Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
ructure
4.1 Introduction
()hjectives
4lh INTRODUCTION
aware that freshly mixed concrete is a semiliquid-solid mass and needs
setting, hardening and achieving strength. Till such number of days, it is
shape and position by certain separate supporting system. The system
i) Formwork in which the concrete is poured to have its internal faces exactly
matching with the external faces of the member under consideration. In case
of beams of rectangular section 300 x 600 mm the internal dimension of the
formwork having sheets on two vertical sides and one bottom side leaving
top face open for lowering down the designed steel-reinforcement cage and
pouring the concrete. In the case of R.C.C. dome construction, there will be
two forms of dornical shape one to match on the lowerhottom surface of
concrete dome and another form to suit the top surface of the dome making
arrangement to hold them so that the clear gap equal to thickness of the
dome remains constant even after pouring the concrete between the two parts.
ii) Staging and Centering are meant to provide supports from a rigid ground
(or previousIy cast R.C.C. members which have already gained strength) to
the formwork so that formwork is able to withstand both vertical and
horizontal forces.
objectives
going thr9ugh this unit, you will be acquainted with basic information of
(Sheeting
Span -
[, Span I Sheefing
Pr@ssure
sleeper commcted
i) Any timber that is straight and structurally strong and soupd may be used for
formwork, although the wide distribution and abundance of softwoods make
them generally most economical for all types of formwork,. The softwtmds
are usually lighter in weighter and are generally easier to work. Hardwood
caps and wedges may be introduced where additional strength cross grain is
needed.
ii) Partially seasoned stock is preferred for formwork, since fully dried timber
swells excessively when it becomes wet and green timber will dry out and
warp during hot weather, causing difficulties of alignment and uneveu
surface. (:)Id and new sheeting or boards should not be used together in the
same panel if uniform form finish is important.
iii) Refer Table 4.1 for some typical species of structural timber, m d e names,
availability etc, as per 15883, Table 4.1. Timber which has been surfaced to
attain smoothness of surface and uniformity of size is called "dressed"
timber. The surfacing may he on one side 6 1 s ) . two sides (S2S). two edges
(S2E). Dressed timber is generally used for formwork because it is easier to
handle and work, but roughsawl1boards and timbers may be used in bracing
and shoring, or as a form surface material to secure a special texture effect
in the f i s h e d concrete.
iv) Tongue and groove boards are to be used for sheathing where smnt~>lhness of
surface is an important consideration. "Matching" of the boards, that is
fitting the tongue into the groove of the adjacent board improves alignment
of the sheathing and also prevents loss of mortar through the joints.
v) Refer I.S.4891 for preferred sizes of timber which are reproduced in
Tables 4.2,4.3 & 4.4 (these are sawn sizes).
Table 4.2 :Referred Cut Sizes of Structural Timbers for Roof Trusses from 3 to 20 m
20 40 SO 60 80 - - -
Table 4.3 :Prefeired Cut Sizes of Structural Timbers for Purlins, Rafters, Heams etc.
Table 4.4 :Preferred Cut Sizes of Structural Tlmbers for Partition Framing and
Covering
Depth (mm)
t-free concrete reduce the cost of finishing and rubbing exposed surfaces. Also
exceptionally high strength/stiffness to weight ratio; it is easy to handle, cut
; it can be bent ru~dc a be
~ for~ned
~ into curves and has good thermal
properties. When bonded with phenol fornlalclehyde synthetic resin and treated
preservatives, plywood becomes highly water-pnmf m d durable against
+
electrical insulation properties ax1 easy workability using hand tools.
+
Foll
cement concrete and acts as barrier against wtnd extractives.
ing are d e generally available sizes and thickness of plywood.
Detailing dReinforced Table 4.5
Concrete Construction
Plywood Size m x m Thickness (mm)
2.44 X 1.22
4.3.4 Steel
Steel has long been an irrlportant material for the fabrication of special purpose fornu, all
steel panel systems for ger~eralbuilding construction have been succt:sst~,illyfabricated
and used; and steel framing and bracing are Important in ths ccins&uc:tion of mrulj, wc.n>d
and plywood panel systems; horiaelal and vertical sheres of ssec'! are wldcly ?!xi:rl today.
Standard and lightweight ut~u:::ural steel rnernbers coaslsting of channel), mgies. I
beams, open telescopic trusf bcalal? a!lrl oti~ers,car1 be used to support !hc stieathnng. With
proper inalntenance they Inst nnu~fllor~ycrluld therebq may prove econonmcal even
though their initial cost is high. It I \ very colmnon to use circular steel plpes for staging
work as they have the best structur;~llyefficient cross-sectional shape for carrying 'axial
compressive loads. For durability these can also be galvanised.
Prefabricated forms and forming system9 have become increasingly popular as they save
both material and labour cost. They are built for durability even after repeated uses. Some
of these proprietary system are described below:
i) Panel Forms
There are two types commordy in use - all steel panels and plywood panels
set in steel metal frame. They are light and are manufactured in standard
modular sizes of 600 rnrn wide and 1150, 1000,900 & 800 mn long.
Generally all steel panels are 2 mm thick with pressed flanges and stifher
(Ref Figure 4.2 (a), (b)). 9 to 12 mrn thick plywood panel forms are fixed
onto metal frame by sunk carriage bolts or slipped into metal frame as
shown in Figure 4.1. (c), (d). They are 900 x 1200 & 1500 in plan.
ii) Wall Panels
Wall panels are also similar in design and construction as referred in floor
panels above.
iii) Adjustable Spans
They are basically telescopic lattice type horizontal beams. They are used
for supporting the sheathing or floor panels and can be used for spans
varying from 2 to 5 m (Refer Figure 4.2 (e), (0,(g)).
iv) Vertical Props
There are several types of adjustable individual props. Some of them have
provisions for adjustment both at the top and bottom. Figure 4.2 (b) shows a
prop with tripod base for stability and hence can stand independently. There
is also a provision for height adjustment at tripod and in the mop. The
adjustable two way head helps in holding the longitudinal beam in both
directions.
v) Staging Frames
Refer Figure 4.3 (a) & (b) for staginglshoring frames and Figure 4.3 (c) for
heavy duty tower frames which can be used upto 10 m heights.
/.Carriage nut Principles d Design and Detailing
of Formwork and Scsffddinp:
( a ) Section- floor panel
-
( c 1 Section- floor panel
]:I L
-- - - - ------
-- - ,,- - - - - - ,I 1
(
I
I
) Plan - floor panel
~ondtudiml
beam
Floor prop
Removable
folding tr ;pop
q*)
Spreader
Screw jack
U head
n
u - U -
-Water seal (optional )
"
n
S~)rCudcr
(c) COIIC
I
(0 Strap Tie Use with Panel
(h) Straight Tie with AUarhed Elastic Tube (Suggested Load Capacity 20 to 224 W)
Dccallinp: of Reinforced
C o n c ~ i Construction
e
(i) Thlreded Rzu with Unatta~chedI'lstic Sleeve (Suggested 1,t)ad Ca~pneily20 111220 kN)
( k ) P l d n Coil Type, Coil'l'ypes are also available with 4 Struts (Suggmted I,oud C:npacily 20 10 ILO kN)
(nl Plain Tie with Sl~e-RollI)iscon~wctinp.Ends may have Water Stop (Suggested Imrrd Capacity I4 to 2tW)kN)
-
Figure 4.4 (n to 11) : Fomt Ties (Suggested Working Load Approximately 9 to 22 k N (:e~~o.r;~lly
;md for Taper
Ties 20 to 220 kN)
Figure 4.5 (n) :Representative of the Mnny Special Purpose Tying Devices are these Two for Altachmmt t o
Reinforcing Steel. The Lower Single-end Coil Tie can be Welded in the Field, while the u p p r r one is Suitable for
lnstulation whew Welding to the Reinforcing Bar is not Permittrd
Principles rbf I)csign und Detailing
rpf Fnrmw~~rk and Scdolding
~ i , , ~4s
, . (c)
~ :plws Designed to fill Tie Cone Holm are avnilable in Mortar or Plastic: with folours e w e r
matc.iw or wi(h surrounding concreie. Various types of Epoxies be used to assure a Positive
Sed. H u p may be sized for Flwh Irwtollntion if desired
b) Double Couplers
These s e used to assemble scaffold tubes finilly at right atlgles.
c) Screw Type Adjustable Base
This is a Screw Type Adjustable Base used for adjustment of
base-height in the range of 80 to 200 mrn from ground level. This is
provided with a robust threaded rod and a 150 mnl square base- plate.
d) Tubular Type Adjustable Base
This is telescopie tubular arrangement used for coarse adjustment of
height in steps between 600 mrn to 1000 mm.
e) Swivel Coupler
Swivel couplers are used to assemhle two tubes at any angle.
f) Expanding Joint Pin
These are special bars or pins used for intercomecrhg scaffold tubes
end to end. When tiUed, the pin expwds, internally to apply grip
against the wall of the tubes to make r firm joint.
ix) Slip fonn Shuttedng is a special type of device in which formwork for
concrete tanks/vessles can be made to move or dip upward as the concrete in
" ~ e rrinb wrtiw is set. The conar(ins cpo go ~on~uousIy.
"" ae h e = h a a i ~ system ofjacks,
p'affom md
jacw.
rods, ~o&~ieg~,
Figure 4.9
s l i ~ ~ @ - f ~ m w oover
r*
R,C. wdl,
Detailing ot Reir~lomed
Concrete Construction
Fknre 46 (a)to (h) :Smple screw -or (left) she* the Two Pnrta of the Unit Assembled in Concrete
Embedded Ao&omge Unit only is shown for aeved other tgpw of Fonn-l)sehor. Some of these require abon
shorn on the I d t . The Crbnped Anchor q a f r o s an lntcrually Threaded Bolt Canneetion, and the H ~ ~ c - P ~ U
..
...
- . .. .- .- . . . Principles nf Design and llrtililing
of Formwork iuwl S c a d d i n g
-. ...- HOLES ORLLLE
....
--.....
..
...
....
. -. . THREAOEO ROD
.. .. .. . . . . . . .
..,.. . . . . . . - * . .. .. ... .. -. .. . .: .. TO CONNECT TO
:One t l t h e several available Anchons lor Ofl-rock Tying. The Anchor Unit b placed in a h d e
r e k . When (he BoH o r External Fmtener is inserld it expands thc Anchors. Thus tightening it
VII~ the rock .%me Rock Anchors are domiu~cdto he surrnunded hy grnut i n Ute rock cavity
(a) Rabcd-Pmition with Fonns in Pmition (b) Struck-Position for Removd of Fonns
Figure 4 7 :Dr~phends
I
(a) Adjuntable Stirrup Head (h) Double Coupler
Woter
Shutt
4.3.5 Aluminium
Density of aluminium is 33 8 that of steel. Use of aluminium alloys for fortning and
shoring applications can be, therefore, useful where cost of transport and hatxllinp is a
major consideration. Alunlinium is very light. Aluminium is ;ul ideal strucmr;ll malerial to
be used in launching heavy precast concrete girders of bridges etc. However. pure
aluminium is attacked chemically by wet concrete and special treatme~~ts to alu~lli~lium
forms are required. However. as use of aluminium is not that comnon we woultl not
proceed further with this topic. The main aspect is that its basic cost is too hipll.
b
4. .6 Glass Fibre Reinforced Plastics
G or FRP forms are strong and light and'are capable of producing high quality
ete surfaces and generally last through numirous re-uses with nominal touch-ups.
can he readily fabricated to complex shapes. FRPIGRP coatings can also be applied
Prineiiplcr ot Design and &tailing:
of Formwork and Scadding
er f(xming material such as plywood or steel to get high quality finished surfaces or
re-uses. Again these being uncomnlon usages we would not proceed further with
FRP.
4.317 Form Lining Materials
1
The following are die special purpose form liners:
a) Rubber Liners
Neoprene arid other types of r h h e r lnals 11lay be used as baseliners in
repetitive factory precasting work.
1 b) Vacuum Liners
Vacuum treatment removes water aid air bubbles from surface layer of
iieshly placed concrete thus iolpn,vinp ils durability and strength. The
vacuum treatment is achieved (specially of mads, factory floors, run-ways)
on fonned surfaces using two-layer o i screen or wire mesh covered by a
layer of cloth.The liner is sealed witli rubher or caulking material around the
edges of the form panel. A series of opcnings in the form panel backing is
connected to a vacuum pump and as s m n as concrete is placed the liner is
covered over the fresh axicrete and vacuum is applied.
As more water than that required for chenlical hydration is invariably used in
concretes, the concrete produced lnay have internal voids and less strength.
llie form liner incorporating textile fabrics helps in draining of excess waer
thus reducing voids and producing strong and durable surface and body
concrete. These can be used in heavy slabs, beams, columns, walls, piers,
1 dal~isetc.
) Insulation Form Llners
These can he used to keep concrete at such temperatures during casting that
it does not dry out in hot weather or does not freeze in cold weather so that
concrete lnay gain strength without loss of heat of hydration. These liners
liuy consist of insulated sandwitched panels or foamed polystyrene plastic
boards.
Indicate the basic element of fonn-work arid scaffolding. Draw neat sketches
of the same.
Enumerate at least five different nlaterials which can be used as for m-work.
i()
"In the case of timber, a partially seasoned stock is preferred for
formwork". Is the slatement correct. Give suitable explanation.
Indicate the density (X L,llowing wood-varieties referrills to I.S.88:1
it)
1 c ) Eucalyptus
I d ) Indian Oak
y el Teak
V) I11dicate briefly howplywood is manufactured and explain its important
properties including its density a i d approximate modulus of nlpture (Refer
Taple 4.7).
Indicate salient feature of tlle plain shuttering wood? What ruie the general
available sizes.
D v i n g crt ReinfcA'r.ner( .....;:
'>.
I 3._
~i~~;:~_i?;t?~i:.'~;r'a~:,~:j.i-i;;?iiionssteeliscc~>~o~cforfomwork:'Draw
Concrete Ctmsts-r ctv,n- ni::r: -:.lici:i:i.t i:f ?*::~.ii.\:prr; [231;4 arid the adjustable tubulx prop.
j R; 'rh<ig:i 'f:? (f;>-:!ivtjr&ftr; ~ t a i ~ c a in s c() (VI) above us~llpplywood sheets.
J i) 3!!) 11.; ntv, o:k ir, r.fyw:'nd sheeting, timbrr-heams, aid steel props
f d i r
-9' Di ,r;D !bc 3 , r ,* icib, in c;r:rx.i ti;r a rrti~intnpwall, 2 m helow groutid level
: "i, F ~ C ' J-r;si , ~ 1;ri !:\t<:j, 25 nietres long amd 200 illin unitornl tNck11css.
?l:r* it,: t.. : 3iictre ,!la heel-slab 1s 2 nlctres. Assiarnr: the concrete with
c-!t.,,~
tteier 'Thblc 4 6 for vaiues of modulus of elasticity. allowable stresses in hcudinp. shsar &
ct)mprt:asiari rcproducetl iiom IS : 883 for common t~n~hers.
A x ~ a('on~presslvc
l Stressas, on,III Nln1m2 (Clause 5 1 . 1 ) .
I
Slenderness 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180
Ratio
1150x600
900 X 600
1150
900
(mm)
300
400
"
d
/'q
M.S. 16.9
~ & i Charts
~ n for Formwork (Struts)
Height IBreadth ( S l d or L l d )
is':' I It&!
ts ,<,I.l*or~li\vc~rk
(Wall and Colunlns Sheeting)
. - -
Span (metre 1
IJesignChortq fur Furmwnrk t.ldsts, Yokes & Bearers37 nun Wido)
2
I ) Safe shann; .?as = I .4 Nlmtli
1
2) Safe bending stress = 7.0 N/~iiai'
3
3 ) Assu~iirtlE (Young's Modulus) = 8.5 x 10. ~ / m m ?
4 ) Ileflection. not rxcwtling 3 111nland not a x d i n g span1360
5 ) Vduls dlow for tinibex bring 3 111111less than no~ninalsizes
SPCBF{ mat re )
Ilt CitagbZ, for Rwn~wurk(.loists, Yokrs A Isenrer\ fs2 liuzr 12'idr I
i) S:\ft- sh~rrillgstrcss = 1.4 Nirntn2
2) S,~ii:irnding srl.css = 7.11 ~ i l n r n '
.i) ,\::stiillwl f; (Y1,ung's Modul~s)= 8.5 x 103 N / I ~ I I I ~
-I ; t)ellcclion, not excaalinp 3 nrtn ;~nclnot c x ~ e u l i l ~spanlZh0
g
5) Vi~luei dl,*w fcr tiniher being 3 111111 lrss than notllind si~rs
+- R
p = 150 43400+ 2800 - (maximum of 2000 psf for 150 h
T T
whichever is smaller)
iv) For walls with rate of placement greater than 10 f t . h
p=150h
v) For slipform
All these formulae are for concrete made with OPC with unit weight of 25 Principles ofDesip;n and Detailing
k ~ l d c o n t a i n i n gno admixtures, with sluii~pless than 100 mm and placed of Fonnwork and Scaffolding
with normal internal vibration. Concrete pressure on form work can also be
based on CIRIA Report, refer Tables 4.10.. 4.1 1,4.12, for design pressures
p, (height lirnit).pr (arching limit) and y , (st~ffeninglimit) respectively.
(
i \ c) Horizontal Loads
Bracings and props should be designed for all the possible horizontal loads
due to wind, inclined supports, dumping of concrete and equipments.
However, in no case, this horizontal load acting in any direction at each
floor line should be less than 1.5 kN/m of 11oor edge or 2% (of total dead
load on the form distributed as a unifornl load/nl of slab edge whichever is
greater. Wallforms also should be designed to meet wind load requirements
\I where,
F = the average force,
w = weight of the equipment, and
u = acceleration or deceleration.
ncrete buckets are used, it may be necessary to ullload the concrete at one
bution. This can cause impact due to dropping and utibalanced loading on
-
Table 4.10 :Horizont~lPressurep1 Helght Llrnlt
1
As deflection is 6 > -
360
(= 2.8 mm) or 1.6 mm, change span
1=1240 i f 6 9 3 mm
Assume 1= 1.30 m
Check bending stress
0.5 x 7500 x 1 . 3 x~ 1000
M = Nmm = 6.34 x l d Nmm
10
Beam Design : Assume size of 50 x 160 (50 x 150) and span 1.25 m.
(Refer T d l e 6 of IS :883 )
Total Load = 7.5 x 1.25 x 1.25 = 11.7 kN
Detailing of Reinforced
Concrtte Construction
0.329E 0.329~10~
Compressive stress = - = = 2.85 N/mn2 compared to
(sW2 . 342
2.4 N/mm2 from Chart 4.2.
STRtSS 25 T H I C K PLANKS
PERM~SSIBLE
198B JCL 6.5
T ( 5 0 k 100)
O N SO0 o ~ c
1.25 SPAN
0.12~10~x6
Bending stress.f = = N1mm2
144000
I Y-l
Section y 3,
Section X-k ;O
?
F'lgrue 413 I Lnyoat Plan of Panel
B1-TELESCOPING BEAM
c) Telescopic beam
Approximate span 5.7 m.
Refer Figure 4.15 showing prop on the centre-line of symmetry.
Load = 1.2 x 7.5 = 9.0 kNlm
Refer Table 4.9 B for a total load of 7.8 kN/m2 and spacing of 1.2 m the
beam span % 2840 mm, hence provide two beams on 5.7 m with one central
52
row of props of capacity - = 26 kN each.
2
d) Formwork for main beam
Assume depth of beam = 600 mm,
Slab thickness = 200 mm.
Refer Figure 4.25 for details
i) Bottom sheetlng
Load of Concrete = 0.8 x 25 = 20 kN/m2
Live load + Self weight = 2.5 kN/m2
Total Load = 22.5 kN/rn2
Prop on 1.2 c l c
M,, =
w P --
- 2.25 x (1.2)' = 0.32 lrNm
10 10
nr
placement of 15 m/hr, slump of concrete 100 mm,and temperature -10%. Design
the forms.
Solutlon
Evaluate the design lateral pressures as per Tables 4.10.4.11.4.12.
Since h = 5 m, thickness, d = 600 mrn and R = 15 m/hr for columns.
p, = height limit = 125 kN/m2 (Table 4.10)
p, = arching limit = 110 kNlm2 (Table 4.1 1)
p, = stiffening effect = 150 kNlm2 a able 4.12j
:. Adopt design pressure = 110 kN/m2.
a) Let ids use timber sheathing and timber yokes.
i) Use 40 mm thick planks with yokes at 500 nunc/c
72
Direct tension in yoke ( I) = - = 16 kN.
2
Design size of yoke (Refer Figure 4.17).
(a)SECTIONAL ELEVATION
Direct tension = -
1*00 - 2 N/mm2, (allowable 1.25 N/mm2)
8000
244 lo6
Bending tension = = 11.3 N/mm2, (allowable 12.8 N/-~)
1.7 x lo7
Maximum tensile stress = 2 + 11.3 = 13.3 N/rnm2 > 12.8 N I ~ ~ I I ~ '
This is only marginally exceeded (within 5%) and hence car1 be accepted.
If required change section to 80 x 160 mm
Direct tension to be transmitted at the comers of yokes through bolts. Using
16 mm diameter two bolts to have shear capacity (considering threaded bolts)
=2 ~2~0.7~80~1.25=28000N=28kN.
Load on the bolt is simultaneously along two directions each being 16 kN.
.: Resultant load = 16 fi=
24 kN < 28 kN.
Note .: As we proceed upwards, the lateral load reduces and hence yoke spacing
could be increased in which case plank would need deflection check.
b) Let us use plywood,sheuthing timber yokes and adjustable nnd dcmountuble
steel column clumps (Refer Figure 4.18 (a) ( b ) )
Assume c/c distance between clamp (1) and (2) as 400 mm and a total load
on clamp (1) as (53 kN x 0.6) = 32 kN.
For 25 mm plywood, where E = 7000 ~ l m m ~
I
Plywood
25 thick
PLAN
(a) Plan
Principles d Design and Detailing
of Formwork and Scaffdding
Steel clamp momber
( 5mm .x 50mm 1
OaY lo''
Bending stress = = 3.4 N/-2
1000 x 402
5'42 (lo)'
Bending stress =
70 x (20012
= I 1.6 N / m 2 :. O.K.
47.5 x (0.6)~/ 10
Bending suess = x lo6 = 7.3 N I I I I ~ ~:. ~ o .~.
2.33 x (10)"
(Alter~lativelyuse two 60 x 100 nun wales for better detailing.)
V) Rearing: Joist or stud on wale
Load = 15 x 1.9 = 28.5 kN
A = 70 x 140 = 9800 nun'
28500
Bearing stress = -= 2.9 N/nmi2
9800
Try wales 60 x 100 mm, A = 2 x 60 x 70 = 8400 run*
Bearing suess = - - 3.4 ~1-2
28500 - > 1.25 x 1.8x 1.17
MOO
Hence use bearing plate between stud 'and wales 25 mil thick.
28500
Area required = = 12670 mm2 i.e. 150 x 100 ~iirii.
1.25 x 1.8
I
Q!
s 5100-42
Try 120 x 140 timber, - = - -
d 120
Compression capaclty = 1.82 x 1.25 x 120 x 140 = 38 kN.
1) Plywood used shall not be delaminated and all edges shall be properly
sealed.
2) Manufacturers' certificate indicating all important engineering properties be
available at site.
3) Ul~loadingof plywood at site shall be by lifting and not sliding to avoid
edge damages.
4) It shall be stacked on raised level with proper ventilahon and protected
fro111strong sunlight.
5) Coat all the form panels wlth mould oil.
Structural Steel
1) A manufacturers' certificate indicating all Important engineering properties
1s to be insisted.
2) Collfirmatory tests to be done in laboratories for all mportant properties.
3) All steel to be stored above ground lcvel platform.
4) The steel to be cleaned and painted with antirust paints to avoid stainlng
concrete.
5) ,411 accessories illust be as per proprietary systelxls w ~ t hthreads. bolts, nuts
etc. 111 order.
Detailing d ReMomed
concrete cwstmction
4.7 SUPERVISION OF FORMWORK AND STAGING
Let us make a list of sonie of the deficiencies in relation to formwork so that you will
know importance of supervision better: .
1) Inadequate lateral and diagonal bracings for vertical props and stagings,
2) Inadequate area of the vertical props to cater to the loading,
3) Poor splicing of timber props,
4) Inadequate details when in double stages props are one over the other,
5) Lack of bracings at joints in props,
6) Props not in plumb,
7) Locking devices on steel props not locked, in operative or defective,
8) Unstable or l m e soil under the props,
9) Improper packings under props to make up the height,
10) Insufficient connectors at joints i.e. nails, bolts etc:,
11) Inadequate forms for lateral pressures of concrete,
12) Inadequately tightened or secured form ties,
13) Inadequately securedwedges for form and scaffoldings,
14) Failure to check tightness of props on floors below,
15) Failure ti) inspect ru~dtl~oroughlycheck cleanliness, tightness o f joints.
rusting etc.,
16) Failure to co~ltrolvertical rate of placement of concrete md consequent
increased lateral loads,
17) Uneven placement of concrete imposing unbalanced load on forills and
props,
18) Vibrations and shock arising from external and internal vibrators,
equipn~entslike buggies and lifts with loose joineries,
19) Premature removal of props specially under cantilevers,
20) Overloading of phyrietory standard systems and thdr ;~ccessories,
21) Use of defective .ind substmdard wood,
22) Improper sequence of stripping of forms,
23) Lack of wettingof timber forms before concreting, thereby absorbing water
from fresh concrete and swelling, that causes warping and htwleyconlbing,
ruld
24) Failure to seal edges of cut plywood results in blemishes in concrete.
Check List for Formwork Supervision
1) The formwork drawing be made available well in advance nf construction
schedule.
2) All form materid (be it timber, plywood or steel) as indicated on drawings
along with all accessories such as wedges, blockings, headplates, couplers.
at site along with all the tools etc.
or specitications.
bngth
Fa)lanbs
i) Elevation of formed soffit before removal of 2 20 mm
props.
b) Beams
i j Variation of lcvel of formed soffit before
removal of props.
I -
i~ I Devisltio~~
from speoified size I ) upto 300 mm -6mm
2)300to900mm +12mm
- -
Columns and Walls
I
I
i) Var~ationfrom specified size I ) upto 300 mm
-
2)300to900mm
- 6 rnm
t10mm
ii! Out of plumbness in completed structure -25m
30 mm high
-
I iij) Variation in the size of wall openings - 6 m
+ 25 mm
d) Footings
i) Dimensions in plan -12mm
+ 50 mm
ii) Thickness k 5%
15) No steel prop shall be used if the tube has a bend or crease in it or corrosion
has reduced the area of section or its head or base plate is bent or the pin is
damaged.
16) Props should not be off-centre by more than 25 rnnl and should be generally
in plumb and not out of plumb by more than 1 in 40.
17) All props and shores must be braced as per designs and the design loild shall
not be exceeded.
18) When using double staging, the props must he in one line in vertical plane
and shall be braced in plane of staging as also in vertical planes as per
design/manufacturers' requirement.
19) All accessories after every reuse shall be checked for their size shape,
threads, pins, or any damage etc. to maintain integrity of the system.
20) All formwork must be checked for the rigidity so that internal and external
vibrators;equipments etc. do not affect the form joints or dislodge props. A
separate team of . work force be assigned this task of supervision and
corrective actions must be taken immediately.
21) Ties, separators, form blockouts must be inspected before and during
consttuction. The ties or tie bolts in beams columns and walls be properly
tightened to avoid diqprtions in cross- sections.
Principles of 'Designm d Detailing
22) Before concreting beams, columns and walls, all dirt, shavings, tie-wire, of Formwork and Scaffolding
clippings, nails, etc. shall be removed from within the formwork. Also
ensure that all the inserts, embedments, cutout blanks are in correct locations.
Ensure further that these are secured firmly in its position against
displacements caused due to pouring of concrete and due to vibrations.
23) The rate of placement of concrete shall conform to the design requirements
so that excess horizontal pressures do not develop on forms. Also dumping
or uneven loading of concrete shall be avoided, and vibrators shall not be
used to spread the concrete.
24) Enough working platforms and adequate accesses are to be provided so also
safely nets and belts.
25) Premature removal of forms and props shall be guarded against instruction
for deshuttering & removal of forms be taken from structural consultants.
Refer Table 4.16 for IS 456 guidelines for form strippings in ordinary normal
circunlstances and using O.P.C.
26) Sloping or horizontal top forms are subjected to upward pressures from the
fresh concrete and need to be firmly restrained and tied down.
27) Special care need be exercised at the base of props that support ramps,
staircase slabs, arches, shells as they also induce in addition to vertical load a
horizontal load as well. These structures need bracings and raker for better
stability.
28) Forms must be given enough camber so that after their removal the
structures do not exhibit pronounced sag.
29) Stripping sequence or order and rate is also very important so that Ule load
shall be gradually be transferred to the structure without jerks and impact
ties and clamps should be loosened gradually and the same to be collected
systematically. Props under simply supported or continuous slabs and beams
be removed from centre to both supports evenly and props under cantilever
beam be removed from free end to the support and earlier than the beam at
the back.
Table 4.17 : Form Stripping Time as per IS 456
Items Stripping Time
a) Walls, colurm~sand vertical faces of all 24 tn 48 11rs after casting
structural members is completed
C 1
b) Slabs (props left under) 3 days (i.e. 72 hours)
C) --- --
Beam soffits (props left urrder) 7 days
Removal of props under slab-
1) Spanning upto 4.5 m 7 days
2) Spanning over 4.5 m . -- -- 14 days
Removal of props undel 1,-.1:136 md arches
14 days
2) Spanning over 6 m 2 1 days
I Note :Fomq shall not be muck untll the ii~Tetehas reached a strength at l a s t twlce the stress to which the concrete
may be ~ubjectedat the t ~ of
m removal c b t formwork.
i) Referring to chart 4.1 &tennine the suitable thickness of timber plank for
slab sheeting considering load of 7.5 kN/m2over a span of 1.2 metres.
I iii)
ii) Referring to chart 4.3 determine the suitable thickness of timber plank for
wall-sheeting considering load of 7.5 kN& over a span of 1.2 metres.
Referrirlg to chart 4.5 for Timber Beams de'termine the
of the 62
wide beam to support a U.D.L. of 7.5 m/m over a span of 1.2 metre.
'Vj "'"g chm4.2 (a) for timber prop &tennine ~e sde compessive aid
S'ess
(1' '' prop of height 3 metres and diameter (a) 50 mm (b) 65 mm
& (d) 100 nun. State also Ule a i a l load capacity in
Detailing of Reinforced
Concrete Construction
v) Write clearly the functions of the following:
a) Tie Bolt;
b) Wedge;
c ) Sleeper;
d) Raker prop;
e) Joint sealers;
vi) Design a suitable formwork and scaffolding for a staircare 1.5 ll~etrewide,
having midlanding at 3 metres, has 20 risers each of 150 mm and 19 treads
each of 300 mnm and a waist slab of 200 mm thickness in R.C.C. Use all
timber members. Check the base of prop when safe load hexing capacity
of compacted ground is 20 kN/m2.
vii) Redesign the formwork for staircase in (vi) above using plywood sheets.
viii) Design the formwork in plywood sheeting, timber-beams ruld steel-props for
a concrete beam (400 mm wide x 2000 mm deep) soffit being at 4 nletres
level. Assume temperature of 20°C at the time of concreting, slulnp of 100
mm and the rate of placement of concrete as 2 metres per hour.
ix) Design the formwork in wood for a retaining-wall, (2 m) below ground level
'md (3 m) above ground 25 metres long and 300 mrn uniform thickness. The
clear toe is !metre and heel-slab is 2 metres. Assurne the concrete with
(a) temperature of 15°C (b) s l u q of 50 mm and (c) rate of placement of
concrete is ? metreshour. Assunie w~ndpressure to be 1.S kN/11i3.
- - -----
4.8 SUMMARY
In this unit you have been given basic ideas as to the funcuons of formwork In
consuuction of R.C. concrete structures, various materials. their engmeeri~lgproperties
and inspection of form materials and supervision of the same. It is hoped tllar you now
realise the Importance of formwork desiin and execution and supervisit~nat site. It is to
be noted that for t~mberforn~workthe properties should be verified by conducting
laboratory tests whenever there are doubts. Care should be taken in scaffr)lding by
providing bracing (diagonal) and l..ieral ties.
In c g e of use of structural steel and steel plates, it is a l l y necessary to check against
corrosion. Note the reduction in Ule area of sections. Making neat joints both it] case of
timber scaffolding or steel scaffolding IS of utmost inlpr)rtance and needs to be supervised.
:
Menlber of formwork nearest and in contact with
~ollcrete.
Mernher resting on ground nearest tobase in formwork
01'walls, colunuls etc.
PrinciyIes of I)r'iixn :~tidL)et;lilinr:
of Forn~work;~ndScaffolding
t
Sle per :
:
A menlber under tlle ba:.%of prop for spreading the load
011 larger
area in poor ground.
k temporary member keeping oppoite sheeting at
correct distance.
: A systetn of vertical, Ilorizontal and inclined members
of fonr~work.
~!!#~,rrn : -4 coniinuousi:~clllnbinp formwork for tall structures.
4 ANSWERS TO SAQs
j !-I !i!10 jvi! art. availat~lein the text of this unit in pc>rtion4.7 md 3.4 svnle
prmicrl cf sii::tea'i~j are ~ ~ n i l i i b ?later
i : in rhe Tables or Charts
VII) Sled f(~rinu'n$k hag an advanl'lgc that lighler rnemher$ are possible since
rabncated 110i10w ~nenlhers;Ire made with adequate del>th T~mber
scctltn IS dlw,iyb bo/~dmd 11t'ncc heailer Tlle ntilrihrr ot reuse of steel
form 1s much Inore thiul number i ~ usages
f of I I ' * plywood. Hence in a
peritxl of 10 years. for prolects where I'ornls ( , i\ed repeatedly steel
formworks will be cheaper. rile thickness ot dr, 2nlent of 5 to 6 Inn1 is
sAQr
acceptable.
i
Detailing of Reinforced Raker under ramps :any inclined rne~nherwould have lo,ul conlponcllls
Concrete Construction in vertical and horizontal directions giving resultant 111 inl'linctl tlirectr )n and
the inclined raker prop is the best suited to resist the SiIIIX.
5) Joint sealers : These help in preventing loss of n~olsturcliom uuihsr
sheetinglplywood at their cut-edges.
vi)
SPLICE
k
J
(a) Elevation (b)Cms-section
Figure 4.22 :Fonnwork lor RC Beam
viii)
Principles vf Ilrsign and Detailing
of hrmu.clrk and S e m d i n p ,
Figure 4.21
FURTHER READING --- .-- . - -- --