Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
'Commencement Date" shall refer to the date specified in the Contract for
the turn-over of physical possession ofthe Site to the Contractor.
' ~ o m ~ l e t i &Date" shall refer to the date specified in the Contract for the
completion of the Works, or in the event that the date specified in the
Contract as the Completion Date is extended in accordance with GC-7, then
the date as modified or re-calculated in accordance thereto.
'Contract" shall mean the principal written agreement entered into between
the Owner and the Contractor for the purpose of executing and completing
the Works.
"Contract Documents" shall mean the set of agreements entered into by the
Owner and Contractor for the purpose of evidencing the terms and conditions
accepted and understood by them for the execution and completion of the
Works. The documents constituting the Contract Documents are specified in the
Contract in the order of their priority, and are intended to be read and
construed as a single contract. Each document is intended to be complementary
to the other documents even if reference to the other documents is not made in
any one document. However, in case of any conflict in the application or
interpretation of provisions found in two or more documents, the document
which the Contract specifies as having a priority over the others will prevail.
Should there be any conflict between documents belonging to the same class,
such as a conflict between drawings, or between specifications, the Contractor
shall be deemed to have included in the Contract Price, the higher cost of
undertaking the Works.
"Contract Price" shall mean the total sum of money which the Owner is
obligated t o pay the Contractor under the Contract for the execution and
completion of the Works.
"Contractor" shaU mean the party named in the Contract which shall be
principally responsible for the execution and completion of the Works.
'Force Ma-ieure" shall mean an act of nature, God or man which is beyond
the control of the Owner or Contractor. For purposes of the Contract
Documents, Force Majeure shall include (i) rebellion, armed uprising, riot,
civil commotion or any act of terrorism; (ii) a court or government order
enjoining or prohibiting the execution of the Works; (iii) natural calamities,
such as widespread flooding, typhoons for the period when typhoon signal
No. 3 is hoisted in the Metro Manila area by the Philippine Atmospheric
Geological and Astronomical Administration (PAGASA) or exceptionally
adverse weather conditions (established in relation to PAGASA7s historical
weather records over a period of not less than ten years); provided that, rain,
wind, flood or other natural phenomena of inconsequential degree for the
locality of the Site shall not be considered Force Majeure; and (iv) strikes,
lockouts, or work stoppages of a city-wide or regional scale affecting any of
the trades employed upon the Works or any of the trades engaged in the
preparation, manufacture or transportation of any of the goods or materials
required for the Works or caused by concerted mass action on the part of the
Contractor's employees which are illegal per se or later determined to be
illegal by the appropriate government agency.
'Interim Certificate" shall refer to the certificate attesting t o the portion of the
Contract Price to be due to the Contractor upon the lapse of a given period or
upon the completion of a portion of the Works prior to Completion Date, as
provided for under the Contract, signed by the Project Manager, approved by the
Project Director and issued to the Contractor pursuant to GC-9(C).
"Proiect Director" shall mean the head of the Project Management Team and
the principal representative of the Owner.
"Proiect Management Team" shall mean the group headed by the Project
Director cnmposed of the persons and entitles who will be responsible for
executing and completing the Works, either directly or through properly
authorized agents, including without limitation, the Project Manager,
architect, engineers, Quantity Surveyor, consultants and other personnel
directly reporting to the Owner, the respective obligations of whom are set
forth in Exhibit A.
"Proiect Manaeer" shall mean the person or entity chosen by the Owner to
perform the functions specified herein and as set forth in Exhibit A.
'Provisional Sum" shall refer to a portion of the Contract Price which is so
designated in the Bills of Quantities for the execution of work, supply of goods,
materials or services or for contingencies, which may be used in whole, in part
or not at all at the direction and instruction of the Project Director.
"Site" shall mean the place or area where the Works will be executed.
'Variation" shall mean any change in the terms of the Contract Documents for
the execution and completion of the Works (other than an increase in the cost of
supplying labor as a result of an increase in minimum wages as mandated by the
applicable Statute) which will alter the ultimate use to which the Works will be
put or the manner in which the Works will be executed and completed. A
Variation shall include (i) the addition of fbrther works, materials or goods;
(ii) omission from the Works of certain types of work, materials or goods; (iii)
demolition or removal of part of the Works; (iv) substitution of different work,
materials or goods; (v) changes in the type, standard or quality of the Works;
(vi) changes in the plans, elevations, lay-out or dimension of the Works; (vii)
changes, additions or omissions ordered in the Works by the Project Director
to be carried out by any Nominated Sub-contractor/Supplier, or other
contractor or supplier; and (viii) postponement of the execution of part of the
Works as ordered by the Owner.
'Warrantv Period" shall refer to the period of one year fiom the issuance of
the Certificate of Acceptance of the Works by the Owner during which the
Contractor warrants the Works against all defects, errors o r omissions in or
of workmanship and materials firnished by the Contractor, Nominated Sub-
contractorfSupp1ier or any other sub-contractor/supplier working under the
attendance, direction or supervision of the Contractor, and as part of such
warranty, the Contractor agrees to undertake or to commence remedial or
corrective measures to correct all defects, errors or omissions from receipt of
a written notice from the Owner pursuant to GC-lo@).
'Works" shall mean the building, structure or any other form of permanent
improvement or facility resulting fiom the execution and completion of
construction activities by the Contractor pursuant to the Contract Documents,
including temporaty improvements or facilities required for the execution
and the maintenance of the building, structure or permanent improvement to
be constructed or installed pursuant to the Contract.
A. Master Program: Following the approval of the Contractor's bid or proposal and
within the period of specified in the Contract Documents (or in the absence
- thereof, within the period of fifteen days following such acceptance), the
Contractor shall submit to the Project Director for his approval a Master
Program showing the order or sequence in which the Works will be executed
and any relevant temporary works or methods of work which may be
relevant to such sequence or order, together with a Cash Flow Forecast
which predicts the amount of interim payments payable in accordance with
the Contract Documents. The Contractor will update the Master Program
within fourteen days from any extension of time award given under GC-7.
The approval of the Master Program by the Project Director shall signify the
Owner's agreement with the proposed order or sequence in which the Works
shall be executed, and shall be taken into account in determining a
reasonable order or sequence for the Contractor to supply any outstanding
information or details to the Project Director, but shall not otherwise change
the contractual obligations of either party in relation to the Completion Date
or as to a reasonable time for giving or receiving further information. In the
event, however, that tlte Contractor incurs delay of at least thirty days in the
execution of the Works based on the Master Program for reasons that do not
entitle the Contractor to an extension of the Contract Period, then the
Contractor shall within seven days from the request of the Project Director
submit a revised Master Program to show how the Contractor intends to meet
the Completion Date pursuant to GC-I 1(A). .
C. Possession of the Site: In the absence of any provision in the Contract to the
contrary, free and uninterrupted possession of the whole of the Site shall be
given to the Contractor on the Commencement Date. Upon the
commencement of such possession, the Contractor shall be deemed to have
inspected the Site and to have filly taken into account the conditions which
may affect the nature, extent and cost of executing the Works in the Site;
including the nature of the soil, any customs duties or clearance fees,
restrictions and conditions affecting the Site. Consequently, the Owner shall
in no way be responsible for any cost or expense which may develop on
account of the failure of Contractor to make an accurate examination of
present or future factors related to possession of the Site which may
adversely affect the execution and completion of the Works in accordance
with the Contract Documents. If, at any time during the execution of the
Works, the Project Director requires the Contractor to make boreholes or t o
carry out exploratory excavation on the Site, the requirement shall be
considered a Variation, unless an item or a Provisional Sum in respect of
such work is included in the Bills of Quantities.
D. Quality of Goods. Materials and Workmanship: Upon the possession of the Site
on Commencement Date, the Contractor shall then proceed to execute and
complete the Works diligently and with due expedition using methods of
construction which are in accordance with sound practice and which are not
likely to endanger any existing structure, finish, adjacent property or the safety
of members of the public. Without prejudice to the generality of the foregoing,
the Contractor shall carry out the Works in a good and workmanlike manner,
using goods, materials and labor which, unless otherwise stated in the Contract
Documents, shall be of the best of their kind and shall strictly comply with the
specifications and the purpose for which they shall be used under the Contract
Documents. The Contractor shall upon the request of the Project Director
provide the necessary evidence and information confirming that the materials,
goods, labor or workmanship used in the Works comply with this Condition.
The Contractor's failure to so provide the evidence and information required
under this-condition shall provide the Project Director with sufficient basis to
order the removal of the goods, materials or stoppage of labor at the expense of
the Contractor and to deduct the cost thereof from the Contract Price if not
fohhwith replaced by the Contractor with the kind of goods, materials and labor
which comply with the Contract Documents and adequately fulfill the
requirements of this Condition. For this purpose, the Project Director stlall have
the right to object to and require the Contractor to remove and to permanently
bar from the Site any person employed by the Contractor in the execution of the
Works who in the opinion of the Project Director is guilty of misconduct, is
incompetent or nezligent, in the proper performance of his duties or whose
employment is otherwise considered by said Project Director to be undesirable.
Unless the Contract expressly states otherwise, the Contractor shall provide
the Site with the plant, eoods and materials necessary for the due and timely
performance of the Works in the Site, and shall not remove the same from the
Site until the completion of the Works without the prior written consent of the
Project Director. If the plant or equipment to be used in the completion of the
Works is not owned but only leased from a third person by the Contractor, then
the Project Director shall not be obliged to accept such plant or equipment
unless the Contractor is able submit a written agreement from the lessor or
owner of such plant or equipment for the use of such plant or equipment in the
Site until the completion of the Works and the assignment of such lease to the
Owner in the event that the Contract is terminated before the completion of the
Works or the Contractor defaults under the terms of the lease entered into with
such Owner.
k
E. O~eningUu And Testin?: The Contractor shall noti@ the Project Director in
writing before executed Works are covered up and shall give him at least
three working days' prior written notice to inspect executed Works. Unless
the Contractor does so, the Owner shall not be liable for the cost to the
Contractor of opening up, inspecting or testing executed Works, nor will any
extension of time be granted to the Contractor for any delay caused thereby.
The Contractor shall comply with instructions from the Project Director
made at any time after the 3-day period herein specified for the opening up
or inspection of any executed Works or for carrying out tests or
investigations of any goods, materials or finished Works, and for the
postponement of the execution of firther Works until such tests are
completed. If such opening up, inspection or investigation is the reasonable
and prudent consequence of defective work by the Contractor or by reason of
its negligence or omission, such investigation, inspection or opening up shall
be done at the expense of the Contractor and shall not be used as basis for
any extension of time. In all other cases where there is no breach, omission
or fault of the Contractor, the opening up, tests or investigations conducted at
the request of the Project Director shall be done at the expense of the Owner
and shall entitle the Contractor to an extension of the Completion Date, if
appropriate, unless and to the extent that defective work or any of the
Contract Documents is disclosed thereby.
F. Care and Maintenance of the Works: The Contractor will be &lly responsible
for the care and maintenance of the Works from the Commencement Date
until the Works are completed and accepted by the Owner. The Contractor
will be filly responsible for the care of and safekeeping of all temporary
buildings, plant, goods, materials and things brought to Site in connection
with, or for the purpose of executing and completing the Works. Unless the
Contract should provide otherwise, the Contractor shall be filly responsible
for the adequacy, design, stability and safety of all Site operations, temporary
works and methods of construction.
G. No Desisn Resaonsibilities: Except when the Contract provides to yhe
contrary or leaves the design, specifications or choice of materials to be used
in the Works to the Contractor or Nominated Sub-contractor/Supplier, the
design and/or specifications of the Works shall be provided to the Contractor
for the account of the Owner. The Contractor shall not be responsible for the
design or specifications of the Works, or for the suitability of such design or
specifications to the purpose for which the Works shall be used or occupied,
provided that in this case, the Contractor shall have complied with all the
requirements imposed upon it under the Contract Documents for the proper
and due execution and completion ofthe Works. Notwithstanding the absence
of responsibility of the Contractor with respect to the design or specificat~ons
- of the Works (unless the Contract provides otherwise), the Contractor shall
have the duty to warn the Project Director if any insufficiency in the design
or specifications is discovered as the Works are being executed.
H. Divergence: The Contractor shall within thirty days after the Contract has
become effective carehlly check the Contract Documents for any discrepancy or
divergence between or among the said documents and verify all dimensions
shown on the contract drawings before use. The Contractor will immediately
issue a written notice to the Project Director if any discrepancy or divergence
should be found between or among the Contract Documents, or between any
Contract Document or Statute, or between any of the Contract Documents and
any instructions issued to the contractor. Forthwith upon the receipt of such
written notice, the Project Director shall issue instructions to the Contractor to
verify the divergence or inconsistency. If a portion of the finished Works needs
to be rectified or any of the Works needs to be aborted following the verification
of such divergence or discrepancy, then the work to be done in rectifying or
aborting the Works shall be deemed a Variation and covered under GC-4 and an
appropriate valuation thereof andlor extension of the Completion Date shall be
made in accordance with GC-7; provided that, in the event that the divergence
or discrepancy could have been discovered earlier by the Contractor using due
skill and care, then the cost to be incurred in rectifying or aborting the Works
shall be for the account of the Contractor.
-Com~liancewith Statutes; The Contractor shall comply with and give all
notices required or which shall become required by Statutes t o the extent
applicable to the Works, including without limitation, all restrictions imposed on
the execution of the Works in connection with pollution (including noise
pollution) and the use of hazardous materials In case the Site is within any of its
Owner's controlled commercial or residential develop~nentsor subdivisions, the
Contractor shall in addition comply with the construction guidelines drawn up
by the Owner for such development or subdivision, including the payment of
the necessary fees and charges covering security and janitorial services for the
perimeter of the Site as required under such guidelines. When particular
requirements are set out in the Bills of Quantities, the Contractor shall be
deemed to have allowed for compliance with these requirements as well.
The Contractor shall only carry out noisy or vibratory operations during
working hours and shall execute the Works on non-working days as may be
designated or approved by the relevant authority and without complaint
from the neighboring properties.
J. Taxes. Permits and Fees: The Contractor shall pay for all taxes (including
income and value-added taxes), fees and assessments imposed or t o be
imposed by the national, provincial, city, municipality or barangay
government in connection with the performance of the Works and all taxes,
benefits, Social Security contributions, levies or fees that the Statutes require
t o be paid in connection with the employment of the Contractor's personnel,
consultants or agents. The Contractor shall secure all necessary permits and
pay any fees or charges legally demandable, or which shall become legally
demandable under the Statutes. Unless the Contract Documents provide
otherwise, such fees, or charges are deemed to have been included in the
Contract Price even if not specifically set out in the Bills of Quantities.
The Contractor shall, upon demand by the Owner, produce and make available
for inspect&, examination and/or reproduction its payrolls, vouchers and other
papers in order to ascertain that the Contractor has fully complied, or is hlly
complying, with its obligations under this Condition, including official receipts
of payments of the required contributions and fees to the Social Security
System, Medical Care Commission and State Insurance Fund, as well as
payments for taxes due to the govenunent by reason of the Works.
K. Owner's Access: The Contractor shall permit the Project Director, Project
Manager, Quantity Surveyor or any member of the Project Management Team,
as the Project Director may require, access to the Works and to the workshops or
other places of the Contractor where work is being prepared for the Contract.
When work is to be so prepared in workshops o r other places of a sub-
contractor, the Contractor shall by a term in the sub-contract secure a similar
right of access to those workshops or places for the Project Director, Project
Manager, Quantity Surveyor or other members of the Project
AUOENCON
10119/95
Management Team, and shall do all things reasonably 'necessary to make
such access effective. The Contractor shall provide the necessary facilities at
the Site to enable the Project Director and the other representatives of the
Owner and their respective staff to hold ofice and conduct periodic
inspections of the Works in progress.
- to time. It is specifically acknowledged and agreed that the exercise by the Owner of its
rights pursuant to this Condition shall not constitute taking possession of the whole or
any part of the Works.
0. Drawings: The Contractor shall be entitled to receive from the Project Director
two copies of the contract drawings, one copy of whjch shall always be kept in
the Site for use by the Project Director or Project Manager, and copies of such
fbrther drawings, schedules or details as necessary to explain, clarifjl or amplif4r
the contract drawings and enable the contractor to carry out and complete the
Works in accordance with the Contract Documents. At the request of the Project
Director, the Contractor shall submit working drawings at such times as to
prevent delay in the execution of the Works or the work being undertaken by
Owner's design team. These working drawings may be rejected, approved or
amended by the Project Director. If the working drawings are rejected, the
Contractor shall revise them as necessary and re-submit the revised working
drawings for approval of the Project Director. No claims for extra payment or
extension of time will be accepted in connection with the disapproval of work
drawings or their subsequent amendment. On the other hand, the submission to
and approval by the Project Director of such working drawings (and any revision
thereof if applicable) shall not relieve the Contractor of any of its duties or
responsibilities under the Contract Documents. The Contractor shall make
accurate records of parts of the Works
which will become hidden from view as the execution df the Works
progresses, as may be directed by the Project Director. Such records shall be
checked and verified by the Project Director while the affected part o f the
Works is open for inspection, and the print of such records shall be
submitted to the Project Director as soon as practicable.
P. Establishing Levels and set tin^ Out Data: The Contractor shall determine a
datum level with the Project Director which may be required for the
execution of the Works based on accurately dimensioned drawings and such
information to be supplied by the Project Director as shall enable the
Contractor to set out the Works at ground level. Any errors arising fiom
inaccurate setting out by the Contl-actor shall be amended by the Contractor
at its own cost, or with the Owner's consent, accepted without amendment;
provided that in the latter case, t1,c Contract Price shall be reduced to take
into account any loss of value suffered by the Owner as a result of such error
o r the reduced cost to the Contractor resulting from the error, whichever is
determined to be greater. The checking of any setting out or of any line or
level by the Project Manager shall n o t in any way relieve the Contractor of
its responsibility for the correc~ic,;?~thereof
All o!)c!:..!i:olis necessary for the execution and completion of the Works and
the rc:ii.- :.:;i~lgof any defects therein shall, so far as compliance with the requir
.:ii.-.ilts of the Contract permits, be carried on so as not to interfere unnecess;!rilv
or improperly with the convenience of the public, access to, use and
oici~l~ationof public or private roads and footpaths to or of properties
whetlic. lii i l ~ epossession of the Owner or of any other person. For this
purpose:, ;he Contractor shall save harmless and indemnify the Owner in
respe-.! ..i all claims, proceedings, damages, costs, charges and expenses
what:;;,^. ,. ;:rising out of, or in relation to, any such matters insofar as the
Cont i.2 -:, . ,i. is responsible therefor.
-.
12 ‘ NJG ENCON
10/19/95
The Contractor shall use every reasonable means to prevent any of the roads
or bridges communicating with or on the routes to the Site from being
damaged or injured by any traffic of the Contractor or. any of their sub-
contractors. In particular, the Contractor shall select routes, choose and use
vehicles and restrict and distribute loads so that any such extraordinary
traffic as will inevitably arise fiom the moving of materials, plant,
Contractor's equipment or temporary works from and to the Site shall be
limited, as far as reasonably possible, and so that no unnecessary damage or
injury may be occasioned to such roads and bridges.
S. Compliance with Instructions: The Contractor shall forthwith comply with all
instructions issued by the Project Director in regard to those matters where the
Project Director is expressly empowered by these General Conditions to issue
- instructions, which shall include the following:
(i) the Project Director may require the Contractor to open up for
inspection any work covered up or to arrange for or carry out any test of any
materials or goods (whether or not already incorporated in the Works) or of
any executed work;
(ii) the Project Director may require the rectification or removal from
the Site of any work, materials or goods which in the Project Director's
opinion are not in accordance with the Contract Documents;
(iii) the Project Director may require the acceleration of the construction
of the Works, or the alteration of the sequence of timing of any part of the
Works; provided that, before commencing any work in connection
with the same, the Contractor shall, within ten days of receiving the
instruction issued under this clause (iii), submit a detailed account of the time
and cost implications of complying with the instruction, including all direct,
indirect and consequential costs. Upon receipt of the detailed account
required under clause (iii) from the Contractor, the Project Director may in
writing either (1) accept the detailed account, in which case it will be binding
on both parties as regards time and money; (2) reject the detailed account and
withdraw the instruction, and in which case, no adjustment to the Contract
Price or Contract Period will be allowed; (3) reject the detailed account and
allow the instructions to stand, in which case, the valuation of such
instruction will then be made in accordance with GC-4(C), GC-4(D) and GC-
9(F). In no case shall the Contractor be required to accelerate when, within
seven days of receiving the instruction from the Project Director, the
Contractor makes representations in writing that such acceleration is, under
the circumstances, unreasonable or totally impractical and the Project
Director agrees with the representation made.
If the Contractor does not comply with any instruction issued in writing by
the Project Director, when the Contractor is required to do so by these
General Conditions, then not less than three (3) days from the Contractor
receipt of such the instruction, the Project Director may (but not vexatiously)
issue a written notice requiring immediate compliance. If within seven days
after receipt of such notice, the Contractor has still not complied, the Project
Director, without prejudice to the exercise of the remedies o f the Owner under
GC-I l(C), may employ and pay other persons t o execute any work which may
be necessary to give effect to such instruction. All costs incurred in connection
with such employment may be deducted by the Owner from any monies due or
to become due to the Contractor under the Contract or may be recoverable from
the Contractor by the Owner as a debt.
These representations and warranties shall survive the execution of the Contract
Documents and shall subsist and be filly effective during the entire Contract
Period.
A. Nomination by the Owner: The Owner shall have the discretion to choose sub-
contractors to perform specific work or supply materials or goods for the Works
in the following instances:
(i) Where a certain item of work or specific goods or materials ire
identified in the Contract Documents as a Prime Cost Sum, or where the work to
be performed by a particular sub-contractor or suppIier cannot be sufficiently
precisely described for pricing purposes at the time of the bidding or
negotiation, the Owner shall have the right to select a sub-contractor to carry out
work or supply any goods or materials so described.
(ii) Where work, materials or goods are identified as 'Provisional" or
'Provisional Sum" in the Contract Documents, the Owner shall be entitled to
either select sub-contractors or suppliers to carry out or supply some or all of the
work or materials or goods so described or shall instruct the Contractor to
carry out or supply some or all of such work or materials or goods itself.
. Where an amount is stipulated in the
(iii)
Contract Documents as a 'Contingency", 'Contin~encyItem"
or 'Contingency Sum'', the Owner may, but shall not be bound to, give instructions
for the carrying out of work under such items.
Acceptance bv the Contractor:, In the event that the Owner elects to designate
certain sub-contractors and suppliers to undertake specific items of work or to
supply specific goods or materials under GC-3(A), and the Contractor accepts
and approves of the nomination of these sub-contractors or suppliers, the
Contractor shall become hlly responsible for all Nominated Sub-
ContractorslSuppliers, and for any default or breach of contract on their part in
the same way and to the same extent that the Contractor is liable for its
performance of the Works or those of other sub-contractors selected and
engaged by the Contractor. In this case, the Owner shall in no circumstance be
liable to the Contractor for the default of any Nominated Sub-
Contractor/Supplier. Without prejudice to the generality of the foregoing, the
Contractor shall be deemed to have accepted as its own responsibility under the
Contract Documents all the obligations expressly or impliedly undertaken by
Nominated Sub-Contractors/Suppliers under their respective sub-contracts,
including any obligations as to the design, suitability, quality or performance of
their work, materials or goods, or in regard to providing d e s i ~ nservices and
whether or not such obligations are espressly mentioned or repeated in the
Contract Documents. In particular, in cases where the Owner relies, and having
regard to all the circun~stancesmay be reasonably expected by the Contractor to
have relied, upon the skill and judgment of a Nominated Sub-
ContractorISupplier for the design or suitability of the latter's work or materials,
the Owner shall for the purposes of the Contract Documents be deemed to have
so relied upon the skll and judgment of the Contractor.
For the purposes of this GC-3(D), a valid objection shall, in a case to which
paragraph (ii) applies, mean an objection justified on the available known
facts at the time of the Owner's designation of the sub-contractor/supplier, and
a valid objection in a case which falls under paragraph (i) shall be one which
was made prior to entering into the relevant sub-contract.
Options of the Owner in the Event of Obiections under GC-3(D)(i): Where the
Contractor raises a valid objection to a sub-contractor/supplier chosen by the
Owner for the reasons under GC-3(D)(i), the Owner may, as an alternative to
ALIGENCON
10/19/9J
making a further designation either (i) instruct the Contractor itself to carry out
or arrange to carry out or supply the work or materials o r goods as in CC-3(E),
and payment for such work, materials or goods will be on the same basis as
provided for under GC-3O.I);or (ii) instruct the Contractor to enter into the sub-
contract notwithstanding any term validly objected to by the Contractor. In such
event no liability shall be imposed under the Contract Documents upon the
Contractor in respect of the work, goods or materials of the Nominated Sub-
ContractorISupplier to the extent that the Contractor, by reason of the terms of
the sub-contract it objects to, is unable to impose a corresponding liability upon
the Nominated Sub-ContractorlSupplier, and the Owner will to the same extent
indemnify the Contractor against any damage, loss, expenditure or claim arising
as a consequence of the term it objects to. Whenever circumstances warrant, the
Owner shall also extend the Completion Date for the Works or affected portion
thereof.
H. Pavment for Work by the Contractor: In the event that the Owner exercises its
option under.GC-3(E) and 3(F) to instruct the Contractor to do some or all of the
work or supply some or all of the goods or materials which was intended for a
specific sub-contractor/supplier, or the Contractor elects to do the work
intended for the Nominated Sub-contractor/Supplier under GC-3(G), the sum
due to the Contractor for the said work or materials or goods shall be valued in
accordance with the provisions for valuing Variations under GC-4, except in
cases where the Contract Period and any preliminary items of expenditure i n the
Bills of Quantities shall be deemed to be inclusive of such work or materials as
are described in or to be inferred from the relevant Prime Cost Sum or
Provisional Sum items (unless materially altered in kind or extent so as to
constitute a Variation).
ALIGENCON -
10/19/95
(iv) bonds or insurance policies required to be submitted hereunder
shall'be issued by companies acceptable to the Owner, and unless otherwise
stated in the Contract, the cost of obtaining such bonds and insurance
policies and maintaining the same throughout the period required under GC-
5(A) shall be borne by the Contractor.
G. Other Indemnities: The Contractor shall take all necessary precautions and
exercise due care and diligence in the execution of the Works so as not .to
cause injury, damage or loss to any person and property. The Contractor shall
hold the Owner free and harmless from all claims for injuries, damages or
losses to persons and property, and shall indemnifjr it for whatever
payments, fines or damages it is made to pay or suffer by reason of any act,
accident or occurrence caused by or attributable to the fault, negligence or
deliberate act of the Contractor who shall obtain and keep in force during the
lifetime of the Contract adequate insurance coverage therefor, including
third-party liability and all-risk insurance coverage.
B. Errors or Omissions in the Bills of Quantities: The quantity and quality of the
Works included in the Contract Price shall be deemed to be that which is set out
in the Bills of Quantities and as shown in the drawings and as described in the
specifications. Any error or omission in either description or quantity in the Bills
of Quantities shall not vitiate the Contract or release the Contractor from any
obligations, duties, responsibilities or liabilities under the Contract. Such errors
will be corrected and treated as if they were a Variation instruction issued by the
Project Director under GC-4; provided that, no adjustment in the Contract Price
or Completion Date will be made due to any errors in rates, calculations or
computations made by the Contractor.
Provisional Sums and Prime Cost Sums: The payment of the portion of the
Contract Price which is described in the Bills of Quantities as Provisional Sums
and Prime Cost Sums shall be made to the Contractor subject to the condition
that the Project Director shall have approved and issued instructions in regard to
the expenditure of such sums and to the execution of work or use of materials
corresponding thereto in the Bills of Quantities. If required by the Project
Director, the Contractor shall, within seven days of the Project Director's written
request, submit a detailed estimate of the value of work for which a Provisional
Sum is included in the Bills of Quantities. A11 quantities marked provisional or
approximate in the Bills of Quantities will be subject to remeasurement and the
I
I
final quantities at the rate specified in the Bills of Quantities shall be deducted
from the Contract Price and the value added to the Contract Price for the i
purpose of computing the Final Account [in
accorhnce with GC-4(C)1.
28 - ALIGENCON
10119/95
i
IGC-7: EXTENSION OF CONTRACT PERlOD I
Justified Extension of Completion: Upon it becoming reasonably apparent that
the progress of the Works is delayed or is likely to be delayed, the Contractor
shall immediately give written notice thereof to the Project Director, together
with fully substantiated details of the cause of the delay and estimated length of
delay. If the Project Director is of the opinion that the completion of the Works
is likely to be, or has been delayed beyond the Completion Date or beyond any
extended time previously fixed under this GC-7 by reason o f
(i) Force Majeure directly affecting the Site;
(ii) issuance by the Project Director of instructions authorizing a
Variation;
(iii) the failure by the Contractor to receive In due time all the necessary
instructions, drawings, details or levels from the Project Director or Project
Manager which were specifically applied for in writing by the Contractor on a
date which having regard to the then Completion Date was neitl~er
unreasonably distant from nor i~nreasonablyclose to the date on which it was
necessary for the Contractor to receive the same; provided that, the delay was
not due to any delay by the Contractor in providing information or working
drawings as required under GC-'(0);
(iv) delay on the part of artists, tradesman or others engaged by the Owner
in executing work not forming part of the Contract;
(v) opening up for inspection of any work covered up or of the testing of
any of the work, materials or goods in accordance with GC-2(E), unless the
inspection or test showed that the work. materials or zoods were not. in
accordance with the Contract Documents, or was as a result of the Contractor
covering up work before giving notice for inspection;
(vi) compliance with the provisions of GC-14(A) or with Project
Director's instructions issued thereunder;
(vii) any delay caused by prevention or suspension ordered by the
Owner;
(vii) existence of physical obstructions or physical conditions, other than
climatic conditions on the Site, which could not have been foreseeable by an
experienced contractor; or
(viii) any delay or prevention on the part of the Owner;
then the Project Director shall request the Project Manager to assess the length
of the extension of the Completion Date which is required to complete the
Works. Such assessment shall be presented to the Owner for approval. A request
From the Contractor for an extension of the Completion Date due to the
occurrence of an event other than those specified in the preceding sub-paragraph
will be denied, it being understood that the contractor shall do all that may
reasonably be required to proceed with the completion of the Works within the
Contract Period specified in the Contract.
B. Contractor's Obligation to Prevent Delay. In the event that the Owner
approves an extension of the Completion Date, and upon written notice, the
Contractor shall provide the Project Director within twenty-eight days from
the occurrence of such event with full details of the effect of the event on the
progress of the Works, on other trades or activities including the works of
Nominated Sub-Contractors/Suppliers or other sub-contractors/suppliers,
on the Site and the steps to be taken by the Contractor t o comply with its
obligation to prevent the delay.
Within six months fiom the issuance of the Certificate of Acceptance from the
whole Works, the Project Director shall fix the Completion Date having due
- regard to all matters notified by the Contractor under GC-7(A).
-- -- - I
PC-8:CONTRACTPRICE
A. Fixed Lumu Sum: Unless the Contract provides otherwise, the Contract Price
shall be deemed to be a fixed lump sum price which constitutes the complete
consideration or payment for the quantity and quality of work specified in the
Contract Documents and shall not be subject to any adjustment except to the
extent allowed under GC-9(B). The quality and quantity of the Works included
in the Contract Price shall be deemed to be that which is set out in the Bills of
Quantities and as shown in the drawings and as described in the specifications.
The Contract Price shall be deemed to include all costs to the Contractor for
materials, tools, equipment, labor, overhead and profits and specifically shall
include but not limited to, insurance premiums, escalation costs of materials,
contingencies other than Force Majeure, overtime or extra work, Site delivery
charges, warehouse and purchasing costs, local and national income, personal
and corporate taxes. The currency of the Contract is Philippine Pesos. No
adjustment shall be made to the Contract Price for any fluctuation in exchange
rate against any other currency. The Contractor represents that in proposing or
agreeing to the Contract Price specified in the Contract that it has taken into
account any possible escalation in the cost of Contractor-supplied materials or in
the cost of the use of Contractor-provided tools and equipment or the escalation
in the foregoing costs by reason of any delay, whatever may be the period, in
completing the Works due to causes directly o r indirectly attributable to or
caused by the national, provincial, city or municipal government or any agency,
entity or official of the government, or any firm, company or person. The
Contractor also confirms that the rates and sums included in the Bills of
Quantities are adequate and provide for all matters and things necessary to
achieve the proper and timely completion of the Works.
ALIGENCON
10119/95
within the Contract Period, the Owner agrees to adjust the Contract Price to
take into account the increase in minimum wages required to be given by the
Contractor to the persons employed by or under contract with the Contractor
for the execution of the Works who will be affected by such increase in
minimum wage, subject to the condition that all work activities of the
Contractor are on schedule on the date the increase in minimum wage takes
effect. Any additional cost to be incurred by the Contractor arising from the
increase in minimum wages shall be subject to evaluation by the Quantity
Surveyor and Contractor. The actual amount of the increase in the Contract
Price arising by reason of an increase in minimum wages shall be subject to
the mutual agreement of the Owner and Contractor.
.
C. Lumw Sum Price for a Section of the Works: Where the price for a section of the
Works is a lump sum price based on the drawings and/or specifications and not
based on rates specified in the Bills of Quantities, the quality and quantity of the
work for such section included in the Contract Price shall be deemed to be that
which is shown by the drawings and/or described in the specifications; provided
that: (j) if any discrepancy or divergence is found between the working drawings
and the specifications, the specifications shall take precedence over the working
drawings, unless otherwise specifically stated to the contrary in the
specifications; and (ii) any error in the description, quantity or omission of items
from the drawings and/or the specifications shall not vitiate the Contract but
shall be corrected and shall be deemed to be a Variation required by the Project
Director and subject to GC-4.
D. Provisional Sums and Prime Cost Sums: The Contractor shall be deemed .to
have made due allowance in the Preliminaries section of the Bills of
Quantities for Provisional Sum and Prime Cost Sum work. If Provisional
Sums or Prime Cost Sums are not expended in accordance herewith, the
portion of the Contract Price corresponding to Preliminaries will be reduced
and such reduction shall be taken into account in the computation of the
amount due under an interim Certificate and the Final Account, and the
saving in time will be considered against any extension of the Contract
Period granted irnder GC-7.
B. Progress Billings: Not later than fourteen days from each of the dates (or in
the event that the Contract specifies periods, fourteen days from the end of
each such period) specified in the Contract for the submission of progress
billings, the Contractor shall deliver to the Project Manager and Quantity
Surveyor a progress billing statement as of the relevant date or period then
ending, indicating the following:
(i) the estimated value of the completed portion of the Works and of the
materials and goods delivered in connection with such completed portion;
(ii) in case of Variations, a valuation thereof using the principles established in
GC-4;
(iii) the value of unfixed goods and materials delivered to the Site and properly
protected against damage or deterioration, it being understood that
such unfixed goods and materials shall not be removed except for use upon
the Works unless the Project Director has consented in writing to such
removal, which consent shall not be unreasonably withheld;
(iv) in case of work valued in the Bills of Quantities as Provisional Sums, a
valuation thereof using the principles under GC-6(C);
(v) in case of work done by a Nominated Sub-contractor/Supplier, a
valuation of all work properly done and materials or goods delivered but subject to
the terms of payment under the relevant ~ u b - c o n t r a c t / s u ~ ~ ( ~ contract
and to GC-8@);
(vi) any other additional amounts due to the Contractor under the
terms of the Contract Documents, other than damages or penalties arising
from a breach of the Contract Documents as perceived by the Contractor
which should be settled in accordance with GC-14;
(vii) the amount to be deducted from the aggregate value of the
foregoing items as a liquidation of the advance downpayment which should
be in the same proportion that the estimated value of the completed portion
of the Work under sub-clause (i) bears to the Contract Price; and
(viii)the amount to be retained by the Owner as the Retention Amount.
Each progress billing shall be supported by (i) test results (to the extent
applicable) demonstrating that the items of work so accomplished have passed
the requirements of the Contract Documents, (ii) an affidavit of the Contractor
to the effect that all costs of labor, materials, services, equipment and supplies
used in the accomplishment of such items have been paid for by the Contractor,
and (iii) other supporting documents required by the Owner
E. Direct Pavment: Without prejudice to the powers of the Project Manager and
the Owner under GC-8(D), the Owner may, but shall not be bound to, pay
some or all of any sums which would have been due to the Nominated Sub-
contractor/Supplier (or other sub-contractor/suppIier) but which were not
certified to for payment by the Project Manager under the Interim
Certificate, directly to such Nominated Sub contractor/Supplier (or other
sub-contractor/supplier). Having done so, the Owner may at any time
thereafter but before the issuance of the Final Account deduct the sums so
paid from any sums due or subsequently becoming due to the Contractor
under the Contract, or otherwise recove: the same from the Contractor,
subject to the terms of the final judgment or award in the dispute between
such Nominated Sub contractor between the Owner and Contractor.
F. Final Account: Upon the completion of the Works, the Contractor shall give
written notice to the Project Director to that effect, together with a request that
the Works be inspected (and where necessary, be subjected to final testing) and a
final claim for the balance of the Contract Price due to it, specitjrlng in detail the
quantities, rates and prices of the completed Works, any adjustments to the
Contract Price which it believes to be entitled to and any additional
compensation claimed by the Contractor under the terms of the Contract
Documents, together with explanations, supporting vouchers and all documents
(including detailed calculations and measurements) necessary for
the purposes of the computation of the Final Account. The Project Manazer,
Quantity Surveyor and Project Director shall conduct a final inspection and
testing of the Works within ten days from receipt of such written notice.
+.
In the event that the Works are found after such inspection and testing to
conform to the Contract Documents, then the Project Manager shall issue a
Certificate of Completion to the Contractor and certifL to the payment of the
balance of the Contract Price under a Final Account. Notwithstanding anything
contained in these Conditions, the Project Manager shall not be obliged to issue
a Certificate of Completion until a stage of constnlction has been reached at
which the Works are, apart from merely trivial deficiencies. ready for
occupancy and use for their intended purpose and are free from known
omissions or deficiencies including but not limited to omissions or deficiencies
which would be an impediment to the issuance of an occupancy permit from the
governmental agency.
The balance of the Contract price which shall be stated in the Final Accoilnt as
due to the Contractor shall be based on:
(i) the sum of all amounts previously paid under the Interim
Certificates;
(ii) the Contract Price adjusted as necessary. in accordance with the
terms of the Contract Documents to take into account any deductions from or
set-off against any amounts due to the Contractor under the Contract, or any
other contract entered into between the Owner and the Contractor, and
deductions from the Contract Price representing sums to be directly paid to any
Nominated Sub-contractor/Supplier (or any other sub-contractor/supplier) under
the relevant sub-contract/supply contract, and any other deductions allowed
under the Contract Documents.
The difference (if any) between the amounts specified above shall be expressed
in the Final Account as a balance due to the Contractor from the Owner, or to
the Obvnes from the Contractor, as the case may be. However, in the event that
the Contractor within seven days frorrl the daic tl~;.:Fnal Account is issued
objects to the Final Account only insofar as the arnounis to be directly paid to
any Nominated Sub-contractor/Supplier (or any other sub-contractorlsupplier)
and hrnishes the Owner with satisfactory evidence of the reason why such
amounts should not be paid to such sub-contractor/supplier, then the Owner shall
have the option (but not the obligation) to withhold the payment of such amount
to the Nominated Sub-contractor/Supplier and await the release of a final
judgment on the dispute between such sub-contractor/supplier and the
Contractor, or consign the amounts in question to a local court and request the
court to release the consigned amount subject to a final determination of the
rights and obligations of such sub-contractor/supplier and the Contractor. In this
case, the Owner may proceed to effect the release of the unaffected portion of
the balance of the Contract Price to the Contractor.
G. Certificate of Acceptance: Unless the Contractor objects to the other items in the
Final Account and submits such objection to arbitration under GC-14, the
Owner shall issue a Certificate of Acceptance of the Works and effect the
payment of the Final Account within fourteen days after the submission by the
Project Manager of the Final Account t o the Owner, subject to the
Contractor's submission of or compliance with the following requirements:
(i) original and three copies of all required
governmental permits (including occupancy permit);
(ii) one reproducible and three sets of prints of "AS-
BUILT" drawings;
(iii) original and three copies of Operating Manuals, S~~pplier's
Warranties, Preventive Maintenance Manual and Spare P a m List of
machineries and equipment supplied and installed by the Contractor,
Nominated Sub-contractors/Suppliers; and
(iv) release of all liens arising out of or in connection with the
Contract Documents, provided that, in the event that a Nominated Sub-
contractor/Supplier (or any other sub-contractor/supplier) refuses to furnish a
release or receipt in full, the Contractor may fbrnish the Owner with a bond
satisfactory to the latter, to indemnify it against any such lien; provided
hrther that if any lien remains unsatisfied after all payments are made, the
Contractor shall refun'd to the Owner all monies that the latter may be
compelled to pay in discharging such lien, including all costs and reasonable
allowance for legal and professional fees.
36 ALIGENCON
10113195
1
during the carrying out of the Works or before the issue of the said certificate
would not have disclosed;
(iii) any defect of the Works developed within the Warranty Period;
(iv) any accidental inclusion or exclusion of any work, materials, goods
or figures in any computation or any arithmetical errors in any computation; and
(v) any lien which remains unsatisfied which the Owner is compelled to pay as
a condition for the discharge of such lien.
Loss and Expense: If upon written application being made to the Project
Director by the Contractor, the Project Director determines that the Contractor
incurs a direct loss and/or expense for which it will not be reimbursed under
ALIGENCON -
10113l95
any other provision in the Contract by reason of the regular progress of the
Works or of any part thereof having been materially affected by:
(i) a Variation required or approved by the Project Director;
(ii) the Contractor not having received in due time necessary
instructions, drawings, details or levels from the Project Director which the
Contractor specifically applied for in writing on a date which having regard
to the Completion Date was neither unreasonably distant from nor
unreasonably close to the date on which it was necessary for the Contractor
to receive the same;
(iii) delay on the part of artists, tradesmen or others engaged by the Owner in
executing work not forming part of the Contract;
(iv) the opening up for inspection of any work covered up or the testing
h
of any of the work, materials or goods in accordance with GC-2(E), (including
making good in consequence of such opening up or testing), unless the
inspection or test showed that the work, materials or goods were not in
accordance with the Contract, or was as a result of the Contractor covering
up work before giving notice of inspection; or
(v) instructions issued by the Project Director under GC-14(A);
11; or
(vii) any deiay or prevention on the part of the Owner;
then the Project Director shall ascertain the amount of such loss andfor
expense. Any amount from time to time so ascertained shall be added to the
Contract Price, and if an Interim Certificate is issued after the date of
ascertainment any such amount shall be included in such Interim Certificate.
The Contractor shall submit to the Project Director written notice of the
Contractor's intent to file a claim for such loss and expense, and shall within
two months from the occurrence of the loss or incurring of expense, submit
to the Project Director a fully detailed and substantiated claim showing the
build-up of the loss and/or expense claimed by the Contractor. Any lapse of
time longer than the periods stated above shall be deemed to be an
unreasonable distant time for the above stated purpose and the Contractor
shall be deemed to have waived its right on such claims. The provision o f
the timely submission of the notification of intention to claim and the filly
detailed and substantiated build-up of such loss and/or expense is a
prerequisite for any claim under this GC-9(I) to be accepted for
consideration. Notification only of a hture intention to submit a claim under
this heading will not be accepted as complying with the requirements of this
GC-9(I). The payment to the Contractor of the loss or expense incurred in
the prosecution of the Works pursuant to this GC-9(T) shall exclude its right
to recover damages for breach of contract under GC-7.
ALIGENCON
10/19/95
GC-10: RETENTION AIND RELEASE OF RETENTION MONEY
Retention Amount: The Owner will retain a portion of the amount certified for
payment under each Interim Certificate and the Final Account, representing the
Retention Amount, as security for the repair or remedy of defects and
deficiencies in the Works which develop during the Warran~yPeriod. Unless the
Contract provides to the contrary, the Retention Amount shall equal 10% of face
amount of each Interim Certificate or Final ~ c c o u n t . The Owner's interest in
the Retention Amount shall be that of a trustee for the Contractor (but without
oblization to invest the said amount or pay interest thereon); provided that, the
Contractor's beneficial interest therein shall be subject to the preferred right of
the Owner to have recourse thereto from time to time for payment of any
amount to which it is entitled and to deduct therefrom any sum due or to become
due from the Contractor under the provisions of the Contract.
B. Remedv of Defects: The Project Director shall give the Contractor written
notice of any defect, shrinkage or other fault which shall appear within the
Warranty Period. If the cause of such defect, shrinkage or fault is due or found
to be due to any breach by the Contractor, Nominated Sub-contractoriSupplier,
or any other contractor or sub-contractor working under the direction or
supervision of the Contractor, of any of their obligations unde:
the Contract Documents or relevant sub-contract or supply contract, or the
performance of maintenance work is specificaIly required after the acceptance
of the Works under the Contract Docilments, then the Contractor shall be
responsible for repairing and making good the same to the Project Director's
satisfaction. Such repairs and corrective works shall be executed with the least
disturbance and without cost to the Owner and at the entire cost and expense of
the Contractor, and shall commence within three days after receipt of the
written notice to the Contractor from the Project Director and shall be
completed Githin a period agreed upon with the Project Director. In no case
shall the Contractor be required to make good at its cost any damage caused
by Force Majeure which may appear afier the acceptance of the Works, unless
the Project Manager shall certify that such damage is due to injury which took
place before acceptance.
Not later than fourteen days afier the expiration of the Warranty Period, the
Contractor shall specify in a Schedule of Defects t o be delivered to the
Contractor any remaining defect, shrinkage or fault found in the Works. Within
a reasonable time afier receipt of such Schedule, the defects, shrinkage
and other faults therein specified shall be made good by the Contractor and
entirely at its cost unless the Project Director shall otherwise instruct. After the
delivery of the Schedule of Defects, the Project Director shall cease to be
entitled to issue any instructions for the making good of any defects, shrinkage
or fault found in the Works. The Contractor shall assign to the Owner any
guarantees or quotations for future maintenance offered by plumbing,
mechanical, electrical or other sub-contractors and suppliers if and when
such guarantees or quotations extend beyond the Warranty Period.
E. Release of Retention Amount: Within fourteen days fiom the issuance of the
Maintenance Certificate, the Retention Amount (or the balance thereof
remaining after deduction of amounts due from the Contractor under the
terms of the Contract Documents) shall be released to the Contractor without
interest. Unless the Contract provides to the contrary, the Project Manager
may auth~rizethe release of the Retention Amount (or portion thereof) to the
Contractor even prior to the expiry of the Warranty Period or issuance of the
Maintenance Certificate upon the submission by the Contractor of the bond
required under GC-S(A)(iii).
A. Catch-up Schedule: Time is of the essence of the Contract. In the event that the
Contractor incurs delay of at least thirty days in completing a portion of the
Works by the completion date specified therefor in the Master Program, the
Owner will require the Contractor to submit within seven days from receipt of
written notice from the Project Manager, a confirmed catch-up schediile to get
over the delay incurred. The intention of this GC-ll(A)is not to extend
ALIGENCON
10119195
the Contract Period but to confirm the Contractor's ability to perform and
complete the balance of the Works within the Contract Period.
B. Events of Default: For purposes of the Contract, the Contractor shall be deemed
in default upon the occurrence of any o f the following events:
(i) the Contractor incurs delay of at least thirty days in
complying with the catch-up schedule required under GC-I l(A);
(ii) the Contractor fails to complete the Works in accordance
with the Contract Documents within the Contract Period or the extension period
grafited by the Owner, and the Project Manager certifies that the Works could
have been completed within the Contract Period or such extension;
(iii) the Contractor assigns t o another or permits the
-
performance by another of the Contractor's principal functions without the approval of the Owner;
(iv) the Contractor has failed to commence the Works or has
suspended the performance of the Works without justification for thirty days
after receivin~written notice from the Project Director to proceed or to
continue;
(v) the Contractor has removed plant, goods, equipment or
materials from the Sire which 2re necessary for the due and timely performance
of the Wcrks w i i h ~ u the consent of the Project Director in violation of GC-
2(D);
(vi) the Contractor becomes insolvent or bankrupt, or performs any Act of
Bankruptcy;
(vii) the Contractor unreasonably or unjustifiably refuses or fails
to comply with any written direction or instruction from the Project Manager or
Project Director; or
(viii) the Contractor has failed to remove materials from the
Site or to pull down and replace work for thirty days after receiving written
notice from the Project Manager that the said materials or work has been
condemned or rejected by the Project Director.
--
ALIGENCON 41
10/19/35
over the performance of the remaining Works by employing another contractor
to complete the Works or employing in-house personnel t o undertake and
complete the balance of the Works without releasing the Contractor fiorn its
obligations under the Contract Documents. In this case, the Owner o r such
other contractor will be entitled to use the plant, materials o r goods which have
been reserved exclusively for the performance of the Works, or the Owner may
at any time sell such plant, materials or goods and apply the proceeds of the sale
to the satisfaction of the sums due from the Contractor. The Project Manager
and Quantity Surveyor shall conduct an investigation of the work accomplished
by the Contractor prior to the occurrence of an event of default, and shall issue a
joint certification of the amount (if any) which the Contractor shall be deemed
k
to have reasonably earned or would have reasonably accrued to the Contractor
in respect of such work, and the value o f the unused or partially unused plant,
equipment or materials; provided that, the Owner shall not be liable to pay any
such amount until the lapse of the Warranty Period or thereafter until the costs
of execution and maintenance, damages for delay in completion and all other
expenses incurred by the Owner in taking over the Works shall have been
ascertained. The Contractor shall then be entitled to receive only such amount as
certified. However, if the costs o f execution and maintenance or damages for
delay in completion and all other expenses shall exceed value of the work so
accomplished by the Contractor prior to the occurrence of an event of default,
then the Contractor shall continue to be liable for the difference.
(ii) the Owner may require the Contractor (except when the
termination occurs by reason of the bankruptcy of the Contractor or of its
having committed an Act of Bankuptcy) to assign to the Owner without the
necessity of reimbursement, within fourteen days of the date of termination, the
benefit of any agreement for the supply of materials o r goods andlor for the
execution of any work for the purposes of the Contract. In any case, the Owner
may pay any supplier or sub-contractor for any materials or goods delivered-or
works executed for the purposes of the Contract (whether before or after the
date of termination) in so far as the price thereof has not already been paid by
the Contractor. Payments made under this GC-1l(C)(ii) may be deducted by the
Owner from any sum due or to become due to the Contractor.
(iii) the Owner may withhold the release o f all o r a portion of the
Contractor's billings to cover the amount of liquidated damages due to the
Owner under GC-5(F) and the expenses and costs to be incurred by the
Owner under GC-I l(C)(i), or apply the amount of liquidated damages and
costs and expenses against the amounts due to the Contractor from the
Owner under other contracts entered into between them, and wherever
necessary, forfeit the Retention Amount to cover the Contractor's liabilities
by virtue of such termination.
(iv) the Owner may collect liquidated damages as provided for
under GC-5(F) or seek recourse against the bonds or insurance poIicies
specified under GC-5(A).
42 ALIGENCON
10119/95
(v) the Contractor shall pay to the Owner the amount of any direct loss
andlor damage caused to the Owner by reason o f the termination. The Owner
shall not be bound by any provision of the Contract t o make any krther
payment t o the Contractor; provided that, in the event that the Project
Manager certifies the amount of expenses properly incurred by the Owner
and the amount of any direct loss andlor damage caused to the Owner by
reason of the termination and such amounts when added to the monies paid
to the Contractor before the date of termination exceed the total amount
which would have been payable to the Contractor upon due completion, the
difference shall be a debt payable to the Owner by the Contractor. If the said
amounts when added to the said monies are less than the said total amount,
the difference shall be a debt payable by the Owner to the Contractor.
(vi) in the event that total expenditures of the Owner in completing
the Work by itself or with the help of other contractors, subcontractors or
other third persons, including all payments made to the Contractor prior to
the rescission, cancellation or termination, are less than the Contract Price,
then the Owner may use the difference to settle unpaid wages of Contractor's
laborers who have actually worked at the Site. The amount that the Owner
shall pay shall not exceed whatever is necessary to cover the unpaid balance
of such employees' basic cash wases during the time that they directly and
exclusively devoted themselves to the execution of the Works, earned after
the last payroll period as reflected in Contractor's payroll, vouchers and other
papers, but not beyond the effective date of rescission, cancellation or
termination as established in the written notice to be sent to the Contractor.
Notwithstanding any provision found in these General Conditions to the
contrary, nothing in this GC-11(C) shall be construed as an undertaking 'by
Owner to answer or otherwise be liable to pay for the unpaid claims of
laborers or the suppliers of materials. In the event that the Owner decides to
pay such claims, the Owner shall not in any event pay more than what is
established by the claimants to the f i l l and complete satisfaction of the
Owner as legitimate, subsisting and reasonable unpaid claims after the
corresponding documents and supporting papers have been executed and
delivered to the Owner, and the corresponding quitclaim, in such form and
with such contents as the Owner may determine, is executed, duly sworn and
delivered to the Owner within such period, in such copies and in such place
or places that the Owner may in its absolute discretion determine.
(vii) The Owner shall have full authority to sell, mortgage or dispose
of Contractor's equipment, tools, supplies and materials at the cost to be
determined by the Owner if the Owner shall find it necessary to do so to
complete the Works at no cost to the Owner or to pay for the unpaid claims
of laborers or of the suppliers of materials.
(viii) the Owner may decide to resume with the construction of the Works
and may choose to negotiate with the Contractor for an amendment of the
Contract. In this case, the Contractor will be under obligation to continue with
the Works and the indemnity paid by the insurer by reason of the
UIGENCO N - 43
10119/95
occurrence of any of the fore~oingevents will totally and solely _go to the
Owner.
If the Project Director does not give written instructions to proceed with the
Works within ninety days from the Contractor's receipt of written instructions to
suspend progress on the Works, unless the suspension is due to causes specified
in sub-clauses (i) to (iv) above, then the Contractor may serve wr-itten notice on
the Project Director requiring permissiorl within twenty-eight days from the
latter's receipt thereof to proceed with the Works or that part thereof which was
suspended. If the Project Director fails to give permission to proceed with the
Works within such twenty-eight day period, then tile
Contractor may but is not bound to, elect ' o r treat th e suspension where it
affects only a portion of the Works as a Variation, or when it affects the
whole Works, as an abandonment of the Contract by the Owner.
Upon the occurrence of any of the foregoing events, the Contractor without
acting unreasonably or vexatiously may give the Owner written notice of its
intention to terminate the Contract. Such notice shall be given at least twenty
eight days prior to the intended date of termination and shall specify the
event(s) which gave rise to it. Should the event(s) specified in the notice
remain in existence at the end of the period of twenty e i ~ h tdays. then the
Contractor may forthwith send the Owner a notice of termination. Without
prejudice to the accrued rizhts or remedies of either party or to any liability
which may accrue before the Contractor, any Nominated Sub-
Contractors/Suppliers, any sub-contractor or supplier shall have removed
their temporary buildings, plant, tools, equipment, materials or goods from
the Site, the respectice rights and liabilities of the Contractor and the Owner
shall be as follows:
(i) The Contractor shall with all reasonable dispatch and in such
manner and with such precautions to prevent accidental damase or damage
to other persons or property, remove from the Site all of its own temporary
buildings, plant, tools, equipment, materials and goods (except for unfixed
goods or materials which have been paid for by the Owner or in respect of
which the Owner shall tender payment to the Contractor tosether with any
transport or other costs necessary to secure their return) and shall give
facilities to Nominated Sub-Contractors/Suppliers or any sub-contractor or
supplier to enable them to do the same.
(ii) after allowing for previous payments, the Contractor shall be paid by the
Owner (1) the contract value of all work executed before termination;
(2) the total value of work begun and executed but not completed as of the
date of termination, the value beins ascertained in accordance with GC- 4(D) as
if such work were a Variation required by the Project Director; (3) any sum
ascertained in respect of direct loss andfor expense under GC-9(I), whether
ascertained before or after the date of termination; (4) the cost of materials or
goods properly ordered for the Works for which the Contractor shall have paid
or for which the Contractor is legally bound t o pay, and on such payment by the
Owner, any materials or goods so paid for shall become the property of the
Owner; (5) reasonable costs of removal fiom the Site (including protection and
safeguarding of the Works as aforesaid) insofar as this has not been already
included in payments made or the value of work or materials; paid; and (6) any
direct and actual loss and/or damage caused to the Contractor arising from the
termination (except where the Contract is terminated by Force Majeure).
(iv) the Contractor shall relieve the Owner from liability for any
clairns of third parties as a result of the exercise of its right to cancel, rescind
or terminate the Contract. The Owner may require the Contractor to execute
an unequivocal sworn undertaking to release the Owner fiom any and all
claims, whether judicial or extrajudicial that Contractor, its employees or
third parties may file against the Owner.
IJpon the expiration of fourteen days from the date by which the notice of
tennination shall have been given or received by the Owner, the Contracior
shall be entitled to receive payment for works done prior to the occurrence of
such an event in accordance with measurementlsurvey which will be camed
out by the Quantity Surveyor. The parties hereto in the event of the outbreak
of hostilities may at any time by agreement between them make such further
or other arrangements as they may think fit to meet the circumstances.
B. War Damage: In the event that the Works or any part thereof sustains any
damage due to war, civil uprising, rebellion or act o f terrorism, then
notwithstanding anything expressed or implied elsewhere in the Contract, the
occurrence of such damage shall be disregarded in computing any amounts
payable to the Contractor under or by virtue of the Contract. The Project
Director may issue instructions requiring the Contractor t o remove andlor
- dispose of any debris and/or damaged work andlor to execute such protective work
as shall be specified. The Contractor shall reinstate or make good such damage and
shall proceed with the carrying out and completion of the Works, and the Project
Director shall grant to the Contractor a fair and reasonable extension of time for
completion of the Works. The removal and disposal of debris or damaged work, the
execution of protective works and the reinstatement and making good of such war
damage shall be deemed to be a Variation required by the Project Director.
1GC-14: ARBITRATION I
A. Basis For Arbitration: In the event that any dispute or difference arises
between the Owner and the Contractor, either during the progress or after the
completion or abandonment of the Works, in connection with the
interpretation of the Contract Documents or as t o any matter of whatsoever
nature arising thereunder or in connection therewith (including any matter
left by the Contract to the discretion of the Project Manager or Project
Director), the Owner and the Contractor hereby agree to exert all efforts to
settle their differences or-disputes amicably. Failing these efforts such
dispute or difference shall be referred to arbitration in accordance with the
rules and procedures of the Philippine Construction Arbitration Law.
B. --Procedure for Arbitration: Notice of the demand for arbitratioti shall be filed in
writing with the other party to the Contract and a copy filed with the Project
Manager. The demand for arbitration shall be made within a reasonable time
after the dispute has arisen and attempts to settle such dispute amicably have
failed. In no case, however, shall the demand be made later than the date of the
issuance of the Final Account, except as otherwise expressly stipulated in the
Contract. Reference to arbitration of questions relating to the issuance or non-
issuance of any certificate, or of any dispute or difference under these General
Conditions, shall not be made until after the acceptance of the Works, or
termination or alleged termir~ationof the Contract, or abandonment of thc
Works, unless with the written consent of the Owner and the Contractor.
Notwithstanding any such reference to arbitration, the Contractor shall not
cause any delay to the Works during any arbitration proceedings, and shall
comply or continue compliance with any instruction o r decision given by
Project Director in regard to the subject matter of such reference unless and
until the same shall be the subject of an award given by the arbitrators
appointed in accordance with the provisions hereof
48 -. ALIGENCON
10/19/95
excavation or its removal; (ii) take all steps which may be necessary to preserve
the object in the exact position and condition in which it was found; and (iii)
inform the Project Director of the discovery and precise location of the object.
The Project Director shall issue instructions in regard to what is to be done
concerning an object reported by the Contractor as an antiquity, including
requiring the Contractor to permit the examination, excavation or removal of the
object by a third party. Any such third party shall be deemed to be a person for
whom the Owner is responsible and not to be, a sub-contractor.
B. Royalties: All royalties or other sums payable in respect of the supply and
use in carrying out the Works as described by or referred t o in the Contract
- Documents of patented or copyright articles, processes or inventions shall be
deemed to have been included in the Contract Price. The Contractor shall
indemnify the Owner from and against all claims, proceedings, damages,
costs and expenses which may be brought or made against the Owner or to
which the Owner may be put by reason of being held to have infringed any
patent or copyright rights in relation to any such articles, processes and
inventions. However, should the Contractor in compliance with the Project
Director's instructions use any patented or copyright articles, processes or
inventions in carrying out the Works, the Contractor shall not be liable in
respect of any infringement or alleged infringement of any such patent or
copyright rights in relation to any such articles, processes and inventions and
all royalties damages or other monies which the Contractor may be liable to
pay to the persons entitled to such rights shall be added to the Contract Price.
D. Authorized Signatories: Except for the Contract, all the Contract Documents
shall be signed by the Project Director and the authorized representative(s)
designated by the Contractor. The Contract shall be signed by the attorneys-in-
fact of the Owner and the authorized representatives of the Contractor. A11
the Contract Documents, when signed as required hereunder, shall be fi~lly
binding on the parties.
E. Other Works: The Owner shall have power at any time to execute other works
(whether or not in corlnection with the Works) on the Site at the same t i n e as
the Works'are being executed. The Contractor shall give reasonable facilities
for these works; provided that, the Contractor shall not be responsible for
damage done to other works except for damage caused by the negligence,
omission or default of its own employees, agents or sub-contractor/suppliers.
Any damage done to the Works in the execution of other works shall be
deemed to be damage which is wholly caused by the neglect or default of a
servant of thC Owner acting in the course.of their employment as such.