Sei sulla pagina 1di 119

Tests

Pos: 20 /gds-BA/Überschriften/1 Prüfungen @ 0\mod_1312281268471_28.docx @ 722 @ 1 @ 1

9 Tests
Pos: 21 /gds-BA/Prüfungen/Allgemeines zur Prüfung/1.1 Allgemeines zur Prüfung 002 @ 53\mod_1380182098962_28.docx @ 2604913 @ 22 @ 1

9.1 General information on tests

In order to aseptically fill and pack foodstuffs, the production process must fulfil specific quality
criteria. The following of these criteria must be controlled through the following test
procedures.

All tests must be documented. Use respective forms for that purpose, see chapter
“Checklists/Forms”.
This section describes the individual procedures to test the quality characteristics.

Production controls
The proper condition of the equipment used (combibloc filling machine, UHT system) and of all
materials required is the essential condition for a trouble-free production process.
For this reason, it is recommended to carry out the necessary tests and control measures
before production start-up and during production.
The following chart is a summary of all measures to be taken and time intervals of tests to be
carried out.

Summary of test- and control measures

Measures Check-up intervals Who?


upon
delivery / Start of when
daily
when production required
refilling
Machine operator,
Cleaning control
plant laboratory
Plant laboratory /
Sterilisation control
machine operator
Machine operator,
H2O2test
plant laboratory
Controls of packaging Machine operator,
material quality assurance
Package test,
Machine operator,
including blue/red dye
plant laboratory
test
Final packaging
Machine operator
checks
Bacteriological
Plant laboratory
controls

Follow protection mark Stand 15.11.2013 9-1


ISO 16016. cb 1 / cf 1
Tests

Documentation

INFO
  For reasons of product liability and production safety, it is necessary to have available a
detailed production documentation. This is the only way to prove that the foodstuff has been
treated/processed correctly. The manufacturer of the foodstuff is liable for the consequential
damages incurred by the consumer through the consumption of a foodstuff treated incorrectly.

Important elements of the documentation:


 General production data, such as date, production time (time: start-end)
 Product and carton package (format)
 Responsible staff members (machine operator, division manager, shift supervisor)
 Quantity produced
 Plant and equipment used
 Additional resources used (possibly recipes)
 Results of chemical-physical analyses
 Microbiological results
 Production Checklist
 Protocols from the filling machine
 Acquisition of production- and machine faults, including time, duration and reason for fault
 Data on cleaning, disinfection and other sanitary measures

INFO
  The filling machine operating company must make available forms for that purpose.
The weight control of the cartons including a statistical analysis of the results and an
extensive micro-biological test of the products are stipulated by law. The products must
be tested in accordance with the respectively valid guidelines. The results of the tests must be
kept for certain periods of time to enable control measures through legal departments.

In general, such safekeeping periods also apply to the printouts of the protocols of the plants
used (such as heating plant and filling machine) on which important process parameters such
as heating temperature, flow volume etc.) are recorded during the complete production time.
The Protocols, Forms and Checklists must be identified (together with date, product
filled and signatures of responsible person) and must be kept at a safe custody
together with the other product documentation.
See Chapter "Checklists/Forms".
Pos: 22 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-2 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 23 /gds-BA/Prüfungen/Packstoff/1.1 Packstoff @ 21\mod_1335451563513_28.docx @ 171704 @ 2 @ 1

9.2 Packaging material

All packaging materials used for the filling on combibloc filling machines have been produced
in accordance with the valid combibloc specifications in our production facilities Linnich,
Wittenberg (Germany), Saalfelden (Austria), Rayong (Thailand), Suzhou (China), Curitiba
(Brazil) or Riad (Saudi Arabia). In order to match a large variety of products to be filled, the
packaging material does not consist of one single material but is a compound material made
of different laminations. Thus, the packaging material is also called a compound packaging
material, since the properties of the individual components as a "compound" add up to an
overall property.
The composite packaging material consists of 70 % of paper-board.

Schematic structure of a carton package

1 Polyethylene

2 Polyethylene

Aluminium foil (for


3 aseptic composite
material only)
1
2
4 Polyethylene 3
4
5
5 Paper board 6
7

6 Polyethylene

bi bloc ®
m
SI G Co
7 Colour

00005201

Ill. 9-1

Follow protection mark Stand 15.11.2013 9-3


ISO 16016. cb 1 / cf 1
Tests

Significance of individual layers


Printing ink – used to print onto the carton package.
Outside PE (polyethylene) – is designed to protect outside of compound material
against moisture and water vapor.
Paper board – used as a stability agent, provides the shape to the final
carton package, provides the required stability of shape
and rigidity and makes the carton package transportable.
Laminating PE (polyethylene) – is designed as a laminate agent between the board and
the aluminium.
Aluminium film – serves, in particular, as a light protection, gas-, diffusion-
and aromatic barrier.
Adhesive (PE) – used to increase the adhesive between aluminium and
inner coating to prevent a delamination of the layers.
Inside PE – necessary as a protection against moisture penetration of
the board, as welding material for top, bottom and
longitudinal seam and as a protection against re-infection.

The base material for the carton package is the paper board. The board provides rigidity, grip
stability and stability under load to the carton package and provides the condition for a folding
of the carton packages through creasability. The specific requirements towards the paper
board are manifold and not easy to combine.
Pos: 24 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-4 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 25 /gds-BA/Prüfungen/Packstoff/1.1.1 Herstellungsprozess eines Mantels @ 2\mod_1312788519560_28.docx @ 6986 @ 3 @ 1

9.2.1 Production process of a sleeve

From the paper board roll to the sleeve

1 2 3 4 5 6 7 8

2 9 2
00005002

Ill. 9-2

1 Board roll 6 Sealing of longitudinal seam


2 Polyethylene (PE) 7 Finished sleeve
3 Coated compound 8 Shipping box
4 Printing 9 Aluminium
5 Creasing/Cutting of blanks

Usually printing is done onto the outer PE layer after the coating (see Ill. 9-2). The printed roll
is creased and cut into individual blanks on the cutter in two separate operating stages.
An identification number is printed onto each blank, which informs the specialist about the
position of the blan on the web see section 9.2.4.
At the outfeed of the cutter, the sleeves are stacked and transported to the automatic folding
and sealing machine.
The production of a sleeve is completed with the sealing of the longitudinal seam (see Ill. 9-3).

Follow protection mark Stand 15.11.2013 9-5


ISO 16016. cb 1 / cf 1
Tests

The finished sleeves are taken up by a conveyor belt and fed to a boxing machine via a
counting unit. Boxes containing the same type of sleeves are automatically palletised, shrink-
foiled and made ready for delivery.
During all of the production cycle, the manufacturing is continuously controlled. Sampling is
effected at specific steps of the processing and tests are carried out according to specified
quality criteria pursuant to ISO 9001. The test results are archived, in order to enable
assessments of the respective production at a later stage. In addition, sample sleeves are
stored documenting production by way of finished products.

Cross section of longitudinal seam of combibloc carton package

00005102

Ill. 9-3

1 Aluminum foil
2 Board
3 Polyethylene (PE)
Pos: 26 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-6 Stand 06.12.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 27 /gds-BA/Prüfungen/Packstoff/1.1.1 Packstoffeingangskontrollen und -lagerung 002 @ 53\mod_1380182483902_28.docx @ 2605002 @ 33 @ 1

9.2.2 Incoming controls of packaging material and storage

It is essential for aseptic packaging that the packaging materials to be used are in an
undamaged condition, because otherwise a contamination of the foodstuff with germs (through
leaks, for example) may happen and this would result in a perishing of the foodstuff or even in
a health hazard.
In order to avoid a processing of defective sleeves, always check goods delivered for
completeness and damages. Claims must be immediately notified to the respective carrier or
supplier, respectively (do not forget to state delivery data).

NOTE
Board moisture
Unusable sleeves
An optimum processing of sleeves is only guaranteed with a specific board humidity. For this
reason, each pallet is shrink-wrapped before leaving the processing plant. This should prevent
a drying-off or wetting of the sleeves. If this plastic film is missing or defective upon delivery,
this may lead to problems when processing the sleeves and during production.
 Only use sleeves, which had been wrapped into a film before.

The system is designed for a specific process temperature and relative air humidity.
Deviations from that can lead to faults (leaks for example). Follow the following storage
conditions to allow a problem-free processing of the material:

Temperature: + 15 °C to + 35 °C
Relative humidity in the air: 50% to 70%

NOTE
Temperature
Unusable sleeves
The optimal functioning of sleeves is only guaranteed only at a certain temperature. Failure to
observe this temperature may lead to processing and production problems
 Only use sleeves that were stored above + 5 °C.
 Do not store sleeves outdoors. Do not store in the open!

Follow protection mark Stand 15.11.2013 9-7


ISO 16016. cb 1 / cf 1
Tests

Are the sleeves delivered or sored within the above mentioned conditions the sleeves can be
used directly for filling processing.
In case the delivery or a storage at temperatures of 15 - 35 °C is not possible, the pallet must
be placed into the filling area or into a room with operating temperature two days before
processing to achieve a climatic adaptation. If the sleeves have been stored below 15°C
remove immediately shrink wrapping to allow an adaptation to the room climate. If the sleeves
have been stored over 35 °C the shrink wrapping should only be removed just before the
processing to maintain the inner climate of the pallet
In order to avoid damages to the sleeves, the pallets shall not be stacked on top of each other
without a rigid intermediate layer. In order to avoid any soiling, it is recommended to close
open boxes and to cover open pallets.
Avoid any long-term storage of sleeves (more than 24 months). Thus, use the sleeves in the
sequence of the delivery. Under local specific environmental conditions the maximum period
of storage can be shorter.

Pos: 28 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-8 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 29 /gds-BA/Prüfungen/Packstoff/1.1.1 Längsnaht-Sollmaße/Packstofftoleranzen cb1 @ 26\mod_1368778814127_28.docx @ 202288 @ 3 @ 1

9.2.3 Longitudinal seam default values/Tolerances of packaging materials

D
00005502

Ill. 9-4

Format D E
cb1 11.8 ± 0.8 mm 8.7 ± 1 mm

If the dimensions of the longitudinal seams are outside the tolerances specified for the
packaging material, please inform SIG Combibloc Service, see chapter "General
Information/Addresses of Service Agencies".

Pos: 30 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-9


ISO 16016. cb 1 / cf 1
Tests

Pos: 31 /gds-BA/Prüfungen/Packstoff/1.1.1 Packstoff-Identifikation 003 BuPP cb1+7 @ 24\mod_1344242645352_28.docx @ 181620 @ 3 @ 1

9.2.4 Packaging material identification

In case of any possible claims, the respective production may be tracked and checked by
using the box inscription and the blank identification number. This way, it is possible to check
at a later stage, whether any irregularities occurred during this production. This enables a
faster analysis of problems during the filling process caused from the side of the packaging
material.

Box inscription
Each box is coded during production. The coding includes all important data on the product
and on production and differs for each type of carton package.
The wording is made up of several components:

Example for an inscription on a shipping box


a b c d
240 PC091500 FRUIT RED BERRY MIX 10030/9

e f g h i j k l
715456500 SWIFT 0004 2588 31.12.12 23:59 20216558 3114

Identification print Amount of digits available


a Number of sleeves in a shipping box 3 digits
b* Product hierarchy 8 digits
c Short ID of material 20 digits
d* Technical Information Code 7 digits
e Material number 9 digits
f Customer text 11 digits (field e + f max. 20 digits)
g* Production plant 4 digits
0004 = Linnich / Germany
0044 = Wittenberg / Germany
0100 = Saalfelden / Austria
0070 = Rayong / Thailand
0170 = Suzhou / China
0800 = Riad / Saudi Arabia (Obeikan)
0354 = Curitiba / Brazil

h* Production line 4 digits


i, j * Date, time of production 14 digits
DD.MM.YY_HH:MM
k Order number of production 8 digits

l Continuous number of shipping box 4 digits

This is a clear identification of each shipping box.

9-10 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Blank Identification number


The blank identification number is printed
next to the print design number. It informs
about the position of the blank on the web.

3 329 140 combibloc


SIG

00005204

III. 9-5
Pos: 32 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-11


ISO 16016. cb 1 / cf 1
Tests

Pos: 33 /gds-BA/Prüfungen/Packungsprüfung/1.1 Packungsprüfung 002 cb1/7 @ 53\mod_1380183138679_28.docx @ 2605031 @ 22 @ 1

9.3 Carton check-up

WARNING
Non-sterile conditions
Health risk through non-sterile conditions
The aseptic filling is at hazard in case of defective cartons. Unsterile cartons present a health
risk for the consumer.
 Strictly follow test instructions and thus make sure that only defect-free products will reach
the customer!

The carton check-up is designed to determine whether the carton package is sufficiently leak-
proof. This is a condition for the reliable and permanent protection of the product.
In addition, it is tested
 whether the carton package has the required weight,
 whether the head space corresponds to the specifications and
 whether the product is below specified residual H2O2 limits.
At the same time it is ensured that the opening system works properly.
The test and check procedures listed up in this section must be carried out by the operating
staff at the intervals specified. This ensures a production under uniform, optimum conditions.
Enter actual settings at the beginning of production and changes during production into
Production Checklist, see section 12.1.2.

INFO
  The figures show the sleeve or carton package, respectively, prepared for the application of a
fitment. This preparation is waived when operating the filling machine without downstream
applicator for opening features.

In case of any faults you cannot eliminate, please inform SIG Combibloc Service, see chapter
General Information/Addresses of Customer Service Agencies".
Pos: 34 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-12 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 35 /gds-BA/Prüfungen/Packungsprüfung/1.1.1 Kurzübersicht Prüfungsarbeiten BuPP cb1 @ 53\mod_1380267013660_28.docx @ 2609233 @ 334444 @ 1

9.3.1 Short overview of the test procedures

The following pictures show a short overview of the test and check procedures, which must be
carried out in the course of the carton check-up. The individual testing methods will then be
briefly presented.
The testing process defined in this manual must be strictly followed for final confirmation.

9.3.1.1 Short overview of the test procedures combibloc-carton package

30 29
5. 3.
1. 21 22 20 19 21

6. 8.
2.
243,00

4.
3.

4.

5.

6.

7.

8.

9. 1
1
² ² - T est

1. 7. 8.
H O

10.
3.
00180100

III. 9-6

Follow protection mark Stand 15.11.2013 9-13


ISO 16016. cb 1 / cf 1
Tests

9.3.1.2 Tests

Test 1: Sleeve activation pattern


Purpose of testing:
The check of the activation pattern of the
sleeve’s bottom section enables a check of
the bottom heating function and an
evaluation of the adjusted temperature.
For this purpose, the borderlines of the
activation and the heating-up of the 00180107
activated areas are tested.
Corrective and preventive measures can be III. 9-7
taken by using the activation patterns in
order to avoid or prevent possible leakers at
the bottom section.
Test process: See section 9.3.5.3

Test 2: Filling volume (weight)

Purpose of testing:
The weight check is necessary to ensure a
constant filling volume in the carton
package.
Testing process: See section 9.3.6

c ®
biblo
Com
SIG

243,00
00180171

III. 9-8

9-14 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Test 3: Visual check of outer appearance


in terms of bottom and top forming

2
Purpose of testing:
The check of the package forming enables a
fast identification of irregularities with regard
to the sealing of bottom, top and top flaps as
well as the overall appearance of the
package. 000AI001

Particular attention is given to: III. 9-9


- bottom and top forming
- overlap of bottom and top section
- position and accuracy of the date
- possible damages and scratch marks
on the package
- sealing and alignment of top flaps.
Testing process: See section 9.3.7

Test 4: Head space

Purpose of testing:
In order to obtain a well shaped package, it
is essential to keep the head space as small
as possible. The head space will be mainly
influenced by foam formationof the product
and the steam injection.
Testing process: See section 9.3.8

00005224

III. 9-10

Follow protection mark Stand 15.11.2013 9-15


ISO 16016. cb 1 / cf 1
Tests

Test 5: Top sealing

Purpose of testing:
The testing of top sealing enables a quick
evaluation of the sealing quality as well as a
check of the alignment of the sealing tools /
package pockets.
Testing is carried out on the following items :
- the complete area of the weld
- the light gap in the weld,
- the appearance of the weld,
- any burning marks and any signs of 000AI002

channel forming beside the III. 9-11


longitudinal seam,
- the dimension of the longitudinal
seam, if necessary (e.g. in case of
any previous irregularities).
Testing process: See sections 9.3.9 and
9.3.10

40 38 37

2
2
000AI012

III. 9-12

9-16 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Test 6: Activation of top flaps

Purpose of testing:
Causes for badly sealed top flaps and
leaking tops can be reliably determined with
the aid of activation patterns. 000AI004

For this purpose, the activated area of the III. 9-13


top flaps, temperature, pressing force and
top forming are checked.
Testing process: See section 9.3.11

Follow protection mark Stand 15.11.2013 9-17


ISO 16016. cb 1 / cf 1
Tests

Test 7: Activation pattern and forming at


the bottom section, as well as heating up
through drying station

Purpose of testing:
A check of the activation pattern of the
package bottom enables once more an
evaluation of the bottom heater function and
an evaluation of the temperature setting, see
test 1 on page 9-14.
Again, the pattern of the activation
borderlines and the heating-up of the 000AI005

activated areas are checked.


III. 9-14
In the course of this inspection further
attention is given to
- bottom forming,
- any possible channel forming at the
transition area to the longitudinal seal
and beside the triangle tips,
- possible loads on the folding edges,
- heating-up through drying air.
Any channel forming in the sealing area can
only be detected by visual check.

Testing process: See section 9.3.12

00180151

III. 9-15

9-18 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Test 8: Bottom sealing

Purpose of testing:
A check of the bottom seal enables a fast
evaluation of the quality of the package
bottom. The forming of any channels can
thus be safely detected.

00180106

III. 9-16

Testing process: See sections 9.3.9 and


9.3.13

000AI003

III. 9-17

Test 9: H2O2 residue check

Purpose of testing:
The H2O2 test strips indicate whether the
filled package has left the filling machine
below residual H2O2 limits.
Testing process: See section 9.3.15 H O -Test
² ²

SIG
Com
b ibloc
®
00005266

III. 9-18

Follow protection mark Stand 15.11.2013 9-19


ISO 16016. cb 1 / cf 1
Tests

Test 10: Blue/red dye test

Purpose of testing:
After all other inspection tests have been
successfully completed, the blue/red dye
test is the final and conclusive test for
package tightness.
Testing process: See section 9.3.16

00005267

III. 9-19

INFO
  As long as the blue/red dye test does not fulfill the requirements stated in the test manual,
production must be interrupted until the cause has been found and repaired.

Pos: 36 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-20 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 37 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1 Prüfarbeiten und Intervalle (Übersicht) 004 cb1 @ 53\mod_1380267178280_28.docx @ 2609262 @ 33 @ 1

9.3.2 Check-up works and intervals (Summary)

INFO
  Ensure correct function of steam injection before control works!

Check-up intervals

After all repair and maintenance


When changing production date
When changing product or print
At the beginning of production

Procedure: see section


When changing pallet
Each 4 hours
Every hour

design

works

biblo
Com
SIG
Check-up works
1. Activation pattern at
sleeve * * 9.3.5.3

2. Filling volume (weight)


9.3.6
243,00
00180119

3. Visual check / forming


(date print, damages 9.3.7
etc.)

4. Head space
9.3.8

5. Top sealing 9.3.10

6. Activation of top flaps 9.3.11

7. Activation pattern at
bottom section 9.3.12

8. Bottom sealing 9.3.13


9. H2O2 residual check
9.3.15

10. Blue/red dye test


- Reaction time: 30 min * 9.3.16

* Only if required, if the other tests do not result in a reliable evaluation, e.g. with a simultaneous
change of print design, of the date of manufacturing, or if the storage conditions of the pallet
considerably deviate from the standard conditions specified:
Pos: 38 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-21


ISO 16016. cb 1 / cf 1
Tests

Pos: 39 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1 Kennpunkte der combibloc-Packung 004 BuPP cb1 @ 24\mod_1357655803708_28.docx @ 184956 @ 3 @ 1

9.3.3 Identification points at packages

In order to improve the communication with regard to the location of package leakers,
activation faults etc., certain ID points are specified for the packages.

III. 9-20 combibloc carton package

9-22 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

000AI009

III. 9-21 combibloc carton package

Follow protection mark Stand 15.11.2013 9-23


ISO 16016. cb 1 / cf 1
Tests

ID Identification Position
6 Creased cross top Opposite to longitudinal seam
7 Creased cross top Longitudinal seam side
8 Longitudinal seam Edge of longitudinal seam - top web
9 Creased cross top Opposite to longitudinal seam
10 Creased cross top Longitudinal seam side
11 Top corner
12 Creased cross top Top triangle – right to the longitudinal seam
13 Top corner
14 Top corner
15 Creased cross top Top triangle - opposite to longitudinal seam
16 Top corner
17 Longitudinal seam Longitudinal seam - top edge
18 Longitudinal seam Longitudinal seam sealing top / bottom
19 Bottom corner
20 Bottom corner
21 Bottom corner
22 Bottom corner
23 Bottom Bottom edge broad side - longitudinal seam side
24 Bottom Bottom edge narrow side - longitudinal seam side
25 Bottom Bottom edge narrow side - opposite to longitudinal seam
26 Bottom Bottom sealing - longitudinal seam
27 Bottom Folding edge between ID 29 +30
28 Longitudinal seam Longitudinal seam - bottom edge
29 Bottom Triangle tip - longitudinal seam side
30 Bottom Triangle tip - opposite to longitudinal seam
31 Bottom Bottom edge broad side opposite to longitudinal seam side
32 Bottom Channel next to triangle tip ID 30 - opposite to longitudinal seam side
33 Bottom Channel next to triangle tip ID 29
34 Bottom Channel next to longitudinal seam
35 Longitudinal seam Channel next to longitudinal seam - top
36 Top seam Sealing point - top triangle opposite to longitudinal seam
37 Top seam Sealing point - top web crease opposite to longitudinal seam
38 Top seam Sealing point next to inner edge of longitudinal seam
39 Top seam Sealing point next to outer edge of longitudinal seam
40 Top seam Sealing point – top web crease right to the longitudinal seam
41 Top seam Sealing point – top triangle right to the longitudinal seam
42 Longitudinal seam Channel in the area of the web crease line - top
43 Bottom Diagonal - transition web - longitudinal seam side
44 Bottom Diagonal - transition web - opposite to longitudinal seam side
80 Opening Coated straw opening

9-24 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Detailed view to fault ID points:

X1. of III. 9-21 combibloc carton package

000AI011

III. 9-22

Carton package bottom in the area of the triangle tip / longitudinal seam.

29: Triangle tip – longitudinal seam side


30: Triangle tip – opposite to longitudinal seam side
32 + 33 Channel next to the triangle tip
34: Channel next to longitudinal seam
Pos: 40 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-25


ISO 16016. cb 1 / cf 1
Tests

Pos: 41 /gds-BA/Prüfungen/Packungsprüfung/1.1.1 Anwendung des Polarisationsfilters 003 cb1 @ 53\mod_1380267282917_28.docx @ 2609291 @ 334444 @ 1

9.3.4 Use of polarisation filter

The polarisation filter is used to check the activation (heating-up) of the sleeve. The
polyethylene (PE) activated at the inner surfaces can be made visible through the polarisation
filter.
The use of the filter is only possible for aluminium coated sleeves. The filter is attached to this
Chapter. If necessary, the polarisation filter is available through SIG Combibloc (Item no.
8889.80201).

00180107

III. 9-23

1. Place polarisation filter onto areas to be checked.


2. Turn filter so that the activated areas (heated up to welding temperature) are shown
coloured and that the boundary sections of the activation pattern (/arrows) can be reliably
assessed.

III. 9-24

9-26 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

9.3.4.1 Explanation of the activation border

At the activated area usually a border line


and then an activation gleam can be seen.
The border line is shown in Ill. 9-25 and Ill.
9-26 (see arrows) and is called activation
border on the activation pattern.

Ill. 9-25

INFO
  The activated areas are shown with deviating colours under the polarisation filter;
however, the colour or colour shade does not allow any conclusion regarding the
activation temperature.
In case of an uneven distribution of temperature within an activation area, this may, however,
be indicated by different colour shades depending on the temperature.

Ill. 9-26

Follow protection mark Stand 15.11.2013 9-27


ISO 16016. cb 1 / cf 1
Tests

9.3.4.2 Example for different coloured activation pattern

The colour of activation pattern depends on the used packaging material and can also differ
on production lots.
When using further carton package structures in the future, the colour can be different from
the shown examples as well.

III. 9-27
Pos: 42 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-28 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 43 /gds-BA/Überschriften/1.1.1 Bodenaktivierung @ 1\mod_1312368483144_28.docx @ 2147 @ 3 @ 1

9.3.5 Bottom activation


Pos: 44 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1.1 Aktivierbild am Mantel 005 cb1 @ 53\mod_1380267406210_28.docx @ 2609320 @ 44 @ 1

9.3.5.1 Activation pattern at sleeve

WARNING
Hot surfaces
Risk of injuries through hot machine components
The machine components in the area of the bottom heating may be hot and may cause burns
in contact.
 Wear protective gloves and long-sleeved work clothes.
 Do not touch hot components.
 Allow filling machine to cool down.

The check-up of the activation of the sleeve at the bottom section allows a control of the
function of the bottom heater and an assessment of the temperature set. For this purpose, the
borderlines of the activation and the heating-up of the activated areas are tested.

INFO
  A faulty activation may be the reason for a poor sealing and may lead to bottom leakers.
Good activation patterns do not necessarily mean tight bottom sections. Requirements see
section 9.3.17.

Test intervals:
 at the beginning of production.
 when changing product, print design or pallet with a change of the day of manufacturing in
the shipping box inscription.
 when changing pallet without a change of the day of manufacturing in the shipping box
inscription, as necessary *.
 after all repair and maintenance works.
* The check when required means that the activation pattern at the sleeve may give hints to
the reason of a welding problem. The activation patterns do not substitute the visual
checks of the bottom sealing and the blue/red dye test.

Take into account the following points when producing activation patterns:
 Air pressure within tolerance range.
 Only use sleeves of the same date of production.
 Production of activation patterns at the same time for all tracks.
 Only sleeves from the pallet intended for processing may be taken for the production of
activation patterns, which should have adapted to the room temperature of the filling room,
see section 9.2.2.
 Activation heads and hoods free from soiling and properly installed.

Follow protection mark Stand 15.11.2013 9-29


ISO 16016. cb 1 / cf 1
Tests

1. Allow filling machine to "warm up".

NOTE
Faulty production of activation patterns
Incorrect setting of filling machine through unusable activation patterns
Activation patterns, which will correctly and reliably allow conclusions about the bottom sealing
can only be produced on a filling machine properly warmed up ready for production. A
specifically installed sensor is used to measure the ambient temperature in the area of the
bottom heating.
 When producing the activation patterns, the required ambient temperature in the area of
the bottom heating must have been reached.
 Do not produce activation patterns, if the ambient temperature in the area of the bottom
heating has not been reached.

INFO
  The sleeves to be tested shall not be inside the magazine during the warming-up of the
machine.

2. The sleeves placed into the sleeve magazine for the production of activation patterns must
be pushed onto the mandrels within two minutes in order to avoid any excessive heating-
up of the sleeves before the infeed.
6 sleeves of each filling machine track are sucked off. The last sleeve of each track is
used as a test sample.
Procedure see following page.

NOTE
Improper handling of sleeves
Incorrect setting of filling machine through unusable activation patterns
If the sleeves to be tested are touched in the activation areas, the results of the analysis will
be incorrect.
 Do not touch activated section of sleeves.
 Be careful when removing the sleeves from the mandrels.
 Do not touch mandrel surface in order to avoid contamination.

9-30 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

3. Pull off activated sleeves from mandrels:

- Pull off activated sleeves cautiously


and immediately.

00180075

III. 9-28

4. In case of a re-adjustment of the temperature, repeat activation test from item 1.

Test samples
The test samples must be kept at least until the results of the bacteriological tests are
available. The samples will serve as a proof for the correct setting of the filling machine in
case of complaints; thus, keep the reserve samples as long as possible.
For this purpose, each test sample must show the following data:
 Production line or manufacturing no. of filling machine
 Track no.
 Temperature of bottom heating
 Air pressure of bottom heating
 Date and time of test
 Shift, day of manufacturing or production and time of sleeve and number of shipping box
(see sample).

Example for an inscription on a shipping box


240 PC091500 FRUIT RED BERRY MIX 10030/9
715456500 SWIFT 0004 2588 31.12.12 23:59 202016558 3114
Date, time of Shipping box no.
production
Pos: 45 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-31


ISO 16016. cb 1 / cf 1
Tests

Pos: 46 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1.1 Auswertung von Aktivierbildern "Bodenaktivierung" 004 cb 1 @ 25\mod_1357658772450_28.docx @ 185025 @ 4 @ 1

9.3.5.2 Analysis of activation patterns

1. Cut open activated sleeves opposite to longitudinal seam along the line through point 21.
2. Place polarisation filter onto aluminium-coated side of opened-up sleeve.
The activated section shows a deviating colour under the polarisation filter.

30 29

21 22 20 19 21

00180165

III. 9-29

= Activated PE
= Groove (crease lines)

The points 19 - 30 correspond to the identification points at the package, see section 9.3.3.
The proper temperature has been set, if
 the activated sections are conjoin.
 the activation limits are within the admissible range (details are described on the following
pages).
 no channel generation is visible.
Pos: 47 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-32 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 48 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1.1 Beurteilung der Aktiviertemperatur 003 (Bodenaktivierung) cb1 @ 53\mod_1380267897679_28.docx @ 2609349 @ 44 @ 1

9.3.5.3 Evaluation of activation temperature

Correct activation
Example:

30 29

21 22 20 19 21

00180109

III. 9-30

= Activated PE
= Groove (crease lines)

III. 9-31

INFO
  The coloured pictures in this carton check-up are shown for a better understanding, decisions
have to be made on the basis of the imaged schematic drawings within this document!

Follow protection mark Stand 15.11.2013 9-33


ISO 16016. cb 1 / cf 1
Tests

Characteristics for a correct activation:


 Folding edge
The activated border area goes close to
the groove (crease line) and, within the
still tolerable upper temperature, may
protrude into the groove (crease line),
see arrows in III. 9-32.

19 21

00180110

III. 9-32

 ID points: 19, 20, 21, 22


The activated areas stop immediately before the circles around the ID points 19, 20, 21
and 22 shown in the in III. 9-30 and in III. 9-33. The activation may slightly extend into this
area in the upper, still admissible temperature range.
 ID points: 29, 30
The activation reaches as far as the ID points 29 and 30 within the circular line, but must
not protrude beyond downwards in the direction of the triangle, see arrows in III. 9-33.

MAX MIN

29 30

20 19 21 22

00180111

III. 9-33

9-34 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Explanation of the circular line:


The circular area in the groove (crease line) cross area corresponds with the area X within the
circular line which goes as far as the grooves (crease lines), see III. 9-34.

x x

00180023

III. 9-34

Follow protection mark Stand 15.11.2013 9-35


ISO 16016. cb 1 / cf 1
Tests

Examples for a correct activation pattern of the machine type CFA 112:
Min – Max

Min.

30 29

21 22 20 19 21

00180112

III. 9-35

Opti

30 29

21 22 20 19 21

00180167

III. 9-36

x
Max.

30 29

21 22 20 19 21

00180166

III. 9-37

= Activated PE
= Groove (crease lines)
= Wrinkle generation
X = Blister generation

9-36 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Examples for a correct activation pattern of the machine type CFA 112:
Min – Max

Min

III. 9-38

Opti

III. 9-39

Max

III. 9-40

Follow protection mark Stand 15.11.2013 9-37


ISO 16016. cb 1 / cf 1
Tests

Examples for a correct activation pattern of the machine type CFA 124:
Min – Max

Min

00180156

III. 9-41

Opti

00180157

III. 9-42

Max

00180158

III. 9-43

= Activated PE
= Groove (crease lines)
= Wrinkle generation
X = Blister generation

9-38 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Examples for a correct activation pattern of the machine type CFA 124:
Min – Max

Min

III. 9-44

Opti

III. 9-45

Max

III. 9-46

Follow protection mark Stand 15.11.2013 9-39


ISO 16016. cb 1 / cf 1
Tests

Over-activation
Examples for inadmissible over-activation due to incorrect setting of machine components.

30 29

21 22 20 19 21

00180115

III. 9-47

= Activated PE
= Groove (crease lines)
= Wrinkle generation

III. 9-48

9-40 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Over-activation
Examples for inadmissible over-activation due to excessive activation temperature.

30 29

21 22 20 19 21

00180116

III. 9-49

= Activated PE
= Groove (crease lines)
= Wrinkle generation
X = Blister generation
A blister generation usually indicates an excessive activation.
Activation blisters are not allowed to reach the crease line.

III. 9-50

 The activated sections exceed the allowable borderlines over the whole area.
 The activated areas inadmissibly extend over points 19, 20, 21, 22, 29 and 30.

Follow protection mark Stand 15.11.2013 9-41


ISO 16016. cb 1 / cf 1
Tests

Under-activation
Examples for inadmissible under-activation due to incorrect setting of machine components:

30 29

21 22 20 19 21

00180117

III. 9-51

= Activated PE
= Groove (crease lines)
= Wrinkle generation

III. 9-52

9-42 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Under-activation
Examples for inadmissible under-activation due to insufficient activation temperature:

Severe breaks (see arrows) in the activation profile are not allowed.

30 29

21 22 20 19 21

00180118

III. 9-53

= Activated PE
= Groove (crease lines)

III. 9-54

An insufficient activation may result in a poor sealing quality and in faulty foldings.

Pos: 49 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-43


ISO 16016. cb 1 / cf 1
Tests

Pos: 50 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung "Über- und Unteraktivierung durch die Bodenheizung" BuPP cb1+cb7 @ 53\mod_1380184964671_28.docx @ 2605205 @ 44 @ 1

9.3.5.4 Fault elimination in case of over- and under-activation through bottom heating

WARNING
Hot surfaces
Risk of injuries through hot machine components
The machine components in the area of the bottom heating may be hot and may cause burns
in contact.
 Wear protective gloves and long-sleeved work clothes.
 Do not touch hot components.
 Allow filling machine to cool down.

INFO
  Enter changes of settings into Production Checklist.

1. Check temperature values for bottom heating and correct in accordance with the activation
patterns produced before.
Check temperature reading at operating unit.
The temperature should be nearly constant, i.e. should only show slight variations. Major
variations of the temperature readings indicate a defect of the temperature controller.
2. Check air pressure for bottom heating and have setting corrected through qualified staff, if
necessary.
In case of deviation, check sterile air pressure and set correctly, if necessary. See section
7.25.
Higher air pressure = stronger activation
Lower air pressure = weaker activation
3. Check air piping system for leaks.
4. Check activation heads and hoods for packaging material residue and deposits and clean,
if necessary. See section 8.11.4.3.

NOTE
Incorrect installation of activation heads and hoods
Damaging of filling machine
If the activation heads and hoods are installed incorrectly, machine components may be
damaged.
 Make sure when installing the activation heads and hoods that these are properly
installed.

5. Check temperature sensor of bottom heating for fixed position and for visible damages.
Have temperature sensor replaced by qualified staff, if required.
6. Check heating elements and have replaced by qualified staff, if required.
7. Check feeding of sleeves onto mandrels.
8. Check activation heads of bottom heating for correct installation position.
9. Check distance of activation heads to mandrels by qualified staff.
If the measures described above do not result in correct activation patterns, inform SIG
Combibloc Service, see chapter "General information/Addresses of customer service
agencies".

Pos: 51 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-44 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 52 /gds-BA/Prüfungen/Packungsprüfung/1.1.1.1 Einfluss einer Fehlfaltung neben der Rilllinie (Bodenheizung) cb1 @ 53\mod_1380268052351_28.docx @ 2609378 @ 44 @ 1

9.3.5.5 Impact of faulty folding beside the groove (crease line) on the bottom forming

In the course of the activation


pattern test an inspection of the
triangular folding is advisable.

The folding procedure was correct if


the folding was carried out along
both diagonal grooves (crease
lines).

III. 9-55

Faulty folding beside the groove


(crease line) acc. to III. 9-56 can
indicate
- incorrect pusher setting
- wrong bottom heater setting
or wrong activation nozzle
setting
- wrong position of bottom
heater heads
- incorrect lateral folder
setting
III. 9-56
For the evaluation of any faulty
folding an examination of the bottom
forming (inside and outside) is
necessary.

INFO
  For such an evaluation only samples which have been pulled off the mandrel without any
damage may be used!

Follow protection mark Stand 15.11.2013 9-45


ISO 16016. cb 1 / cf 1
Tests

Examination and evaluation of


bottom forming „inside“ see section
9.3.12.7

III. 9-57

If, in case of faulty foldings, unusual


package bottoms with a significantly
inconsistent alignment acc. to III.
9-58 are detected, proceed acc. to
chapter 9.3.5.6.
If, in case of faulty folding acc. to III.
9-56 no unusual bottom forms are
detected, production can be started
or continued.

III. 9-58
Pos: 53 /gds-BA/Prüfungen/Packungsprüfung/1.1.1.1 Fehlerbehebung bei Fehlfaltung (Rilllinie Bodenheizung) @ 24\mod_1344333895905_28.docx @ 182003 @ 4 @ 1

9.3.5.6 Fault elimination in case of faulty foldings

1. Check feeding of sleeves onto mandrels.


2. Check temperature values for bottom heating and correct in accordance with the activation
patterns produced before.
3. Have setting of lateral and longitudinal folder checked by qualified staff.
4. Check activation heads of bottom heating for correct installation position as well as for
package residue and deposits and clean, if necessary.
5. Have setting of mandrels to bottom press checked by qualified staff acc. to MI.

If the measures described above do not result in a correct package forming or bottom forming,
inform SIG Combibloc Service, see chapter “General information/Addresses of customer
service agencies”.

Pos: 54 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-46 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 55 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1 Füllvolumen (Gewicht) 003 cb1 @ 53\mod_1380268339079_28.docx @ 2609407 @ 33 @ 1

9.3.6 Filling volume (weight)

INFO
  Set fill volume (weight), so that the respective state regulations or statutory provisions are
fulfilled.

Test intervals:
 at the beginning of production
 each hour during production
 after change of product
 after all repair and maintenance work
1. Take off two packages of each track at
off-conveyor.
2. Check weight of package removed by
using scale. Com
biblo

SIG

243,00
00180171

III. 9-59

INFO
  Use test sample afterwards to carry out visual test of bottom or top forming or to check head
space.
Pos: 56 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung "Volumenkorrektur" @ 27\mod_1371557947362_28.docx @ 206460 @ 44 @ 1

9.3.6.1 Elimination of fault

Volume correction
The setting of the filling volume is done at the operating unit.

INFO
  Enter changes of settings into Production Checklist.

If the measures described above do not result in correct filling volume, inform SIG Combibloc
Service, see Chapter “General information/Addresses of customer service agencies”.
Pos: 57 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-47


ISO 16016. cb 1 / cf 1
Tests

Pos: 58 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1 Visuelle Kontrolle / Boden-, Giebelformung 004 cb1 @ 53\mod_1380268687338_28.docx @ 2609436 @ 33 @ 1

9.3.7 Visual check: outer appearance of bottom and top forming

Test intervals:
 at the beginning of production
 each hour during production
 when changing product, print design or pallet
 after all repair and maintenance works

INFO
  Use test samples used to check fill weight before.

1. Check overall appearance of package.


a
Particularly check the following points:
- Mechanical damages and
deformations
- Check of top folding
- The overlap of the top section is
slightly positive to ensure a quick test.
A positive overlap of the top section
"a" of 0-2 mm is admissible, III. 9-60.
In individual cases, these dimensions
may deviate slightly.
- The top flaps are correct and properly
bonded (details of top flap activation -
see section 9.3.11)
- Position and correctness of date

biblo
Com
SIG
00180175

III. 9-60

9-48 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

2. Check of bottom folding along the


bottom edge.
The bottom folding was carried out along
the groove (crease line).

00180169

III. 9-61

- The groove (crease line) is visible


exactly along the bottom edge
according to (see III. 9-63) or slightly
above the bottom edge according to
III. 9-62.

000AI006

III. 9-62

- The folded bottom web X1


according to III. 9-63 runs flush with
the bottom flap X2 and may have a
slightly negative or positive overlap
to the bottom flap edge X2 at the
outer bottom edges.
- Extreme wrinkles on the bottom
edge are not permitted.

X2 X1 000AI007

III. 9-63

Follow protection mark Stand 15.11.2013 9-49


ISO 16016. cb 1 / cf 1
Tests

- The overlap of the bottom section


shall not be negative! A positive
overlap of the bottom section "b" of
0-2 mm is necessary, see III. 9-64
(measuring range = package
centre).

00180120

III. 9-64

III. 9-65

III. 9-66

INFO
  Use test sample afterwards to check head space or to check top sealing.

Pos: 59 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-50 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 60 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung "Giebel/Boden" 002 @ 53\mod_1380185951977_28.docx @ 2605321 @ 44 @ 1

9.3.7.1 Elimination of fault

INFO
  Enter changes of settings into Production Checklist.

Top section
1. Check function and folding position of top prefolding tools.
2. Check correct installation position of top sealing tools.
3. Check function and temperature of steam injection.
4. Check top flap folder and heads for soiling as well as for deposits and proper function, see
section 9.3.11.1.

Bottom
1. Check feeding of sleeves onto mandrels.
2. Have lateral and longitudinal folder settings checked through qualified staff.
3. Check temperature and air pressure of bottom heating, see section 9.3.5.4.
4. Check activation heads of bottom heating for correct installation position as well as for
package residue and deposits and clean, if necessary.
5. Have setting of mandrels to bottom press checked by qualified staff acc. to MI.

If the measures described above do not result in a correct package forming, inform SIG
Combibloc Service, see chapter “General information/Addresses of customer service
agencies”.
Pos: 61 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-51


ISO 16016. cb 1 / cf 1
Tests

Pos: 62 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1 Kopfraumvolumen 005 cb1 @ 53\mod_1380269403331_28.docx @ 2609465 @ 33 @ 1

9.3.8 Head space

INFO 1
The head space achievable with the steam
injection depends on the generation of foam
of the product and on the steam supply.
Only use package with correctly set filling
volume to check head space.
Test intervals:
 at the beginning of production
 when changing product
 after all repair and maintenance work
00005224
 when required, f.ex. when changing the
package forming appearance III. 9-67

INFO
  Use the test samples used to check the fill weight or for the visual control / forming before.

Equipment required:
 Graduated cylinder, volume = 50 ml
 Water-filled container
 Scissors

The following head space volumes (1) may be achieved with a properly working steam
injection:

Format range non-foaming heavily foaming


CFA112 ~ 5 ml ~ 15 ml
CFA124 ~ 5 ml ~ 15 ml

INFO
  When using packages with underfilling, the head space can be different.

9-52 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Measuring of head space


1. Undo top flaps of test package and
1
raise top web (1).

®
bi bloc
Com
SI G
00005225

III. 9-68

2. Immerse test package, with top web


pointing downwards, into container filled
with water.
3. Cut open top flap section as shown and
hold package in this position.

000AI014

III. 9-69

Follow protection mark Stand 15.11.2013 9-53


ISO 16016. cb 1 / cf 1
Tests

4. Completely fill up graduated cylinder


inside container.

000AI015

III. 9-70

5. Position graduated cylinder as shown


on, so that no air can penetrate into
cylinder.
6. Bring test package (top web is still
pointing downwards) to opening of the
immersed graduated cylinder.

000AI016

III. 9-71

7. Now turn test package and slightly


squeeze, until all of the air inside the
package is fully forced into the
graduated cylinder

00005229

III. 9-72

9-54 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

8. The water volume displaced in the


graduated cylinder corresponds to the
head space volume of the test package,

A
see dimension "A“ in III. 9-73.
10
20
30
40
50

00180121

III. 9-73
Pos: 63 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung "Kopfraumvolumen" @ 27\mod_1371557500248_28.docx @ 206364 @ 44 @ 1

9.3.8.1 Elimination of fault

INFO
  Enter changes of settings into Production Checklist.

1. Check accuracy of filling and adjust, if necessary,


2. Check product for foam generation,
3. Check steam supply and function of steam injection (function of cycle valve of steam
injection, set steam temperature, function of condensate trap).

INFO
  The steam temperature has an impact on the top sealing. After changing the steam
temperature, it is thus necessary to check the top seam.

If the measures described above do not result in the reduction of the head space intended,
inform SIG Combibloc Service, see Chapter “General information/Addresses of customer
service agencies”.
Pos: 64 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-55


ISO 16016. cb 1 / cf 1
Tests

Pos: 65 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1 Packungsdichtigkeit allgemein 002 cb1 @ 53\mod_1380269707106_28.docx @ 2609584 @ 334444 @ 1

9.3.9 General leak test for carton package

A faulty top or bottom sealing leads to top / bottom leakers.


The squeezing of the package and the check of the top and bottom seal enables a quick
assessment of the quality of the package top / bottom section.
Test intervals:
 at the beginning of production
 each hour during production
 when changing product, print design or pallet with a change of the day of manufacturing in
the shipping box inscription
 after all repair and maintenance works

NOTE
Incorrect steam injection
Incorrect top sealing
If steam injection is incorrect, top sealing will be carried out incorrectly.
 Check function of steam injection before test works.

9.3.9.1 Test for top leakers by squeezing of the carton package

1. Check one package of each track of the


test packages used for the prior testing
of the top and bottom forming.
2. The package is taken as shown on
picture III. 9-74, turn away longitudinal
seam of package from body.
3. Both forefingers are placed onto top
triangles (2) and pressed slightly.
4. While slightly pressing the top triangles,
exert medium pressure onto package by
1
the other fingers until top web starts
bulging (1) (squeezing time approx 5
seconds).
2

00180122

III. 9-74

INFO
  No product shall penetrate.
Do not return squeezed packages to the converting process.

9-56 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

9.3.9.2 Test for bottom leakers by squeezing of the carton package

1. Check one package of each track of the


test packages used for the prior
2
squeezing test of the top seal.
2. The package is taken as shown on
picture III. 9-75, turn away longitudinal
seam of package from body.
3. Both forefingers are placed onto top
triangles (2) and pressed slightly.
4. While slightly pressing the top triangles,
exert medium pressure onto package by
the other fingers until bottom web starts 1 00180106
bulging (1) (squeezing time approx 5
seconds ). III. 9-75

INFO
  No product shall penetrate.
Do not return squeezed packages to the converting process.

Pos: 66 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1 Giebelverschweißung 004 cb1 @ 53\mod_1380269880068_28.docx @ 2609933 @ 334444 @ 1

9.3.10 Top sealing

A faulty top sealing leads to top leakers.


The complete test for top leakers includes the following test procedures:
 Squeezing of the carton package.
 Visual check.
 Check-up of weld position on top and check of the top seal.
 “Blue/red dye test" as a final and conclusive check for top leakers.

The check of the top seal enables a quick assessment of the quality of the package top
section.

Test intervals:
 at the beginning of production
 each hour during production
 when changing product, print design or pallet with a change of the day of manufacturing in
the shipping box inscription
 after all repair and maintenance works

INFO
  Use the test samples used to check the general leak test for package.

Follow protection mark Stand 15.11.2013 9-57


ISO 16016. cb 1 / cf 1
Tests

9.3.10.1 Check-up of weld position

1. Undo top flaps from finished


package top or fold up and 2
check impression of sealing
tools (1).

With a correct setting of welding


tools, mark of welding tools (1) is
1
parallel to upper edge (2) of top
web, see III. 9-76.

00005232

III. 9-76

If welding tools are not set parallel, 2


the impression of the welding tools
(1) runs off angle to the upper edge
(2) of the top web, see III. 9-77.

00180124

III. 9-77

A strong angular impression of the


welding tools (1) up to the upper
edge (2) is not permitted, as shown 2
in III. 9-78.
Detail measure for the valid working
range, see in chapter 9.3.10.4
below III. 9-84.

00180105

III. 9-78

9-58 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

9.3.10.2 Overlap of top section

The overlap of the top section is slightly


positive to ensure a quick test.
A positive overlap "A" of 0 to 2 mm is
admissible, see III. 9-79.
A
In individual cases, these dimensions may
deviate slightly.

00180125

III. 9-79

INFO
  In order to carry out further tests, one package of each track is cut open and drained.

Pos: 67 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-59


ISO 16016. cb 1 / cf 1
Tests

Pos: 68 /gds-BA/Prüfungen/Packungsprüfung/1.1.1.1 Prüfung der Schweißnaht 003 cb1 @ 25\mod_1357736044216_28.docx @ 185225 @ 4 @ 1

9.3.10.3 Check up of weld

1. Cut open package slightly on top of


package bottom section at the 3 sides
next to or opposite to the longitudinal
9
seam side and drain product.
2. Now push down top section and open 14
package at right edge opposite to
longitudinal seam through point 14 up to
point 9 up to weld.
The points marked correspond to the
identification points at the package, see
section 9.3.3.

00005235

III. 9-80

3. Slowly open up weld on complete length


of package top from inside towards
outside.

00005236

III. 9-81

9-60 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

4. For checking the light gap in weld, hold


the sample (welding seam) against
sufficient light source, as shown in III.
9-82.

00180154

III. 9-82

5. For checking the PE-wedge on weld


seam edge, ensure the present PE-
wedge by touch with the finger.

00180155

III. 9-83
Pos: 69 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-61


ISO 16016. cb 1 / cf 1
Tests

Pos: 70 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1.1 Auswertung der Schweißnaht 005 cb1 @ 54\mod_1380285023565_28.docx @ 2610252 @ 44 @ 1

9.3.10.4 Analysis of weld

Example 1: Correct top welding.

37 40 41 40 38 37 36 37

1
40 38 37
A A
B

X
C
B
A

2
2

00180126

III. 9-84

= Interwoven sections with two layers of aluminium


= Open board
A = Optimum light gap in weld: 1 to 1,5 mm
allowed: 1.5 ± 0.5 mm (dimensions are not applicable to longitudinal seam
section)
B = Total width of weld 3 + 1 mm
C = Distance from upper edge top web approx. 2 - 1 mm
X = Cross section through weld
1 = Opposite sections board / structure containing the seam
2 = Weld seam edge / PE wedge

The sealing parameters or the settings of the sealing tools are correct if
 the complete area of the weld (III. 9-84, Item. 1) is interwoven. On one side, the aluminium
is still visible in the weld.
 a clearly noticeable PE wedge / weld edge (III. 9-84, Item 2) towards the product which
mainly guarantees that there are no package leakers.
 the translucent weld has the same width of (dimension A) on the complete length.
 the aluminium layer of the translucent weld (III. 9-84, dimension A) is mostly destroyed or
if only a few aluminium parts can be detected.

9-62 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Example 2: Allowed top welding at transitional section to longitudinal seam.

35 35 x
B
A

39 38 39 38 39 38 39 38

D 2

00180170

allowed, optimum allowed,


when PE wedge is detectably when discolouring towards the
present bottom is blocked by PE wedge
III. 9-85

= Open board
= Unwelded sections
= Interwoven sections with two aluminium layers
X = Discolouring
A = Light gap in weld
B = Total width of weld
D = Allowed: less than 1 mm
2 = Weld seam edge / PE wedge is present

Follow protection mark Stand 15.11.2013 9-63


ISO 16016. cb 1 / cf 1
Tests

35 35 x
A
B

40 39 38 40 39 38 40 39 38 40 39 38
00180128

allowed limit, optimum allowed limit,


when PE wedge is detectably when discolouring towards the
present bottom is blocked by PE wedge
III. 9-86

As slight constriction of the PE wedge is allowed with a non-translucent weld if the PE wedge
is detectably present.
A weak pointed discolouring at the transitional area to the longitudinal seam "Point 38" or
"Point 39" is allowed.
to X:
The point-shaped discolouring
- must be completely inside the interwoven area,
- and must be blocked by a PE wedge against the product and,
- must not be larger than the light gap in the discoloured area.

9-64 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Example 3: Faulty top welding at transitional section to longitudinal seam.

III. 9-87

= Open board
= Unwelded sections
= Interwoven sections with two aluminium layers
= Discolouring
A = Light gap in weld
B = Total width of weld

35 35
B
A

40 39 38 40 39 38 40 39 38 40 39 38
00180130

III. 9-88

Follow protection mark Stand 15.11.2013 9-65


ISO 16016. cb 1 / cf 1
Tests

At transitional area to longitudinal seam the weld is, as described, not allowed acc. to III. 9-87
and III. 9-88 if:
- no detectable PE wedge with a weak sealing is present,
- the interwoven section of the weld seam becomes smaller than the light gap "A",
- a continuous unwelded section is present,
- the point-shaped discolouring is larger than the light gap in the discoloured area.

Possible reasons:
 Anvil is positioned laterally to direction of movement
 Package pockets are displaced laterally to the running direction or bent (since usually only
individual pockets are displaced or damaged, all pockets must be checked for their correct
positions and intactness).
 Longitudinal seam deviating from default dimension. see section 9.2.3.
 Pressure too low (risk of channel).
 Pressure too high (risk of discolouring points).
Visible coloured point from the outside is not allowed.

In case of the occurrence of a large-scale discolouring at the transitional section to the


longitudinal seam not blocked with a PE wedge towards the product or if a continuous channel
is detected in the area (ID point 35) proceed according to section 9.3.10.5.

9-66 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Example 4: Faulty welding with energy output too low.

37 40 41 40 38 37 36 37

B
A

00180131

III. 9-89

= Open board
= Interwoven sections with two aluminium layers
A = Light gap in weld
B = Total width of weld

III. 9-90

In case of an excessively low welding energy, the light gap A in the middle of the seam is too
small or does not exist at all. The width of the weld B becomes smaller with a reduced welding
energy resulting from:
 a pressing force of welding tools which is too low
 the influence of the steam injection
 the influence of drying temperature
 the influence of the packaging material

Follow protection mark Stand 15.11.2013 9-67


ISO 16016. cb 1 / cf 1
Tests

Example 5: Inadmissible discolouring in centre of weld.

37 40 41 40 38 37 36 37

B
A

A
B
00180132

III. 9-91

= Open board
= Interwoven sections with two aluminium layers
= Discolouring
A = Light gap in weld
B = Total width of weld

III. 9-92

Inadmissible colouring in the translucent welding seam A-A caused by:


 excessive pressing force of welding tools
 the influence of the steam injection
 the influence of the packaging material

9-68 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Example 6: Faulty setting of welding tools.


Use of welding tools not parallel.

41 40 38 37 36
A

A
B

B
A

00180133

III. 9-93

= Open board
= Interwoven sections with two aluminium layers
= Discolouring
A = Light gap in weld
B = Total width of weld

III. 9-94

Example 7: faulty welding with worn-out welding tools.

III. 9-95

Follow protection mark Stand 15.11.2013 9-69


ISO 16016. cb 1 / cf 1
Tests

Example 8: Faulty welding tool setting with energy output too low.
Use of welding tools not parallel.

41 40 38 37 36
A
B
A

A
B
00180134

III. 9-96

= Open board
= Interwoven sections with two aluminium layers
A = Light gap in weld
B = Total width of weld

III. 9-97

A variation in the width of the light gap in the weld "A" is caused by:
 a setting of the welding tools which is not parallel

9-70 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Example 9: Faulty position of weld.


The distance between weld and groove (crease line) is too small.

A
B

00180102

III. 9-98

= Open board
= Interwoven sections with two aluminium layers
A = Light gap in weld
B = Total width of weld
C = Distance from upper edge top web

Detail measure for the valid working range, see section 9.3.10.4, III. 9-84.

III. 9-99

Possible reasons for a faulty position of weld:


 faulty setting of welding tools
 incorrect position of package pockets in relation to welding tools.

Follow protection mark Stand 15.11.2013 9-71


ISO 16016. cb 1 / cf 1
Tests

Example 10: Faulty position of weld.


The distance between weld and package edge is too small.

A
B

00180101

III. 9-100

= Open board
= Interwoven sections with two aluminium layers
A = Light gap in weld
B = Total width of weld
C = Distance from upper edge top web
Detail measure for the valid working range, see section 9.3.10.4, III. 9-84.

III. 9-101

Possible reasons for a faulty position of weld:


 faulty setting of welding tools
 incorrect position of package pockets in relation to welding tools.

INFO
  Afterwards use test samples to check activation of top flaps.

Pos: 71 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-72 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 72 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/generell/1.1.1.1 Fehlerbehebung "Giebelverschweißung" 005 cb1 @ 54\mod_1380522965051_28.docx @ 2610403 @ 44 @ 1

9.3.10.5 Elimination of fault

INFO
  Enter changes of settings into Production Checklist.

1. Check the actual longitudinal seam dimensions ”D” and ”E” at respective packages and at
randomly selected sleeves from the batch involved.

Longitudinal seam default values/Tolerances


of packaging materials: E
Format D E
Cb 1 11;8 ± 0,8 mm 8,7 ± 1 mm

00005244

III. 9-102

2. If the dimensions of the longitudinal seams are outside the tolerances specified for the
packaging material, please inform SIG Combibloc Service, see chapter "General
Information/Addresses of Service Agencies".
3. Have parameter setting of ultrasonic generators checked by qualified staff and adjusted, if
necessary.
4. In order to obtain the correct surface pressure of the welding tools, check air pressure
setting for pressure cylinders and correct setting, if necessary (depending on packaging
material, temperature of steam injection and drying temperature).
5. Check function of steam injection and have repaired by qualified staff, if necessary.
6. Have setting of anvils and welding horns checked or corrected by qualified staff.
7. Have setting and condition of package pockets checked, or corrected, if necessary, by
qualified staff.
8. Check temperature setting of drying zone, check product data, check function of the
heater unit and temperature sensor or have fault eliminated by qualified staff.

If the measures described above do not result in correct top sealing, inform SIG Combibloc
Service, see Chapter “General information/Addresses of customer service agencies”.
Pos: 73 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

Follow protection mark Stand 15.11.2013 9-73


ISO 16016. cb 1 / cf 1
Tests

Pos: 74 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1 Aktivierung der Giebellaschen 004 cb1 @ 54\mod_1380523100592_28.docx @ 2610432 @ 33 @ 1

9.3.11 Activation of top flaps

Impact of activation of top flaps on top leakers


An excessive activation of the top flaps at the topforming station can cause a sealing inside of
the package and may cause top leakers during loading and transport.

Test intervals:
 at the beginning of production
 each hour during production
 when changing product, print design or pallet with a change of the day of manufacturing in
the shipping box inscription
 after all repair and maintenance works

INFO
  Use test samples used to check top welding before.

1. In order to evaluate the activation, place polarisation filter onto aluminium-coated side of
opened-up section of top.
The activated section shows a deviating colour under the polarisation filter.

Analysis
Admissible activation
Example:

1 1

00180135

III. 9-103
= Open board
= Interwoven sections with two aluminium layers
= Activated PE

With a correct activation of the top flaps, insides of the package show no or only slightly
discoloured areas (1). The activated sections are located in the centre of the top flaps.
An activation exceeding the groove (crease lines), as well as a blister generation are
inadmissible.
In case of a faulty sealing of the top flaps proceed according to chapter 9.3.11.1. Before
increasing the activation temperatur, other parameters as position of the activation heads,
soiling, etc. have to be checked as well.

9-74 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Inadmissible activation
Example:

2 1

00180136

III. 9-104

= Open board
= Interwoven sections with two aluminium layers
= Activated PE
= Blister

An excessive activation (2) exceeding the groove (crease lines) is not allowed.
The reason for an excessive activation on one side may, for example, be a clogging of the
opposite activation head (see Item 1) or an incorrect position of the activation heads.

INFO
  If the reason was not detected and the temperature of the top forming station had been raised
as a wrong measure, this will result in an excessive activation in point (2).

III. 9-105

Follow protection mark Stand 15.11.2013 9-75


ISO 16016. cb 1 / cf 1
Tests

Wrong setting of activation head


Example:

1 2

00180137

III. 9-106
= Open board
= Interwoven sections with two aluminium layers
= Activated PE
= Blister

III. 9-107

Abb. 9-108
A misaligned position of activation (1) or an excessive activation on both sides ((1) and (2))
exceeding the groove (crease lines), as well as a blister generation are not allowable.
The reason for an offset position of the activated area (1) is the incorrect position of the
activation head.

INFO
  If the reason was not detected and the temperature of the top forming station had been raised
as a wrong measure, this will result in an excessive activation on both sides.

INFO
  Afterwards use test samples to check the activation of bottom section of carton package.
Pos: 75 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ @ 1

9-76 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 76 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung "Giebellaschen" cb1/7 @ 53\mod_1380189210102_28.docx @ 2605524 @ 44 @ 1

9.3.11.1 Elimination of fault

WARNING
Hot surfaces
Risk of injuries through hot machine components
The machine components in the area of the bottom heating may be hot and may cause burns
in contact.
 Wear protective gloves and long-sleeved work clothes.
 Do not touch hot components.
 Allow hot machine parts to cool down.

INFO
  Enter changes of settings into Production Checklist!

1. Check temperature setting for top-forming station and adjust, if necessary.


2. Check temperature reading at operating unit.
The temperature should be nearly constant, i.e. should only show slight variations.
Large deviations of the temperature readings indicate a defect.

3. Check air piping system for leaks.


4. Check activation heads for soiling and
clean, if necessary. See illustration.
5. Check position of activation heads (1)
and adjust, if necessary. See illustration.
6. Check temperature sensor at heaters of
top forming station for fixed installation
and check for visible damages. If
necessary, have temperature sensor
replaced by qualified staff.
7. Check heating tube and hot-air
distributor for soiling and damages,
clean and have repaired by qualified
staff, if necessary.

1
00005050

Ill. 9-109

If the measures described above do not result in correctly sealed top flaps, inform SIG
Combibloc Service, see chapter “General information/Addresses of customer service
agencies”.

Pos: 77 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

Follow protection mark Stand 15.11.2013 9-77


ISO 16016. cb 1 / cf 1
Tests

Pos: 78 /gds-BA/Überschriften/1.1.1 Aktivierbild am Packungsboden @ 8\mod_1313391534724_28.docx @ 17391 @ 3 @ 1

9.3.12 Activation pattern at bottom section


Pos: 79 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1.1 Prüfung der verschweißten Bereiche "Aktivierbild Packungsboden" 003 @ 53\mod_1380190305122_28.docx @ 2606227 @ 443 @ 1

9.3.12.1 Check of welded sections

Test intervals:
 at the beginning of production
 each hour during production
 when changing product, print design or pallet with a change of the day of manufacturing in
the shipping box inscription
 after all repair and maintenance works

INFO
Use the test samples that were used to
check the top seam and the top flap
activation before.

00005248

III. 9-110

1. Tear open package at all four edges


down to bottom and fold down sides of
package.

00005061

III. 9-111

Pos: 80 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

9-78 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 81 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1.1 Auswertung von Aktivierbildern "Packungsboden" 004 cb1 @ 54\mod_1380523466935_28.docx @ 2610461 @ 44 @ 1

9.3.12.2 Analysis of activation patterns

Activation with correct activation temperature


1. Place polarisation filter onto upper half of package.
The activated section shows a deviating colour under the polarisation filter.

Example for a correct activation of packages bottom without visible heating up through drying
station:

= Activated PE
= Still admissible
21 19
activation exceeding
groove (crease line)
X = Longitudinal seam 30 29
activation

22 X 20

00180172

III. 9-112

 The points 19, 20, 21, 22, 29 and 30 identified correspond to the identification points at the
package, see section 9.3.3.
 Between points 29 and 30, activation shall only be visible at the side of the longitudinal
seam.

III. 9-113

INFO
  The corresponding sleeve activation, see III. 9-30 in chapter see section 9.3.5.3.
For an explanation regarding the activation border see chapter 9.3.4.1.

Follow protection mark Stand 15.11.2013 9-79


ISO 16016. cb 1 / cf 1
Tests

Examples for a correct activation pattern of bottom section of package: Min – Max

Min
= Activated PE
21 19
= Still admissible
activation exceeding
crease line
30 29
= groove (crease line)

X = Longitudinal seam
activation
22 X 20

00180173

III. 9-114

Opti
21 19

30 29

22 X 20

00180174

III. 9-115

Max

21 19

30 29

X
22 20

00180141

III. 9-116

9-80 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Over-activation
Examples for inadmissible over-activation due to incorrect setting of machine components.

 The activated sections


excessively extend over the
complete area.
21 19
 The bottom edges are activated.
 The activation considerably
protrudes over the groove 30 29
(crease line) in the folded
areas..

X
22 20

00180142

III. 9-117

= Activated PE
= Inadmissible activation exceeding groove (crease line)
= Wrinkle generation
X = Longitudinal seam activation

III. 9-118

Follow protection mark Stand 15.11.2013 9-81


ISO 16016. cb 1 / cf 1
Tests

Over-activation
Examples for inadmissible over-activation due to excessive activation temperature.

 The activated sections


excessively extend over the
complete area.
21 19
 The bottom edges are activated.
 The activation considerably
protrudes over the groove 30 29
(crease line) in the folded areas.

X
22 20

00180143

III. 9-119

= Activated PE
=Inadmissible activation exceeding groove (crease line)
= Wrinkle generation
X = Longitudinal seam activation

III. 9-120

9-82 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Under-activation
Example for inadmissible under-activation due to incorrect setting of machine components:

The small activated areas at the


lower side of the triangles indicated
by the arrows (III. 9-121) show a
noncontinuous activation pattern
which is not permitted.

III. 9-121

= Activated PE
= Longitudinal seam activation
X = Still admissible activation exceeding groove (crease line)

III. 9-122

Follow protection mark Stand 15.11.2013 9-83


ISO 16016. cb 1 / cf 1
Tests

Under-activation
Example for inadmissible under-activation due to insufficient activation temperature:

21 19

30 29

X
22 20

00180144

III. 9-123

= Activated PE
X = Longitudinal seam activation

III. 9-124
Pos: 82 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung "Aktivierbild Packungsboden" BuPP @ 53\mod_1380190622016_28.docx @ 2606755 @ 444 @ 1

9.3.12.3 Elimination of fault

INFO
  Enter changes of settings into Production Checklist.

For the fault elimination please follow to the fault elimination of the activation pattern at the
sleeve, see section 9.3.5.4.
If the measures described above do not result in correct activation patterns, inform SIG
Combibloc Service, see section "General information/Addresses of customer service
agencies".
Pos: 83 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

9-84 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 84 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1.1 Optische Prüfung der Bodenverschweißung 002 cb1 @ 25\mod_1357742160817_28.docx @ 185363 @ 4 @ 1

9.3.12.4 Visual check of bottom seal

III. 9-125
X = PE protrusion is not necessary at these points.
Pos: 85 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1.1 Einfluss von Aluminiumbrüchen an der Umlegekante auf die Bodendichtheit 002 cb1 @ 54\mod_1380523852042_28.docx @ 2610490 @ 444 @ 1

9.3.12.5 Influence of aluminium breakage at the folding edge on bottom seal

Aluminium breakage in the area of the folding edge can, under certain circumstances, lead to
leaking bottoms. In case of strong over-activation of the bottom the folding edge is overheated
which can result in cracks at the folding edge after the longitudinal folding / bottom pressing,
see III. 9-126 and III. 9-127.

III. 9-126

INFO
  Leaking package bottoms can be a result of this; however, they most frequently are caused by
incorrect adjustment of other mechanical components such as pusher, lateral or longitudinal
folder position, pressure and incorrect mandrel position in relation to bottom press.
If over activation is not the problem and if the blue/red dye test is ok, production can be started
or continued.

Follow protection mark Stand 15.11.2013 9-85


ISO 16016. cb 1 / cf 1
Tests

III. 9-127
Pos: 86 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

9-86 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 87 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung Bodenformung @ 53\mod_1380191304614_28.docx @ 2607851 @ 44 @ 1

9.3.12.6 Fault elimination

1. Check activation pattern and temperature values of the bottom heating and, if necessary,
correct in accordance with the activation patterns produced before.

INFO
  Generating activation patterns – see section 9.3.5.1.

2. Check feeding of sleeves onto mandrels.


3. Have setting of lateral and longitudinal folders checked by qualified staff.
4. Have setting of positioning of mandrels to bottom press checked by qualified staff.
5. Check overlap of the bottom section.
6. Blue/red dye test, see section 9.3.16.1.

If the measures described above do not lead to a correct result, inform SIG Combibloc
Service, see chapter “General information/Addresses of customer service agencies”.
Pos: 88 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

Follow protection mark Stand 15.11.2013 9-87


ISO 16016. cb 1 / cf 1
Tests

Pos: 89 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1.1 Prüfung der Bodenformung (Innen) 002 cb1 @ 25\mod_1357742853134_28.docx @ 185409 @ 4 @ 1

9.3.12.7 Check of bottom forming (inside)

Bottom offset - inside

If correctly set, both triangle tips (2)


are positioned directly beside the
folding edge (1), see III. 9-128.

III. 9-128

III. 9-129
Max. tolerable offset:
“A“ = 2 mm

III. 9-130

9-88 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

An excessive distance (A) between the folding edge (1) and the triangle tip (2) according to III.
9-131 is a sign of a possible incorrect bottom folding.

INFO
  In case of a distance (A) larger than 2mm stop the machine and proceed according to chapter
9.3.12.8. If the measures according to this chapter do not lead to a correct result, have the
basic setting checked by Combibloc Service.
A distance smaller than 2 mm does not necessarily mean that the bottom seal is leakproof,
especially if there are other misadjustments, such as wrong bottom temperature, wrong
pressure etc.
In case of doubt, a check according to chapter 9.3.12.8 respectively the examination of the
basic setting acc. MI is advisable.
Once the examinations have been carried out, the blue/red dye test is obligatory and decisive
for a production start or continuation.

Examples of incorrect „bottom offset – inside and outside”

III. 9-131

Follow protection mark Stand 15.11.2013 9-89


ISO 16016. cb 1 / cf 1
Tests

The reason for an excessive distance between the triangle tip and the folding edge is mostly a
consequence of a faulty folding in the bottom area and may be caused by:
- incorrect bottom temperature setting
- incorrect activating nozzle setting
- incorrect pusher setting
- incorrect setting of lateral and longitudinal folders,
- incorrect mandrel position in relation to bottom press

In case of any excessive distance (A) acc. to III. 9-131 proceed acc. to chapter 9.3.12.8.

9-90 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Position of triangular flaps


With correctly folded triangular flaps
the tip of the triangle (2) is
positioned in alignment with the
notch in the mandrel (3) or slightly
behind – see III. 9-132.

III. 9-132
Any excessive distance acc. to III.
9-133 can lead to a channel at ID
point 29 or 30 respectively to
leaking bottoms, especially if,
- the activation temperature
is too low in this area, or
- the bottom contact pressure
is too low.
In this case proceed acc. to chapter
9.3.12.8.
See also III. 9-151 in chapter
9.3.13.2.
III. 9-133

Pos: 90 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

Follow protection mark Stand 15.11.2013 9-91


ISO 16016. cb 1 / cf 1
Tests

Pos: 91 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung Bodenformung @ 53\mod_1380191304614_28.docx @ 2607851 @ 44 @ 1

9.3.12.8 Fault elimination

1. Check activation pattern and temperature values of the bottom heating and, if necessary,
correct in accordance with the activation patterns produced before.

INFO
  Generating activation patterns – see section 9.3.5.1.

2. Check feeding of sleeves onto mandrels.


3. Have setting of lateral and longitudinal folders checked by qualified staff.
4. Have setting of positioning of mandrels to bottom press checked by qualified staff.
5. Check overlap of the bottom section.
6. Blue/red dye test, see section 9.3.16.1.

If the measures described above do not lead to a correct result, inform SIG Combibloc
Service, see chapter “General information/Addresses of customer service agencies”.
Pos: 92 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

9-92 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 93 /gds-BA/Prüfungen/Packungsprüfung/1.1.1.1 Einfluss der Trockenstation auf die Bodendichtheit 003 cb1 @ 25\mod_1357743213921_28.docx @ 185432 @ 4 @ 1

9.3.12.9 Influence of drying station on bottom leakers

Allowable heating-up through drying station


The hot air of the drying station flowing towards the bottom section of the package heats up
this section, particularly for small package heights. This generates a bright or coloured section
with visible border zones. The areas activated through the bottom heating remain fully visible.

Example for a correct bottom activation with a visible, but still admissible heating-up through
the drying station.

= Activation through
bottom heating
= Heating up through 21 19
drying station

30 29

22 20

00180152

III. 9-134

III. 9-135

Follow protection mark Stand 15.11.2013 9-93


ISO 16016. cb 1 / cf 1
Tests

Inadmissible activation through drying station


An excessive heating-up through drying air leads, in particular at the groove (crease lines), to
an inadmissible activation of the polyethylene. This may lead to damages to the inner coating.
The sections activated by the bottom heater are not fully visible anymore.

Example of an "Over-activation" through the drying station..

= Activation through
bottom heating
= Heating up through 21 19
drying station
= Discoloured border
areas 30 29

22 20

00180153

III. 9-136

III. 9-137

Pos: 94 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

9-94 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 95 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung "Unzulässige Aktivierung durch die Trockenstation" @ 27\mod_1371555745331_28.docx @ 206172 @ 44 @ 1

9.3.12.10 Elimination of fault in case of inadmissible activation through drying station

1. Have temperature setting of all heads of drying zone checked or adjusted by qualified
staff.
Check temperature reading at operating unit.
The temperature should be nearly constant, i.e. should only show slight variations. Large
deviations of the temperature readings indicate a defect.

2. Have sterile air pressure checked by qualified staff, .


If inadmissible activation areas at the bottom section of the carton cannot be eliminated to a
sufficient extent by way of the measures described, inform SIG Combibloc-Service,see
Section "General Information/Addresses of Customer Services".

INFO
  Use test samples afterwards to check the welded bottom sections.

Pos: 96 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

Follow protection mark Stand 15.11.2013 9-95


ISO 16016. cb 1 / cf 1
Tests

Pos: 97 /gds-BA/Überschriften/1.1.1 Bodenverschweißung @ 2\mod_1312788584904_28.docx @ 7161 @ 3 @ 1

9.3.13 Bottom sealing


Pos: 98 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1.1 Prüfung der verschweißten Bereiche "Bodenverschweißung" 004 cb1 @ 54\mod_1380525270088_28.docx @ 2610519 @ 434 @ 1

9.3.13.1 Check of welded sections

The check of the bottom sealing enables a quick assessment of the quality of the package
bottom section. Any channel generation can be reliably detected this way.

Test intervals:
 at the beginning of production
 each hour during production
 when changing product, print design or pallet with a change of the day of manufacturing in
the shipping box inscription
 after all repair and maintenance works

The complete test for bottom leakers includes the following test procedures:
 Squeezing of the carton package
 Use the same test sample used for the “top seal squeezing test” (description and
implementation, see section 9.3.9).
 Visual check
 Check of bottom sealing
 “Blue/red dye test" as a conclusive check for bottom leakers

The squeezing of the carton package and the check of the bottom seal enables a quick
assessment of the quality of the carton package bottom section.

INFO
  For further testing, use test samples used for the prior check of the activation pattern of the
bottom section of the package.

9-96 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

INFO
  In order to check the bottom section of the package, tear open according to instructions given.
See following pages.

Tear off bottom section of package


1. Loosen web and lift up.

III. 9-138

2. Separate web at both sides and fold


over diagonal folding edges.

III. 9-139

Follow protection mark Stand 15.11.2013 9-97


ISO 16016. cb 1 / cf 1
Tests

3. Carefully and slowly tear open package


bottom from the inside along the four
diagonal folding edges and web.

III. 9-140

4. Cut open bottom section opposite to


edge seam.

00005258

Abb. 9-141

9-98 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

5. Open up package bottom for test


purposes.

00005259

III. 9-142
Pos: 99 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

Follow protection mark Stand 15.11.2013 9-99


ISO 16016. cb 1 / cf 1
Tests

Pos: 100 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1.1 Auswertung der verschweißten Bereiche 004 cb1 @ 54\mod_1380525384567_28.docx @ 2610548 @ 44 @ 1

9.3.13.2 Analysis of welded sections

Correct welding of bottom section


Example 1:

30 29

21 22 20 19 21

00180145

III. 9-143

= Activated PE
= Open board

III. 9-144

The points 19 - 30 correspond to the identification points at the package, see section 9.3.3.
Total area torn open only shows paper board.

9-100 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Example 2:

30 29

21 22 20 19 21

00180146

III. 9-145

= Activated PE
= Open board

Small-scale, unwelded sections (see arrows) next to longitudinal seam, which are enclosed,
are admissible.

INFO
  If large-scale unwelded sections will occur next to the longitudinal seam that extend up to the
end of the package edge or that stop shortly before, see section 9.3.14.1.

Follow protection mark Stand 15.11.2013 9-101


ISO 16016. cb 1 / cf 1
Tests

Example 3:

30 29

21 22 20 19 21
A A C C

00180147

III. 9-146

= Activated PE
= Open board
= Open aluminium

The torn section shows board as well as aluminium. In this case, the polarisation filter should
be placed onto the bottom torn open to enable a reliable evaluation.
If aluminium sections are coloured under the polarisation filter, such sections are coated with
PE. If no discolouring is visible on the respective, opposite sections A-A, the welding is
correct.
In this case, the PE layer was separated from the aluminium and is located on one side.
Unwelded (closed) island sections in the C-C area are insignificant.

9-102 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Example 4:

A B

30 29

21 22 20 19 21

00180103

III. 9-147

= Activated PE
= Open board
A = Overall length of welding seam 8mm (tolerance = - 2 mm)
A
B = Permitted channel length = <
2

Smaller unwelded areas beside the


triangle tips as far as half of the
overall welded area are permitted,
see arrow in III. 9-147 and III. 9-148.

III. 9-148

INFO
  For these examinations only the tear-open methods described in these instructions are
permitted.

INFO
  In case of unwelded areas beside the triangle tips larger than half of the possible welded area
or in case of unwelded areas that reach as far as the package edge proceed acc. to section
9.3.14.1.

Follow protection mark Stand 15.11.2013 9-103


ISO 16016. cb 1 / cf 1
Tests

Faulty welding
Example 1:

30 29

21 22 20 19 21
B B

00180148

III. 9-149

= Activated PE
= Open board

The opposite aluminium areas B-B in the sample both are coloured under the polarisation
filter. In this case, there is a polyethylene layer on both sides, i.e. there has been no welding.
A channel B-B results in leakers at the bottom section.

9-104 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Example 2:

30
29

21 22 20 19 21

00180104

III. 9-150

= activated PE
= open board

In III. 9-150 and III. 9-151 an end-to-


end channel reaching as far as the
package edge is shown in the area
of ID 29. An end-to-end channel at
ID 29 or 30 leads to leaking bottoms.

III. 9-151

INFO
  For these examinations only the tear-open methods described in these instructions are
permitted.

Follow protection mark Stand 15.11.2013 9-105


ISO 16016. cb 1 / cf 1
Tests

Possible causes and measures:


- Bottom temperature and the activation pattern deviates from the requirements
according to chapter 9.3.5.3.
- Sleeve feed position onto the mandrels deviates from MI setting (have checked by
qualified staff).
- Lateral and longitudinal folder setting deviates from MI setting (have checked by
qualified staff).
- Mandrel end position to bottom press deviates from MI setting (have checked by
qualified staff).

Further necessary measures:


- Check bottom forming (inside and outside) for irregularities.
- Check bottom overlap for irregularities.
- Blue/red dye test according chapter 9.3.16.1.

Pos: 101 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

9-106 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 102 /gds-BA/Prüfungen/Packungsprüfung/1.1.1 Prüfung der Bodendichtheit 003 cb1 @ 25\mod_1357744532975_28.docx @ 185501 @ 3 @ 1

9.3.14 Check of bottom tightness

A faulty bottom sealing leads to bottom leakers.


The complete test for bottom leakers includes the following procedures:
 Check of bottom activation
- Activation pattern at sleeve (1)
- Activation at completely sealed bottom section of package (7)
- Heating-up through drying air (7)
 Visual control
- Outer appearance of carton package, bottom folding (3)
 Squeezing of the carton package
 Check of welded sections (8)

3
2

00180149

III. 9-152

Only if the above mentioned points have shown a correct result, the subsequent check for
bottom leakers shall be ensured by way of the " blue/red dye test".
Pos: 103 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 3 @ 1

Follow protection mark Stand 15.11.2013 9-107


ISO 16016. cb 1 / cf 1
Tests

Pos: 104 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung "Bodendichtheit" 004 cb1 @ 54\mod_1380525615760_28.docx @ 2610577 @ 44 @ 1

9.3.14.1 Elimination of fault

INFO
  Enter changes of settings into Production Checklist.

Procedure:
 Check activation at sleeve and at bottom: see sections 9.3.5.1 and 9.3.12.2.
 Check temperature values for bottom heating and drying zone: see section 9.3.5.4.
 Check sterile air pressure and air pressure for bottom heater: see section 9.3.5.4 or see
section 7.24.
 Check function of water cooling (temperature and flow volume) for mandrels and bottom
press.
 Check activation heads and die profile of mandrels and of bottom press for soiling and
damages.

In case of any channels beside the triangle tips the further measures are necessary:
 Check sleeve feed onto the mandrels.
 Have lateral and longitudinal folders checked by qualified staff.
 Have mandrel position to bottom press checked by qualified staff.
 Check bottom formation (inside and outside) for irregularities.
 Check bottom overlap.
 Squeezing test: see sections 9.3.9 and 9.3.13.1.
 Blue/red dye test: see section 9.3.16.1.

If the measures described above do not lead to a correct result, inform SIG Combibloc
Service, see chapter “General information/Addresses of customer service agencies”.

9-108 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Test samples
The test samples must be kept at least until the results of the bacteriological tests are
available. The samples will serve as a proof for the correct setting of the filling machine in
case of complaints; thus, keep the reserve samples as long as possible.
For this purpose, each test sample must show the following data:
 Production line or manufacturing no. of filling machine
 Track no.
 Temperature of bottom heating
 Welding pressure ultrasonics (top welding pressure)
 Date and time of test
 Shift, day of manufacturing or production and time of sleeve and number of shipping box
(see sample).

Example for an inscription on a shipping box


240 PC091500 FRUIT RED BERRY MIX 10030/9
715456500 SWIFT 0004 2588 31.12.12 23:59 20216558 3114
Date, time of Shipping box no.
production

Follow protection mark Stand 15.11.2013 9-109


ISO 16016. cb 1 / cf 1
Tests

It is recommended to jointly store the test samples of each track as follows:


S1. Activation pattern,
S2. Sample with bottom and top torn open,
S3. Welded bottom section of package (if required),
S4. Welded top section of package (if required)

30 29
S1.
21 22 20 19 21

S2.

S3.

S4.

00180150

III. 9-153
Pos: 105 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

9-110 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 106 /gds-BA/Prüfungen/Packungsprüfung/generell/1.1.1 H2O2-Nachweis 003 @ 52\mod_1380016777718_28.docx @ 2601363 @ 33 @ 1

9.3.15 H2O2 residual test

WARNING
Hydrogen peroxide (H2O2)
Risk of injuries through H2O2
Use H2O2 test to control, whether residues are inside the product. H2O2 causes caustic burns,
irritates eyes, skin and respiratory organs.
Since the check-up in a carton filled with product only gives results for milk products, water
and apple juice, run empty cartons for all other products () and fill afterwards with
demineralised and chlorine-free water.
 Run empty cartons only under exceptional circumstances under the supervision of the
machine operator to ensure, that the filling machine is not damaged through the empty
cartons.
 Strictly follow safety instructions given by manufacturer.
 Wear eye protection and protective clothing.
 Dilute any spilled H2O2 immediately with plenty of water and rinse into sewage system.

The H2O2 test strips (source of supply, see section 13.7) indicate whether the filled package
has left the filling machine free from H2O2.

Test intervals:
 at the beginning of production
 after all repair and maintenance works
Test procedure:
1. Take off one package per track, clean outside with water and dry off to remove H2O2
residue from the outside.
2. Open up or cut open packages taken out.
3. When carrying out the H2O2 residue test with empty packages, fill up packages with de-
mineralised water (or chlorine-free water) to nominal volume.

Follow protection mark Stand 15.11.2013 9-111


ISO 16016. cb 1 / cf 1
Tests

NOTE
Improper storage of H2O2 test strips
H2O2 test strips become unusable
H2O2 test strips may become unusable through improper storage. This results in unusable or
false measuring results.
 The containers for the H2O2 test strips must be stored in a closed condition.
 Immediately close container again after you took out a test strip.

4. Take out test strips from container (1).

H O -Test
² ²
SIG
Com
b ibloc
®
00005266

Ill. 9-154

5. Dip test strips into liquid for 5 seconds.


The control mark of the test strips shall not touch the outer walls of the package.
6. Check control mark for colour change.
There shall be no discolouring of the control mark; any later discolouring in the air is of no
importance.
7. Check de-mineralised water that is used to fill empty packages by using a second strip.
Such counter-check shall not show any discolouring of the control mark.
8. Check proper function of strip by getting control mark into contact with H2O2.
Result: blue colouring through H2O2 residue.
Pos: 107 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 3 @ 1

9-112 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 108 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung "H2O2-Nachweis" @ 27\mod_1371550997334_28.docx @ 206032 @ 44 @ 1

9.3.15.1 Elimination of fault

INFO
  Enter changes of settings into Production Checklist.

WARNING
Hydrogen peroxide (H2O2)
Risk of injuries through H2O2
H2O2 causes caustic burns, irritates eyes, skin and respiratory organs.
 Strictly follow safety instructions given by manufacturer.
 Wear eye protection and protective clothing.
 Dilute any spilled H2O2 immediately with plenty of water and rinse into sewage system.

1. Clean H2O2 vaporizers.


2. Check H2O2 spray quantity, adjust if required or have fault eliminated through qualified
SIG staff.
3. Check H2O2 transporting air pressure and adjust, if necessary.
4. Have temperature setting for H2O2 vaporisers and drying zone checked or set by qualified
staff.
Check the relevant parameters at the operating unit.
The temperatures may only vary within the alarm limits specified.
5. Check sterile air pressure, .
6. Have H2O2 dosing, H2O2 vaporisers and temperature sensors checked or repaired by
qualified staff.
7. Have heaters, air infeed and temperature sensors of drying zone checked or repaired by
qualified staff, if necessary.

If the measures described above do not lead to a correct result, inform SIG Combibloc
Service, see Section "General information/Addresses of customer service agencies".
Pos: 109 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

Follow protection mark Stand 15.11.2013 9-113


ISO 16016. cb 1 / cf 1
Tests

Pos: 110 /gds-BA/Prüfungen/Packungsprüfung/1.1.1 Prüfen der Packung auf Dichtheit durch Blau- /1.1.1 Prüfen der Packung auf Dichtheit durch Blau- / Rottest @ 53\mod_1380195109296_28.docx @ 2607967 @ 33 @ 1

9.3.16 Check of carton package for leakers with “blue/red dye test”

WARNING
Non-sterile conditions
Health risk through non-sterile conditions
If the weld is not completely sealed, this may result in faulty and unsterile cartons. Unsterile
cartons present a health risk for the consumer.
 A channel formation in the weld area can only be reliably detected through a visual
control, see section 9.3.13.2 unter "Faulty welding - bottom section" and in section
9.3.10.4 under "Analysis weld - top section".

WARNING
Solvent naphtha
Risk of injuries through white spirit
Blue/Red dye test liquid contains white spirit. White spirit is easily inflammable. White spirit
may irritate eyes, skin and respiratory organs.
 Wear eye protection and protective clothing.
 Strictly follow safety instructions of manufacturer and general safety instructions given in
Chapter "Safety".

NOTE
Wrong white spirit
Unusable or incorrect blue test results
When using white spirit not approved by SIG Combibloc, the results cannot be compared.
 In order to get comparable results when carrying out a blue/red dye test of combibloc
packaging material, only use the de-aromatised white spirit (such as Shellsol D60 or Exxol
D60 (LAWS)* approved by SIG Combibloc.

The final and conclusive test for package leakers is the "blue/red dye test".
After all other inspection tests have been successfully completed the “blue/red dye test" is
carried out. It rounds up the quality check-up and provides hints for fault points at filling
machine and packaging material.

Test liquid:
 Solvent naphtha (de-aromatized), with a boiling range of 180 - 220°C.

 Adding of ink 1 tip of knife on 1 litre of test liquid; solvent blue B01 (CAS No. 7354-14-2;
C.I.Solvent blue 35 – Anthrachinone ink), respectively oil red 5B02 (Sudanred) is used as
the ink for the test liquid .
 The using of ink must be conform with the local law.

9-114 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

INFO
  The blue/red dye test liquid can be used again, after separating the residual water.

Test intervals:
 at the beginning of production
 each four hours during production
 when changing product, print design and pallet*
 after all repair and maintenance works

* When changing the day of manufacturing or if the storage conditions of the new pallet
deviate from the standard conditions specified.

INFO
  Before filling in agent, make sure that the top flaps remain sealed. Blue/red dye test liquid
penetrations with top flaps not sealed to the package or after tearing off top flaps are
insignificant to the tightness of the package.
Pos: 111 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 3 @ 1

Follow protection mark Stand 15.11.2013 9-115


ISO 16016. cb 1 / cf 1
Tests

Pos: 112 /gds-BA/Prüfungen/Packungsprüfung/1.1.1.1 Durchführung der Tests "Blau-/Rottest" 002 cb1 @ 54\mod_1380526078333_28.docx @ 2610606 @ 44 @ 1

9.3.16.1 Procedure of tests

One package of each mandrel in succession


is tested for leakers using the blue/red dye
test liquid.
1. Cut open packages in the middle without
damaging bottom or top section.
2. Drain package halves, rinse them with
water and carefully remove all product
residue and grease.
3. Dry package halves by carefully
knocking them against packages or by
blowing them out with oil-free
compressed air.
4. Fill test liquid into both halves so bottom 00005267
is covered.
III. 9-155

INFO
  The above-mentioned steps point 1 to point 4 are to be carried out uninterrupted and in
sequence.
The blue/red dye test liquid must be filled into both halves immediately after point 1-3.

5. Allow test liquid to react for 30 minutes.


6. Test packages in all sections for
penetrations.

INFO
  Within the 30 min residence time no mechanical load is permitted!

Pos: 113 /gds-BA/Prüfungen/Packungsprüfung/1.1.1.1 Auswertung "Blau-/1.1.1.1 Auswertung "Blau-/Rottest" @ 53\mod_1380195763208_28.docx @ 2608205 @ 444 @ 1

9.3.16.2 Analysis

NOTE
Incorrect blue test analysis
Faulty top sealing through wrong performance of blue test
The blue/red dye test must be carried out correctly, in order to early detect a poor top sealing
and to prevent faulty productions.
 After 30 min. of reaction time, no penetrations shall show.
 If penetrations occur during the reaction time of the blue test, the test must be repeated. If
penetrations are detected again after a repeated blue test procedure, the fault must be
immediately eliminated. Only then production may be continued.
 If during an 8-hour production more than altogether three faulty cartons are detected with
a correct blue/red dye test procedure, immediately eliminate fault. Only then production
may be continued.
Pos: 114 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

9-116 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 115 /gds-BA/Prüfungen/Packungsprüfung/1.1.1.1 Durchfärbung "Blau-/Rottest" @ 24\mod_1345455418485_28.docx @ 182855 @ 4 @ 1

9.3.16.3 Penetrations

If the testing agent will penetrate at the possible penetration points according to III. 9-156 and
III. 9-157 it becomes visible at the points marked with arrows.

Points of penetration: ○
Examples:
 Possible paths of penetration of
blue/red dye test agent through
damages in the bottom section. 20 22
28

26
29 30
27
25
24
43 44

19 21

00005268

III. 9-156

 Possible paths of penetration of


blue/red dye test agent through
channels in the bottom section.

34 33 32

00005269

III. 9-157
Pos: 116 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

Follow protection mark Stand 15.11.2013 9-117


ISO 16016. cb 1 / cf 1
Tests

Pos: 117 /gds-BA/Prüfungen/Packungsprüfung/Fehlerbehebung/1.1.1.1 Fehlerbehebung "Blau-/1.1.1.1 Fehlerbehebung "Blau-/Rottest" cb7+1 @ 53\mod_1380195862033_28.docx @ 2608264 @ 44 @ 1

9.3.16.4 Elimination of fault

WARNING
Blue/Red dye test liquid
Risk of injuries through blue/red dye test liquid
The blue/red dye test liquid contains chemical substances, which may be a hazard to the
environment.
 Strictly follow safety data sheet and instructions for disposal of respective countries.
 Blue/Red dye test liquid must be disposed of as hazardous waste.
 The disposal of drained cartons used for "Blue/Red dye test" is not allowed on class 3
household waste dumps unless the filling company has received a confirmation from an
independent, recognised institute (such as the Chemical Test Institute) that the country-
specific regulations have been followed.
 In order to receive this proof of disposal, the test result must be attached to the application
for disposal on a deposit.
 In case this proof for disposal is not granted, cartons must be disposed of as hazardous
waste.

INFO
  Enter changes of settings into Production Checklist.

1. Check bottom activation and bottom weld, see sections 9.3.5.3 and 9.3.13.2.
2. Check top welding, see section 9.3.10.4.
Pos: 118 /gds-BA/____ Seitenumbruch ____ @ 15\mod_1315315453688_0.docx @ 90840 @ 4 @ 1

9-118 Stand 15.11.2013 Follow protection mark


cb 1 / cf 1 ISO 16016.
Tests

Pos: 119 /gds-BA/Prüfungen/Reklamationsabwicklung/1.1 Reklamationsabwicklung 002 @ 24\mod_1345456368441_28.docx @ 182901 @ 2 @ 1

9.4 Handling of claims

In case of deviation, the related forms needs to be filled out containing the following contents.

Important contents/components of a claim:

Information required:
 Customer designation
 Type of production line
 Fault/Problem description stating the ID points
 Inscription on shipping box (material identification, format, manufacturer, date of
manufacturing etc.), see section 9.2.4.
 Track code (can be seen on bottom section), see III. 9-5.
 Quantity (product claimed, quantity produced, quantity still available from faulty
production)
 Measures taken and impacts.

Test samples:
 At least 20 faulty samples
 In case the fault has been detected at the packaging material or at the fitment only after
the filling, also keep some faulty filled packages.
 Test samples acc. to III. 9-153 from the claimed production day, together with the required
data such as:
- Filling machine no.
- Track no.
- Temperature of bottom heating
- Air pressure of bottom heating
- Welding pressure ultrasonics (top welding pressure)
- Date and time of test
- Date/Time of production or manufacturing of sleeve

Pos: 120 /gds-BA/----- Kapitelende ----- @ 15\mod_1315909119380_0.docx @ 91880 @ 2 @ 1

Follow protection mark Stand 15.11.2013 9-119


ISO 16016. cb 1 / cf 1

Potrebbero piacerti anche