Sei sulla pagina 1di 16

Commissioning of Instrumentation

MRPL, Phase-III Refinery Project, Mangalore, India

S-01838/KSIN & ASDO

1 Electrical and Instrument Engineering Department

Commissioning of Instrumentation

MRPL, Phase-III Refinery Project


Mangalore, India
97,293 Nm3/h Hydrogen unit

Speaker:

Kuldeep Singh & Ashish Dogra


Electrical & Instrument Engineering Department

2 Electrical and Instrument Engineering Department

Kuldeep singh & Ashish Dogra


Kuldeep Singh

Education: B.Tech in Instrumentation (2001)


Employed with Topsoe: Since Jan 2009
Engineering: Ammonia, Hydrogen, Methanol,

Ashish Dogra

Education: B.Tech in Electronics (2004)


Employed with Topsoe: Since Sep. 2010
Engineering: Refinery, Hydrogen

3 Electrical and Instrument Engineering Department

1
Participants background
 Operators?
 Instrument Maintenance?
 Mechanical Engineers?
 Instrument Engineers?
 Process engineers?
 Other?

4 Electrical and Instrument Engineering Department

Topics
 Planning
 Documentation for erection and commissioning
 Checks during mechanical erection
 Calibration
 DCS, ESD & subsystems
 Critical loops and 2oo3 philosophy
 Test of electrical system and cables
 Pressure & leak tests
 Tools required at site
 Precommissioning
 Commissioning (loop check)
 Assemble all erection and check documentation
 Hand over to operation
 Initial controller settings to use at plant start-up

5 Electrical and Instrument Engineering Department

The key to a successful start-up is Planning

 Develop a detailed work plan


 Fix responsibilities within the instrument “team”
 Agree on work rules with other disciplines
 Resources:
- staff
- equipment
- vendor specialists
- documentation
 Time schedule
- instrument tests and loop checks make up 20-25 %
of the total instrument work at site
 Let start-up team make priorities for loop check

6 Electrical and Instrument Engineering Department

2
Documentation for erection and commissioning

 Piping and Instrument diagrams


 Instrument lists, I/O List, data sheets & detail specifications
 Installation drawings (hook-ups, JB’s, cable dwgs. etc.)
 Instrument location drawings
 Loop diagrams
 Vendor documentation
 Setpoint list for alarms & trips (maintained by process)
 Erection and commissioning schedule
………………….
 Forms for check, calibration, loop check etc
 Access to documentation from other disciplines
 Adequate facilities for copying and distribution

7 Electrical and Instrument Engineering Department

Checks during mechanical erection


 Flow elements:
- check and measure pipe ID and circularity
- check grinding of flange welds
- tapping orientation
- flow direction and straight lengths
- check and measure flow element bore
- check flow element calculations
- store orifices in a safe place until installation
 Nozzle allocation
 Check control elements that later will be boxed up
 Check accessibility of instrument tappings, valves etc.
 Solve conflicts (fouling) with other disciplines
- it is not always the one that came first that is right !
 Co-ordinate cable runs with electrical

8 Electrical and Instrument Engineering Department

Flow
Orifice

9 Electrical and Instrument Engineering Department

3
Flow
Nozzle

10 Electrical and Instrument Engineering Department

Calibration
 Be sure that your calibration equipment is calibrated
and certified by an approved and renowned authority
 Be sure that you have the necessary and adequate
calibration equipment
 Allow electronic calibration equipment to warm up
 Record calibration results on dedicated forms, that
later can be used as maintenance files
 Set up the calibration system:
- who will do what
- procedures for calibration
- procedure for witnessing
- clearly mark instruments that have been calibrated
- check ranges and settings against the engineering
documents

11 Electrical and Instrument Engineering Department

Calibration ...
 All instruments should be calibrated or checked:
- dp cells
- pressure transmitters
- displacement level transmitters
- pressure gauges
- filled temperature elements
- thermocouples and RTD’s
- control valves
- safety relief valves
- analysers
- switches (process and electrical)
- speed and vibration probes
- flame detectors
- Combustible & Toxic gas and fire alarms
- etc

12 Electrical and Instrument Engineering Department

4
Calibration Record Sheets
 Transmitters, indicators, recorders
 Switches
 Temperature elements
 pH transmitters
 Control valves and accessories
 Safety relief valves

13 Electrical and Instrument Engineering Department

Transmitters
Indicators
Recorders

14 Electrical and Instrument Engineering Department

Switches

15 Electrical and Instrument Engineering Department

5
Temperature
elements

16 Electrical and Instrument Engineering Department

pH
transmitters

17 Electrical and Instrument Engineering Department

Control valves
and accessories

18 Electrical and Instrument Engineering Department

6
Safety relief
valves

19 Electrical and Instrument Engineering Department

DCS, ESD & subsystems


 After installation and power up and before connecting
field cables the systems shall be thoroughly tested (SAT)
 A thorough FAT shall be done at the vendor before the system
arrives at site
 The tests should preferably be done together with vendor
specialists.
 Take care of proper grounding (electrical and signal)
 Keep software back up copies in a safe place
 Set up procedures for software and hardware changes
 Limit access to systems (both operator area and marshalling area)
 Test function of UPS

20 Electrical and Instrument Engineering Department

Critical loops and 2oo3 philosophy


 Steam/ Carbon ratio, feed MW and IS-1 actuation
 MOV interlocks
 DCS close loops

21 Electrical and Instrument Engineering Department

7
Test of electrical system and cables
 Cabling:
- signal wiring (4-20 mA, thermocouple, RTD etc.)
- power
- control wiring (signal exchange with electrical)
- grounding
 Execute and record tests:
- insulation test (to be done after stripping and
glanding but before termination of cable)
- visual inspection of workmanship, ferrulling,
shielding, grounding, cable laying, segregation etc.
- continuity test (including shields and drain wires)
- be aware of ground loops
 Avoid repair of damaged cables, pull new ones

22 Electrical and Instrument Engineering Department

Pressure and leak tests


 Hydrostatic test of hook-ups and impulse lines shall take place after
full assembly and verification of correct material choice.
 Co-ordinate test pressures with mechanical.
 Set up procedures for tests, witnessing and records.
 Remember to test vessel mounted instruments and instrument air
distribution systems.
 Clearly mark tested installations.
 Set up a procedure with mechanical to handle leaking root valves.
 Tube installations to be checked with manufacturer’s gap inspection
gauge
 Remove test medium after test

23 Electrical and Instrument Engineering Department

Pressure and leak tests ...


 Check that instruments can withstand the test pressure.
- many differential pressure instruments cannot
withstand full test pressure on one side only.
 Dry out instrument air piping after test.
 Pneumatic tubing shall be checked for leaks using
instrument air. Bubbler test is recommended.
 Remember to blow out pneumatic tubing.

24 Electrical and Instrument Engineering Department

8
Tools required at site
 Hand held pressure caliberator
 HART calibrator
 Multimeter
 Stop watch to record opening and closing time of valves
 Measuring tape for checking Orifice Meter run

25 Electrical and Instrument Engineering Department

Precommissioning
 Precommissioning is the work done after the erection is completed
but before the instruments are energised.
 Check that the erection is made in accordance with the engineering
drawings: hook-ups, P&I diagrams, JB drawings etc.
 Check that the required tests and calibrations as described before
have been done.
 Precommissioning includes check of wiring, cabling, junction boxes,
air supply and painting.
 Set up procedures and records.
 Precommissioning is the final check for single instruments as
pressure, level and temperature gauges.

26 Electrical and Instrument Engineering Department

Installation
check sheet

27 Electrical and Instrument Engineering Department

9
Commissioning (loop check)
 Commissioning (loop check) is the work done after
precommissioning with the instruments energised (electrical and
pneumatic).
 Definition:
“A loop consists of two or more instrument components that
interchange common intelligence”
 The loop check brings together all the previous work of checking
and testing and shall ensure that nothing is overlooked.
 In a loop check the complete transmission line from the process side
of the measuring instruments to/via the indicator/display/controller to
the final control element is checked.

28 Electrical and Instrument Engineering Department

Commissioning (loop check) ….


 The loop check includes connections to other loops.
 Loop check may involve other disciplines like electrical.
 Set up procedures and records for loop check.
 Set up procedures to involve process or operating staff in the loop
checks.
 Keep lists of and clearly mark (where possible) which loops that
have passed the test.

29 Electrical and Instrument Engineering Department

Loop
check sheet

30 Electrical and Instrument Engineering Department

10
Assemble all erection and check documentation

 Often this topic is “forgotten”.


 The erection and check documentation is of high value during plant
running and trouble shooting.

31 Electrical and Instrument Engineering Department

Hand over to operation


 Set up a formal procedure for handing over the instrument system to
operation.
 The procedure should
- allow for part hand over
- define who takes instruments on-line
- define who makes the tuning of controllers

32 Electrical and Instrument Engineering Department

Initial controller settings to use at plant start-up


(none-critical loops)

 Reasonable initial controller settings give the start-up team time to


concentrate on critical loops
 .. and minimise the risk to switch controllers to manual mode (and
leave it there forever)
 The main practical objective during start-up is to limit the amplitude
of oscillation.
 The ideal objective: Stability can be taken care of later.
 Assumptions for recommended settings:
Proper sizing of valves, vessels, instrument ranges, minimum
process dead time etc.

33 Electrical and Instrument Engineering Department

11
Initial controller settings….
Primary influences:

 The process transfer function -


- how sensitive
- how fast
 The sensor (transmitter) -
- input span
- transient response
 The controller itself -
- proportional action
- reset action
- rate action
 The final controlling element

34 Electrical and Instrument Engineering Department

Initial controller settings…


Liquid level
 Proportional action is all that is needed; however reset action is
often added to keep the level at set point after a load change. With
reset action the loop can never be ideally stabilised (two
integrators).
 Recommended settings (displacer or dp-cell sensor):
Proportional band - 20 %
Reset - 5 repeats/min
Rate - 0 min (for dp-cells the rate can
be set to cancel out the transmitter dampning)
 Surge tank: reset - 1 repeat/min and
time-const. x max. flow x 100%
Prop. band = ------------------------------------------------
tank area x span of sensor

35 Electrical and Instrument Engineering Department

Initial controller settings …


Pressure

 Slow systems (e.g. gas and large volume):


Proportional band - 200 % x overshoot / span
Reset - 2 repeats/min
Rate - 0 min

 Fast systems (e.g. gas and small volume or liquid):


Proportional band - 200 %
Reset - 20 repeats/min
Rate - 0 min

36 Electrical and Instrument Engineering Department

12
Initial controller settings …
Temperature
 Thermal systems (e.g. heat transfer):
Typical large time constants and negligible dead
time.
Proportional band - 200 % x overshoot / span
Reset - 0.2 repeats/min
Rate - 0.5 min

 Mixing systems (e.g. steam or water injection):


Typical dead time.
Proportional band - 200 % x overshoot / span
Reset - 0.2 repeats/min
Rate - 0 min

37 Electrical and Instrument Engineering Department

Initial controller settings …


Flow
 Flow loops are most often fast and behave like fast pressure loops:

Proportional band - 200 %


Reset - 20 repeats/min
Rate - 0 min

38 Electrical and Instrument Engineering Department

Graph

39 Electrical and Instrument Engineering Department

13
Graph

40 Electrical and Instrument Engineering Department

Reformer furnace Pressure Transmitters

41 Electrical and Instrument Engineering Department

Magnetic level gauge

42 Electrical and Instrument Engineering Department

14
Cable ducts

43 Electrical and Instrument Engineering Department

Analyser shelter

44 Electrical and Instrument Engineering Department

Rack room

45 Electrical and Instrument Engineering Department

15
Questions

?
46 Electrical and Instrument Engineering Department

16

Potrebbero piacerti anche