1 Solar Field Drainage system provided by Open Trepezoidal Drains
Assumation: 2 The Minimum Longitudnal Slope of the drain shall be : 1 in 120 The Minimum Longitudnal Slope of the pipe culvert shall be : 1 in 120 Free Board in drain shall be : 150mm The minimum and maximum velocity of fllow in drain shall be maintained as follows to ensure 3 proper flow : Minimum 0.45 m/sec (Assumed) Maximum 2.70 m/sec (Assumed) The minimum and maximum velocity of fllow in pipe culverts shall be maintained as follows to 4 ensure proper flow : Minimum 0.75 m/s (Assumed) Maximum 2.7m/s (Assumed) The pipe for road crossings shall be designed for flow in half filled conduit with minimum dia 5 300mm. 6 Catchment Area has been considered as per Contour Layout.
Irrigation Works: The Principles on Which Their Design and Working Should Be Based, with Special Details Relating to Indian Canals and Some Proposed Improvements