Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Commissioning of Instrumentation
Speaker:
Ashish Dogra
1
Participants background
Operators?
Instrument Maintenance?
Mechanical Engineers?
Instrument Engineers?
Process engineers?
Other?
Topics
Planning
Documentation for erection and commissioning
Checks during mechanical erection
Calibration
DCS, ESD & subsystems
Critical loops and 2oo3 philosophy
Test of electrical system and cables
Pressure & leak tests
Tools required at site
Precommissioning
Commissioning (loop check)
Assemble all erection and check documentation
Hand over to operation
Initial controller settings to use at plant start-up
2
Documentation for erection and commissioning
Flow
Orifice
3
Flow
Nozzle
Calibration
Be sure that your calibration equipment is calibrated
and certified by an approved and renowned authority
Be sure that you have the necessary and adequate
calibration equipment
Allow electronic calibration equipment to warm up
Record calibration results on dedicated forms, that
later can be used as maintenance files
Set up the calibration system:
- who will do what
- procedures for calibration
- procedure for witnessing
- clearly mark instruments that have been calibrated
- check ranges and settings against the engineering
documents
Calibration ...
All instruments should be calibrated or checked:
- dp cells
- pressure transmitters
- displacement level transmitters
- pressure gauges
- filled temperature elements
- thermocouples and RTD’s
- control valves
- safety relief valves
- analysers
- switches (process and electrical)
- speed and vibration probes
- flame detectors
- Combustible & Toxic gas and fire alarms
- etc
4
Calibration Record Sheets
Transmitters, indicators, recorders
Switches
Temperature elements
pH transmitters
Control valves and accessories
Safety relief valves
Transmitters
Indicators
Recorders
Switches
5
Temperature
elements
pH
transmitters
Control valves
and accessories
6
Safety relief
valves
7
Test of electrical system and cables
Cabling:
- signal wiring (4-20 mA, thermocouple, RTD etc.)
- power
- control wiring (signal exchange with electrical)
- grounding
Execute and record tests:
- insulation test (to be done after stripping and
glanding but before termination of cable)
- visual inspection of workmanship, ferrulling,
shielding, grounding, cable laying, segregation etc.
- continuity test (including shields and drain wires)
- be aware of ground loops
Avoid repair of damaged cables, pull new ones
8
Tools required at site
Hand held pressure caliberator
HART calibrator
Multimeter
Stop watch to record opening and closing time of valves
Measuring tape for checking Orifice Meter run
Precommissioning
Precommissioning is the work done after the erection is completed
but before the instruments are energised.
Check that the erection is made in accordance with the engineering
drawings: hook-ups, P&I diagrams, JB drawings etc.
Check that the required tests and calibrations as described before
have been done.
Precommissioning includes check of wiring, cabling, junction boxes,
air supply and painting.
Set up procedures and records.
Precommissioning is the final check for single instruments as
pressure, level and temperature gauges.
Installation
check sheet
9
Commissioning (loop check)
Commissioning (loop check) is the work done after
precommissioning with the instruments energised (electrical and
pneumatic).
Definition:
“A loop consists of two or more instrument components that
interchange common intelligence”
The loop check brings together all the previous work of checking
and testing and shall ensure that nothing is overlooked.
In a loop check the complete transmission line from the process side
of the measuring instruments to/via the indicator/display/controller to
the final control element is checked.
Loop
check sheet
10
Assemble all erection and check documentation
11
Initial controller settings….
Primary influences:
12
Initial controller settings …
Temperature
Thermal systems (e.g. heat transfer):
Typical large time constants and negligible dead
time.
Proportional band - 200 % x overshoot / span
Reset - 0.2 repeats/min
Rate - 0.5 min
Graph
13
Graph
14
Cable ducts
Analyser shelter
Rack room
15
Questions
?
46 Electrical and Instrument Engineering Department
16