 0.00%
Story1 118 236 pushx Max 0 0 0.21% 0.08%
Story1 118 236 pushx Min -0.4688 -0.0137 0.00% 0.00%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


107

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 119 238 pushx Max 0 0 0.19% 0.07%
Story1 119 238 pushx Min -0.4688 -0.0142 0.01% 0.00%
Story1 120 240 pushx Max 0 0 0.16% 0.05%
Story1 120 240 pushx Min -0.4688 -0.0147 0.07% 0.00%
Story1 121 242 pushx Max 0 0 0.12% 0.02%
Story1 121 242 pushx Min -0.4688 -0.0152 0.15% 0.00%
Story1 122 244 pushx Max 0 0 0.00% 0.00%
Story1 122 244 pushx Min -0.4688 -0.0157 0.59% 0.01%
Story1 123 247 pushx Max 0 0 0.00% 0.00%
Story1 123 247 pushx Min -0.4685 -0.0153 0.48% 0.01%
Story1 124 248 pushx Max 0 0 0.00% 0.00%
Story1 124 248 pushx Min -0.4685 -0.0149 0.48% 0.01%
Story1 125 250 pushx Max 0 0 0.00% 0.00%
Story1 125 250 pushx Min -0.4685 -0.0144 0.39% 0.02%
Story1 126 252 pushx Max 0 0 0.00% 0.00%
Story1 126 252 pushx Min -0.4685 -0.014 0.27% 0.02%
Story1 127 254 pushx Max 0 0 0.01% 0.01%
Story1 127 254 pushx Min -0.4685 -0.0136 0.14% 0.01%
Story1 128 256 pushx Max 0 0 0.07% 0.03%
Story1 128 256 pushx Min -0.4685 -0.0132 0.03% 0.00%
Story1 129 258 pushx Max 0 0 0.12% 0.05%
Story1 129 258 pushx Min -0.4685 -0.0129 0.00% 0.00%
Story1 130 260 pushx Max 0 0 0.16% 0.06%
Story1 130 260 pushx Min -0.4685 -0.0125 0.00% 0.00%
Story1 131 262 pushx Max 0 0 0.18% 0.08%
Story1 131 262 pushx Min -0.4685 -0.0122 0.00% 0.00%
Story1 132 264 pushx Max 0 0 0.21% 0.08%
Story1 132 264 pushx Min -0.4685 -0.0127 0.00% 0.00%
Story1 133 266 pushx Max 0 0 0.22% 0.09%
Story1 133 266 pushx Min -0.4685 -0.0132 0.00% 0.00%
Story1 134 268 pushx Max 0 0 0.21% 0.08%
Story1 134 268 pushx Min -0.4685 -0.0137 0.00% 0.00%
Story1 135 270 pushx Max 0 0 0.19% 0.07%
Story1 135 270 pushx Min -0.4685 -0.0142 0.02% 0.00%
Story1 136 272 pushx Max 0 0 0.16% 0.05%
Story1 136 272 pushx Min -0.4685 -0.0147 0.09% 0.00%
Story1 137 274 pushx Max 0 0 0.12% 0.03%
Story1 137 274 pushx Min -0.4685 -0.0152 0.17% 0.00%
Story1 138 276 pushx Max 0 0 0.00% 0.00%
Story1 138 276 pushx Min -0.4685 -0.0157 0.59% 0.02%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


108

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 139 279 pushx Max 0 0 0.00% 0.00%
Story1 139 279 pushx Min -0.4682 -0.0153 0.67% 0.02%
Story1 140 280 pushx Max 0 0 0.00% 0.00%
Story1 140 280 pushx Min -0.4682 -0.0149 0.67% 0.02%
Story1 141 282 pushx Max 0 0 0.00% 0.00%
Story1 141 282 pushx Min -0.4682 -0.0144 0.44% 0.03%
Story1 142 284 pushx Max 0 0 0.00% 0.00%
Story1 142 284 pushx Min -0.4682 -0.014 0.28% 0.02%
Story1 143 286 pushx Max 0 0 0.02% 0.01%
Story1 143 286 pushx Min -0.4682 -0.0136 0.14% 0.01%
Story1 144 288 pushx Max 0 0 0.09% 0.03%
Story1 144 288 pushx Min -0.4682 -0.0132 0.03% 0.00%
Story1 145 290 pushx Max 0 0 0.14% 0.05%
Story1 145 290 pushx Min -0.4682 -0.0129 0.00% 0.00%
Story1 146 292 pushx Max 0 0 0.17% 0.06%
Story1 146 292 pushx Min -0.4682 -0.0125 0.00% 0.00%
Story1 147 294 pushx Max 0 0 0.19% 0.08%
Story1 147 294 pushx Min -0.4682 -0.0122 0.00% 0.00%
Story1 148 296 pushx Max 0 0 0.21% 0.08%
Story1 148 296 pushx Min -0.4682 -0.0127 0.00% 0.00%
Story1 149 298 pushx Max 0 0 0.21% 0.09%
Story1 149 298 pushx Min -0.4682 -0.0132 0.00% 0.00%
Story1 150 300 pushx Max 0 0 0.21% 0.08%
Story1 150 300 pushx Min -0.4682 -0.0137 0.00% 0.00%
Story1 151 302 pushx Max 0 0 0.18% 0.07%
Story1 151 302 pushx Min -0.4682 -0.0142 0.03% 0.00%
Story1 152 304 pushx Max 0 0 0.15% 0.06%
Story1 152 304 pushx Min -0.4682 -0.0147 0.11% 0.00%
Story1 153 306 pushx Max 0 0 0.12% 0.04%
Story1 153 306 pushx Min -0.4682 -0.0152 0.21% 0.00%
Story1 154 308 pushx Max 0 0 0.00% 0.00%
Story1 154 308 pushx Min -0.4682 -0.0157 0.67% 0.02%

Tabla 10_Cuadro de Derivas en virtud de carga de empuje para Analisis no Lineal Modal

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


109

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
A partir de estos graficos se obtiene la secuencia de falla como
desplazamiento ultimo es de 0.48cm o 4.8 mm por lo cual que la capacidad
del edificio se encuentra ajustada para la solicitación sísmica exigida por la
norma colombiana de diseño y además se puede inferir que la
vulnerabilidad sísmica del edificio es baja

3.4) METODO CUALITATIVO

EVALUACION CUALITATIVA POR INDICADORES

La metodología propuesta en el presente trabajo se denomina “Evaluación


Cualitativa por Indicadores”, como ya se ha dicho, esta evaluación simplificada
tiene un carácter descriptivo, antes que analítico, toda vez que se fundamenta en
una inspección visual y en el registro de las características observables de las
edificaciones, con las cuales, y apoyado en el juicio y la opinión de expertos y en
fundamentos teóricos de la norma NSR - 10 se presume unas fallas y puntos
críticos y se suponen posibles comportamientos estructurales, para finalizar
dando a cada edificio un grado de exposición al riesgo sismico cualitativo, que
servirá como una caracterización preliminar de las edificaciones, insumo para
análisis y evaluaciones posteriores.

Este análisis cualitativo, debe apoyarse en la observación y registro de las


características y posibles elementos que puedan ser agentes de mal
comportamiento del sistema estructural ante una solicitación sísmica. Para
facilitar el estudio de estos componentes, se plantea la incorporación de unos
“indicadores” que relacionen estas particularidades de forma separada y faciliten
su evaluación de forma independiente. En la observación de cada uno de estos
parámetros, se da un valor numérico a cada una de estos indicadores
dependiendo de las características observadas y de la importancia que
representan en función del comportamiento de la totalidad del sistema
estructural. Al finalizar, la evaluación cualitativa global del edificio, se obtendrá
del promedio de estos valores y su relación con un rango de análisis que
determinará si las edificaciones presentan una exposición Alta, Moderada, o
Baja.

El resultado obtenido de este ejercicio de análisis, no debe considerarse como


resultado definitivo del estado real de las edificaciones en cuanto a su
vulnerabilidad sismica, se trata de una aproximación empírico analítica de
carácter cualitativo, sustentada en la evaluación por indicadores establecidos
desde categorías contempladas por la Norma Sismo Resistente Colombiana

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


110

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
NSR – 10, cuya ponderación o grado de importancia se basa en la opinión de
expertos y en fundamentos teóricos de la norma, con el ánimo de estimar un
posible escenario de vulnerabilidad, teniendo en cuenta que el evento sísmico
esperado para las zonas de amenaza sísmica alta del Departamento de Nariño
es de 0.25 g (NSR – 10).

Metodológicamente se trabaja desde un formulario tipo Encuesta, con preguntas


cerradas de única respuesta organizado en indicadores que establecen la
sumatoria y cuantificación numérica ascendente de cada una de las variables.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


111

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
EVALUACIÓN CUALITATIVA POR INDICADORES

LEVANTAMIENTO E INFORME DEL ESTADO ACTUAL PARA LAS ADECUACIONES DE LA INFRAESTRUCTURA DE


CUBIERTA DEL CENTRO NACIONAL DE ATENCION EN FRONTERA CENAF
NOMBRE INSTITUCIÓN CENAF
DIRECCIÓN RUMICHACA
CÓDIGO DE INSPECCIÓN VULNERABILIDAD MODERADO

Sistema Constructivo Estructuras Metálicas de cubiertas

Indicadores de Vulnerabilidad Grado de Importancia


Epoca de Construcción Respuesta Severidad 5%
Antes de 1984 0 0 0 0
A Entre 1984 a 1998 0 0 0 0
Entre 1998 a 2010 1 1 0.25 0.0125
Despues de 2010 0 0 0 0
TOTAL 0.0125

Configuración del pórtico Respuesta 45%

B Numero de apoyos 2 peralte minimo


Luz maxima entre apoyos (m) 21 1.05
Peralte de sección transversal existente (m) 0.7 2 0.5 0.225
TOTAL 0.225
Seccion de elementos Respuesta Calificación 10%
Angulos de Acero 0 0 0 -
Perfiles en "C" 0 0 0 -
D
Perfiles en Cajon 0 0 0 -
Perfiles Cuadrados 1 2 0.5 0.05
Varilla Lisa 0 0 0 -
TOTAL 0.05
Tipo de conexión entre elementos Respuesta Severidad 5%
Pernada 0 0 0 0
E Soldadas 1 2 0.5 0.025
Remachada 0 0 0
Amarradas 0 0 0
TOTAL 0.03

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


112

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Tipo de Apoyos Respuesta Severidad 5%
F Cumple con Norma 0 0 0 0

No cumple con Norma 1 4 1 0.05

TOTAL 0.05
Modificaciones en la Edificación Respuesta Severidad 5%
G Estructurales sin Código 0 0 0 0
No ha Presentado Modificaciones 1 0 0

TOTAL -

Deflexiones Respuesta Severidad 5%


Sobre 1 elemento 0 0 0 0
Sobre 2 elementos 0 0 0
H
Sobre 3 elementos 0 0 0
Mas de 4 elementos 0 0 0 0

No presenta deflexiones 1 0 0 0

TOTAL -

Corrosión y desintegración Respuesta Severidad 5%


Sobre 1 elemento 0 0 0 0
Sobre 2 elementos 0 0 0
I
Sobre 3 elementos 0 0 0
Mas de 4 elementos 0 0 0 0

No presenta corrosión 1 0 0 0
TOTAL -

Pandeo y Fallamiento Respuesta Severidad 5%


Sobre 1 elemento 0 0 0 0
Sobre 2 elementos 0 0 0
J
Sobre 3 elementos 0 0 0
Mas de 4 elementos 0 0 0 0

No presenta pandeo 1 0 0 0

TOTAL -

Pérdida de verticalidad Respuesta Severidad 5%


Sobre 1 elemento 0 0 0 0
Sobre 2 elementos 0 0 0
K
Sobre 3 elementos 0 0 0
Mas de 4 elementos 0 0 0 0

No presenta perdida de verticalidad 1 0 0 0

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


113

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
TOTAL -

Dilataciones Respuesta Severidad 5%


No cumple Dilataciones 0 0 0 0
L
No Presenta Dilataciones 0 0 0 0
Edificacion Aislada / cumple Dilataciones 0 0
TOTAL 0
INDICADOR DE VULNERABILIDAD CUALITATIVA 0.36

Entre el rango de valores Menores o iguales al .3


Grado de Vulnerabilidad Leve Continua en operación

Entre el rango de valores mayores a


a .3 y el valor menor o igual a .7
Se Requiere un estudio detallado
Grado de Vulnerabilidad Moderada

Entre el rango de valores mayores


a .7 e igual a 1
Se requiere un estudio de patologia y vulnerabilidad sismica que
permitan establecer la conveniencia o no de reforzar o
repotenciar la estructura

Grado de Vulnerabilidad Severa

Descripción Valor Severidad

No incide en la valoración de vulnerabilidad 0 Nula

Incide escasamente entre un


1% a 25% de la edificacion 1 Baja

Incide entre un 25% a 50% de la


caracterizaciónen la edificacion 2 Media

Incide entre un 51% a 75% de la


caracterización de la edificacion 3 Alta

Incide entre un 75% a 100% de la


caracterización de la edificacion 4 Muy alta

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


114

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Pese a calificar con un ponderado de 0.36 para determinar el grado de exposición
al riesgo sismico, la edificación presenta condiciones favorables para su
estabilidad y la resistencia de solicitaciones Sismicas. Es conveniente
recomendar un estudio de Vulnerabilidad de mayor detalle para futuras
intervenciones particularmente sobre el sector de la Zona B y C en el que se han
previsto algunas particularidades en temas de apoyo y conexión entre elementos.

El valor de 0.36. tan cercano a 0.3 que permite la continuidad del funcionamiento
de la edificación, viabiliza el cambio de cubierta para reducción de cargas y mejor
desempeño del edificio.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


115

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
3.5) EVALUACIÓN DE ANCLAJES Y APOYOS.

Para la determinación del estado de anclajes y apoyos, se analizará por las zonas
de cubiertas, pudiendo determinar un estado basado en la inspección visual y
registro fotográfico.

a) ZONA A ACCESO PEATONAL

En esta zona, los anclajes entre elementos de cubierta de cuerdas superior,


inferior y celosia se conectan desde platinas de conexión que sirven de soporte
para su fijación mediante un perno de ½” pulgada ajustado con tuerca. Se aprecia
que la sujeción de estas platinas se desarrolla mediante cordones de soldadura
por punto de arco y se estima una resistencia aproximada a los 60000 psi.

La estructura de Cubierta se asienta sobre columnas de acero conformadas por


angulos metalicos, en cuya transición se encuentra una placa de acero soldada
de sección generalmente de 10cmx10cmx6mm o 15cmx15cmx6mm en el que
reposa el nudo conector entre cuerdas y diagonales.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


116

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 39_Registro fotográfico Conexión Columna en Angulo y pilar en concreto (Fuente: propia)

Como dato importante, debe señalarse que no existe una platina de transición,
entre la estructura de apoyo de Cubierta conformada por una columna de
aproximadamente sección transversal de 25cm x 25cm con angulos de 2”x2”
3mm entre parales, tirantes y diagonales. y el Pedestal de Concreto de sección
transversal de 50x50cm y 50 cm de peralte.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


117

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Dicha condición supone un punto critico de falla especialmente por cortante entre
ambos sistemas estructurales justamente en la unión de dichos elementos,
pudiendo generar fatiga y efecto de columna corta en este sistema.

b) ZONA B ATENCION AL PUBLICO

En esta zona, los anclajes entre elementos de cubierta de cuerdas superior,


inferior y celosia se conectan desde platinas de conexión que sirven de soporte
para su fijación mediante un perno de ½” pulgada ajustado con tuerca. Se aprecia
que la sujeción de estas platinas se desarrolla mediante cordones de soldadura
por punto de arco y se estima una resistencia aproximada a los 60000 psi.

La estructura de Cubierta se asienta sobre pilares de concreto, notándose una


transición entre el apoyo y la superestructura mediante el desarrollo de un apoyo
conformado por 4 Angulos metalicos que rematan sobre una Platina Base que
sirve de soporte al Nudo. Sin embargo y debido a la configuración de los porticos
de concreto y la modulación estructural de la cubierta, no existe coincidencia en
el centro exacto de dichos elementos, por lo cual algunos de estos se encuentran
desplazados desarrollando apoyos excéntricos o en algunos casos sin
continuidad hacia el suelo.

Figura 40_Registro fotográfico Conexión Columna en Angulo y pilar en concreto (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


118

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 41_Registro fotográfico Conexión de nudo apoyado sobre Muro (Fuente: propia)

Figura 42_Registro fotográfico Conexión de nudo de Cubierta, Platina de Conexión y pilar en Concreto y
Angulo (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


119

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Es importante resaltar que debido a la no coincidencia de ejes entre los pórticos
de concreto y los nudos de cubierta el desarrollo de apoyos se establece casi de
manera artesanal, notándose la improvisación en cuanto a criterios para
sustentar la estructura y transmitira adecuadamente al suelo. Esto se demostró
en el análisis no Lineal en donde los elementos que presentan falla, son aquellos
cercanos a los nodos de apoyo, presentándose fatigas y secuencias de falla
particularmente de los cordones inferiores.

c) ZONA C OFICINAS
En esta zona, los anclajes entre elementos de cubierta de cuerdas superior,
inferior y celosia se conectan desde platinas de conexión que sirven de soporte
para su fijación mediante un perno de ½” pulgada ajustado con tuerca. Se aprecia
que la sujeción de estas platinas se desarrolla mediante cordones de soldadura
por punto de arco y se estima una resistencia aproximada a los 60000 psi.

La estructura de Cubierta se asienta sobre pilares de concreto, notándose una


transición entre el apoyo y la superestructura mediante el desarrollo de un apoyo
conformado por 4 Angulos metalicos que rematan sobre una Platina Base que
sirve de soporte al Nudo.

De igual manera, existe un punto de conexión con la cubierta de la zona B para


sustentarse desde una celosia de aproximadamente 2.05 metros de alto y 22.75
metros de largo, conformando una configuración tipo Warren, trabajando un
doble angulo de 2” entre sus cordones superiores, Inferiores y Diagonales,
sujetos por Platinas cuadradas chafllaneadas en dos de sus esquinas, de sección
25cm x 25cm y 4 mm de espesor.

Sin embargo y debido a la configuración de los porticos de concreto y la


modulación estructural de la cubierta, no existe coincidencia en el centro exacto
de dichos elementos, por lo cual algunos de estos se encuentran desplazados
desarrollando apoyos excéntricos o en algunos casos sin continuidad hacia el
suelo.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


120

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 43_Registro fotográfico Conexión de nudo de Cubierta, Celosia, y columna en Angulo entre
cubiertas Zona B y C (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


121

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 44_Discontinuidad de nudo de Cubierta respecto a su eje de apoyo Zona B (Fuente: propia)

Figura 45_Cercania de nudo de Cubierta respecto a su eje de apoyo Zona B (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


122

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
En este caso de cubierta, existe una particularidad entorno a la definición de
apoyos, en tanto se evidencia un cordon inferior perimetral anclado a los
elementos de concreto que trata de subsanar la necesidad de apoyo entre los
nudos de la cubierta y la superestructura, por lo cual, existe un apoyo indirecto
que transmite su carga hacia los nudos. Por ende se mantiene dicha
discotinuidad y se prevee una falla de los elementos cercanos a estos nudos

d) ZONA D ESCALERAS

En esta zona, los anclajes entre elementos de cubierta de cuerdas superior,


inferior y celosia se conectan desde platinas de conexión que sirven de soporte
para su fijación mediante un perno de ½” pulgada ajustado con tuerca. Se aprecia
que la sujeción de estas platinas se desarrolla mediante cordones de soldadura
por punto de arco y se estima una resistencia aproximada a los 60000 psi.

La estructura de Cubierta se asienta directamente hacia la superestructura por


placas base de sección generalmente de 10cmx10cmx6mm en el que reposa el
nudo conector entre cuerdas y diagonales. No obstante también se observa la
proyección de un nudo conector para soporte de la estructura directamente sobre
la columna en concreto sin elemento de transición.

Figura 46_Coincidencia de nudo (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


123

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Debido a sus dimensiones, la estructura puede considerarse como
suficientemente apoyada, en donde no se evidencian problemas de
discontinuidad o excentricidad, permitiendo una correcta transmisión de cargas
con la estructura y el suelo.

e) ZONA E PUENTE

La estructura de cubierta se soporta sobre los pilares en concreto o mampostería


sobre una platina base de 10cm x 10 cm x 3mm de espesor con 6 pernos de ½”
y sobre el Muro con Platinas de conexión de 15cm x 15 cm x 3mm. En total son
2 apoyos sobre platinas en losa y 7 apoyos sobre pared

Figura 47_Apoyos de Pared Zona E Puente (Fuente: propia)

Pese a sus dimensiones, la cubierta encuentra particularmente en los apoyos


de Pared cierta improvisación en su fijación, por lo cual tal y como se demostró
en el análisis cuantitativo, los elementos que presentan falla son aquellos que
se encuentran cerca al nudo, presentándose fatigas, agrietamientos y
secuencias de falla que pueden comprometer la estabilidad de la edificación.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


124

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 48_Apoyos de losa E Puente (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


125

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
3.6) EVALUACIÓN DE CORROSIÓN.

Cabe resaltar que el nivel de corrosión de las cinco estructuras de cubierta es


bueno, en tanto dicha edificación presenta una capa considerable de
anticorrosivo y pintura en esmalte. No obstante, se presentan algunas
oxidaciónes importantes sobre los Canales de desague y algunas diagonales y
particularmente sobre el tramo comprendido entre los ejes 5 y 6 y ejes A y B de
la Zona A de acceso peatonal, debido al desplazamiento de bajantes y desagues
rotos. Como Inspección visual y dada su limitación, este estudio no permite
establecer si existen oxidaciones a nivel microscopico debido a la magnitud y
limitantes del estudio. Sin embargo, la revisión general de todos los sistemas de
cubierta permite establecer que no existen factores de corrosividad o presencia
de patologías que alteren el buen comportamiento estructural de la edificación.

Es importante resaltar que, pese a su buen estado, se hace evidente la falta de


mantenimiento, limpieza y pintura que las estructuras presentan, habiendo
escenarios de eflorescencias por contaminación Luminica y ambiental por la
exposición al frecuente smoke del transito de vehiculos

Figura 49_Corrosividad sobre canales, Zona B Atención (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


126

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 50_Ausencia de Mantenimiento y concentración de costras de polvo sobre nudos, Zona a Acceso
Peatonal (Fuente: propia)

Figura 51_Corrosión superficial debido a la exposición de lluvia lateral, Luminosidad y exposición al


Smoke, zona C Oficinas (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


127

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Para confirmar el estado de corrosividad, se procedió desde métodos manuales,
limpieza, escarificación, pulido y aplicación de Fenolftaleina para verificar el
grado de Acidez o alcalinidad que pudieran presentar la estructura,
particularmente las soldaduras y elementos de unión.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


128

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF
129

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 52_Proceso de Escarificación Manual, limpieza y pulido con Thiner (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


130

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 53_Aplicación de Fenolftaleina (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


131

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 54_Resultado de ensayo de Fenolftaleina Sobre Columna Zona A Acceso peatonal (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


132

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 55_Resultado de ensayo de Fenolftaleina Sobre Celosia entre Zona B y C (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


133

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Como puede apreciarse, la Soldadura y el Perfil metálico se encuentra en
suficientes condiciones respecto a su nivel de acidez y alcalinidad. Existen
algunos rastros de escoria por tratarse de una soldadura en Campo pero no
compromete la integridad del material estructural.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


134

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
4) CONCLUSIONES Y RECOMENDACIONES.

Debe considerarse el propósito de este estudio, que trata de determinar si el


cambio de material de cubierta y la proyección de una estructura de soporte para
una teja de Policarbonato alveolar, tendrá impactos sobre la estabilidad e
integridad a nivel estructural, además de recomendar el manejo y conducción de
aguas lluvias.

4.1) CONCLUSION Y RECOMENDACIÓN PARA LA ESTABILIDAD


GENERAL DE LA EDIFICACIÓN Y PROYECCIÓN DE CUBIERTA

Para dicho fin aprovechando la modelación en el análisis, puede considerarse


una reducción de cargas y analizar el comportamiento de la estructura. Se
mantienen los mismos parámetros de análisis, con la única modificación del
cuadro de cargas y posibles puntales soportados en la estructura existente.

O Carga muerta
Peso de cubierta
Canal en Lamina galvanizada
3.6 kg/m2
calibre 22
Lamina en policarbonato 8 mm 2.73 kg/m2
Apoyos intermedios de
estructura para pendiente de 6.5 Kg/m2
canal

Total 12.85 kg/m2


O Carga viva

2.3.1 VIVA SEGÚN CODIGO (NSR-10) B.4.2 50 kg/m2

• Carga de granizo
2.3.1 GRANIZO SEGÚN CODIGO (NSR-10) B.4.8.3.2 100 kg/m2

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


135

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 56_Cambio de carga Muerta de 22.5kg a 13 kgm. Reducción del 42% (Fuente: propia)

A continuación se presentan los resultados tras la reducción de cargas muertas


en el análisis de cubierta:

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


136

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 57_Relación de Deflexiones Cordon Inferior (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


137

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 58_Relación de Deflexiones Cordon Superior (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


138

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Figura 59_Relación de Deflexiones e índices de Capacidad Cordon Superior (Fuente: propia)

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


139

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
TABLE: Steel Frame Summary - AISC
LRFD 93
Labe Unique Design Design PMM PMM M Major
Story l Name Type Section Status Combo Ratio Ratio

Story1 B1 81F Beam tubo No Message Comb5(C) 0.08 0.08

Story1 B1 Beam tubo No Message Comb11(T) 0.075 0.075

Story1 B2 820 Beam tubo No Message Comb5(C) 0.071 0.071

Story1 B2 Beam tubo No Message Comb11(T) 0.067 0.067

Story1 B3 821 Beam tubo No Message Comb5(C) 0.071 0.071

Story1 B3 Beam tubo No Message Comb11(T) 0.063 0.063

Story1 B4 822 Beam tubo No Message Comb5(C) 0.072 0.072

Story1 B4 Beam tubo No Message Comb11(T) 0.068 0.068

Story1 B5 823 Beam tubo No Message Comb5(C) 0.07 0.07

Story1 B5 Beam tubo No Message Comb11(T) 0.066 0.066

Story1 B6 824 Beam tubo No Message Comb5(C) 0.073 0.073

Story1 B6 Beam tubo No Message Comb11(T) 0.069 0.069

Story1 B7 825 Beam tubo No Message Comb5(C) 0.08 0.08

Story1 B7 Beam tubo No Message Comb11(T) 0.058 0.058

Story1 B8 826 Beam tubo No Message Comb5(C) 0.08 0.08

Story1 B8 Beam tubo No Message Comb11(T) 0.033 0.033

Story1 B9 827 Beam tubo No Message Comb5(C) 0.073 0.073

Story1 B9 Beam tubo No Message Comb11(T) 0.063 0.063

Story1 B10 828 Beam tubo No Message Comb4(C) 0.07 0.07

Story1 B10 Beam tubo No Message Comb11(T) 0.066 0.066

Story1 B11 829 Beam tubo No Message Comb5(C) 0.07 0.07

Story1 B11 Beam tubo No Message Comb11(T) 0.055 0.055

Story1 B12 82A Beam tubo No Message Comb5(C) 0.071 0.071

Story1 B12 Beam tubo No Message Comb11(T) 0.067 0.067

Story1 B13 82B Beam tubo No Message Comb5(C) 0.079 0.079

Story1 B13 Beam tubo No Message Comb11(T) 0.032 0.032

Story1 B14 82C Beam tubo No Message Comb4(C) 0.147 0.147

Story1 B14 Beam tubo No Message Comb11(T) 0.112 0.112

Story1 B15 82D Beam tubo No Message Comb4(C) 0.129 0.129

Story1 B15 Beam tubo No Message Comb11(T) 0.122 0.122

Story1 B16 82E Beam tubo No Message Comb5(C) 0.134 0.134

Story1 B16 Beam tubo No Message Comb11(T) 0.118 0.118

Story1 B17 82F Beam tubo No Message Comb5(C) 0.135 0.135

Story1 B17 Beam tubo No Message Comb11(T) 0.123 0.123

Story1 B18 830 Beam tubo No Message Comb5(C) 0.136 0.136

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


140

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 B18 Beam tubo No Message Comb11(T) 0.121 0.121

Story1 B19 831 Beam tubo No Message Comb5(C) 0.131 0.131

Story1 B19 Beam tubo No Message Comb11(T) 0.125 0.125

Story1 B20 832 Beam tubo No Message Comb5(C) 0.147 0.147

Story1 B20 Beam tubo No Message Comb11(T) 0.14 0.14

Story1 B21 833 Beam tubo No Message Comb5(C) 0.148 0.148

Story1 B21 Beam tubo No Message Comb11(T) 0.078 0.078

Story1 B22 834 Beam tubo No Message Comb5(C) 0.133 0.133

Story1 B22 Beam tubo No Message Comb11(T) 0.107 0.107

Story1 B23 835 Beam tubo No Message Comb5(C) 0.133 0.133

Story1 B23 Beam tubo No Message Comb11(T) 0.127 0.127

Story1 B24 836 Beam tubo No Message Comb5(C) 0.133 0.133

Story1 B24 Beam tubo No Message Comb11(T) 0.119 0.119

Story1 B25 837 Beam tubo No Message Comb4(C) 0.129 0.129

Story1 B25 Beam tubo No Message Comb11(T) 0.121 0.121

Story1 B26 838 Beam tubo No Message Comb4(C) 0.147 0.147

Story1 B26 Beam tubo No Message Comb11(T) 0.14 0.14

Story1 B27 839 Beam tubo No Message Comb4(C) 0.146 0.146

Story1 B27 Beam tubo No Message Comb11(T) 0.112 0.112

Story1 B28 83A Beam tubo No Message Comb4(C) 0.13 0.13

Story1 B28 Beam tubo No Message Comb11(T) 0.123 0.123

Story1 B29 83B Beam tubo No Message Comb4(C) 0.134 0.134

Story1 B29 Beam tubo No Message Comb11(T) 0.117 0.117

Story1 B30 83C Beam tubo No Message Comb5(C) 0.146 0.146

Story1 B30 Beam tubo No Message Comb11(T) 0.122 0.122

Story1 B31 83D Beam tubo No Message Comb5(C) 0.147 0.147

Story1 B31 Beam tubo No Message Comb11(T) 0.113 0.113

Story1 B32 83E Beam tubo No Message Comb5(C) 0.135 0.135

Story1 B32 Beam tubo No Message Comb11(T) 0.128 0.128

Story1 B33 83F Beam tubo No Message Comb5(C) 0.136 0.136

Story1 B33 Beam tubo No Message Comb11(T) 0.13 0.13

Story1 B34 840 Beam tubo No Message Comb5(C) 0.085 0.085

Story1 B34 Beam tubo No Message Comb11(T) 0.056 0.056

Story1 B35 841 Beam tubo No Message Comb4(C) 0.061 0.061

Story1 B35 Beam tubo No Message Comb11(T) 0.058 0.058

Story1 B36 842 Beam tubo No Message Comb5(C) 0.061 0.061

Story1 B36 Beam tubo No Message Comb11(T) 0.058 0.058

Story1 B37 843 Beam tubo No Message Comb5(C) 0.059 0.059

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


141

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 B37 Beam tubo No Message Comb11(T) 0.058 0.058

Story1 B38 844 Beam tubo No Message Comb5(C) 0.061 0.061

Story1 B38 Beam tubo No Message Comb11(T) 0.058 0.058

Story1 B39 845 Beam tubo No Message Comb4(C) 0.064 0.064

Story1 B39 Beam tubo No Message Comb11(T) 0.061 0.061

Story1 B40 846 Beam tubo No Message Comb5(C) 0.064 0.064

Story1 B40 Beam tubo No Message Comb11(T) 0.061 0.061

Story1 B41 847 Beam tubo No Message Comb5(C) 0.097 0.097

Story1 B41 Beam tubo No Message Comb11(T) 0.057 0.057

Story1 B42 848 Beam tubo No Message Comb5(C) 0.138 0.138

Story1 B42 Beam tubo No Message Comb11(T) 0.109 0.109

Story1 B43 849 Beam tubo No Message Comb5(C) 0.146 0.146

Story1 B43 Beam tubo No Message Comb11(T) 0.138 0.138

Story1 B44 84A Beam tubo No Message Comb4(C) 0.143 0.143

Story1 B44 Beam tubo No Message Comb11(T) 0.122 0.122

Story1 B45 84B Beam tubo No Message Comb4(C) 0.132 0.132

Story1 B45 Beam tubo No Message Comb11(T) 0.117 0.117

Story1 B46 84C Beam tubo No Message Comb4(C) 0.131 0.131

Story1 B46 Beam tubo No Message Comb11(T) 0.124 0.124

Story1 B47 84D Beam tubo No Message Comb4(C) 0.147 0.147

Story1 B47 Beam tubo No Message Comb11(T) 0.14 0.14

Story1 B48 84E Beam tubo No Message Comb4(C) 0.08 0.08

Story1 B48 Beam tubo No Message Comb11(T) 0.058 0.058

Story1 B49 84F Beam tubo No Message Comb4(C) 0.071 0.071

Story1 B49 Beam tubo No Message Comb11(T) 0.059 0.059

Story1 B50 850 Beam tubo No Message Comb4(C) 0.095 0.095

Story1 B50 Beam tubo No Message Comb11(T) 0.089 0.089

Story1 B51 851 Beam tubo No Message Comb4(C) 0.148 0.148

Story1 B51 Beam tubo No Message Comb11(T) 0.112 0.112

Story1 B52 852 Beam tubo No Message Comb4(C) 0.147 0.147

Story1 B52 Beam tubo No Message Comb11(T) 0.14 0.14

Story1 B53 853 Beam tubo No Message Comb5(C) 0.137 0.137

Story1 B53 Beam tubo No Message Comb11(T) 0.115 0.115

Story1 B54 854 Beam tubo No Message Comb4(C) 0.132 0.132

Story1 B54 Beam tubo No Message Comb11(T) 0.113 0.113

Story1 B55 855 Beam tubo No Message Comb4(C) 0.129 0.129

Story1 B55 Beam tubo No Message Comb11(T) 0.123 0.123

Story1 B56 856 Beam tubo No Message Comb4(C) 0.124 0.124

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


142

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 B56 Beam tubo No Message Comb11(T) 0.119 0.119

Story1 B57 857 Beam tubo No Message Comb5(C) 0.121 0.121

Story1 B57 Beam tubo No Message Comb11(T) 0.113 0.113

Story1 B58 858 Beam tubo No Message Comb5(C) 0.119 0.119

Story1 B58 Beam tubo No Message Comb11(T) 0.114 0.114

Story1 B59 859 Beam tubo No Message Comb5(C) 0.121 0.121

Story1 B59 Beam tubo No Message Comb11(T) 0.116 0.116

Story1 B60 85A Beam tubo No Message Comb4(C) 0.124 0.124

Story1 B60 Beam tubo No Message Comb11(T) 0.112 0.112

Story1 B61 85B Beam tubo No Message Comb4(C) 0.128 0.128

Story1 B61 Beam tubo No Message Comb11(T) 0.113 0.113

Story1 B62 85C Beam tubo No Message Comb4(C) 0.135 0.135

Story1 B62 Beam tubo No Message Comb11(T) 0.128 0.128

Story1 B63 85D Beam tubo No Message Comb4(C) 0.137 0.137

Story1 B63 Beam tubo No Message Comb11(T) 0.13 0.13

Story1 B64 85E Beam tubo No Message Comb4(C) 0.146 0.146

Story1 B64 Beam tubo No Message Comb11(T) 0.138 0.138

Story1 B65 85F Beam tubo No Message Comb4(C) 0.146 0.146

Story1 B65 Beam tubo No Message Comb11(T) 0.139 0.139

Story1 B66 860 Beam tubo No Message Comb4(C) 0.092 0.092

Story1 B66 Beam tubo No Message Comb11(T) 0.086 0.086

Story1 B67 861 Beam tubo No Message Comb4(C) 0.072 0.072

Story1 B67 Beam tubo No Message Comb11(T) 0.059 0.059

Story1 B68 862 Beam tubo No Message Comb4(C) 0.082 0.082

Story1 B68 Beam tubo No Message Comb11(T) 0.031 0.031

Story1 B69 863 Beam tubo No Message Comb4(C) 0.165 0.165

Story1 B69 Beam tubo No Message Comb11(T) 0.109 0.109

Story1 B70 864 Beam tubo No Message Comb4(C) 0.15 0.15

Story1 B70 Beam tubo No Message Comb11(T) 0.115 0.115

Story1 B71 865 Beam tubo No Message Comb4(C) 0.137 0.137

Story1 B71 Beam tubo No Message Comb11(T) 0.13 0.13

Story1 B72 866 Beam tubo No Message Comb4(C) 0.132 0.132

Story1 B72 Beam tubo No Message Comb11(T) 0.114 0.114

Story1 B73 867 Beam tubo No Message Comb4(C) 0.127 0.127

Story1 B73 Beam tubo No Message Comb11(T) 0.122 0.122

Story1 B74 868 Beam tubo No Message Comb4(C) 0.124 0.124

Story1 B74 Beam tubo No Message Comb11(T) 0.112 0.112

Story1 B75 869 Beam tubo No Message Comb4(C) 0.121 0.121

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


143

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 B75 Beam tubo No Message Comb11(T) 0.113 0.113

Story1 B76 86A Beam tubo No Message Comb5(C) 0.119 0.119

Story1 B76 Beam tubo No Message Comb11(T) 0.114 0.114

Story1 B77 86B Beam tubo No Message Comb4(C) 0.121 0.121

Story1 B77 Beam tubo No Message Comb11(T) 0.113 0.113

Story1 B78 86C Beam tubo No Message Comb4(C) 0.124 0.124

Story1 B78 Beam tubo No Message Comb11(T) 0.118 0.118

Story1 B79 86D Beam tubo No Message Comb4(C) 0.128 0.128

Story1 B79 Beam tubo No Message Comb11(T) 0.113 0.113

Story1 B80 86E Beam tubo No Message Comb4(C) 0.132 0.132

Story1 B80 Beam tubo No Message Comb11(T) 0.114 0.114

Story1 B81 86F Beam tubo No Message Comb4(C) 0.137 0.137

Story1 B81 Beam tubo No Message Comb11(T) 0.115 0.115

Story1 B82 870 Beam tubo No Message Comb4(C) 0.151 0.151

Story1 B82 Beam tubo No Message Comb11(T) 0.115 0.115

Story1 B83 871 Beam tubo No Message Comb4(C) 0.163 0.163

Story1 B83 Beam tubo No Message Comb11(T) 0.109 0.109

Story1 B84 872 Beam tubo No Message Comb4(C) 0.165 0.165

Story1 B84 Beam tubo No Message Comb11(T) 0.157 0.157

Story1 B85 873 Beam tubo No Message Comb4(C) 0.149 0.149

Story1 B85 Beam tubo No Message Comb11(T) 0.142 0.142

Story1 B86 874 Beam tubo No Message Comb4(C) 0.136 0.136

Story1 B86 Beam tubo No Message Comb11(T) 0.116 0.116

Story1 B87 875 Beam tubo No Message Comb4(C) 0.132 0.132

Story1 B87 Beam tubo No Message Comb11(T) 0.125 0.125

Story1 B88 876 Beam tubo No Message Comb4(C) 0.127 0.127

Story1 B88 Beam tubo No Message Comb11(T) 0.113 0.113

Story1 B89 877 Beam tubo No Message Comb4(C) 0.124 0.124

Story1 B89 Beam tubo No Message Comb11(T) 0.112 0.112

Story1 B90 878 Beam tubo No Message Comb4(C) 0.121 0.121

Story1 B90 Beam tubo No Message Comb11(T) 0.116 0.116

Story1 B91 879 Beam tubo No Message Comb4(C) 0.119 0.119

Story1 B91 Beam tubo No Message Comb11(T) 0.114 0.114

Story1 B92 87A Beam tubo No Message Comb4(C) 0.121 0.121

Story1 B92 Beam tubo No Message Comb11(T) 0.116 0.116

Story1 B93 87B Beam tubo No Message Comb4(C) 0.124 0.124

Story1 B93 Beam tubo No Message Comb11(T) 0.118 0.118

Story1 B94 87C Beam tubo No Message Comb4(C) 0.127 0.127

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


144

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 B94 Beam tubo No Message Comb11(T) 0.122 0.122

Story1 B95 87D Beam tubo No Message Comb4(C) 0.132 0.132

Story1 B95 Beam tubo No Message Comb11(T) 0.114 0.114

Story1 B96 87E Beam tubo No Message Comb4(C) 0.136 0.136

Story1 B96 Beam tubo No Message Comb11(T) 0.116 0.116

Story1 B97 87F Beam tubo No Message Comb4(C) 0.15 0.15

Story1 B97 Beam tubo No Message Comb11(T) 0.114 0.114

Story1 B98 880 Beam tubo No Message Comb4(C) 0.164 0.164

Story1 B98 Beam tubo No Message Comb11(T) 0.11 0.11

Story1 B99 881 Beam tubo No Message Comb4(C) 0.152 0.152

Story1 B99 Beam tubo No Message Comb11(T) 0.145 0.145


B10
Story1 0 882 Beam tubo No Message Comb4(C) 0.138 0.138
B10
Story1 0 Beam tubo No Message Comb11(T) 0.122 0.122
B10
Story1 1 883 Beam tubo No Message Comb4(C) 0.134 0.134
B10
Story1 1 Beam tubo No Message Comb11(T) 0.118 0.118
B10
Story1 2 884 Beam tubo No Message Comb4(C) 0.131 0.131
B10
Story1 2 Beam tubo No Message Comb11(T) 0.125 0.125
B10
Story1 3 885 Beam tubo No Message Comb4(C) 0.127 0.127
B10
Story1 3 Beam tubo No Message Comb11(T) 0.113 0.113
B10
Story1 4 886 Beam tubo No Message Comb4(C) 0.124 0.124
B10
Story1 4 Beam tubo No Message Comb11(T) 0.118 0.118
B10
Story1 5 887 Beam tubo No Message Comb4(C) 0.121 0.121
B10
Story1 5 Beam tubo No Message Comb11(T) 0.115 0.115
B10
Story1 6 888 Beam tubo No Message Comb5(C) 0.119 0.119
B10
Story1 6 Beam tubo No Message Comb11(T) 0.114 0.114
B10
Story1 7 889 Beam tubo No Message Comb4(C) 0.121 0.121
B10
Story1 7 Beam tubo No Message Comb11(T) 0.112 0.112
B10
Story1 8 88A Beam tubo No Message Comb4(C) 0.124 0.124
B10
Story1 8 Beam tubo No Message Comb11(T) 0.112 0.112
B10
Story1 9 88B Beam tubo No Message Comb4(C) 0.127 0.127
B10
Story1 9 Beam tubo No Message Comb11(T) 0.113 0.113
B11
Story1 0 88C Beam tubo No Message Comb4(C) 0.131 0.131
B11
Story1 0 Beam tubo No Message Comb11(T) 0.115 0.115
B11
Story1 1 88D Beam tubo No Message Comb4(C) 0.134 0.134
B11
Story1 1 Beam tubo No Message Comb11(T) 0.118 0.118
B11
Story1 2 88E Beam tubo No Message Comb4(C) 0.138 0.138
B11
Story1 2 Beam tubo No Message Comb11(T) 0.122 0.122
B11
Story1 3 88F Beam tubo No Message Comb4(C) 0.152 0.152

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


145

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B11
Story1 3 Beam tubo No Message Comb11(T) 0.111 0.111
B11
Story1 4 890 Beam tubo No Message Comb5(C) 0.165 0.165
B11
Story1 4 Beam tubo No Message Comb11(T) 0.073 0.073
B11
Story1 5 891 Beam tubo No Message Comb4(C) 0.149 0.149
B11
Story1 5 Beam tubo No Message Comb11(T) 0.116 0.116
B11
Story1 6 892 Beam tubo No Message Comb5(C) 0.137 0.137
B11
Story1 6 Beam tubo No Message Comb11(T) 0.116 0.116
B11
Story1 7 893 Beam tubo No Message Comb4(C) 0.132 0.132
B11
Story1 7 Beam tubo No Message Comb11(T) 0.126 0.126
B11
Story1 8 894 Beam tubo No Message Comb4(C) 0.127 0.127
B11
Story1 8 Beam tubo No Message Comb11(T) 0.112 0.112
B11
Story1 9 895 Beam tubo No Message Comb4(C) 0.124 0.124
B11
Story1 9 Beam tubo No Message Comb11(T) 0.118 0.118
B12
Story1 0 896 Beam tubo No Message Comb5(C) 0.121 0.121
B12
Story1 0 Beam tubo No Message Comb11(T) 0.112 0.112
B12
Story1 1 897 Beam tubo No Message Comb5(C) 0.119 0.119
B12
Story1 1 Beam tubo No Message Comb11(T) 0.113 0.113
B12
Story1 2 898 Beam tubo No Message Comb5(C) 0.121 0.121
B12
Story1 2 Beam tubo No Message Comb11(T) 0.112 0.112
B12
Story1 3 899 Beam tubo No Message Comb4(C) 0.124 0.124
B12
Story1 3 Beam tubo No Message Comb11(T) 0.111 0.111
B12
Story1 4 89A Beam tubo No Message Comb4(C) 0.127 0.127
B12
Story1 4 Beam tubo No Message Comb11(T) 0.121 0.121
B12
Story1 5 89B Beam tubo No Message Comb4(C) 0.132 0.132
B12
Story1 5 Beam tubo No Message Comb11(T) 0.114 0.114
B12
Story1 6 89C Beam tubo No Message Comb5(C) 0.137 0.137
B12
Story1 6 Beam tubo No Message Comb11(T) 0.13 0.13
B12
Story1 7 89D Beam tubo No Message Comb5(C) 0.15 0.15
B12
Story1 7 Beam tubo No Message Comb11(T) 0.116 0.116
B12
Story1 8 89E Beam tubo No Message Comb5(C) 0.164 0.164
B12
Story1 8 Beam tubo No Message Comb11(T) 0.11 0.11
B12
Story1 9 89F Beam tubo No Message Comb5(C) 0.107 0.107
B12
Story1 9 Beam tubo No Message Comb11(T) 0.101 0.101
B13
Story1 0 8A0 Beam tubo No Message Comb5(C) 0.101 0.101
B13
Story1 0 Beam tubo No Message Comb11(T) 0.06 0.06
B13
Story1 1 8A1 Beam tubo No Message Comb5(C) 0.077 0.077
B13
Story1 1 Beam tubo No Message Comb11(T) 0.057 0.057
B13
Story1 2 8A2 Beam tubo No Message Comb5(C) 0.072 0.072

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


146

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B13
Story1 2 Beam tubo No Message Comb12(T) 0.056 0.056
B13
Story1 3 8A3 Beam tubo No Message Comb5(C) 0.067 0.067
B13
Story1 3 Beam tubo No Message Comb11(T) 0.057 0.057
B13
Story1 4 8A4 Beam tubo No Message Comb4(C) 0.063 0.063
B13
Story1 4 Beam tubo No Message Comb11(T) 0.054 0.054
B13
Story1 5 8A5 Beam tubo No Message Comb5(C) 0.06 0.06
B13
Story1 5 Beam tubo No Message Comb11(T) 0.058 0.058
B13
Story1 6 8A6 Beam tubo No Message Comb5(C) 0.059 0.059
B13
Story1 6 Beam tubo No Message Comb11(T) 0.055 0.055
B13
Story1 7 8A7 Beam tubo No Message Comb4(C) 0.06 0.06
B13
Story1 7 Beam tubo No Message Comb11(T) 0.058 0.058
B13
Story1 8 8A8 Beam tubo No Message Comb4(C) 0.063 0.063
B13
Story1 8 Beam tubo No Message Comb11(T) 0.059 0.059
B13
Story1 9 8A9 Beam tubo No Message Comb5(C) 0.066 0.066
B13
Story1 9 Beam tubo No Message Comb11(T) 0.063 0.063
B14
Story1 0 8AA Beam tubo No Message Comb5(C) 0.072 0.072
B14
Story1 0 Beam tubo No Message Comb11(T) 0.068 0.068
B14
Story1 1 8AB Beam tubo No Message Comb5(C) 0.077 0.077
B14
Story1 1 Beam tubo No Message Comb11(T) 0.073 0.073
B14
Story1 2 8AC Beam tubo No Message Comb5(C) 0.102 0.102
B14
Story1 2 Beam tubo No Message Comb11(T) 0.096 0.096
B14
Story1 3 8AD Beam tubo No Message Comb5(C) 0.105 0.105
B14
Story1 3 Beam tubo No Message Comb11(T) 0.099 0.099
B14
Story1 4 8AE Beam tubo No Message Comb4(C) 0.067 0.067
B14
Story1 4 Beam tubo No Message Comb11(T) 0.026 0.026
B14
Story1 5 8AF Beam tubo No Message Comb4(C) 0.059 0.059
B14
Story1 5 Beam tubo No Message Comb11(T) 0.055 0.055
B14
Story1 6 8B0 Beam tubo No Message Comb4(C) 0.065 0.065
B14
Story1 6 Beam tubo No Message Comb11(T) 0.027 0.027
B14
Story1 7 8B1 Beam tubo No Message Comb4(C) 0.122 0.122
B14
Story1 7 Beam tubo No Message Comb11(T) 0.062 0.062
B14
Story1 8 8B2 Beam tubo No Message Comb4(C) 0.108 0.108
B14
Story1 8 Beam tubo No Message Comb11(T) 0.1 0.1
B14
Story1 9 8B3 Beam tubo No Message Comb4(C) 0.121 0.121
B14
Story1 9 Beam tubo No Message Comb11(T) 0.115 0.115
B15
Story1 0 8B4 Beam tubo No Message Comb5(C) 0.121 0.121
B15
Story1 0 Beam tubo No Message Comb11(T) 0.061 0.061
B15
Story1 1 8B5 Beam tubo No Message Comb5(C) 0.106 0.106

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


147

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B15
Story1 1 Beam tubo No Message Comb11(T) 0.089 0.089
B15
Story1 2 8B6 Beam tubo No Message Comb5(C) 0.122 0.122
B15
Story1 2 Beam tubo No Message Comb11(T) 0.116 0.116
B15
Story1 3 8B7 Beam tubo No Message Comb5(C) 0.108 0.108
B15
Story1 3 Beam tubo No Message Comb11(T) 0.103 0.103
B15
Story1 4 8B8 Beam tubo No Message Comb4(C) 0.107 0.107
B15
Story1 4 Beam tubo No Message Comb11(T) 0.098 0.098
B15
Story1 5 8B9 Beam tubo No Message Comb5(C) 0.122 0.122
B15
Story1 5 Beam tubo No Message Comb11(T) 0.117 0.117
B15
Story1 6 8BA Beam tubo No Message Comb5(C) 0.069 0.069
B15
Story1 6 Beam tubo No Message Comb11(T) 0.048 0.048
B15
Story1 7 8BB Beam tubo No Message Comb5(C) 0.068 0.068
B15
Story1 7 Beam tubo No Message Comb11(T) 0.044 0.044
B15
Story1 8 8BC Beam tubo No Message Comb4(C) 0.065 0.065
B15
Story1 8 Beam tubo No Message Comb11(T) 0.062 0.062
B15
Story1 9 8BD Beam tubo No Message Comb4(C) 0.055 0.055
B15
Story1 9 Beam tubo No Message Comb11(T) 0.052 0.052
B16
Story1 0 8BE Beam tubo No Message Comb5(C) 0.079 0.079
B16
Story1 0 Beam tubo No Message Comb11(T) 0.039 0.039
B16
Story1 1 8BF Beam tubo No Message Comb5(C) 0.119 0.119
B16
Story1 1 Beam tubo No Message Comb11(T) 0.113 0.113
B16
Story1 2 8C0 Beam tubo No Message Comb5(C) 0.11 0.11
B16
Story1 2 Beam tubo No Message Comb11(T) 0.089 0.089
B16
Story1 3 8C1 Beam tubo No Message Comb5(C) 0.112 0.112
B16
Story1 3 Beam tubo No Message Comb11(T) 0.106 0.106
B16
Story1 4 8C2 Beam tubo No Message Comb5(C) 0.107 0.107
B16
Story1 4 Beam tubo No Message Comb11(T) 0.102 0.102
B16
Story1 5 8C3 Beam tubo No Message Comb5(C) 0.107 0.107
B16
Story1 5 Beam tubo No Message Comb11(T) 0.095 0.095
B16
Story1 6 8C4 Beam tubo No Message Comb5(C) 0.111 0.111
B16
Story1 6 Beam tubo No Message Comb11(T) 0.106 0.106
B16
Story1 7 8C5 Beam tubo No Message Comb5(C) 0.116 0.116
B16
Story1 7 Beam tubo No Message Comb11(T) 0.089 0.089
B16
Story1 8 8C6 Beam tubo No Message Comb5(C) 0.122 0.122
B16
Story1 8 Beam tubo No Message Comb11(T) 0.116 0.116
B16
Story1 9 8C7 Beam tubo No Message Comb5(C) 0.12 0.12
B16
Story1 9 Beam tubo No Message Comb11(T) 0.114 0.114
B17
Story1 0 8C8 Beam tubo No Message Comb5(C) 0.109 0.109

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


148

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B17
Story1 0 Beam tubo No Message Comb11(T) 0.092 0.092
B17
Story1 1 8C9 Beam tubo No Message Comb4(C) 0.107 0.107
B17
Story1 1 Beam tubo No Message Comb11(T) 0.102 0.102
B17
Story1 2 8CA Beam tubo No Message Comb4(C) 0.106 0.106
B17
Story1 2 Beam tubo No Message Comb11(T) 0.101 0.101
B17
Story1 3 8CC Beam tubo No Message Comb4(C) 0.106 0.106
B17
Story1 3 Beam tubo No Message Comb11(T) 0.098 0.098
B17
Story1 4 8CD Beam tubo No Message Comb4(C) 0.106 0.106
B17
Story1 4 Beam tubo No Message Comb11(T) 0.101 0.101
B17
Story1 5 8CE Beam tubo No Message Comb4(C) 0.109 0.109
B17
Story1 5 Beam tubo No Message Comb11(T) 0.104 0.104
B17
Story1 6 8CF Beam tubo No Message Comb5(C) 0.122 0.122
B17
Story1 6 Beam tubo No Message Comb11(T) 0.092 0.092
B17
Story1 7 8D0 Beam tubo No Message Comb4(C) 0.12 0.12
B17
Story1 7 Beam tubo No Message Comb11(T) 0.115 0.115
B17
Story1 8 8D1 Beam tubo No Message Comb5(C) 0.108 0.108
B17
Story1 8 Beam tubo No Message Comb11(T) 0.095 0.095
B17
Story1 9 8D2 Beam tubo No Message Comb4(C) 0.104 0.104
B17
Story1 9 Beam tubo No Message Comb11(T) 0.096 0.096
B18
Story1 0 8D3 Beam tubo No Message Comb4(C) 0.104 0.104
B18
Story1 0 Beam tubo No Message Comb11(T) 0.1 0.1
B18
Story1 1 8D4 Beam tubo No Message Comb4(C) 0.105 0.105
B18
Story1 1 Beam tubo No Message Comb11(T) 0.08 0.08
B18
Story1 2 8D5 Beam tubo No Message Comb4(C) 0.105 0.105
B18
Story1 2 Beam tubo No Message Comb11(T) 0.089 0.089
B18
Story1 3 8D6 Beam tubo No Message Comb5(C) 0.062 0.062
B18
Story1 3 Beam tubo No Message Comb11(T) 0.059 0.059
B18
Story1 4 8D7 Beam tubo No Message Comb5(C) 0.065 0.065
B18
Story1 4 Beam tubo No Message Comb11(T) 0.028 0.028
B18
Story1 5 8D8 Beam tubo No Message Comb4(C) 0.12 0.12
B18
Story1 5 Beam tubo No Message Comb11(T) 0.115 0.115
B18
Story1 6 8D9 Beam tubo No Message Comb5(C) 0.107 0.107
B18
Story1 6 Beam tubo No Message Comb11(T) 0.102 0.102
B18
Story1 7 8DA Beam tubo No Message Comb5(C) 0.104 0.104
B18
Story1 7 Beam tubo No Message Comb11(T) 0.098 0.098
B18
Story1 8 8DB Beam tubo No Message Comb5(C) 0.103 0.103
B18
Story1 8 Beam tubo No Message Comb11(T) 0.099 0.099
B18
Story1 9 8DC Beam tubo No Message Comb5(C) 0.108 0.108

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


149

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B18
Story1 9 Beam tubo No Message Comb11(T) 0.089 0.089
B19
Story1 0 8DD Beam tubo No Message Comb4(C) 0.119 0.119
B19
Story1 0 Beam tubo No Message Comb11(T) 0.114 0.114
B19
Story1 1 8DE Beam tubo No Message Comb4(C) 0.12 0.12
B19
Story1 1 Beam tubo No Message Comb11(T) 0.114 0.114
B19
Story1 2 8DF Beam tubo No Message Comb5(C) 0.107 0.107
B19
Story1 2 Beam tubo No Message Comb11(T) 0.102 0.102
B19
Story1 3 8.00E+00 Beam tubo No Message Comb5(C) 0.104 0.104
B19
Story1 3 Beam tubo No Message Comb11(T) 0.099 0.099
B19
Story1 4 8.00E+01 Beam tubo No Message Comb5(C) 0.103 0.103
B19
Story1 4 Beam tubo No Message Comb11(T) 0.099 0.099
B19
Story1 5 8.00E+02 Beam tubo No Message Comb5(C) 0.107 0.107
B19
Story1 5 Beam tubo No Message Comb11(T) 0.089 0.089
B19
Story1 6 8.00E+03 Beam tubo No Message Comb4(C) 0.12 0.12
B19
Story1 6 Beam tubo No Message Comb11(T) 0.115 0.115
B19
Story1 7 8.00E+04 Beam tubo No Message Comb4(C) 0.12 0.12
B19
Story1 7 Beam tubo No Message Comb11(T) 0.114 0.114
B19
Story1 8 8.00E+05 Beam tubo No Message Comb5(C) 0.107 0.107
B19
Story1 8 Beam tubo No Message Comb11(T) 0.089 0.089
B19
Story1 9 8.00E+06 Beam tubo No Message Comb5(C) 0.104 0.104
B19
Story1 9 Beam tubo No Message Comb11(T) 0.089 0.089
B20
Story1 0 8.00E+07 Beam tubo No Message Comb5(C) 0.104 0.104
B20
Story1 0 Beam tubo No Message Comb11(T) 0.099 0.099
B20
Story1 1 8.00E+08 Beam tubo No Message Comb5(C) 0.107 0.107
B20
Story1 1 Beam tubo No Message Comb11(T) 0.097 0.097
B20
Story1 2 8.00E+09 Beam tubo No Message Comb4(C) 0.12 0.12
B20
Story1 2 Beam tubo No Message Comb11(T) 0.063 0.063
B20
Story1 3 8EA Beam tubo No Message Comb5(C) 0.12 0.12
B20
Story1 3 Beam tubo No Message Comb11(T) 0.114 0.114
B20
Story1 4 8EB Beam tubo No Message Comb5(C) 0.107 0.107
B20
Story1 4 Beam tubo No Message Comb11(T) 0.102 0.102
B20
Story1 5 8EC Beam tubo No Message Comb5(C) 0.104 0.104
B20
Story1 5 Beam tubo No Message Comb11(T) 0.099 0.099
B20
Story1 6 8ED Beam tubo No Message Comb5(C) 0.104 0.104
B20
Story1 6 Beam tubo No Message Comb11(T) 0.099 0.099
B20
Story1 7 8EE Beam tubo No Message Comb5(C) 0.107 0.107
B20
Story1 7 Beam tubo No Message Comb11(T) 0.102 0.102
B20
Story1 8 8EF Beam tubo No Message Comb5(C) 0.12 0.12

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


150

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B20
Story1 8 Beam tubo No Message Comb11(T) 0.114 0.114
B20
Story1 9 8F0 Beam tubo No Message Comb5(C) 0.12 0.12
B20
Story1 9 Beam tubo No Message Comb11(T) 0.114 0.114
B21
Story1 0 8F1 Beam tubo No Message Comb5(C) 0.107 0.107
B21
Story1 0 Beam tubo No Message Comb11(T) 0.102 0.102
B21
Story1 1 8F2 Beam tubo No Message Comb5(C) 0.104 0.104
B21
Story1 1 Beam tubo No Message Comb11(T) 0.099 0.099
B21
Story1 2 8F3 Beam tubo No Message Comb5(C) 0.104 0.104
B21
Story1 2 Beam tubo No Message Comb11(T) 0.099 0.099
B21
Story1 3 8F4 Beam tubo No Message Comb5(C) 0.107 0.107
B21
Story1 3 Beam tubo No Message Comb11(T) 0.102 0.102
B21
Story1 4 8F5 Beam tubo No Message Comb5(C) 0.12 0.12
B21
Story1 4 Beam tubo No Message Comb11(T) 0.114 0.114
B21
Story1 5 8F6 Beam tubo No Message Comb4(C) 0.12 0.12
B21
Story1 5 Beam tubo No Message Comb11(T) 0.114 0.114
B21
Story1 6 8F7 Beam tubo No Message Comb5(C) 0.107 0.107
B21
Story1 6 Beam tubo No Message Comb11(T) 0.097 0.097
B21
Story1 7 8F8 Beam tubo No Message Comb5(C) 0.104 0.104
B21
Story1 7 Beam tubo No Message Comb11(T) 0.099 0.099
B21
Story1 8 8F9 Beam tubo No Message Comb5(C) 0.104 0.104
B21
Story1 8 Beam tubo No Message Comb11(T) 0.099 0.099
B21
Story1 9 8FA Beam tubo No Message Comb5(C) 0.107 0.107
B21
Story1 9 Beam tubo No Message Comb11(T) 0.097 0.097
B22
Story1 0 8FB Beam tubo No Message Comb4(C) 0.12 0.12
B22
Story1 0 Beam tubo No Message Comb11(T) 0.114 0.114
B22
Story1 1 8FC Beam tubo No Message Comb4(C) 0.12 0.12
B22
Story1 1 Beam tubo No Message Comb11(T) 0.115 0.115
B22
Story1 2 8FD Beam tubo No Message Comb5(C) 0.107 0.107
B22
Story1 2 Beam tubo No Message Comb11(T) 0.102 0.102
B22
Story1 3 8FE Beam tubo No Message Comb5(C) 0.104 0.104
B22
Story1 3 Beam tubo No Message Comb11(T) 0.098 0.098
B22
Story1 4 8FF Beam tubo No Message Comb5(C) 0.104 0.104
B22
Story1 4 Beam tubo No Message Comb11(T) 0.099 0.099
B22
Story1 5 900 Beam tubo No Message Comb5(C) 0.107 0.107
B22
Story1 5 Beam tubo No Message Comb11(T) 0.102 0.102
B22
Story1 6 901 Beam tubo No Message Comb4(C) 0.119 0.119
B22
Story1 6 Beam tubo No Message Comb11(T) 0.092 0.092
B22
Story1 7 902 Beam tubo No Message Comb4(C) 0.12 0.12

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


151

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B22
Story1 7 Beam tubo No Message Comb11(T) 0.115 0.115
B22
Story1 8 903 Beam tubo No Message Comb5(C) 0.107 0.107
B22
Story1 8 Beam tubo No Message Comb11(T) 0.089 0.089
B22
Story1 9 904 Beam tubo No Message Comb4(C) 0.104 0.104
B22
Story1 9 Beam tubo No Message Comb11(T) 0.076 0.076
B23
Story1 0 905 Beam tubo No Message Comb4(C) 0.104 0.104
B23
Story1 0 Beam tubo No Message Comb11(T) 0.098 0.098
B23
Story1 1 906 Beam tubo No Message Comb5(C) 0.105 0.105
B23
Story1 1 Beam tubo No Message Comb11(T) 0.085 0.085
B23
Story1 2 907 Beam tubo No Message Comb5(C) 0.107 0.107
B23
Story1 2 Beam tubo No Message Comb11(T) 0.102 0.102
B23
Story1 3 908 Beam tubo No Message Comb5(C) 0.064 0.064
B23
Story1 3 Beam tubo No Message Comb11(T) 0.06 0.06
B23
Story1 4 909 Beam tubo No Message Comb5(C) 0.064 0.064
B23
Story1 4 Beam tubo No Message Comb11(T) 0.028 0.028
B23
Story1 5 90A Beam tubo No Message Comb4(C) 0.12 0.12
B23
Story1 5 Beam tubo No Message Comb11(T) 0.115 0.115
B23
Story1 6 90B Beam tubo No Message Comb5(C) 0.108 0.108
B23
Story1 6 Beam tubo No Message Comb11(T) 0.103 0.103
B23
Story1 7 90C Beam tubo No Message Comb4(C) 0.105 0.105
B23
Story1 7 Beam tubo No Message Comb11(T) 0.1 0.1
B23
Story1 8 90D Beam tubo No Message Comb4(C) 0.105 0.105
B23
Story1 8 Beam tubo No Message Comb11(T) 0.1 0.1
B23
Story1 9 90E Beam tubo No Message Comb4(C) 0.105 0.105
B23
Story1 9 Beam tubo No Message Comb11(T) 0.099 0.099
B24
Story1 0 90F Beam tubo No Message Comb5(C) 0.105 0.105
B24
Story1 0 Beam tubo No Message Comb11(T) 0.1 0.1
B24
Story1 1 910 Beam tubo No Message Comb4(C) 0.107 0.107
B24
Story1 1 Beam tubo No Message Comb11(T) 0.1 0.1
B24
Story1 2 911 Beam tubo No Message Comb5(C) 0.122 0.122
B24
Story1 2 Beam tubo No Message Comb11(T) 0.116 0.116
B24
Story1 3 912 Beam tubo No Message Comb5(C) 0.12 0.12
B24
Story1 3 Beam tubo No Message Comb11(T) 0.114 0.114
B24
Story1 4 913 Beam tubo No Message Comb5(C) 0.109 0.109
B24
Story1 4 Beam tubo No Message Comb11(T) 0.09 0.09
B24
Story1 5 914 Beam tubo No Message Comb4(C) 0.107 0.107
B24
Story1 5 Beam tubo No Message Comb11(T) 0.102 0.102
B24
Story1 6 915 Beam tubo No Message Comb4(C) 0.107 0.107

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


152

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B24
Story1 6 Beam tubo No Message Comb11(T) 0.097 0.097
B24
Story1 7 916 Beam tubo No Message Comb5(C) 0.107 0.107
B24
Story1 7 Beam tubo No Message Comb11(T) 0.099 0.099
B24
Story1 8 917 Beam tubo No Message Comb5(C) 0.107 0.107
B24
Story1 8 Beam tubo No Message Comb11(T) 0.102 0.102
B24
Story1 9 918 Beam tubo No Message Comb4(C) 0.108 0.108
B24
Story1 9 Beam tubo No Message Comb11(T) 0.103 0.103
B25
Story1 0 919 Beam tubo No Message Comb5(C) 0.123 0.123
B25
Story1 0 Beam tubo No Message Comb11(T) 0.057 0.057
B25
Story1 1 91A Beam tubo No Message Comb5(C) 0.12 0.12
B25
Story1 1 Beam tubo No Message Comb11(T) 0.114 0.114
B25
Story1 2 91B Beam tubo No Message Comb5(C) 0.109 0.109
B25
Story1 2 Beam tubo No Message Comb11(T) 0.104 0.104
B25
Story1 3 91C Beam tubo No Message Comb5(C) 0.111 0.111
B25
Story1 3 Beam tubo No Message Comb11(T) 0.106 0.106
B25
Story1 4 91D Beam tubo No Message Comb4(C) 0.108 0.108
B25
Story1 4 Beam tubo No Message Comb11(T) 0.088 0.088
B25
Story1 5 91E Beam tubo No Message Comb5(C) 0.108 0.108
B25
Story1 5 Beam tubo No Message Comb11(T) 0.094 0.094
B25
Story1 6 91F Beam tubo No Message Comb5(C) 0.114 0.114
B25
Story1 6 Beam tubo No Message Comb11(T) 0.108 0.108
B25
Story1 7 920 Beam tubo No Message Comb5(C) 0.116 0.116
B25
Story1 7 Beam tubo No Message Comb11(T) 0.091 0.091
B25
Story1 8 921 Beam tubo No Message Comb5(C) 0.122 0.122
B25
Story1 8 Beam tubo No Message Comb11(T) 0.116 0.116
B25
Story1 9 922 Beam tubo No Message Comb5(C) 0.069 0.069
B25
Story1 9 Beam tubo No Message Comb11(T) 0.049 0.049
B26
Story1 0 923 Beam tubo No Message Comb5(C) 0.068 0.068
B26
Story1 0 Beam tubo No Message Comb11(T) 0.045 0.045
B26
Story1 1 924 Beam tubo No Message Comb4(C) 0.065 0.065
B26
Story1 1 Beam tubo No Message Comb11(T) 0.061 0.061
B26
Story1 2 925 Beam tubo No Message Comb5(C) 0.054 0.054
B26
Story1 2 Beam tubo No Message Comb11(T) 0.048 0.048
B26
Story1 3 926 Beam tubo No Message Comb5(C) 0.08 0.08
B26
Story1 3 Beam tubo No Message Comb11(T) 0.075 0.075
B26
Story1 4 927 Beam tubo No Message Comb4(C) 0.11 0.11
B26
Story1 4 Beam tubo No Message Comb11(T) 0.104 0.104
B26
Story1 5 928 Beam tubo No Message Comb4(C) 0.108 0.108

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


153

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B26
Story1 5 Beam tubo No Message Comb11(T) 0.103 0.103
B26
Story1 6 929 Beam tubo No Message Comb5(C) 0.123 0.123
B26
Story1 6 Beam tubo No Message Comb11(T) 0.117 0.117
B26
Story1 7 92A Beam tubo No Message Comb5(C) 0.122 0.122
B26
Story1 7 Beam tubo No Message Comb11(T) 0.061 0.061
B26
Story1 8 92B Beam tubo No Message Comb5(C) 0.107 0.107
B26
Story1 8 Beam tubo No Message Comb11(T) 0.101 0.101
B26
Story1 9 92C Beam tubo No Message Comb5(C) 0.122 0.122
B26
Story1 9 Beam tubo No Message Comb11(T) 0.116 0.116
B27
Story1 0 92D Beam tubo No Message Comb5(C) 0.122 0.122
B27
Story1 0 Beam tubo No Message Comb11(T) 0.116 0.116
B27
Story1 1 92E Beam tubo No Message Comb4(C) 0.107 0.107
B27
Story1 1 Beam tubo No Message Comb11(T) 0.089 0.089
B27
Story1 2 92F Beam tubo No Message Comb4(C) 0.121 0.121
B27
Story1 2 Beam tubo No Message Comb11(T) 0.115 0.115
B27
Story1 3 930 Beam tubo No Message Comb4(C) 0.068 0.068
B27
Story1 3 Beam tubo No Message Comb11(T) 0.048 0.048
B27
Story1 4 931 Beam tubo No Message Comb4(C) 0.058 0.058
B27
Story1 4 Beam tubo No Message Comb11(T) 0.054 0.054
B27
Story1 5 932 Beam tubo No Message Comb4(C) 0.065 0.065
B27
Story1 5 Beam tubo No Message Comb11(T) 0.027 0.027
B27
Base 6 933 Beam tubo No Message Comb5(C) 0.098 0.012
B27
Base 7 934 Beam tubo No Message Comb5(C) 0.036 0.007
B27
Base 7 Beam tubo No Message Comb3(T) 0.012 0.012
B27
Base 8 935 Beam tubo No Message Comb5(C) 0.033 0.009
B27
Base 9 936 Beam tubo No Message Comb4(C) 0.02 0.009
B27
Base 9 Beam tubo No Message Comb3(T) 0.014 0.013
B28
Base 0 937 Beam tubo No Message Comb5(C) 0.04 0.006
B28
Base 0 Beam tubo No Message Comb3(T) 0.015 0.012
B28
Base 1 938 Beam tubo No Message Comb4(C) 0.013 0.009
B28
Base 1 Beam tubo No Message Comb3(T) 0.021 0.012
B28
Base 2 939 Beam tubo No Message Comb5(T) 0.075 0.009
B28
Base 4 93B Beam tubo No Message Comb5(C) 0.105 0.016
B28
Base 5 93C Beam tubo No Message Comb5(T) 0.066 0.018
B28
Base 6 93D Beam tubo No Message Comb5(C) 0.106 0.027
B28
Base 7 93E Beam tubo No Message Comb5(C) 0.486 0.04
B28
Base 8 93F Beam tubo No Message Comb5(C) 0.033 0.008
B28
Base 8 Beam tubo No Message Comb3(T) 0.022 0.013

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


154

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B28
Base 9 940 Beam tubo No Message Comb5(T) 0.041 0.009
B29
Base 0 941 Beam tubo No Message Comb5(T) 0.063 0.006
B29
Base 1 942 Beam tubo No Message Comb3(T) 0.029 0.014
B29
Base 2 943 Beam tubo No Message Comb4(C) 0.058 0.007
B29
Base 2 Beam tubo No Message Comb12(T) 0.006 0.005
B29
Base 3 944 Beam tubo No Message Comb5(C) 0.242 0.008
B29
Base 4 945 Beam tubo No Message Comb5(C) 0.289 0.009
B29
Base 5 946 Beam tubo No Message Comb5(C) 0.023 0.007
B29
Base 5 Beam tubo No Message Comb3(T) 0.021 0.012
B29
Base 6 947 Beam tubo No Message Comb3(T) 0.044 0.013
B29
Base 7 948 Beam tubo No Message Comb3(T) 0.058 0.01
B29
Base 8 949 Beam tubo No Message Comb3(T) 0.046 0.012
B29
Base 9 94A Beam tubo No Message Comb2(C) 0.01 0.008
B29
Base 9 Beam tubo No Message Comb3(T) 0.035 0.012
B30
Base 0 94B Beam tubo No Message Comb5(C) 0.042 0.008
B30
Base 0 Beam tubo No Message Comb3(T) 0.031 0.013
B30
Base 1 94C Beam tubo No Message Comb5(C) 0.082 0.011
B30
Base 1 Beam tubo No Message Comb12(T) 0.013 0.008
B30
Base 2 94D Beam tubo No Message Comb5(C) 0.07 0.009
B30
Base 3 94E Beam tubo No Message Comb3(T) 0.039 0.013
B30
Base 4 94F Beam tubo No Message Comb3(T) 0.049 0.01
B30
Base 5 950 Beam tubo No Message Comb3(T) 0.047 0.011
B30
Base 6 951 Beam tubo No Message Comb3(T) 0.042 0.011
B30
Base 7 952 Beam tubo No Message Comb3(T) 0.036 0.011
B30
Base 8 953 Beam tubo No Message Comb3(T) 0.025 0.013
B30
Base 9 954 Beam tubo No Message Comb3(T) 0.034 0.011
B31
Base 0 955 Beam tubo No Message Comb3(T) 0.036 0.011
B31
Base 1 956 Beam tubo No Message Comb3(T) 0.032 0.011
B31
Base 2 957 Beam tubo No Message Comb3(T) 0.019 0.013
B31
Base 3 958 Beam tubo No Message Comb3(T) 0.024 0.012
B31
Base 4 959 Beam tubo No Message Comb3(T) 0.026 0.012
B31
Base 5 95A Beam tubo No Message Comb3(T) 0.023 0.012
B31
Base 6 95B Beam tubo No Message Comb3(T) 0.018 0.013
B31
Base 7 95C Beam tubo No Message Comb3(T) 0.017 0.013
B31
Base 8 95D Beam tubo No Message Comb3(T) 0.019 0.012
B31
Base 9 95E Beam tubo No Message Comb3(T) 0.021 0.012
B32
Base 0 95F Beam tubo No Message Comb3(T) 0.019 0.012
B32
Base 1 960 Beam tubo No Message Comb3(T) 0.016 0.013

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


155

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B32
Base 2 961 Beam tubo No Message Comb3(T) 0.017 0.013
B32
Base 3 962 Beam tubo No Message Comb3(T) 0.019 0.012
B32
Base 4 963 Beam tubo No Message Comb3(T) 0.02 0.012
B32
Base 5 964 Beam tubo No Message Comb3(T) 0.019 0.012
B32
Base 6 965 Beam tubo No Message Comb3(T) 0.016 0.013
B32
Base 7 966 Beam tubo No Message Comb3(T) 0.019 0.013
B32
Base 8 967 Beam tubo No Message Comb3(T) 0.023 0.012
B32
Base 9 968 Beam tubo No Message Comb3(T) 0.025 0.012
B33
Base 0 969 Beam tubo No Message Comb3(T) 0.023 0.012
B33
Base 1 96A Beam tubo No Message Comb3(T) 0.018 0.013
B33
Base 2 96B Beam tubo No Message Comb3(T) 0.024 0.013
B33
Base 3 96C Beam tubo No Message Comb3(T) 0.031 0.011
B33
Base 4 96D Beam tubo No Message Comb3(T) 0.034 0.011
B33
Base 5 96E Beam tubo No Message Comb3(T) 0.031 0.011
B33
Base 6 96F Beam tubo No Message Comb3(T) 0.023 0.013
B33
Base 7 970 Beam tubo No Message Comb3(T) 0.037 0.013
B33
Base 8 971 Beam tubo No Message Comb3(T) 0.044 0.011
B33
Base 9 972 Beam tubo No Message Comb3(T) 0.045 0.011
B34
Base 0 973 Beam tubo No Message Comb3(T) 0.043 0.011
B34
Base 1 974 Beam tubo No Message Comb3(T) 0.035 0.011
B34
Base 2 975 Beam tubo No Message Comb3(T) 0.04 0.013
B34
Base 3 976 Beam tubo No Message Comb3(T) 0.05 0.01
B34
Base 4 977 Beam tubo No Message Comb3(T) 0.047 0.011
B34
Base 5 978 Beam tubo No Message Comb2(C) 0.009 0.008
B34
Base 5 Beam tubo No Message Comb3(T) 0.042 0.011
B34
Base 6 979 Beam tubo No Message Comb5(C) 0.028 0.007
B34
Base 6 Beam tubo No Message Comb3(T) 0.039 0.012
B34
Base 7 97A Beam tubo No Message Comb5(C) 0.05 0.009
B34
Base 7 Beam tubo No Message Comb3(T) 0.029 0.015
B34
Base 8 97B Beam tubo No Message Comb5(C) 0.049 0.009
B34
Base 8 Beam tubo No Message Comb3(T) 0.02 0.013
B34
Base 9 97C Beam tubo No Message Comb3(T) 0.034 0.014
B35
Base 0 97D Beam tubo No Message Comb3(T) 0.049 0.01
B35
Base 1 97E Beam tubo No Message Comb3(T) 0.037 0.012
B35
Base 2 97F Beam tubo No Message Comb4(C) 0.046 0.007
B35
Base 2 Beam tubo No Message Comb3(T) 0.023 0.013
B35
Base 3 980 Beam tubo No Message Comb4(C) 0.085 0.007
B35
Base 3 Beam tubo No Message Comb12(T) 0.008 0.005

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


156

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B35
Base 4 981 Beam tubo No Message Comb4(C) 0.094 0.008
B35
Base 5 982 Beam tubo No Message Comb5(C) 0.041 0.008
B35
Base 5 Beam tubo No Message Comb3(T) 0.017 0.013
B35
Base 6 983 Beam tubo No Message Comb5(T) 0.04 0.01
B35
Base 7 984 Beam tubo No Message Comb5(T) 0.06 0.006
B35
Base 8 985 Beam tubo No Message Comb5(C) 0.021 0.008
B35
Base 8 Beam tubo No Message Comb3(T) 0.023 0.014
B35
Base 9 986 Beam tubo No Message Comb4(C) 0.075 0.008
B36
Base 0 987 Beam tubo No Message Comb5(C) 0.285 0.009
B36
Base 1 988 Beam tubo No Message Comb5(C) 0.332 0.011
B36
Base 2 989 Beam tubo No Message Comb5(C) 0.024 0.007
B36
Base 2 Beam tubo No Message Comb3(T) 0.018 0.012
B36
Base 3 98A Beam tubo No Message Comb5(T) 0.079 0.012
B36
Base 5 98C Beam tubo No Message Comb5(C) 0.107 0.015
B36
Base 6 98D Beam tubo No Message Comb5(T) 0.066 0.02
B36
Base 7 98E Beam tubo No Message Comb5(C) 0.102 0.018
B36
Base 8 98F Beam tubo No Message Comb5(C) 0.579 0.062
B36
Base 9 990 Beam tubo No Message Comb5(C) 0.042 0.009
B36
Base 9 Beam tubo No Message Comb3(T) 0.02 0.013
B37
Base 0 991 Beam tubo No Message Comb5(C) 0.048 0.007
B37
Base 0 Beam tubo No Message Comb3(T) 0.014 0.012
B37
Base 1 992 Beam tubo No Message Comb4(C) 0.016 0.009
B37
Base 1 Beam tubo No Message Comb3(T) 0.022 0.012
B37
Base 2 993 Beam tubo No Message Comb5(C) 0.031 0.01
B37
Base 2 Beam tubo No Message Comb3(T) 0.014 0.013
B37
Base 3 994 Beam tubo No Message Comb4(C) 0.023 0.009
B37
Base 3 Beam tubo No Message Comb3(T) 0.014 0.013
B37
Base 4 995 Beam tubo No Message Comb5(C) 0.081 0.019
B37
Base 5 996 Beam tubo No Message Comb5(C) 0.033 0.007
B37
Base 5 Beam tubo No Message Comb3(T) 0.014 0.012
B37
Base 6 997 Beam tubo No Message Comb5(C) 0.043 0.009
B37
Base 7 998 Beam tubo No Message Comb5(C) 0.225 0.008
B37
Base 8 999 Beam tubo No Message Comb5(C) 0.464 0.013
B37
Base 9 99A Beam tubo No Message Comb5(C) 0.576 0.014
B38
Base 0 99B Beam tubo No Message Comb5(C) 0.413 0.012
B38
Base 1 99C Beam tubo No Message Comb5(C) 0.096 0.008
B38
Base 2 99D Beam tubo No Message Comb5(C) 0.234 0.008
B38
Base 3 99E Beam tubo No Message Comb5(C) 0.408 0.011

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


157

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B38
Base 4 99F Beam tubo No Message Comb5(C) 0.333 0.01
B38
Base 5 9A1 Beam tubo No Message Comb5(C) 0.08 0.008
B38
Base 6 9A2 Beam tubo No Message Comb5(C) 0.03 0.009
B38
Base 6 Beam tubo No Message Comb3(T) 0.015 0.014
B38
Base 7 9A3 Beam tubo No Message Comb4(C) 0.035 0.01
B38
Base 8 9A4 Beam tubo No Message Comb5(C) 0.107 0.01
B38
Base 9 9A5 Beam tubo No Message Comb4(C) 0.603 0.017
B39
Base 0 9A6 Beam tubo No Message Comb5(C) 0.901 0.033
B39
Base 1 9A7 Beam tubo No Message Comb5(C) 0.485 0.014
B39
Base 2 9A8 Beam tubo No Message Comb5(C) 0.085 0.008
B39
Base 3 9A9 Beam tubo No Message Comb5(C) 0.347 0.011
B39
Base 4 9AA Beam tubo No Message Comb5(C) 0.74 0.022
B39
Base 5 9AB Beam tubo No Message Comb4(C) 0.486 0.014
B39
Base 6 9AC Beam tubo No Message Comb5(C) 0.08 0.009
B39
Base 7 9AD Beam tubo No Message Comb4(C) 0.033 0.01
B39
Base 8 9AE Beam tubo No Message Comb6(C) 0.03 0.005
B39
Base 8 Beam tubo No Message Comb3(T) 0.018 0.016
B39
Base 9 9AF Beam tubo No Message Comb3(T) 0.017 0.014
B40
Base 0 9B0 Beam tubo No Message Comb4(C) 0.045 0.008
B40 Error: See
Base 1 9B1 Beam tubo Message Comb3(C) 1.852 0.616
B40
Base 2 9B2 Beam tubo No Message Comb4(C) 0.741 0.017
B40
Base 3 9B3 Beam tubo No Message Comb3(C) 0.098 0.016
B40
Base 4 9B4 Beam tubo No Message Comb3(C) 0.018 0.015
B40
Base 4 Beam tubo No Message Comb4(T) 0.052 0.005
B40
Base 5 9B6 Beam tubo No Message Comb5(T) 0.383 0.009
B40
Base 6 9B7 Beam tubo No Message Comb5(T) 0.382 0.009
B40
Base 7 9B8 Beam tubo No Message Comb5(T) 0.334 0.008
B40
Base 8 9B9 Beam tubo No Message Comb4(T) 0.049 0.006
B40
Base 9 9BA Beam tubo No Message Comb3(C) 0.421 0.02
B41
Base 0 9BB Beam tubo No Message Comb4(C) 0.782 0.018
B41 Error: See
Base 1 9BC Beam tubo Message Comb4(C) 1.704 0.0001632
B41
Base 2 9BD Beam tubo No Message Comb6(C) 0.032 0.01
B41
Base 2 Beam tubo No Message Comb4(T) 0.036 0.02
B41
Base 3 9BE Beam tubo No Message Comb3(T) 0.019 0.014
B41
Base 4 9C0 Beam tubo No Message Comb4(C) 0.057 0.012
B41
Base 5 9C1 Beam tubo No Message Comb4(C) 0.894 0.036
B41
Base 6 9C2 Beam tubo No Message Comb4(C) 0.508 0.016
B41
Base 7 9C3 Beam tubo No Message Comb3(C) 0.05 0.016

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


158

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B41
Base 8 9C4 Beam tubo No Message Comb4(T) 0.072 0.006
B41
Base 9 9C5 Beam tubo No Message Comb4(T) 0.257 0.007
B42
Base 0 9C6 Beam tubo No Message Comb5(T) 0.339 0.009
B42
Base 1 9C7 Beam tubo No Message Comb5(T) 0.381 0.009
B42
Base 2 9C8 Beam tubo No Message Comb5(T) 0.379 0.009
B42
Base 3 9C9 Beam tubo No Message Comb5(T) 0.334 0.009
B42
Base 4 9CA Beam tubo No Message Comb4(T) 0.247 0.007
B42
Base 5 9CB Beam tubo No Message Comb4(T) 0.064 0.006
B42
Base 6 9CC Beam tubo No Message Comb3(C) 0.08 0.017
B42
Base 7 9CD Beam tubo No Message Comb4(C) 0.55 0.016
B42
Base 8 9CF Beam tubo No Message Comb4(C) 0.88 0.036
B42 Error: See
Base 9 9D0 Beam tubo Message Comb4(C) 1.917 0.001
B43
Base 0 9D1 Beam tubo No Message Comb4(C) 0.82 0.023
B43
Base 1 9D2 Beam tubo No Message Comb4(C) 0.079 0.011
B43
Base 2 9D3 Beam tubo No Message Comb4(T) 0.071 0.006
B43
Base 3 9D4 Beam tubo No Message Comb4(T) 0.258 0.007
B43
Base 4 9D5 Beam tubo No Message Comb4(T) 0.339 0.009
B43
Base 5 9D6 Beam tubo No Message Comb4(T) 0.379 0.009
B43
Base 6 9D7 Beam tubo No Message Comb4(T) 0.377 0.009
B43
Base 7 9D8 Beam tubo No Message Comb4(T) 0.334 0.009
B43
Base 8 9D9 Beam tubo No Message Comb4(T) 0.249 0.007
B43
Base 9 9DC Beam tubo No Message Comb4(T) 0.065 0.006
B44
Base 0 9DD Beam tubo No Message Comb4(C) 0.095 0.011
B44
Base 1 9DE Beam tubo No Message Comb4(C) 0.842 0.027
B44 Error: See
Base 2 9DF Beam tubo Message Comb4(C) 1.916 0.0002929
B44
Base 3 9.00E+00 Beam tubo No Message Comb4(C) 0.646 0.025
B44
Base 4 9.00E+01 Beam tubo No Message Comb4(C) 0.444 0.012
B44
Base 5 9.00E+02 Beam tubo No Message Comb3(C) 0.04 0.017
B44
Base 6 9.00E+03 Beam tubo No Message Comb4(T) 0.074 0.006
B44
Base 7 9.00E+04 Beam tubo No Message Comb4(T) 0.261 0.007
B44
Base 8 9.00E+05 Beam tubo No Message Comb4(T) 0.343 0.009
B44
Base 9 9.00E+06 Beam tubo No Message Comb5(T) 0.383 0.009
B45
Base 0 9.00E+07 Beam tubo No Message Comb5(T) 0.382 0.009
B45
Base 1 9.00E+08 Beam tubo No Message Comb4(T) 0.339 0.009
B45
Base 2 9.00E+09 Beam tubo No Message Comb4(T) 0.256 0.007
B45
Base 3 9EA Beam tubo No Message Comb4(T) 0.072 0.006
B45
Base 4 9EB Beam tubo No Message Comb4(C) 0.043 0.01
B45
Base 5 9EC Beam tubo No Message Comb4(C) 0.455 0.013

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


159

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
B45
Base 6 9ED Beam tubo No Message Comb4(C) 0.647 0.02
B45
Base 7 9EE Beam tubo No Message Comb4(C) 0.675 0.026
B45
Base 8 9EF Beam tubo No Message Comb4(C) 0.488 0.014
B45
Base 9 9F0 Beam tubo No Message Comb3(C) 0.056 0.017
B46
Base 0 9F1 Beam tubo No Message Comb4(T) 0.075 0.006
B46
Base 1 9F2 Beam tubo No Message Comb4(T) 0.266 0.007
B46
Base 2 9F3 Beam tubo No Message Comb5(T) 0.351 0.009
B46
Base 3 9F4 Beam tubo No Message Comb5(T) 0.393 0.01
B46
Base 4 9F5 Beam tubo No Message Comb5(T) 0.393 0.01
B46
Base 5 9F6 Beam tubo No Message Comb5(T) 0.35 0.009
B46
Base 6 9F7 Beam tubo No Message Comb4(T) 0.265 0.007
B46
Base 7 9F8 Beam tubo No Message Comb4(T) 0.075 0.006
B46
Base 8 9F9 Beam tubo No Message Comb3(C) 0.064 0.017
B46
Base 9 9FA Beam tubo No Message Comb4(C) 0.495 0.014
B47
Base 0 9FB Beam tubo No Message Comb4(C) 0.684 0.02
B47 Error: See
Base 1 9FC Beam tubo Message Comb5(C) 2.025 0.001
B47
Base 2 9FD Beam tubo No Message Comb4(C) 0.919 0.034
B47
Base 3 9FE Beam tubo No Message Comb3(C) 0.093 0.017
B47
Base 4 9FF Beam tubo No Message Comb4(T) 0.076 0.007
B47
Base 5 A00 Beam tubo No Message Comb5(T) 0.276 0.008
B47
Base 6 A01 Beam tubo No Message Comb5(T) 0.362 0.009
B47
Base 7 A02 Beam tubo No Message Comb5(T) 0.405 0.01
B47
Base 8 A03 Beam tubo No Message Comb5(T) 0.405 0.01
B47
Base 9 A04 Beam tubo No Message Comb5(T) 0.364 0.009
B48
Base 0 A05 Beam tubo No Message Comb5(T) 0.278 0.008
B48
Base 1 A06 Beam tubo No Message Comb4(T) 0.077 0.006
B48
Base 2 A07 Beam tubo No Message Comb3(C) 0.298 0.019
B48
Base 3 A08 Beam tubo No Message Comb4(C) 0.938 0.038
B48 Error: See
Base 4 A09 Beam tubo Message Comb5(C) 2.073 0.0003948
B48
Base 5 A9D Beam tubo No Message Comb4(T) 0.245 0.008
B48
Base 6 A9E Beam tubo No Message Comb5(T) 0.338 0.009
B48
Base 7 2129 Beam tubo No Message Comb5(C) 0.205 0.046
B48
Base 8 2130 Beam tubo No Message Comb5(T) 0.194 0.046
B48
Base 9 2131 Beam tubo No Message Comb5(C) 0.206 0.049
B49
Base 0 2132 Beam tubo No Message Comb5(T) 0.194 0.044

Story1 D1 A0A Brace tubo No Message Comb4(C) 0.053 0.047

Story1 D1 Brace tubo No Message Comb12(T) 0.043 0.037

Story1 D2 A0B Brace tubo No Message Comb5(C) 0.045 0.032

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


160

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 D3 A0C Brace tubo No Message Comb5(C) 0.039 0.024

Story1 D4 A0D Brace tubo No Message Comb4(C) 0.035 0.025

Story1 D4 Brace tubo No Message Comb12(T) 0.032 0.022

Story1 D5 A0E Brace tubo No Message Comb12(C) 0.05 0.021

Story1 D6 A0F Brace tubo No Message Comb12(T) 0.046 0.019

Story1 D7 A10 Brace tubo No Message Comb5(C) 0.059 0.024

Story1 D7 Brace tubo No Message Comb12(T) 0.038 0.018

Story1 D8 A11 Brace tubo No Message Comb12(C) 0.034 0.02

Story1 D8 Brace tubo No Message Comb5(T) 0.036 0.024

Story1 D9 A12 Brace tubo No Message Comb5(C) 0.052 0.022

Story1 D10 A13 Brace tubo No Message Comb5(T) 0.042 0.027

Story1 D11 A14 Brace tubo No Message Comb5(C) 0.055 0.022

Story1 D12 A15 Brace tubo No Message Comb12(T) 0.042 0.021

Story1 D13 A16 Brace tubo No Message Comb3(C) 0.068 0.023

Story1 D14 A17 Brace tubo No Message Comb5(C) 0.053 0.047

Story1 D14 Brace tubo No Message Comb12(T) 0.065 0.038

Story1 D15 A18 Brace tubo No Message Comb5(C) 0.053 0.047

Story1 D15 Brace tubo No Message Comb12(T) 0.057 0.037

Story1 D16 A19 Brace tubo No Message Comb3(C) 0.068 0.022

Story1 D17 A1A Brace tubo No Message Comb5(T) 0.044 0.024

Story1 D18 A1B Brace tubo No Message Comb5(C) 0.058 0.023

Story1 D19 A1C Brace tubo No Message Comb5(T) 0.041 0.027

Story1 D20 A1D Brace tubo No Message Comb5(C) 0.059 0.025

Story1 D20 Brace tubo No Message Comb12(T) 0.032 0.019

Story1 D21 A1E Brace tubo No Message Comb12(T) 0.044 0.02

Story1 D22 A1F Brace tubo No Message Comb4(C) 0.047 0.028

Story1 D23 A20 Brace tubo No Message Comb4(C) 0.036 0.026

Story1 D23 Brace tubo No Message Comb12(T) 0.031 0.022

Story1 D24 A21 Brace tubo No Message Comb5(C) 0.035 0.024

Story1 D25 A22 Brace tubo No Message Comb5(C) 0.048 0.032

Story1 D26 A23 Brace tubo No Message Comb4(C) 0.053 0.047

Story1 D26 Brace tubo No Message Comb12(T) 0.043 0.037

Story1 D27 A24 Brace tubo No Message Comb4(C) 0.056 0.04

Story1 D28 A25 Brace tubo No Message Comb5(T) 0.028 0.011

Story1 D29 A26 Brace tubo No Message Comb5(C) 0.047 0.007

Story1 D30 A27 Brace tubo No Message Comb5(T) 0.032 0.006

Story1 D31 A28 Brace tubo No Message Comb5(C) 0.068 0.007

Story1 D32 A29 Brace tubo No Message Comb5(T) 0.039 0.005

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


161

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 D33 A2A Brace tubo No Message Comb3(C) 0.023 0.01

Story1 D34 A2B Brace tubo No Message Comb12(C) 0.006 0.004

Story1 D34 Brace tubo No Message Comb5(T) 0.03 0.008

Story1 D35 A2C Brace tubo No Message Comb4(T) 0.044 0.004

Story1 D36 A2D Brace tubo No Message Comb4(C) 0.07 0.009

Story1 D37 A2E Brace tubo No Message Comb5(T) 0.054 0.005

Story1 D38 A2F Brace tubo No Message Comb3(C) 0.085 0.013

Story1 D39 A30 Brace tubo No Message Comb5(T) 0.048 0.01

Story1 D40 A31 Brace tubo No Message Comb3(C) 0.091 0.024

Story1 D41 A32 Brace tubo No Message Comb5(C) 0.045 0.033

Story1 D41 Brace tubo No Message Comb12(T) 0.032 0.026

Story1 D42 A33 Brace tubo No Message Comb4(C) 0.032 0.007

Story1 D43 A34 Brace tubo No Message Comb3(C) 0.02 0.012

Story1 D44 A35 Brace tubo No Message Comb3(T) 0.018 0.012

Story1 D45 A36 Brace tubo No Message Comb5(C) 0.035 0.007

Story1 D46 A37 Brace tubo No Message Comb3(T) 0.02 0.014

Story1 D47 A38 Brace tubo No Message Comb5(C) 0.11 0.015

Story1 D48 A39 Brace tubo No Message Comb5(C) 0.089 0.017

Story1 D49 A3A Brace tubo No Message Comb5(C) 0.087 0.018

Story1 D50 A3B Brace tubo No Message Comb5(C) 0.051 0.008

Story1 D51 A3C Brace tubo No Message Comb5(C) 0.05 0.017

Story1 D52 A3D Brace tubo No Message Comb5(C) 0.019 0.008

Story1 D52 Brace tubo No Message Comb3(T) 0.019 0.008

Story1 D53 A3E Brace tubo No Message Comb3(C) 0.05 0.014

Story1 D54 A3F Brace tubo No Message Comb12(T) 0.056 0.027

Story1 D55 A40 Brace tubo No Message Comb5(C) 0.097 0.033

Story1 D56 A41 Brace tubo No Message Comb5(T) 0.062 0.01

Story1 D57 A42 Brace tubo No Message Comb4(C) 0.084 0.011

Story1 D58 A43 Brace tubo No Message Comb4(T) 0.047 0.002

Story1 D59 A44 Brace tubo No Message Comb3(C) 0.02 0.01

Story1 D59 Brace tubo No Message Comb5(T) 0.019 0.006

Story1 D60 A46 Brace tubo No Message Comb3(C) 0.011 0.009

Story1 D60 Brace tubo No Message Comb4(T) 0.011 0.004

Story1 D61 A47 Brace tubo No Message Comb5(T) 0.03 0.006

Story1 D62 A48 Brace tubo No Message Comb5(C) 0.052 0.007

Story1 D63 A49 Brace tubo No Message Comb5(T) 0.025 0.007

Story1 D64 A4A Brace tubo No Message Comb5(C) 0.035 0.007

Story1 D65 A4B Brace tubo No Message Comb4(T) 0.026 0.011

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


162

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 D66 A4C Brace tubo No Message Comb4(C) 0.049 0.04

Story1 D67 A4D Brace tubo No Message Comb5(T) 0.062 0.031

Story1 D68 A4E Brace tubo No Message Comb5(C) 0.066 0.013

Story1 D69 A4F Brace tubo No Message Comb5(C) 0.031 0.008

Story1 D69 Brace tubo No Message Comb3(T) 0.013 0.009

Story1 D70 A50 Brace tubo No Message Comb5(C) 0.093 0.017

Story1 D71 A51 Brace tubo No Message Comb5(C) 0.069 0.014

Story1 D72 A52 Brace tubo No Message Comb5(C) 0.104 0.013

Story1 D73 A53 Brace tubo No Message Comb3(T) 0.02 0.012

Story1 D74 A54 Brace tubo No Message Comb5(C) 0.034 0.007

Story1 D75 A55 Brace tubo No Message Comb3(T) 0.016 0.011

Story1 D76 A56 Brace tubo No Message Comb3(C) 0.021 0.012

Story1 D77 A57 Brace tubo No Message Comb4(C) 0.039 0.007

Story1 D78 A58 Brace tubo No Message Comb4(C) 0.053 0.033

Story1 D79 A59 Brace tubo No Message Comb4(C) 0.051 0.031

Story1 D80 A5A Brace tubo No Message Comb4(T) 0.029 0.009

Story1 D81 A5B Brace tubo No Message Comb4(C) 0.054 0.013

Story1 D82 A5C Brace tubo No Message Comb4(T) 0.03 0.006

Story1 D83 A5D Brace tubo No Message Comb4(C) 0.104 0.011

Story1 D84 A5E Brace tubo No Message Comb4(T) 0.067 0.007

Story1 D85 A5F Brace tubo No Message Comb3(C) 0.02 0.018

Story1 D85 Brace tubo No Message Comb4(T) 0.03 0.02

Story1 D86 A60 Brace tubo No Message Comb5(T) 0.11 0.025

Story1 D87 A61 Brace tubo No Message Comb4(T) 0.118 0.02

Story1 D88 A62 Brace tubo No Message Comb4(C) 0.102 0.018

Story1 D89 A63 Brace tubo No Message Comb5(T) 0.074 0.009

Story1 D90 A64 Brace tubo No Message Comb4(C) 0.101 0.013

Story1 D91 A65 Brace tubo No Message Comb5(T) 0.043 0.005

Story1 D92 A66 Brace tubo No Message Comb3(C) 0.093 0.012

Story1 D93 A67 Brace tubo No Message Comb4(C) 0.063 0.046

Story1 D94 A68 Brace tubo No Message Comb4(C) 0.09 0.017

Story1 D95 A69 Brace tubo No Message Comb4(T) 0.025 0.008

Story1 D96 A6A Brace tubo No Message Comb4(C) 0.026 0.006

Story1 D97 A6B Brace tubo No Message Comb4(T) 0.023 0.002

Story1 D98 A6C Brace tubo No Message Comb3(C) 0.022 0.012

Story1 D98 Brace tubo No Message Comb4(T) 0.017 0.011

Story1 D99 A6D Brace tubo No Message Comb4(C) 0.367 0.021


D10
Story1 0 A6E Brace tubo No Message Comb5(C) 1.199 0.102

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


163

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D10
Story1 1 A6F Brace tubo No Message Comb5(T) 0.112 0.028
D10
Story1 2 A70 Brace tubo No Message Comb4(C) 0.302 0.014
D10
Story1 3 A71 Brace tubo No Message Comb5(T) 0.047 0.015
D10
Story1 4 A72 Brace tubo No Message Comb5(C) 0.059 0.004
D10
Story1 5 A73 Brace tubo No Message Comb3(C) 0.015 0.011
D10
Story1 5 Brace tubo No Message Comb5(T) 0.026 0.007
D10
Story1 6 A74 Brace tubo No Message Comb5(C) 0.041 0.022
D10
Story1 6 Brace tubo No Message Comb12(T) 0.031 0.015
D10
Story1 7 A75 Brace tubo No Message Comb3(T) 0.076 0.011
D10
Story1 8 A76 Brace tubo No Message Comb3(C) 0.1 0.021
D10
Story1 9 A77 Brace tubo No Message Comb12(T) 0.06 0.03
D11
Story1 0 A78 Brace tubo No Message Comb5(C) 0.074 0.037
D11
Story1 1 A79 Brace tubo No Message Comb5(T) 0.05 0.038
D11
Story1 2 A7A Brace tubo No Message Comb5(C) 0.055 0.039
D11
Story1 3 A7B Brace tubo No Message Comb5(C) 0.041 0.039
D11
Story1 3 Brace tubo No Message Comb12(T) 0.034 0.03
D11
Story1 4 A7C Brace tubo No Message Comb5(T) 0.044 0.039
D11
Story1 5 A7D Brace tubo No Message Comb5(C) 0.06 0.038
D11
Story1 6 A7E Brace tubo No Message Comb5(T) 0.053 0.039
D11
Story1 7 A7F Brace tubo No Message Comb5(C) 0.079 0.036
D11
Story1 8 A80 Brace tubo No Message Comb5(T) 0.062 0.036
D11
Story1 9 A81 Brace tubo No Message Comb5(C) 0.1 0.034
D12
Story1 0 A82 Brace tubo No Message Comb5(T) 0.074 0.035
D12
Story1 1 A83 Brace tubo No Message Comb5(C) 0.122 0.025
D12
Story1 2 A84 Brace tubo No Message Comb3(T) 0.094 0.02
D12
Story1 3 A85 Brace tubo No Message Comb12(T) 0.038 0.012
D12
Story1 4 A86 Brace tubo No Message Comb3(C) 0.036 0.018
D12
Story1 4 Brace tubo No Message Comb5(T) 0.022 0.015
D12
Story1 5 A87 Brace tubo No Message Comb4(C) 0.216 0.01
D12
Story1 6 A88 Brace tubo No Message Comb5(T) 0.091 0.028
D12
Story1 7 A89 Brace tubo No Message Comb5(C) 1.006 0.026
D12
Story1 8 A8A Brace tubo No Message Comb4(C) 0.335 0.021
D12
Story1 9 A8B Brace tubo No Message Comb3(C) 0.02 0.011
D12
Story1 9 Brace tubo No Message Comb5(T) 0.01 0.008
D13
Story1 0 A8C Brace tubo No Message Comb4(T) 0.022 0.001
D13
Story1 1 A8D Brace tubo No Message Comb4(C) 0.032 0.006
D13
Story1 2 A8E Brace tubo No Message Comb4(T) 0.028 0.007
D13
Story1 3 A8F Brace tubo No Message Comb4(C) 0.214 0.011

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


164

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D13
Story1 4 A90 Brace tubo No Message Comb4(C) 0.07 0.043
D13
Story1 5 A91 Brace tubo No Message Comb5(C) 0.31 0.015
D13
Story1 6 A92 Brace tubo No Message Comb5(T) 0.079 0.003
D13
Story1 7 A93 Brace tubo No Message Comb4(C) 0.119 0.02
D13
Story1 8 A94 Brace tubo No Message Comb4(T) 0.118 0.019
D13
Story1 9 A95 Brace tubo No Message Comb5(T) 0.094 0.024
D14
Story1 0 A96 Brace tubo No Message Comb4(T) 0.03 0.017
D14
Story1 1 A97 Brace tubo No Message Comb4(T) 0.055 0.006
D14
Story1 2 A98 Brace tubo No Message Comb4(C) 0.084 0.01
D14
Story1 3 A99 Brace tubo No Message Comb4(T) 0.025 0.006
D14
Story1 4 A9A Brace tubo No Message Comb4(C) 0.039 0.013
D14
Story1 5 A9B Brace tubo No Message Comb4(T) 0.031 0.008
D14
Story1 6 A9C Brace tubo No Message Comb4(C) 0.023 0.018
D14
Story1 6 Brace tubo No Message Comb4(T) 0.042 0.031
D14
Story1 7 A9F Brace tubo No Message Comb4(C) 0.053 0.047
D14
Story1 7 Brace tubo No Message Comb12(T) 0.043 0.037
D14
Story1 8 AA0 Brace tubo No Message Comb12(C) 0.036 0.025
D14
Story1 8 Brace tubo No Message Comb4(T) 0.05 0.034
D14
Story1 9 AA1 Brace tubo No Message Comb4(C) 0.069 0.024
D15
Story1 0 AA2 Brace tubo No Message Comb4(T) 0.048 0.03
D15
Story1 1 AA3 Brace tubo No Message Comb4(C) 0.069 0.023
D15
Story1 2 AA4 Brace tubo No Message Comb6(C) 0.017 0.009
D15
Story1 2 Brace tubo No Message Comb3(T) 0.036 0.021
D15
Story1 3 AA5 Brace tubo No Message Comb4(T) 0.058 0.023
D15
Story1 4 AA6 Brace tubo No Message Comb5(C) 0.98 0.022
D15
Story1 5 AA7 Brace tubo No Message Comb5(T) 0.115 0.024
D15
Story1 6 AA8 Brace tubo No Message Comb4(C) 0.415 0.022
D15
Story1 7 AA9 Brace tubo No Message Comb5(T) 0.072 0.01
D15
Story1 8 AAA Brace tubo No Message Comb5(C) 0.264 0.008
D15
Story1 9 AAB Brace tubo No Message Comb5(T) 0.049 0.005
D16
Story1 0 AAC Brace tubo No Message Comb5(C) 0.105 0.006
D16
Story1 1 AAD Brace tubo No Message Comb5(T) 0.04 0.009
D16
Story1 2 AAE Brace tubo No Message Comb5(C) 0.073 0.008
D16
Story1 3 AAF Brace tubo No Message Comb5(T) 0.032 0.012
D16
Story1 4 AB0 Brace tubo No Message Comb5(C) 0.054 0.013
D16
Story1 5 AB1 Brace tubo No Message Comb5(T) 0.025 0.013
D16
Story1 6 AB2 Brace tubo No Message Comb4(C) 0.034 0.014
D16
Story1 7 AB3 Brace tubo No Message Comb3(C) 0.016 0.015

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


165

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D16
Story1 7 Brace tubo No Message Comb5(T) 0.016 0.014
D16
Story1 8 AB4 Brace tubo No Message Comb5(C) 0.017 0.014
D16
Story1 8 Brace tubo No Message Comb1(T) 0.005 0.004
D16
Story1 9 AB5 Brace tubo No Message Comb5(C) 0.031 0.014
D17
Story1 0 AB6 Brace tubo No Message Comb5(T) 0.022 0.014
D17
Story1 1 AB7 Brace tubo No Message Comb5(C) 0.05 0.013
D17
Story1 2 AB8 Brace tubo No Message Comb5(T) 0.03 0.012
D17
Story1 3 AB9 Brace tubo No Message Comb5(C) 0.072 0.012
D17
Story1 4 ABA Brace tubo No Message Comb5(T) 0.038 0.01
D17
Story1 5 ABB Brace tubo No Message Comb5(C) 0.098 0.005
D17
Story1 6 ABC Brace tubo No Message Comb5(T) 0.046 0.007
D17
Story1 7 ABD Brace tubo No Message Comb5(C) 0.288 0.008
D17
Story1 8 ABE Brace tubo No Message Comb5(T) 0.065 0.007
D17
Story1 9 ABF Brace tubo No Message Comb4(C) 0.403 0.021
D18
Story1 0 AC0 Brace tubo No Message Comb5(T) 0.108 0.022
D18
Story1 1 AC1 Brace tubo No Message Comb5(C) 0.92 0.024
D18
Story1 2 AC2 Brace tubo No Message Comb4(T) 0.069 0.03
D18
Story1 3 AC3 Brace tubo No Message Comb4(C) 0.038 0.023
D18
Story1 3 Brace tubo No Message Comb3(T) 0.032 0.02
D18
Story1 4 AC4 Brace tubo No Message Comb4(C) 0.058 0.023
D18
Story1 5 AC5 Brace tubo No Message Comb6(C) 0.015 0.006
D18
Story1 5 Brace tubo No Message Comb4(T) 0.042 0.03
D18
Story1 6 AC6 Brace tubo No Message Comb4(C) 0.058 0.023
D18
Story1 7 AC7 Brace tubo No Message Comb12(C) 0.041 0.027
D18
Story1 7 Brace tubo No Message Comb4(T) 0.048 0.036
D18
Story1 8 AC8 Brace tubo No Message Comb4(C) 0.054 0.048
D18
Story1 8 Brace tubo No Message Comb12(T) 0.043 0.037
D18
Story1 9 AC9 Brace tubo No Message Comb5(C) 0.117 0.025
D19
Story1 0 ACA Brace tubo No Message Comb5(T) 0.106 0.018
D19
Story1 1 ACB Brace tubo No Message Comb5(T) 0.066 0.022
D19
Story1 2 ACC Brace tubo No Message Comb5(C) 0.043 0.012
D19
Story1 3 ACD Brace tubo No Message Comb5(T) 0.05 0.014
D19
Story1 4 ACE Brace tubo No Message Comb5(C) 0.048 0.004
D19
Story1 5 ACF Brace tubo No Message Comb5(T) 0.035 0.006
D19
Story1 6 AD0 Brace tubo No Message Comb5(C) 0.047 0.005
D19
Story1 7 AD1 Brace tubo No Message Comb3(T) 0.038 0.009
D19
Story1 8 AD2 Brace tubo No Message Comb5(C) 0.05 0.006
D19
Story1 9 AD3 Brace tubo No Message Comb3(T) 0.037 0.011

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


166

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D20
Story1 0 AD4 Brace tubo No Message Comb3(C) 0.043 0.012
D20
Story1 1 AD5 Brace tubo No Message Comb3(T) 0.027 0.012
D20
Story1 2 AD6 Brace tubo No Message Comb3(C) 0.029 0.012
D20
Story1 3 AD7 Brace tubo No Message Comb5(C) 0.013 0.007
D20
Story1 3 Brace tubo No Message Comb3(T) 0.016 0.013
D20
Story1 4 AD8 Brace tubo No Message Comb5(T) 0.014 0.008
D20
Story1 5 AD9 Brace tubo No Message Comb5(C) 0.029 0.007
D20
Story1 6 ADA Brace tubo No Message Comb3(T) 0.024 0.012
D20
Story1 7 ADB Brace tubo No Message Comb5(C) 0.045 0.008
D20
Story1 8 ADC Brace tubo No Message Comb3(T) 0.034 0.011
D20
Story1 9 ADD Brace tubo No Message Comb5(C) 0.058 0.007
D21
Story1 0 ADE Brace tubo No Message Comb3(T) 0.043 0.009
D21
Story1 1 ADF Brace tubo No Message Comb5(C) 0.062 0.004
D21
Story1 2 AE0 Brace tubo No Message Comb3(T) 0.041 0.01
D21
Story1 3 AE1 Brace tubo No Message Comb5(C) 0.038 0.004
D21
Story1 4 AE2 Brace tubo No Message Comb5(T) 0.041 0.014
D21
Story1 5 AE3 Brace tubo No Message Comb5(C) 0.021 0.01
D21
Story1 5 Brace tubo No Message Comb3(T) 0.015 0.011
D21
Story1 6 AE4 Brace tubo No Message Comb5(T) 0.054 0.023
D21
Story1 7 AE5 Brace tubo No Message Comb5(T) 0.104 0.016
D21
Story1 8 AE6 Brace tubo No Message Comb5(C) 0.116 0.023
D21
Story1 9 AE7 Brace tubo No Message Comb5(C) 0.392 0.024
D22
Story1 0 AE8 Brace tubo No Message Comb5(T) 0.065 0.014
D22
Story1 1 AE9 Brace tubo No Message Comb3(T) 0.042 0.021
D22
Story1 2 AEA Brace tubo No Message Comb5(C) 0.1 0.014
D22
Story1 3 AEB Brace tubo No Message Comb5(T) 0.047 0.011
D22
Story1 4 AEC Brace tubo No Message Comb5(C) 0.103 0.007
D22
Story1 5 AED Brace tubo No Message Comb5(T) 0.039 0.003
D22
Story1 6 AEE Brace tubo No Message Comb5(C) 0.084 0.005
D22
Story1 7 AEF Brace tubo No Message Comb5(T) 0.035 0.006
D22
Story1 8 AF0 Brace tubo No Message Comb5(C) 0.063 0.007
D22
Story1 9 AF1 Brace tubo No Message Comb5(T) 0.028 0.006
D23
Story1 0 AF2 Brace tubo No Message Comb5(C) 0.046 0.008
D23
Story1 1 AF3 Brace tubo No Message Comb5(T) 0.022 0.009
D23
Story1 2 AF4 Brace tubo No Message Comb5(C) 0.03 0.009
D23
Story1 3 AF5 Brace tubo No Message Comb3(C) 0.013 0.013
D23
Story1 3 Brace tubo No Message Comb5(T) 0.013 0.01
D23
Story1 4 AF6 Brace tubo No Message Comb3(C) 0.015 0.013

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


167

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D23
Story1 4 Brace tubo No Message Comb1(T) 0.004 0.003
D23
Story1 5 AF7 Brace tubo No Message Comb4(C) 0.027 0.009
D23
Story1 6 AF8 Brace tubo No Message Comb5(T) 0.02 0.008
D23
Story1 7 AFA Brace tubo No Message Comb5(C) 0.044 0.008
D23
Story1 8 AFB Brace tubo No Message Comb5(T) 0.026 0.006
D23
Story1 9 AFC Brace tubo No Message Comb5(C) 0.061 0.007
D24
Story1 0 AFD Brace tubo No Message Comb5(T) 0.032 0.006
D24
Story1 1 AFE Brace tubo No Message Comb5(C) 0.077 0.005
D24
Story1 2 AFF Brace tubo No Message Comb5(T) 0.04 0.003
D24
Story1 3 B00 Brace tubo No Message Comb5(C) 0.103 0.007
D24
Story1 4 B01 Brace tubo No Message Comb5(T) 0.049 0.01
D24
Story1 5 B02 Brace tubo No Message Comb5(C) 0.105 0.014
D24
Story1 6 B03 Brace tubo No Message Comb4(T) 0.046 0.023
D24
Story1 7 B04 Brace tubo No Message Comb5(T) 0.063 0.015
D24
Story1 8 B05 Brace tubo No Message Comb5(C) 0.381 0.024
D24
Story1 9 B06 Brace tubo No Message Comb5(T) 0.139 0.048
D25
Story1 0 B07 Brace tubo No Message Comb5(C) 0.742 0.036
D25
Story1 1 B08 Brace tubo No Message Comb5(T) 0.118 0.025
D25
Story1 2 B09 Brace tubo No Message Comb5(C) 0.301 0.016
D25
Story1 3 B0A Brace tubo No Message Comb5(T) 0.073 0.011
D25
Story1 4 B0B Brace tubo No Message Comb5(C) 0.091 0.006
D25
Story1 5 B0C Brace tubo No Message Comb5(T) 0.046 0.004
D25
Story1 6 B0D Brace tubo No Message Comb5(C) 0.066 0.005
D25
Story1 7 B0E Brace tubo No Message Comb5(T) 0.034 0.006
D25
Story1 8 B0F Brace tubo No Message Comb5(C) 0.053 0.008
D25
Story1 9 B10 Brace tubo No Message Comb3(T) 0.03 0.012
D26
Story1 0 B11 Brace tubo No Message Comb5(C) 0.038 0.009
D26
Story1 1 B12 Brace tubo No Message Comb3(T) 0.023 0.013
D26
Story1 2 B13 Brace tubo No Message Comb3(C) 0.026 0.013
D26
Story1 3 B14 Brace tubo No Message Comb5(C) 0.014 0.01
D26
Story1 3 Brace tubo No Message Comb3(T) 0.015 0.013
D26
Story1 4 B15 Brace tubo No Message Comb5(T) 0.015 0.01
D26
Story1 5 B16 Brace tubo No Message Comb4(C) 0.029 0.01
D26
Story1 6 B17 Brace tubo No Message Comb5(T) 0.023 0.009
D26
Story1 7 B18 Brace tubo No Message Comb5(C) 0.044 0.009
D26
Story1 8 B19 Brace tubo No Message Comb3(T) 0.03 0.012
D26
Story1 9 B1A Brace tubo No Message Comb5(C) 0.057 0.008
D27
Story1 0 B1B Brace tubo No Message Comb5(T) 0.037 0.006

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


168

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D27
Story1 1 B1C Brace tubo No Message Comb5(C) 0.071 0.005
D27
Story1 2 B1D Brace tubo No Message Comb5(T) 0.044 0.004
D27
Story1 3 B1E Brace tubo No Message Comb5(C) 0.09 0.005
D27
Story1 4 B1F Brace tubo No Message Comb5(T) 0.068 0.011
D27
Story1 5 B20 Brace tubo No Message Comb5(C) 0.284 0.015
D27
Story1 6 B21 Brace tubo No Message Comb5(T) 0.114 0.027
D27
Story1 7 B22 Brace tubo No Message Comb5(C) 0.728 0.015
D27
Story1 8 B23 Brace tubo No Message Comb5(T) 0.141 0.051
D27
Story1 9 B24 Brace tubo No Message Comb5(T) 0.125 0.051
D28
Story1 0 B25 Brace tubo No Message Comb5(C) 1.094 0.051
D28
Story1 1 B26 Brace tubo No Message Comb5(T) 0.106 0.022
D28
Story1 2 B27 Brace tubo No Message Comb5(C) 0.435 0.018
D28
Story1 3 B28 Brace tubo No Message Comb5(T) 0.053 0.009
D28
Story1 4 B29 Brace tubo No Message Comb5(C) 0.254 0.005
D28
Story1 5 B2A Brace tubo No Message Comb5(T) 0.04 0.004
D28
Story1 6 B2B Brace tubo No Message Comb5(C) 0.089 0.005
D28
Story1 7 B2C Brace tubo No Message Comb5(T) 0.036 0.007
D28
Story1 8 B2D Brace tubo No Message Comb5(C) 0.065 0.008
D28
Story1 9 B2E Brace tubo No Message Comb5(T) 0.03 0.007
D29
Story1 0 B2F Brace tubo No Message Comb5(C) 0.047 0.009
D29
Story1 1 B30 Brace tubo No Message Comb5(T) 0.023 0.01
D29
Story1 2 B31 Brace tubo No Message Comb4(C) 0.03 0.01
D29
Story1 3 B32 Brace tubo No Message Comb3(T) 0.015 0.013
D29
Story1 4 B33 Brace tubo No Message Comb3(C) 0.015 0.013
D29
Story1 4 Brace tubo No Message Comb1(T) 0.007 0.007
D29
Story1 5 B34 Brace tubo No Message Comb4(C) 0.028 0.01
D29
Story1 6 B35 Brace tubo No Message Comb5(T) 0.021 0.009
D29
Story1 7 B36 Brace tubo No Message Comb5(C) 0.045 0.009
D29
Story1 8 B37 Brace tubo No Message Comb5(T) 0.028 0.007
D29
Story1 9 B38 Brace tubo No Message Comb5(C) 0.063 0.008
D30
Story1 0 B39 Brace tubo No Message Comb5(T) 0.035 0.007
D30
Story1 1 B3A Brace tubo No Message Comb5(C) 0.085 0.005
D30
Story1 2 B3B Brace tubo No Message Comb5(T) 0.041 0.004
D30
Story1 3 B3C Brace tubo No Message Comb5(C) 0.251 0.005
D30
Story1 4 B3D Brace tubo No Message Comb5(T) 0.055 0.008
D30
Story1 5 B3E Brace tubo No Message Comb5(C) 0.44 0.018
D30
Story1 6 B3F Brace tubo No Message Comb5(T) 0.109 0.022
D30
Story1 7 B40 Brace tubo No Message Comb5(C) 1.106 0.048

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


169

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D30
Story1 8 B41 Brace tubo No Message Comb5(T) 0.133 0.056
D30
Story1 9 B42 Brace tubo No Message Comb5(C) 0.291 0.02
D31
Story1 0 B43 Brace tubo No Message Comb5(T) 0.245 0.001
D31
Story1 1 B44 Brace tubo No Message Comb5(T) 0.075 0.023
D31
Story1 2 B45 Brace tubo No Message Comb3(C) 0.019 0.012
D31
Story1 2 Brace tubo No Message Comb5(T) 0.016 0.01
D31
Story1 3 B46 Brace tubo No Message Comb5(T) 0.055 0.009
D31
Story1 4 B47 Brace tubo No Message Comb5(C) 0.05 0.004
D31
Story1 5 B48 Brace tubo No Message Comb5(T) 0.039 0.004
D31
Story1 6 B49 Brace tubo No Message Comb5(C) 0.058 0.006
D31
Story1 7 B4A Brace tubo No Message Comb5(T) 0.032 0.007
D31
Story1 8 B4B Brace tubo No Message Comb5(C) 0.051 0.008
D31
Story1 9 B4C Brace tubo No Message Comb5(T) 0.025 0.009
D32
Story1 0 B4D Brace tubo No Message Comb5(C) 0.038 0.009
D32
Story1 1 B4E Brace tubo No Message Comb5(T) 0.019 0.009
D32
Story1 2 B4F Brace tubo No Message Comb3(C) 0.024 0.013
D32
Story1 3 B50 Brace tubo No Message Comb5(C) 0.015 0.01
D32
Story1 3 Brace tubo No Message Comb3(T) 0.007 0.005
D32
Story1 4 B51 Brace tubo No Message Comb5(T) 0.015 0.01
D32
Story1 5 B52 Brace tubo No Message Comb4(C) 0.028 0.01
D32
Story1 6 B53 Brace tubo No Message Comb5(T) 0.022 0.009
D32
Story1 7 B54 Brace tubo No Message Comb5(C) 0.041 0.009
D32
Story1 8 B55 Brace tubo No Message Comb5(T) 0.027 0.009
D32
Story1 9 B57 Brace tubo No Message Comb5(C) 0.053 0.008
D33
Story1 0 B58 Brace tubo No Message Comb5(T) 0.032 0.007
D33
Story1 1 B59 Brace tubo No Message Comb5(C) 0.06 0.006
D33
Story1 2 B5A Brace tubo No Message Comb5(T) 0.037 0.004
D33
Story1 3 B5B Brace tubo No Message Comb5(C) 0.05 0.003
D33
Story1 4 B5C Brace tubo No Message Comb5(T) 0.051 0.009
D33
Story1 5 B5D Brace tubo No Message Comb3(C) 0.017 0.012
D33
Story1 5 Brace tubo No Message Comb5(T) 0.017 0.009
D33
Story1 6 B5E Brace tubo No Message Comb5(T) 0.073 0.024
D33
Story1 7 B5F Brace tubo No Message Comb5(T) 0.245 0.004
D33
Story1 8 B60 Brace tubo No Message Comb5(C) 0.305 0.021
D33
Story1 9 B61 Brace tubo No Message Comb5(C) 0.101 0.03
D34
Story1 0 B62 Brace tubo No Message Comb5(C) 0.062 0.018
D34
Story1 1 B63 Brace tubo No Message Comb4(C) 0.052 0.01
D34
Story1 2 B64 Brace tubo No Message Comb5(C) 0.07 0.008

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


170

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D34
Story1 3 B65 Brace tubo No Message Comb5(T) 0.022 0.005
D34
Story1 4 B66 Brace tubo No Message Comb5(C) 0.082 0.004
D34
Story1 5 B67 Brace tubo No Message Comb5(T) 0.035 0.005
D34
Story1 6 B68 Brace tubo No Message Comb5(C) 0.078 0.006
D34
Story1 7 B69 Brace tubo No Message Comb5(T) 0.037 0.007
D34
Story1 8 B6A Brace tubo No Message Comb5(C) 0.065 0.008
D34
Story1 9 B6B Brace tubo No Message Comb3(T) 0.032 0.012
D35
Story1 0 B6C Brace tubo No Message Comb5(C) 0.048 0.009
D35
Story1 1 B6D Brace tubo No Message Comb3(T) 0.026 0.013
D35
Story1 2 B6E Brace tubo No Message Comb4(C) 0.031 0.01
D35
Story1 3 B6F Brace tubo No Message Comb3(T) 0.017 0.013
D35
Story1 4 B70 Brace tubo No Message Comb3(C) 0.015 0.013
D35
Story1 4 Brace tubo No Message Comb2(T) 0.011 0.011
D35
Story1 5 B71 Brace tubo No Message Comb4(C) 0.028 0.01
D35
Story1 6 B72 Brace tubo No Message Comb5(T) 0.023 0.01
D35
Story1 7 B73 Brace tubo No Message Comb5(C) 0.046 0.009
D35
Story1 8 B74 Brace tubo No Message Comb5(T) 0.031 0.008
D35
Story1 9 B75 Brace tubo No Message Comb5(C) 0.062 0.008
D36
Story1 0 B76 Brace tubo No Message Comb5(T) 0.037 0.007
D36
Story1 1 B77 Brace tubo No Message Comb5(C) 0.075 0.006
D36
Story1 2 B78 Brace tubo No Message Comb5(T) 0.037 0.005
D36
Story1 3 B79 Brace tubo No Message Comb5(C) 0.082 0.004
D36
Story1 4 B7A Brace tubo No Message Comb5(T) 0.025 0.004
D36
Story1 5 B7B Brace tubo No Message Comb5(C) 0.072 0.008
D36
Story1 6 B7C Brace tubo No Message Comb4(C) 0.047 0.01
D36
Story1 7 B7D Brace tubo No Message Comb5(C) 0.059 0.014
D36
Story1 8 B7E Brace tubo No Message Comb5(C) 0.097 0.031
D36
Story1 9 B7F Brace tubo No Message Comb5(T) 0.061 0.031
D37
Story1 0 B80 Brace tubo No Message Comb5(T) 0.052 0.018
D37
Story1 1 B81 Brace tubo No Message Comb5(C) 0.027 0.011
D37
Story1 2 B82 Brace tubo No Message Comb3(C) 0.045 0.011
D37
Story1 3 B83 Brace tubo No Message Comb5(T) 0.023 0.006
D37
Story1 4 B84 Brace tubo No Message Comb5(C) 0.061 0.003
D37
Story1 5 B85 Brace tubo No Message Comb5(T) 0.027 0.004
D37
Story1 6 B86 Brace tubo No Message Comb5(C) 0.06 0.005
D37
Story1 7 B87 Brace tubo No Message Comb5(T) 0.027 0.006
D37
Story1 8 B88 Brace tubo No Message Comb5(C) 0.05 0.007
D37
Story1 9 B89 Brace tubo No Message Comb5(T) 0.023 0.006

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


171

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D38
Story1 0 B8A Brace tubo No Message Comb5(C) 0.038 0.009
D38
Story1 1 B8B Brace tubo No Message Comb5(T) 0.018 0.008
D38
Story1 2 B8C Brace tubo No Message Comb5(C) 0.024 0.01
D38
Story1 3 B8D Brace tubo No Message Comb3(C) 0.016 0.013
D38
Story1 3 Brace tubo No Message Comb1(T) 0.004 0.003
D38
Story1 4 B8E Brace tubo No Message Comb12(C) 0.008 0.006
D38
Story1 4 Brace tubo No Message Comb5(T) 0.014 0.01
D38
Story1 5 B8F Brace tubo No Message Comb5(C) 0.027 0.01
D38
Story1 6 B90 Brace tubo No Message Comb5(T) 0.02 0.009
D38
Story1 7 B91 Brace tubo No Message Comb5(C) 0.04 0.008
D38
Story1 8 B92 Brace tubo No Message Comb5(T) 0.024 0.006
D38
Story1 9 B93 Brace tubo No Message Comb5(C) 0.052 0.007
D39
Story1 0 B94 Brace tubo No Message Comb5(T) 0.026 0.006
D39
Story1 1 B95 Brace tubo No Message Comb5(C) 0.061 0.005
D39
Story1 2 B96 Brace tubo No Message Comb5(T) 0.025 0.004
D39
Story1 3 B97 Brace tubo No Message Comb5(C) 0.061 0.002
D39
Story1 4 B98 Brace tubo No Message Comb5(T) 0.02 0.007
D39
Story1 5 B99 Brace tubo No Message Comb3(C) 0.047 0.011
D39
Story1 6 B9A Brace tubo No Message Comb5(C) 0.032 0.012
D39
Story1 7 B9B Brace tubo No Message Comb5(T) 0.051 0.015
D39
Story1 8 B9C Brace tubo No Message Comb5(T) 0.059 0.032
D39
Story1 9 B9D Brace tubo No Message Comb5(C) 0.501 0.019
D40
Story1 0 B9E Brace tubo No Message Comb5(T) 0.282 0.051
D40
Story1 1 B9F Brace tubo No Message Comb4(C) 0.05 0.044
D40
Story1 1 Brace tubo No Message Comb12(T) 0.062 0.035
D40
Story1 2 BA0 Brace tubo No Message Comb5(T) 0.101 0.002
D40
Story1 3 BA1 Brace tubo No Message Comb5(T) 0.059 0.023
D40
Story1 4 BA2 Brace tubo No Message Comb5(C) 0.039 0.014
D40
Story1 4 Brace tubo No Message Comb3(T) 0.016 0.014
D40
Story1 5 BA3 Brace tubo No Message Comb5(T) 0.06 0.01
D40
Story1 6 BA4 Brace tubo No Message Comb5(C) 0.081 0.009
D40
Story1 7 BA5 Brace tubo No Message Comb5(T) 0.051 0.003
D40
Story1 8 BA6 Brace tubo No Message Comb5(C) 0.08 0.005
D40
Story1 9 BA7 Brace tubo No Message Comb3(T) 0.044 0.009
D41
Story1 0 BA8 Brace tubo No Message Comb5(C) 0.067 0.007
D41
Story1 1 BA9 Brace tubo No Message Comb3(T) 0.041 0.011
D41
Story1 2 BAA Brace tubo No Message Comb3(C) 0.05 0.012
D41
Story1 3 BAB Brace tubo No Message Comb3(T) 0.03 0.012

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


172

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D41
Story1 4 BAC Brace tubo No Message Comb3(C) 0.034 0.013
D41
Story1 5 BAD Brace tubo No Message Comb3(T) 0.018 0.013
D41
Story1 6 BAE Brace tubo No Message Comb3(C) 0.014 0.013
D41
Story1 6 Brace tubo No Message Comb4(T) 0.012 0.008
D41
Story1 7 BAF Brace tubo No Message Comb5(C) 0.028 0.008
D41
Story1 8 BB0 Brace tubo No Message Comb5(T) 0.023 0.008
D41
Story1 9 BB1 Brace tubo No Message Comb5(C) 0.047 0.009
D42
Story1 0 BB2 Brace tubo No Message Comb3(T) 0.034 0.011
D42
Story1 1 BB3 Brace tubo No Message Comb5(C) 0.065 0.007
D42
Story1 2 BB4 Brace tubo No Message Comb3(T) 0.045 0.01
D42
Story1 3 BB5 Brace tubo No Message Comb5(C) 0.079 0.005
D42
Story1 4 BB6 Brace tubo No Message Comb5(T) 0.052 0.003
D42
Story1 5 BB7 Brace tubo No Message Comb5(C) 0.082 0.009
D42
Story1 6 BB8 Brace tubo No Message Comb5(T) 0.063 0.009
D42
Story1 7 BB9 Brace tubo No Message Comb5(C) 0.041 0.015
D42
Story1 7 Brace tubo No Message Comb3(T) 0.019 0.014
D42
Story1 8 BBA Brace tubo No Message Comb5(T) 0.064 0.025
D42
Story1 9 BBB Brace tubo No Message Comb5(T) 0.104 0.006
D43
Story1 0 BBC Brace tubo No Message Comb5(C) 0.499 0.021
D43
Story1 1 BBD Brace tubo No Message Comb5(C) 0.802 0.038
D43
Story1 2 BBE Brace tubo No Message Comb5(T) 0.083 0.017
D43
Story1 3 BBF Brace tubo No Message Comb4(C) 0.375 0.009
D43
Story1 4 BC0 Brace tubo No Message Comb5(T) 0.041 0.006
D43
Story1 5 BC1 Brace tubo No Message Comb5(C) 0.11 0.007
D43
Story1 6 BC2 Brace tubo No Message Comb5(T) 0.034 0.009
D43
Story1 7 BC3 Brace tubo No Message Comb3(C) 0.082 0.012
D43
Story1 8 BC4 Brace tubo No Message Comb5(T) 0.03 0.011
D43
Story1 9 BC5 Brace tubo No Message Comb3(C) 0.058 0.012
D44
Story1 0 BC6 Brace tubo No Message Comb5(T) 0.026 0.013
D44
Story1 1 BC7 Brace tubo No Message Comb5(C) 0.042 0.014
D44
Story1 2 BC8 Brace tubo No Message Comb5(T) 0.02 0.013
D44
Story1 3 BC9 Brace tubo No Message Comb5(C) 0.028 0.015
D44
Story1 4 BCA Brace tubo No Message Comb3(C) 0.018 0.015
D44
Story1 5 BCB Brace tubo No Message Comb12(C) 0.012 0.011
D44
Story1 5 Brace tubo No Message Comb5(T) 0.016 0.015
D44
Story1 6 BCC Brace tubo No Message Comb5(C) 0.031 0.015
D44
Story1 7 BCD Brace tubo No Message Comb5(T) 0.022 0.013
D44
Story1 8 BCE Brace tubo No Message Comb5(C) 0.044 0.014

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


173

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D44
Story1 9 BCF Brace tubo No Message Comb5(T) 0.026 0.013
D45
Story1 0 BD0 Brace tubo No Message Comb5(C) 0.058 0.012
D45
Story1 1 BD1 Brace tubo No Message Comb5(T) 0.03 0.011
D45
Story1 2 BD2 Brace tubo No Message Comb5(C) 0.077 0.01
D45
Story1 3 BD3 Brace tubo No Message Comb5(T) 0.033 0.009
D45
Story1 4 BD4 Brace tubo No Message Comb5(C) 0.212 0.006
D45
Story1 5 BD5 Brace tubo No Message Comb5(T) 0.041 0.006
D45
Story1 6 BD6 Brace tubo No Message Comb4(C) 0.382 0.009
D45
Story1 7 BD7 Brace tubo No Message Comb5(T) 0.085 0.018
D45
Story1 8 BD8 Brace tubo No Message Comb5(C) 0.83 0.027
D45
Story1 9 BD9 Brace tubo No Message Comb5(T) 0.283 0.052
D46
Story1 0 BDA Brace tubo No Message Comb5(C) 0.537 0.024
D46
Story1 1 BDB Brace tubo No Message Comb5(T) 0.251 0.003
D46
Story1 2 BDC Brace tubo No Message Comb5(C) 0.387 0.014
D46
Story1 3 BDD Brace tubo No Message Comb5(T) 0.113 0.027
D46
Story1 4 BDE Brace tubo No Message Comb5(C) 0.284 0.022
D46
Story1 5 BDF Brace tubo No Message Comb5(T) 0.091 0.032
D46
Story1 6 BE0 Brace tubo No Message Comb5(C) 0.127 0.03
D46
Story1 6 Brace tubo No Message Comb12(T) 0.037 0.019
D46
Story1 7 BE1 Brace tubo No Message Comb3(T) 0.085 0.016
D46
Story1 8 BE2 Brace tubo No Message Comb3(C) 0.106 0.022
D46
Story1 9 BE3 Brace tubo No Message Comb5(T) 0.065 0.038
D47
Story1 0 BE4 Brace tubo No Message Comb5(C) 0.08 0.037
D47
Story1 1 BE5 Brace tubo No Message Comb5(T) 0.055 0.039
D47
Story1 2 BE6 Brace tubo No Message Comb5(C) 0.06 0.039
D47
Story1 3 BE7 Brace tubo No Message Comb5(T) 0.044 0.04
D47
Story1 4 BE8 Brace tubo No Message Comb12(C) 0.032 0.03
D47
Story1 4 Brace tubo No Message Comb5(T) 0.042 0.04
D47
Story1 5 BE9 Brace tubo No Message Comb5(C) 0.057 0.039
D47
Story1 6 BEA Brace tubo No Message Comb5(T) 0.053 0.039
D47
Story1 7 BEB Brace tubo No Message Comb5(C) 0.078 0.037
D47
Story1 8 BEC Brace tubo No Message Comb5(T) 0.064 0.038
D47
Story1 9 BED Brace tubo No Message Comb5(C) 0.101 0.034
D48
Story1 0 BEE Brace tubo No Message Comb5(T) 0.077 0.036
D48
Story1 1 BEF Brace tubo No Message Comb5(C) 0.128 0.03
D48
Story1 2 BF0 Brace tubo No Message Comb5(T) 0.093 0.032
D48
Story1 3 BF1 Brace tubo No Message Comb5(C) 0.292 0.022
D48
Story1 4 BF2 Brace tubo No Message Comb5(T) 0.117 0.028

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


174

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
D48
Story1 5 BF3 Brace tubo No Message Comb5(C) 0.4 0.014
D48
Story1 6 BF4 Brace tubo No Message Comb5(T) 0.259 0.002
D48
Story1 7 BF5 Brace tubo No Message Comb5(C) 0.551 0.021
D48
Story1 8 BF6 Brace tubo No Message Comb5(C) 0.055 0.048
D48
Story1 8 Brace tubo No Message Comb3(T) 0.058 0.035

Tabla 11_Tabla de valores de índice de capacidad cubierta tipo.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


175

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story Label Unique Name Load Case/Combo Displacement X Displacement Y Drift X Drift Y
m m
Story1 1 3 pushx Max 0 0 0.00% 0.01%
Story1 1 3 pushx Min -0.004707 -0.000168 0.16% 0.02%
Story1 2 4 pushx Max 0 0 0.00% 0.01%
Story1 2 4 pushx Min -0.004707 -0.000163 0.16% 0.02%
Story1 3 6 pushx Max 0 0 0.00% 0.00%
Story1 3 6 pushx Min -0.004707 -0.000158 0.13% 0.04%
Story1 4 8 pushx Max 0 0 0.00% 0.06%
Story1 4 8 pushx Min -0.004707 -0.000153 0.11% 0.00%
Story1 5 10 pushx Max 0 0 0.00% 0.05%
Story1 5 10 pushx Min -0.004707 -0.000149 0.13% 0.00%
Story1 6 12 pushx Max 0 0 0.00% 0.02%
Story1 6 12 pushx Min -0.004707 -0.000144 0.17% 0.02%
Story1 7 14 pushx Max 0 0 0.00% 0.00%
Story1 7 14 pushx Min -0.004707 -0.00014 0.18% 0.04%
Story1 8 16 pushx Max 0 0 0.00% 0.00%
Story1 8 16 pushx Min -0.004707 -0.000136 0.18% 0.05%
Story1 9 19 pushx Max 0 0 0.01% 0.06%
Story1 9 19 pushx Min -0.004707 -0.000142 0.04% 0.00%
Story1 10 20 pushx Max 0 0 0.01% 0.06%
Story1 10 20 pushx Min -0.004707 -0.000147 0.04% 0.00%
Story1 11 22 pushx Max 0 0 0.00% 0.07%
Story1 11 22 pushx Min -0.004707 -0.000152 0.04% 0.00%
Story1 12 24 pushx Max 0 0 0.00% 0.02%
Story1 12 24 pushx Min -0.004707 -0.000157 0.06% 0.01%
Story1 13 26 pushx Max 0 0 0.00% 0.00%
Story1 13 26 pushx Min -0.004707 -0.000162 0.06% 0.04%
Story1 14 28 pushx Max 0 0 0.00% 0.02%
Story1 14 28 pushx Min -0.004707 -0.000167 0.05% 0.00%
Story1 15 30 pushx Max 0 0 0.00% 0.00%
Story1 15 30 pushx Min -0.004707 -0.000172 0.05% 0.02%
Story1 16 33 pushx Max 0 0 0.00% 0.01%
Story1 16 33 pushx Min -0.004704 -0.000168 0.16% 0.02%
Story1 17 34 pushx Max 0 0 0.00% 0.01%
Story1 17 34 pushx Min -0.004704 -0.000163 0.16% 0.02%
Story1 18 36 pushx Max 0 0 0.00% 0.00%
Story1 18 36 pushx Min -0.004704 -0.000158 0.13% 0.04%
Story1 19 38 pushx Max 0 0 0.00% 0.06%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


176

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 19 38 pushx Min -0.004704 -0.000153 0.11% 0.00%
Story1 20 40 pushx Max 0 0 0.00% 0.05%
Story1 20 40 pushx Min -0.004704 -0.000149 0.13% 0.00%
Story1 21 42 pushx Max 0 0 0.00% 0.02%
Story1 21 42 pushx Min -0.004704 -0.000144 0.17% 0.02%
Story1 22 44 pushx Max 0 0 0.00% 0.00%
Story1 22 44 pushx Min -0.004704 -0.00014 0.18% 0.04%
Story1 23 46 pushx Max 0 0 0.00% 0.00%
Story1 23 46 pushx Min -0.004704 -0.000136 0.18% 0.05%
Story1 24 49 pushx Max 0 0 0.01% 0.06%
Story1 24 49 pushx Min -0.004704 -0.000142 0.04% 0.00%
Story1 25 50 pushx Max 0 0 0.01% 0.06%
Story1 25 50 pushx Min -0.004704 -0.000147 0.04% 0.00%
Story1 26 52 pushx Max 0 0 0.00% 0.07%
Story1 26 52 pushx Min -0.004704 -0.000152 0.04% 0.00%
Story1 27 54 pushx Max 0 0 0.00% 0.02%
Story1 27 54 pushx Min -0.004704 -0.000157 0.06% 0.01%
Story1 28 56 pushx Max 0 0 0.00% 0.00%
Story1 28 56 pushx Min -0.004704 -0.000162 0.06% 0.04%
Story1 29 58 pushx Max 0 0 0.00% 0.02%
Story1 29 58 pushx Min -0.004704 -0.000167 0.05% 0.00%
Story1 30 60 pushx Max 0 0 0.00% 0.00%
Story1 30 60 pushx Min -0.004704 -0.000172 0.05% 0.02%
Story1 31 63 pushx Max 0 0 0.00% 0.01%
Story1 31 63 pushx Min -0.004701 -0.000168 0.23% 0.02%
Story1 32 64 pushx Max 0 0 0.00% 0.01%
Story1 32 64 pushx Min -0.004701 -0.000163 0.23% 0.02%
Story1 33 66 pushx Max 0 0 0.00% 0.00%
Story1 33 66 pushx Min -0.004701 -0.000158 0.11% 0.05%
Story1 34 68 pushx Max 0 0 0.00% 0.09%
Story1 34 68 pushx Min -0.004701 -0.000153 0.08% 0.00%
Story1 35 70 pushx Max 0 0 0.00% 0.05%
Story1 35 70 pushx Min -0.004701 -0.000149 0.15% 0.00%
Story1 36 72 pushx Max 0 0 0.00% 0.01%
Story1 36 72 pushx Min -0.004701 -0.000144 0.21% 0.02%
Story1 37 74 pushx Max 0 0 0.00% 0.00%
Story1 37 74 pushx Min -0.004701 -0.00014 0.21% 0.05%
Story1 38 76 pushx Max 0 0 0.00% 0.00%
Story1 38 76 pushx Min -0.004701 -0.000136 0.19% 0.05%
Story1 39 78 pushx Max 0 0 0.02% 0.02%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


177

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 39 78 pushx Min -0.004701 -0.000132 0.06% 0.01%
Story1 40 80 pushx Max 0 0 0.07% 0.04%
Story1 40 80 pushx Min -0.004701 -0.000129 0.00% 0.00%
Story1 41 82 pushx Max 0 0 0.11% 0.06%
Story1 41 82 pushx Min -0.004701 -0.000125 0.00% 0.00%
Story1 42 84 pushx Max 0 0 0.16% 0.08%
Story1 42 84 pushx Min -0.004701 -0.000122 0.00% 0.00%
Story1 43 86 pushx Max 0 0 0.20% 0.08%
Story1 43 86 pushx Min -0.004701 -0.000127 0.00% 0.00%
Story1 44 88 pushx Max 0 0 0.22% 0.08%
Story1 44 88 pushx Min -0.004701 -0.000132 0.00% 0.00%
Story1 45 90 pushx Max 0 0 0.21% 0.08%
Story1 45 90 pushx Min -0.004701 -0.000137 0.00% 0.00%
Story1 46 92 pushx Max 0 0 0.19% 0.07%
Story1 46 92 pushx Min -0.004701 -0.000142 0.00% 0.00%
Story1 47 94 pushx Max 0 0 0.13% 0.06%
Story1 47 94 pushx Min -0.004701 -0.000147 0.04% 0.00%
Story1 48 96 pushx Max 0 0 0.09% 0.08%
Story1 48 96 pushx Min -0.004701 -0.000152 0.12% 0.00%
Story1 49 98 pushx Max 0 0 0.00% 0.00%
Story1 49 98 pushx Min -0.004701 -0.000157 0.67% 0.02%
Story1 50 100 pushx Max 0 0 0.00% 0.00%
Story1 50 100 pushx Min -0.004701 -0.000162 0.08% 0.07%
Story1 51 102 pushx Max 0 0 0.08% 0.09%
Story1 51 102 pushx Min -0.004701 -0.000167 0.04% 0.00%
Story1 52 104 pushx Max 0 0 0.00% 0.00%
Story1 52 104 pushx Min -0.004701 -0.000172 0.67% 0.02%
Story1 53 107 pushx Max 0 0 0.00% 0.00%
Story1 53 107 pushx Min -0.004697 -0.000168 0.67% 0.02%
Story1 54 108 pushx Max 0 0 0.00% 0.00%
Story1 54 108 pushx Min -0.004697 -0.000163 0.67% 0.02%
Story1 55 110 pushx Max 0 0 0.00% 0.00%
Story1 55 110 pushx Min -0.004697 -0.000158 0.09% 0.05%
Story1 56 112 pushx Max 0 0 0.07% 0.15%
Story1 56 112 pushx Min -0.004697 -0.000153 0.04% 0.00%
Story1 57 114 pushx Max 0 0 0.00% 0.00%
Story1 57 114 pushx Min -0.004697 -0.000149 0.67% 0.02%
Story1 58 116 pushx Max 0 0 0.00% 0.01%
Story1 58 116 pushx Min -0.004697 -0.000144 0.41% 0.02%
Story1 59 118 pushx Max 0 0 0.00% 0.00%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


178

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 59 118 pushx Min -0.004697 -0.00014 0.26% 0.04%
Story1 60 120 pushx Max 0 0 0.00% 0.00%
Story1 60 120 pushx Min -0.004697 -0.000136 0.16% 0.04%
Story1 61 122 pushx Max 0 0 0.02% 0.02%
Story1 61 122 pushx Min -0.004697 -0.000132 0.06% 0.01%
Story1 62 124 pushx Max 0 0 0.07% 0.04%
Story1 62 124 pushx Min -0.004697 -0.000129 0.00% 0.00%
Story1 63 126 pushx Max 0 0 0.11% 0.06%
Story1 63 126 pushx Min -0.004697 -0.000125 0.00% 0.00%
Story1 64 128 pushx Max 0 0 0.16% 0.08%
Story1 64 128 pushx Min -0.004697 -0.000122 0.00% 0.00%
Story1 65 130 pushx Max 0 0 0.20% 0.08%
Story1 65 130 pushx Min -0.004697 -0.000127 0.00% 0.00%
Story1 66 132 pushx Max 0 0 0.22% 0.08%
Story1 66 132 pushx Min -0.004697 -0.000132 0.00% 0.00%
Story1 67 134 pushx Max 0 0 0.22% 0.08%
Story1 67 134 pushx Min -0.004697 -0.000137 0.00% 0.00%
Story1 68 136 pushx Max 0 0 0.19% 0.07%
Story1 68 136 pushx Min -0.004697 -0.000142 0.00% 0.00%
Story1 69 138 pushx Max 0 0 0.13% 0.06%
Story1 69 138 pushx Min -0.004697 -0.000147 0.05% 0.00%
Story1 70 140 pushx Max 0 0 0.09% 0.08%
Story1 70 140 pushx Min -0.004697 -0.000152 0.12% 0.00%
Story1 71 142 pushx Max 0 0 0.00% 0.00%
Story1 71 142 pushx Min -0.004697 -0.000157 0.67% 0.02%
Story1 72 144 pushx Max 0 0 0.00% 0.00%
Story1 72 144 pushx Min -0.004697 -0.000162 0.08% 0.07%
Story1 73 146 pushx Max 0 0 0.08% 0.09%
Story1 73 146 pushx Min -0.004697 -0.000167 0.04% 0.00%
Story1 74 148 pushx Max 0 0 0.00% 0.00%
Story1 74 148 pushx Min -0.004697 -0.000172 0.67% 0.02%
Story1 75 151 pushx Max 0 0 0.00% 0.02%
Story1 75 151 pushx Min -0.004694 -0.000153 0.46% 0.00%
Story1 76 152 pushx Max 0 0 0.00% 0.02%
Story1 76 152 pushx Min -0.004694 -0.000149 0.46% 0.00%
Story1 77 154 pushx Max 0 0 0.00% 0.00%
Story1 77 154 pushx Min -0.004694 -0.000144 0.37% 0.01%
Story1 78 156 pushx Max 0 0 0.00% 0.00%
Story1 78 156 pushx Min -0.004694 -0.00014 0.25% 0.02%
Story1 79 158 pushx Max 0 0 0.00% 0.00%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


179

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 79 158 pushx Min -0.004694 -0.000136 0.15% 0.02%
Story1 80 160 pushx Max 0 0 0.04% 0.02%
Story1 80 160 pushx Min -0.004694 -0.000132 0.05% 0.01%
Story1 81 162 pushx Max 0 0 0.09% 0.04%
Story1 81 162 pushx Min -0.004694 -0.000129 0.00% 0.00%
Story1 82 164 pushx Max 0 0 0.12% 0.06%
Story1 82 164 pushx Min -0.004694 -0.000125 0.00% 0.00%
Story1 83 166 pushx Max 0 0 0.17% 0.08%
Story1 83 166 pushx Min -0.004694 -0.000122 0.00% 0.00%
Story1 84 168 pushx Max 0 0 0.20% 0.08%
Story1 84 168 pushx Min -0.004694 -0.000127 0.00% 0.00%
Story1 85 170 pushx Max 0 0 0.22% 0.08%
Story1 85 170 pushx Min -0.004694 -0.000132 0.00% 0.00%
Story1 86 172 pushx Max 0 0 0.21% 0.08%
Story1 86 172 pushx Min -0.004694 -0.000137 0.00% 0.00%
Story1 87 174 pushx Max 0 0 0.19% 0.07%
Story1 87 174 pushx Min -0.004694 -0.000142 0.00% 0.00%
Story1 88 176 pushx Max 0 0 0.16% 0.05%
Story1 88 176 pushx Min -0.004694 -0.000147 0.05% 0.00%
Story1 89 178 pushx Max 0 0 0.13% 0.04%
Story1 89 178 pushx Min -0.004694 -0.000152 0.13% 0.00%
Story1 90 180 pushx Max 0 0 0.00% 0.00%
Story1 90 180 pushx Min -0.004694 -0.000157 0.56% 0.02%
Story1 91 183 pushx Max 0 0 0.00% 0.00%
Story1 91 183 pushx Min -0.004691 -0.000153 0.67% 0.02%
Story1 92 184 pushx Max 0 0 0.00% 0.00%
Story1 92 184 pushx Min -0.004691 -0.000149 0.67% 0.02%
Story1 93 186 pushx Max 0 0 0.00% 0.00%
Story1 93 186 pushx Min -0.004691 -0.000144 0.44% 0.00%
Story1 94 188 pushx Max 0 0 0.00% 0.00%
Story1 94 188 pushx Min -0.004691 -0.00014 0.28% 0.01%
Story1 95 190 pushx Max 0 0 0.00% 0.01%
Story1 95 190 pushx Min -0.004691 -0.000136 0.15% 0.01%
Story1 96 192 pushx Max 0 0 0.05% 0.03%
Story1 96 192 pushx Min -0.004691 -0.000132 0.04% 0.01%
Story1 97 194 pushx Max 0 0 0.10% 0.05%
Story1 97 194 pushx Min -0.004691 -0.000129 0.00% 0.00%
Story1 98 196 pushx Max 0 0 0.13% 0.06%
Story1 98 196 pushx Min -0.004691 -0.000125 0.00% 0.00%
Story1 99 198 pushx Max 0 0 0.17% 0.08%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


180

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 99 198 pushx Min -0.004691 -0.000122 0.00% 0.00%
Story1 100 200 pushx Max 0 0 0.20% 0.08%
Story1 100 200 pushx Min -0.004691 -0.000127 0.00% 0.00%
Story1 101 202 pushx Max 0 0 0.22% 0.08%
Story1 101 202 pushx Min -0.004691 -0.000132 0.00% 0.00%
Story1 102 204 pushx Max 0 0 0.21% 0.08%
Story1 102 204 pushx Min -0.004691 -0.000137 0.00% 0.00%
Story1 103 206 pushx Max 0 0 0.19% 0.07%
Story1 103 206 pushx Min -0.004691 -0.000142 0.00% 0.00%
Story1 104 208 pushx Max 0 0 0.16% 0.05%
Story1 104 208 pushx Min -0.004691 -0.000147 0.06% 0.00%
Story1 105 210 pushx Max 0 0 0.13% 0.02%
Story1 105 210 pushx Min -0.004691 -0.000152 0.16% 0.00%
Story1 106 212 pushx Max 0 0 0.00% 0.00%
Story1 106 212 pushx Min -0.004691 -0.000157 0.67% 0.02%
Story1 107 215 pushx Max 0 0 0.00% 0.00%
Story1 107 215 pushx Min -0.004688 -0.000153 0.48% 0.02%
Story1 108 216 pushx Max 0 0 0.00% 0.00%
Story1 108 216 pushx Min -0.004688 -0.000149 0.48% 0.02%
Story1 109 218 pushx Max 0 0 0.00% 0.00%
Story1 109 218 pushx Min -0.004688 -0.000144 0.39% 0.00%
Story1 110 220 pushx Max 0 0 0.00% 0.01%
Story1 110 220 pushx Min -0.004688 -0.00014 0.27% 0.01%
Story1 111 222 pushx Max 0 0 0.00% 0.01%
Story1 111 222 pushx Min -0.004688 -0.000136 0.15% 0.01%
Story1 112 224 pushx Max 0 0 0.06% 0.03%
Story1 112 224 pushx Min -0.004688 -0.000132 0.04% 0.00%
Story1 113 226 pushx Max 0 0 0.11% 0.05%
Story1 113 226 pushx Min -0.004688 -0.000129 0.00% 0.00%
Story1 114 228 pushx Max 0 0 0.14% 0.06%
Story1 114 228 pushx Min -0.004688 -0.000125 0.00% 0.00%
Story1 115 230 pushx Max 0 0 0.17% 0.08%
Story1 115 230 pushx Min -0.004688 -0.000122 0.00% 0.00%
Story1 116 232 pushx Max 0 0 0.21% 0.08%
Story1 116 232 pushx Min -0.004688 -0.000127 0.00% 0.00%
Story1 117 234 pushx Max 0 0 0.22% 0.09%
Story1 117 234 pushx Min -0.004688 -0.000132 0.00% 0.00%
Story1 118 236 pushx Max 0 0 0.21% 0.08%
Story1 118 236 pushx Min -0.004688 -0.000137 0.00% 0.00%
Story1 119 238 pushx Max 0 0 0.19% 0.07%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


181

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 119 238 pushx Min -0.004688 -0.000142 0.01% 0.00%
Story1 120 240 pushx Max 0 0 0.16% 0.05%
Story1 120 240 pushx Min -0.004688 -0.000147 0.07% 0.00%
Story1 121 242 pushx Max 0 0 0.12% 0.02%
Story1 121 242 pushx Min -0.004688 -0.000152 0.15% 0.00%
Story1 122 244 pushx Max 0 0 0.00% 0.00%
Story1 122 244 pushx Min -0.004688 -0.000157 0.59% 0.01%
Story1 123 247 pushx Max 0 0 0.00% 0.00%
Story1 123 247 pushx Min -0.004685 -0.000153 0.48% 0.01%
Story1 124 248 pushx Max 0 0 0.00% 0.00%
Story1 124 248 pushx Min -0.004685 -0.000149 0.48% 0.01%
Story1 125 250 pushx Max 0 0 0.00% 0.00%
Story1 125 250 pushx Min -0.004685 -0.000144 0.39% 0.02%
Story1 126 252 pushx Max 0 0 0.00% 0.00%
Story1 126 252 pushx Min -0.004685 -0.00014 0.27% 0.02%
Story1 127 254 pushx Max 0 0 0.01% 0.01%
Story1 127 254 pushx Min -0.004685 -0.000136 0.14% 0.01%
Story1 128 256 pushx Max 0 0 0.07% 0.03%
Story1 128 256 pushx Min -0.004685 -0.000132 0.03% 0.00%
Story1 129 258 pushx Max 0 0 0.12% 0.05%
Story1 129 258 pushx Min -0.004685 -0.000129 0.00% 0.00%
Story1 130 260 pushx Max 0 0 0.16% 0.06%
Story1 130 260 pushx Min -0.004685 -0.000125 0.00% 0.00%
Story1 131 262 pushx Max 0 0 0.18% 0.08%
Story1 131 262 pushx Min -0.004685 -0.000122 0.00% 0.00%
Story1 132 264 pushx Max 0 0 0.21% 0.08%
Story1 132 264 pushx Min -0.004685 -0.000127 0.00% 0.00%
Story1 133 266 pushx Max 0 0 0.22% 0.09%
Story1 133 266 pushx Min -0.004685 -0.000132 0.00% 0.00%
Story1 134 268 pushx Max 0 0 0.21% 0.08%
Story1 134 268 pushx Min -0.004685 -0.000137 0.00% 0.00%
Story1 135 270 pushx Max 0 0 0.19% 0.07%
Story1 135 270 pushx Min -0.004685 -0.000142 0.02% 0.00%
Story1 136 272 pushx Max 0 0 0.16% 0.05%
Story1 136 272 pushx Min -0.004685 -0.000147 0.09% 0.00%
Story1 137 274 pushx Max 0 0 0.12% 0.03%
Story1 137 274 pushx Min -0.004685 -0.000152 0.17% 0.00%
Story1 138 276 pushx Max 0 0 0.00% 0.00%
Story1 138 276 pushx Min -0.004685 -0.000157 0.59% 0.02%
Story1 139 279 pushx Max 0 0 0.00% 0.00%

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


182

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Story1 139 279 pushx Min -0.004682 -0.000153 0.67% 0.02%
Story1 140 280 pushx Max 0 0 0.00% 0.00%
Story1 140 280 pushx Min -0.004682 -0.000149 0.67% 0.02%
Story1 141 282 pushx Max 0 0 0.00% 0.00%
Story1 141 282 pushx Min -0.004682 -0.000144 0.44% 0.03%
Story1 142 284 pushx Max 0 0 0.00% 0.00%
Story1 142 284 pushx Min -0.004682 -0.00014 0.28% 0.02%
Story1 143 286 pushx Max 0 0 0.02% 0.01%
Story1 143 286 pushx Min -0.004682 -0.000136 0.14% 0.01%
Story1 144 288 pushx Max 0 0 0.09% 0.03%
Story1 144 288 pushx Min -0.004682 -0.000132 0.03% 0.00%
Story1 145 290 pushx Max 0 0 0.14% 0.05%
Story1 145 290 pushx Min -0.004682 -0.000129 0.00% 0.00%
Story1 146 292 pushx Max 0 0 0.17% 0.06%
Story1 146 292 pushx Min -0.004682 -0.000125 0.00% 0.00%
Story1 147 294 pushx Max 0 0 0.19% 0.08%
Story1 147 294 pushx Min -0.004682 -0.000122 0.00% 0.00%
Story1 148 296 pushx Max 0 0 0.21% 0.08%
Story1 148 296 pushx Min -0.004682 -0.000127 0.00% 0.00%
Story1 149 298 pushx Max 0 0 0.21% 0.09%
Story1 149 298 pushx Min -0.004682 -0.000132 0.00% 0.00%
Story1 150 300 pushx Max 0 0 0.21% 0.08%
Story1 150 300 pushx Min -0.004682 -0.000137 0.00% 0.00%
Story1 151 302 pushx Max 0 0 0.18% 0.07%
Story1 151 302 pushx Min -0.004682 -0.000142 0.03% 0.00%
Story1 152 304 pushx Max 0 0 0.15% 0.06%
Story1 152 304 pushx Min -0.004682 -0.000147 0.11% 0.00%
Story1 153 306 pushx Max 0 0 0.12% 0.04%
Story1 153 306 pushx Min -0.004682 -0.000152 0.21% 0.00%
Story1 154 308 pushx Max 0 0 0.00% 0.00%
Story1 154 308 pushx Min -0.004682 -0.000157 0.67% 0.02%

Tabla 12_Tabla de valores de desplazamiento máximo análisis no Lineal Modal con modificación de
cubierta.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


183

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
El análisis tanto lineal como no lineal determina una secuencia de falla
como desplazamiento ultimo es de 0.46cm o 4.6 mm sin que se presente
colapso o afectaciones graves para la edificación, lo cual confirma que que
la capacidad del edificio como desplazamiento máximo de 0.7cm o 7.00 mm
como limite de su deriva se encuentra ajustada para la solicitación sísmica
exigida por la norma colombiana de diseño, además de viabilizar el proceso
de reemplazo de la cubierta por Teja de Lamina Alveolar.

Para este propósito es importante considerar las siguientes variables.

APOYOS

1. Los apoyos en las Cubiertas desde la Zona B a la Zona C, deben


garantizar su continuidad hacia la placa de entrepiso o elemento
estructural predominante como Pilar en Concreto o Columna de Acero.

2. A continuación, se presenta un esquema para garantizar dicha


continuidad de los apoyos de la cubierta.

Figura 60_Diagrama para refuerzo y consolidación de apoyos tipo (Fuente: propia)

a. Se deben ajustar las medidas de cada apoyo por independiente, en


tanto algunos son excéntricos, concéntricos y medianeros. Por Ende la
configuración puede variar.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


184

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
b. Previa a su instalación debe verificarse si los apoyos diagonales
permiten la inclusión de Platina base de sujeción a la Losa o por el
contrario debe obviarse alguno de los elementos.
c. Durante el proceso de ajuste y monte del apoyo, debe apuntalarse en
caso de ser necesaria la estructura adyacente con perfiles distanciados
a 1 del apoyo para los trabajos de maniobraje y soldadura.
d. Una vez instalado el conjunto de apoyos, debe soldarse la estructura
existente a la propuesta, siguiendo las recomendaciones técnicas del
diseñador o calculista que proyecte la nueva cubierta.
e. Bajo ninguna circunstancia deben suprimirse apoyos simultaneos.
Debe trabajarse en secuencia Lateral haciendo uno por vez y
trabajando por tramos para garantizar la continuidad de ocupación y
uso del edificio

CORROSION

3. Debe restituirse el proceso de aplicación de anticorrosivo y esmalte de


la cubierta para garantizar la conservación de la edificación en tanto no
se presentan daños o alteraciones de oxidación o perdida de la
integridad del material. Se puede desarrollar así:

a. Se debe programar por zonas y por tramos para garantizar la


habitalibilidad del Edificio.
b. Mediante Equipo de hidrolavado, es necesario remover costras de
polvo y suciedad de todos y cada uno de los elementos que conforman
la cubierta (uniones, cordones inferior y superior, y diagonales)
c. En la medida de lo posible especialmente la Zona A, Celosía de la Zona
C y Puente de la zona E debe escarificarse desde procedimientos
manuales como Lijado y cepillado o mecánicos como Chorro de arena
o agua de alta presión que Eliminen la capa de pintura y anticorrosivo
disgregado.
d. En el caso de la Zona A entre ejes 5 y 6, zona A y B, debe eliminarse
completamente la capa de corrosión y de vegetación predominante por
escorrentia de aguas lluvias que han dado lugar a especies invasivas
como musgos y lodos.
e. Aplicar Anticorrosivo especial para zonas exteriores en abundante
capa
f. Aplicar el esmalte para Acabado

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


185

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
PROYECCION DE CUBIERTA

En tanto las cargas de cubierta existentes son mayores a las proyectadas, queda
a criterio del proyectista la definición de aguas, configuración geométrica y forma
de Cubierta. Sin embargo, este estudio recomienda la siguiente posibilidad de
proyección.

Es importante anotar que la nueva estructura de Cubierta se debe fijar sobre los
nudos que conforma en cordon Superior por lo cual, la modulación del
policarbonato estará sujeta a la medida de 1.40 metros y 1.50 metros en su
sentido más corto. Esto deberá tenerse en cuenta al momento de la proyección
de detalles arquitectonicos, costos y presupuestos que prevean dicho
desperdicio.3

Figura 61_Esquema de modulación de cubierta.

186
3
La medida comercial del Policarbonato mas usada es 1.05 y 2.10 metros de ancho
INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Se puede mantener la direccionalidad de los canales actuales. Sin embargo ante
la demanda de capacidad de las cubiertas, y el índice de pluviosidad de la región
es necesario proyectar cada 3 modulos del cordon superior un Canal el lamina
Galvanizada que pueda dar abasto ante fenómenos atmosféricos previsibles y no
previsibles.

Es posible proyectar a una mayor cantidad de modulos la proyección de


cubiertas, sin que sobrepase 5 modulos, por cuanto en tema de pendientes de
desague, obligaría a generar una sobreestructura sobre la ya existente, y
generaría un sobrepeso considerable, además de cargas puntuales que
inviabilizarian la propuesta de reemplazo de cubierta. Ante esta situación cabe
resaltar también que actualmente existen sistemas de cubierta de mayor facilidad
de instalación, razón por la cual no es viable financieramente desarrollar un
sistema de cubierta que no sobrepase los 50 cm de altura desde el punto mas
alto de la estructura existente.

Peso de cubierta
Canal en Lamina galvanizada
3.6 kg/m2
calibre 22
Lamina en policarbonato 8 mm 2.73 kg/m2
Apoyos intermedios de
estructura para pendiente de 53.92 Kg/m2
canal en perfil 1.5mm
Apoyos intermedios de
estructura para pendiente de 71.07 Kg/m2
canal en perfil 2mm
Apoyos intermedios de
estructura para pendiente de 87.90 Kg/m2
canal en perfil 2.5mm
Apoyos intermedios de
estructura para pendiente de 104.42 Kg/m2
canal en perfil 3mm

Tabla 13_Tabla de valores comparativos de peso de cubierta para un caso de cubierta a dos aguas
sobrepuesta a la existente con una pendiente del 13% y configurada a mitad del total de la longitud

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


187

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
De igual Manera, el manejo de desagues particularmente para la zona A de
Acceso peatonal, y Zona E de Escaleras, debe desarrollarse en cada Eje
estructural con un Bajante de Aguas Lluvias de 4” a cada Lado. Sujeto con
Grapas hacia la estructura de columnas en Angulo. Estas pueden verter
directamente sobre la calle o direccionarse con una cañuela y/o sistema de
recolección de aguas lluvias mediante cajas o pozos.

En las zonas B, C y D, debe procurarse la verificación de descole, funcionamiento


de redes de bajantes e impermeabilización de cubiertas previo a funcionar como
colector de aguas lluvias de dichos bajantes. En caso contrario deberán
proyectarse Sistemas de Drenaje de Aguas lluvias y direccionados hacia la calle.
En la actualidad, no se presenta algún sintoma de empozamiento, filtración o
daño de dicho sistema por lo que se recomienda su impermebilización y
direcciónamiento de aguas lluvias.

4.2) CONCLUSION GENERAL

El cambio del sistema de tejas trapezoidales de lamina de Acrilico a sistema


de teja Alveolar de policarbonato se considera viable en tanto, se sigan las
recomendaciones anteriormente expuestas.

El desague de las cubiertas dependerá de la fase proyectual y de


construcción en tanto este estudio está limitado a la caracterización y
levantamiento de las propiedades actuales y posibilidades de capacidad
para soporte de una cubierta en sistema de Lamina alveolar

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


188

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Bibliografía

A., G. (2004). On Drift Limits Associated with Different Damage Levels,”


International Workshop on Performance-Based Seismic Design. McMaster
University: Department of Civil Engineering.
ALCOCER, S. H. (2013). Envolvente de Resistencia lateral de piso para
estructuras de mampostería confinada. Revista de Ingeniería Sísmica N°
89, 24-54. Obtenido de
http://www.redalyc.org/articulo.oa?id=61829627002
ALEXANDROS, L. K. (2014). Practice-oriented model for pushover analysis of a
class of timber-framed masonry buildings. Engineering Structures.
Asociación Colombiana de Ingeniería Sísmica. (2010). REGLAMENTO
COLOMBIANO DE CONSTRUCCIÓN SISMO RESISTENTE. Bogotá,
Colombia.
BONETT DIAZ , R. (2003). VULNERABILIDAD Y RIESGO SÍSMICO DE
EDIFICIOS. APLICACIÓN A ENTORNOS URBANOS EN ZONAS DE
AMENAZA ALTA Y MODERADA. BARCELONA: UNIVERSIDAD
POLITECNICA DE CATALUÑA.
BORZIA, B. P. (2008). Simplified pushover-based vulnerability analysis for large-
scale assessment of RC buildings. Engineering Structures 30, 804–820.
BURITICÁ, H. P. (2002). ESCENARIOS DE VULNERABILIDAD Y DE DAÑO
SÍSMICO DE LAS EDIFICACIONES DE MAMPOSTERÍA. Cali, Colombia:
Universidad del Valle.
ERN. (2004). Estudio sobre Desastres en Colombia: Estimación de Perdidas y
Cuantificación de Costos. Bogotá: Departamento Nacional de Planeación.
EstrucMed Ingeniería Especializada. (2015). METODOLOGÍA PARA LA
CONSTRUCCIÓN DE LA CURVA DE VULNERABILIDAD. Medellín,
Colombia.
FEMA. (1998). Handbook for the Seismic Evaluation of Buildings. Washington
D.C.: Applied Technology Council.
FEMA. (2002). Rapid Visual Screening of Buildings for Potential Seismic
Hazards-Second Edition. Washington, United States: Applied Technology
Council.
Grünthal, G., Musson, R., Schwarz, J., & Stucchi, M. (2009). Escala Macrosismica
Europea 1998. Luxemburgo: F. Lorenzo Martín.
GUEVARA , T., & GARCIA, L. (2001). El efecto de columna cortao columna
cautiva. Tecnologia y Construcción Vo. 17-1, 31-42.
HAZUS®MH-MR4. (2003). Multi-hazard Loss Estimation Methodology.
ESTADOS UNIDOS: Agency, Federal Emergency Management.
Recuperado el FEBRERO de 2015, de www.fema.gov/plan/prevent/hazus.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


189

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
IGAC. (1999). MANUAL DE RECONOCIMIENTO PREDIAL. BOGOTÁ:
MINISTERIO DE HACIENDA Y CREDITO PUBLICO.
KIM, S.-C. W. (2004). Linear static analysis of low rise buildings with flexible
diaphragms using the structural separation method. Engineering
Structures 26, 83 - 93.
MONTANA ACEVEDO, L. (2005). ESCENARIOS DE DAÑO EN BOGOTA PARA
UN EVENTO SISMICO BAJO UN MODELO PROBABILISTICO.
BOGOTA, COLOMBIA: UNIVERSIDAD DE LOS ANDES.
MORENO GONZALES, R. (MARZO de 2015). ESTADOS DEL ARTE Y
ASPECTOS CONCEPTUALES. Obtenido de TDX:
http://www.tdx.cat/bitstream/handle/10803/6247/03RMG03de12.pdf?sequ
ence=3
NSR-10. (Marzo de 2010). Norma SismoResistene Colombia NSR - 10. Bogotá:
Ministerio de Ambiente, Vivienda y Desarrollo Territorial - Asociación
colombiana de Ingenieria Sismica.
PATIÑO, P. S. (2014). Análisis estructural de diafragmas de madera. Tesis
pregrado. Quito: Universidad de Cuenca.
PIMBO, W. R. (Marzo de 2013). ESTUDIO DE LA VULNERABILIDAD FISICO
ESTRUCTURAL Y FUNCIONAL EN INSTITUCIONES PUBLICAS ANTE
EL RIESGO DE SISMOS, DESLIZAMIENTOS E INUNDACIONES EN EL
AREA URBANA DE LA CIUDAD DE GUARANDA DE FEBRERO DEL
2012 A FEBRERO DEL 2013. GUARANDA, ECUADOR: UNIVERSIDAD
ESTATAL DE BOLIVAR.
Romana, M., & Cortes, J. C. (2008). Metodologia de Inspección Técnica de
Edificios. Madrid: Universidad Politécnica de Madrid.
ROSSETTOA, T. Y. (2005). A new analytical procedure for the derivation of
displacement-based vulnerability curves for populations of RC structures.
Engineering Structures 27, 397–409.
UPC. (2013). ESTADO DEL CONOCIMIENTO SOBRE METODOLOGIAS DE
EVALUACIÓN DE VULNERABILIDAD DE EDIFICIOS. Ingenieria y
Sociedad U.C. Vol. 8 No.1, 7-28.
VALCARCEL, J. (1 de FEBRERO de 2013). ANALISIS Y GESTION DEL RIESGO
SISMICO DE EDIFICIOS Y SISTEMAS ESENCIALES. BARCELONA:
UNIVERSIDAD POLITECNICA DE CATALUÑA.
VARGAS, Y. (2013). ANALISIS ESTRUCTURAL ESTATICO Y DINAMICO
PROBABILISTA DE EDIFICIOS DE HORMIGON ARMADO. ASPECTOS
METODOLOGICOS Y APLICACIONES A LA EVALUACIÓN DEL DAÑO.
BARCELONA: UNIVERSIDAD POLITECNICA DE CATALUÑA.
Whitman, R., Reed, J., & Hong , S.-T. (1973). EARTHQUAKE DAMAGE
PROBABILITY MATRICES. Proceedings of the fifth World Conference on

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


190

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño
Earthquake Engineering, 2531-2540. Roma, Italia.
doi:http://www.iitk.ac.in/nicee/wcee/article/5_vol2_2531.pdf
YAMÍN, L. E. (2007). Estudios de ulnerabilidad sísmica, rehabilitación y refuerzo
de casas en adobe y tapia pisada. APUNTES, 286-303. Obtenido de
http://revistas.javeriana.edu.co/index.php/revApuntesArq/article/viewFile/
8984/7283
YEPEZ, M. (1996). METODOLOGIA PARA LA EVALUACIÓN DE
VULNERABILIDAD Y RIESGO SISMICO DE ESTRUCTURAS
APLICANDO TÉCNICAS DE SIMULACIÓN. BARCELONA.
ZORA, F. N. (DICIEMBRE de 2013). IDENTIFICACIÓN DEL ÍNDICE DE
VULNERABILIDAD SISMICA DE ESCUELAS DE MEDELLIN. MEDELLIN,
COLOMBIA: UNIVERSIDAD EAFIT.

INFORME ESTRUCTURAL DEL ESTADO DE LA CUBIERTA CENAF


191

Email: julianestebanortiz@gmail.com
Cel. 315 6884405
Mza. 15a casa 9 Sumatambo
Pasto Nariño