Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Project Management
1. Initiating
2. Planning
3. Executing
4. Monitoring and Controlling
5. Closing
Planning
create Project Management Plan [why the project? what to deliver? who
does what? when be accepted? how to execute?], subsidiary documents
(schedule baseline, cost baseline, performance management baseline,
scope baseline (scope statement, WBS, WBS dictionary) and subsidiary
management plans (scope, schedule, budget, quality, human resources [roles
& responsibility, organization chart and staffing management plan include the
staff need, rewards, safety and training need] , stakeholder, requirements,
process improvement, communication, change, risk and procurement) – all are
not finalized until a thorough risk management has been performed, need to
be approved before work begins
all plan and documents can be formal or informal, generalized or detailed,
depending on needs (tailoring)
Project Management Plan may be continually updated during the project
with rolling wave planning / progressive elaboration
obtain approval of the plan from designated stakeholders, changes to the
project management plan and subsidiary documents/plans need formal
procedures described in the change control system
hold the kick-off meeting
planning process group is MOST important for project management, with
around 1/2 of all the 49 process in this group
may need re-planning when significant changes to the baseline is observed in
the executing/monitoring processes
Closing
The 49 processes of project management are grouped under one of the 5 process
groups/10 knowedge areas listed above and will be discussed in more details next.
3 new processes are added while 1 deleted in PMBOK® Guide 6th edition, resulting
in a total of 49 processes from 47 processes in PMBOK® Guide 5th edition:
Added processes
o Manage Project Knowledge – in Executing Process Group / Project
Integration Management knowledge area
o Implement Risk Responses – in Executing Process Group / Project Risk
Management knowledge area
o Control Resources – in Monitoring and Controlling Process Group /
Project Resource Management knowledge area
Deleted process
o Close Procurement – activities now are included in Control
Procurements and Close Project or Phase process
In the PMBOK® Guide 6th edition, many tools and techniques have been grouped
according to their purpose with a view to better supporting tailoring:
Data gathering
Data analysis
Decision making
Communication
Interpersonal and team skills
Communication skills
Organization System
Project Life Cycle vs Project Management Life Cycle vs Product Life Cycle
The Code of Ethics and Professional Conduct help an individual in making wise
decisions, particularly when faced with difficult situations where the individual may
be asked to compromise his or her integrity or values. The Code of Ethics and
Professional Conduct affirms these four values as its foundation.
Responsibility
Respect
Fairness
corrective and preventive actions usually don‘t affect the baseline, only affect
the performance against the baseline
defect repair: considered as rework, deliverable not accepted, either rework
or scrap, strongly advise defect prevention to defect repair
the work performance info is fed from all other control processes (e.g. control
schedule, control stakeholder engagement, control communications, control
costs, control quality, etc.)
Data Analysis Techniques include:
o Alternatives analysis
o Cost-benefit analysis
o Earned value analysis
o Root cause analysis
o Trend analysis – forecasts future performance based on past
performance
o Variance analysis – analyzes the differences (or variances) between
planned and actual performance
Decision Making is a technique to achieve a decision e.g. by voting.
must ensure all procurements are closed before formal closure of the
project/phase, all procurement documentation must be collected, indexed and
filed
obtain formal approval to close out the project/phase (administrative
closure)
o obtain approval and deliver the deliverables (maybe with training)
o formal sign off by designated stakeholders/customer
finish and archive documentation, lessons learnt and update to organizational
process asset
if the contract comes with a warranty, make sure that changes during the
project are evaluated against the origin clauses, ensure alignment of the
warranty and changes
to close a project as neatly and permanently possible
for multi-phase projects, this process will be performed once for every phase
end and once for the whole project (5 times for project with 4 phases)
The final report is a summary of the project performance, including:
o Summary level description of the project or phase
o Scope objectives
o Quality objectives
o Cost objectives
o Summary of the validation information for the final product, service or
result
o Schedule objectives
o Summary of how the final product, service, or result achieved the
business needs
o Summary of any risks or issues encountered on the project and how
they were addressed
litigation can be further pursued after the closure
Collect Requirements
Define Scope
to define both the project& product scope in details, outlines what WILL and
what WILL NOT be included in the deliverables, including details of
constraints and assumptions
o vs project charter which includes only high-level descriptions
may provide alternatives if the budget and schedule could not meet
management‘s expectations
Product analysis includes techniques such as:
o product breakdown
o systems analysis
o requirements analysis
o systems engineering
o value engineering – a part of product analysis technique (Value
Engineering (value analysis, value management, value methodology)
with a view to finding alternatives to constraints to improve
product/reduce cost without sacrificing the scope)
Create WBS
the WBS must be created for every project (if you take on a running project
without WBS, you must stop the project immediately and prepare the WBS
first)
o WBS is a structured hierarchy created by the organization/stakeholders,
can be in an organization chart or table form, based on the project
deliverables (not tasks needed)
o WBS is a decomposition tool to break down work into lowest level
manageable (time and cost can be estimated, work package can be
assigned to a team member) work packages, e.g. by phase or major
deliverables
o the work packages are broken down enough to delegate to a staff, usu.
8 – 80 hours work and different work packages can be at different
levels of decompositions
o WBS does not show dependencies between work packages, but a WBS
dictionary does (WBS dictionary clarifies WBS by adding additional
information)
o WBS includes 100% of scope (100% rule)
o can be a template in OPA
a higher level above a work package is ‗control account‗ (control point where
scope, cost and schedule are compared to earn value for performance
measurement)
o a work package can have only ONE control account
code of accounts: a numbering system to identify WBS components
Validate Scope
Control Scope
Define Activities
Sequence Activities
Develop Schedule
the schedule baseline is the approved and signed version of project schedule
that is incorporated into the PM plan
the project schedule is calendar-based taking into accounts
holidays/resource availability/vacations
o vs the time estimate (work effort/level of effort) just describes the
man hours/man days
the Schedule Data includes schedule milestones, schedule activities, activities
attributes, and documentation of all assumptions and constraints, alternative
schedules and scheduling of contingency reserves
Slack/Float
o Slack/Float: activities that can be delayed without impacting the
schedule
o Free slack/float: time an activity can be delayed without delaying the
Early Start of the successor
o Total slack/float: time an activity can be delayed from early start
without delaying the project end date (scheduling flexibility), can be
negative, 0 (on the critical path) or positive
o Project Float: without affecting another project
Control Schedule
Estimate Costs
Determine Budget
Control Costs
Earned value management (EVM) bases on the concept that i) work completed will
deliver value and ii) the value delivered equals the budget put into the work. The
value gained can be assessed along the progression of the project. In reality, earned
value management is very complicated as value usually cannot simply be assessed
based on the percentage of completion.
Good news here: PMI has simplified PMP® EVM calculation to very “ideal” situations!
You will just need to know the following to get your PMP® EVM questions correct.
To speak more clearly how the value is to be managed, a number of terms are
defined in EVM (explained with the example of building 10 houses each has a value of
US$1000 expected to be completed in 10 weeks in proportion):
EVM is based on monitoring these three aspects along the project in order to
reveal the health of the project with the following indices:
From my experience, the most difficult process of solving EVM problems for PMP®
Exams is to identify the PV, EV and AC from the wordy calculation questions. Then
you will just have to recall the correct formula to substitute the values into to get the
answer — the question will usually ask you directly about the actual indices to get.
If EV line is below PV, the project is behind schedule; if EV is above PV, the
project is ahead of schedule.
If AC line is below EV, the project is within budget; if AC is above EV, the
project is over budget.
Below is an example of the EVM charts you would be likely to encounter in your
PMP® Exam — solid lines represent actual figures while dotted lines represent
forecasted figures:
Judging from the chart above, we can infer that the project is currently
over budget and behind schedule.
quality policy (either organizational or just for the project), methods and
procedures to meet the objectives and satisfy customer‘s needs
o including identifying the quality requirements and document how to
achieve
Manage Quality
Control Quality
The Resource Management Plan is to organize and lead the project team as
well as other resources
o include roles and responsibilities (identify resources that can take up
the responsibilities) as documented (ownership of deliverables) in RAM
in the form of RACI chart (matrix) or in a chart/text form, org charts –
an organizational breakdown structure (OBS) and staffing
management plan – staff acquisition, release, resource calendar,
resource histogram, training, rewards, compliance & safety
requirements
networking is useful in understanding skills of individuals and the political and
interpersonal factors within the organization
Data Representation techniques:
o Hierarchical-type charts
Work breakdown structures (WBS)
Organizational breakdown structure (OBS) — the OBS displays
organizational relationships and then uses them for assigning
work to resources in a project (WBS); the org chart also indicates
the reporting structure of the project
Resource breakdown structure (RBS)
RACI chart
as a planning process
closely related to Estimate Cost Process (in Project Cost Management
knowledge area)
Data Analysis includes:
o Various levels of resource capability or skills
o Different sizes or types of machines
o Different tools (manual versus automated)
o Make-rent-or-buy decisions
resource calendar spells out the availability of resources (internal/external)
during the project period
matches human resources to activities (as human resources will affect
duration)
effort (man day, work week, etc.) vs duration vstime lapsed (total time
needed, including holidays, time off)
―alternative analysis‖ includes make-or-buy decisions, different tools, different
skills, etc.
Resource Requirements (formerly Activity Resource Requirements) details the
types and amounts of resources required for each activity in a work package.
The basis of estimates include methods, assumptions, constraints, the range of
estimates, confidence levels, risks, etc.
Acquire Resources
Develop Team
Manage Team
Control Resources
Manage Communications
Monitor Communications
Identify Risks
to find out and document all risks affecting the project from all aspects of the
project, including:
o agreements/contracts within/outside of the organization
o procurements
o requirements, schedule, cost, resource, quality, scope, etc. from the
project management plan
Data Gathering Techniques: brainstorming, checklists, interviews, Delphi
technique [a panel of independent experts, maintain anonymity, use
questionnaire, encourage open critique],
Data Analysis Techniques:
o root cause analysis [performed after an event to gain understanding
to prevent similar events from occurring], SWOT analysis, assumption
and constraint analysis
root cause analysis: safety-based (prevent accidents),
production-based, process-based (include business process),
failure-based, systems-based (all above)
root cause analysis tools: FMEA, Pareto Analysis, Bayesian
Inference (conditional probability), Ishikawa Diagrams, Kepner-
Tregoe
o Monte Carlo analysis can identify points of schedule risks
prioritizing risks for further analysis/action and identify high priority risks
o risks requiring near-term responses are more urgent to address
o need to identify bias and correct it (e.g. risk attitude of the
stakeholders)
Data Analysis Techniques include:
o Risk data quality assessment
o Risk probability and impact assessment
the cost, schedule and risk management plan contains guidelines on how to
quantitatively analyze risks
o involves mathematical modelling for forecasts and trend analysis
Representation of Uncertainty (probability distribution) reflects the risks as a
probability distribution, which can be in the following distribution types:
o Triangular
o Normal (bell-shaped curve)
o Lognormal
o Beta
o Uniform
o Discrete
Data Analysis Techniques:
o sensitivity analysis (using the tornado diagram as presentation) for
determining the risks that have the most impact on the project
o Failure Modes Effects Analysis (FMEA)
o FMEA for manufactured product or where risk may be undetectable,
Risk Priority Number (RPN) = severity (1-10) x occurrence ([0.07%] 1-10
Control Risks
when all the above risk planning processes have been performed with due
diligence, the project is said to have a low-risk profile
responsibilities include:
o to check if assumptions are still valid, procedures are being followed
and any deviance
o to identify new risks and evaluate effectiveness of risk response plan
o any need to adjust contingency and management reserves
Conduct Procurements
Control Procurements
(The “Close Procurements” process in PMBOK® Guide 5th Edition has been
moved and merged into “Control Procurements and Close Project or Phase”)
Identify Stakeholders