Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PHASORS AND
SYSTEM ARRANGEMENTS
Characteristics of Faults
• Reliability Comparisons
Resistor
The current and voltage are in phase in a purely resistive circuit, as shown in Figure
2-1.
Inductor
The current lags the voltage by π/2 radians or 90o in a purely inductive circuit, as
shown in Figure 2-2.
Complex Impedance
In general, impedance is a complex number of the form Z = R+ jX, where R
(resistance) is the real part and X (reactance) is the reactive or imaginary part.
The inductive reactance (XL) in a coil or wire that is measured in ohms (Ω) is equal to
2π times the frequency (f) times the inductance (L) of the coil that is measured in
Henries (H) or XL = 2πfL. The capacitive reactance (XC) of a capacitor that is
measured in ohms (Ω) is equal to the reciprocal of 2π times the frequency (f) times
the capacitance that is measured in farads (F) or XC = 1/(2πfC).
Introduction
A three-phase system has three sources of power with a certain time interval
between each source. It is very easy to generate three-phase voltages by
connecting three windings 120o apart on a generator. Figure 2-6 shows a three-
phase system in an ABC phase rotation sequence.
Three wires of a three-phase system can provide 173% ( 3) more power than two
wires of a single-phase system. When both single-phase and three-phase loads are
supplied from the same power supply, a three-phase, four-wire system (3φ, 4-wire),
which is called a wye (Y) connection, is used to supply power. If there are only
three-phase loads, a three-phase, three wire system (3φ, 2-wire), which is called a
delta (Δ) connection, is used to supply power.
System elements:
a. p.f. correction capacitor d. induction motor
b. pure resistive heater e. synchronous motor
c. generator
Power (Single-Phase):
• S = EI = (P2 + Q2)1/2
• P = EI cos θ = S cos θ
• Q = EI sin θ = S sin θ
• cos θ = P/S = p.f.
• sin θ = Q/S
• tan θ = Q/P
Power (Three-Phase):
• S = 3 EI =(P2 + Q2)1/2
• P = 3 EI cos θ = S cos θ
• Q = 3 EI sin θ = S sin θ
• cos θ = P/S = p.f.
• sin θ = Q/S
• tan θ = Q/P
Motors:
• kWin = (hpout x .746 kW/hpout)/(η)
• kVAin = kWin/p.f.
• I = (hpout x .746 kW/hpout)/( 3 x kV x η x p.f.)
= kVA/( 3 x kV)
• Note: If η x p.f. ≈ .746 then kVAin = hpout
Transformers:
• kVA = 3 x kV x I
• Ipri = kVA/( 3 x kVpri)
• Isec = kVA/( 3 x kVsec)
Van
Vab
Ia
Vbc
Ic Ib
Vcn
Vbn
Vbc
Figure 2-9.
Relationship between Current and Voltage for a System with Unity Power
Factor
Back-Feed
67
Ia
Vbc
Fault on
Transformer
Primary
67 Ia
Vbc
Normal Load
67
Vbc
VAB I1 I2 I3 I4
I3 VAB
I1
I2
(a) (b)
Figure 2-12. Examples of Radial Systems
Advantages
Ö Simple to operate
Disadvantages
Ö No redundancy
Comments
(a)
(b)
Advantages
Ö Faults on the high side loop do not cause outages, if the loop is closed, and
proper relaying is used
Disadvantages
Comments
Advantages
Ö Simple to operate
Disadvantages
Ö Only provides redundancy for faults on the primary side of the selector
switch
Comments
(a) (b)
Figure 2-15. Example of Secondary Selective System
Advantages
Ö Simple to operate
Disadvantages
Comments
Line
Bus
Disc. Switch
Circuit Breaker
Lines
The single-bus scheme is not normally used for major substations. Dependence on
one main bus can cause serious outage in the event of breakers or bus failure. The
station must be de-energized in order to carry out bus maintenance or add bus
extensions. Although the protective relaying is relatively simple, the single bus
scheme is considered inflexible and subject to complete outage.
Line Line
Transformer
Figure 2-17. Examples of Double Bus-Double Breaker Scheme
The double-bus-double-breaker scheme requires two circuit breakers for each feeder
circuit. Normally each circuit is connected to both busses. In some cases, half of the
circuits could operate on each bus. For these cases, bus or breaker failure would
cause the loss of half the circuits. The location of the main bus must be such as to
prevent faults spreading to both buses. The use of two breakers per circuit makes
this scheme expensive. However, it represents a high order of reliability when all
circuits are connected to operate on both busses.
Line Line
Main Bus
Bus
Tie
Breaker
Transfer Bus
Transformer
When a circuit breaker is removed from service for maintenance, the bus tie circuit
breaker is used to keep that circuit energized. Unless the protective relays are also
transferred, the bus-ti relaying must be capable of protecting transmission lines or
generators. This is considered rather unsatisfactory since relaying selectivity is poor.
A satisfactory alternative consists of connecting the line and bus relaying to current
transformers located on the lines rather than on the breakers. For this arrangement
line and bus relaying need not be transferred when a circuit breaker is taken out of
service for maintenance, with the bus-tie breaker used to keep the circuit energized.
If the main bus is ever taken out of service for maintenance, no circuit breakers
remain to protect any of the feeder circuits. Failure of any breaker or failure of the
main bus can cause complete loss of service of the station.
Bus No. 1
Bus No. 2
Line Line
This scheme used two main busses, and each circuit includes two bus selector
disconnect switches. A bus –tie circuit connects to the two main busses and, when
closed, allows transfer of a feeder from one bus to the other bus without de-
energizing the feeder circuit by operating the bus selector disconnect switches. The
circuits may all operate from the No. 1 main bus, or half of the circuits may be
operated off either bus. In the first case, the station will be out of service for bus or
breaker failure. In the second case, half of the circuits would be lost for bus or
breaker failure.
In some cases circuits operate from both the No. 1 and No. 2 bus and the bus-tie
breaker is normally operated closed. For this type of operation a very selective bus
protective relaying scheme is required in order to prevent complete loss of the
station for a fault on either bus.
Disconnect switch operation becomes quite involved with the possibility of operator
error, injury and possible shutdown. The double-bus-single-breaker scheme is poor
in reliability and is not used for important substations.
Transformer
Line
Transformer
Line
In the ring-bus scheme, the breakers are arranged in a ring with circuits connected
between breakers. There is the same number of circuits as there are breakers.
During normal operation, all breakers are closed. For a circuit fault, two breakers are
tripped, and in the event one of the breakers fails to operate to clear the fault, an
additional circuit will be tripped by operation of breaker-failure backup relays. During
breaker maintenance, the ring is broken, but all lines remain in service.
The circuits connecter to the ring are arranged so that sources are alternated with
loads. For an extended circuit outage, the line disconnects switch may be opened
and the ring can be closed
No changes to protective relays are required for any of the various operating
conditions or during maintenance.
The ring bus scheme is economical in cost, has good reliability, is safe for operation,
is flexible, and is normally considered suitable for important substations up to a limit
of five circuits. Protective relaying and automatic reclosing are more complex than
for previous schemes described. It is common practice to build major substations
initially as a ringbus; for more than five outgoing circuits, the ring bus is usually
developed to the breaker-and-a-half scheme.
Line Line
Bus No. 1
Tie
Breaker
Bus No. 2
Line
Line
Under normal operating conditions, all breakers are closed and both busses are
energized. AA circuit is tripped by opening the two associated circuit breakers. Tie
breaker failure will trip one additional circuit, but no additional circuit is lost if a line
trip involves failure of a bus tie breaker.
Either bus may be taken out of service at any time with no loss of service. With
sources connected opposite loads, it is possible to operate with both busses out of
service. Breaker maintenance can be done with no loss of service, no relay changes,
and simple operation of the breaker disconnects.
The breaker and a half arrangement is more expensive than the other schemes,
except the double breaker-double-bus scheme. However, the breaker-and-a-half
scheme is superior in flexibility, reliability, and safety. Protective relaying and
automatic reclosing schemes are more complex than for other schemes.
Ring bus 1. Low initial and ultimate cost 1. If a fault occurs during a breaker
2. Flexible operation for maintenance period, the ring can be
breaker maintenance separated into two sections
3. Any breaker can be 2. Automatic reclosing and protective
removed for maintenance relaying circuitry rather complex
without interrupting load 3. If a single set of relays are used, the
4. Requires only one breaker circuit must be taken out of service
per circuit to maintain the relays (Common on
all schemes)
5. Does not use main bus
4. Requires potential devices on all
6. Each circuit is fed by two
circuits since there is no definite
breakers
potential reference point. These
7. All switching is done with devices may be required in all cases
breakers for synchronizing, live line, or
voltage indication
5. Breaker failure during a fault on one
of the circuits causes loss of one
additional circuit owing to operation
of breaker-failure relaying
Breaker and a 1. Most flexible operation 1. 1½ breakers per circuit
Half 2. Highly reliable 2. Relaying and automatic reclosing
3. Breaker failure of bus side are somewhat involved since the
breakers removes only one middle breaker must be responsive
circuit from service to either of its associate circuits
4. All switching is done with
breakers
5. Simple operation; no
disconnect switching
required for normal
operation
6. Either main bus can be
taken out of service at any
time for maintenance
7. Bus failure does not remove
any feeder circuits from
service