Sei sulla pagina 1di 80

CONSTRUCTION ENGINEERING PROJECT

NATIONAL UNIVERSITY OF CIVIL ENGINEERING


DIVISION OF CONSTRUCTION TECHNOLOGY AND MANAGEMENT

PROJECT
CONSTRUCTION ENGINEERING I
CONSTRUCTION OF MONOLITHIC REINFORCED CONCRETE IN
MULTI-STOREY BUILDING

Content: Design construction method of monolithic reinforced concrete


in multi-storey building

Tutor: VUONG DO TUAN CUONG


Student:

Class: 56XE
Id Number

i
CONSTRUCTION ENGINEERING PROJECT

DATA

Number of storeys 8
Number of spans 21
[σ] Wood (kG/cm2) 90
γ Wood (kG/m3) 600
Season Winter
b (m) 12
A 2.2
Foudation A (m) B 2.4
C 2.2
t (cm) 40
B (m) 3.3
1 5.8
L (m)
2 4.0
H1 (m) 4.5
Ht (m) 3.4
Hm (m) 3.4
F.1; F.2 30/45
F.3; F.4 30/40
C1 (d/h1)
F.5; F.6 30/35
Body F.7; F.8 30/30
Column
F.1; F.2 30/50
F.3; F.4 30/45
C2 (d/h2)
F.5; F.6 30/40
F.7; F.8 30/35
s (cm) 15
D1g 25/40
D1
D1b 25/60
Beam D (cm)
D2 25/35
D3 20/30
Dm 20/60
Roof
m (cm) 15
Reinf.
µ% 1.0
ratio

ii
CONSTRUCTION ENGINEERING PROJECT

CALCULATION
I. DRAWINGS:

A
st r u c t u r e pl a n

B B
A

1
CONSTRUCTION ENGINEERING PROJECT

a -A

2
CONSTRUCTION ENGINEERING PROJECT

B -B

3
CONSTRUCTION ENGINEERING PROJECT

II. PRELIMINARY DATA:


1. Preliminary concrete volume, steel mass and form work area:
CONCRETE VOLUME
Volume
Size
per Volume Total
Element Quantity
Width element (m3) (m3)
Length (m) Height (m)
(m) (m3)
F[1;2] 4.50 0.30 0.45 0.61 88.00 53.46
F[3;4] 3.40 0.30 0.40 0.41 88.00 35.90
C1
F[5;6] 3.40 0.30 0.35 0.36 88.00 31.42
F[7;8] 3.40 0.30 0.30 0.31 88.00 26.93
Column
F[1;2] 4.50 0.30 0.50 0.68 132.00 89.10
F[3;4] 3.40 0.30 0.45 0.46 132.00 60.59
C2
F[5;6] 3.40 0.30 0.40 0.41 132.00 53.86
F[7;8] 3.40 0.30 0.35 0.36 132.00 47.12
D1b 5.80 0.25 0.60 0.87 308.00 267.96 2812.81
D1
D1g 4.00 0.25 0.40 0.40 308.00 123.20
D2 3.30 0.25 0.35 0.29 735.00 212.23
Beam
D3 3.30 0.20 0.30 0.20 588.00 116.42
Dmb 5.80 0.25 0.60 0.87 44.00 38.28
Dm
Dmg 4.00 0.25 0.60 0.60 44.00 26.40
S1 5.80 3.30 0.15 2.87 336.00 964.66
Slab
S2 4.00 3.30 0.15 1.98 336.00 665.28

4
CONSTRUCTION ENGINEERING PROJECT

STEEL MASS
Steel
Volumn Reinf. Steel Mass Total
Element Unit Weight
(m3) ratio (%) (Kg) (Kg)
(Kg/m3)
F[1;2] 53.46 0.01 7850.00 4196.61
F[3;4] 35.90 0.01 7850.00 2818.46
C1
F[5;6] 31.42 0.01 7850.00 2466.16
F[7;8] 26.93 0.01 7850.00 2113.85
Column
F[1;2] 89.10 0.01 7850.00 6994.35
F[3;4] 60.59 0.01 7850.00 4756.16
C2
F[5;6] 53.86 0.01 7850.00 4227.70
F[7;8] 47.12 0.01 7850.00 3699.23
D1b 267.96 0.01 7850.00 21034.86 220805.37
D1
D1g 123.20 0.01 7850.00 9671.20
D2 212.23 0.01 7850.00 16660.15
Beam
D3 116.42 0.01 7850.00 9139.28
Dmb 38.28 0.01 7850.00 3004.98
Dm
Dmg 26.40 0.01 7850.00 2072.40
S1 964.66 0.01 7850.00 75725.50
Slab
S2 665.28 0.01 7850.00 52224.48

FORMWORK AREA

Size Number Area of


Area Total
Element of Formwork
Width (m2) (m2)
Length (m) Height (m) Elements (m2)
(m)
F[1;2] 4.50 0.30 0.45 6.75 88.00 594.00
F[3;4] 3.40 0.30 0.40 4.76 88.00 418.88
C1
F[5;6] 3.40 0.30 0.35 4.42 88.00 388.96
F[7;8] 3.40 0.30 0.30 4.08 88.00 359.04
Column
F[1;2] 4.50 0.30 0.50 7.20 132.00 950.40
F[3;4] 3.40 0.30 0.45 5.10 132.00 673.20
C2
F[5;6] 3.40 0.30 0.40 4.76 132.00 628.32
F[7;8] 3.40 0.30 0.35 4.42 132.00 583.44
D1b 5.80 0.25 0.60 9.86 308.00 3036.88 37539.08
D1
D1g 4.00 0.25 0.40 5.20 308.00 1601.60
D2 3.30 0.25 0.35 3.96 735.00 2910.60
Beam
D3 3.30 0.20 0.30 3.30 588.00 1940.40
Dmb 5.80 0.25 0.60 9.86 44.00 433.84
Dm
Dmg 4.00 0.25 0.60 6.80 44.00 299.20
S1 5.80 3.30 0.15 40.02 336.00 13446.72
Slab
S2 4.00 3.30 0.15 27.60 336.00 9273.60

5
CONSTRUCTION ENGINEERING PROJECT

2. Vertical transport equipment:

Select tower crane on rail because:

 Concrete volume is large (>100m3 concrete per slab)


 Capable of reduce number of labours.
 Capable of reduce time for transporting materials
 High quality in construction process
 Length of building is great meanwhile height is average.

III. FORMWORK DESIGN:


1. Slab formwork:

The slab formworks are laid on the stringers. The shores are necessary for the slab stringers.

Distance between T-shores must me calculated based on durability and deformity condition.

a. Calculating diagram:

2 1 1 2 1

3 3
4

MC 1-1

1- Concrete slab; 2- Boards; 3- Stud; 4 – Stringer;

 Select a typical slab to calculate the formwork: L1=5.8+4 (m), B=3.3 (m)
(axis C-D-E;1-2).
 Calculate on a strip with width 1(m). (perpendicular to the stringer’s direction).
Calculating diagram is a continuous beam with stringers acting as supports.

6
CONSTRUCTION ENGINEERING PROJECT

l l l

Calculating diagram of a slab strip with width 1m

b. Loads:

 Self-weight of slab formwork (q1), (n1=1.1)


g1tc   w 1  slab. fw.  600 1 0.03=18(kg / m)
g1tt  g1tc  n1 =18 1.1=19.8(kg / m)
 Self-weight of concrete slab (q2), (n2=1.2)
g 2tc   conc 1  slab  2500 1 0.15  375(kg / m)
g 2tt  q2tc  n 2 =375 1.2=450(kg / m)
 Self-weight of steel (q3), (n3=1.2)
g3tc   steel 1  slab    7850 1 0.15  0.01  11.78(kg / m)
g3tt  q3tc  n 3 =11.78 1.2=14.14(kg / m)
 Live load by pouring concrete (q4), (n4=1.3)
p4tc  600 1  600(kg / m)
p4tt  p4tc  n 3 =600 1.3=780(kg / m)
 Live load of workers and construction equipment (q5), (n5=1.3)
p5tc  250 1  250(kg / m)
p5tt  p5tc  n 5 =250 1.3=325(kg / m)
 Total load for checking Durability condition of slab formwork:

q tt  G tt  Ptt  19.8  450  14.14  780  325  1588.94(kg / m)

 Total load for checking Deformity condition of bottom board:

7
CONSTRUCTION ENGINEERING PROJECT

q tc  G tc  18  375  11.78  404.78(kg / m)

c. Distance between stringers:

 Geometric properties of slab formwork:


b b 100  33
3

I sl .board    225(cm 4 )
12 12
b b 100  32
2

Wsl .board    150(cm3 )


6 6
 Distance of stringers based on the Durability condition:
M
  [ ]w
Wsl .board

Legend: M: Maximum bending moment:

qtt .l12 1588.94.l12


M   158.89l12
10 10

Wsl .board  1.5 104 (m3 )

[ ]w  90 104 (kg / m2 )

 158.89  l12  90 104.1,5.104  l1  0.9 m


 Distance of stringers based on the Deformity condition:
f  f 

Legend: f : calculating deflection of slab formwork

qtc  l2 4 404.78l2 4
f   8
 1.28 103 l2 4
128.EI 128 1.110  225 10
9

1
f  L (TCVN 4435:1995, corresponding with component
400
having exposed surface)

 1.28 103 l2 4  l2 / 400  l2  1.25(m)

 Select lstringer  min(l1 ; l2 )  lstringer  0.9(m)

8
CONSTRUCTION ENGINEERING PROJECT

 Number of stringers per a typical slab (figure below)

d. Slab shores:

Calculating diagram: continuous beam with slab shores acting as supports


Select the cross-section of stringer: 0,08 x 0,12 m
The distance between loads applied on each stringer: bstringer  l stringer  0.9(m)

Stringers and slab shores in a typical slab

9
CONSTRUCTION ENGINEERING PROJECT

 Geometric properties of stringer:


b  h3 0.08  0.123
I stringer    1,15.105 (m4 )
12 12
b  h2 0.08  0.122
Wstringer    1,92.104 (m3 )
6 6
 Loads:
 Load from slab formwork:
q1tt  qtt  bstringer  1588.94  0.9  1430.05(kg / m)

q1tc  qtc  bstringer  404.78  0.9  364.30(kg / m)

 Self-weight of stringer:
q2tt  n   g  Fxg  1.1 600  0.08  0.12  6.34(kg / m)
q2tc   g  Fxg  600  0.08  0.12  5.76(kg / m)
 Total load for checking Durability condition of slab shores:

qttstringer  q1tt  qtt2  1430.05  6.34  1436.39(kg / m)

 Total load for checking Deformity condition of slab shores:

qtcstringer  q1tc  qtc2  364.30  5.76  376.06(kg / m)

 Distance between slab shores:


 Durability condition:
M
  [ ]w
Wstringer
10  Wstringer 10  90 104 1.92 104
 l1  tt
  1.10(m)
qstringer 1436.39
 Deformity condition
f  f 
128EI s tringer 128 1.1109 1.15 105
 l2  3  3  2.21(m)
tc
400qstringer 400  376.06
 Select lshore  1(m)

10
CONSTRUCTION ENGINEERING PROJECT

 Design slab shore:

Select slab shore: bcxhc=0.1x0.1(m),   600(kg / m3 ) ,    90(kg / c m2 ) ,


E  1.1109 (kg / c m2 )

 Geometric properties:
bc  hc 0.1 0.13
3

I   8.33 106 (m 4 )
12 12
Ac  bc  hc  0.1 0.1  0.01(m 2 )
Ic 8.33 106
rc    0.029(m)
Ac 0.01
H c  (h floor  hslab  h wedge  slab.board  h stringer ) 
 (4.5  0.15  0.1  0.03  0.12) 1
 4.1(m)
Slenderness:
H 4.1 3100 3100
 c   141.38  75    2   0.16
rc 0.029  141.382
 Check Durability condition:

qttstringer  lshore 1335.28 1


   834550(kg / m2 )     90 104 (kg / m2 )
A 0.16  0.01

 Total deformity of slab formwork:


 Deformity of T-shore:
V l (13.35 100)  410
 c  tc c   0.05(cm)
Ac  E 100 110000
 Maximum deformity of slab board:
qtc  l 4 4.048  904
f max    0.08(cm)
128EI b.board 128 110000  225
 Absolute deformity of slab formwork:
L
 slab   c  f max  0.05  0.08  0.13(cm)   0.58(cm)
1000

11
CONSTRUCTION ENGINEERING PROJECT

2. Beam formwork:

Beam formwork includes 2 side boards and 1 bottom board.

Bottom board is calculated as continuous beam with T-head shores acting as supports.

Side board is calculated as continuous beam with studs acting as supports.

d 1b bea m f o r mw o r k
(sc : 1/ 20)
a. Formwork of beam D1b and DM:

Dimension of beam D1b and DM: bxh=25x60(cm)

Thickness of bottom board:  b  4(cm)

Thickness of side board:  s  3(cm)

 Calculating bottom board:


 Loads:
o Self-weight of bottom board (q1), (n1=1.1)
q1tc   g  Fd

Legend:

 g - Unit weight of wood,  g  600(kg / m3 )


Fd - Cross-section area of bottom board

12
CONSTRUCTION ENGINEERING PROJECT

g1tc  600  (0.04  0.25)=6(kg / m)


g1tt  g1tc  n1 =6 1.1=6.6(kg / m)
o Self-weight of concrete beam (q2), (n2=1.2)
g 2tc   conc  b  h  2500  0.25  0.6  375(kg / m)
g 2tt  q2tc  n 2 =375 1.2=450(kg / m)
o Self-weight of steel (q3), (n3=1.2)
g3tc   steel  b  h    7850  0.25  0.6  0.01  11.8(kg / m)
g3tt  q3tc  n 3 =11.8 1.2=14.2(kg / m)
o Live load by pouring concrete (q4), (n4=1.3)
p4tc  600  0.25  150(kg / m)
p4tt  p4tc  n 3 =150 1.3=195(kg / m)
o Live load ofworkers and construction equipment(q5), (n5=1.3)
p5tc  250  0.25  62.5(kg / m)
p5tt  p5tc  n 5 =62.5 1.3=81.3(kg / m)
 Total load for checking Durability conditionof bottom board:

q tt  G tt  Ptt  6.6  450  14.2  195  81.3  747.1(kg / m)

 Total load for checking Deformity condition of bottom board:

q tc  G tc  6  375  11.8  392.8(kg / m)

 Distance between T-shores to support bottom board:


o Geometric properties of bottom board:
b b 25  43
3

I b.board    133.3(cm 4 )
12 12
b b 25  42
2

Wb.board    66.7(cm3 )
6 6
o T-shore distance::
Durability condition:
10  Wb.board 10  90  66.7
l1  tt
  89.64(cm)
q 7.471
Deformity condition:
128EI b.board 3 128 110000  133.3
l2  3   106.1(cm)
400q tc 400  3.928
 Select T-shore distance: l  70(cm)

13
CONSTRUCTION ENGINEERING PROJECT

 Calculating side board:


 Design height of side board:
h s.board  hbeam  hslab  h fw.slab  60  15  3  42(cm)
 Loads:
o Horizontal load of concrete motar:
g1tc   conc  hbeam  hs.board  2500  0.6  0.42  630(kg / m)
g1tt  g1tc  n  630 1.3  819(kg / m)
o Horizontal loadby pouring concrete. Use bucket with volume larger than
0.8m3. According to TCVN 4453-1995:
p2tc  hs.board  400  0.42  600  252(kg / m)
p2tt  p2tc  n  252 1.3  327.6(kg / m)
 Total load for checking Durability conditionof side board:
q tt  G tt  Ptt  819  327.6  1146.6(kg / m)
 Total load for checking Deformity condition of side board:
q tc  G tc  630(kg / m)
 Distance between T-shores to support side board:
o Geometric properties of side board:
b b 42  33
3

I s.board    94.5(cm 4 )
12 12
b b 42  32
2

Ws.board    63(cm3 )
6 6
o T-shore distance:
Durability condition:
10  Ws.board 10  90  63
l1  tt
  70.32(cm)
q 11.466
Deformity condition:
128EI s.board 3 128 110000  94.5
l2  3   80.8(cm)
400q tc 400  6.3
 Select T-shore distance: l  70(cm)

 T-shorefor beam D1b and DM:


 Vertical loads from bottom board applied on T-shore: (P1: design load, P2:
standard load)
P1  7.471 70  522.97(kg )

14
CONSTRUCTION ENGINEERING PROJECT

P2  3.928  70  274.96(kg )
 Loads from side boards and transmit through braces:

11.466  70
N1   802.62(kg )
2  cos(60)

6.3  70
N2   441(kg )
2  cos(60)

 Self-weight of side boards:


B1  2  600  0.42  0.7 1.1  388.08(kg )
B2  2  600  0.42  0.7  352.80(kg )
 Total loads applied on T-shore:

Vtt  2 N1 sin(60)  P1  B1  2  802.62  sin(60)  522.97  388.08  2301.23(kg )


Vtc  2 N2 sin(60)  P2  B2  2  441 sin(60)  274.96  352.80  1391.59(kg )

Select T-shore: bcxhc=12x12(cm),   600(kg / m3 ) ,    90(kg / c m2 )


E  110000(kg / c m2 )

 Geometric properties:
bc  hc 12 123
3

I   1728(cm 4 )
12 12
Ac  bc  hc  12 12  144(cm2 )
Ic 1728
rc    3.46(cm)
Ac 144

H c  (h floor  hbeam  h wedge  b.board )   (450  60  10  4) 1  376(cm)

Slenderness:
H 376 3100 3100
 c   108.7  75    2   0.26
rc 3.46  108.7 2
 Check Durability condition:

Vtt 2301.23
   61.46(kg / c m2 )     90(kg / c m2 )
  A 0.26 144

 Total deformity of bottom board:

15
CONSTRUCTION ENGINEERING PROJECT

 Deformity of T-shore:
V  l 1391.59  376
 c  tc c   0.036(cm)
Ac  E 144 110000
 Maximum deformity of bottom board:
qtc  l 4 3.928  704
Fmax    0.05(cm)
128EI b.board 128 110000 133.3
 Absolute deformity of main beam formwork:
Ldc
 dc   c  Fmax  0.036  0.05  0.086(cm)   0.58(cm)
1000

b. Formwork for beam D1g:

Dimension of beam D1b: bxh=25x40 (cm)

Thickness of bottom board:  b  4(cm)

Thickness of side board:  s  3(cm)

 Calculating bottom board:


 Loads:
o Self-weight of bottom board (q1), (n1=1.1)
q1tc   g  Fd

Legend:

 g - Unit weight of wood,  g  600(kg / m3 )


Fd - Cross-section area of bottom board
g1tc  600  (0.04  0.25)=6(kg / m)
g1tt  g1tc  n1 =6 1.1=6.6(kg / m)
o Self-weight of concrete beam (q2), (n2=1.2)
g 2tc   conc  b  h  2500  0.25  0.4  250(kg / m)
g 2tt  q2tc  n 2 =250 1.2=300(kg / m)
o Self-weight of steel (q3), (n3=1.2)
g3tc   steel  b  h    7850  0.25  0.4  0.01  7.9(kg / m)
g3tt  q3tc  n 3 =7.9 1.2=9.5(kg / m)
o Live load by pouring concrete (q4), (n4=1.3)
p4tc  600  0.25  150(kg / m)
p4tt  p4tc  n 3 =150 1.3=195(kg / m)

16
CONSTRUCTION ENGINEERING PROJECT

o Live load of workers and construction equipment (q5), (n5=1.3)


p5tc  250  0.25  62.5(kg / m)
p5tt  p5tc  n 5 =62.5 1.3=81.3(kg / m)
 Total load for checking Durability conditionof bottom board:

qtt  G tt  Ptt  6.6  300  9.5  195  81.3  592.4(kg / m)

 Total load for checking Deformity condition of bottom board:

q tc  G tc  6  250  7.9  263.9(kg / m)

 Distance between T-shores to support bottom board:


o Geometric properties of bottom board:
b b 25  43
3

I b.board    133.3(cm 4 )
12 12
b b 25  42
2

Wb.board    66.7(cm3 )
6 6
o T-shore distance:
Durability condition:
10  Wb.board 10  90  66.7
l1  tt
  106.7(cm)
q 5.924
Deformity condition:
128EI b.board 3 128 110000  133.3
l2  3   121.2(cm)
400q tc 400  2.639
 Select T-shore distance: l  80(cm)

 Calculating side board:


 Design height of side board:
h s.board  hbeam  hslab  h fw.slab  40  15  3  22(cm)
 Loads:
o Horizontal load of concrete motar:
g1tc   conc  hbeam  hs.board  2500  0.4  0.22  220(kg / m)
g1tt  g1tc  n  220 1.3  286(kg / m)
o Horizontal load by pouring concrete. Use bucket with volume larger than
0.8m3. According to TCVN 4453-1995:
p2tc  hs.board  600  0.22  600  132(kg / m)
p2tt  p2tc  n  132 1.3  171.6(kg / m)

17
CONSTRUCTION ENGINEERING PROJECT

 Total load for checking Durability conditionof side board:


qtt  G tt  Ptt  286  171.6  457.6(kg / m)
 Total load for checking Deformity condition of side board:
q tc  G tc  220(kg / m)
 Distance between T-shores to support side board::
o Geometric properties of side board:
b b 22  33
3

I s.board    49.5(cm 4 )
12 12
b b 22  32
2

Ws.board    33(cm3 )
6 6
o T-shore distance:
Durability condition:
10  Ws.board 10  90  33
l1  tt
  80.56(cm)
q 4.576
Deformity condition:
128EI s.board 3 128 110000  49.5
l2  3   92.5(cm)
400q tc 400  2.20
 Select T-shore distance: l  80(cm)

 T-shore for beam D1g:


 Vertical loads from bottom board applied on T-shore:
p1  5.924  80  473.92(kg )
p2  2.639  80  211.1(kg )
 Loads from side boards and transmit through braces:

4.576  80
N1   366.08(kg )
2  cos(60)

2.20  80
N2   176(kg )
2  cos(60)

 Self-weight of side boards:


B1  2  600  0.22  0.8 1.1  232.32(kg )

B2  2  600  0.22  0.8  211.2(kg )

 Total loads applied on T-shore:

18
CONSTRUCTION ENGINEERING PROJECT

Vtt  2 N1 sin(60)  P1  B1  2  366.08  sin(60)  473.92  232.32  1340.31(kg )

Vtc  2 N2 sin(60)  P2  B2  2 176  sin(60)  211.1  211.2  727.1(kg )

Select T-shore: bcxhc=10x10(cm),   600(kg / m3 ) ,    90(kg / c m2 ) ,


E  110000(kg / c m2 )

 Geometric properties:
bc  hc 10 103
3

I   833.33(cm 4 )
12 12
Ac  bc  hc  10 10  100(cm2 )
Ic 833.33
rc    2.89(cm)
Ac 100
H c  (h floor  hbeam  h wedge  b.board )   (450  40  10  4) 1  396(cm)

Slenderness:
H 396 3100 3100
 c   137.02  75    2   0.17
rc 2.89  137.022
 Check Durability condition:

Vtt 1340.31
   78.84(kg / c m2 )     90(kg / c m2 )
  A 0.17 100

 Total deformity of bottom board:


 Deformity of T-shore:
V l 727.1 396
 c  tc c   0.026(cm)
Ac  E 100 110000
 Maximum deformity of bottom board:
qtc  l 4 2.639  804
Fmax    0.058(cm)
128EI b.board 128 110000 133.3
 Absolute deformity of main beam formwork:

Ldc
 dc   c  Fmax  0.026  0.058  0.084(cm)   0.58(cm)
1000

19
CONSTRUCTION ENGINEERING PROJECT

c. Formwork for beam D2:

Dimension of beam D2: bxh=25x35 (cm)

Thickness of bottom board:  b  4(cm)

Thickness of side board:  s  3(cm)

d 2 bea m f o r mw o r k
(sc : 1/ 20)

 Calculating bottom board:


 Loads:
o Self-weight of bottom board (q1), (n1=1.1)
q1tc   g  Fd

Legend:

 g - Unit weight of wood,  g  600(kg / m3 )


Fd - Cross-section area of bottom board
g1tc  600  (0.04  0.25)=6(kg / m)
g1tt  g1tc  n1 =6 1.1=6.6(kg / m)
o Self-weight of concrete beam (q2), (n2=1.2)
g 2tc   conc  b  h  2500  0.25  0.35  218.8(kg / m)
g 2tt  q2tc  n 2 =218.8 1.2=262.6(kg / m)
o Self-weight of steel (q3), (n3=1.2)

20
CONSTRUCTION ENGINEERING PROJECT

g3tc   steel  b  h    7850  0.25  0.35  0.01  6.9(kg / m)


g3tt  q3tc  n 3 =6.9 1.2=8.3(kg / m)
o Live load by pouring concrete (q4), (n4=1.3)
p4tc  600  0.25  150(kg / m)
p4tt  p4tc  n 3 =150 1.3=195(kg / m)
o Live load of workers and construction equipment (q5), (n5=1.3)
p5tc  250  0.25  62.5(kg / m)
p5tt  p5tc  n 5 =62.5 1.3=81.3(kg / m)
 Total load for checking Durability conditionof bottom board:

qtt  G tt  Ptt  6.6  262.6  8.3  195  81.3  553.8( kg / m)

 Total load for checking Deformity condition of bottom board:

q tc  G tc  6  218.8  6.9  231.7(kg / m)

 Distance between T-shores to support bottom board:


o Geometric properties of bottom board:
b b 25  43
3

I b.board    133.3(cm 4 )
12 12
b b 25  42
2

Wb.board    66.7(cm3 )
6 6
o T-shore distance:
Durability condition:
10  Wb.board 10  90  66.7
l1  tt
  104.1(cm)
q 5.538
Deformity condition:
128EI b.board 3 128 110000  133.3
l2  3   126.5(cm)
400q tc 400  2.317
 Select T-shore distance: l  90(cm)

 Calculating side board:


 Design height of side board:
h s.board  hbeam  hslab  h fw.slab  35  15  3  17(cm)
 Loads:
o Horizontal load of concrete motar:
g1tc   conc  hbeam  hs.board  2500  0.35  0.17  148.8(kg / m)

21
CONSTRUCTION ENGINEERING PROJECT

g1tt  g1tc  n  148.8 1.3  193.4(kg / m)


o Horizontal load of pouring concrete. Use bucket with volume larger than
0.8m3. According to TCVN 4453-1995:
p2tc  hs.board  600  0.17  600  102(kg / m)
p2tt  p2tc  n  102 1.3  132.6(kg / m)

 Total load for checking Durability conditionof side board:


q tt  G tt  Ptt  193.4  132.6  326(kg / m)
 Total load for checking Deformity condition of side board:
q tc  G tc  148.8(kg / m)

 Distance between T-shores to support side board::


o Geometric properties of side board:
b b 17  33
3

I s.board    38.3(cm 4 )
12 12
b b 17  32
2

Ws.board    25.5(cm3 )
6 6
o T-shore distance:
Durability condition:
10  Ws.board 10  90  25.5
l1  tt
  90.1(cm)
q 2.818
Deformity condition:
128EI s.board 3 128 110000  38.3
l2  3   96.8(cm)
400q tc 400 1.488
 Select T-shore distance: l  90(cm)

 T-shore for beam D2:


 Vertical load from slab:
1588.94  0.45  0.15
S1   53.63(kg )
2
404.78  0.45  0.15
S2   13.66(kg )
2
 Vertical loads from bottom board applied on T-shore:
p1  5.538  90  439.92(kg )
p2  2.317  90  208.53(kg )

22
CONSTRUCTION ENGINEERING PROJECT

 Self-weight of side boards:


B1  2  600  0.17  0.9 1.1  201.96(kg )
B2  2  600  0.17  0.9  183.6(kg )
 Total loads applied on T-shore:

Vtt  S1  P1  B1  53.63  439.92  201.96  695.51(kg )

Vtc  S2  P2  B2  13.66  208.53  183.6  405.79(kg )

Select T-shore: bcxhc=10x10(cm),   600(kg / m3 ) ,    90(kg / c m2 ) ,


E  110000(kg / c m2 )

 Geometric properties:
bc  hc 10 103
3

I   833.33(cm 4 )
12 12
Ac  bc  hc  10 10  100(cm2 )
Ic 833.33
rc    2.89(cm)
Ac 100
H c  (h floor  hbeam  h wedge  b.board )   (450  35  10  4) 1  401(cm)

Slenderness:
H 401 3100 3100
 c   138.75  75    2   0.16
rc 2.89  138.752
 Check Durability condition:

Vtt 695.51
   43.47(kg / c m2 )     90(kg / c m2 )
  A 0.16 100

 Total deformity of bottom board:


 Deformity of T-shore:
V l 405.79  401
 c  tc c   0.015(cm)
Ac  E 100 110000
 Maximum deformity of bottom board:
qtc  l 4 2.317  904
Fmax    0.081(cm)
128EI b.board 128 110000 133.3
 Absolute deformity of main beam formwork:

23
CONSTRUCTION ENGINEERING PROJECT

Ldc
 dc   c  Fmax  0.015  0.081  0.096(cm)   0.58(cm)
1000

d. Formwork for beam D3:

Dimension of beam D2: bxh=20x30 (cm)

Thickness of bottom board:  b  4(cm)

Thickness of side board:  s  3(cm)

 Calculating bottom board:


 Loads:
o Self-weight of bottom board (q1), (n1=1.1)
q1tc   g  Fd

Legend:

 g - Unit weight of wood,  g  600(kg / m3 )


Fd - Cross-section area of bottom board
g1tc  600  (0.04  0.2)=4.8(kg / m)
g1tt  g1tc  n1 =4.8 1.1=5.3(kg / m)
o Self-weight of concrete beam (q2), (n2=1.2)
g 2tc   conc  b  h  2500  0.2  0.3  150(kg / m)
g 2tt  q2tc  n 2 =150 1.2=180(kg / m)
o Self-weight of steel (q3), (n3=1.2)
g3tc   steel  b  h    7850  0.2  0.3  0.01  4.7(kg / m)
g3tt  q3tc  n 3 =4.7 1.2=5.6(kg / m)
o Live load by pouring concrete (q4), (n4=1.3)
p4tc  600  0.2  120(kg / m)
p4tt  p4tc  n 3 =120 1.3=156(kg / m)
o Live load of workers and construction equipment (q5), (n5=1.3)
p5tc  250  0.2  50(kg / m)
p5tt  p5tc  n 5 =50 1.3=65(kg / m)
 Total load for checking Durability conditionof bottom board:

qtt  G tt  Ptt  5.3  180  5.6  156  65  411.9(kg / m)

24
CONSTRUCTION ENGINEERING PROJECT

 Total load for checking Deformity condition of bottom board:

q tc  G tc  4.8  150  4.7  159.5(kg / m)

 Distance between T-shores to support bottom board:


o Geometric properties of bottom board:
b b 20  43
3

I b.board    106.7(cm 4 )
12 12
b b 20  42
2

Wb.board    53.3(cm3 )
6 6
o T-shore distance::
Durability condition:
10  Wb.board 10  90  53.3
l1  tt
  107.9(cm)
q 4.119
Deformity condition:
128EI b.board 3 128 110000 106.7
l2  3   133.0(cm)
400q tc 400 1.595
 Select Distance between T-shores s to support bottom board: l  90(cm)

 Calculating side board:


 Design height of side board:
h s.board  hbeam  hslab  h fw.slab  30  15  3  12(cm)
 Loads:
o Horizontal load of concrete motar:
g1tc   conc  hbeam  hs.board  2500  0.3  0.12  90(kg / m)
g1tt  g1tc  n  90 1.3  117(kg / m)
o Horizontal load of pouring concrete. Use bucket with volume larger than
0.8m3. According to TCVN 4453-1995:
p2tc  hs.board  600  0.12  600  72( kg / m)
p2tt  p2tc  n  72 1.3  93.6(kg / m)
 Total load for checking Durability conditionof side board:
qtt  G tt  Ptt  117  93.6  210.6(kg / m)
 Total load for checking Deformity condition of side board:
q tc  G tc  90(kg / m)
 Distance between T-shores to support side board::
o Geometric properties of side board:

25
CONSTRUCTION ENGINEERING PROJECT

b b 12  33
3

I s.board    27(cm 4 )
12 12
b b 12  32
2

Ws.board    18(cm3 )
6 6
o T-shore distance:
Durability condition:
10  Ws.board 10  90 18
l1  tt
  90.5(cm)
q 2.106
Deformity condition:
128EI s.board 3 128 110000  27
l2  3   101.8(cm)
400q tc 400  0.9
 Select T-shore distance: l  90(cm)

 T-shore for beam D3:


 Vertical load from slab:
1588.94  0.45  0.155
S1   55.41(kg )
2
404.78  0.45  0.155
S2   14.11(kg )
2
 Vertical loads from bottom board applied on T-shore:
p1  4.119  90  370.71(kg )
p2  1.595  90  143.55(kg )
 Self-weight of side boards:
B1  2  600  0.12  0.9 1.1  142.56(kg )
B2  2  600  0.12  0.9  129.6(kg )
 Total loads applied on T-shore:

Vtt  S1  P1  B1  55.41  370.71  142.56  568.68(kg )

Vtc  S2  P2  B2  14.11  143.55  129.6  287.26(kg )

Select T-shore: bcxhc=10x10(cm),   600(kg / m3 ) ,    90(kg / c m2 ) ,


E  110000(kg / c m2 )

 Geometric properties:
bc  hc 10 103
3

I   833.33(cm 4 )
12 12

26
CONSTRUCTION ENGINEERING PROJECT

Ac  bc  hc  10 10  100(cm2 )
Ic 833.33
rc    2.89(cm)
Ac 100
H c  (h floor  hbeam  h wedge  b.board )   (450  30  10  4) 1  406(cm)

Slenderness:
H 406 3100 3100
 c   140.48  75    2   0.16
rc 2.89  140.482

 Check Durability condition:

Vtt 568.68
   35.54(kg / c m2 )     90(kg / c m2 )
  A 0.16 100

 Total deformity of bottom board:


 Deformity of T-shore:
V l 287.26  406
 c  tc c   0.01(cm)
Ac  E 100 110000
 Maximum deformity of bottom board:
qtc  l 4 1.595  904
Fmax    0.07(cm)
128EI b.board 128 110000 106.7
 Absolute deformity of main beam formwork:
Ldc
 dc   c  Fmax  0.07  0.01  0.08(cm)   0.58(cm)
1000

27
CONSTRUCTION ENGINEERING PROJECT

3. Column formwork:

1-1 (sc : 1/ 10)

C1 c o l u mn f o r mw o r k
(sc : 1/ 35)

Select the biggest column to design column formwork and use these parameters for the
others.
 Calculating the formwork for column C2 of the first floor: bxh = 22x50 (cm)
 Calculating diagram: continuous beam with clamp acting as supports:

28
CONSTRUCTION ENGINEERING PROJECT

 Loads applied on column formwork:


According to TCVN 4453-1995:
 Horizontal pressure of the newly formed concrete (using needle vibrators):
q1tc   conc  H

Legend:

 conc - self-weight of newly formed concrete,  conc  2500(kg / m3 )

H=75 (cm) : height of concrete layers (not higher than impact radius of needle vibrator
R=75(cm)).
q1tc   conc  H  2500  0.75  1875 (kg / m 2 )
q1tt  q1tt  n  1875 1.3  2437.5 (kg / m 2 )
 Horizontal pressure of pouring concrete:
Normally, pouring and vibrating do not occur simultaneously.
According to TCVN 4453-1995, bucket with volume larger than 0.8 (m3):
q 2tc =600(kg/m 2 ) , reliability coefficient n = 1.3
q2tt  1.3  600  780 (kg / m 2 )
 Total load for checking Durability conditionof column formwork (applied on larger side
h=50(cm)):

q tt   q1tt  q11
2   h   2437.5  780   0.5  1608.75 (kg / m)

 Total load for checking Deformity condition of column form work (applied on larger
side h=50(cm)):

q tc  q1tc  h  1875  0.5  937.5(kg / m)


 Geometric properties of column side board:
b b 50  33
3

I    112.5(cm 4 )  1.125  106 (m4 )


12 12
b b 50  32
2

W    75(cm3 )  7.5 105 (m3 )


6 6
 Distance between clamp:
 Durability condition:
10  W 10  90 104  7.5 105
l1    0.65(m)
qtt 1608.75

29
CONSTRUCTION ENGINEERING PROJECT

 Deformity condition:
128EI 3 128 1.1109 1.125 106
l2  3   0.75(m)
400qtc 400  937.5

 Select lclamp  0.65(m)  65(cm)

30
CONSTRUCTION ENGINEERING PROJECT

IV. LIST OF CONCRETE VOLUME, REINFORCEMENT MASS, FORMWORK


AREA, AND LABOUR FOR RESPECTIVE WORKS:

Concrete Volume (m³)


Dimension(m) Total
Floor Component V0(m³) Quantity V(m³)
l b h (m³)
[1] [2] [3] [4] [5] [6] [7] [8] [9] [10]
C1 4.300 0.300 0.450 0.58 46.00 26.70
C2 4.300 0.300 0.500 0.65 46.00 29.67 71.90
C3 4.500 0.300 0.500 0.68 23.00 15.53
D1b 6.025 0.250 0.600 0.90 46.00 41.57
1 D1g 4.000 0.250 0.400 0.40 46.00 18.40 349.28
D2 3.000 0.250 0.350 0.26 105.00 27.56
277.39
D3 3.075 0.200 0.300 0.18 84.00 15.50
S1 3.075 2.725 0.150 1.26 84.00 105.58
S2 3.075 1.775 0.150 0.82 84.00 68.77
C1 2.800 0.300 0.450 0.38 46.00 17.39
C2 2.800 0.300 0.500 0.42 46.00 19.32 47.06
C3 3.000 0.300 0.500 0.45 23.00 10.35
D1b 6.025 0.250 0.600 0.90 46.00 41.57
2 D1g 4.000 0.250 0.400 0.40 46.00 18.40 324.44
D2 3.000 0.250 0.350 0.26 105.00 27.56
277.39
D3 3.075 0.200 0.300 0.18 84.00 15.50
S1 3.075 2.725 0.150 1.26 84.00 105.58
S2 3.075 1.775 0.150 0.82 84.00 68.77
C1 2.800 0.300 0.400 0.34 92.00 30.91
C2 2.800 0.300 0.450 0.38 92.00 34.78 84.32
C3 3.000 0.300 0.450 0.41 46.00 18.63
D1b 6.025 0.250 0.600 0.90 92.00 83.15
3,4 D1g 4.000 0.250 0.400 0.40 92.00 36.80 639.09
D2 3.000 0.250 0.350 0.26 210.00 55.13
554.77
D3 3.075 0.200 0.300 0.18 168.00 31.00
S1 3.075 2.725 0.150 1.26 168.00 211.16
S2 3.075 1.775 0.150 0.82 168.00 137.54

31
CONSTRUCTION ENGINEERING PROJECT

Concrete Volume (m³)


Dimension(m) Total
Floor Component V0(m³) Quantity V(m³)
l b h (m³)
C1 2.800 0.300 0.350 0.29 92.00 27.05
C2 2.800 0.300 0.400 0.34 92.00 30.91 74.52
C3 3.000 0.300 0.400 0.36 46.00 16.56
D1b 6.025 0.250 0.600 0.90 92.00 83.15
5,6 D1g 4.000 0.250 0.400 0.40 92.00 36.80 629.29
D2 3.000 0.250 0.350 0.26 210.00 55.13
554.77
D3 3.075 0.200 0.300 0.18 168.00 31.00
S1 3.075 2.725 0.150 1.26 168.00 211.16
S2 3.075 1.775 0.150 0.82 168.00 137.54
C1 2.800 0.300 0.300 0.25 46.00 11.59
C2 2.800 0.300 0.350 0.29 46.00 13.52 32.36
C3 3.000 0.300 0.350 0.32 23.00 7.25
D1b 6.025 0.250 0.600 0.90 46.00 41.57
7 D1g 4.000 0.250 0.400 0.40 46.00 18.40 309.75
D2 3.000 0.250 0.350 0.26 105.00 27.56
277.39
D3 3.075 0.200 0.300 0.18 84.00 15.50
S1 3.075 2.725 0.150 1.26 84.00 105.58
S2 3.075 1.775 0.150 0.82 84.00 68.77
C1 2.800 0.300 0.300 0.25 46.00 11.59
C2 2.800 0.300 0.350 0.29 46.00 13.52 31.88
C3 2.800 0.300 0.350 0.29 23.00 6.76
DMb 6.025 0.250 0.600 0.90 46.00 41.57
8 DMg 4.000 0.250 0.600 0.60 46.00 27.60 318.46
D2 3.000 0.250 0.350 0.26 105.00 27.56
286.59
D3 3.075 0.200 0.300 0.18 84.00 15.50
S1 3.075 2.725 0.150 1.26 84.00 105.58
S2 3.075 1.775 0.150 0.82 84.00 68.77

32
CONSTRUCTION ENGINEERING PROJECT

Labour For Concrete Work


Quota Man-hour Man-day Total
Floor Component V(m³)
(h/m³) (h) (day) (day)
[1] [2] [3] [4] [5] [6] [7] [8]
C1 26.70 11.80 315.10 39.39
C2 29.67 11.80 350.11 43.76 106.05
C3 15.53 11.80 183.20 22.90
D1b 41.57 7.00 291.01 36.38
1 D1g 18.40 7.00 128.80 16.10 307.11
D2 27.56 7.00 192.94 24.12
201.06
D3 15.50 8.00 123.98 15.50
S1 105.58 5.00 527.90 65.99
S2 68.77 5.00 343.86 42.98
C1 17.39 11.80 205.18 25.65
C2 19.32 11.80 227.98 28.50 69.41
C3 10.35 11.80 122.13 15.27
D1b 41.57 7.00 291.01 36.38
2 D1g 18.40 7.00 128.80 16.10 270.47
D2 27.56 7.00 192.94 24.12
201.06
D3 15.50 8.00 123.98 15.50
S1 105.58 5.00 527.90 65.99
S2 68.77 5.00 343.86 42.98
C1 30.91 11.80 364.76 45.60
C2 34.78 11.80 410.36 51.29 124.37
C3 18.63 11.80 219.83 27.48
D1b 83.15 7.00 582.02 72.75
3,4 D1g 36.80 7.00 257.60 32.20 526.49
D2 55.13 7.00 385.88 48.23
402.12
D3 31.00 8.00 247.97 31.00
S1 211.16 5.00 1055.80 131.98
S2 137.54 5.00 687.72 85.97
C1 27.05 11.80 319.17 39.90
C2 30.91 11.80 364.76 45.60 109.92
C3 16.56 11.80 195.41 24.43
D1b 83.15 7.00 582.02 72.75
5,6 D1g 36.80 7.00 257.60 32.20 512.04
D2 55.13 7.00 385.88 48.23
402.12
D3 31.00 8.00 247.97 31.00
S1 211.16 5.00 1055.80 131.98
S2 137.54 5.00 687.72 85.97

33
CONSTRUCTION ENGINEERING PROJECT

Labour For Concrete Work


Quota Man-hour Man-day Total
Floor Component V(m³)
(h/m³) (h) (day) (day)
[1] [2] [3] [4] [5] [6] [7] [8]
C1 11.59 14.00 162.29 20.29
C2 13.52 11.80 159.58 19.95 50.92
C3 7.25 11.80 85.49 10.69
D1b 41.57 7.00 291.01 36.38
7 D1g 18.40 7.00 128.80 16.10 251.98
D2 27.56 7.00 192.94 24.12
201.06
D3 15.50 8.00 123.98 15.50
S1 105.58 5.00 527.90 65.99
S2 68.77 5.00 343.86 42.98
C1 11.59 14.00 162.29 20.29
C2 13.52 11.80 159.58 19.95 50.21
C3 6.76 11.80 79.79 9.97
DMb 41.57 7.00 291.01 36.38
8 DMg 27.60 7.00 193.20 24.15 259.32
D2 27.56 7.00 192.94 24.12
209.11
D3 15.50 8.00 123.98 15.50
S1 105.58 5.00 527.90 65.99
S2 68.77 5.00 343.86 42.98

34
CONSTRUCTION ENGINEERING PROJECT

Reinforcement Mass (kg)


Concrete Reinf. Unit Reinf.
Total
Floor Component Volume Ratio weight Quantity Mass
(kg)
(m³) µ( %) (kg/m³) (kg)
[1] [2] [3] [4] [5] [6] [7] [8] [9]
C1 0.58 1 7850 46 2096.19
C2 0.65 1 7850 46 2329.10 5643.99
C3 0.68 1 7850 23 1218.71
D1b 0.90 1 7850 46 3263.44
1 D1g 0.40 1 7850 46 1444.40 27418.75
D2 0.26 1 7850 105 2163.66
21774.76
D3 0.18 1 7850 84 1216.59
S1 1.26 1 7850 84 8288.04
S2 0.82 1 7850 84 5398.63
C1 0.38 1 7850 46 1364.96
C2 0.42 1 7850 46 1516.62 3694.05
C3 0.45 1 7850 23 812.48
D1b 0.90 1 7850 46 3263.44
2 D1g 0.40 1 7850 46 1444.40 25468.81
D2 0.26 1 7850 105 2163.66
21774.76
D3 0.18 1 7850 84 1216.59
S1 1.26 1 7850 84 8288.04
S2 0.82 1 7850 84 5398.63
C1 0.34 1 7850 92 2426.59
C2 0.38 1 7850 92 2729.92 6618.96
C3 0.41 1 7850 46 1462.46
D1b 0.90 1 7850 92 6526.88
3,4 D1g 0.40 1 7850 92 2888.80 50168.49
D2 0.26 1 7850 210 4327.31
43549.52
D3 0.18 1 7850 168 2433.19
S1 1.26 1 7850 168 16576.08
S2 0.82 1 7850 168 10797.26

35
CONSTRUCTION ENGINEERING PROJECT

Reinforcement Mass (kg)


Concrete Reinf. Unit Reinf.
Total
Floor Component Volume Ratio weight Quantity Mass
(kg)
(m³) µ( %) (kg/m³) (kg)
C1 0.29 1 7850 92 2123.27
C2 0.34 1 7850 92 2426.59 5849.82
C3 0.36 1 7850 46 1299.96
D1b 0.90 1 7850 92 6526.88
5,6 D1g 0.40 1 7850 92 2888.80 49399.34
D2 0.26 1 7850 210 4327.31
43549.52
D3 0.18 1 7850 168 2433.19
S1 1.26 1 7850 168 16576.08
S2 0.82 1 7850 168 10797.26
C1 0.25 1 7850 46 909.97
C2 0.29 1 7850 46 1061.63 2540.34
C3 0.32 1 7850 23 568.73
D1b 0.90 1 7850 46 3263.44
7 D1g 0.40 1 7850 46 1444.40 24315.10
D2 0.26 1 7850 105 2163.66
21774.76
D3 0.18 1 7850 84 1216.59
S1 1.26 1 7850 84 8288.04
S2 0.82 1 7850 84 5398.63
C1 0.25 1 7850 46 909.97
C2 0.29 1 7850 46 1061.63 2502.42
C3 0.29 1 7850 23 530.82
D1b 0.90 1 7850 46 3263.44
8 D1g 0.60 1 7850 46 2166.60 24999.38
D2 0.26 1 7850 105 2163.66
22496.96
D3 0.18 1 7850 84 1216.59
S1 1.26 1 7850 84 8288.04
S2 0.82 1 7850 84 5398.63

36
CONSTRUCTION ENGINEERING PROJECT

Labour for reinforcement work


Floo Componen Reinf. Mass Quota Man-hour Man-day Total
r t (kg) (h/m³) (h) (day) (day)
[1] [2] [3] [4] [5] [6] [7] [8]
C1 2096.19 5.36 112.36 14.04
C2 2329.10 5.36 124.84 15.60 37.81
C3 1218.71 5.36 65.32 8.17
D1b 3263.44 4.39 143.27 17.91
203.3
1 D1g 1444.40 4.39 63.41 7.93
8
D2 2163.66 4.39 94.98 11.87
165.56
D3 1216.59 5.55 67.52 8.44
S1 8288.04 6.98 578.51 72.31
S2 5398.63 6.98 376.82 47.10
C1 1364.96 5.36 73.16 9.15
C2 1516.62 5.36 81.29 10.16 24.75
C3 812.48 5.36 43.55 5.44
D1b 3263.44 4.39 143.27 17.91
190.3
2 D1g 1444.40 4.39 63.41 7.93
1
D2 2163.66 4.39 94.98 11.87
165.56
D3 1216.59 5.55 67.52 8.44
S1 8288.04 6.98 578.51 72.31
S2 5398.63 6.98 376.82 47.10
C1 2426.59 5.36 130.07 16.26
C2 2729.92 5.36 146.32 18.29 44.35
C3 1462.46 5.36 78.39 9.80
D1b 6526.88 4.39 286.53 35.82
375.4
3,4 D1g 2888.80 4.39 126.82 15.85
7
D2 4327.31 4.39 189.97 23.75
331.13
D3 2433.19 5.55 135.04 16.88
S1 16576.08 6.98 1157.01 144.63
S2 10797.26 6.98 753.65 94.21

37
CONSTRUCTION ENGINEERING PROJECT

Labour for reinforcement work


Reinf. Man-
Quota Man-day Total
Floor Component Mass hour
(h/m³) (day) (day)
(kg) (h)
[1] [2] [3] [4] [5] [6] [7] [8]
C1 2123.27 5.36 113.81 14.23
C2 2426.59 5.36 130.07 16.26 39.19
C3 1299.96 5.36 69.68 8.71
D1b 6526.88 4.39 286.53 35.82
5,6 D1g 2888.80 4.39 126.82 15.85 370.32
D2 4327.31 4.39 189.97 23.75
331.13
D3 2433.19 5.55 135.04 16.88
S1 16576.08 6.98 1157.01 144.63
S2 10797.26 6.98 753.65 94.21
C1 909.97 5.36 48.77 6.10
C2 1061.63 5.36 56.90 7.11 17.02
C3 568.73 5.36 30.48 3.81
D1b 3263.44 4.39 143.27 17.91
7 D1g 1444.40 4.39 63.41 7.93 182.58
D2 2163.66 4.39 94.98 11.87
165.56
D3 1216.59 5.55 67.52 8.44
S1 8288.04 6.98 578.51 72.31
S2 5398.63 6.98 376.82 47.10
C1 909.97 5.36 48.77 6.10
C2 1061.63 5.36 56.90 7.11 16.77
C3 530.82 5.36 28.45 3.56
DMb 3263.44 4.39 143.27 17.91
8 DMg 2166.60 4.39 95.11 11.89 186.29
D2 2163.66 4.39 94.98 11.87
169.53
D3 1216.59 5.55 67.52 8.44
S1 8288.04 6.98 578.51 72.31
S2 5398.63 6.98 376.82 47.10

38
CONSTRUCTION ENGINEERING PROJECT

Formwork Area (m²)


Dimension (m) Area A0 Total
Floor Component Quantity
(m²) (m²) (m²)
Length Perimeter
[1] [2] [3] [4] [5] [6] [7] [8] [9]
C1 4.300 1.5 6.45 46.00 296.70
C2 4.300 1.6 6.88 46.00 316.48 778.78
C3 4.500 1.6 7.20 23.00 165.60
D1b 6.025 1.7 10.24 46.00 471.16
1 D1g 4.000 1.3 5.20 46.00 239.20 2340.14
D2 3.000 1.2 3.60 105.00 378.00
1561.36
D3 3.075 1.0 3.08 84.00 258.30
S1 0.120 11.6 1.39 84.00 116.93
S2 0.120 9.7 1.16 84.00 97.78
C1 2.800 1.5 4.20 46.00 193.20
C2 2.800 1.6 4.48 46.00 206.08 509.68
C3 3.000 1.6 4.80 23.00 110.40
D1b 6.025 1.7 10.24 46.00 471.16
2 D1g 4.000 1.3 5.20 46.00 239.20 2071.04
D2 3.000 1.2 3.60 105.00 378.00
1561.36
D3 3.075 1.0 3.08 84.00 258.30
S1 0.120 11.6 1.39 84.00 116.93
S2 0.120 9.7 1.16 84.00 97.78
C1 2.800 1.4 3.92 92.00 360.64
C2 2.800 1.5 4.20 92.00 386.40 954.04
C3 3.000 1.5 4.50 46.00 207.00
D1b 6.025 1.7 10.24 92.00 942.31
3,4 D1g 4.000 1.3 5.20 92.00 478.40 4076.76
D2 3.000 1.2 3.60 210.00 756.00
3122.72
D3 3.075 1.0 3.08 168.00 516.60
S1 0.120 11.6 1.39 168.00 233.86
S2 0.120 9.7 1.16 168.00 195.55

39
CONSTRUCTION ENGINEERING PROJECT

Formwork Area (m²)


Dimension (m) Area A0 Total
Floor Component Quantity
(m²) (m²) (m²)
Length Perimeter
[1] [2] [3] [4] [5] [6] [7] [8] [9]
C1 2.800 1.3 3.64 92.00 334.88
C2 2.800 1.4 3.92 92.00 360.64 888.72
C3 3.000 1.4 4.20 46.00 193.20
D1b 6.025 1.7 10.24 92.00 942.31
5,6 D1g 4.000 1.3 5.20 92.00 478.40 4011.44
D2 3.000 1.2 3.60 210.00 756.00
3122.72
D3 3.075 1.0 3.08 168.00 516.60
S1 0.120 11.6 1.39 168.00 233.86
S2 0.120 9.7 1.16 168.00 195.55
C1 2.800 1.2 3.36 46.00 154.56
C2 2.800 1.3 3.64 46.00 167.44 411.70
C3 3.000 1.3 3.90 23.00 89.70
D1b 6.025 1.7 10.24 46.00 471.16
7 D1g 4.000 1.3 5.20 46.00 239.20 1973.06
D2 3.000 1.2 3.60 105.00 378.00
1561.36
D3 3.075 1.0 3.08 84.00 258.30
S1 0.120 11.6 1.39 84.00 116.93
S2 0.120 9.7 1.16 84.00 97.78
C1 2.800 1.2 3.36 46.00 154.56
C2 2.800 1.3 3.64 46.00 167.44 411.70
C3 3.000 1.3 3.90 23.00 89.70
DMb 6.025 1.7 10.24 46.00 471.16
8 DMg 4.000 1.7 6.80 46.00 312.80 2046.66
D2 3.000 1.2 3.60 105.00 378.00
1634.96
D3 3.075 1.0 3.08 84.00 258.30
S1 0.120 11.6 1.39 84.00 116.93
S2 0.120 9.7 1.16 84.00 97.78

40
CONSTRUCTION ENGINEERING PROJECT

Labour For Formwork Installation


F.work area Quota Man-hour Man-day Total
Floor Component
(m²) (h/m²) (h) (day) (day)
[1] [2] [3] [4] [5] [6] [7] [8]
C1 296.70 1.20 356.04 44.51
C2 316.48 1.20 379.78 47.47 116.82
C3 165.60 1.20 198.72 24.84
D1b 471.16 1.50 706.73 88.34
1 D1g 239.20 1.60 382.72 47.84 408.81
D2 378.00 1.60 604.80 75.60
291.99
D3 258.30 1.60 413.28 51.66
S1 116.93 1.00 116.93 14.62
S2 97.78 1.14 111.46 13.93
C1 193.20 1.00 193.20 24.15
C2 206.08 1.00 206.08 25.76 63.71
C3 110.40 1.00 110.40 13.80
D1b 471.16 1.50 706.73 88.34
2 D1g 239.20 1.60 382.72 47.84 355.70
D2 378.00 1.60 604.80 75.60
291.99
D3 258.30 1.60 413.28 51.66
S1 116.93 1.00 116.93 14.62
S2 97.78 1.14 111.46 13.93
C1 360.64 1.00 360.64 45.08
C2 386.40 1.00 386.40 48.30 119.26
C3 207.00 1.00 207.00 25.88
D1b 942.31 1.50 1413.47 176.68
3,4 D1g 478.40 1.60 765.44 95.68 703.24
D2 756.00 1.60 1209.60 151.20
583.98
D3 516.60 1.60 826.56 103.32
S1 233.86 1.00 233.86 29.23
S2 195.55 1.14 222.93 27.87

41
CONSTRUCTION ENGINEERING PROJECT

Labour For Formwork Installation


F.work area Quota Man-hour Man-day Total
Floor Component
(m²) (h/m²) (h) (day) (day)
[1] [2] [3] [4] [5] [6] [7] [8]
C1 334.88 1.00 334.88 41.86
C2 360.64 1.00 360.64 45.08 111.09
C3 193.20 1.00 193.20 24.15
D1b 942.31 1.50 1413.47 176.68
5,6 D1g 478.40 1.60 765.44 95.68 695.07
D2 756.00 1.60 1209.60 151.20
583.98
D3 516.60 1.60 826.56 103.32
S1 233.86 1.00 233.86 29.23
S2 195.55 1.14 222.93 27.87
C1 154.56 1.30 200.93 25.12
C2 167.44 1.00 167.44 20.93 57.26
C3 89.70 1.00 89.70 11.21
D1b 471.16 1.50 706.73 88.34
7 D1g 239.20 1.60 382.72 47.84 349.25
D2 378.00 1.60 604.80 75.60
291.99
D3 258.30 1.60 413.28 51.66
S1 116.93 1.00 116.93 14.62
S2 97.78 1.14 111.46 13.93
C1 154.56 1.30 200.93 25.12
C2 167.44 1.00 167.44 20.93 57.26
C3 89.70 1.00 89.70 11.21
DMb 471.16 1.50 706.73 88.34
8 DMg 312.80 1.60 500.48 62.56 363.97
D2 378.00 1.60 604.80 75.60
306.71
D3 258.30 1.60 413.28 51.66
S1 116.93 1.00 116.93 14.62
S2 97.78 1.14 111.46 13.93

42
CONSTRUCTION ENGINEERING PROJECT

Labour For Formwork Dismantlement


F.work area Quota Man-hour Man-day Total
Floor Component
(m²) (h/m²) (h) (day) (day)
[1] [2] [3] [4] [5] [6] [7] [8]
C1 296.70 0.38 112.75 14.09
C2 316.48 0.38 120.26 15.03 36.99
C3 165.60 0.38 62.93 7.87
D1b 471.16 0.32 150.77 18.85
1 D1g 239.20 0.32 76.54 9.57 98.10
D2 378.00 0.32 120.96 15.12
61.11
D3 258.30 0.32 82.66 10.33
S1 116.93 0.27 31.57 3.95
S2 97.78 0.27 26.40 3.30
C1 193.20 0.32 61.82 7.73
C2 206.08 0.32 65.95 8.24 20.39
C3 110.40 0.32 35.33 4.42
D1b 471.16 0.32 150.77 18.85
2 D1g 239.20 0.32 76.54 9.57 81.50
D2 378.00 0.32 120.96 15.12
61.11
D3 258.30 0.32 82.66 10.33
S1 116.93 0.27 31.57 3.95
S2 97.78 0.27 26.40 3.30
C1 360.64 0.32 115.40 14.43
C2 386.40 0.32 123.65 15.46 38.16
C3 207.00 0.32 66.24 8.28
D1b 942.31 0.32 301.54 37.69
3,4 D1g 478.40 0.32 153.09 19.14 160.39
D2 756.00 0.32 241.92 30.24
122.22
D3 516.60 0.32 165.31 20.66
S1 233.86 0.27 63.14 7.89
S2 195.55 0.27 52.80 6.60

43
CONSTRUCTION ENGINEERING PROJECT

Labour For Formwork Dismantlement


F.work area Quota Man-hour Man-day Total
Floor Component
(m²) (h/m²) (h) (day) (day)
[1] [2] [3] [4] [5] [6] [7] [8]
C1 334.88 0.32 107.16 13.40
C2 360.64 0.32 115.40 14.43 35.55
C3 193.20 0.32 61.82 7.73
D1b 942.31 0.32 301.54 37.69
5,6 D1g 478.40 0.32 153.09 19.14 157.77
D2 756.00 0.32 241.92 30.24
122.22
D3 516.60 0.32 165.31 20.66
S1 233.86 0.27 63.14 7.89
S2 195.55 0.27 52.80 6.60
C1 154.56 0.32 49.46 6.18
C2 167.44 0.32 53.58 6.70 16.47
C3 89.70 0.32 28.70 3.59
D1b 471.16 0.32 150.77 18.85
7 D1g 239.20 0.32 76.54 9.57 77.58
D2 378.00 0.32 120.96 15.12
61.11
D3 258.30 0.32 82.66 10.33
S1 116.93 0.27 31.57 3.95
S2 97.78 0.27 26.40 3.30
C1 154.56 0.32 49.46 6.18
C2 167.44 0.32 53.58 6.70 16.47
C3 89.70 0.32 28.70 3.59
DMb 471.16 0.32 150.77 18.85
8 DMg 312.80 0.32 100.10 12.51 80.52
D2 378.00 0.32 120.96 15.12
64.06
D3 258.30 0.32 82.66 10.33
S1 116.93 0.27 31.57 3.95
S2 97.78 0.27 26.40 3.30

44
CONSTRUCTION ENGINEERING PROJECT

III. CREATING CONSTRUCTION SCHEDULE:


1. Construction method:
 Deviding into 2 phases:
 Phase 1: constructing columns, walls and a side of staircases.
 Phase 2: constructing beams, slabs and the other sides of staircases.
 Line of balance method: deviding project into different tasks. Each task is executed
by a particular group of workers. The tasks are:
 Installing column reinforcements.
 Installing column formworks.
 Pouring columns.
 Dismantling column formworks, installing formwork of beams and slabs.
 Installing reinforcement of beams, slabs.
 Pouring beams, slabs.
 Dismantling beam and slab formworks.

2. Devide construction site into partitions:


a. Principle:

 Number of partitions should ensure the continuous production line.


 Difference between the largest and smallest partition should not exceed 25%.
 Volume of concrete in a partition must be poured continuously in a work shift.
 Partion must stop at settlement joint of building.
 Partion must stop at position with low value of internal forces.
 Guarantee of conditions : m ≥ n+1
where : m: total number of partitions; n: total number of tasks

b. Arrange construction site:

45
CONSTRUCTION ENGINEERING PROJECT

46
CONSTRUCTION ENGINEERING PROJECT

 Devide construction site into 9 partitions.

Concrete volume of largest partition (partition 3):

Total
Component V0(m³) Quantity V(m³)
(m³)
[1] [2] [3] [4] [5]
D1b 0.90 5.00 4.52
D1g 0.40 5.25 2.10
D2 0.26 13.67 3.59
34.59
D3 0.18 10.67 1.97
S1 1.26 10.67 13.41
S2 0.82 11.00 9.01

Concrete volume of smallest partition (partition 9):

Total
Component V0(m³) Quantity V(m³)
(m³)
[1] [2] [3] [4] [5]
D1b 0.90 5.00 4.52
D1g 0.40 5.25 2.10
D2 0.26 10.33 2.71
27.68
D3 0.18 8.00 1.48
S1 1.26 8.00 10.06
S2 0.82 8.33 6.82

Difference between 2 partitions (partition 3):

34.59  27.68
  100%  19.98%  25%
34.59

47
CONSTRUCTION ENGINEERING PROJECT

CONCRETE VOLUMN PER PARTITION


Volume
Number Volume Total Man- Total
per Quota Man-day
Floor Partition Component of per Volume hour day
component (h/m3) (day)
component partition(m3) (m3) (h) (day)
(m3)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 0.58 6.00 3.48 11.80 41.10 5.14
Column C2 0.65 6.00 3.87 9.38 11.80 45.67 5.71 13.83
C3 0.675 3 2.03 11.80 23.90 2.99
D1b 0.90 6.00 5.42 7.00 37.96 4.74
1,4,6,7,8 D1g 0.40 6.00 2.40 7.00 16.80 2.10
Beam
D2 0.26 11.67 3.06 7.00 21.44 2.68
31.97 23.35
D3 0.1845 9.33 1.72 8.00 13.77 1.72
S1 1.26 9.33 11.73 5.00 58.63 7.33
Slab
S2 0.82 9.33 7.64 5.00 38.19 4.77
C1 0.58 5.00 2.90 11.80 34.25 4.28
Column C2 0.65 5.00 3.23 8.15 11.80 38.06 4.76 12.02
C3 0.675 3.00 2.03 11.80 23.90 2.99
D1b 0.90 5.00 4.52 7.00 31.63 3.95
2,3 D1g 0.40 5.25 2.10 7.00 14.70 1.84
1 Beam
D2 0.26 13.67 3.59 7.00 25.12 3.14
34.59 24.91
D3 0.1845 10.67 1.97 8.00 15.75 1.97
S1 1.26 10.67 13.41 5.00 67.06 8.38
Slab
S2 0.82 11.00 9.01 5.00 45.03 5.63
C1 0.58 5.00 2.90 11.80 34.25 4.28
Column C2 0.65 5.00 3.23 8.15 11.80 38.06 4.76 12.02
C3 0.675 3.00 2.03 11.80 23.90 2.99
D1b 0.90 5.00 4.52 7.00 31.63 3.95
5,9 D1g 0.40 5.25 2.10 7.00 14.70 1.84
Beam
D2 0.26 10.33 2.71 7.00 18.98 2.37
27.68 20.19
D3 0.1845 8.00 1.48 8.00 11.81 1.48
S1 1.26 8.00 10.06 5.00 50.28 6.28
Slab
S2 0.82 8.33 6.82 5.00 34.10 4.26
Total 106.33

48
CONSTRUCTION ENGINEERING PROJECT

CONCRETE VOLUMN PER PARTITION


Volume
Number Volume Total Man- Total
per Quota Man-day
Floor Partition Component of per Volume hour day
component (h/m3) (day)
component partition(m3) (m3) (h) (day)
(m3)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 0.38 6.00 2.27 11.80 26.76 3.35
Column C2 0.42 6.00 2.52 6.14 11.80 29.74 3.72 9.05
C3 0.45 3 1.35 11.80 15.93 1.99
D1b 0.90 6.00 5.42 7.00 37.96 4.74
1,4,6,7,8 D1g 0.40 6.00 2.40 7.00 16.80 2.10
Beam
D2 0.26 11.67 3.06 7.00 21.44 2.68
31.97 23.35
D3 0.1845 9.33 1.72 8.00 13.77 1.72
S1 1.26 9.33 11.73 5.00 58.63 7.33
Slab
S2 0.82 9.33 7.64 5.00 38.19 4.77
C1 0.38 5.00 1.89 11.80 22.30 2.79
Column C2 0.42 5.00 2.10 5.34 11.80 24.78 3.10 7.88
C3 0.45 3.00 1.35 11.80 15.93 1.99
D1b 0.90 5.00 4.52 7.00 31.63 3.95
2,3 D1g 0.40 5.25 2.10 7.00 14.70 1.84
2 Beam
D2 0.26 13.67 3.59 7.00 25.12 3.14
34.59 24.91
D3 0.1845 10.67 1.97 8.00 15.75 1.97
S1 1.26 10.67 13.41 5.00 67.06 8.38
Slab
S2 0.82 11.00 9.01 5.00 45.03 5.63
C1 0.38 5.00 1.89 11.80 22.30 2.79
Column C2 0.42 5.00 2.10 5.34 11.80 24.78 3.10 7.88
C3 0.45 3.00 1.35 11.80 15.93 1.99
D1b 0.90 5.00 4.52 7.00 31.63 3.95
5,9 D1g 0.40 5.25 2.10 7.00 14.70 1.84
Beam
D2 0.26 10.33 2.71 7.00 18.98 2.37
27.68 20.19
D3 0.1845 8.00 1.48 8.00 11.81 1.48
S1 1.26 8.00 10.06 5.00 50.28 6.28
Slab
S2 0.82 8.33 6.82 5.00 34.10 4.26
Total 93.25

49
CONSTRUCTION ENGINEERING PROJECT

CONCRETE VOLUMN PER PARTITION


Volume
Number Volume Total Man- Total
per Quota Man-day
Floor Partition Component of per Volume hour day
component (h/m3) (day)
component partition(m3) (m3) (h) (day)
(m3)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 0.34 6.00 2.02 11.80 23.79 2.97
Column C2 0.38 6.00 2.27 5.50 11.80 26.76 3.35 8.11
C3 0.405 3 1.22 11.80 14.34 1.79
D1b 0.90 6.00 5.42 7.00 37.96 4.74
1,4,6,7,8 D1g 0.40 6.00 2.40 7.00 16.80 2.10
Beam
D2 0.26 11.67 3.06 7.00 21.44 2.68
31.97 23.35
D3 0.1845 9.33 1.72 8.00 13.77 1.72
S1 1.26 9.33 11.73 5.00 58.63 7.33
Slab
S2 0.82 9.33 7.64 5.00 38.19 4.77
C1 0.34 5.00 1.68 11.80 19.82 2.48
Column C2 0.38 5.00 1.89 4.79 11.80 22.30 2.79 7.06
C3 0.405 3.00 1.22 11.80 14.34 1.79
D1b 0.90 5.00 4.52 7.00 31.63 3.95
2,3 D1g 0.40 5.25 2.10 7.00 14.70 1.84
3,4 Beam
D2 0.26 13.67 3.59 7.00 25.12 3.14
34.59 24.91
D3 0.1845 10.67 1.97 8.00 15.75 1.97
S1 1.26 10.67 13.41 5.00 67.06 8.38
Slab
S2 0.82 11.00 9.01 5.00 45.03 5.63
C1 0.34 5.00 1.68 11.80 19.82 2.48
Column C2 0.38 5.00 1.89 4.79 11.80 22.30 2.79 7.06
C3 0.405 3.00 1.22 11.80 14.34 1.79
D1b 0.90 5.00 4.52 7.00 31.63 3.95
5,9 D1g 0.40 5.25 2.10 7.00 14.70 1.84
Beam
D2 0.26 10.33 2.71 7.00 18.98 2.37
27.68 20.19
D3 0.1845 8.00 1.48 8.00 11.81 1.48
S1 1.26 8.00 10.06 5.00 50.28 6.28
Slab
S2 0.82 8.33 6.82 5.00 34.10 4.26
Total 90.67

50
CONSTRUCTION ENGINEERING PROJECT

CONCRETE VOLUMN PER PARTITION


Volume
Number Volume Total Man- Total
per Quota Man-day
Floor Partition Component of per Volume hour day
component (h/m3) (day)
component partition(m3) (m3) (h) (day)
(m3)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 0.29 6.00 1.76 11.80 20.82 2.60
Column C2 0.34 6.00 2.02 4.86 11.80 23.79 2.97 7.17
C3 0.36 3 1.08 11.80 12.74 1.59
D1b 0.90 6.00 5.42 7.00 37.96 4.74
1,4,6,7,8 D1g 0.40 6.00 2.40 7.00 16.80 2.10
Beam
D2 0.26 11.67 3.06 7.00 21.44 2.68
31.97 23.35
D3 0.1845 9.33 1.72 8.00 13.77 1.72
S1 1.26 9.33 11.73 5.00 58.63 7.33
Slab
S2 0.82 9.33 7.64 5.00 38.19 4.77
C1 0.29 5.00 1.47 11.80 17.35 2.17
Column C2 0.34 5.00 1.68 4.23 11.80 19.82 2.48 6.24
C3 0.36 3.00 1.08 11.80 12.74 1.59
D1b 0.90 5.00 4.52 7.00 31.63 3.95
2,3 D1g 0.40 5.25 2.10 7.00 14.70 1.84
5,6 Beam
D2 0.26 13.67 3.59 7.00 25.12 3.14
34.59 24.91
D3 0.1845 10.67 1.97 8.00 15.75 1.97
S1 1.26 10.67 13.41 5.00 67.06 8.38
Slab
S2 0.82 11.00 9.01 5.00 45.03 5.63
C1 0.29 5.00 1.47 11.80 17.35 2.17
Column C2 0.34 5.00 1.68 4.23 11.80 19.82 2.48 6.24
C3 0.36 3.00 1.08 11.80 12.74 1.59
D1b 0.90 5.00 4.52 7.00 31.63 3.95
5,9 D1g 0.40 5.25 2.10 7.00 14.70 1.84
Beam
D2 0.26 10.33 2.71 7.00 18.98 2.37
27.68 20.19
D3 0.1845 8.00 1.48 8.00 11.81 1.48
S1 1.26 8.00 10.06 5.00 50.28 6.28
Slab
S2 0.82 8.33 6.82 5.00 34.10 4.26
Total 88.09

51
CONSTRUCTION ENGINEERING PROJECT

CONCRETE VOLUMN PER PARTITION


Volume
Number Volume Total Man- Total
per Quota Man-day
Floor Partition Component of per Volume hour day
component (h/m3) (day)
component partition(m3) (m3) (h) (day)
(m3)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 0.25 6.00 1.51 11.80 17.84 2.23
Column C2 0.29 6.00 1.76 4.22 11.80 20.82 2.60 6.23
C3 0.315 3 0.95 11.80 11.15 1.39
D1b 0.90 6.00 5.42 7.00 37.96 4.74
1,4,6,7,8 D1g 0.40 6.00 2.40 7.00 16.80 2.10
Beam
D2 0.26 11.67 3.06 7.00 21.44 2.68
31.97 23.35
D3 0.1845 9.33 1.72 8.00 13.77 1.72
S1 1.26 9.33 11.73 5.00 58.63 7.33
Slab
S2 0.82 9.33 7.64 5.00 38.19 4.77
C1 0.25 5.00 1.26 11.80 14.87 1.86
Column C2 0.29 5.00 1.47 3.68 11.80 17.35 2.17 5.42
C3 0.315 3.00 0.95 11.80 11.15 1.39
D1b 0.90 5.00 4.52 7.00 31.63 3.95
2,3 D1g 0.40 5.25 2.10 7.00 14.70 1.84
7 Beam
D2 0.26 13.67 3.59 7.00 25.12 3.14
34.59 24.91
D3 0.1845 10.67 1.97 8.00 15.75 1.97
S1 1.26 10.67 13.41 5.00 67.06 8.38
Slab
S2 0.82 11.00 9.01 5.00 45.03 5.63
C1 0.25 5.00 1.26 11.80 14.87 1.86
Column C2 0.29 5.00 1.47 3.68 11.80 17.35 2.17 5.42
C3 0.315 3.00 0.95 11.80 11.15 1.39
D1b 0.90 5.00 4.52 7.00 31.63 3.95
5,9 D1g 0.40 5.25 2.10 7.00 14.70 1.84
Beam
D2 0.26 10.33 2.71 7.00 18.98 2.37
27.68 20.19
D3 0.1845 8.00 1.48 8.00 11.81 1.48
S1 1.26 8.00 10.06 5.00 50.28 6.28
Slab
S2 0.82 8.33 6.82 5.00 34.10 4.26
Total 85.51

52
CONSTRUCTION ENGINEERING PROJECT

CONCRETE VOLUMN PER PARTITION


Volume
Number Volume Total Man- Total
per Quota Man-day
Floor Partition Component of per Volume hour day
component (h/m3) (day)
component partition(m3) (m3) (h) (day)
(m3)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 0.25 6.00 1.51 11.80 17.84 2.23
Column C2 0.29 6.00 1.76 4.16 11.80 20.82 2.60 6.13
C3 0.294 3 0.88 11.80 10.41 1.30
D1b 0.90 6.00 5.42 7.00 37.96 4.74
1,4,6,7,8 D1g 0.60 6.00 3.60 7.00 25.20 3.15
Beam
D2 0.26 11.67 3.06 7.00 21.44 2.68
33.17 24.40
D3 0.1845 9.33 1.72 8.00 13.77 1.72
S1 1.26 9.33 11.73 5.00 58.63 7.33
Slab
S2 0.82 9.33 7.64 5.00 38.19 4.77
C1 0.25 5.00 1.26 11.80 14.87 1.86
Column C2 0.29 5.00 1.47 3.61 11.80 17.35 2.17 5.33
C3 0.294 3.00 0.88 11.80 10.41 1.30
D1b 0.90 5.00 4.52 7.00 31.63 3.95
2,3 D1g 0.60 5.25 3.15 7.00 22.05 2.76
8 Beam
D2 0.26 13.67 3.59 7.00 25.12 3.14
35.64 25.83
D3 0.1845 10.67 1.97 8.00 15.75 1.97
S1 1.26 10.67 13.41 5.00 67.06 8.38
Slab
S2 0.82 11.00 9.01 5.00 45.03 5.63
C1 0.25 5.00 1.26 11.80 14.87 1.86
Column C2 0.29 5.00 1.47 3.61 11.80 17.35 2.17 5.33
C3 0.294 3.00 0.88 11.80 10.41 1.30
D1b 0.90 5.00 4.52 7.00 31.63 3.95
5,9 D1g 0.60 5.25 3.15 7.00 22.05 2.76
Beam
D2 0.26 10.33 2.71 7.00 18.98 2.37
28.73 21.11
D3 0.1845 8.00 1.48 8.00 11.81 1.48
S1 1.26 8.00 10.06 5.00 50.28 6.28
Slab
S2 0.82 8.33 6.82 5.00 34.10 4.26
Total 88.12

53
CONSTRUCTION ENGINEERING PROJECT

REINFORCEMENT MASS PER PARTITION


Mass
Number Mass Total Man- Total
per Quota Man-day
Floor Partition Component of per mass hour day
component (h/100kg) (day)
component partition(kg) (kg) (h) (day)
(kg)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8]/100
[10]=[9]/8 [11]
C1 45.57 6.00 273.42 5.36 14.66 1.83
Column C2 50.63 6.00 303.80 736.17 5.36 16.28 2.04 4.93
C3 52.99 3 158.96 5.36 8.52 1.07
D1b 70.94 6.00 425.67 4.39 18.69 2.34
1,4,6,7,8 D1g 31.40 6.00 188.40 4.39 8.27 1.03
Beam
D2 20.61 11.67 240.47 4.39 10.56 1.32
2509.87 18.89
D3 14.48 9.33 135.13 5.55 7.50 0.94
S1 98.67 9.33 920.56 6.98 64.26 8.03
Slab
S2 64.27 9.33 599.63 6.98 41.85 5.23
C1 45.57 5.00 227.85 5.36 12.21 1.53
Column C2 50.63 5.00 253.16 639.97 5.36 13.57 1.70 4.29
C3 52.99 3.00 158.96 5.36 8.52 1.07
D1b 70.94 5.00 354.72 4.39 15.57 1.95
2,3 D1g 31.40 5.25 164.85 4.39 7.24 0.90
1 Beam
D2 20.61 13.67 281.69 4.39 12.37 1.55
2715.54 20.82
D3 14.48 10.67 154.54 5.55 8.58 1.07
S1 98.67 10.67 1052.78 6.98 73.48 9.19
Slab
S2 64.27 11.00 706.96 6.98 49.35 6.17
C1 45.57 5.00 227.85 5.36 12.21 1.53
Column C2 50.63 5.00 253.16 639.97 5.36 13.57 1.70 4.29
C3 52.99 3.00 158.96 5.36 8.52 1.07
D1b 70.94 5.00 354.72 4.39 15.57 1.95
5,9 D1g 31.40 5.25 164.85 4.39 7.24 0.90
Beam
D2 20.61 10.33 212.86 4.39 9.34 1.17
2173.00 16.38
D3 14.48 8.00 115.87 5.55 6.43 0.80
S1 98.67 8.00 789.34 6.98 55.10 6.89
Slab
S2 64.27 8.33 535.36 6.98 37.37 4.67
Total 69.60

54
CONSTRUCTION ENGINEERING PROJECT

REINFORCEMENT MASS PER PARTITION


Mass
Number Mass Total Man- Total
per Quota Man-day
Floor Partition Component of per mass hour day
component (h/100kg) (day)
component partition(kg) (kg) (h) (day)
(kg)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8]/100
[10]=[9]/8 [11]
C1 29.67 6.00 178.04 5.36 9.54 1.19
Column C2 32.97 6.00 197.82 481.83 5.36 10.60 1.33 3.23
C3 35.33 3 105.98 5.36 5.68 0.71
D1b 70.94 6.00 425.67 4.39 18.69 2.34
1,4,6,7,8 D1g 31.40 6.00 188.40 4.39 8.27 1.03
Beam
D2 20.61 11.67 240.47 4.39 10.56 1.32
2509.87 18.89
D3 14.48 9.33 135.13 5.55 7.50 0.94
S1 98.67 9.33 920.56 6.98 64.26 8.03
Slab
S2 64.27 9.33 599.63 6.98 41.85 5.23
C1 29.67 5.00 148.37 5.36 7.95 0.99
Column C2 32.97 5.00 164.85 419.19 5.36 8.84 1.10 2.81
C3 35.33 3.00 105.98 5.36 5.68 0.71
D1b 70.94 5.00 354.72 4.39 15.57 1.95
2,3 D1g 31.40 5.25 164.85 4.39 7.24 0.90
2 Beam
D2 20.61 13.67 281.69 4.39 12.37 1.55
2715.54 20.82
D3 14.48 10.67 154.54 5.55 8.58 1.07
S1 98.67 10.67 1052.78 6.98 73.48 9.19
Slab
S2 64.27 11.00 706.96 6.98 49.35 6.17
C1 29.67 5.00 148.37 5.36 7.95 0.99
Column C2 32.97 5.00 164.85 419.19 5.36 8.84 1.10 2.81
C3 35.33 3.00 105.98 5.36 5.68 0.71
D1b 70.94 5.00 354.72 4.39 15.57 1.95
5,9 D1g 31.40 5.25 164.85 4.39 7.24 0.90
Beam
D2 20.61 10.33 212.86 4.39 9.34 1.17
2173.00 16.38
D3 14.48 8.00 115.87 5.55 6.43 0.80
S1 98.67 8.00 789.34 6.98 55.10 6.89
Slab
S2 64.27 8.33 535.36 6.98 37.37 4.67
Total 64.94

55
CONSTRUCTION ENGINEERING PROJECT

REINFORCEMENT MASS PER PARTITION


Mass
Number Mass Total Man- Total
per Quota Man-day
Floor Partition Component of per mass hour day
component (h/100kg) (day)
component partition(kg) (kg) (h) (day)
(kg)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8]/100
[10]=[9]/8 [11]
C1 26.38 6.00 158.26 5.36 8.48 1.06
Column C2 29.67 6.00 178.04 431.67 5.36 9.54 1.19 2.89
C3 31.79 3 95.38 5.36 5.11 0.64
D1b 70.94 6.00 425.67 4.39 18.69 2.34
1,4,6,7,8 D1g 31.40 6.00 188.40 4.39 8.27 1.03
Beam
D2 20.61 11.67 240.47 4.39 10.56 1.32
2509.87 18.89
D3 14.48 9.33 135.13 5.55 7.50 0.94
S1 98.67 9.33 920.56 6.98 64.26 8.03
Slab
S2 64.27 9.33 599.63 6.98 41.85 5.23
C1 26.38 5.00 131.88 5.36 7.07 0.88
Column C2 29.67 5.00 148.37 375.62 5.36 7.95 0.99 2.52
C3 31.79 3.00 95.38 5.36 5.11 0.64
D1b 70.94 5.00 354.72 4.39 15.57 1.95
2,3 D1g 31.40 5.25 164.85 4.39 7.24 0.90
3,4 Beam
D2 20.61 13.67 281.69 4.39 12.37 1.55
2715.54 20.82
D3 14.48 10.67 154.54 5.55 8.58 1.07
S1 98.67 10.67 1052.78 6.98 73.48 9.19
Slab
S2 64.27 11.00 706.96 6.98 49.35 6.17
C1 26.38 5.00 131.88 5.36 7.07 0.88
Column C2 29.67 5.00 148.37 375.62 5.36 7.95 0.99 2.52
C3 31.79 3.00 95.38 5.36 5.11 0.64
D1b 70.94 5.00 354.72 4.39 15.57 1.95
5,9 D1g 31.40 5.25 164.85 4.39 7.24 0.90
Beam
D2 20.61 10.33 212.86 4.39 9.34 1.17
2173.00 16.38
D3 14.48 8.00 115.87 5.55 6.43 0.80
S1 98.67 8.00 789.34 6.98 55.10 6.89
Slab
S2 64.27 8.33 535.36 6.98 37.37 4.67
Total 64.02

56
CONSTRUCTION ENGINEERING PROJECT

REINFORCEMENT MASS PER PARTITION


Mass
Number Mass Total Man- Total
per Quota Man-day
Floor Partition Component of per mass hour day
component (h/100kg) (day)
component partition(kg) (kg) (h) (day)
(kg)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8]/100
[10]=[9]/8 [11]
C1 23.08 6.00 138.47 5.36 7.42 0.93
Column C2 26.38 6.00 158.26 381.51 5.36 8.48 1.06 2.56
C3 28.26 3 84.78 5.36 4.54 0.57
D1b 70.94 6.00 425.67 4.39 18.69 2.34
1,4,6,7,8 D1g 31.40 6.00 188.40 4.39 8.27 1.03
Beam
D2 20.61 11.67 240.47 4.39 10.56 1.32
2509.87 18.89
D3 14.48 9.33 135.13 5.55 7.50 0.94
S1 98.67 9.33 920.56 6.98 64.26 8.03
Slab
S2 64.27 9.33 599.63 6.98 41.85 5.23
C1 23.08 5.00 115.40 5.36 6.19 0.77
Column C2 26.38 5.00 131.88 332.06 5.36 7.07 0.88 2.22
C3 28.26 3.00 84.78 5.36 4.54 0.57
D1b 70.94 5.00 354.72 4.39 15.57 1.95
2,3 D1g 31.40 5.25 164.85 4.39 7.24 0.90
5,6 Beam
D2 20.61 13.67 281.69 4.39 12.37 1.55
2715.54 20.82
D3 14.48 10.67 154.54 5.55 8.58 1.07
S1 98.67 10.67 1052.78 6.98 73.48 9.19
Slab
S2 64.27 11.00 706.96 6.98 49.35 6.17
C1 23.08 5.00 115.40 5.36 6.19 0.77
Column C2 26.38 5.00 131.88 332.06 5.36 7.07 0.88 2.22
C3 28.26 3.00 84.78 5.36 4.54 0.57
D1b 70.94 5.00 354.72 4.39 15.57 1.95
5,9 D1g 31.40 5.25 164.85 4.39 7.24 0.90
Beam
D2 20.61 10.33 212.86 4.39 9.34 1.17
2173.00 16.38
D3 14.48 8.00 115.87 5.55 6.43 0.80
S1 98.67 8.00 789.34 6.98 55.10 6.89
Slab
S2 64.27 8.33 535.36 6.98 37.37 4.67
Total 63.10

57
CONSTRUCTION ENGINEERING PROJECT

REINFORCEMENT MASS PER PARTITION


Mass
Number Mass Total Man- Total
per Quota Man-day
Floor Partition Component of per mass hour day
component (h/100kg) (day)
component partition(kg) (kg) (h) (day)
(kg)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8]/100
[10]=[9]/8 [11]
C1 19.78 6.00 118.69 5.36 6.36 0.80
Column C2 23.08 6.00 138.47 331.35 5.36 7.42 0.93 2.22
C3 24.73 3 74.18 5.36 3.98 0.50
D1b 70.94 6.00 425.67 4.39 18.69 2.34
1,4,6,7,8 D1g 31.40 6.00 188.40 4.39 8.27 1.03
Beam
D2 20.61 11.67 240.47 4.39 10.56 1.32
2509.87 18.89
D3 14.48 9.33 135.13 5.55 7.50 0.94
S1 98.67 9.33 920.56 6.98 64.26 8.03
Slab
S2 64.27 9.33 599.63 6.98 41.85 5.23
C1 19.78 5.00 98.91 5.36 5.30 0.66
Column C2 23.08 5.00 115.40 288.49 5.36 6.19 0.77 1.93
C3 24.73 3.00 74.18 5.36 3.98 0.50
D1b 70.94 5.00 354.72 4.39 15.57 1.95
2,3 D1g 31.40 5.25 164.85 4.39 7.24 0.90
7 Beam
D2 20.61 13.67 281.69 4.39 12.37 1.55
2715.54 20.82
D3 14.48 10.67 154.54 5.55 8.58 1.07
S1 98.67 10.67 1052.78 6.98 73.48 9.19
Slab
S2 64.27 11.00 706.96 6.98 49.35 6.17
C1 19.78 5.00 98.91 5.36 5.30 0.66
Column C2 23.08 5.00 115.40 288.49 5.36 6.19 0.77 1.93
C3 24.73 3.00 74.18 5.36 3.98 0.50
D1b 70.94 5.00 354.72 4.39 15.57 1.95
5,9 D1g 31.40 5.25 164.85 4.39 7.24 0.90
Beam
D2 20.61 10.33 212.86 4.39 9.34 1.17
2173.00 16.38
D3 14.48 8.00 115.87 5.55 6.43 0.80
S1 98.67 8.00 789.34 6.98 55.10 6.89
Slab
S2 64.27 8.33 535.36 6.98 37.37 4.67
Total 62.18

58
CONSTRUCTION ENGINEERING PROJECT

REINFORCEMENT MASS PER PARTITION


Mass
Number Mass Total Man- Total
per Quota Man-day
Floor Partition Component of per mass hour day
component (h/100kg) (day)
component partition(kg) (kg) (h) (day)
(kg)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8]/100
[10]=[9]/8 [11]
C1 19.78 6.00 118.69 5.36 6.36 0.80
Column C2 23.08 6.00 138.47 326.40 5.36 7.42 0.93 2.19
C3 23.08 3 69.24 5.36 3.71 0.46
D1b 70.94 6.00 425.67 4.39 18.69 2.34
1,4,6,7,8 D1g 47.10 6.00 282.60 4.39 12.41 1.55
Beam
D2 20.61 11.67 240.47 4.39 10.56 1.32
2604.07 19.41
D3 14.48 9.33 135.13 5.55 7.50 0.94
S1 98.67 9.33 920.56 6.98 64.26 8.03
Slab
S2 64.27 9.33 599.63 6.98 41.85 5.23
C1 19.78 5.00 98.91 5.36 5.30 0.66
Column C2 23.08 5.00 115.40 283.54 5.36 6.19 0.77 1.90
C3 23.08 3.00 69.24 5.36 3.71 0.46
D1b 70.94 5.00 354.72 4.39 15.57 1.95
2,3 D1g 47.10 5.25 247.28 4.39 10.86 1.36
8 Beam
D2 20.61 13.67 281.69 4.39 12.37 1.55
2797.96 21.28
D3 14.48 10.67 154.54 5.55 8.58 1.07
S1 98.67 10.67 1052.78 6.98 73.48 9.19
Slab
S2 64.27 11.00 706.96 6.98 49.35 6.17
C1 19.78 5.00 98.91 5.36 5.30 0.66
Column C2 23.08 5.00 115.40 283.54 5.36 6.19 0.77 1.90
C3 23.08 3.00 69.24 5.36 3.71 0.46
D1b 70.94 5.00 354.72 4.39 15.57 1.95
5,9 D1g 47.10 5.25 247.28 4.39 10.86 1.36
Beam
D2 20.61 10.33 212.86 4.39 9.34 1.17
2255.43 16.83
D3 14.48 8.00 115.87 5.55 6.43 0.80
S1 98.67 8.00 789.34 6.98 55.10 6.89
Slab
S2 64.27 8.33 535.36 6.98 37.37 4.67
Total 63.50

59
CONSTRUCTION ENGINEERING PROJECT

FORMWORK INSTALLATION PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 6.45 6.00 38.70 1.20 46.44 5.81
Column C2 6.88 6.00 41.28 101.58 1.20 49.54 6.19 15.24
C3 7.20 3 21.60 1.20 25.92 3.24
D1b 10.24 6.00 61.46 1.50 92.18 11.52
1,4,6,7,8 D1g 5.20 6.00 31.20 1.60 49.92 6.24
Beam
D2 3.60 11.67 42.01 1.60 67.22 8.40
187.20 35.07
D3 3.08 9.33 28.69 1.60 45.90 5.74
S1 1.39 9.33 12.99 1.00 12.99 1.62
Slab
S2 1.16 9.33 10.86 1.14 12.38 1.55
C1 6.45 5.00 32.25 1.20 38.70 4.84
Column C2 6.88 5.00 34.40 88.25 1.20 41.28 5.16 13.24
C3 7.20 3.00 21.60 1.20 25.92 3.24
D1b 10.24 5.00 51.21 1.50 76.82 9.60
2,3 D1g 5.20 5.25 27.30 1.60 43.68 5.46
1 Beam
D2 3.60 13.67 49.21 1.60 78.74 9.84
188.19 35.15
D3 3.08 10.67 32.81 1.60 52.50 6.56
S1 1.39 10.67 14.85 1.00 14.85 1.86
Slab
S2 1.16 11.00 12.80 1.14 14.60 1.82
C1 6.45 5.00 32.25 1.20 38.70 4.84
Column C2 6.88 5.00 34.40 88.25 1.20 41.28 5.16 13.24
C3 7.20 3.00 21.60 1.20 25.92 3.24
D1b 10.24 5.00 51.21 1.50 76.82 9.60
5,9 D1g 5.20 5.25 27.30 1.60 43.68 5.46
Beam
D2 3.60 10.33 37.19 1.60 59.50 7.44
161.13 30.19
D3 3.08 8.00 24.60 1.60 39.36 4.92
S1 1.39 8.00 11.14 1.00 11.14 1.39
Slab
S2 1.16 8.33 9.70 1.14 11.05 1.38
Total 142.13

60
CONSTRUCTION ENGINEERING PROJECT

FORMWORK INSTALLATION PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 4.20 6.00 25.20 1.00 25.20 3.15
Column C2 4.48 6.00 26.88 66.48 1.00 26.88 3.36 8.31
C3 4.80 3 14.40 1.00 14.40 1.80
D1b 10.24 6.00 61.46 1.50 92.18 11.52
1,4,6,7,8 D1g 5.20 6.00 31.20 1.60 49.92 6.24
Beam
D2 3.60 11.67 42.01 1.60 67.22 8.40
187.20 35.07
D3 3.08 9.33 28.69 1.60 45.90 5.74
S1 1.39 9.33 12.99 1.00 12.99 1.62
Slab
S2 1.16 9.33 10.86 1.14 12.38 1.55
C1 4.20 5.00 21.00 1.00 21.00 2.63
Column C2 4.48 5.00 22.40 57.80 1.00 22.40 2.80 7.23
C3 4.80 3.00 14.40 1.00 14.40 1.80
D1b 10.24 5.00 51.21 1.50 76.82 9.60
2,3 D1g 5.20 5.25 27.30 1.60 43.68 5.46
2 Beam
D2 3.60 13.67 49.21 1.60 78.74 9.84
188.19 35.15
D3 3.08 10.67 32.81 1.60 52.50 6.56
S1 1.39 10.67 14.85 1.00 14.85 1.86
Slab
S2 1.16 11.00 12.80 1.14 14.60 1.82
C1 4.20 5.00 21.00 1.00 21.00 2.63
Column C2 4.48 5.00 22.40 57.80 1.00 22.40 2.80 7.23
C3 4.80 3.00 14.40 1.00 14.40 1.80
D1b 10.24 5.00 51.21 1.50 76.82 9.60
5,9 D1g 5.20 5.25 27.30 1.60 43.68 5.46
Beam
D2 3.60 10.33 37.19 1.60 59.50 7.44
161.13 30.19
D3 3.08 8.00 24.60 1.60 39.36 4.92
S1 1.39 8.00 11.14 1.00 11.14 1.39
Slab
S2 1.16 8.33 9.70 1.14 11.05 1.38
Total 123.18

61
CONSTRUCTION ENGINEERING PROJECT

FORMWORK INSTALLATION PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 3.92 6.00 23.52 1.00 23.52 2.94
Column C2 4.20 6.00 25.20 62.22 1.00 25.20 3.15 7.78
C3 4.50 3 13.50 1.00 13.50 1.69
D1b 10.24 6.00 61.46 1.50 92.18 11.52
1,4,6,7,8 D1g 5.20 6.00 31.20 1.60 49.92 6.24
Beam
D2 3.60 11.67 42.01 1.60 67.22 8.40
187.20 35.07
D3 3.08 9.33 28.69 1.60 45.90 5.74
S1 1.39 9.33 12.99 1.00 12.99 1.62
Slab
S2 1.16 9.33 10.86 1.14 12.38 1.55
C1 3.92 5.00 19.60 1.00 19.60 2.45
Column C2 4.20 5.00 21.00 54.10 1.00 21.00 2.63 6.76
C3 4.50 3.00 13.50 1.00 13.50 1.69
D1b 10.24 5.00 51.21 1.50 76.82 9.60
2,3 D1g 5.20 5.25 27.30 1.60 43.68 5.46
3,4 Beam
D2 3.60 13.67 49.21 1.60 78.74 9.84
188.19 35.15
D3 3.08 10.67 32.81 1.60 52.50 6.56
S1 1.39 10.67 14.85 1.00 14.85 1.86
Slab
S2 1.16 11.00 12.80 1.14 14.60 1.82
C1 3.92 5.00 19.60 1.00 19.60 2.45
Column C2 4.20 5.00 21.00 54.10 1.00 21.00 2.63 6.76
C3 4.50 3.00 13.50 1.00 13.50 1.69
D1b 10.24 5.00 51.21 1.50 76.82 9.60
5,9 D1g 5.20 5.25 27.30 1.60 43.68 5.46
Beam
D2 3.60 10.33 37.19 1.60 59.50 7.44
161.13 30.19
D3 3.08 8.00 24.60 1.60 39.36 4.92
S1 1.39 8.00 11.14 1.00 11.14 1.39
Slab
S2 1.16 8.33 9.70 1.14 11.05 1.38
Total 121.72

62
CONSTRUCTION ENGINEERING PROJECT

FORMWORK INSTALLATION PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 3.64 6.00 21.84 1.00 21.84 2.73
Column C2 3.92 6.00 23.52 57.96 1.00 23.52 2.94 7.25
C3 4.20 3 12.60 1.00 12.60 1.58
D1b 10.24 6.00 61.46 1.50 92.18 11.52
1,4,6,7,8 D1g 5.20 6.00 31.20 1.60 49.92 6.24
Beam
D2 3.60 11.67 42.01 1.60 67.22 8.40
187.20 35.07
D3 3.08 9.33 28.69 1.60 45.90 5.74
S1 1.39 9.33 12.99 1.00 12.99 1.62
Slab
S2 1.16 9.33 10.86 1.14 12.38 1.55
C1 3.64 5.00 18.20 1.00 18.20 2.28
Column C2 3.92 5.00 19.60 50.40 1.00 19.60 2.45 6.30
C3 4.20 3.00 12.60 1.00 12.60 1.58
D1b 10.24 5.00 51.21 1.50 76.82 9.60
2,3 D1g 5.20 5.25 27.30 1.60 43.68 5.46
5,6 Beam
D2 3.60 13.67 49.21 1.60 78.74 9.84
188.19 35.15
D3 3.08 10.67 32.81 1.60 52.50 6.56
S1 1.39 10.67 14.85 1.00 14.85 1.86
Slab
S2 1.16 11.00 12.80 1.14 14.60 1.82
C1 3.64 5.00 18.20 1.00 18.20 2.28
Column C2 3.92 5.00 19.60 50.40 1.00 19.60 2.45 6.30
C3 4.20 3.00 12.60 1.00 12.60 1.58
D1b 10.24 5.00 51.21 1.50 76.82 9.60
5,9 D1g 5.20 5.25 27.30 1.60 43.68 5.46
Beam
D2 3.60 10.33 37.19 1.60 59.50 7.44
161.13 30.19
D3 3.08 8.00 24.60 1.60 39.36 4.92
S1 1.39 8.00 11.14 1.00 11.14 1.39
Slab
S2 1.16 8.33 9.70 1.14 11.05 1.38
Total 120.26

63
CONSTRUCTION ENGINEERING PROJECT

FORMWORK INSTALLATION PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 3.36 6.00 20.16 1.30 26.21 3.28
Column C2 3.64 6.00 21.84 53.70 1.00 21.84 2.73 7.47
C3 3.90 3 11.70 1.00 11.70 1.46
D1b 10.24 6.00 61.46 1.50 92.18 11.52
1,4,6,7,8 D1g 5.20 6.00 31.20 1.60 49.92 6.24
Beam
D2 3.60 11.67 42.01 1.60 67.22 8.40
187.20 35.07
D3 3.08 9.33 28.69 1.60 45.90 5.74
S1 1.39 9.33 12.99 1.00 12.99 1.62
Slab
S2 1.16 9.33 10.86 1.14 12.38 1.55
C1 3.36 5.00 16.80 1.30 21.84 2.73
Column C2 3.64 5.00 18.20 46.70 1.00 18.20 2.28 6.47
C3 3.90 3.00 11.70 1.00 11.70 1.46
D1b 10.24 5.00 51.21 1.50 76.82 9.60
2,3 D1g 5.20 5.25 27.30 1.60 43.68 5.46
7 Beam
D2 3.60 13.67 49.21 1.60 78.74 9.84
188.19 35.15
D3 3.08 10.67 32.81 1.60 52.50 6.56
S1 1.39 10.67 14.85 1.00 14.85 1.86
Slab
S2 1.16 11.00 12.80 1.14 14.60 1.82
C1 3.36 5.00 16.80 1.30 21.84 2.73
Column C2 3.64 5.00 18.20 46.70 1.00 18.20 2.28 6.47
C3 3.90 3.00 11.70 1.00 11.70 1.46
D1b 10.24 5.00 51.21 1.50 76.82 9.60
5,9 D1g 5.20 5.25 27.30 1.60 43.68 5.46
Beam
D2 3.60 10.33 37.19 1.60 59.50 7.44
161.13 30.19
D3 3.08 8.00 24.60 1.60 39.36 4.92
S1 1.39 8.00 11.14 1.00 11.14 1.39
Slab
S2 1.16 8.33 9.70 1.14 11.05 1.38
Total 120.82

64
CONSTRUCTION ENGINEERING PROJECT

FORMWORK INSTALLATION PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 3.36 6.00 20.16 1.30 26.21 3.28
Column C2 3.64 6.00 21.84 53.70 1.00 21.84 2.73 7.47
C3 3.90 3 11.70 1.00 11.70 1.46
D1b 10.24 6.00 61.46 1.50 92.18 11.52
1,4,6,7,8 D1g 6.80 6.00 40.80 1.60 65.28 8.16
Beam
D2 3.60 11.67 42.01 1.60 67.22 8.40
196.80 36.99
D3 3.08 9.33 28.69 1.60 45.90 5.74
S1 1.39 9.33 12.99 1.00 12.99 1.62
Slab
S2 1.16 9.33 10.86 1.14 12.38 1.55
C1 3.36 5.00 16.80 1.30 21.84 2.73
Column C2 3.64 5.00 18.20 46.70 1.00 18.20 2.28 6.47
C3 3.90 3.00 11.70 1.00 11.70 1.46
D1b 10.24 5.00 51.21 1.50 76.82 9.60
2,3 D1g 6.80 5.25 35.70 1.60 57.12 7.14
8 Beam
D2 3.60 13.67 49.21 1.60 78.74 9.84
196.59 36.83
D3 3.08 10.67 32.81 1.60 52.50 6.56
S1 1.39 10.67 14.85 1.00 14.85 1.86
Slab
S2 1.16 11.00 12.80 1.14 14.60 1.82
C1 3.36 5.00 16.80 1.30 21.84 2.73
Column C2 3.64 5.00 18.20 46.70 1.00 18.20 2.28 6.47
C3 3.90 3.00 11.70 1.00 11.70 1.46
D1b 10.24 5.00 51.21 1.50 76.82 9.60
5,9 D1g 6.80 5.25 35.70 1.60 57.12 7.14
Beam
D2 3.60 10.33 37.19 1.60 59.50 7.44
169.53 31.87
D3 3.08 8.00 24.60 1.60 39.36 4.92
S1 1.39 8.00 11.14 1.00 11.14 1.39
Slab
S2 1.16 8.33 9.70 1.14 11.05 1.38
Total 126.10

65
CONSTRUCTION ENGINEERING PROJECT

FORMWORK DISMANTLEMENT PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 6.45 6.00 38.70 0.38 14.71 1.84
Column C2 6.88 6.00 41.28 101.58 0.38 15.69 1.96 4.83
C3 7.20 3 21.60 0.38 8.21 1.03
D1b 10.24 6.00 61.46 0.32 19.67 2.46
1,4,6,7,8 D1g 5.20 6.00 31.20 0.32 9.98 1.25
Beam
D2 3.60 11.67 42.01 0.32 13.44 1.68
187.20 7.34
D3 3.08 9.33 28.69 0.32 9.18 1.15
S1 1.39 9.33 12.99 0.27 3.51 0.44
Slab
S2 1.16 9.33 10.86 0.27 2.93 0.37
C1 6.45 5.00 32.25 0.38 12.26 1.53
Column C2 6.88 5.00 34.40 88.25 0.38 13.07 1.63 4.19
C3 7.20 3.00 21.60 0.38 8.21 1.03
D1b 10.24 5.00 51.21 0.32 16.39 2.05
2,3 D1g 5.20 5.25 27.30 0.32 8.74 1.09
1 Beam
D2 3.60 13.67 49.21 0.32 15.75 1.97
188.19 7.35
D3 3.08 10.67 32.81 0.32 10.50 1.31
S1 1.39 10.67 14.85 0.27 4.01 0.50
Slab
S2 1.16 11.00 12.80 0.27 3.46 0.43
C1 6.45 5.00 32.25 0.38 12.26 1.53
Column C2 6.88 5.00 34.40 88.25 0.38 13.07 1.63 4.19
C3 7.20 3.00 21.60 0.38 8.21 1.03
D1b 10.24 5.00 51.21 0.32 16.39 2.05
5,9 D1g 5.20 5.25 27.30 0.32 8.74 1.09
Beam
D2 3.60 10.33 37.19 0.32 11.90 1.49
161.13 6.32
D3 3.08 8.00 24.60 0.32 7.87 0.98
S1 1.39 8.00 11.14 0.27 3.01 0.38
Slab
S2 1.16 8.33 9.70 0.27 2.62 0.33
Total 34.22

66
CONSTRUCTION ENGINEERING PROJECT

FORMWORK DISMANTLEMENT PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 4.20 6.00 25.20 0.32 8.06 1.01
Column C2 4.48 6.00 26.88 66.48 0.32 8.60 1.08 2.66
C3 4.80 3 14.40 0.32 4.61 0.58
D1b 10.24 6.00 61.46 0.32 19.67 2.46
1,4,6,7,8 D1g 5.20 6.00 31.20 0.32 9.98 1.25
Beam
D2 3.60 11.67 42.01 0.32 13.44 1.68
187.20 7.34
D3 3.08 9.33 28.69 0.32 9.18 1.15
S1 1.39 9.33 12.99 0.27 3.51 0.44
Slab
S2 1.16 9.33 10.86 0.27 2.93 0.37
C1 4.20 5.00 21.00 0.32 6.72 0.84
Column C2 4.48 5.00 22.40 57.80 0.32 7.17 0.90 2.31
C3 4.80 3.00 14.40 0.32 4.61 0.58
D1b 10.24 5.00 51.21 0.32 16.39 2.05
2,3 D1g 5.20 5.25 27.30 0.32 8.74 1.09
2 Beam
D2 3.60 13.67 49.21 0.32 15.75 1.97
188.19 7.35
D3 3.08 10.67 32.81 0.32 10.50 1.31
S1 1.39 10.67 14.85 0.27 4.01 0.50
Slab
S2 1.16 11.00 12.80 0.27 3.46 0.43
C1 4.20 5.00 21.00 0.32 6.72 0.84
Column C2 4.48 5.00 22.40 57.80 0.32 7.17 0.90 2.31
C3 4.80 3.00 14.40 0.32 4.61 0.58
D1b 10.24 5.00 51.21 0.32 16.39 2.05
5,9 D1g 5.20 5.25 27.30 0.32 8.74 1.09
Beam
D2 3.60 10.33 37.19 0.32 11.90 1.49
161.13 6.32
D3 3.08 8.00 24.60 0.32 7.87 0.98
S1 1.39 8.00 11.14 0.27 3.01 0.38
Slab
S2 1.16 8.33 9.70 0.27 2.62 0.33
Total 28.29

67
CONSTRUCTION ENGINEERING PROJECT

FORMWORK DISMANTLEMENT PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 3.92 6.00 23.52 0.32 7.53 0.94
Column C2 4.20 6.00 25.20 62.22 0.32 8.06 1.01 2.49
C3 4.50 3 13.50 0.32 4.32 0.54
D1b 10.24 6.00 61.46 0.32 19.67 2.46
1,4,6,7,8 D1g 5.20 6.00 31.20 0.32 9.98 1.25
Beam
D2 3.60 11.67 42.01 0.32 13.44 1.68
187.20 7.34
D3 3.08 9.33 28.69 0.32 9.18 1.15
S1 1.39 9.33 12.99 0.27 3.51 0.44
Slab
S2 1.16 9.33 10.86 0.27 2.93 0.37
C1 3.92 5.00 19.60 0.32 6.27 0.78
Column C2 4.20 5.00 21.00 54.10 0.32 6.72 0.84 2.16
C3 4.50 3.00 13.50 0.32 4.32 0.54
D1b 10.24 5.00 51.21 0.32 16.39 2.05
2,3 D1g 5.20 5.25 27.30 0.32 8.74 1.09
3,4 Beam
D2 3.60 13.67 49.21 0.32 15.75 1.97
188.19 7.35
D3 3.08 10.67 32.81 0.32 10.50 1.31
S1 1.39 10.67 14.85 0.27 4.01 0.50
Slab
S2 1.16 11.00 12.80 0.27 3.46 0.43
C1 3.92 5.00 19.60 0.32 6.27 0.78
Column C2 4.20 5.00 21.00 54.10 0.32 6.72 0.84 2.16
C3 4.50 3.00 13.50 0.32 4.32 0.54
D1b 10.24 5.00 51.21 0.32 16.39 2.05
5,9 D1g 5.20 5.25 27.30 0.32 8.74 1.09
Beam
D2 3.60 10.33 37.19 0.32 11.90 1.49
161.13 6.32
D3 3.08 8.00 24.60 0.32 7.87 0.98
S1 1.39 8.00 11.14 0.27 3.01 0.38
Slab
S2 1.16 8.33 9.70 0.27 2.62 0.33
Total 27.83

68
CONSTRUCTION ENGINEERING PROJECT

FORMWORK DISMANTLEMENT PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 3.64 6.00 21.84 0.32 6.99 0.87
Column C2 3.92 6.00 23.52 57.96 0.32 7.53 0.94 2.32
C3 4.20 3 12.60 0.32 4.03 0.50
D1b 10.24 6.00 61.46 0.32 19.67 2.46
1,4,6,7,8 D1g 5.20 6.00 31.20 0.32 9.98 1.25
Beam
D2 3.60 11.67 42.01 0.32 13.44 1.68
187.20 7.34
D3 3.08 9.33 28.69 0.32 9.18 1.15
S1 1.39 9.33 12.99 0.27 3.51 0.44
Slab
S2 1.16 9.33 10.86 0.27 2.93 0.37
C1 3.64 5.00 18.20 0.32 5.82 0.73
Column C2 3.92 5.00 19.60 50.40 0.32 6.27 0.78 2.02
C3 4.20 3.00 12.60 0.32 4.03 0.50
D1b 10.24 5.00 51.21 0.32 16.39 2.05
2,3 D1g 5.20 5.25 27.30 0.32 8.74 1.09
5,6 Beam
D2 3.60 13.67 49.21 0.32 15.75 1.97
188.19 7.35
D3 3.08 10.67 32.81 0.32 10.50 1.31
S1 1.39 10.67 14.85 0.27 4.01 0.50
Slab
S2 1.16 11.00 12.80 0.27 3.46 0.43
C1 3.64 5.00 18.20 0.32 5.82 0.73
Column C2 3.92 5.00 19.60 50.40 0.32 6.27 0.78 2.02
C3 4.20 3.00 12.60 0.32 4.03 0.50
D1b 10.24 5.00 51.21 0.32 16.39 2.05
5,9 D1g 5.20 5.25 27.30 0.32 8.74 1.09
Beam
D2 3.60 10.33 37.19 0.32 11.90 1.49
161.13 6.32
D3 3.08 8.00 24.60 0.32 7.87 0.98
S1 1.39 8.00 11.14 0.27 3.01 0.38
Slab
S2 1.16 8.33 9.70 0.27 2.62 0.33
Total 27.36

69
CONSTRUCTION ENGINEERING PROJECT

FORMWORK DISMANTLEMENT PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 3.36 6.00 20.16 0.32 6.45 0.81
Column C2 3.64 6.00 21.84 53.70 0.32 6.99 0.87 2.15
C3 3.90 3 11.70 0.32 3.74 0.47
D1b 10.24 6.00 61.46 0.32 19.67 2.46
1,4,6,7,8 D1g 5.20 6.00 31.20 0.32 9.98 1.25
Beam
D2 3.60 11.67 42.01 0.32 13.44 1.68
187.20 7.34
D3 3.08 9.33 28.69 0.32 9.18 1.15
S1 1.39 9.33 12.99 0.27 3.51 0.44
Slab
S2 1.16 9.33 10.86 0.27 2.93 0.37
C1 3.36 5.00 16.80 0.32 5.38 0.67
Column C2 3.64 5.00 18.20 46.70 0.32 5.82 0.73 1.87
C3 3.90 3.00 11.70 0.32 3.74 0.47
D1b 10.24 5.00 51.21 0.32 16.39 2.05
2,3 D1g 5.20 5.25 27.30 0.32 8.74 1.09
7 Beam
D2 3.60 13.67 49.21 0.32 15.75 1.97
188.19 7.35
D3 3.08 10.67 32.81 0.32 10.50 1.31
S1 1.39 10.67 14.85 0.27 4.01 0.50
Slab
S2 1.16 11.00 12.80 0.27 3.46 0.43
C1 3.36 5.00 16.80 0.32 5.38 0.67
Column C2 3.64 5.00 18.20 46.70 0.32 5.82 0.73 1.87
C3 3.90 3.00 11.70 0.32 3.74 0.47
D1b 10.24 5.00 51.21 0.32 16.39 2.05
5,9 D1g 5.20 5.25 27.30 0.32 8.74 1.09
Beam
D2 3.60 10.33 37.19 0.32 11.90 1.49
161.13 6.32
D3 3.08 8.00 24.60 0.32 7.87 0.98
S1 1.39 8.00 11.14 0.27 3.01 0.38
Slab
S2 1.16 8.33 9.70 0.27 2.62 0.33
Total 26.89

70
CONSTRUCTION ENGINEERING PROJECT

FORMWORK DISMANTLEMENT PER PARTITION


Area
Number Area Total Man- Total
per Quota Man-day
Floor Partition Component of per Area hour day
component (h/m2) (day)
component partition(m2) (m2) (h) (day)
(m2)
[1] [2] [3] [4] [5] [6]=[4]*[5] [7] [8] [9]=[6]*[8] [10]=[9]/8 [11]
C1 3.36 6.00 20.16 0.32 6.45 0.81
Column C2 3.64 6.00 21.84 53.70 0.32 6.99 0.87 2.15
C3 3.90 3 11.70 0.32 3.74 0.47
D1b 10.24 6.00 61.46 0.32 19.67 2.46
1,4,6,7,8 D1g 6.80 6.00 40.80 0.32 13.06 1.63
Beam
D2 3.60 11.67 42.01 0.32 13.44 1.68
196.80 7.72
D3 3.08 9.33 28.69 0.32 9.18 1.15
S1 1.39 9.33 12.99 0.27 3.51 0.44
Slab
S2 1.16 9.33 10.86 0.27 2.93 0.37
C1 3.36 5.00 16.80 0.32 5.38 0.67
Column C2 3.64 5.00 18.20 46.70 0.32 5.82 0.73 1.87
C3 3.90 3.00 11.70 0.32 3.74 0.47
D1b 10.24 5.00 51.21 0.32 16.39 2.05
2,3 D1g 6.80 5.25 35.70 0.32 11.42 1.43
8 Beam
D2 3.60 13.67 49.21 0.32 15.75 1.97
196.59 7.69
D3 3.08 10.67 32.81 0.32 10.50 1.31
S1 1.39 10.67 14.85 0.27 4.01 0.50
Slab
S2 1.16 11.00 12.80 0.27 3.46 0.43
C1 3.36 5.00 16.80 0.32 5.38 0.67
Column C2 3.64 5.00 18.20 46.70 0.32 5.82 0.73 1.87
C3 3.90 3.00 11.70 0.32 3.74 0.47
D1b 10.24 5.00 51.21 0.32 16.39 2.05
5,9 D1g 6.80 5.25 35.70 0.32 11.42 1.43
Beam
D2 3.60 10.33 37.19 0.32 11.90 1.49
169.53 6.65
D3 3.08 8.00 24.60 0.32 7.87 0.98
S1 1.39 8.00 11.14 0.27 3.01 0.38
Slab
S2 1.16 8.33 9.70 0.27 2.62 0.33
Total 27.95

71
CONSTRUCTION ENGINEERING PROJECT

3. Construction equipment:
Building length: 69.7m

Building width: 19.6m

Building height: 28.3m

Use tower crane as vertical transport equipment.

a. Vertical transport equipment:

Select tower crane on rail because:

 Concrete volume is large (>100m3 concrete per slab)


 Capable of reduce number of labours.
 Capable of reduce time for transporting materials
 High quality in construction process
 Length of building is great meanwhile height is average.
 Required height of tower crane:
Hyc=hct + hat + hck + ht = 28.3+1+1.5+1.5=32.3(m)
Legend:
hct: height of building
hat: safety distance
hck: height of structure components
ht: height of hanging kits
 Working range of tower crane:

72
CONSTRUCTION ENGINEERING PROJECT

Ry/ c  ld  lat  ldg  B


Legend:

B=19.6m: building width

ldg=7m : distance from centre of the counterweight to the outter edge of the tower crane

lat=1m : safety distance

ldg=1.4m : width of scaffold and clearance

 Ry / c  l d  l at  l dg  B  7  1 1.4  19.6  29(m)

 Length of rail:

Lr  L1  L2  2L3  2L4  49  5  21.5  2 0.5  58(m)


Legend:

L1=49m: Distance between two farthest position of tower crane

L2=5m: Width of base part of tower crane

L3 : Braking distance of crane ( ≥1.5m)

L4 : Length of the edge part of the rail ( ≥0.5m)

73
CONSTRUCTION ENGINEERING PROJECT

 Load capacity:
Select concrete bucket of Tan Hoa Phat Company with volume V=1.5 m3.
Self-weight of concrete bucket is 300Kg
 Required capacity: Q  300  0.6  2500  4050( Kg)

 Select tower crane:


Select tower crane base on the following
requirements:
 Load capacity: Q=4.05(T)
 Maximum operating radius: Rrequire=29 (m)
 Hoisting height: H=32.3 (m)

 Select tower crane KB-403A with the following parameters:


 Load capacity: Q=5 - 8 (T)
 Maximum operating radius: R=30 (m)
 Hoisting height: H=57.5 (m)
 Speed:
o Hoisting speed: 40 m/min
o Lowering speed: 5 m/min
o Trolleying speed: 30 m/min
o Slewing speed: 0.6 r/min

 Cycle of tower crane:


n
T=E  t i
i 1

Legend:
E: silmutaneous gestures factor E=0.8
Si
ti   (3  4) s : time for gesture number i with speed vi
vi
t1=10(s): time for hanging the bucket on the lifting hook.

74
CONSTRUCTION ENGINEERING PROJECT

H 32.3
t2   60  4   60  4  52.45( s) : hoisting time.
vhoisting 40
0.5
t3   60  4  52.35( s) : slewing time to pouring position.
0.6
R 29
t4   60  4   60  4  62( s) : time for trolley get to pouring position.
vxecon 30
H lowering 1  1.5
t5  4  60  4  34( s) : time for lowering the bucket to
vlowering 5

constructing position
t 6  120( s) : pouring concrete time.
H lowering 1  1.5
t7   60  4   60  4  7.75( s) : time for lifting bucket to former
vhoisting 40

position
t8  t 4  62(s)
t 9  t 3  52.35(s)
H 32.3
t10   60  4   60  4  391.6( s) :time for taking a new bucket.
vlowering 5

 t i  10  52.45  52.35  62  34  120  7.75  62  52.35  391.6  844.5( s)

 Productivity of tower crane per working shift (for concrete transporting only):
N  Q  nck  ktt  ktg  T
Legend:
Q=1.5x2.5=3.75(T): Lifting capacity at maximum operating radius
n
tck  E  ti  0.8  844.5  675.6( s) : time period of a cycle
i 1

3600 3600
nck    5.33( s) : number of cycle in an hour.
tck 675.6

ktt  0.8 : weighting factor.


k tg  0.9 : factor considering time-used of crane.

75
CONSTRUCTION ENGINEERING PROJECT

T=8 (h): time of a working shift

 N  Q  nck  ktt  ktg  T   conc.  3.75  5.33 0.8  0.9  8  2.5  46.05(m / shift )  34.59(m )
3 3

 Total mass of materials that need to be transported in a typical day (26thday):


 Concrete: Vconcrete  34.59  5.5  40.09(m3 )

 Reinforcement: mre inf .  2.51  0.43  2.94(T)

 Formwork: m formwork  (161.13  7.78  54.1)  0.04  0.6  5.35(T)

 Stringer: mstringer  4 14  (0.08  0.12  3.075)  0.6  1(T)

 Shore: mshore  56  0.1 0.1 3.13  52  0.12  0.12  3.06  0.6  4  9.5(T)

Total material mass (except for concrete):

 m  2.94  5.35 1  9.5  18.79(T)


Maximum time to transport 40.09(m3) concrete:
40.09  2.5
t  6.9 (hours)
3.75  5.33  0.8  0.9
Productivity of tower crane for hoisting other materials (in 1hour):
N  Q  nck  ktt  ktg 1  6.5  5.33  0.8  0.9 1  24.94(T )  18.79(T )

b. Concrete mixer:
Select unforced concrete mixer HD750 of Hoa Phat Company

V  n  K1  K 2
N ( m3 / h)
1000

Legend:

V=550:Finish product capacity (l)

3600 3600
n: number of mix batches in 1 hour n    18.95
Tck 20  20  150

(Tck includes time for pouring the mix design into the mixer’s barrel, mixing
concrete and pouring concrete mortar to the transport equipment respectively)

76
CONSTRUCTION ENGINEERING PROJECT

K1: Factor of finished product of concrete (K1=0.67 – 0.72)

K2: Factor of using the mixer with time (K2=0.9 – 0.95)

V  n  K1  K 2 550 18.95  0.67  0.9


 N   6.28(m3 / h)
1000 1000

 Total volume of concrete can be mixed in a shift: 6.28  8  50.24(m / shift )


3

c. Concrete vibrating equipment:


 Concrete volume of columns needs to be vibrated: V=13.83(m3)
 Concrete volume of beams needs to be vibrated: V=12.17(m3)
 Concrete volume of slab needs to be vibrated: V=22.42(m3)
(Note: calculate for largest partion)
 Use needle vibrator for columns and beams and slabs.
Select 8 needle vibrators I-21A with productivity 6m3/shift

d. Construction hoist:
 Use 2 construction hoists (single cage type) of Hoa Phat Group for transporting
labours.

4. Construction time:
k
T (m  n  1)  t (day)
c

Legend:

k=1: Time to finish a task in a partition

c=1: Number of shift per day

m=9x8=72 partions: number of partions of the building

n=7: number of single tasks in construction site

t=18days: interruption time, including due to “2.5 lelvel” rule.

k 1
 T  (m  n  1)  t  (72  7  1)  18  96(days)
c 1

There are 7 task at site as below:

77
CONSTRUCTION ENGINEERING PROJECT

1. Install column reinforcement

2. Install column formwork

3. Pour column concrete

4. Dismantle column formwork, install beam and slab formwork

5. Install beam and slab reinforcement

6. Pour beam and slab concrete

7. Dismantle beam and slab formwork

By applying “2.5 level” rule, the construction schedule diagram is drawn as below:
1 2 34 5 6 7
FLOOR - PARTITION

CONSTRUCTION SCHEDULE DIAGRAM

78