Material Work Quantity Rate

Cement 4000cf 1.25cf/bag →3200 bags


Steel 100ton
Aggregate 10000cf 1100cf/dumper→9.09dumpers
Sand 5000cf 1100cf/dumper→4.54 dumpers
Reday Mix Concrete 20000cf
Bricks 25000bricks
Paint 15 gallon
Electric wires 30 coils
EquipmenRequired
Mobile and 2
Theodolite 1
Autolevel 2
Total Stat 1
Leveller 4
Generator a 1,7
Excavator 2
Tower cran 1
Concrete M 3
Manpower Work Quantity Rate Hours Persons req
Project Manager 52000sq.f 8hr/day 4380 1
Constructon Manager 52000sq.f 8hr/day 4380 1
Site Engineer 52000sq.f 8hr/day 4380 3
Foreman 52000sq.f 8hr/day 4380 1
Surveyor 52000sq.f 8hr/day 4380 5
Mason 5000sq.f 107sq.f/8hr 46 4
Labor 7000sq.f 8hr/day 4380 12
Plumber 8hr/day 60 7
Electrician 8hr/day 55 4
Watering man 4hr/day 200 2
Painter 5000sq.f 196sq.f/8hr 25.5 3 ✔
Manpower 1st day 2nd day 3rd day 4th day 5th day 6th day 7th day
Project Manager 1 1 1 1 1 1 1
Constructon Manager 1 1 1 1 1 1 1
Site Engineer 1 1 1 1 1 1 1
Foreman 1 1 1 1 1 1 1
Surveyor 2 2 3 2 5 5 5
Mason 4 4 4 4 4 4 4
Labor 5 5 5 5 12 12 12
Plumber 3 3 3 3 3 3 3
Electrician 3 3 3 3 3 3 3
Watering man 1 1 1 1 1 2 2
Painter 3 3 3 3 3 3 3