Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
op V1
2.1.2 Related Documents
Section 01300-Submittals
2.1.3 Standards
C
All activities relating to this section of the specification shall comply with the
Q
2.1.4 Submittals
A. Method statements.
The Contractor shall submit method statements to the Engineer for approval four
PAGE 11
op V1
B. Drawings
The Contractor shall submit drawings to the Engineer for approval in advance of
commencing the site activity in accordance with Section 01300 of the
C -
specification. These shall comprise but not necessarily be limited to:
y
1.
C
Detailed fabrication and placement drawings for all reinforcement indicating:
C
a. Layout of the individual panels.
C. Samples
Representative samples, as agreed with the Engineer, must be submitted for all
reinforcement that the Contractor proposes to use in the Works, at the same
time as the particulars are submitted.
C. To allow the Engineer to inspect the Works, the Contractor shall give the Engineer
PAGE 12
D. The Engineer shall have access to the fabrication plant for inspection and
verification of length, size and bending of steel reinforcement as indicated in the
bending schedules. Advance notice of the date of commencement and duration of
op V1
shop fabrication shall be provided by the Contractor.
E. The Engineer reserves the right to sample and test each batch of reinforcement
upon its arrival at the work site.
C -
y
1.
C
The following tests shall be carried out for each delivery of
reinforcement, to the procedures and frequencies given in BS 4449 unless
C
otherwise directed by the Engineer.
c. Yield stress.
d. Elongation.
2. Test results for each bar diameter shall be submitted to the Engineer three
weeks before concrete works commences on site. Reinforcement not
meeting the required standards shall be removed from site at the
Contractor’s expense.
3. Further tests may be called for, at the Contractor’s expense, if the source
of supply of reinforcement changes.
PAGE 13
a. The tag shall show the manufacturers test number, batch number
and other applicable data that will identify the material with the
corresponding certificate issued for that batch of steel.
op V1
Plastic sheeting is not allowed.
C -
y
5. Equipment handling for epoxy coated reinforcement if specified shall be
C
adequately padded to prevent damage to coating and the reinforcement shall
be adequately supported to prevent bar to bar abrasion from sags in the
C
bundle when lifting.
Q
6. Provide tags for all bundles of reinforcement and include bar schedule and
bar mark reference after bending. The bundle tag shall be traceable back to
the manufacturer’s consignment.
B. Deformed high yield bars shall have yield strength of 460N/mm2 and shall be
classified as Type 2 unless otherwise specified.
C. The mill test report for three different samples shall be furnished to the Engineer
for each consignment of steel reinforcement bars proposed for use on the project.
D. The bars in each consignment shall be legibly tagged in accordance with CARES
requirements (or similar international certification organisation) by the
manufacturer and/or fabricator before being offered for inspection. The tag shall
show the manufacturer's test number and consignment number and other
applicable data that will identify the material with the certificate issued for that
PAGE 14
consignment of steel.
E. The fabricator shall furnish copies of a certification which shows the heat number
or numbers from which each size of bar in the shipment was fabricated.
F. The Contractor shall provide certificates confirming that samples taken from the
bars delivered to the Works pass all the tests required in BS 4449. The frequency
of sampling and the method of quality control shall be in accordance with BS
4449. The Engineer reserves the right to inspect, sample and instruct testing of
the reinforcement steel upon its arrival at the work site, in accordance with clause
op V1
B of BS 4449. All such sampling and associated testing costs shall be borne by
the Contractor.
G. All reinforcement bars shall be free from detrimental dirt, mill scale, loose rust,
C -
paint, grease, oil or other foreign substance, fins, or tears. There shall be no
y
C
evidence of visual flaws in the bars, test specimens or on the sheared ends of the
bars.
C
H. All reinforcement shall be cleaned before use to remove rust, oil, grease, salt and
other deleterious materials. Where pitting has occurred, the bars shall be rejected.
Q
Blasting may be required when the reinforcement is in position, or partially cast in.
Partially set concrete adhering to exposed bars during concreting operations shall
be removed.
PAGE 15
A. Welded wire fabric to be used for the reinforcement of concrete shall conform to
the following requirements.
B. Welded steel wire fabric reinforcement shall have yield strength of 460N/mm2 and
shall be classified as Type 2 unless otherwise specified.
C. Dimensions: Welded steel wire fabric shall conform to the size and dimensions
shown on the Drawings.
D. Properties: Wire fabric furnished under this Specification shall conform to both BS
4483 and BS 4449.
op V1
2.2.3 Spacer Blocks
A. Spacers as approved by the Engineer shall be of such material and design as will
be durable, not lead to corrosion of the reinforcement and not cause spilling of the
C -
y
concrete cover.
C
B. Spacer blocks made from cement, sand and small aggregate shall match the mix
C
proportions of the surrounding concrete so far as is practicable be comparable in
strength, durability and appearance. Their surface shall be roughened to ensure
Q
B. The contractor is to furnish three (3) copies of all test certificates for each size and
type of coupler proposed, demonstrating their compliance with the requirements
of relevant British Standards, and the particular performance requirements of this
specification.
C. The performance criteria for couplers for each representative gauge length
assembly comprising of reinforcement the size, grade and profile to be used and
a couple of the precise type to be used the following minimum criteria must be
attained.
D. The strength of the coupled bar in both tension and compression must exceed
125 percent of the yield strength of the bar (1.15fy) for grade 250 and 500A and
500B reinforcement or 95 percent of the ultimate actual tensile strength of the
reinforcement bars.
PAGE 16
manufacturer's test number and consignment number and other applicable data
that will identify each coupler with the certificate issued for that consignment.
F. The Contractor shall provide certificates confirming that samples taken from the
couplers delivered to the Works pass all the tests required by this specification.
The frequency of sampling and the method of quality control shall be in
accordance with British Standards and agreed with the Engineer prior to
commencing.
op V1
1. Prior to installation in the permanent works, 3 tests of each coupler size and
type to be used are to be completed by an approved independent testing
laboratory with results submitted for review and approval by the Engineer.
C -
Failure of any one of these tests will result in the immediate testing of no less
y
C
than 25 couplers from the failed batch to determine if manufacturing defects
exist.
C
2. Once initial testing is successfully completed and couplers are approved for
use in the permanent works 1 sample for every 200 couplers of each coupler
Q
type. If one coupler test fails 25 from the failed batch must be tested
immediately to determine if a manufacturing defect exists in the current
delivery. The subsequent rate of testing will then be reassessed.
H. The Engineer reserves the right to inspect, sample and instruct testing of the
coupler assemblies upon its arrival at the work site. All such sampling and
associated testing costs shall be borne by the Contractor.
2.2.5 Accessories
A. Tie wires shall be 1.6mm diameter soft annealed steel wires. For epoxy-coated
reinforcement, this shall be PVC coated.
B. Steel chairs, bolsters and bar supports shall be of sufficient size, shape and
strength to provide adequate support to steel reinforcement during placement
of concrete.
PAGE 17
op V1
3. The contractor shall prepare reinforcement detail drawings and other
relevant shop drawings to the following scales:
C -
y
b. Beams and column elevations 1:20
C
c. Beam and column sections 1:20 or 1:10
C
4. hop drawings shall show all openings for services, up stands or plinths for
equipment and cast-in items and be fully coordinated with relevant trades.
Q
PAGE 18
5135. The Contractor shall submit full technical details of his proposed
procedures prior to seeking approval
2. Hot rolled high yield bars shall not be straightened or bent again, having
once been bent. If the Engineer gives approval to bend mild steel
reinforcement projecting from the concrete, the internal radius of bend shall
not be less than four times the nominal size of the bar.
C. Placing and Fixing Reinforcement
1. Reinforcement shall be placed and maintained in the position shown in the
Contract Drawings. Unless otherwise permitted by the Engineer, all bar
op V1
intersections shall be tied together using 1.2mm diameter steel wire and the
ends of the tying wire shall be turned into the main body of the concrete
2. Spacer blocks or other supports approved by the Engineer, shall be provided
C -
and used to retain the reinforcement at proper distances from the forms. The
y
C
contractor shall secure the cage/reinforcement by providing adequate
supports. All reinforcement shall be so rigidly supported and fastened that
C
displacement will not occur during construction. Reinforcing steel shall be
inspected in place and must be approved by the Engineer before any
Q
concrete is deposited.
3. No splices shall be made in the reinforcement except where described in the
Contract Drawings or where approved by the Engineer.
4. Reinforcement temporarily left projecting from the concrete at construction or
other joints shall not be bent out of position during the periods in which
concreting is suspended, except with the approval of the Engineer.
5. Minimum lap lengths are as follows unless otherwise noted in the contract
drawings.
Table 2-1: Minimum Lap Lengths
Lap Length (mm) Diameter (mm) Lap Length (mm)
Diameter (mm)
400 20 1000
8
500 25 1250
10
600 32 1600
12
800 40 2000
16
6. The minimum lap length for deformed high yield bars and welded steel wire
fabric reinforcement shall comply with BS EN 1992 C.3.12.8.
D. Electrical Continuity of Reinforcement
1. The Contractor shall provide and ensure the electrical continuity of all
reinforcing steel.
PAGE 19
2.3.2 Placement
A. All steel reinforcement shall be securely and accurately fixed in position as shown
on the drawings and supported to ensure that the reinforcement cage as a whole
shall retain its shape and correct position in the forms during the process of
depositing and compacting the concrete.
op V1
Concrete cover to Reinforcement Minimum cover
C -
External work in a tidal environment 75mm
y
C
and concrete placed in or under water.
links
C. Turn ends of tie wires into the main body of the concrete. Do not allow tie wire to
project towards the surface.
D. Place chairs, bolsters, or bar supports between parallel layers of steel reinforcement
in slabs.
H. Welding of steel reinforcement shall not be carried out unless authorized by the
Engineer.
PAGE 20
by the Engineer.
J. Steel reinforcement shall be fixed so that it does not come into contact with other
non-ferrous or dissimilar metals.
L. Do not fix reinforcement above membranes applied to blinding and other horizontal
surfaces until cement mortar screed protection has been applied.
op V1
A. At the time of concreting, all steel reinforcement shall be thoroughly cleaned and
freed from all loose rust, loose mill scale, oil, grease, mud, paint and other
C -
deleterious material to the satisfaction of the Engineer including partially set
y
C
concrete, which may have been deposited during the placing of a previous lift of
concrete.
C
B. Immediately prior to concrete placing, all reinforcing steel shall be thoroughly
washed with high-pressure potable water jets and shall be free off and corrosion
Q
product.
END OF SECTION
PAGE 21