Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
12/12
13/12
Membuat acuan untuk refuse bin 1m×1m dan kerja simen dilakukan
14/12
Kasar
Week 2 ( 17/12 - 21/12)
17/12
Menggali lubang pada setiap tempat yang akan masukkan tiang listrik ke dalam
lubang
Didirikan lubang
18/12
19/12
Pemasangan “cable
defect bumbung
20/12
Plaster syiling Cornice
compound
21/12
asphalt
24/12
26/12
Barrier watermark
27/12
PLAN TAPAK BINA TAMAN SERI MUTIARA
Plan column
1/1/2019
Format DO Summary
2/1
4/1
1. Box culvert is laid on sand bedding. Before placing the sand bedding, excavate deeper and placed a
layer of hard core.
2. compact sand bedding by tamping and screeded off to the required level.
3. Spread a layer of 3 mm thick mortar on top of the legs of a U-shape section to ensure uniform
bearing between the U-Shape section and lid slad
4. Filling the lifting holes with mortar or left as weep holes after installation.
5. Complete the culvert structure wing walls, construct aprons and kerb as required to prevent erosion
of the bedding.
14/1-18/1
14/1 surveying
4. Measure the antenna height above the control point or marker, either the sland height or the
vertical height.
5. Record the antenna height, point name and start time in the field notes.
receivers
15/1 CBR TEST
1. The CBR test is performed by measuring the pressure required to penetrate a soil sample with a
plunger of standard area.
2. The measured pressure is then divided by the pressure required to achieve an equal penetration on
a standard crushed rock material.
The harder the surface, the higher the CBR value. Typically, a value of 2% equates to clay, while some
sands may have a CBR value of 10%. High quality sub-base will have a value of between 80-100%
(maximum).
3. The CBR test is carried out on soils with a maximum particle size of 20mm. (Note: For material
greater than 20mm please see Plate Bearing Tests). The technique involves driving a small cylindrical
plunger (approx 50mm) into the ground at a uniform rate, using a four wheel drive vehicle as the
reaction load to provide the force.
4. Tests are normally carried out at surface level or at depths of between 500-1000mm in 20-30m
intervals along the proposed construction centreline.
6. Procedure :
1. Install the corner bead at corner window, door column and other.
2. 3.
3, Install the
step formwork
of staircase.
5.
22/1 roof trusses
2. Install the fascia board 3. install the sisalation foil and wire mesh
1) The ready mixed concrete with certain mix proportion is poured into the mould in 3 layers
and each layer must be tamped 25 times using the compacting steel. The mould in filled up by using
the hand float until it overflow and leveled the surface. Make 6 sample cubes.
2. Construction of ground floor column is initiated from starter bar of stump, pad footing or pile cap
5. Fill the formwork with concrete.Compact each layer using vibrator poker
2. Make a mix of skim coat. Mix until smooth, creamy consistency is obtained.
4. Apply the skim coat for 2nd layer. Apply between 3-5mm thickness.
28/1 boundary stone
29/1 landscape]
Perancangan
2. Membuat island
5. Pokok kecil tidak ditanam berdekatan pokok besar supaya tidak terhalang daripada
2. make the mortar mixed ratio as specified in the construction drawing / specification
3. Apply bricks for the first layer using thread.Pegs, beams, floors, and straightness tests are tested using
spirit level gauge, gauge and bracket.
1. Mark 4 corner aligned raccording to boundary stone. The centerlines are marked using wood.
2. Levelling work is done to get balanced surface. Make a wooden fence “profile board”. Height is
‘finish floor level’ ( FFL )
3. nails are driven at locations along the line which is described according to drawing, to obtain
4. the line is marked using a yarn holding between nails the lines perpendicular to the base line
5. Finally, by direct measurements from grid lines are marked to give the column centre.
13/1 corring test
2. Ketebalan sampel diukur menggunakan pita ukur. perlu dicatat didalam borang yang disediakan.
3. Lubang pengorekan perlu di tutup dengan Cold Mix atau Hot Mix dan dipadatkan dengan
sempurna
14/1 MPK inspection
JKR inspection
15/1 STP inspection
Boundary stone
18/2/2019 PILING
Mass of Hammer,W : 3T
Mass of Pile,P1 :
Temporary Compression :
Drop of Hammer,h :
Coefficient of Resitution,o :