PETRONAS CARIGALI
MIE INFRASTRUCTURE & ENERGY SDN BHD
SDN BHD
REV ISSUE
PREPARED BY REVIEWED BY APPROVED BY REVIEWED BY
DATE
NO. FOR
NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE
0 AFC 08.12.15 YS 08.12.15 MSI 08.12.15 MA 08.12.15
PROVISION OF DESIGN & BUILD FOR SABAH OIL AND GAS
MIEIE TERMINAL (SOGT) ELEVATED ACCESS ROAD, PETRONAS CARIGALI
Document No. EAR-MIEIE-C-MOS-0009
Document Title. METHOD STATEMENT FOR PROJECT SIGNAGES
Revision No. (Date) 0 (08/12/2015)
Page No. 2 of 16
CONTENT
SECTION DESCRIPTION PAGE
1 PURPOSE…………………………………………………………………………………....... 3
2 SCOPE………………………………………………………………………………………..... 3
3 REFERENCES………………………………………………………………………………… 3
4 DEFINITIONS………………………………………………………………………………….. 3
5 PROCEDURE…………………………………………………………………………………. 4
5.1 WORK PREPARATION………………………………………………………………….. 4
5.2 REQUIREMENT OF MANPOWER…………………………………………………….. 4
5.3 REQUIREMENT FOR EQUIPMENT AND MACHINERIES…………………………. 5
5.4 SCHEDULE……………………………………………………………………………….. 5
6 SEQUENCE OF WORK………………………………………………………………………. 5
7 EMERGENCY RESPONSE………………………………………………………………….. 7
8 COMPULSORY HSE REQUIREMENT …………………………………………………….. 8
9 RECORD……………………………………………………………………………………….. 8
10 ANNEXS………………………………………………………………………………………. 8
- PROJECT SIGNAGES LAYOUT PLAN AND DETAILS
- JOB HAZARD ANALYSIS (JHA)
- WBS
- CALIBRATION CERTIFICATE (TOTAL STATION)
PROVISION OF DESIGN & BUILD FOR SABAH OIL AND GAS
MIEIE TERMINAL (SOGT) ELEVATED ACCESS ROAD, PETRONAS CARIGALI
Document No. EAR-MIEIE-C-MOS-0009
Document Title. METHOD STATEMENT FOR PROJECT SIGNAGES
Revision No. (Date) 0 (08/12/2015)
Page No. 3 of 16
1. Purpose
The purpose of this method statement is to show the correct method of construction work for
the Project signboard for the Provision of Design and Build for Sabah Oil and Gas
Terminal (SOGT) Elevated Access Road, Petronas Carigali.
It is part of the Local Authority (Majlis Daerah Papar) requirement for the Contractor to erect
and maintaining the project signages throughout the Project duration.
2. Scope
3. References
The requirements contained in the latest editions of the following Codes and Standard shall
form an integral part of this method:
“THK” Thickness
“IFC” Issued for Construction
5. Procedure
MIEIE to ensure the proposed Project Signages Drawing has been reviewed and commented
By CLIENT prior to start any works.
Survey team shall mark/peg the correct position of Project Signages based on the AFC
drawing REV 0.
5.4 Schedule
The work of Project Signages will based of the following schedule :
6. Sequence of Work
The following are the sequence of work for Critical Personnel Crossing but not limited
to this:
a) Application of Permit To Work (PTW)
Permit to Work (PTW) shall be applied and discussed at the early stage of
Project Signboard construction works. MIEIE’s personnel shall work closely to
CLIENT representative and to comply all their requirement. Apart from that,
MIEIE’s personnel shall ensure the construction of Project Signboard will use
the IFC drawing.
Tool box meeting on daily basis shall be carried out by safety personal prior to
start work. The safety personal shall highlight the potential hazard of the work
to be done according to the Job Hazard Analysis (JHA). Safety personal shall
ensure the JHA produce are discussed and review with CLIENT according to
their respective sequence of works and to be attached with the PTW.
b) Survey works
The survey team shall ensure all marking/pegging made are clearly visible and
recheck as to ensure the correct location of Project Signboard. Reference level
shall be established at any existing permanent structure. Any issues with
regards to the survey works must be cleared prior to start/continue any
construction works.
Figure 1
Prior to column pole concreting works, the Project Signages in which consist of
Timber Board (12 mm THK) and RHS (100mm x 50mm x 3 mm THK) are to be
manually assemble. The Timber Board will be drilled directly to the RHS as for
the main support. Site Personnel to ensure the dimension and spacing of
Timber Board are according to the IFC Rev 0 drawing.
Figure 2
Once the Column pole are concrete, the construction works should continue
with the excavation of bracing pole. The top bracing will be installed manually
to the erected project signboard using the metal ladder and drill machine.
7. Emergency Response
In the event of MAJOR emergency from SOGT Plant, MIE-IE shall follow / ride on SOGT ERT
procedure.
On the other hand, for any emergency case at site, MIEIE site safety supervisor shall be alert
immediately. For emergency response plan, appointed Sub contractor and internal general
workers shall follow HSE document provided. All personnel involved shall follow HSE program
during commencing of works.
The evacuation route, assembly location, and emergency communication net work shall be
prominently displayed at the site office and in MIEIE and Subcontractors main office, field office
and at the gates of the construction site.
HSE officer shall plan emergency drill to be in line with the risks of accidents and emergency
situations that might occur at the site in order to confirm effectivness of the accidents and
emergency response organization and to have all personnel at the site raise their awareness
of emergency response system.
The following requirements shall be followed by the Contractor and appointed Subcontractor
prior to start or entering the site works:-
a) KPKK SERVICE PROVIDER FORM – To be filled individual and to submit one (1) week
before enter the site.
b) DAILY MANIFEST – Minimum 1 day before 2 pm.
c) CONTRACTOR COMPETENCY CARD (CCC) FOR CONTRACTORS – To submit
Seven (7) days before, particular work.
9. Record
a) All activities shall be recorded in daily progress report, including of manpower,
equipment and tools.
10. Annex
- Project Signboard Layout Plan and Details
- Job Hazard Analysis
- WBS
- Calibration Certificate (Total Station)
PROVISION OF DESIGN & BUILD FOR SABAH OIL AND GAS
MIEIE TERMINAL (SOGT) ELEVATED ACCESS ROAD, PETRONAS CARIGALI
Document No. EAR-MIEIE-C-MOS-0009
Document Title. METHOD STATEMENT FOR PROJECT SIGNAGES
Revision No. (Date) 0 (08/12/2015)
Page No. 10 of 16
WBS
PROVISION OF DESIGN & BUILD FOR SABAH OIL AND GAS
MIEIE TERMINAL (SOGT) ELEVATED ACCESS ROAD, PETRONAS CARIGALI
Document No. EAR-MIEIE-C-MOS-0009
Document Title. METHOD STATEMENT FOR PROJECT SIGNAGES
Revision No. (Date) 0 (08/12/2015)
Page No. 13 of 16