The drawings were approved in the month of September 2018. Due to water in the Budameru major
drains in rainy season the Contractor not able to take up the bridge work at Km45+020 until
December 2018. The Contractor prepared the Temporary traffic diversion road in the month of
December 2018. Due to Pethay cyclone alert (from 16-12-2018 to 20-12-2018) the drainage
Department Officials instructed to clear off the diversion road from the drain area for free flow of
flood water. Accordingly the Diversion road was partially removed. After reducing the water in the
drain Temporary traffic diversion road works were commenced and completed in the first week of
January 2019. The Contractor not started the major bridge work at this location due to his own
reasons (Contractor planned to start the bridge work after completion of raft foundation of other
bridge at Km.46+700. Due to delay in start of bridge work, the quantum of work to be executed and
by considering the past Contractor’s performance it is very difficult to complete the bridge with the
proposed extended period.