ladrillo KK-18
Cantidad
Ladrillo Soga Pedido Semana 1 Semana 2 Semana 3 Semana 4 Semana 5 Semana 6 Semana 7 Semana 8
Piso Total (m2) Saldo
13x24x9 18-Feb 25-Feb 4-Mar 11-Mar 18-Mar 25-Mar 1-Apr 8-Apr
Piso 01 79.00 79.00 79 79.00
Piso 02 79.00 79.00 79 79.00
Piso 03 96.00 96.00 96 96.00
Piso 04 163.00 163.00 163 163.00
Piso 05 0.00 0
417 417 259 158 0 0 0 0 0 0
% 62% 38% 0% 0% 0% 0% 0% 0%
cant x m2
Cemento 0.218 56 34 0 0 0 0 0 0 90.91
Arena Gruesa 0.031 8 5 0 0 0 0 0 0 12.93
ladrillos KK 40 10360 6320 0 0 0 0 0 0 16,680
1726.7 1580.0 0.0 0.0 0.0 0.0
6 5
RESUMEN-SEMANAL
Cemento 56 34 0 0 0 0 0 0 91
Arena Gruesa 8 5 0 0 0 0 0 0 13
ladrillos KK 10360 6320 0 0 0 0 0 0 16,680
MATERIAL X DIA
Cemento 9 6 0 0 0 0 0 0
Arena Gruesa 1 1 0 0 0 0 0 0
ladrillos KK 1727 1053 0 0 0 0 0 0
6 4
16,680.00 16,680.00 10,360.00 6,320.00 0.00 0.00 0.00 0.00 0.00 0.00
CRONOGRAMA DE DESPACHO DE LADRILLO TECHO h= 0.25 m
8.33 1.05
445.20
445.20
445.20
445.20 445.20 445.20 0.00