Cantidad

Pedido Semana 1 Semana 2


Descripción Material
15-Feb 18-Feb
Ladrillo KK 10,360.00 6,320.00
Tabique de ladrillo Cemento 56.46 34.44
Arena gruesa 8.03 4.90
Arena fina
Tarrajeo de interior
Cemento
Arena fina
Tarrajeo de exterior
Cemento
Ladrillo de techo Ladrillo 30x30x25cm 445.20

Ladrillo KK 16,680.00 und


Cemento 603.51 bol
Arena gruesa 12.93 m3
Arena fina 61.51 m3
Ladrillo 30x30x25cm 1,780.80 und
Semana 3 Semana 4 Semana 5 Semana 6
TOTAL
25-Feb 4-Mar 11-Mar 18-Mar
16,680.00 und
90.91 bol
12.93 m3
33.70 11.62 45.31 m3
280.80 96.80 377.60 bol
8.10 8.10 16.20 m3
67.50 67.50 135.00 bol
445.20 445.20 445.20 1,780.80 und
Semana 1 Semana 2 Semana 3 Semana 4 Semana 5 Semana 6 Semana 7
Piso tarrajeo interior tarrajeo exterior Total (m2)
18-Feb 25-Feb 4-Mar 11-Mar 18-Mar 25-Mar 1-Apr
Piso 01 242.00 242.00 242.00
Piso 02 242.00 242.00 242.00
Piso 03 702.00 702.00 702
Piso 04 702.00 702.00 702 0
1888 1888 0 1404 484 0 0 0 0
0% 74% 26% 0% 0% 0% 0%
cat x m2
Cemento bol 0.200 0 281 97 0 0 0 0 378 Bol.
Arena Fina m3 0.024 0 34 12 0 0 0 0 45 m3

Semana 1 Semana 2 Semana 3 Semana 4 Semana 5 Semana 6 Semana 7


Piso tarrajeo exterior Total (m2)
18-Feb 25-Feb 4-Mar 11-Mar 18-Mar 25-Mar 1-Apr
Piso 01 0.00
Piso 02 0.00
Piso 03 0.00
Piso 04 675.00 675.00 338 338
675 0 338 338 0 0 0 0
0% 18% 18% 0% 0% 0% 0%
cat x m2
Cemento bol 0.200 0 68 68 0 0 0 0 135 Bol.
Arena Fina m3 0.024 0 8 8 0 0 0 0 16 m3
Cantidad
Ladrillo Cabeza Pedido Semana 1 Semana 2 Semana 3 Semana 4 Semana 5 Semana 6 Semana 7 Semana 8
Piso Total (m2) Saldo
24x13x9 18-Feb 25-Feb 4-Mar 11-Mar 18-Mar 25-Mar 1-Apr 8-Apr
Piso 01 0 0
Piso 02 0 0
Piso 03 0 0
Piso 04 0 0
0.00 0 0 0 0 0 0 0 0 0
788 % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
cant x m2
Cemento 0.408 Bol 0 0 0 0 0 0 0 0 0
Arena Gruesa 0.058 m3 0 0 0 0 0 0 0 0 0
ladrillo KK 65 und 0 0 0 0 0 0 0 0 0

ladrillo KK-18
Cantidad
Ladrillo Soga Pedido Semana 1 Semana 2 Semana 3 Semana 4 Semana 5 Semana 6 Semana 7 Semana 8
Piso Total (m2) Saldo
13x24x9 18-Feb 25-Feb 4-Mar 11-Mar 18-Mar 25-Mar 1-Apr 8-Apr
Piso 01 79.00 79.00 79 79.00
Piso 02 79.00 79.00 79 79.00
Piso 03 96.00 96.00 96 96.00
Piso 04 163.00 163.00 163 163.00
Piso 05 0.00 0
417 417 259 158 0 0 0 0 0 0
% 62% 38% 0% 0% 0% 0% 0% 0%
cant x m2
Cemento 0.218 56 34 0 0 0 0 0 0 90.91
Arena Gruesa 0.031 8 5 0 0 0 0 0 0 12.93
ladrillos KK 40 10360 6320 0 0 0 0 0 0 16,680
1726.7 1580.0 0.0 0.0 0.0 0.0
6 5
RESUMEN-SEMANAL
Cemento 56 34 0 0 0 0 0 0 91
Arena Gruesa 8 5 0 0 0 0 0 0 13
ladrillos KK 10360 6320 0 0 0 0 0 0 16,680

MATERIAL X DIA
Cemento 9 6 0 0 0 0 0 0
Arena Gruesa 1 1 0 0 0 0 0 0
ladrillos KK 1727 1053 0 0 0 0 0 0

6 4

CRONOGRAMA DE DESPACHO DE LADRILLO KK - 18


ladrillo KK-18 Cantidad
Pedido Semana 1 Semana 2 Semana 3 Semana 4 Semana 5 Semana 6 Semana 7 Semana 8
Piso Total Saldo
13x24x9 15-Feb 18-Feb 25-Feb 4-Mar 11-Mar 18-Mar 25-Mar 1-Apr
Piso 01 3,160.00 3,160.00 3,160.00 3,160.00
Piso 02 3,160.00 3,160.00 3,160.00 3,160.00
Piso 03 3,840.00 3,840.00 3,840.00 3,840.00
Piso 04 6,520.00 6,520.00 6,520.00 6,520.00

16,680.00 16,680.00 10,360.00 6,320.00 0.00 0.00 0.00 0.00 0.00 0.00
CRONOGRAMA DE DESPACHO DE LADRILLO TECHO h= 0.25 m
8.33 1.05

Metrado (m2) Ladrillo techo (und) Semana 1


Fecha Max. De
Piso Total (und)
0.30x0.30x0.25 inicio Ejecucion 18-Feb
SSHH

Piso 01 53 424 445 445.20


Piso 02 53 424 445
Piso 03 53 424 445
Piso 04 53 424 445
Total 1,696.00 1,780.80 445.20
Semana 2 Semana 3 Semana 4 Semana 5

25-Feb 4-Mar 11-Mar 18-Mar

445.20
445.20
445.20
445.20 445.20 445.20 0.00