GOVERNMENT OF ANDHRA PRADESH

PANCHAYATI RAJ ENGINEERING DEPARTMENT


CHITTOOR DISTRICT

DETAILED CUM ABSTRACT ESTIMATE

Providing CC road in Reddivaripalle H/o


N.W.:
Vepurikota

Grant: SDF 2013-14 (Plain)

Est. Rs. 200000

Habitation Reddivaripalle

G.P.: Vepurikota

Mandal: Mulakalacheruvu

Sub Divn.: B. Kothakota.

Division.: MADANAPALLE
SPECIFICATION REPORT

Specification Report to acccompany the Detailed Estimate for the work

Providing CC road in Reddivaripalle H/o Vepurikota

Grant: SDF 2013-14 (Plain) Est.Cost Rs. 200000

The streets are slushy and water logged during raining season causing ill health to the Public

To provide safe and hygeinic conditions, it is necessary to provide the CC Pavement in the Village.

The work is administratively sanctioned vide proceedings Roc.No. 19/SPWD/(CMA)/DSO-1/2012

dt. 29-06-2013 of the District Collector, Chittoor.

The following provisions are made in the Detailed Estimate;

1 Earthwork excavation in OG Soils for undulated areas levelling

2 Filling of Sand for levelling the surface area.

3 M 20 Design mix using 12 and 20mmHBG MC Metal for CC Pavement over 125 microns Polythene sheet

4 Provision for laying of Mastic Pads of 12.70 mm thick for expansion joints

5 Provision for QC at 0.50 % and Vat at 5% and provision for unforeseen items.

6 Provision for unforeseen items if any.

The Detailed Estimate is prepared as per Standard Schedule of Rates

2013-14 and the work will be carried out as per Standard Specifications.

Asst. Exe. Engineer,


PRI, B.Kothakota.
DETAILED CUM ABSTRACT ESTIMATE
N.W. Providing CC road in Reddivaripalle H/o Vepurikota

Grant: SDF 2013-14 (Plain) Est. Cost Rs. 200000


Dimensions
S.No Description of work No. Qty. Rate Amount
Length Breadth Depth

Excavation for levelling of roadway in OG Soil using


1
manual means with initial lift and lead
1 16.70 2.10 0.10 3.51 131.20 461
Filling in undulations with sand including cost and
2 conveyance of sand, watering, ramming and labour
charges etc. 1 31.00 2.10 0.05 3.26 #N/A #N/A
Laying of Plain cement concrete pavement as per
design mix M20 using 12mm and 20mm HBG
Machine Crushed Metal, with side formwork, over
3
125 microns thick Polythene sheet including cost
and conveyance of all materials, labour charges
and curing etc., complete. 1 78.75 3.00 0.170 40.16 #N/A #N/A

Supply, delivery and fixing of Mastic Pads of 12.70


4 mm thick including cost and conveyance and labour
charges etc., complete for expansion joints.
8 3.00 - 0.170 4.08 498.00 2032

Sub Total Rs. #N/A

5 Provision for Q C charges at 0.50% #N/A

7 Provisition for VAT @ 5.00 % #N/A

6 Provision for Unforeseen items of work and sanitation #N/A

T O T A L Rs. : 200000

The work is administratively sanctioned vide proceedings Roc.No.


19/SPWD/(CMA)/DSO-1/2012 dt. 29-06-2013 of the District Collector,
Chittoor.
Asst. Exe. Engineer,
PRI, B.Kothakota.

Technically sanctioned for Rs.________ lakhs (Rupees ________


____________________________________ only)

vide SDR No. _____/2013-14 dt._________________

Dy. Executive Engineer,


PRI Sub division,
B. Kothakota.
LEAD STATEMENT

N.W. Providing CC road in Reddivaripalle H/o Vepurikota

Grant: SDF 2013-14 (Plain) Est.Cost Rs. 200000

Lead
source of Lead in charges Initial Add S Loading
SNo Descri ption of Material Unit Total
supply Kms excluding cost Fee Charges
14%

1 Sand for Mortar Local 1 cum 13.00 #N/A 385.00 40.00 13.33 #N/A

2 Sand for Filling Local 1 cum 6.00 #N/A 285.00 40.00 13.33 #N/A

20mm to 12 mm
Setti
3 Machine crushed HBG 1 cum 30.00 #N/A 1150.00 50.00 0.00 #N/A
Palle
Metal

4 Cement Local 1 MT. 0.00 0.00 5500 0.00 0.00 5500.00

Certified that the leads adopted are correct and nearest to the best of my knowledge and belief

Asst. Exe. Engineer,


PRI, B.Kothakota.
DATA
N.W. Providing CC road in Reddivaripalle H/o Vepurikota
Grant: SDF 2013-14 (Plain) Est.Rs. 200000
S. Description Unit Qty Rate Amount
No
1 Excavation for levelling of roadway in OG Soil using manual means with
Taking output = 120 cum
initial lift and lead
a) Mazdoor (Unskilled) day 46.80 280.00 13104.00
13104.00 x1/120 109.20
Add Seinerage charges 22.00
Rate per cum = (a)/120 131.20
2 Filling in undulations with sand including cost and conveyance of sand,
Unit = cum
watering, ramming and labour charges etc.,
a) Labour Mazdoor (Unskilled) day 0.31 280.00 86.80
b) Material sand cum 1.00 #N/A #N/A

Rate per cum = a+b #N/A


3
Laying of Plain cement concrete pavement as per design mix M20 using
12mm and 20mm HBG Machine Crushed Metal, with side formwork, over
125 microns thick Polythene sheet including cost and conveyance of all
materials, labour charges and curing etc., complete. for 75 Cum. Qty.

a) Mason (1st class) day 5 350.00 1750.00


Mason (2nd class) day 5 320.00 1600.00
Mazdoor (Unskilled) day 150 280.00 42000.00
Mazdoor (Skilled) day 6 320.00 1920.00
Surveyor day 2 500.00 1000.00
Mazdoor (Semi-Skilled) day 6 280.00 1680.00
49950.00
Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) with weigh batcher and hour 36 417.40 15026.40
b) suitable capacity calibrated water tank
Vibrator hour 9 152.50 1372.50
Pan Vibrator hour 9 42.00 378.00
Water tanker 8 kl capacity hour 5 372.00 1860.00
18636.90
c) 20 mm to 12 mm HBG MC aggregate cum 67.50 #N/A #N/A
Sand as per IS:383 and conforming to Clause 1500.2.4.2 @ 0.45
cum/cum of concrete cum 33.75 #N/A #N/A
Cement @ 330 kg/cum of concrete MT 24.75 5500.00 136125.00
Polythene sheet 125 micron sqm 412.50 15.00 6187.50
Water for curing (M-189) kl 18.00 100.00 1800.00
#N/A

d) Centering Charges at 3% on a+b+c #N/A x 0.03 = #N/A


Cost for 75 cum = a+b+c+d #N/A

Rate per cum = (a+b+c+d)/75 #N/A x 1/75 #N/A


4 Supply, delivery and fixing of Mastic Pads of 12.70 mm thick including
cost and conveyance and labour charges etc., complete for expansion sqm 1.000 498.00 498.00
joints.
Asst. Exe. Engineer,
PRI, B.Kothakota.
WORKING ESTIMATE
N.W. Providing CC road in Reddivaripalle H/o Vepurikota MB No.

Grant: SDF 2013-14 (Plain) Est.Cost Rs. 200000


Dimensions
S.No Description of work No. Qty. Rate Amount
Length Breadth Depth

Excavation for levelling of roadway in OG Soil using


1
manual means with initial lift and lead
QVP No. 12. 4.73 131.20 621
Filling in undulations with sand including cost and
2 conveyance of sand, watering, ramming and labour
charges etc.,
QVP No. 12. 4.81 #N/A #N/A
Laying of Plain cement concrete pavement as per
design mix M20 using 10mm and 20mm HBG
Machine Crushed Metal, with side formwork, over
3
125 microns thick Polythene sheet including cost
and conveyance of all materials, labour charges
and curing etc., complete. QVP No. 13. 31.62 #N/A #N/A

Supply, delivery and fixing of Mastic Pads of 12.70


4 mm thick including cost and conveyance and labour
charges etc., complete for expansion joints.
QVP No. 13. 4.08 498.00 2032

Sub Total Rs. #N/A

5 Provision for Q C charges at 0.50% #N/A

7 Provisition for VAT @ 5.00 % #N/A

6 Provision for Unforeseen items of work and sanitation 0

T O T A L Rs. : #N/A

Asst. Exe. Engineer,


PRI, B.Kothakota.
COMPARATIVE STATEMENT
N.W.: Providing CC road in Reddivaripalle H/o Vepurikota
Grant: SDF 2013-14 (Plain) MB No. Est.Cost Rs. 200000
As per Original Estimate As per Working Estimate
S. No Description of work Excess Less
Qty. Rate Per Amount Qty. Rate Per Amount
1 Excavation for levelling of roadway in OG Soil using
3.51 131.20 461 4.73 131.20 621 160 0
manual means with initial lift and lead
2 Filling in undulations with sand including cost and
conveyance of sand, watering, ramming and labour 3.26 #N/A #N/A 4.81 #N/A #N/A #N/A #N/A
charges etc.,
3 Laying of Plain cement concrete pavement as per
design mix M20 using 10mm and 20mm HBG
Machine Crushed Metal, with side formwork, over
40.16 #N/A #N/A 31.62 #N/A #N/A #N/A #N/A
125 microns thick Polythene sheet including cost and
conveyance of all materials, labour charges and
curing etc., complete.
4 Supply, delivery and fixing of Mastic Pads of 12.70
mm thick including cost and conveyance and labour 4.08 498.00 2032 4.08 498.00 2032 0 0
charges etc., complete for expansion joints.
5 Provision for Q C charges at 0.50% #N/A #N/A #N/A #N/A
6 Provisition for VAT @ 5.00 % #N/A #N/A #N/A #N/A
7 Provision for Unforeseen items of work #N/A 0 #N/A #N/A

T O T A L Rs. : #N/A #N/A #N/A #N/A

As per Original Estimate #N/A As per Excess: #N/A


As per Working Estimate #N/A As per Less: #N/A
Difference: #N/A Difference: #N/A

Asst. Exe. Engineer,


PRI, B.Kothakota.
COMPLETION REPORT
N.W.: Providing CC road in Reddivaripalle H/o Vepurikota
Grant: SDF 2013-14 (Plain) MB No. Est.Cost Rs. 200000
As per Working Estimate As per Execution
S. No Description of work Excess Less Remarks
Qty. Rate Per Amount Qty. Rate Per Amount
1 Excavation for levelling of roadway in OG Soil using
4.73 131.20 621.00 4.73 131.20 620.58 0.00 0.42
manual means with initial lift and lead
2 Filling in undulations with sand including cost and
conveyance of sand, watering, ramming and labour 4.81 #N/A #N/A 4.81 #N/A #N/A #N/A #N/A
charges etc.,
3 Laying of Plain cement concrete pavement as per
design mix M20 using 10mm and 20mm HBG
Machine Crushed Metal, with side formwork, over
31.62 #N/A #N/A 31.62 #N/A #N/A #N/A #N/A
125 microns thick Polythene sheet including cost and
conveyance of all materials, labour charges and
curing etc., complete.
4 Supply, delivery and fixing of Mastic Pads of 12.70
mm thick including cost and conveyance and labour 4.08 498.00 2032.00 4.08 498.00 2031.84 0.00 0.16
charges etc., complete for expansion joints.
5 Provision for Q C charges at 0.50% #N/A #N/A #N/A #N/A
6 Provisition for VAT @ 5.00 % #N/A #N/A #N/A #N/A
7 Provision for Unforeseen items of work 0.00 0.00 0.00 0.00

T O T A L Rs. : #N/A #N/A #N/A #N/A

As per Working Estimate #N/A As per Excess: #N/A


As per Execution #N/A As per Less: #N/A
Difference: #N/A Difference: #N/A

Asst. Exe. Engineer,


PRI, B.Kothakota.
ll
l Bi

&
Fi
na CONTRACT CERTIFICATE
t
1s
Name Of Work : Providing CC road in Reddivaripalle H/o Vepurikota

Name Of Contractor: Chairman, Habitation Works Committee, Reddivaripalle


Vocher: ......................................................

Last Certificate If Any MB No.


Month August 2013

Number In And Month Of The Last Schedule If Any


Habitation Reddivaripalle

Grama Panchayat Vepurikota


Est. Cost Rs. 200000
Voucher No. .............................

Supervisor No….. Asst. Exe. Engineer,PRI, B.Kothakota.


Authority: SDF 2013-14 (Plain)
Covering List No….. .......................
Scheduleno…….. .......................
Rate in Total amount
Sno. Total Qty. Description of Work
Rs. Up to date

Excavation for levelling of roadway in OG Soil using manual


1 4.73 means with initial lift and lead 131.20 620.58

Filling in undulations with sand including cost and conveyance


2 4.81 of sand, watering, ramming and labour charges etc., #N/A #N/A

Laying of Plain cement concrete pavement as per design mix


M20 using 10mm and 20mm HBG Machine Crushed Metal,
with side formwork, over 125 microns thick Polythene sheet
including cost and conveyance of all materials, labour charges
3 31.62 and curing etc., complete. #N/A #N/A

Supply, delivery and fixing of Mastic Pads of 12.70 mm thick


including cost and conveyance and labour charges etc.,
4 4.08 complete for expansion joints. 498.00 2031.84
Grand Total Rs. #N/A

Signature of contractor…………………………………………………………..Date…………..

Certified that the proceeding claim is correct, that the necessary Check Measurement Certificate
measurements have been made by me on……………..........and Work and
Certified that the -------------------------- duly checked.
and recorded on page…..of
MB No. Materials were

and that the work has been satisfactorily performed.

Certified also that the Meaterials billed for have been received Check Meaured by me on (Dates)
and of brought to account

Asst. Exe. Engineer, Dy. Executive Engineer,


PRI, B.Kothakota. PRI Sub division,
B. Kothakota.
Memorandum of payment made
Total value of work done
Amount of previous payment from last certificate No____ of ____ forwarded
Rs Ps Rs Ps

with account of ________________________________________________

Fines and other deductions up to date

Payment now made By cash Rs………………

"Cheque No…….of ……….

"Value of stock supplied


Blance due

Allotment for the year


Expenditure including this bill
Balance available
PAY RUPEES RECEIVED RUPEES
Only as family payment in settlement of all demands.

Witness

Hd.Clerk or Preslbent or
Ad.Account Engineer
Date Payee
INVERNACULAR
AUDIT ENFACEMENT
Admited Rs…………………………………………..
Total Rs………………………………………………
Date Auditor
DISTRICT ENGINEER'S REMARKS
NOTES
1.This form is intended for use in the case of unning account I.e. for works in progress of
supplie incorse of delivery, when the liability is discharged in full single payment Form No.33-A should be used
2.Payment will be made only up nonetenth of the total value of the work done.The balance being
retained as security both for the due performance of the contracts or to cover possible over payment
which may be deducted on check measurment in the case of work whose estimate cost dose not
exceed Rs 50/- payment may be made in full on the measuring officers certificate subject to
subequent check measurement by the proper check measuring authority.
3.In calucating theamount of each item due to the contractor in this bill.Sums of six pices or less shall be
omitted and sums exceeding six pices up to one anua shall be recorded as one anua.
4.Payment made in case of sum excluding Rs. 100- should be atte by two witness and for smaller sums
by one witness, payment made by cheque to recognized firms or institutions need not be so witnessed.
5.When the payee signs in the vernacular the amount acknowledged should also be noted in same
veraculler as well as in English.
6.In case other then well known firms all parties must sign. If there will be more then contractor the payee
must produce a power of attorney form he firm.
7.No contract certificate bearing on remarks should be accepted. If any corrections are necessary
the figures should be neatly scored out and initrailes by the officer concerned incase of correction made in the Engineer's
Office Head Accountant may be authorised to chyooe due to clerical elrose are but the Engineer's should affix his
intilals to all corrections in the ratmummn as well as those in the totals of the bill and the pass order. This rule applied
(MUTATIS MUTANDIS) to payment from miscellous grants.
8.In case in which the materials billed or taken over charged by an officer other than the officer signing
the certificate from of the bill the names of the former should be noted in the remarks colum or the bill.Necessary
ameandment being made at the same time in the excluding post on of the certificate relating to material.
lead
Bricks per
in Sand Metal
KM
1000 Nos.
Note: Rates are exclusive of 14% contractor's profit
1 26.32 25.35 42.19
2 36.84 35.44 59.04
3 49.12 49.12 78.77
4 59.65 59.65 95.61
5 70.18 70.18 112.54
6 80.70 80.70 129.39
7 91.23 91.23 146.23
8 101.75 101.75 163.07
9 112.28 112.28 179.91
10 122.81 122.81 196.75
11 133.33 133.33 213.60
12 143.86 143.86 230.44
13 154.39 154.39 247.28
14 164.91 164.91 264.12
15 175.44 175.44 280.96
16 185.96 185.96 297.81
17 196.49 196.49 314.65
18 207.02 207.02 331.49
19 217.54 217.54 348.33
20 228.07 228.07 365.18
21 238.60 238.60 382.02
22 249.12 249.12 398.86
23 259.65 259.65 415.70
24 270.18 270.18 432.54
25 280.70 280.70 449.39
26 291.23 291.23 466.23
27 301.75 301.75 483.07
28 312.28 312.28 499.91
29 322.81 322.81 516.75
30 333.33 333.33 533.60
31 342.11 342.11 547.63
32 350.88 350.88 561.67
33 359.65 359.65 575.70
34 368.42 368.42 589.74
35 377.19 377.19 603.77
36 385.96 385.96 617.81
37 394.74 394.74 631.84
38 403.51 403.51 645.88
39 412.28 412.28 659.91
40 421.05 421.05 673.95
41 429.82 429.82 687.98
42 438.60 438.60 702.02
43 447.37 447.37 716.05
44 456.14 456.14 730.09
45 464.91 464.91 744.12
46 473.68 473.68 758.16
47 482.46 482.46 772.19
48 491.23 491.23 786.23
49 500.00 500.00 800.26
50 508.77 508.77 814.30
51 517.54 517.54 828.33
52 526.32 526.32 842.37
53 535.09 535.09 856.40
54 543.86 543.86 870.44
55 552.63 552.63 884.47
56 561.40 561.40 898.51
57 570.18 570.18 912.54
58 578.95 578.95 926.58
59 587.72 587.72 940.61
60 596.49 596.49 954.65
61 605.26 605.26 968.68
62 614.04 614.04 982.72
63 622.81 622.81 996.75
64 631.58 631.58 1010.79
65 640.35 640.35 1024.82
66 649.12 649.12 1038.86
67 657.89 657.89 1052.89
68 666.67 666.67 1066.93
69 675.44 675.44 1080.96
70 684.21 684.21 1095.00
71 692.98 692.98 1109.04
72 701.75 701.75 1123.07
73 710.53 710.53 1137.11
74 719.30 719.30 1151.14
75 728.07 728.07 1165.18
76 736.84 736.84 1179.21
77 745.61 745.61 1193.25
78 754.39 754.39 1207.28
79 763.16 763.16 1221.32
80 771.93 771.93 1235.35
81 780.70 780.70 1249.39
82 789.47 789.47 1263.42
83 798.25 798.25 1277.46
84 807.02 807.02 1291.49
85 815.79 815.79 1305.53
86 824.56 824.56 1319.56
87 833.33 833.33 1333.60
88 842.11 842.11 1347.63
89 850.88 850.88 1361.67
90 859.65 859.65 1375.70
91 868.42 868.42 1389.74
92 877.19 877.19 1403.77
93 885.96 885.96 1417.81
94 894.74 894.74 1431.84
95 903.51 903.51 1445.88
96 912.28 912.28 1459.91
97 921.05 921.05 1473.95
98 929.82 929.82 1487.98
99 938.60 938.60 1502.02
100 947.37 947.37 1516.05
101 956.14 956.14 1530.09
102 964.91 964.91 1544.12
103 973.68 973.68 1558.16
104 982.46 982.46 1572.19
105 991.23 991.23 1586.23
106 1000.00 1000.00 1600.26
107 1008.77 1008.77 1614.30
108 1017.54 1017.54 1628.33
109 1026.32 1026.32 1642.37
110 1035.09 1035.09 1656.40
111 1043.86 1043.86 1670.44
112 1052.63 1052.63 1684.47
113 1061.40 1061.40 1698.51
114 1070.18 1070.18 1712.54
115 1078.95 1078.95 1726.58
116 1087.72 1087.72 1740.61
117 1096.49 1096.49 1754.65
118 1105.26 1105.26 1768.68
119 1114.04 1114.04 1782.72
120 1122.81 1122.81 1796.75
121 1131.58 1131.58 1810.79
122 1140.35 1140.35 1824.82
123 1149.12 1149.12 1838.86
124 1157.89 1157.89 1852.89
125 1166.67 1166.67 1866.93
126 1175.44 1175.44 1880.96
127 1184.21 1184.21 1895.00
128 1192.98 1192.98 1909.04
129 1201.75 1201.75 1923.07
130 1210.53 1210.53 1937.11