TECHNICAL SPECIFICATION OF QUOTATION

1 ページ
【TABLE OF CONTENTS】
1) General items
2) Conditions of design
3) Utility
4) Technical specification of conveyor
5) Construction and Installation work
6) Regulation of trail run
7) Assurance
8) Acceptance inspection
9) Submission documents

2 ページ
1) 一般事項
General items
1-1. Delivery
After holding and confirming the supplied drawing, we would manufacture
goods within 150 days (5 months).
1-2. Delivery address
Factory of Vina Kyouei Steel Co., Ltd
1-3. Delivery method
Before delivering equipments, we give the provisional construction and
engine trial run at the factory of SANKITECH.
After that, we would deliver to factory of Vina Kyouei Steel Co., Ltd

2) CONDITIONS OF DESIGN
2-1. Goods which being conveyed
The outbreak dusts when melting the electric furnace
Ingredients of dust Iron oxide etc,…
Granularity of dust 0.5μm 〜 15μm
Specific gravity 0.5 〜 0.6t/㎥
Temperature of dust 60℃ or under
2-2. Amount of delivered goods
Vertical conveyor 5t/h = 8.3㎥/h
Connecting conveyor 3t/h = 5㎥/h
※Specific gravity 0.6t/㎥ in calculation
2-3. Operation time
24h/day
2-4. Establishment place
Outdoor
2-5. Specification of coating
In the inside and outside furface, just paint 1 time ※ Electrostatic paint
We would paint the colors which be able to be supplied in Vietnam.
Concerning the purchased accessosies, we would paint the standard colors
of maker. The's not specification of coating thickness.

3 ページ
3) Utility
3-1. Electrical power
Power  AC380V 50Hz φ3 Voltage fluctuation within ±10%
3-2. The others
There're not compressed air and water industrial water.

4) Technical specification of conveyors


4-1. Vertical flight conveyor
① Material property of flame SS400 PL4.0t
※Steel plates which can be purchased in Vietnam

② Flight SS400 Separate structure/Fixation bolts 


Base PL4.0t/ Scraper PL3.0t
Conveying Width W360X150H 
Pitch of grader= 200mm
③ Chain Tsubakimoto brand RF03100R-2LA2-GSA
※ Chain would be used SS material,
which against corrosion of environment.

④ Length of conveyor Horizontal 3.5m+3.9m+ Vertical 13.5m = 20.9m


⑤ Motor Sumitomo Cyclo drive 6000 series
3.7kwx4P/With brake
※Due not to using outdooor, we would
establish the rainproof cover whole motor

⑥ Speed 5~15m/min Inverter


⑦ Conveying ability 5t/h = 8.3㎥/h
※Specific gravity 0.6t/㎥ in calculation

4-2. Inclining flight conveyor


① Material property of flame SS400 PL4.0t
※Steel plates which can be purchased in Vietnam.

② Flight SS400 Separate structure/Fixation bolts 


Base PL4.0t/ Scraper PL3.0t
Conveying Width W360X150H 
Pitch of grader = 600mm
③ Chain Tsubakimoto brand RF03100R-2LA2-GSA
※ Chain would be used SS material,
which against corrosion of environment.

④ Length of conveyor Horizontal 19.9m+2.4m+ Vertical 5.2m = 27.5m

4 ページ
⑤ Motor Sumitomo Cyclo drive 6000 series
2.2kwx4P/ without brake
※Due not to using outdooor, we would establish

the rainproof cover whole motor


⑥ Speed 2~6m/min Inverter
⑦ Conveying ability 3t/h = 5㎥/h
※Specific gravity 0.6t/㎥ in calculation

5) Construction and Installation work


In case of nescessaity of construction-installation work and dispatch, will give
the separate quotation. Besides, frame of vertical conveyor have to be fixed the tank,
so we will compare on installation method and quotation of this part in the meeting.

6) Regulation of trail run


The superviser of trial run will be decided same time to contruction-installation
work in the factory of customer. We will make the separate quotation.

7) Assurance
7-1. Assurance period
Assurance period would be counted within 1 year after actual work or
completing installation.
7-2. Assurance contents
In assurance period, if the customer use, follow up the using manual and
maintenance management, in case of any inconvenient and fault which
based on responsibility of customer, we will support, exchange parts or repair
speedily upon discussion with the customer.
7-3. Exemption from responsibility and outside of assurance items
① Incase of being broken down or arised problems of the being loaded
  products as bellow:
①-1. The products being wet into water.
①-2. Throwing into conveyor overloaded in comparision with regulation.
①-3. Impurities (foreign substance, lump)
①-4. Stopping process is too long, so the products being stagnated, etc.
② Broken down due to neglect the importance parts before using.
③ Fault caused by wrong maintenance・inspection・construction and

5 ページ
  Installation work
④ The faults being caused by above reasons when arising the abnormalcy.
⑤ Break-down caused by external factors.
⑤-1. Abnormalcy of utilities (electrical power)
⑤-2. Natural disasters
⑥ The arised damage, operation damage of the third party and Seika
  Corporation being caused by our products.
The other Indirect damages.
⑦ Corrosion and abrasion due to the dusts.
⑧ Special characteristic and troubles excepting specification of the products
  which being exhibited.

8) Acceptance inspection
We will set up the trial run with unburden in the factory of Sankitech VN.
Within 1 month later, setting up the burden trial run and official acceptance work
in the factory of Vina Kyouei Steel (In case of being enable to set up burden trial
run due to convenience of Vina Kyouei Steel, the official acceptance is necessary
and have to do it.)

9) Submission documents
9-1. Completed drawing
9-2. User manual
9-3. Waste parts list